This is the accessible text file for GAO report number GAO-10-384 
entitled 'Military Munitions Response Program: Opportunities Exist to 
Improve Program Management' which was released on April 9, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 
GAO: 

April 2010: 

Military Munitions Response Program: 

Opportunities Exist to Improve Program Management: 

GAO-10-384: 

GAO Highlights: 

Highlights of GAO-10-384, a report to congressional committees. 

Why GAO Did This Study: 

The Department of Defense (DOD) established the military munitions 
response program (MMRP) in 2001 to clean up sites known to be or 
suspected of being contaminated with military munitions and related 
hazardous substances. Cleanup of sites on active and base realignment 
and closure installations is the responsibility of the military 
service—Air Force, Army, Navy, or Marine Corps—that currently controls 
the land, and the Army has delegated execution of cleanup of formerly 
used defense sites (FUDS) to the U.S. Army Corps of Engineers (Corps). 
GAO was mandated to assess the (1) MMRP staffing and funding levels; 
(2) progress DOD has made in cleaning up munitions response sites; (3) 
extent to which DOD has established MMRP performance goals; and (4) 
extent to which DOD collects data on factors influencing project 
duration, as well as the accuracy of its cleanup cost estimates. GAO 
analyzed MMRP data and DOD documents and interviewed officials from 
DOD, the military services, and the Corps. 

What GAO Found: 

The military services and the Corps do not track the time that staff 
work on MMRP activities separately from the time they spend on another 
environmental restoration program—the Installation Restoration Program 
(IRP). Consequently, it is not possible to determine the staffing 
levels for the MMRP. In addition, obligated funds for the MMRP 
increased from $95 million in fiscal year 2002 to approximately $284 
million in fiscal year 2008, and the military services and the Corps 
directed 11 percent of their total MMRP and IRP environmental 
restoration funds to the MMRP during the period—a total of about $1.2 
billion to the MMRP compared with $9.7 billion to the IRP. 

DOD reported to Congress that it had completed its cleanup response 
for 1,318 of its 3,674 sites by the end of fiscal year 2008; however, 
for 1,234 of these sites, DOD’s response was an investigation that 
determined cleanup was not necessary. The remaining 84 sites were 
cleaned up because of such factors as imminent danger to public safety 
and pressing military mission and land reuse needs. In addition, the 
military services and the Corps are still in the process of gathering 
information necessary to prioritize most sites in the MMRP inventory 
for cleanup. When this process is complete, the military services and 
the Corps will consider this information along with other factors, 
such as land reuse plans, to determine which sites to clean up first. 
However, DOD has not issued guidance on how factors other than risk 
should be considered when making decisions about which sites to 
sequence first for cleanup, and the Air Force, the Army, and the Corps 
have begun to independently develop their own approaches. Using 
varying approaches could lead to inconsistent sequencing decisions. 

DOD has not yet established a performance goal for implementing the 
cleanup remedy (referred to as “remedy in place”) or achieving the 
cleanup objective (referred to as “response complete”) at munitions 
response sites located on FUDS, as required by the fiscal year 2007 
National Defense Authorization Act. The act also directs DOD to report 
on interim goals it determines feasible for achieving the performance 
goals, but DOD has not yet done so. Performance goals are important 
because they are used to track progress toward cleaning up munitions 
response sites. By establishing goals, DOD would have better 
information with which to measure MMRP progress. 

DOD gathers data on two of the factors—site size and type of hazard—
that can influence project duration at military munitions response 
sites. As would be expected, these data indicate that the larger the 
munitions response site and the more complex the type of hazard, the 
longer it takes to clean up the site. In addition, because data on 
funds obligated to complete specific phases of the cleanup process are 
not included in DOD’s database for many munitions response sites, it 
is not possible to assess the accuracy of the military services’ and 
the Corps’ cost estimates for the MMRP. 

What GAO Recommends: 

GAO recommends that Congress consider requiring DOD to report 
separately on sites where response is complete because they needed no 
cleanup, and that DOD issue guidance on how factors other than 
relative risk should be considered in munitions response site 
sequencing decisions, and set FUDS performance goals as required by 
law. DOD partially agreed with the recommendations but not with the 
matter for congressional consideration. 

View [hyperlink, http://www.gao.gov/products/GAO-10-384] or key 
components. For more information, contact Anu Mittal at (202) 512-3841 
or mittala@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

The Military Services and the Corps Do Not Track MMRP Staffing Levels, 
and the MMRP Receives a Small Share of DOD's Environmental Restoration 
Funds: 

Most Sites That DOD Has Reported as Response Complete Did Not Require 
Cleanup, and Cleanup Priorities Are Still Being Determined for the 
Majority of Sites: 

DOD Has Not Established a Key Performance Goal for Its MMRP at FUDS, 
as Required by Law, and Has Not Determined and Reported on the 
Feasibility of Interim Goals: 

DOD Collects Limited Data on Factors That Can Affect MMRP Project 
Duration, and Incomplete Data Prevent an Assessment of the Accuracy of 
Its MMRP Cost Estimates: 

Conclusions: 

Matter for Congressional Consideration: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: Comments from the Department of Defense: 

Appendix III: GAO Contact and Staff Acknowledgments: 

Figures: 

Figure 1: Unexploded Ordnance Found at a Munitions Response Site: 

Figure 2: Location and Number of Munitions Response Sites, as of 
Fiscal Year 2008: 

Figure 3: Percentage of Munitions Response Sites at Active and BRAC 
Installations and FUDS, and Distribution among the Military Services 
and the Corps: 

Figure 4: Site Inspection at Beale Air Force Base: 

Figure 5: IRP and MMRP Obligated Funds, Fiscal Years 2002 through 2008: 

Figure 6: MMRP Obligated Funds, Fiscal Years 2002 through 2008: 

Figure 7: Sites the Military Services and the Corps Cleaned Up under 
the MMRP, as of Fiscal Year 2008: 

Figure 8: Sites with Prioritization Protocol Scores Reported to DOD, 
as of Fiscal Year 2008: 

Figure 9: Percentage of Sites with No Obligated Funds Data, by Phase: 

Abbreviations: 

BRAC: base realignment and closure: 

CERCLA: Comprehensive Environmental Response, Compensation, and 
Liability Act: 

Corps: U.S. Army Corps of Engineers: 

DOD: Department of Defense: 

FUDS: formerly used defense sites: 

IRP: Installation Restoration Program: 

MMRP: Military Munitions Response Program: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

April 9, 2010: 

The Honorable Carl Levin: 
Chairman: 
The Honorable John McCain: 
Ranking Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Ike Skelton: 
Chairman: 
The Honorable Howard P. McKeon: 
Ranking Member: 
Committee on Armed Services: 
House of Representatives: 

The Department of Defense (DOD) has identified over 3,600 sites known 
to be, or suspected of being, contaminated with military munitions 
from training and other activities. These sites can pose risks to 
human health and the environment. Military munitions include 
unexploded ordnance (explosives that were fired but did not detonate 
as planned), discarded military munitions (munitions that were 
abandoned without proper disposal), and munitions constituents 
(propellants or other materials originating from munitions).[Footnote 
1] Sites that contain munitions (other than operational ranges) that 
require a response from DOD are known as munitions response sites. 
These sites are located on active installations, base realignment and 
closure (BRAC) installations, and formerly used defense sites (FUDS) 
across the country. About half of the land on which munitions response 
sites are located has been or will be converted to nonmilitary uses, 
which may include residential or commercial development and 
recreation, according to DOD officials. 

Under its Defense Environmental Restoration Program, DOD identifies, 
investigates, and cleans up contamination from hazardous substances, 
pollutants, and contaminants including military munitions at active, 
BRAC, and FUDS locations that were contaminated while under DOD's 
jurisdiction.[Footnote 2] To carry out activities under the Defense 
Environmental Restoration Program, over time DOD has established three 
programs, including the Installation Restoration Program (IRP) and the 
Military Munitions Response Program (MMRP).[Footnote 3] Specifically, 
in 1985, DOD established the IRP to address the release of hazardous 
substances and other contamination, and most of DOD's environmental 
remediation work to date has been conducted under this program. In 
2001, DOD established the MMRP, which focuses on remediating 
unexploded ordnance, discarded military munitions, and munitions 
constituents on munitions response sites. Cleanup of munitions 
response sites on active and BRAC installations is the responsibility 
of the military service--Air Force, Army, or Navy[Footnote 4]--that 
currently controls the land, and cleanup of FUDS sites is the 
responsibility of the U.S. Army Corps of Engineers (Corps).[Footnote 
5] While DOD has overall responsibility for the MMRP, it allows each 
of the military services and the Corps to implement and manage their 
own munitions response programs, including determining how best to 
organize their programs, set program and funding priorities, and track 
management information, in accordance with DOD policies and guidance. 

The National Defense Authorization Act for fiscal year 2009 mandated 
that we review and report to Congress by October 14, 2009, on various 
aspects of DOD's organization, operation, and management of the MMRP. 
[Footnote 6] We briefed the staffs of the Senate and House Committees 
on Armed Services on October 14, 2009. We are following up with this 
report, which provides more detail on the topics covered in the 
briefing. As agreed with your offices, this report assesses the (1) 
MMRP staffing and funding levels; (2) progress DOD has made in 
cleaning up munitions response sites; (3) extent to which DOD has 
established MMRP performance goals; and (4) extent to which DOD 
collects data on factors influencing project duration, as well as the 
accuracy of DOD's cleanup cost estimates. 

In addressing these objectives, we reviewed each of the individual 
MMRPs as implemented by the Air Force, Army, Navy, and the Corps at 
active and BRAC installations and FUDS. We analyzed MMRP funding data, 
as well as data in DOD's environmental programs management database-- 
known as the Knowledge-Based Corporate Reporting System--which 
includes relative priority scores, project duration, and cost 
estimates. We reviewed key documents, such as DOD's Defense 
Environmental Programs Annual Report to Congress, which includes 
information on program performance goals, and the Munitions Response 
Site Prioritization Protocol that is used to assign a relative 
priority to sites in order to prioritize sites for cleanup. We visited 
one BRAC installation (Fort Ord), one active installation (Beale Air 
Force Base), and one FUDS (Camp Beale) to ensure we had the 
opportunity to review various types of MMRP activities at active and 
BRAC installations, as well as FUDS. We met with and obtained 
information and data needed for our review from a key senior DOD 
official responsible for the MMRP within DOD's Office of the Deputy 
Under Secretary of Defense (Installations and Environment); and we 
interviewed senior officials from the Army, Air Force, Navy, and the 
Corps. We also interviewed headquarters and regional officials from 
the Environmental Protection Agency to discuss the MMRP. 

