This is the accessible text file for GAO report number GAO-07-304 
entitled 'Military Base Closures: Projected Savings from Fleet 
Readiness Centers Likely Overstated and Actions Needed to Track Actual 
Savings and Overcome Certain Challenges' which was released on June 29, 
2007.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to Congressional Committees:

United States Government Accountability Office:

GAO:

June 2007:

Military Base Closures:

Projected Savings from Fleet Readiness Centers Likely Overstated and 
Actions Needed to Track Actual Savings and Overcome Certain Challenges:

Military Base Closures:

GAO-07-304:

GAO Highlights:

Highlights of GAO-07-304, a report to congressional committees.

Why GAO Did This Study:

The 2005 Base Realignment and Closure (BRAC) recommendation to 
establish fleet readiness centers was expected to yield more savings 
than any other of the 2005 BRAC recommendations. To achieve these 
savings the Navy plans to integrate civilian depot personnel to 
complete some repairs at intermediate maintenance departments to reduce 
aviation maintenance costs. This report, prepared under the Comptroller 
General authority to conduct evaluations on his own initiative, is one 
in a series of reports related to the 2005 BRAC recommendations. GAO’s 
objectives were to (1) analyze the reasons for changes in costs and 
savings estimates since the recommendation was approved, and (2) 
identify challenges in implementing this BRAC recommendation. GAO 
analyzed Navy and BRAC Commission costs and savings estimates and 
interviewed officials at the Naval Air Systems Command and at three 
fleet readiness centers.

What GAO Found:

The Navy has increased onetime costs, decreased onetime savings and 
increased annual recurring savings expected from the fleet readiness 
centers recommendation, but GAO believes the savings are likely 
overstated. In preparing a detailed business plan for implementing the 
recommendation, the Navy increased onetime costs by $31 million or 96 
percent because of costs associated with relocating employees and 
inflation. The Navy also decreased expected onetime savings from 
reduced inventory levels by $594 million or 92 percent because Navy 
officials believed earlier estimates were too optimistic. GAO’s 
analysis of inventory levels for a sample of aviation items indicates 
that the majority of the revised savings estimate will not occur during 
the 6-year BRAC implementation period and the amount of such savings 
are uncertain at this time. GAO believes the annual recurring savings 
are overstated by about $53 million or 15 percent because the Navy’s 
estimate includes $28 million in savings from eliminating military 
personnel, which may be assigned elsewhere rather than taken out of the 
force structure, and $25 million in onetime savings that was 
erroneously reported as recurring savings. While projected savings 
would remain substantial, they are still subject to some uncertainties 
and further efforts will be required to assess actual savings as this 
recommendation is implemented. The Navy faces challenges in ensuring 
projected savings are realized and faces some workforce challenges in 
implementing the recommendation. Since the Navy has already included 
projected BRAC savings in its budget for fiscal years 2007 through 
2011, it will be important for the Navy to monitor the extent to which 
these savings are actually achieved to prevent adverse affects on naval 
aviation readiness or the need for additional funding. The Navy also 
faces workforce challenges, such as identifying and moving about 150 
depot artisans with the right skills to various intermediate 
maintenance departments and integrating a primarily civilian depot 
workforce with the military intermediate department workforce. This 
mixing of diverse cultures could pose some challenges in implementation 
but should help develop a better trained and more productive workforce. 
The Navy will need sustained leadership to successfully establish the 
fleet readiness centers.

What GAO Recommends:

GAO is making recommendations for the Navy to adjust its business plan 
to include only savings directly related to implementing this BRAC 
recommendation and to monitor actual savings realized as the 
recommendation is implemented. In commenting on a draft of this report, 
DOD concurred with our recommendations.

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-304]:

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Brian Lepore at (202) 512-
4523 or leporeb@gao.gov.

[End of section]

Contents:

Letter:

Results In Brief:

Background:

Estimated Savings Likely Overstated:

Challenges to Realizing Savings from Establishing Fleet Readiness 
Centers:

Conclusions:

Recommendations for Executive Action:

Agency Comments and Our Evaluation:

Appendix I: Scope and Methodology:

Appendix II: Fleet Readiness Centers Recommendation:

Appendix III: Comments from the Department of Defense:

Appendix IV: GAO Contacts and Staff Acknowledgments:

Tables:

Table 1: Comparison of Projected Costs and Savings Estimates:

Table 2: Time Frames for Reducing Aviation Component Inventory 
Requirements to Yield Savings:

Figures:

Figure 1: Planned Fleet Readiness Centers (FRC) and Affiliated Sites:

Figure 2: Aviation Components Repair Cycle:

United States Government Accountability Office:

Washington, DC 20548:

June 29, 2007:

Congressional Committees:

On May 13, 2005, the Department of Defense (DOD) made public its 
recommendations to realign and close bases. DOD projected these actions 
would yield nearly $50 billion in net savings over a 20-year period. 
The Base Realignment and Closure (BRAC) Commission[Footnote 1] 
evaluated DOD's recommendations and recommended reducing the estimated 
20-year net savings by about $12 billion over a 20-year period. The 
BRAC Commission recommendations were accepted by the President and the 
Congress, and became effective on November 9, 2005. The recommendation 
to establish six fleet readiness centers reengineers naval air 
maintenance, which blends some civilian depot employees with military 
personnel to complete repairs at intermediate maintenance departments. 
The intent behind this action was to avoid some redundant maintenance 
procedures and supply overhead charges and reduce aviation maintenance 
costs. DOD initially estimated this recommendation would yield about 
$4.7 billion in net savings over 20 years including onetime 
savings[Footnote 2] of about $648 million.

In July 2005,[Footnote 3] we reported some uncertainty regarding the 
magnitude of the expected savings from the recommendation to establish 
fleet readiness centers because the estimates were based on assumptions 
that had undergone limited testing, and were also dependent on 
transformation of the Navy supply system. In addition, after performing 
its own analysis, the BRAC Commission believed the Navy overestimated 
the savings that may be achieved from business process reengineering 
efforts. The BRAC Commission approved the recommendation to establish 
fleet readiness centers with an estimated 20-year net savings of $3.7 
billion. Of the large number of 2005 BRAC recommendations, this 
recommendation is projected to produce the most dollar savings, based 
on DOD's total BRAC savings projections.