We assessed the reliability of data for certain variables related to 
our objectives in DOD's Knowledge-Based Corporate Reporting System, by 
electronically testing for obvious errors in accuracy and 
completeness, reviewing information about the data and the system that 
produced them, and interviewing agency officials knowledgeable about 
the data. When we found inconsistencies in the data, we worked with 
DOD officials to clarify them before conducting our analyses. We 
determined that the data were sufficiently reliable for the purposes 
of providing basic descriptive information about the MMRP and for 
analyzing the duration of phases of the cleanup process. However, we 
found data on funds obligated for cleanup to be incomplete and 
therefore not suitable for analysis. We discuss this data reliability 
problem in more detail later in the report. We conducted this 
performance audit from January 2009 to April 2010 in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings 
and conclusions based on our audit objectives. We believe that the 
evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. Appendix I provides 
additional detail on our scope and methodology. 

Background: 

The National Defense Authorization Act for fiscal year 2002 requires 
DOD to develop and maintain an inventory of defense sites known or 
suspected to contain unexploded ordnance, discarded military 
munitions, or munitions constituents and to annually update the 
inventory and list prioritizing these sites for cleanup.[Footnote 7] 
Figure 1 shows an example of unexploded ordnance found at a munitions 
response site on Beale Air Force Base in 2008. 

Figure 1: Unexploded Ordnance Found at a Munitions Response Site: 

[Refer to PDF for image: photograph] 

Source: Air Force. 

[End of figure] 

As of fiscal year 2008, DOD had identified 3,674 munitions response 
sites in the United States and its territories and outlying areas. 
[Footnote 8] Figure 2 shows the number of sites in each state and in 
United States territories and outlying areas. 

Figure 2: Location and Number of Munitions Response Sites, as of 
Fiscal Year 2008: 

[Refer to PDF for image: map of the U.S. and associated data] 

Alabama: 62; 
Alaska: 260; 
American Samoa: 3; 
Arizona: 144; 
Arkansas: 25; 
California: 526; 
Colorado: 66; 
Connecticut: 8; 
Delaware: 11; 
District of Columbia: 36; 
Florida: 161; 
Georgia: 44; 
Guam: 31; 
Hawaii: 165; 
Idaho: 27; 
Illinois: 74; 
Indiana: 35; 
Iowa: 14; 
Kansas: 66; 
Kentucky: 16; 
Louisiana: 59; 
Maine: 47; 
Marshall Islands: 1; 
Maryland: 111; 
Massachusetts: 83; 
Michigan: 71; 
Minnesota: 11; 
Mississippi: 33; 
Missouri: 31; 
Montana: 22; 
Nebraska: 32; 
Nevada: 66; 
New Hampshire: 15; 
New Jersey: 62; 
New Mexico: 174; 
New York: 95; 
North Carolina: 85; 
North Dakota: 11; 
Northern Mariana Islands: 6; 
Ohio: 29; 
Oklahoma: 42; 
Oregon: 24; 
Pennsylvania: 56; 
Puerto Rico: 32; 
Rhode Island: 19; 
South Carolina: 53; 
South Dakota: 20; 
Tennessee: 45; 
Texas: 270; 
U.S. Virgin Islands: 3; 
Utah: 50; 
Vermont: 5; 
Virginia: 140; 
Wake Island: 1. 
Washington: 78; 
West Virginia: 4; 
Wisconsin: 3; 
Wyoming: 11. 

Source: GAO analysis of DOD data; Map Resources (map). 

[End of figure] 

The majority of munitions response sites are located on active 
installations (46 percent) and FUDS (45 percent), with the remainder 
located on BRAC installations (9 percent). The Corps is responsible 
for cleanup at 45 percent (1,661) of the munitions response sites, the 
Army for 29 percent (1,080), the Air Force for 18 percent (644), and 
the Navy for 8 percent (289), as shown in figure 3. 

Figure 3: Percentage of Munitions Response Sites at Active and BRAC 
Installations and FUDS, and Distribution among the Military Services 
and the Corps: 

[Refer to PDF for image: pie-chart] 

N = 3,674. 

Active installations: 46%; 
FUDS: 45%; 
BRAC installations: 9%. 

Corps: 45%; 
Army: 29%
Air Force: 18%; 
Navy: 8%. 

Source: GAO analysis of DOD data. 

[End of figure] 

Each of the military services and the Corps have established their own 
individual organizational structures to implement the MMRP. These 
structures, which are similar to the structures of their respective 
IRPs, have various levels of management, but for ease of discussion, 
we have identified three broad levels of management. At the 
operational level, key responsibilities rest with project managers who 
directly oversee MMRP activities at Army, Air Force, and Navy active 
and BRAC installations and at FUDS. The project managers' 
responsibilities may include planning munitions response actions, 
developing cleanup cost estimates, coordinating with stakeholders, 
[Footnote 9] and ensuring oversight of program activities, such as 
monitoring technical work conducted by the contractors who are 
responsible for various aspects of the cleanup process. Next, at the 
middle-management level, managers provide direct oversight of MMRP 
activities conducted at the operational level and also serve as 
liaisons between the operational level and the top leadership level of 
the organization. Managers at the middle-management level may be 
responsible for monitoring MMRP activities, such as reviewing cleanup 
plans developed at the operational level, determining operational 
level funding, and ensuring that their munitions response programs are 
in compliance with applicable laws and policies. Finally, managers at 
the leadership level of the organization may conduct program reviews 
to ensure MMRP activities implemented by the operational and middle-
management levels are in compliance with applicable laws, regulations, 
and DOD policy and to approve funding requests for munitions response 
actions that have been recommended by the levels below them. 

Some munitions response sites pose a greater risk to human health or 
the environment than others. The National Defense Authorization Act 
for fiscal year 2002 requires DOD to develop a protocol for assigning 
a relative priority for cleanup for all sites based primarily on 
factors relating to safety and environmental hazard potential. 
[Footnote 10] Initially, the military services and the Corps used a 
process that produced what are known as risk assessment code scores to 
rank the relative risk of munitions response sites based on the risk 
they pose relative to other sites. However, in 2005, DOD, in 
conjunction with the states, tribes, and the Environmental Protection 
Agency, established a new process, known as the Munitions Response 
Site Prioritization Protocol,[Footnote 11] which establishes a 
consistent and transparent approach to evaluating the relative risks 
at munitions response sites and prioritizes them for cleanup. The new 
process uses three hazard evaluation modules to determine a site's 
relative priority score--Explosive Hazard Evaluation, Chemical Warfare 
Materiel Hazard Evaluation, and Health Hazard Evaluation. [Footnote 
12] After the military service or the Corps has gathered sufficient 
data about a site's characteristics to be able to complete at least 
one of the protocol's modules, it assigns the site a relative priority 
score of one through eight, with one representing the highest priority 
or greatest risk and eight the lowest priority or lowest risk. The 
military services and the Corps may not assign a relative priority 
score to some sites and instead assign one of the following 
alternative designations:[Footnote 13] 

* Evaluation pending. Indicates that there are known or suspected 
hazards present but that sufficient information is not available to 
populate the data elements for at least one of the modules and the 
site requires further evaluation. 

* No longer required. Indicates that the site no longer requires a 
priority score because DOD has conducted a response action and 
determined that no further action is required. 

* No known or suspected hazard. Indicates that the site does not 
require an evaluation to determine a relative priority score because 
review of the site concluded that no hazards are present. 

According to DOD's policy, the military services and the Corps will 
clean up munitions response sites with a higher relative priority 
score before a site with a lower score. However, the military services 
and the Corps also can consider other factors, such as military 
mission needs, land reuse plans, and stakeholder concerns, in 
determining which sites to clean up first. DOD refers to the process 
of deciding which sites to clean up first based on relative priority 
scores in combination with other factors as "sequencing" sites for 
cleanup. 

In deciding what actions, if any, are needed to clean up a site 
identified as potentially contaminated with military munitions, DOD 
officials told us that the military services and the Corps follow the 
process established under the Comprehensive Environmental Response, 
Compensation, and Liability Act (CERCLA) of 1980.[Footnote 14] Key 
steps in this process are:[Footnote 15] 

* Preliminary assessment. To determine through a review of existing 
information whether a potential military munitions hazard is present 
and whether further action is needed. 

* Site inspection. To determine whether a hazard or potential hazard 
exists and the nature of any associated threats to human health or the 
environment. The site inspection builds upon the preliminary 
assessment and involves sampling, as appropriate, to determine the 
nature of contamination and potential pathways of exposure and to 
recommend whether further action is warranted. (Figure 4 shows a site 
inspection team surveying a munitions response site at Beale Air Force 
Base.) 

* Remedial investigation/feasibility study. To collect data necessary 
to determine the nature and extent of the hazard and to assess risk to 
human health and the environment. Also, establish objectives for the 
remedial action, and analyze and evaluate cleanup approaches. 
According to DOD, cleanup approaches could include limiting public 
access by installing controls such as barriers, fences, and signs 
coupled with land use controls. 

* Remedial design/remedial action. To design, construct, and operate 
the cleanup remedy selected by the feasibility study. DOD considers 
that it has the "remedy in place" when testing shows that the remedy 
will operate as designed. DOD considers that it has attained "response 
complete" when the cleanup objective is achieved.[Footnote 16] 

Figure 4: Site Inspection at Beale Air Force Base: 

[Refer to PDF for image: photograph] 

Source: Air Force. 

[End of figure] 

The National Defense Authorization Act for fiscal year 2007 directs 
DOD to establish the following performance goals for defense sites 
under the MMRP: 

* complete, by September 30, 2007, preliminary assessments of all 
munitions response sites on active installations and FUDS; 

* complete, by September 30, 2010, site inspections of all munitions 
response sites at active installations and FUDS; 

* achieve, by September 30, 2009, a remedy in place or response 
complete for all munitions response sites at all military 
installations realigned or closed prior to 2005; and: 

* achieve, by a date to be established by the Secretary of Defense, a 
remedy in place or response complete for all munitions response sites 
at all active installations, FUDS, and all military installations 
realigned or closed under the 2005 round of base closures (BRAC 2005). 
[Footnote 17] 

In addition, the act requires that DOD report "such interim goals as 
the Secretary determines feasible" for the military services and the 
Corps to reach their performance goals for remedy in place or response 
complete at active, FUDS, and BRAC 2005 munitions response sites. 

To track information pertaining to the number, description, and status 
of munitions response sites being managed under each of their MMRPs, 
the military services and the Corps maintain their own databases. 
Twice a year they report information requested by DOD about their 
munitions response sites. This information is compiled in a database 
DOD calls the Knowledge-Based Corporate Reporting System. DOD uses the 
information in this database to help oversee the overall MMRP; track 
progress toward the achievement of its program performance goals; and 
to support its need to report on the progress of the MMRP to Congress 
and others, for example in DOD's Defense Environmental Programs Annual 
Report to Congress. 

The Military Services and the Corps Do Not Track MMRP Staffing Levels, 
and the MMRP Receives a Small Share of DOD's Environmental Restoration 
Funds: 

According to a senior DOD official, DOD does not require the military 
services or the Corps to track the time they spend working on MMRP 
activities separately from the time they spend working on other 
environmental restoration program activities. As a result, we were 
unable to determine the staffing levels dedicated to the MMRP. 
According to officials from the Army, Air Force, Navy, and the Corps, 
their staff support both the IRP and the MMRP. However, these 
officials told us they do not separately track the time that staff 
spend working on each of the two programs because Congress does not 
appropriate funding for these programs separately and tracking staff 
time separately would add no value to accomplishing cleanup of these 
sites. Moreover, a senior Army official told us that the extent to 
which staff work on the IRP and MMRP varies greatly among employees 
from day to day, making it extremely difficult to quantify the time 
devoted to each program. 

DOD provides the military services and the Corps combined annual 
funding for all of their environmental restoration programs.[Footnote 
18] It is the responsibility of the military services and the Corps to 
make decisions about how to prioritize that funding among their 
environmental programs, such as the IRP and MMRP. Between 2002 and 
2008, the military services and the Corps directed most of their IRP 
and MMRP environmental restoration funds to their respective IRPs--a 
total of about $9.7 billion compared with the approximately $1.2 
billion they directed to their respective MMRPs (see figure 5). 

Figure 5: IRP and MMRP Obligated Funds, Fiscal Years 2002 through 2008: 

[Refer to PDF for image: multiple line graph] 

Fiscal Year: 2002; 
Total IRP: $1,423 million; 
Total MMRP: $95.3 million. 

Fiscal Year: 2003; 
Total IRP: $1,566.5 million; 
Total MMRP: $136.1 million. 

Fiscal Year: 2004; 
Total IRP: $1,334.1 million; 
Total MMRP: $119.6 million. 

Fiscal Year: 2005; 
Total IRP: $1,239.6 million; 
Total MMRP: $151.1 million. 

Fiscal Year: 2006; 
Total IRP: $1,351.5 million; 
Total MMRP: $202.8 million. 

Fiscal Year: 2007; 
Total IRP: $1,301.6 million; 
Total MMRP: $244.7 million. 

Fiscal Year: 2008; 
Total IRP: $1,448.1 million; 
Total MMRP: $283.5 million. 

Source: GAO analysis of DOD data. 

Note: Totals do not include program management and support costs. 

[End of figure] 

Annual obligations[Footnote 19] for the MMRP have increased from about 
$95 million in fiscal year 2002, the program's first full year of 
operation, to approximately $284 million in fiscal year 2008 (see 
figure 6). 

Figure 6: MMRP Obligated Funds, Fiscal Years 2002 through 2008: 

[Refer to PDF for image: vertical bar graph] 

Fiscal Year: 2002; 
Funds obligated: $95.3 million. 

Fiscal Year: 2003; 
Funds obligated: $136.1 million. 

Fiscal Year: 2004; 
Funds obligated: $119.6 million. 

Fiscal Year: 2005; 
Funds obligated: $151.1 million. 

Fiscal Year: 2006; 
Funds obligated: $202.8 million. 

Fiscal Year: 2007; 
Funds obligated: $244.7 million. 

Fiscal Year: 2008; 
Funds obligated: $283.5 million. 

Source: GAO analysis of DOD data. 

Note: Totals do not include program management and support costs. 

[End of figure] 

According to DOD officials, the majority of munitions response sites 
are still in the investigative phases and are not yet ready for 
cleanup. Officials said that the military services and the Corps 
obligated more money to the IRP than the MMRP for the following 
reasons: (1) most sites in the IRP are being cleaned up or are ready 
for cleanup; (2) cleanup is more costly than investigation; and (3) 
the IRP was established long before the MMRP. As of the end of fiscal 
year 2008, according to DOD's 2008 annual report to Congress, the 
military services and the Corps had achieved response complete status 
at about 79 percent of their IRP sites. Officials from the military 
services and the Corps said they plan to apply more funding to the 
MMRP and less to the IRP as they achieve remedy in place or response 
complete status for additional IRP sites. For example, a senior Corps 
official said that after the Corps meets its IRP goals for FUDS in 
fiscal year 2020, FUDS munitions response program funding should 
increase. Similarly, Air Force officials told us they are directing 
more funding to the IRP to reach its goals. For example, in fiscal 
year 2007, the Air Force directed almost $430 million to its IRP, 
while directing less than $19 million to its MMRP. Air Force officials 
said that after the Air Force achieves remedy in place or response 
complete at its IRP sites, it will increase funding to address cleanup 
needs at its munitions response sites. 

Additionally, Army and Navy officials told us that as they continue to 
make progress toward completing IRP cleanups, they have begun to 
direct more funding to MMRP sites. For example, according to the 
Army's fiscal year 2009 environmental restoration program management 
plan, the Army expects MMRP funding for active installations to reach 
almost $285 million in fiscal year 2011, compared with about $33 
million in fiscal year 2008. Furthermore, Navy officials told us that 
over the past few years, the Navy has begun shifting some funding from 
its IRP to its MMRP. For example, in fiscal year 2005, the Navy 
directed about $20 million to its MMRP, while in 2008, it directed 
approximately $71 million. 

Most Sites That DOD Has Reported as Response Complete Did Not Require 
Cleanup, and Cleanup Priorities Are Still Being Determined for the 
Majority of Sites: 

DOD reported to Congress that it had achieved response complete at 
more than one-third of its munitions response sites by the end of 
fiscal year 2008. According to DOD, most of these sites did not 
require cleanup under the MMRP. For the small number of sites where 
the military services and the Corps have conducted cleanup activities 
under the MMRP, a variety of factors influenced the selection of these 
sites, including immediate danger to public safety and pressing 
military mission needs. However, for the majority of sites in the MMRP 
inventory, the military services and the Corps are still in the 
process of gathering information necessary to assess the sites' 
relative risk levels in order to set cleanup priorities. In some 
cases, they have also begun to develop approaches to sequencing their 
respective sites for cleanup. 

Most Sites DOD Reported as Response Complete Did Not Require Cleanup, 
although DOD Has Cleaned Up a Small Number of Sites for Various 
Reasons: 

DOD reported to Congress having achieved response complete at 1,318 of 
a total of 3,674 munitions response sites by the end of fiscal year 
2008.[Footnote 20] However, according to our analysis of data provided 
by the military services and the Corps, 1,234 of these 1,318 sites did 
not require actual cleanup under the MMRP and were instead 
administratively closed.[Footnote 21] An administrative closure can 
occur for a variety of reasons but does not involve any actual cleanup 
under the MMRP.[Footnote 22] One of the most common reasons for an 
administrative closure was that the sites were investigated and found 
to be free of hazards. Our analysis found more than 700 of the 1,234 
administratively closed sites were closed because, during the 
preliminary assessment, site inspection, or remedial investigation of 
the site, the military services and the Corps concluded that the 
threats assumed to be present when the site was included in the MMRP 
inventory were actually negligible or did not exist.[Footnote 23] For 
example, according to a senior Corps official, the Corps assumed that 
all FUDS forts and camps had firing ranges and therefore included all 
of them in the MMRP inventory. Upon further study, the Corps found 
that many former forts and camps did not have firing ranges, so 
cleanup under the MMRP at these sites was not necessary. Corps and 
military service officials also told us that some sites were 
administratively closed for a variety of reasons, such as (1) they 
were not eligible for MMRP (either because the sites were funded under 
another program--such as the IRP--or were discovered to be currently 
in use by the military);[Footnote 24] (2) they were merged with other 
sites and therefore ceased to exist as independent sites; (3) they 
never actually existed and were added to the inventory in error; or 
(4) the hazard was not of DOD origin and therefore not DOD's 
responsibility to clean up. 

Since 2001, we have been concerned about the lack of clarity in DOD's 
approach for reporting on response complete sites. That year we 
recommended that DOD exclude projects from its "completed" list that 
did not require actual cleanup and were closed solely as the result of 
an administrative action.[Footnote 25] According to DOD's Defense 
Environmental Restoration Program Management Guidance, response 
complete means, in essence, that the military services or the Corps 
have taken and completed remedial actions at a site.[Footnote 26] 
Nevertheless, the department disagreed with our recommendation, and 
its environmental programs annual reports to Congress since 2001 have 
continued to report administratively closed sites as response complete 
with very limited explanation. Specifically, in its fiscal year 2008 
annual report,[Footnote 27] DOD mentioned in a note to a figure that 
the response complete category included both sites it cleaned up and 
sites that did not require actual cleanup, which we have defined as 
administratively closed. A senior DOD official told us that DOD 
reports administratively closed sites and sites that were actually 
cleaned up as response complete because in both cases it has completed 
its response under the CERCLA process. Nonetheless, because DOD does 
not clearly and prominently explain in its reports that many of these 
sites were not actually cleaned up under the MMRP, we continue to 
believe that the information being provided to Congress and the public 
is misleading and overstates the level of progress made cleaning up 
sites under the MMRP. 

Our analysis indicates that the military services and the Corps have 
conducted cleanup activities under the MMRP at 84 of the 1,318 sites 
it reported as response complete as of fiscal year 2008, as shown in 
figure 7. 

Figure 7: Sites the Military Services and the Corps Cleaned Up under 
the MMRP, as of Fiscal Year 2008: 

[Refer to PDF for image: pie-chart] 

N = 84. 

Air Force: 54; 
FUDS: 27; 
Navy: 2; 
Army: 1. 

Source: GAO analysis of DOD data. 

[End of figure] 

According to military service and Corps officials, these sites were 
selected for cleanup based on an assessment of relative risk and other 
factors. These other factors included imminent danger to public 
safety, pressing military mission needs, land reuse plans, and 
stakeholder concerns, for example: 

* Imminent danger. According to a senior Army official, the Corps 
cleaned up the Dolly Sods North FUDS, located in the Monongahela 
National Forest in West Virginia, for imminent danger reasons. This 
site had been assigned a medium risk assessment code score.[Footnote 
28] Hikers visiting the site--a wilderness area currently owned by the 
U.S. Forest Service and visited by approximately 60,000 people 
annually--reported finding military munitions on the ground. For 
example, in 1996, a piece of live ordnance was found about 300 feet 
from a visitor parking lot. As a result, the Corps took cleanup 
actions that involved removing ordnance from trail areas and campsites 
because it determined that these items presented an imminent danger to 
the public. The Corps completed the cleanup in 2000 and also 
implemented an explosives safety education program for visitors to the 
site, which is ongoing. 