Once the recommendation became effective, the Navy became responsible 
for executing the recommendation to establish fleet readiness centers. 
The Office of the Secretary of Defense required the Navy to submit a 
detailed business plan for implementing the recommendation, to update 
estimated costs and savings, and to provide a schedule for implementing 
the recommendation. The fleet readiness center plan was approved by the 
Office of the Secretary of Defense on August 1, 2006.

This report is one in a series of reports that detail the progress DOD 
has made in implementing the base closures and realignments included in 
the 2005 BRAC round. We performed our work on the basis of the 
authority of the Comptroller General to initiate reviews[Footnote 4] 
and are reporting the results to you in order to facilitate your 
oversight of DOD's infrastructure and BRAC initiative. In this report, 
we address the Navy's efforts to implement the BRAC recommendation to 
establish fleet readiness centers. Our specific objectives were to (1) 
analyze the reasons for changes to the costs and savings estimates 
since the recommendation to establish fleet readiness centers was 
amended and approved as part of the 2005 BRAC round; and (2) identify 
the challenges the Navy faces in successfully implementing this BRAC 
recommendation.

To accomplish these objectives, we performed our work at the Naval Air 
Systems Command headquarters, Patuxent River, Maryland; the aviation 
intermediate maintenance departments at North Island, San Diego, 
California; Mayport, Florida; and Whidbey Island, Oak Harbor, 
Washington; and the naval aviation depots at North Island, San Diego, 
California, and Jacksonville, Florida. We analyzed the changes to the 
costs and savings estimates between the BRAC Commission's amended and 
approved recommendation and the Navy's approved business plan and 
interviewed key Navy officials to identify the reasons for changes and 
the challenges they face in implementing the recommendation. To assess 
the reliability of data used to generate costs and savings estimates, 
we reviewed Navy regulations and instructions for reporting aviation 
maintenance data and interviewed officials at the Navy Air Systems 
Command, Naval Aviation Depots, and Commander, Naval Air Forces, about 
the data and assumptions underlying the estimates. Based on these 
discussions and observations and review of the Navy's calculations, we 
believe the DOD data are sufficiently reliable for the purposes of this 
report. We conducted our work between February and December 2006 in 
accordance with generally accepted government auditing standards. 
Further details on the scope and methodology are described in appendix 
I.

Results in Brief:

In comparison to the BRAC Commission estimates, the Navy has increased 
onetime costs, decreased one-time savings, and increased annual 
recurring savings expected from the fleet readiness centers 
recommendation.[Footnote 5] While the Navy has started to implement the 
recommendation and achieve savings, we believe the amount of onetime 
savings are uncertain at this time and projected net annual recurring 
savings are overstated. The savings consist primarily of onetime 
savings from projected decreases in the inventory of aircraft component 
and replacement parts, and annual recurring savings[Footnote 6] from 
reduced depot labor and overhead charges and personnel reductions. In 
preparing its business plan, the Navy reduced expected one-time savings 
from lower inventory levels by 92 percent (from $648 million to $54 
million) because Navy officials believed their initial estimates were 
too optimistic. Even though the Navy reduced its estimated onetime 
savings, our analysis of inventory levels for a sample of aviation 
items concluded that the majority of the revised savings estimate will 
not occur during the 6-year BRAC implementation period, and the amount 
of such savings over time are uncertain. While the Navy projects annual 
recurring savings of about $311 million, we believe they are likely 
overstated by $53 million. The Navy's estimate includes $28 million in 
savings from eliminating military personnel, which may be assigned 
elsewhere rather than taken out of the force structure, and $25 million 
in onetime savings that were erroneously reported as recurring savings. 
While projected savings remain substantial, they are still subject to 
some uncertainties and additional efforts will be required to assess 
actual savings over time as this recommendation is implemented.

The Navy faces challenges in ensuring projected savings from 
implementing its fleet readiness center recommendation are realized 
even as it also faces some workforce challenges in implementing the 
recommendation. Since the Navy has already included projected BRAC 
savings in its budget plans for fiscal years 2007 through 2011, the 
Navy will need to monitor the extent to which these savings are 
achieved. Therefore, if savings are not realized, the Navy may have to 
take funds from other Navy programs or request additional funds to 
offset unrealized savings or be unable to repair aviation components in 
a timely manner which could affect readiness. The Navy has developed an 
interim method for tracking aviation maintenance repair costs and 
calculating the BRAC savings from establishing fleet readiness centers, 
but follow through will be important to validate savings over time. In 
addition, the Navy faces workforce challenges, such as potentially 
moving over 150 depot artisans with the right skills to various 
intermediate maintenance departments and integrating a primarily 
civilian depot workforce with the military intermediate department 
workforce. This mixing of diverse cultures could pose some challenges 
in implementation but could result in a better-trained and more- 
productive workforce. The Navy faces other challenges, such as the need 
for sustained leadership and communication to successfully establish 
the fleet readiness centers. Furthermore, the Navy needs to ensure that 
depot maintenance performed at intermediate departments is accurately 
recorded and reported to satisfy congressional reporting requirements. 
The Navy has recognized many of these challenges and outlined steps to 
be taken to address them.

We are making recommendations to the Secretary of Defense to direct the 
Secretary of the Navy to update the business plan to include only 
savings that are directly related to implementing the BRAC 
recommendation and monitor and update savings as implementation 
progresses. In commenting on a draft of this report, DOD concurred with 
our recommendations. DOD noted that it considers military personnel 
reductions attributable to a BRAC recommendation as real savings. It 
noted that while the department may not reduce end strength, these 
reductions allow the department to reapply these military personnel to 
support new capabilities. We believe the department counting of savings 
from eliminating military personnel positions, without corresponding 
reductions in end strength, creates a false sense of savings available 
for other purposes because they do not represent dollar savings that 
can be readily reallocated outside the military personnel accounts. We 
do agree that assigning these positions to other areas may enhance 
capabilities. DOD's written comments are reprinted in appendix III. DOD 
also provided technical comments, which we have incorporated into this 
report as appropriate.