* Mission needs. According to Air Force officials, the Air Force 
selected the sole munitions response site at Little Rock Air Force 
Base in Arkansas for cleanup in fiscal year 2009 to meet mission 
needs, even though it received a low prioritization protocol score. 
The factors that drove the decision to clean up this site were that 
(1) the site is a possible location for a future Security Forces 
Regional Training Center, and (2) by cleaning up the only MMRP site on 
the base, it would release the entire base from the program and thus 
reduce related administrative costs. The Air Force estimates that site 
cleanup will be complete in fiscal year 2010. 

* Land reuse plans. According to a senior Army official, the Army 
funded cleanup work done by a local redevelopment authority on a 
munitions response site at Fort Ord, a BRAC installation near 
Monterey, California, to meet land reuse plans, even though the Army 
assigned the site a medium risk assessment code score and has not 
scored it under the munitions response site prioritization protocol. 
The Army initiated cleanup at this site largely in response to the 
community's request to implement a land reuse plan to construct a 
veterans' cemetery. The central California coast region currently 
lacks burial space for the approximately 50,000 veterans residing in 
the area, some of whom served in World War II and now wish to be 
buried at Fort Ord. According to a senior Army official, as of January 
2010, the redevelopment authority had completed cleanup, and the 
veterans' cemetery can be developed as soon as funding is available. 

* Stakeholder concerns. According to a senior Army official, the Corps 
decided to clean up the Torpedo and Bombing Range FUDS at Pyramid Lake 
northeast of Reno, Nevada, because of stakeholder concerns, even 
though the Corps assigned the site a low risk assessment code score. 
[Footnote 29] The Corps responded to concerns expressed by the Pyramid 
Lake Paiute Tribe by initiating cleanup using funds from FUDS and 
another program managed by the Corps, the Native American Lands 
Environmental Mitigation Program. Pyramid Lake covers more than 20 
percent of the Pyramid Lake Indian Reservation and is of high cultural 
and social value to the tribe. The Corps removed surface bunkers and 
debris from the site, as well as over 13 tons of rockets and other 
discarded munitions submerged in the lake, and cleanup was completed 
in 2006. 

The Military Services and the Corps Have Evaluated Few Munitions 
Response Sites for Relative Risks and Lack Consistent Approaches for 
Sequencing Sites: 

Before beginning cleanup at most of their munitions response sites, 
the military services and the Corps first gather enough information to 
use the prioritization protocol to assign a relative priority score to 
each site based on its potential environmental and safety hazards. 
Officials from the military services and the Corps told us that data 
necessary to derive a reliable priority score are gathered during the 
site inspection phase. However, as of the end of fiscal year 2008, the 
military services and the Corps had completed the site inspection 
phase for only 38 percent of munitions response sites.[Footnote 30] 
Consequently, during fiscal year 2007--the year the military services 
and the Corps began reporting prioritization protocol scores--and 
fiscal year 2008, the military services were only able to report 
relative priority scores to DOD for 432 sites, or 19 percent of the 
2,333 munitions response sites that needed scoring.[Footnote 31] 
Specifically, the Air Force reported scores for 53 sites, or 13 
percent of its 417 sites; the Army reported scores for 175 sites, or 
29 percent of its 603 sites; and the Navy reported scores for 204 
sites, or 89 percent of its 230 sites. The military services and the 
Corps assigned the remaining 1,901 sites the alternative rating 
"evaluation pending" as of the end of fiscal year 2008, indicating 
that they needed more information before they could calculate relative 
priority scores. 

According to a senior Army official, the Corps has not reported any 
prioritization protocol scores for FUDS to DOD because the scores have 
not yet been finalized pending an internal review. The same official 
said that the Corps will report scores for about 600 sites to DOD by 
the end of fiscal year 2010 and will report scores for the remaining 
sites by fiscal year 2014. The percentage of sites with reported 
scores by military service and the Corps is shown in figure 8. 

Figure 8: Sites with Prioritization Protocol Scores Reported to DOD, 
as of Fiscal Year 2008: 

[Refer to PDF for image: vertical bar graph] 

Air Force (N = 53): 
Percentage of sites reporting scores: 13. 

Army (N = 175): 
Percentage of sites reporting scores: 29. 

Navy (N = 204): 
Percentage of sites reporting scores: 89. 

FUDS[A] (N = 0): 
Percentage of sites reporting scores: 0. 

Source: GAO analysis of DOD data. 

[A] The Corps has not reported any prioritization protocol scores for 
FUDS. 

[End of figure] 

After they have assigned prioritization protocol scores to all of 
their sites, each of the military services and the Corps are to 
determine which sites to sequence and allocate funding to first for 
the next phase of the cleanup process.[Footnote 32] However, currently 
there is no consistent DOD approach for or guidance on considering 
factors other than risk in making sequencing decisions. In the absence 
of guidance from DOD that establishes a consistent set of 
requirements, we found that the Air Force, Army, and the Corps have 
begun to independently develop their own approaches for sequencing, 
and the Navy has not yet determined whether it needs to develop such 
an approach. Specifically, we found the following: 

* The Air Force has developed detailed, written guidance for 
incorporating factors other than risk into its site sequencing 
decisions. The guidance requires the use of a numerical scoring 
process that incorporates prioritization protocol scores, as well as 
legal, scheduling, and mission factors, to sequence its sites for 
cleanup. According to Air Force officials, the Air Force is applying 
this approach to a single pool of both IRP and MMRP sites, which they 
believe allows them to fund cleanups of the highest-priority sites 
first across both programs. In addition, a senior Air Force official 
told us that using the standardized process ensures fairness and 
transparency in site sequencing. 

* According to a senior Army official, the Army is currently 
developing a sequencing policy that it hopes to release by May 2010, 
which will apply to sites managed by both the Army and the Corps. The 
policy will likely require program managers to document the reasons 
for their sequencing decisions to facilitate transparency and allow 
for more effective Army oversight. However, the official said that the 
Army does not plan to require a particular approach to sequencing and 
believes a quantitative approach similar to the Air Force's approach 
could be too restrictive and not allow adequate flexibility for 
decision making. 

* According to a senior Navy official, it is too early to determine 
whether the Navy needs to issue additional guidance beyond the 
framework that establishes the prioritization protocol and sequencing 
considerations currently provided in the DOD regulations. According to 
the official, although the Navy has initially prioritized many sites 
based on preliminary assessment data, it does not expect to begin 
fully sequencing sites until 2011, when it completes site inspections 
and applies the data gathered to generate relative priority scores. 
The Navy will wait to see if it encounters any difficulties before 
deciding on whether to develop additional guidance. 

According to a senior DOD official, the department plans to give the 
military services and the Corps the flexibility to make sequencing 
decisions as they see fit. This official said that the military 
services and the Corps have experience making sequencing decisions for 
the IRP, and DOD has not encountered any problems with these 
decisions. As a result, the official said DOD sees no need to provide 
guidance on how factors other than risk should be considered when 
making decisions about which sites to sequence first for cleanup. 
However, in the absence of such guidance, the military services and 
the Corps may not consistently (1) consider the same range of factors 
in making their decisions or (2) give the same relative significance 
to risk and other factors in making their cleanup sequencing 
decisions. As a result, we believe that this could impact the 
consistency and transparency of sequencing decisions. 

DOD Has Not Established a Key Performance Goal for Its MMRP at FUDS, 
as Required by Law, and Has Not Determined and Reported on the 
Feasibility of Interim Goals: 

DOD has not yet implemented the statutory requirement contained in the 
fiscal year 2007 National Defense Authorization Act to establish a key 
performance goal for reaching remedy in place or response complete at 
munitions response sites on FUDS, although DOD has established the 
required performance goals for active and BRAC 2005 sites.[Footnote 33] 

According to a senior DOD official, the primary reason DOD has not 
established a remedy in place or response complete performance goal 
for munitions response sites on FUDS is that the Corps has not 
completed site inspections at most of these sites. This official told 
us that it is not possible to fully understand each site's cleanup 
requirements before the site inspection is complete, and therefore, 
establishing a goal at this time is premature. In addition, the 
official said that the number of munitions response sites on FUDS is 
still changing because the Corps is subdividing munitions response 
areas into smaller, more manageable sites. The anticipated increase in 
the number of sites is likely to impact cleanup schedules, according 
to this official. Finally, the official told us that DOD expects to 
establish a performance goal for munitions response sites on FUDS 
after the Corps completes site inspections, which is expected at the 
end of fiscal year 2010. Until DOD sets the goal, Congress and the 
public will have less information with which to monitor the progress 
of cleanups at munitions response sites on FUDS. 

The fiscal year 2007 National Defense Authorization Act also requires 
DOD to report "such interim goals as the Secretary determines 
feasible" for the military services and the Corps to reach their 
remedy in place or response complete performance goals.[Footnote 34] 
However, DOD has not yet determined whether such goals are feasible--
the necessary initial step before reporting interim goals. A senior 
DOD official said that DOD will determine whether interim goals are 
feasible after the military services and the Corps have completed the 
site inspection phase for all munitions response sites, which they 
expect to do by the end of fiscal year 2010. The DOD official said 
that it is not practical for DOD to establish interim goals without 
first understanding the nature and extent of cleanup requirements at 
munitions response sites. However, DOD was able to establish its 
performance goals for reaching remedy in place or response complete 
for munitions response sites at active and BRAC 2005 installations, 
and we believe DOD should therefore be able to determine the 
feasibility of related interim goals. Furthermore, until DOD 
determines whether interim goals are feasible, and if so, reports them 
to Congress, DOD will not have addressed this requirement. Moreover, 
since DOD's MMRP remedy in place or response complete performance 
goals are long-term--2017 for sites at BRAC 2005 installations, 2020 
for sites at active installations, and possibly 2060 or later for 
FUDS--without this determination and reporting of interim goals, 
Congress may have limited information with which to measure progress 
of the MMRP over the next decade. 

DOD Collects Limited Data on Factors That Can Affect MMRP Project 
Duration, and Incomplete Data Prevent an Assessment of the Accuracy of 
Its MMRP Cost Estimates: 

DOD collects data on two of the many factors that can influence 
project duration at munitions response sites.[Footnote 35] Our 
analysis of DOD's data on these two factors indicates that the larger 
the munitions response site and the more complex the type of hazard 
the longer the site takes to clean up. However, we were unable to 
assess the accuracy of the military services' and the Corps' estimates 
of the costs to complete phases of the cleanup process because DOD's 
database does not contain complete data on funds obligated for 
completing specific phases of the cleanup process for many munitions 
response sites.[Footnote 36] 

DOD Collects Information on Two Factors That Can Affect MMRP Project 
Duration: 

Although a number of factors can affect project duration at a 
munitions response site, DOD collects information on two of these 
factors--site size and the type of hazard. Specifically, DOD requires 
the military services and the Corps to report the acreage of sites and 
the type of hazard present, such as unexploded ordnance or munitions 
constituents. This information is compiled in DOD's environmental 
programs management database, known as the Knowledge-Based Corporate 
Reporting System. As would be expected, our analysis of DOD's data 
shows a relationship between these two factors and project duration--
that the average project duration for a munitions response site 
corresponds with the size of the site and the type of hazard. For 
example, small munitions response sites have an average project 
duration of 4.3 years, whereas larger sites have an average project 
duration of 5.9 years. Additionally, sites with the longest project 
duration, 5.8 years, were the ones that had unexploded munitions and 
ordnance. In contrast, sites with small arms ranges, had an average 
project duration of 5 years. 

Officials from the military services and the Corps told us that a 
number of other factors can influence project duration, but DOD's 
database does not include information on these factors, which include 
the following: 

* The need to achieve consensus with stakeholders, such as regulators 
or community members, can increase project duration. For example, 
failure to reach consensus with regulators increased project duration 
at the Jackson Park Naval Housing Complex, according to Navy 
officials. One area of disagreement between Navy officials and federal 
regulators was over the number of detected metal pieces that needed to 
be excavated during the remedial investigation phase. Federal 
regulators wanted the Navy to excavate a higher percentage of detected 
metal pieces than the Navy initially intended to excavate. After a 
lengthy process, the Navy and federal regulators were able to reach 
consensus on the percentage of metal pieces to excavate. 

* Obtaining entry rights from current owners of FUDS properties takes 
time and can increase project duration. For example, a senior official 
from the Corps told us that a landowner at the Campbell Island, North 
Carolina, FUDS refused to grant the Corps access to the site because 
of dissatisfaction with the government. The site inspection phase was 
scheduled to start sometime after December 2008; however, as of 
February 2010, the Corps had not yet initiated the site inspection 
because the agency has not yet been able to obtain entry rights from 
the current landowner. Corps officials plan to contact the landowner 
sometime in 2010 in an effort to resolve the issue. 

* Site-specific factors arise that can extend project duration in some 
cases. For example, Air Force officials told us that strict 
requirements from the New Hampshire State Historic Preservation Office 
delayed cleanup at New Boston Air Force Base. It took the Air Force 
longer to complete the investigative phases of the cleanup process 
because the Historic Preservation Office required that all objects 
discovered on the site, that were not unexploded ordnances or 
munitions constituents, be left in place to allow an archeologist to 
photograph and log each item for the historical record. 

Incomplete Data Prevent an Assessment of the Accuracy of MMRP Cleanup 
Cost Estimates: 

We found that DOD lacks complete site-level data on obligated funds 
for the three phases of the cleanup process we examined--preliminary 
assessment, site inspection, and remedial investigation/feasibility 
study--for fiscal years 2001 through 2008. These are funds that DOD 
has legally committed to pay for activities conducted during a 
particular phase of the cleanup process. Assessing the extent to which 
DOD's estimates of costs for MMRP cleanup phases are accurate requires 
both data on the estimated costs and funds obligated so they can be 
compared to determine how closely the estimates match the obligations. 
Our analysis of the 2,611 munitions response sites where work was 
conducted during the preliminary assessment phase in fiscal years 2001 
through 2008 found that the database did not contain obligated funds 
data for 2,272 (or 87 percent) of the sites.[Footnote 37] According to 
a senior DOD official, the military services and the Corps often are 
unable to report funds obligated for preliminary assessments for 
individual sites because they sometimes conduct preliminary 
assessments for all sites on an installation at the same time. In 
these instances, obligated funds are reported for the entire 
installation as opposed to on a site-by-site basis. Moreover, 
according to this official, the preliminary assessment and site 
inspection phases are often conducted concurrently and obligated funds 
for these two phases are consolidated in the site inspection phase. 
However, our analysis of the 2,322 munitions response sites where work 
was conducted during the site inspection phase in fiscal years 2001 
through 2008--including those sites that had a combined preliminary 
assessment and site inspection phase--found that the database did not 
have obligated funds data for 488 (or 21 percent) of these sites. 
Finally, our analysis of the 283 sites where work was conducted during 
the remedial investigation/feasibility study phase in fiscal years 
2001 through 2008 found the database did not have obligated funds data 
for 116 (or 41 percent) of these sites. Figure 9 summarizes our 
analysis of the percentage of sites in these three phases of the 
cleanup process that did not have obligated funds data. 

Figure 9: Percentage of Sites with No Obligated Funds Data, by Phase: 

[Refer to PDF for image: 3 pie-charts] 

Preliminary assessment phase (by individual site): N = 2,611; 
87%: Had no obligated funds data. 

Site inspection phase (combined with preliminary assessment): N = 
2,322; 
21%: Had no obligated funds data. 

Remedial investigation/feasibility study phase: N = 283; 
41%: Had no obligated funds data. 

Source: GAO analysis of DOD data. 

[End of figure] 

A senior DOD official told us that in fiscal year 2009, DOD 
implemented additional, more rigorous quality assurance and control 
processes designed to detect errors and inconsistencies in its MMRP 
cost estimates. For example, the official said that one of the new 
data checks DOD began performing in 2009 was to examine sites 
scheduled to begin a cleanup phase in the future to ensure that the 
database also includes an estimate of the cost to complete that phase. 
However, the official said DOD is not currently evaluating whether the 
military services and the Corps are reporting obligated funds data for 
project phases that have been completed. DOD requires the military 
services and the Corps to gather obligated funds data and, according 
to the DOD official, they should be reporting these data to DOD for 
inclusion in the Knowledge-Based Corporate Reporting System. In the 
absence of complete site-level information on obligated funds, DOD or 
Congress may not be able to determine the accuracy of the military 
services' and the Corps' reported cost estimates for completing the 
various phases of the cleanup process. Furthermore, DOD or Congress 
ultimately may not have sufficient information to assess whether DOD's 
estimates of its future cleanup liabilities under the MMRP are 
reliable. 

Conclusions: 

Thousands of munitions response sites that potentially pose risks to 
human health and the environment may need to be cleaned up before they 
can be reused, often for nonmilitary purposes. While we recognize that 
managing the MMRP is a large and complex task for DOD, the military 
services, and the Corps, we believe that in several areas there are 
opportunities for program management improvements. First, there is a 
need for guidance on how to conduct site sequencing in a manner that 
is consistent and transparent. While Congress mandated a consistent 
and transparent approach to assessing relative risks to assign cleanup 
priorities at sites, it did not provide for a process for assessing 
other factors, such as stakeholder concerns and military mission 
needs, when making site sequencing decisions; and DOD has not provided 
guidance to the military services and the Corps on how to conduct such 
assessments. Without DOD guidance on how to determine which sites to 
sequence first for cleanup, we are concerned that the military 
services and the Corps could use inconsistent processes for making 
these decisions. Second, we remain concerned about the transparency of 
DOD's response complete information provided to Congress. DOD has 
categorized 1,234 sites as response complete, but these sites did not 
require actual cleanup under the MMRP, and we believe that this fact 
is not adequately explained in DOD's annual report to Congress. As a 
result, Congress and the public may be misled about the extent to 
which actual cleanups have taken place under the MMRP to date. Third, 
despite a legal requirement to do so, DOD has not yet established the 
remedy in place or response complete goal for FUDS nor determined and 
reported any interim goals it finds feasible for the MMRP. 
Implementing these requirements would provide DOD, Congress, and the 
public better information to track progress toward cleaning up 
munitions response sites. Finally, the database that DOD uses to help 
manage its MMRP does not contain complete site-level data on obligated 
funds for the cleanup phases we examined. As a result, it is not 
possible to assess the accuracy of the cost estimates for activities 
conducted during these phases. As the MMRP matures and more sites 
begin actual cleanups, program costs will continue to increase and it 
will be critical for DOD to be able to determine whether its cost 
estimates for phases of the cleanup process are accurate, so that 
Congress and the public can have reasonable assurance that DOD's 
estimates of its future cleanup liabilities under the MMRP are likely 
to be reliable. 

Matter for Congressional Consideration: 

To improve transparency for progress DOD has made in cleaning up MMRP 
sites, Congress may wish to consider requiring that DOD report, in a 
separate category from its accounting of "response complete" sites in 
the Defense Environmental Programs Annual Report to Congress, any 
sites that DOD determined did not require actual cleanup under the 
MMRP and were administratively closed. 

Recommendations for Executive Action: 

To improve consistency, transparency, and management of the MMRP, we 
recommend that the Secretary of Defense take the following three 
actions: 

* develop guidance for the military services and the Corps that 
establishes a consistent approach for how factors other than relative 
risk should be considered in munitions response site sequencing 
decisions; 

* establish and report to Congress (1) a goal for achieving remedy in 
place or response complete for FUDS, as required by law, and (2) such 
interim goals as DOD determines feasible for the remedy in place or 
response complete goals at munitions response sites on active and BRAC 
2005 installations and FUDS; and: 

* establish a process to ensure the completeness of site-level 
obligated funds data in DOD's Knowledge-Based Corporate Reporting 
System database. 

Agency Comments and Our Evaluation: 

We provided a copy of a draft of this report to the Department of 
Defense for its review and comment. DOD partially agreed with two of 
our recommendations and disagreed with one recommendation and the 
matter for congressional consideration. 

DOD said that it partially agreed with our first recommendation that 
the Secretary of Defense develop guidance for the military services 
and the Corps that establishes a consistent approach for how factors 
other than relative risk should be considered in munitions response 
site sequencing decisions. DOD said that it will collect and evaluate 
information and lessons learned from the military services regarding 
their processes for sequencing munitions response sites. If DOD 
determines that additional guidance is necessary, DOD said it will 
develop specific sequencing protocols and issue further guidance to 
ensure consistency across the military services. However, DOD did not 
specify what additional information it needs to collect from the 
military services and the Corps to determine that they currently are 
taking different approaches to sequencing their sites for cleanup. Nor 
did DOD explain in its comments the need for providing the military 
services and the Corps the flexibility to develop different approaches 
to sequencing munitions response sites. Given that this flexibility 
could result in inconsistent processes for making sequencing 
decisions, we continue to believe that DOD needs to provide guidance 
to the military services and the Corps that establishes a consistent 
approach to sequencing. This guidance will ensure that the military 
services and the Corps not only use the Munitions Response Site 
Prioritization Protocol to assign site priorities in a consistent and 
transparent fashion, but also ensure that they consider the same range 
of other factors, in addition to relative risk, in making their 
decisions and assess the significance of those factors in a consistent 
way. 