Background:

The Navy has three levels of naval aviation maintenance-- 
organizational, intermediate, and depot--to support naval 
aviation.[Footnote 7] Organizational maintenance is performed by 
sailors on the flight line and generally items are repaired on the 
aircraft, whether at sea or at a naval station. The intermediate 
maintenance activity is generally performed by sailors at the Navy's 
aviation intermediate maintenance departments, which focus on item 
repairs in close proximity to the flight line but off-aircraft. Depot 
maintenance activities, generally performed by civilian aviation depot 
artisans, provide a comprehensive combination of major repair, 
overhaul, and modifications to weapons systems and components, 
assemblies, and subassemblies in off-flight-line maintenance. The 
current aviation maintenance process generally flows as follows: when 
the organizational maintenance crews cannot fix a broken aircraft 
component or item, it is sent to the intermediate department; if the 
intermediate maintenance department cannot repair an item, it declares 
that the item is beyond its capability of maintenance. The broken item 
is then turned over to the supply system in exchange for a replacement 
part; and the broken item is shipped to the depot for further repairs 
or overhaul.

The recommendation to establish fleet readiness centers affects the 
intermediate department and depot maintenance levels, but not the 
organizational level. It involves moving about 150 artisans from the 
depots to the intermediate departments to perform aviation repairs. In 
addition, six fleet readiness centers will be established to transform 
naval aviation maintenance at the intermediate departments and depots 
as seen in figure 1.

Figure 1: Planned Fleet Readiness Centers (FRC) and Affiliated Sites:

[See PDF for image]

Source: GAO analysis of U.S. Navy data.

[End of figure]: 

According to this BRAC recommendation, relocating depot artisans to 
intermediate departments is expected to reduce the number of items that 
are declared to be beyond the capability of maintenance at the 
intermediate departments and therefore, will not require some items to 
be sent to the depot for repair. As a result, repeated and duplicated 
maintenance procedures are projected to be avoided and turnaround times 
projected to be reduced. More specifically, prior to implementing this 
recommendation, when an item is being repaired by military personnel at 
the intermediate department, they perform diagnostics, disassemble the 
item, and attempt to repair it. When they determine it cannot be 
repaired and declare that it is beyond their capability of maintenance, 
the item is reassembled, repackaged, and shipped to the depot for 
repair. Upon arrival at the depot, the artisans must perform similar 
diagnostics, and repeat the processes of disassembly and repair that 
have already been performed at the intermediate department. According 
to Navy officials, after fleet readiness centers are established, the 
depot artisans positioned at the intermediate departments are expected 
to be able to complete more repairs there, which will reduce or 
eliminate some packaging, shipping, and administrative costs as seen in 
figure 2.

Figure 2: Aviation Components Repair Cycle:

[See PDF for image]

Source: GAO analysis. 

[End of figure]: 

At the time DOD originally submitted its recommendations to the BRAC 
Commission, it estimated this recommendation would yield $341 million 
in annual recurring savings, or $4.7 billion net savings over 20 years. 
The preponderance of the annual recurring savings was expected to come 
from fewer items being sent to the depots for repair, thus reducing per 
item maintenance costs. DOD also expected to achieve significant 
onetime savings by reducing existing inventory levels of aircraft 
component parts. In July 2005, we reported that while there is 
potential for significant savings, there is some uncertainty over the 
full magnitude of savings.[Footnote 8] Our report noted that the Navy 
used assumptions that had undergone limited testing, and the full 
savings realization depends upon the transformation of the Navy's 
supply system to achieve organizational efficiencies. Moreover, we 
pointed out that realizing the full extent of the savings would depend 
on actual implementation of the recommended actions.

The BRAC Commission also believed DOD's overall estimated savings were 
overstated because savings were derived from overhead efficiencies that 
had not been validated. The commission projected annual recurring 
savings of about $248 million a year or $3.7 billion[Footnote 9] net 
present value savings over a 20-year period--about $1 billion less than 
the DOD's estimate. Also, the commission reduced the estimated savings 
because it eliminated the proposed realignment of workload from the 
Naval Support Activity in Crane, Indiana, to Whidbey Island, 
Washington, since the Navy planned to phase out the aircraft associated 
with the proposed workload transfer in 10 to 15 years regardless of 
BRAC. In addition, the commission found errors in DOD's estimation of 
construction costs and the savings projections based on eliminated 
personnel.

The President and the Congress accepted the BRAC Commission 
recommendations, which became effective on November 9, 2005. Once the 
recommendations became effective, the Office of the Secretary of 
Defense designated one of the military services or defense agencies as 
the business manager responsible for implementing each recommendation. 
The Navy is responsible for establishing the six fleet readiness 
centers. The Office of the Secretary of Defense also required the Navy 
to submit a detailed business plan to update estimated costs and 
savings and identify a schedule for implementing the recommendation. 
The Navy's detailed business plan was approved to implement the 
recommendation to establish fleet readiness centers on August 1, 2006. 
However, the Office of the Secretary of Defense has requested that the 
Navy resubmit its plan to accurately reflect the savings realized based 
on the Navy's current implementation of this BRAC recommendation. The 
Navy's plan was still in-process as of March 15, 2007.

In addition, the Navy must comply with Title 10, Section 2466 of the 
United States Code (U.S.C.), which provides that not more than 50 
percent of the funds made available in a fiscal year to the Navy for 
depot maintenance and repair workload may be used to pay for work 
performed by private contractors. The statute also requires the 
Secretary of Defense to submit a report to Congress (known as the "50/ 
50" report) by April 1 annually, on public-private depot maintenance 
funding distributions. The 50/50 report notes the percentage of depot 
maintenance funding between the public and private sectors during the 
preceding fiscal year, the projected distribution for the current 
fiscal year, and the ensuing fiscal year.

Estimated Savings Likely Overstated:

In comparing the Navy's business plan with the BRAC Commission 
estimates of costs and savings, the Navy's business plans shows an 
increase in one-time costs, a decrease in one-time savings, and an 
increase in annual recurring savings as seen in table 1 below.

Table 1: Comparison of Projected Costs and Savings Estimates:

Dollars in millions: Category: Onetime costs; BRAC Commission 
approved[A]: $34; Navy business plan[B]: $65; Difference: Amount: $31; 
Difference: Percent: 96.

Dollars in millions: Category: Onetime savings; BRAC Commission 
approved[A]: 648; Navy business plan[B]: 54; Difference: Amount: (594); 
Difference: Percent: (92).

Dollars in millions: Category: Annual recurring savings; BRAC 
Commission approved[A]: 250; Navy business plan[B]: 311; Difference: 
Amount: 61; Difference: Percent: 25.

Source: DOD data.

Notes: DOD did not accept the final BRAC Commission estimate because it 
was based on actual versus authorized positions.

[A] In constant fiscal year 2005 dollars.

[B] In then year or current dollars.