DOD also partially concurred with our second recommendation, that DOD 
establish a goal of remedy in place or response complete for FUDS, as 
required by law, and interim goals at munitions response sites on 
active and BRAC 2005 installations and FUDS. DOD said that it did not 
concur with what it understood to be a separate part of the 
recommendation--to set a date for "completing cleanup" of FUDS. 
However, we did not intend to convey a further requirement beyond the 
remedy in place or response complete goal for FUDS, and we clarified 
the recommendation accordingly. DOD said that it will establish a 
remedy in place or response complete goal for munitions response sites 
at FUDS and will establish additional short-term interim goals for 
active and BRAC 2005 installations and FUDS once it has a better 
understanding of the nature and extent of cleanup requirements at 
these sites. However, DOD has not committed to a date by which it will 
establish these goals. We believe it is important for DOD to set these 
goals as soon as possible because, until it does so, Congress and the 
public will have less information with which to monitor the progress 
of cleanups at munitions response sites. 

DOD did not agree with our third recommendation to establish a process 
to ensure the completeness of site-level obligated funds data in its 
Knowledge-Based Corporate Reporting System database. DOD stated that 
it has procedures in place to plan, program, budget, and execute funds 
for cleanup actions at munitions response sites. DOD also said that it 
has information on obligated funds but that it is not typically 
available at the individual site level and is tracked outside of the 
Knowledge-Based Corporate Reporting System database. Although we 
recognize that DOD has these phase-level data in another database, we 
continue to believe that without site-level obligations data, DOD does 
not have the ability to compare the corresponding cost estimates to 
determine if they are accurate. In the absence of such a comparison, 
DOD or Congress may not be able to determine the accuracy of the 
military services' and the Corps' estimates of the costs to complete 
various phases of the cleanup process. 

Finally, DOD did not agree with our matter for congressional 
consideration that would require DOD to report in a separate category 
from its "response complete" sites in the Defense Environmental 
Programs Annual Report to Congress any sites that DOD determined did 
not require actual cleanup under the MMRP and were administratively 
closed. DOD said that it believes that all sites that complete the 
CERCLA process should be considered equal accomplishments whether they 
require a removal or remedial action or not. DOD also said that it 
believes it is misleading to characterize a site that achieves closure 
without an actual cleanup differently from one that has been cleaned 
up, and that this undermines the significant work and progress DOD has 
made. We recognize that DOD must conduct assessments and 
investigations to determine that no physical cleanup actions will be 
needed and that this process can require significant time and effort 
to complete. Nonetheless, we believe it is misleading to group 
administratively closed and actually cleaned up sites together because 
the actions DOD took to close those two types of sites are 
significantly different. Also, we do not believe that listing these 
sites in separate categories undermines the progress DOD has made. 
Rather, doing so will improve transparency and more clearly indicate 
the nature of the actions that DOD has taken to reach response 
complete for its munitions response sites. Consequently, we continue 
to believe that Congress may wish to consider requiring DOD to report 
sites that were administratively closed in a separate category from 
those sites requiring actual, physical cleanup. 

DOD also provided technical comments in an enclosure to its letter, 
which we have incorporated in this report as appropriate. DOD's letter 
is included in appendix II. 

We are sending copies of this report to the appropriate congressional 
committees, the Secretary of Defense, and other interested parties. In 
addition, the report will be available at no charge on the GAO Web 
site at [hyperlink, http://www.gao.gov]. 

If you or your staffs have any questions about this report, please 
contact me at (202) 512-3841 or mittala@gao.gov. Contact points for 
our Offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. GAO staff who made major 
contributions to this report are listed in appendix III. 

Signed by: 

Anu K. Mittal: 
Director, Natural Resources and Environment: 

[End of section] 

Appendix I: Objectives, Scope, and Methodology: 

The National Defense Authorization Act for fiscal year 2009 mandates 
that we assess the (1) Military Munitions Response Program's (MMRP) 
staffing and funding levels; (2) progress the Department of Defense 
(DOD) has made cleaning up munitions response sites; (3) extent to 
which DOD has established performance goals for the MMRP; and (4) 
extent to which DOD collects data on factors influencing project 
duration, as well as the accuracy of its cleanup cost estimates. 

In addressing these four objectives, we analyzed MMRP data for fiscal 
years 2001 through 2008 in DOD's environmental programs management 
database--the Knowledge-Based Corporate Reporting System--and the 
Defense Environmental Programs Annual Reports to Congress for fiscal 
years 2002 through 2008. We assessed the reliability of the data for 
relevant variables in the Knowledge-Based Corporate Reporting System 
by electronically testing for obvious errors in accuracy and 
completeness. We also reviewed information about data verification, 
reporting, and security, and the systems that produced the data, and 
interviewed officials knowledgeable about the data. When we found 
inconsistencies in the data, we worked with the officials responsible 
for the data to clarify these inconsistencies before conducting our 
analyses. We determined that the data were sufficiently reliable for 
the purposes of providing descriptive information about the MMRP and 
for analyzing the duration of phases of the MMRP cleanup process. 
However, we found MMRP obligated funds data to be incomplete and 
therefore not suitable for analysis. We discuss this data reliability 
issue in more detail later in this appendix. In addition, we reviewed 
key laws, regulations, policies, and guidance from DOD, the military 
services (Army, Air Force, and Navy),[Footnote 38] and the U.S. Army 
Corps of Engineers (Corps). We visited one base realignment and 
closure (BRAC) installation (Fort Ord), one active installation (Beale 
Air Force Base), and one formerly used defense site (FUDS) (Camp 
Beale) to ensure we had the opportunity to review MMRP operations at 
active and BRAC installations and FUDS. We also interviewed 
headquarters and regional officials from the Environmental Protection 
Agency to discuss the MMRP. 

To assess the military services' and the Corps' MMRP staffing and 
funding levels, we spoke with senior officials from the Office of the 
Deputy Under Secretary of Defense (Installations and Environment), the 
military services, and the Corps who are knowledgeable about how MMRP 
staffing and funding levels are determined. In addition, we reviewed 
the Defense Environmental Programs Annual Reports to Congress for 
fiscal years 2002 through 2008 to determine funding obligated for the 
MMRP. 

To assess the progress DOD has made in cleaning up munitions response 
sites, we identified, as of the end of fiscal year 2008, how many 
sites DOD had administratively closed and how many had been actually 
cleaned up. We defined a site as administratively closed if after 
investigating, DOD determined that it could safely close the site 
without taking remedial action. Specifically, we analyzed data in the 
Knowledge-Based Corporate Reporting System to identify sites that fit 
two criteria: (1) the "response complete"[Footnote 39] date matched 
the end date for the three investigative phases during which no 
remediation actions are taken (preliminary assessment, site 
inspection, and remedial investigation) and (2) no costs were reported 
in the remedial action construction or the remedial action operations 
phase. Senior officials from DOD, the military services, and the Corps 
agreed that these criteria would identify sites that had been closed 
without actual cleanup, which we have defined as being 
administratively closed. These criteria allowed us to identify 712 of 
the 1,318 sites DOD reported as having achieved response complete. 
However, we were unable to determine if any of the remaining 606 sites 
had been administratively closed because sites may have been 
administratively closed without the response complete date matching 
the end date of one of the investigative phases. Therefore, we asked 
the military services and the Corps to identify which sites they had 
administratively closed. The Air Force and the Navy were able to 
provide the information for their relatively small number of sites, 
but senior Army and Corps officials said they did not keep such 
information in a centralized database and it would take them too much 
time to gather it for their many sites. Instead, they provided us with 
the number of sites they had actually cleaned up and indicated that we 
could assume the remaining sites had been administratively closed. In 
addition, we assessed the progress the military services and the Corps 
have made in applying the Munitions Response Site Prioritization 
Protocol to generate relative priority scores for their sites by 
reviewing prioritization protocol data in the Knowledge-Based 
Corporate Reporting System. We considered a site to be scored if it 
was listed in the Knowledge-Based Corporate Reporting System as having 
a numerical relative priority score of one through eight or if it had 
been given the alternative designation of "no known or suspected 
hazard" as of the end of fiscal year 2008. We considered sites to not 
be scored if they had a designation of "evaluation pending" because 
this designation indicates that the military services or the Corps 
need more information to assign the site a relative priority score. We 
excluded from our analysis the 1,341 sites for which the military 
services and the Corps indicated that scoring was no longer required 
because DOD reported that most of these sites had already reached 
response complete. 

To assess the extent to which DOD has established performance goals 
for the MMRP, we reviewed the fiscal year 2007 National Defense 
Authorization Act, the Military Munitions Response Program 
Comprehensive Plan, and the fiscal year 2008 Defense Environmental 
Programs Annual Report to Congress. We also spoke with a senior 
official responsible for the MMRP from the Office of the Deputy Under 
Secretary of Defense (Installations and Environment) to determine the 
progress DOD has made in establishing performance goals. 

To assess the extent to which DOD collects data on factors influencing 
project duration, we reviewed and analyzed data from the Knowledge- 
Based Corporate Reporting System to determine the average length of 
time munitions response sites have been in the cleanup process. To 
determine project duration, we attempted to identify start and end 
dates for phases of the cleanup process for all 3,674 sites in the 
Knowledge-Based Corporate Reporting System. We measured project 
duration as the length of time between the earliest phase start date 
and the latest phase end date, calculated using both month and year 
information.[Footnote 40] Using this method, we were able to calculate 
project duration for 3,112 sites. We were unable to calculate project 
duration for 47 sites because they had no phase dates in the Knowledge-
Based Corporate Reporting System. We did not calculate project 
duration for the remaining 515 sites because they had phase start and 
end dates prior to fiscal year 2001 (when the MMRP was established) 
and were therefore outside the scope of this review. Next, we analyzed 
site size and type to assess their relationship to project duration. 
To analyze site size, we divided the list of sites into three 
similarly sized categories: (1) small (less than 23 acres); (2) medium 
(between 23 and 649 acres); (3) large (650 acres or larger). We also 
created a fourth category for sites reported as zero acres or those 
with missing size data. Once we assigned sites to a category, we were 
able to combine this analysis with our analysis on project duration to 
calculate the mean and median project duration for small, medium, and 
large sites. We reported the mean project duration in the report, and 
there was no substantive difference between the mean and median. We 
used the site-type data in the Knowledge-Based Corporate Reporting 
System to determine the relationship between project duration and type 
of hazard. We limited our analysis of site types to categories that 
included at least 5 percent of the total number of sites and then 
combined the remaining categories into an "other" category. This 
allowed us to analyze project duration for six site-type categories: 
(1) unexploded munitions and ordnance areas, (2) small arms ranges, 
(3) firing ranges, (4) explosive ordnance disposal areas, (5) other, 
and (6) unknown (i.e., information on site type was not available). 
Once we had determined these categories, we combined this analysis 
with our project duration analysis to calculate the mean and median 
project duration for each site type. We reported the mean project 
duration in the report, and there was no substantive difference 
between the mean and median. We also interviewed senior officials from 
the military services and the Corps to obtain their views on factors 
influencing project duration. 

To assess the accuracy of DOD's cleanup cost estimates, we assessed 
the reliability of data on obligated funds in the Knowledge-Based 
Corporate Reporting System for fiscal years 2001 through 2008. We 
analyzed the data to determine the extent to which sites with reported 
activities in three phases of the cleanup process also included data 
on funds obligated for those activities. We restricted our analysis to 
the first three phases of the cleanup process--preliminary assessment, 
site inspection, and remedial investigation/feasibility study--because 
most munitions response sites are in one of these phases. To determine 
if we had a sufficient number of sites to conduct our analysis, we 
calculated the number of sites in each of the three phases that had 
obligated funds data. We found that over 10 percent of sites for all 
three phases were missing obligated funds data. Therefore, we 
concluded that the data were not sufficiently reliable to allow us to 
compare obligated funds to cost estimates for the sites in all three 
phases to determine the accuracy of the estimates. 

We conducted this performance audit from January 2009 to April 2010 in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
3000 Defense Pentagon: 
Washington, DC 20301-3000: 

March 31, 2010: 

Ms. Anu K. Mittal: 
Director, Natural Resources and Environment: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

Dear Ms. Mittal: 

This is the Department of Defense (DoD) response to the GAO Draft Report
10-384, "Military Munitions Response Program, Opportunities Exist to 
Improve Program Management," dated March 2010, (GAO Code 361041). 
DoD's detailed responses to the GAO recommendations and the matter for 
Congressional consideration are provided at Enclosure 1. Enclosure 2 
provides additional substantive issues DoD has with the GAO draft 
report. Additional technical comments have been provided to GAO under 
separate cover. 

The Department partially concurs with GAO's first recommendation that 
the Secretary of Defense develop guidance that establishes a 
consistent approach for how the Military Services consider factors 
other than relative risk in munitions response site sequencing 
decisions. DoD will collect and evaluate information and lessons 
learned from the Military Services describing their processes for 
sequencing munitions response sites for munitions response activities. 
if additional guidance is necessary, DoD will develop specific 
sequencing protocols and issue further guidance to ensure consistency 
across the Military Services. 

The Department partially concurs with GAO's second recommendation that
the Secretary of Defense establish and report to Congress: (1) a 
target date for completing cleanup of Formerly Used Defense Sites 
(FUDS), as required by law; and (2) such interim goals as DoD 
determines feasible for the remedy in place or response complete goals 
at munitions response sites on active installations, installations 
closed under the 2005 Round of Base Realignment And Closures (BRAC), 
and FUDS. The Fiscal Year (FY) 2007 National Defense Authorization Act 
(NDAA) requires DoD to establish a remedy in place or response 
complete goal for munitions response sites at FUDS; DoD will set 
target dates for remedy in place or response complete, not for 
completing cleanup. The FY2007 NDAA also requires DoD to establish 
interim goals to track remedy in place or response complete
progress at active and BRAC 2005 installations and FUDS properties. 
DoD will comply with the requirements outlined in the FY2007 NDAA 
establishing additional short- and long-term performance goals once it 
has a better understanding of the nature and extent of cleanup 
requirements at these sites. 

The Department does not concur with GAO's third recommendation that 
the Secretary of Defense establish a process to ensure the 
completeness of obligated funds data for phases of the Military 
Munitions Response Program cleanup process in DoD's Knowledge-Based 
Corporate Reporting System database. GAO's suggestion that obligated 
funds are incomplete is not correct. Obligated funds data are 
available but are not typically reported for individual sites because 
contracts are often awarded at the installation-level or for groups of 
sites. Further, the Department has procedures in place to plan, 
program, budget, and execute funds for cleanup actions by phase at 
munitions response sites. 

The Department does not concur with GAO's request for Congress to 
consider requiring DoD to report separately on sites closed because 
they did not require removal or remedial actions. DoD believes that 
all sites that complete the Comprehensive Environmental Response, 
Compensation, and Liability Act (CERCLA) process should be considered 
equal accomplishments whether they require a removal or remedial 
action or not. The Department expends significant resources to conduct 
preliminary assessments, site inspections, remedial investigations, 
and feasibility studies to determine and document that it has met its 
cleanup objectives, and that there is no requirement for removal or 
remedial action. When the Department meets the cleanup objectives at a 
given site, the response action is complete, regardless of the phase 
of the CERCLA process in which the action is completed. 

Sincerely, 

Signed by: 

Dorothy Robyn: 
Deputy Under Secretary of Defense (Installations and Environment): 

Enclosures: As stated: 

GAO Draft Report Dated March 2010: 
GAO-10-384 (GAO CODE 361041): 
Enclosure 1: 

"Military Munitions Response Program, Opportunities Exist to Improve
Program Management" 

Department Of Defense Comments To The GAO Recommendations: 

Recommendation 1: The GAO recommends that the Secretary of Defense 
develop guidance for the Military Services and the Corps that 
establishes a consistent approach for how factors other than relative 
risk should be considered in munitions response site sequencing 
decisions. (p. 33/GAO Draft Report) 

DOD Response: DoD partially concurs. OSD believes that it has issued 
sufficient guidance on this subject at this time. This guidance 
appears in the Final Rule of the Munitions Response Site 
Prioritization Protocol (32 CFR Part 179) and is further explained in 
OSD's internal publication entitled Munitions Response Site 
Prioritization Protocol Primer, dated April 2007. Using the guidance 
provided in these documents, the Military Services sequence munitions 
response sites based primarily on the priority determined by applying 
the Munitions Response Site Prioritization Protocol, but also consider 
a range of factors including, but not limited to regulator and 
stakeholder concerns, and cultural, social and economic issues. These 
site-specific factors may influence the sequencing decision, but do 
not alter the priority. In the past three years of implementing this 
guidance, the Military Services have tested various sequencing 
practices and learned from their experiences in the field. Next year, 
after the Military Services begin sequencing their munitions response 
sites in earnest, OSD will collect and evaluate information and 
lessons learned from the Military Services describing their processes 
for sequencing munitions response sites for cleanup action. If we 
determine that the current amount of flexibility enjoyed by the 
Military Services is causing issues, OSD will consider developing 
additional guidance to establish more uniformity across the Military 
Services. 

Recommendation 2: The GAO recommends that the Secretary of Defense 
establish and report to Congress (1) a target date for completing 
cleanup of FUDS, as required by law, and (2) such interim goals as DoD 
determines feasible for the remedy in place or response complete goals 
at munitions response sites on active and BRAC 2005 installations and 
FUDS. (p. 33/GAO Draft Report) 

DOD Response: DoD partially concurs. The FY2007 National Defense 
Authorization Act requires the Secretary to establish a remedy in 
place or response complete goal for FUDS. The legislation does not 
require DoD to set a target date for completing cleanup of 1,111)S; 
therefore, DoD does not concur with this part of the recommendation. 
In addition, the law does not require DoD to establish these goals 
within any certain timeframe. 

The Military Services are currently completing site inspections on a 
very aggressive schedule at munitions response sites on active 
installations and FUDS properties. The data gathered during the site 
inspection phase are critical to informing DoD of cleanup 
requirements. Specifically, the site inspection data is necessary to 
determine how many sites will require additional response actions 
under the Military Munitions Response Program (MMRP) and the potential 
scope of the work. Once the site inspections are complete and the 
Department has sufficient information about site-specific conditions, 
DoD will evaluate performance data to understand the nature and extent 
of cleanup requirements. The Department will use this analysis to meet 
its statutory requirement to establish a long-term remedy in place or 
response complete goal for FUDS. In addition, DoD will establish short-
term interim goals for active and BRAC 2005 installations and FUDS 
properties that are both challenging and reasonable. 

Recommendation 3: The GAO recommends that the Secretary of Defense 
establish a process to ensure the completeness of obligated funds data 
for phases of the MMRP cleanup process in DOD's Knowledge Based 
Corporate Reporting System database. (p. 33/GAO Draft Report) 

DOD Response: DoD does not concur. The Department has procedures in 
place to plan, program, budget, and execute funds for cleanup actions 
at munitions response sites. The Military Services prepare cost 
estimates for future work at the site-level, while obligation data is 
often aggregated across multiple sites because contracts arc typically 
awarded at the installation-level or for a group of sites. The cost 
estimating programs DoD uses are based on ongoing and detailed data 
gathering on costs incurred for various types of environmental 
restoration work at a very detailed level. The Military Services 
report this data in DoD's Knowledge-Based Corporate Reporting System 
database. The Department reviews this data for accuracy and 
completeness prior to inclusion of the site-level obligations and cost 
estimates in the Defense Environmental Programs Annual Report to 
Congress. The Military Services also report obligations and cost 
estimates at the phase-level in the Select and Native Programming Data 
Input System. Because this data is at the phase- rather than site-
level, obligations for contracts awarded at the installation-level or 
for a group of sites are captured in the system. this information is 
reported in the Defense Environmental Programs Annual Report to 
Congress. Thus, complete obligation data is captured and provided to 
Congress and the public, but the Knowledge-Based Corporate Reporting 
System is not the source of the data. 

Congressional Consideration: The GAO recommends a matter for 
Congressional Consideration. To improve transparency for progress DoD 
has made in cleaning up MMRP sites, Congress may wish to consider 
requiring that DoD report in a separate category from its accounting 
of "response complete" sites in the Defense Environmental Programs 
Annual Report to Congress, any sites that DoD determined did not 
require actual cleanup under the MMRP and were administratively 
closed. (p.33/GAO Draft Report) 

DOD Response: DoD does not concur. DoD believes that sites achieving 
all cleanup objectives at any point in the process can be 
characterized as response complete under the Comprehensive 
Environmental Response, Compensation, and Liability Act (CERCLA), 
whether they require a removal or remedial action or not. DoD objects 
to a separate classification of "administrative closure" to categorize 
sites that did not require a removal or remedial action because CERCLA 
and the National Oil and Hazardous Substances Pollution Contingency 
Plan (NCP) do not distinguish the status of sites where response 
complete is determined early in the process from those where response 
complete is determined alter active remediation. Furthermore, the NCP 
requires that a "no action" alternative be evaluated throughout the 
investigative phase and selected in the Record of Decision if the 
standards arc already satisfied or there is no risk, so that 
unnecessary actions are not taken using taxpayer funds or required by 
responsible parties. 