[End of table]: 

While the Navy has started to implement the recommendation and achieve 
savings, we believe the latest savings estimates are still overstated 
and uncertain. The majority of the savings consist of onetime savings 
from projected decreases in the inventory of aircraft components and 
replacement parts, and annual recurring savings from reduced depot 
labor and overhead charges and reductions in military personnel. While 
savings from lower inventory levels may be possible, our analysis of a 
judgmental sample of items targeted for inventory reduction concluded 
that the majority of these savings would not occur during the 6-year 
implementation period of this BRAC recommendation.[Footnote 10] 
Further, we believe the Navy's estimated annual recurring savings 
remain overstated because they included savings from eliminating 
military personnel that are not expected to result in a reduction to 
its overall service force structure and included onetime savings 
erroneously reported as recurring savings.

Onetime Costs Increased:

The Navy's business plan shows onetime costs increased by 96 percent 
(from $34 million to $65 million) as compared to the BRAC Commission's 
estimates, which was primarily due to increased costs associated with 
relocating depot employees to the intermediate level, other 
miscellaneous program management actions, and inflation.[Footnote 11] 
For example, Navy officials stated that they need to add more equipment 
or specialized workbenches to support depot artisans relocated to the 
intermediate departments. The program management costs are primarily 
for information technology upgrades. For example, Navy officials stated 
the need for an interim logistics tracking and accounting mechanism, 
using its current Naval Aviation Logistics Command/Management 
Information System to track depot maintenance repairs at the 
intermediate departments. While onetime costs have nearly doubled, they 
have limited effect on the long-term recurring savings expected from 
establishing fleet readiness centers once those savings offset 
implementation costs.

Onetime Savings Have Been Reduced, but Uncertainty Exists about When 
They Will be Achieved:

While the Navy has reduced the projected onetime savings from lower 
levels of inventory, our analysis of a sample of aviation inventory 
items targeted for reduction concludes that the majority of these 
savings would not occur during the 6-year implementation period, and 
the amount of such savings over time is uncertain. In preparing the 
business plan, the Navy reduced its onetime savings by 92 percent (from 
$648 million to $54 million) mostly by lowering the estimated savings 
from reducing inventory of aircraft components and replacement parts. 
According to Navy officials, the initial inventory savings estimate was 
overly optimistic. In addition, the lower estimate was based on the 
BRAC Commission's determination that the Navy's projected savings were 
overstated because the commission found errors in the Navy's savings 
estimates. Additionally, our July 2005 report stated that the magnitude 
of the expected savings for the fleet readiness centers is in part 
dependent upon transformation of the Navy's supply system, such as 
eliminating unneeded management structures and duplicate layers of 
inventory in the supply system.[Footnote 12]

DOD's original submission to the BRAC Commission assumed that the 
dollar value of the inventory of aircraft components and replacement 
parts could be reduced by 15 percent. According to Navy officials, the 
15 percent savings factor was based on the professional judgment of the 
Industrial Joint Cross Service Group members. They expected savings 
because fewer items would need to be kept in the shore-based aviation 
consolidated inventory because items would be getting repaired more 
quickly and returned to the inventory faster.[Footnote 13] However, the 
Navy officials stated that they did not have time during the BRAC 
process to discuss the estimated inventory and supply savings with 
officials from the Navy Supply Command to validate the estimate. Navy 
officials stated that they estimated the onetime savings from inventory 
reductions ($648 million) by multiplying the 15 percent factor times 
the total dollar value of the inventory and supply of aircraft 
components and replacement parts in fiscal year 2003.[Footnote 14]

In developing the business plan, the Navy reduced the inventory and 
supply savings factor from 15 percent to less than 4 percent based on 
discussions with Naval Supply Command officials and a better 
understanding of how other BRAC recommendations affected DOD's and 
Navy's supply system. Specifically, two other recommendations involved 
significant savings projections from reengineering DOD's inventory and 
supply system and the reconfiguration of supply, storage, and 
distribution management. After considering how these other BRAC 
recommendations could affect the Navy's projected inventory and supply 
savings estimates, Navy officials concluded there would be a greater 
potential overlap of savings with the fleet readiness center BRAC 
recommendation. However, the Navy could not provide us documentation to 
support the lower inventory savings estimate.

While savings from lower inventory may be possible, our analysis of a 
judgmental sample of 99 items targeted for inventory reduction 
concludes that the majority of these savings will not occur during the 
6-year implementation period of this BRAC recommendation as the Navy 
originally projected. Our analysis shows that for 83 percent of the 
items sampled, the Navy will take more than the implementation period 
to achieve lower inventory levels because the majority of replacement 
items on-hand is sufficient to provide many years worth of supply, and 
the rate of replacement for that inventory will not be a factor 
contributing to savings, as seen in table 2.

Table 2: Time Frames for Reducing Aviation Component Inventory 
Requirements to Yield Savings:

Fiscal year: 2006-2011; Number of items: 17; Percent: 17.

Fiscal year: 2012-2020; Number of items: 22; Percent: 27.

Fiscal year: Beyond 2021; Number of items: 60; Percent: 56.

Total; Number of items: 99; Percent: 100.

Source: GAO analysis.

[End of table]: 

Since the Navy has not yet identified all of the inventory items that 
could be affected by the fleet readiness centers recommendation, we 
could not estimate the effect of delayed inventory savings reductions 
on the Navy's estimated onetime savings or the total amount of savings 
likely to be realized.

Annual Recurring Savings Likely Remain Overstated:

The Navy increased the annual recurring savings estimate by 25 percent 
(from about $250 million to $311 million) primarily by increasing 
projected savings from military personnel eliminations and inflation. 
These increases were offset to some degree by decreases in projected 
savings from maintaining facilities. However, we believe the Navy's 
revised annual recurring savings estimates are still overstated by 
approximately $53 million because they include $28 million in savings 
from eliminating military personnel, which may be assigned elsewhere 
rather than taken out of the force structure, and $25 million that 
should have been reported as onetime, and not recurring, savings. In 
addition, we estimate that projected annual recurring savings increased 
by approximately $42 million due to inflation.[Footnote 15]

The BRAC Commission projected annual recurring savings of about $10 
million from eliminating about 120 military positions, while the Navy 
business plan includes about $28 million in annual recurring savings 
from eliminating about 290 military positions as originally planned. 
Regardless of the number of military personnel affected by the 
recommendations, as we reported in July 2005, the projected net annual 
recurring savings associated with eliminating jobs currently held by 
military personnel could create a false sense of savings available for 
other purposes because they do not represent dollar savings that can be 
readily reallocated outside the military personnel accounts. Rather 
than reduce end strength, these positions are expected to be reassigned 
to other areas, which may enhance capabilities but also limit dollar 
savings available for other uses.[Footnote 16]

The Navy incorrectly reported onetime savings as annual recurring 
savings in its business plan. Navy officials stated that $25 million 
onetime savings were incorrectly categorized as annual recurring 
savings in its business plan. These onetime savings included reductions 
in aviation depot level repair charges, decreased spare parts 
inventory, and reduced materials to repair aviation components. As a 
result of the fleet readiness center implementation to date, Navy has 
begun to reduce its current spare parts inventory, which translates 
into less physical space needed to store the inventory and fewer 
sailors needed to manage it. However, GAO believes that the Navy's 
business plan should correctly report the $25 million as onetime 
savings and not annual recurring savings.

Increases in the Navy's annual recurring savings estimates were offset 
to some degree by decreases in projected savings expected from reduced 
facility costs. According to the Navy officials, the projected 
reductions in personnel should result in reducing floor space for 
numerous work shops, but they will not free up enough space to allow 
the Navy to vacate any buildings at this time. Since no buildings will 
be vacated, the Navy reduced the annual recurring savings expected from 
facilities maintenance by about $3 million. Navy officials indicated 
that as fleet readiness center implementation progresses, there may be 
opportunities to combine similar work shops at some sites, which may 
result in entire buildings being vacated, and produce savings in the 
funding for facilities maintenance. If this occurs, a Navy official 
noted the business plan would be updated to reflect these savings.

In addition, Navy's implementation efforts are beginning to show 
savings. The Navy reported savings of $19 million from October 2006 to 
April 2007 at the 6 fleet readiness centers. These savings are from 
repairing selected aviation items at the fleet readiness centers 
instead of sending them to the depots for repair.

Challenges to Realizing Savings from Establishing Fleet Readiness 
Centers:

The Navy faces challenges in ensuring that projected savings are 
realized from implementing the fleet readiness center recommendation in 
addition to some workforce challenges in implementing the 
recommendation. Since the Navy has already included projected BRAC 
savings in its budget for fiscal years 2007 through 2011, the Navy will 
need to monitor the extent to which these savings are achieved. If 
savings are not realized, the Navy may need to get funds from another 
Navy program or request additional funds to offset unrealized savings 
or be unable to repair aviation components in a timely manner, which 
could impact readiness. Accordingly, the Navy has developed an interim 
method for tracking aviation maintenance repair costs and calculating 
the BRAC savings from establishing fleet readiness centers, which 
addresses our prior recommendation to DOD to update and track savings. 
In addition, the Navy acknowledges that other challenges remain, such 
as identifying and moving necessary depot artisans with the right 
skills to various intermediate maintenance departments and integrating 
a primarily civilian depot workforce with the military intermediate 
department workforce. Navy officials recognize that this mixing of 
workforces could create some cultural tension in the workforce, but 
this blending may facilitate the development of a better-trained and 
more-productive workforce. The Navy has recognized many of these 
challenges and outlined steps to be taken to address them. Our prior 
work has shown that strong and sustained executive leadership is needed 
if reform efforts are to succeed.[Footnote 17] Furthermore, our prior 
work has raised questions about the reasonableness and consistency of 
depot maintenance workload data submitted to the Congress.[Footnote 18] 
Therefore, the Navy will need to ensure that depot maintenance work 
performed at intermediate departments is accurately reported to satisfy 
congressional reporting requirements.

Planned Short-Term Monitoring Will Need to Be Extended:

The Navy has developed an interim method for tracking aviation 
maintenance repair costs and calculating the BRAC savings from 
establishing fleet readiness centers, but it will be important to 
ensure this effort continues over time to validate savings. Navy 
officials noted that if the expected savings are not realized, this 
decrease in savings could adversely affect the Navy's ability to 
perform its mission within budgeted funds. Furthermore, inadequate 
implementation could affect readiness, and the Navy may need to request 
additional funds to offset unrealized savings. Our previous work has 
raised concerns with prior DOD efforts to reduce related operating 
budgets in advance of actual savings being realized.[Footnote 19]

The Navy reduced its aviation maintenance budget for fiscal years 2007 
through 2011 by the estimated BRAC savings it projects will result from 
establishing fleet readiness centers. Navy officials recognized its 
challenges in achieving these estimated savings as well as the 
importance of monitoring and tracking the actual and realized BRAC 
savings. The Navy has developed an interim method for calculating the 
BRAC savings realized at the newly established fleet readiness centers 
during the implementation time frame. This interim method utilizes 
information from two separate logistic systems, one at the depots and 
the other at the intermediate departments, to allow Navy officials to 
evaluate each fleet readiness center's performance in meeting its BRAC 
savings targets. However, this short-term solution for tracking BRAC 
savings is not designed to go beyond 2011 or address long-standing 
business and financial system challenges.

Workforce Challenges:

Identifying Maintenance Items and Critical Skills:

To achieve desired savings, the Navy has begun identifying which items 
currently repaired at the depots could be repaired at the former 
intermediate departments (now fleet readiness centers/sites). The Navy 
originally calculated about 38,000 items that were beyond the 
capability of maintenance of the intermediate departments, which could 
be repaired by potentially moving about 150 depot artisans to the 
intermediate departments. As of November 2006, the Navy has identified 
about 1,800 items that can be repaired at intermediate departments. 
Twenty-five depot artisans have already begun to repair 127 of these 
items at the intermediate departments. The number of items ultimately 
selected will dictate the number of personnel needed and savings to be 
realized. Our prior work on strategic workforce planning highlighted 
the need for organizations to identify the right number of staff with 
the right skills and competencies in the right locations to fulfill 
their missions and goals.[Footnote 20] Based on the items identified 
for repair, the Navy will determine the skill sets required for depot 
artisans to perform repairs at the intermediate departments. 
Consequently, the Navy will request depot artisan volunteers to 
relocate to the intermediate departments. If artisans do not volunteer 
to relocate to the intermediate departments or if artisans with the 
necessary skill sets have retired or stopped working through normal 
attrition, the Navy plans to hire or contract for the necessary skill 
sets. Navy officials stated that intermediate departments are located 
in heavily industrialized areas that may enable them to hire people 
with the necessary skill sets.

Introducing Civilian Depot Artisans at Intermediate Departments:

As the Navy establishes the fleet readiness centers, the Navy will 
relocate some civilian depot artisans to work alongside military 
personnel at the intermediate maintenance departments, which has the 
potential to create cultural challenges within the workforce. Navy 
officials recognized that this mixing of civilian and military 
workforces with their differences in working environments could create 
some cultural tension, but this blending may facilitate the development 
of a better-trained and more-productive workforce. The Navy's civilian 
depot artisans work under a collective bargaining agreement which 
specifies employee work hours, maximum allowable excess work hours, and 
the number and duration of an artisan's guaranteed breaks. At the 
intermediate maintenance departments, the military personnel are 
required to work according to mission needs, which may exceed normal 
work hours and disallow breaks, if necessary. Navy officials stated 
that they do not foresee any labor problems when the Navy establishes 
fleet readiness centers. Our prior work recognizes that certain 
organizational and environmental differences cause stresses that may 
affect an agency's ability to attain its strategic goals. Certain key 
human capital practices can be employed to overcome such differences, 
such as developing policies and procedures to allow for the flexible 
use of the workforce to ensure consistency, equity, transparency, and 
address employee concerns.[Footnote 21]

While this mixing of diverse cultures could pose some challenges in 
implementation, it could also help in developing a better-trained and 
more-productive workforce if properly managed. As implementation of 
this BRAC recommendation begins, the Navy will temporarily assign 
civilian artisans to predominately military intermediate maintenance 
departments to perform repairs. As fleet readiness centers are 
established, the temporary assignments will become permanent. As the 
artisans and military personnel become accustomed to working side-by- 
side, the Navy may combine similar shops that have existed separately 
at depots and intermediate maintenance departments to assure efficient 
use of personnel, equipment, and facilities. This effort to determine 
if shops can be combined will begin over the next several years. 
According to Navy officials, when depot artisans begin to work with 
military personnel, the artisans will provide on-the-job training as a 
means to increase the military personnel ability to perform aviation 
repairs and improve aviation maintenance efficiency. However, Navy 
officials stated that some workforce members are concerned about the 
long-term effect of these changes. For example, it is unclear whether 
shops that are comprised of military and civilian workforce members 
will be managed by military or civilian leadership. In addition, these 
combined shops may have an effect on the career paths of aviation 
maintenance officers and civilian managers.

Navy's Communication Strategy to Promote Goals of Fleet Readiness 
Centers:

Communicating the mission and goals of the fleet readiness centers is 
critical to implementing this BRAC recommendation. To address this 
challenge, the Navy has focused on developing a communication plan to 
mitigate the risk of inaccurate or inconsistent information and address 
workforce fears. The communication plan goal is to maximize stakeholder 
ownership and involvement with the implementation of the fleet 
readiness centers to minimize uncertainty and anxiety inherent with 
organizational change. In our prior report,[Footnote 22] we stated that 
strategic workforce planning is most effective when an agency's goals, 
approach, and results are communicated early, clearly, and often. Navy 
officials said that early communication is critical to mitigate rumors 
and speculation about potential workforce changes at the intermediate 
departments and depot maintenance facilities. Accordingly, the Navy has 
developed a detailed communication plan to describe the challenges 
associated with implementing this BRAC recommendation. This plan 
details the approach that will be used to establish fleet readiness 
centers, the goals they are expected to achieve, and the results that 
are desired from introducing depot artisans into the intermediate 
workforce. The Navy expects to evaluate the success of the 
communication plan using several methods including monthly key 
stakeholder feedback reports; postbriefing and post-town hall audience 
surveys; circulation or number of memos and number of people who 
actually saw the message; and other surveys to determine changes in 
awareness (knowledge), attitudes (opinions) or respondent's reports of 
past or anticipated/intended actions (behaviors).

As part of the Navy's communications strategy, the Commander, Aviation 
Depots, Naval Air Systems Command has traveled in excess of 200 days 
during the past year in order to communicate the fleet readiness center 
concept to the entire aviation maintenance workforce. He stated he will 
meet or exceed that travel schedule during the implementation phase to 
ensure that all workforce members have heard his message. During a 
portion of his travel time, he plans to conduct "town hall" meetings 
with the aviation maintenance workforce members at fleet readiness 
center locations and affiliated sites. Following these meetings, the 
commander will send teams to each newly established fleet readiness 
center to introduce the concepts and the expected changes in 
establishing the centers to the workforce. These teams will also 
provide information with regard to procedural changes that will be 
necessary to assure that costs and savings are properly tracked at each 
fleet readiness center and affiliated site. According to Navy 
officials, as the implementation proceeds, efforts will be undertaken 
to apply lessons learned as fleet readiness centers are established.

Providing Sustained Leadership:

Generally, commanding officers in the Navy change commands every 2 
years, which can make sustained leadership in a reorganization effort 
challenging, and there is no guarantee that leadership will remain in 
place throughout the implementation of this BRAC recommendation. Our 
prior work on strategic workforce planning states that sustained 
leadership and succession planning is necessary to achieve workforce 
reorganizations and agency goals.[Footnote 23] Navy officials stated 
that they expect to achieve the largest change in naval aviation 
maintenance since 1959 in only 3 to 5 years and the Commander, Aviation 
Depots, Naval Air Systems Command, expects his assignment to continue 
until fleet readiness center implementation is complete. The Navy has 
26 Naval Aviation Maintenance duty captains, which comprise a cadre of 
officers available for selecting successive commanding officers to 
oversee the implementation of the recommendation to establish and 
manage fleet readiness centers. In addition to top-level leadership, 
the Navy plans to utilize the Navy's chief petty officers, the Marine 
Corps' senior noncommissioned officers, and seasoned civilian 
maintainers as key enablers of the implementation process. Navy 
officials feel that these individuals can reinforce the communications 
of senior Navy leadership and clarify the intent of establishing fleet 
readiness centers to sailors, marines, and the civilian workforce.

Reporting Depot Maintenance Funding between the Public and Private 
Sectors:

Navy officials noted another challenge may exist after fleet readiness 
centers are established that involves accurately recording and 
reporting depot maintenance performed at intermediate departments. 
Under 10 U.S.C. § 2466, the military departments and defense agencies 
can use no more than 50 percent of annual depot maintenance funding for 
work performed by private-sector contractors. In fiscal year 2006, the 
Navy reported that 52 percent of naval aviation depot work was 
performed by civilian depot artisans and 48 percent was performed by 
private contractors. As depot artisans begin to work in intermediate 
maintenance departments, adequate systems and management commitment for 
verifying the amount of public-sector depot maintenance is necessary to 
comply with 50/50 requirements. We previously reported that the Navy 
did not maintain documentation to support the amounts in its 50/50 
report and no formal training on procedural requirements or Navy 
guidance to develop and report the 50/50 data was provided to the 
personnel responsible for compiling the data. Our report noted that 
persistent deficiencies limit the accuracy and usefulness of DOD's 
funding allocation data reported to the Congress, and further, that it 
is difficult to project out-year data due to factors such as changing 
depot maintenance requirements and the ongoing consolidation of 
maintenance facilities. When the fleet readiness centers are 
implemented, depot artisans will be stationed at the intermediate 
departments and must document the depot maintenance performed, which is 
used for entry into the depot accounting system and the Naval Aviation 
Logistics Command/Management Information System. The Navy has drafted a 
handbook that provides procedures and quality assurance for the 
required details of documentation by the artisans. For example, all 
maintenance documentation goes through layers of quality assurance such 
as validation specifications within the Naval Aviation Logistics 
Command/Management Information System, production controls that approve 
each component before moving it back into the supply system, database 
administrator screening, and a final reality check by the fleet 
readiness center command subject matter experts.

Conclusions:

Although projected savings from establishing fleet readiness center 
remain significant, it appears likely that the majority of onetime 
savings from reduced inventory levels may not occur as expected during 
the BRAC implementation period, and projected long-term savings are 
likely overstated. To accurately account for and report BRAC savings, 
the Navy business plan to establish fleet readiness centers should 
include onetime savings that will be achieved during the implementation 
period and long-term savings that are directly attributed to 
implementing the recommendation. While the Navy has recognized the need 
to assess progress against goals and track savings, our prior work has 
shown that sustained leadership and follow-through will be important to 
ensure the recommendation is successfully implemented.

Recommendations for Executive Action:

To improve the reporting of savings projected from BRAC 2005 
recommendations, we recommend that the Secretary of Defense direct the 
Secretary of the Navy to:

* update the business plan for the fleet readiness centers (1) to 
reflect only savings that are directly related to implementing the 
recommendation, and (2) update projected onetime savings when data are 
available; and:

* monitor implementation of the recommendation to determine the extent 
that savings already taken from the Navy budget are actually achieved.

We are sending copies of this report to interested congressional 
committees; the Secretaries of Defense and the Navy; and the Director, 
Office of Management and Budget. We will also make copies available to 
others upon request. In addition, the report will be available at no 
charge on GAO's Web site at [Hyperlink; http://www.gao.gov]: 

Agency Comments and Our Evaluation:

In commenting on a draft of this report, DOD concurred with our 
recommendations. DOD noted that it considers military personnel 
reductions attributable to a BRAC recommendation as real savings. It 
noted that while the department may not reduce end strength, these 
reductions allow the department to reapply these military personnel to 
support new capabilities. We believe the department counting of savings 
from eliminating military personnel positions, without corresponding 
reductions in end strength, creates a false sense of savings available 
for other purposes because they do not represent dollar savings that 
can be readily reallocated outside the military personnel accounts. We 
do agree that assigning these positions to other areas may enhance 
capabilities. DOD's written comments are reprinted in appendix III. DOD 
also provided technical comments, which we have incorporated into this 
report as appropriate.

If you or your staff have any questions about this report, please 
contact me on (202) 512-4523 or leporeb@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. Additional contacts and staff 
acknowledgments are provided in appendix IV.

Signed by: 
Brian J. Lepore: 
Director: 
Defense Capabilities and Management: 

List of Committees:

The Honorable Carl Levin: 
Chairman: 
The Honorable John McCain: 
Ranking Member: 
Committee on Armed Services: 
United States Senate:

The Honorable Daniel K. Inouye: 
Chairman: 
The Honorable Ted Stevens: 
Ranking Member: 
Subcommittee on Defense Committee on Appropriations: 
United States Senate: 

The Honorable Tim Johnson: 
Chairman: 
The Honorable Kay Bailey Hutchison: 
Ranking Member: 
Subcommittee on Military Construction, Veterans' Affairs, and Related 
Agencies: 
Committee on Appropriations: 
United States Senate: 

The Honorable Ike Skelton: 
Chairman: 
The Honorable Duncan L. Hunter: 
Ranking Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable John P. Murtha, Jr. 
Chairman: 
The Honorable C.W. Bill Young: 
Ranking Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives:

The Honorable Chet Edwards: 
Chairman: 
The Honorable Roger F. Wicker: 
Ranking Member: 
Subcommittee on Military Construction, Veterans' Affairs, and Related 
Agencies: 
Committee on Appropriations: 
House of Representatives: 

[End of section]

Appendix I: Scope and Methodology: 

We performed our work at the Office of the Secretary of Defense, the 
office the Commander, Naval Air Forces, Naval Air Systems Command, 
Patuxent River, Maryland; the Naval Aviation Depots in Coronado, 
California, and Jacksonville, Florida, as well as the Aviation 
Intermediate Maintenance Departments located at Oak Harbor, Washington; 
Coronado, California; and Mayport, Florida.

To determine the extent to which estimated costs and savings have 
changed, we compared the Navy's business plan approved in August 2006 
to the recommendation approved by the Base Realignment and Closure 
(BRAC) Commission. We focused on the major factors that affected 
projected onetime costs, onetime savings, and annual recurring savings. 
We determined the reasonableness of these estimates by reviewing and 
analyzing source data and the methodology used to generate savings 
estimates and interviewing Navy officials who prepared these estimates. 
We discussed the reasons for variances in costs and savings estimates 
between the BRAC Commission and the approved business plan with Navy 
officials. To analyze projected onetime savings from reduced levels of 
aircraft component inventory, we took a judgmental sample of 99 items 
targeted for inventory reduction. We calculated the years of supply for 
each item using its required inventory level, inventory on-hand, excess 
on-hand inventory, condition, and recurring and nonrecurring demands. 
Our analysis was reviewed by Navy Supply System officials. We analyzed 
the business plan to identify the major elements that contributed to 
projected annual recurring savings. Our analysis indicated that the 
business plan included savings from an initiative to reduce aviation 
maintenance costs referred to as AirSpeed. We interviewed Navy 
officials to determine the relationship of AirSpeed to the BRAC 
recommendation. To assess the reliability of the data used to generate 
estimates of costs and savings and the validity of underlying 
assumptions used to generate cost and savings estimates, we reviewed 
Navy regulations and instructions for reporting aviation maintenance 
data and interviewed officials at Navy Air Systems Command, Navy 
Aviation depots, Navy Aviation Intermediate Maintenance Departments, 
and Naval Supply Systems Command knowledgeable about the data and the 
assumptions underlying estimated costs and savings. Based on this, we 
believe that the assumptions underlying estimated costs and savings are 
generally valid, and that the data used were sufficiently reliable for 
the purposes of this report.

To determine the challenges to successfully implement the fleet 
readiness centers, we analyzed pertinent documents and reports and 
interviewed officials responsible for developing the original proposal 
and the business plan. We also interviewed Navy officials at the 
Aircraft Intermediate Maintenance Departments at Whidbey Island, 
Washington; North Island, California; and Mayport, Florida; and at 
Naval Aviation Depots at North Island, California, and Jacksonville, 
Florida. In addition, we also reviewed statutes related to continuing 
congressional oversight of annual depot maintenance funding, related 
reports, and court cases involving depot personnel.

We conducted our work from February 2006 to March 2007 in accordance 
with generally accepted government auditing standards.

[End of section]

Appendix II: Fleet Readiness Centers Recommendation: 

165. FLEET READINESS CENTERS (IND 19):

a. Realign Naval Air Station Oceana, VA, by disestablishing the 
Aircraft Intermediate Maintenance Department Oceana, the Naval Air 
Depot Cherry Point Detachment, and the Naval Air Depot Jacksonville 
Detachment; establishing Fleet Readiness Center Mid Atlantic, Naval Air 
Station Oceana, VA; and transferring all intermediate maintenance 
workload and capacity to Fleet Readiness Center Mid Atlantic, Naval Air 
Station Oceana, VA.

b. Realign Naval Air Station Patuxent River, MD, by disestablishing the 
Aircraft Intermediate Maintenance Department at Naval Air Warfare 
Center Aircraft Division; establishing Fleet Readiness Center Mid 
Atlantic Site Patuxent River, Naval Air Station Patuxent River, MD; and 
transferring all intermediate maintenance workload and capacity to 
Fleet Readiness Center Mid Atlantic Site Patuxent River, Naval Air 
Station Patuxent River, MD.

c. Realign Naval Air Station Norfolk, VA, by disestablishing the 
Aircraft Intermediate Maintenance Department Norfolk VA, the Naval Air 
Depot Jacksonville Detachment, and Naval Air Warfare Center Aircraft 
Division Lakehurst Detachment; establishing Fleet Readiness Center Mid 
Atlantic Site Norfolk, Naval Air Station Norfolk, VA; and transferring 
all intermediate and depot maintenance workload and capacity to Fleet 
Readiness Center Mid Atlantic Site Norfolk, Naval Air Station Norfolk, 
VA.

d. Realign Naval Air Station Joint Reserve Base New Orleans, LA, by 
disestablishing the Aircraft Intermediate Maintenance Department, 
establishing Fleet Readiness Center Mid Atlantic Site New Orleans, 
Naval Air Station Joint Reserve Base New Orleans, LA; and transfer all 
intermediate maintenance workload and capacity to Fleet Readiness 
Center Mid Atlantic Site New Orleans, Naval Air Station Joint Reserve 
Base New Orleans, LA.

e. Realign Marine Corps Air Station Cherry Point, NC, as follows: 
disestablish Naval Air Depot Cherry Point; establish Fleet Readiness 
Center East, Marine Corps Air Station Cherry Point, NC; relocate depot 
maintenance workload and capacity for Aircraft Avionics/Electronics 
Components (approximately 39 K DLHs) [direct labor hours], Aircraft 
Hydraulic Components (approximately 69 K DLHs), Aircraft Landing Gear 
Components (approximately 8 K DLHs), Aircraft Other Components 
(approximately 23 K DLHs), and Aircraft Structural Components 
(approximately 126 K DLHs) to Fleet Readiness Center Mid Atlantic, 
Naval Air Station Oceana, VA; relocate depot maintenance workload and 
capacity for Aircraft Avionics/Electronics Components (approximately 11 
K DLHs), Aircraft Hydraulic Components (approximately 19 K DLHs), 
Aircraft Landing Gear Components (approximately 2 K DLHs), Aircraft 
Structural Components (approximately 35 K DLHs), and Aircraft Other 
Components (approximately 6 K DLHs) to Fleet Readiness Center Mid 
Atlantic Site Norfolk, Naval Air Station Norfolk, VA; relocate depot 
maintenance workload and capacity for Aircraft Avionics/Electronics 
Components (approximately 6 K DLHs), Aircraft Hydraulic Components 
(approximately 10 K DLHs), Aircraft Landing Gear Components 
(approximately 1 K DLHs), Aircraft Other Components (approximately 3 K 
DLHs), and Aircraft Structural Components (approximately 18 K DLHs) to 
FleetReadiness Center Mid Atlantic Site Patuxent River, Naval Air 
Station Patuxent River, MD; relocate depot maintenance workload and 
capacity for Aircraft Avionics/Electronics Components (approximately 2 
K DLHs), Aircraft Hydraulic Components (approximately 3 K DLHs), 
Aircraft Landing Gear Components (approximately 0.4K DLHs), Aircraft 
Other Components (approximately 1 K DLHs), and Aircraft Structural 
Components (approximately 6 K DLHs) to FRC Mid Atlantic Site New 
Orleans, Naval Air Station JRB New Orleans, LA; relocate depot 
maintenance workload and capacity for Aircraft Avionics/Electronics 
Components (approximately 9 K DLHs), Aircraft Hydraulic Components 
(approximately 16 K DLHs), Aircraft Landing Gear Components 
(approximately 2 K DLHs), Aircraft Other Components (approximately 6 K 
DLHs) and Aircraft Structural Components (approximately 30 K DLHs) to 
the Fleet Readiness Center East Site Beaufort, hereby established at 
Marine Corps Air Station Beaufort, SC; relocate depot maintenance 
workload and capacity for Aircraft Avionics/Electronics Components 
(approximately 11 K DLHs), Aircraft