In addition, the Department expends significant resources to conduct 
preliminary assessments, site inspections, remedial investigations, 
and feasibility studies to determine and document that it has met its 
cleanup objectives, and that there is no requirement for removal or 
remedial action. When the Department meets the cleanup objectives at a 
given site, the response action is complete, regardless of the phase 
of the CERCLA process in which the action is completed. It is 
misleading to characterize a site that achieves closure without a 
removal or remedial action differently from sites characterized as 
response complete after active remcdiation. This undermines the 
significant work and progress, including collaboration and work with 
regulators and stakeholders, that the Department is making under the 
MMRP. 

The term "response complete" is appropriate for the purposes of MMRP 
metrics and reporting because it reflects that the necessary CERCLA 
response actions for which the Department is responsible have been 
completed. "Response complete" is used by DoD to track progress, but 
is not used to communicate with the pubic regarding the protectiveness 
of the situation at a specific site. Finally, this term is accurate 
and does not misrepresent progress because it means that further 
response work, other than possibly long-term management, is not 
required. This is what DoD is required to report and is an accurate 
representation of progress by the program in the completion of 
necessary CERCLA response actions under the Defense Environmental 
Restoration Program. 

In the past, DoD has identified some sites that it believed required 
cleanup, but later determined that these sites did not require actions 
under CERCLA. For example, some sites were funded under the 
Installation Restoration Program, some sites were double counted, and 
some sites never existed and were added to the inventory in error. DoD 
stopped reporting these sites in its inventory beginning with the 
FY2009 Defense Environmental Programs Annual Report to Congress. 

[End of section] 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Anu K. Mittal, Director, (202) 512-3841 or mittala@gao.gov: 

Staff Acknowledgments: 

In addition to the individual named above, Stephen D. Secrist, 
Assistant Director; Leo G. Acosta; Elizabeth Beardsley; Mark Braza; 
Nancy Crothers; Pamela Davidson; Janida Grima; Amanda Leissoo; Laina 
Poon; and Kim Raheb made significant contributions to this report. 

[End of section] 

Footnotes: 

[1] For complete definitions, see 10 U.S.C. §§ 2710(e)(2)-(3), 
101(e)(5) (2010). 

[2] To be eligible for FUDS cleanup under the Installation Restoration 
Program and the Military Munitions Response Program, according to the 
Defense Environmental Restoration Program Management Guidance (2001) 
and FUDS program policy, a property must have been under the 
jurisdiction of DOD and owned by, leased to, or otherwise possessed by 
the United States at the time of actions leading to contamination by 
hazardous substances prior to October 17, 1986. This jurisdiction 
extends to governmental entities that are the legal predecessors of 
DOD or the components--Army, Navy and Marine Corps, Air Force, and the 
Defense Logistics Agency. 

[3] DOD also operates the much smaller Building Demolition/Debris 
Removal Program to address the demolition and removal of unsafe 
buildings or structures at facilities or sites that meet specified 
criteria. 

[4] The Department of the Navy implements the MMRP at both Navy and 
Marine Corps munitions response sites. 

[5] The Army is the executive agent for the FUDS program but has 
delegated day-to-day program management and execution responsibilities 
to the U.S. Army Corps of Engineers. 

[6] Duncan Hunter National Defense Authorization Act for Fiscal Year 
2009, Pub. L. No. 110-417, § 345, 122 Stat. 4425 (2008). 

[7] Pub. L. No. 107-107 §§ 311(a), (c) (2001); 10 U.S.C. § 2710 (2010). 

[8] American Samoa, Guam, Puerto Rico, the U.S. Virgin Islands, the 
Commonwealth of the Northern Mariana Islands, and Wake Island are all 
U.S. territories. The Marshall Islands is associated with the United 
States through a Compact of Free Association. 

[9] Stakeholders for military munitions cleanups include, but are not 
limited to, federal and state environmental protection agencies, 
federal land managers, environmental and other advocacy groups, and 
members of the general public. 

[10] Pub. L. No. 107-107 §§ 311(b)(1) (2001); 10 U.S.C. § 2710(b)(1) 
(2010). 

[11] 70 Fed. Reg. 58,016 (Oct. 5, 2005) (codified at 32 C.F.R. Pt. 179 
(2010)). 

[12] The Explosive Hazard Evaluation module provides a single DOD-wide 
approach for the evaluation of explosive hazards posed by unexploded 
ordnance, discarded military munitions or munitions constituents. 
Similarly, the Chemical Warfare Materiel Hazard Evaluation module 
provides evaluation of the chemical hazards associated with the 
physiological effects of chemical warfare material such as chemical 
munitions or toxic chemical agents. Finally, the Health Hazard 
Evaluation module provides a process for evaluating the relative risk 
to human health and the environment posed by munitions constituents. 

[13] For complete definitions, see 32 C.F.R. § 179.6(d)(4)-(5) (2010). 

[14] Pub. L. No. 96-510, as amended. A key law amending CERCLA was the 
Superfund Amendments and Reauthorization Act of 1986, Pub. L. No. 99- 
499 (1986), which provided that federal agencies "shall be subject to, 
and comply with, this Act in the same manner and to the same extent, 
both procedurally and substantively," as any private party. Id., § 
120. See 42 U.S.C. § 9620 (2010). 

[15] For complete descriptions, see 40 C.F.R. §§ 300.420, 300.430, 
300.435 (2010). 

[16] After a site reaches response complete, the military services and 
the Corps may conduct long-term management at the site. For example, 
they may monitor environmental conditions, enforce land use controls, 
and maintain any remedies to ensure continued protection as designed. 
Long-term management occurs until no further environmental restoration 
response actions are appropriate or anticipated. 

[17] John Warner National Defense Authorization Act for Fiscal Year 
2007, Pub. L. No. 109-364, § 313, 120 Stat. 2083, 2138 (2006). 

[18] For the purpose of this report, the amount of money the military 
services and the Corps obligated for MMRP activities is used to 
approximate funding received. 

[19] The term "obligations" refers to the amount of money the military 
services and the Corps legally committed for payment. 

[20] DOD, Defense Environmental Programs Annual Report to Congress 
(Fiscal Year 2008), pp.16-17. 

[21] DOD views "cleanup" as any activity that falls within the CERCLA 
process, including studies and investigation. While we acknowledge 
that these are critical steps in the CERCLA process, for purposes of 
this report we distinguish between these activities conducted during 
the earlier phases of the CERCLA process from activities undertaken 
during the remedial action phase. Specifically, we refer to activities 
undertaken during the remedial action phase as "actual cleanup" 
because activities in this phase usually involve physical, on-site 
work to remedy hazards. We refer to sites that DOD determined needed 
no remedial action as "administratively closed." 

[22] Although administratively closed sites did not undergo remedial 
actions, according to military service and Corps officials, actions 
intended to reduce risk, such as erecting fences or warning signs, may 
have been taken at some sites during the investigative phases. 

[23] Our analysis of available data indicated the military services 
and the Corps investigated 741 sites and found them to be free of 
hazards. However, Army and Corps officials believe there were likely 
additional response complete sites where no hazard was present, but 
they were not able to provide us with a specific number. 

[24] The services and the Corps may have cleaned up some munitions 
response sites under the IRP before the MMRP was established as a 
separate program in 2001. Operational ranges are excluded from the 
MMRP. A senior DOD official explained that cleaning up munitions-- 
beyond normal clearance operations--from past military actions while 
new munitions are being deposited by current activities would waste 
resources. 

[25] GAO, Environmental Contamination: Cleanup Actions at Formerly 
Used Defense Sites, [hyperlink, 
http://www.gao.gov/products/GAO-01-557] (Washington, D.C.: July 31, 
2001). 

[26] To reach response complete, any operations required for the 
remedial action must also be completed. For example, a groundwater 
pump-and-treat system would need to operate for some period of time 
before the cleanup objective could be accomplished and the site could 
be considered response complete. 

[27] DOD's fiscal year 2008 annual report is the most recent report as 
of April 2010. 

[28] Risk assessment code scores were used to rank sites by relative 
risk prior to 2007 when the military services and the Corps began 
reporting scores based on the Munitions Response Site Prioritization 
Protocol. This site would not have been scored using the 
prioritization protocol because it was cleaned up in 2000. 

[29] This site would not have been scored using the Munitions Response 
Site Prioritization Protocol because cleanup was completed in 2006. 

[30] Thirty-eight percent represents the number of sites that had a 
site inspection completion date in DOD's Knowledge-Based Corporate 
Reporting System database. 

[31] The military services and the Corps reported that 1,341 munitions 
response sites no longer required scoring using the Munitions Response 
Site Prioritization Protocol, primarily because they categorized the 
sites as response complete. 

[32] DOD's regulation establishing the Munitions Response Site 
Prioritization Protocol provides for subsequent sequencing to consider 
other factors and provides a nonexclusive list of example factors, 
such as mission needs and stakeholder input. The military services and 
the Corps are to use their installation-specific management action 
plans--plans that describe an integrated, coordinated approach for 
conducting all required environmental restoration activities, 
including schedules and cost estimates--as a vehicle for sequencing. 
The regulation does not, however, establish a methodology for how such 
other factors are to be considered. 

[33] After a final remedial action has been constructed and is 
operating as planned, DOD describes the site status as remedy in 
place. While operation of the remedy is ongoing but cleanup objectives 
have not yet been met, the site cannot be considered response 
complete. DOD categorizes sites as response complete at any point in 
the process when it determines no further response is appropriate, 
including sites without a remedy in place. According to DOD, such 
determinations are made in conjunction with regulators and 
stakeholders. 

[34] The act requires the reporting of such feasible interim goals in 
association with the remedy in place or response complete performance 
goals for munitions response sites at active and BRAC 2005 
installations, and FUDS. 

[35] We measured project duration, which was calculated using both 
month and year information, as the length of time between the earliest 
phase start date and the latest phase end date. For the purposes of 
our analysis, if the most recent phase was still in process, we used 
September 2008 as the end date because that was the latest date for 
which we had Knowledge-Based Corporate Reporting System data. 

[36] The military services and the Corps report funds obligated for 
cleanup activities at munitions response sites in a fiscal year to DOD. 

[37] We did not conduct a similar analysis on the extent to which DOD 
had complete data on cost estimates. 

[38] The Department of the Navy (Navy) implements the MMRP at both 
Navy and Marine Corps munitions response sites. 

[39] After the military services or the Corps completes its response 
to potential military munitions hazards, and when no further response 
action is appropriate, DOD describes the site's status as "response 
complete." 

[40] If the latest phase did not have an end date, we used September 
2008 as the end date because we assumed that the site was still in 
that phase at the end of fiscal year 2008, the year for which we had 
Knowledge-Based Corporate Reporting System data. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: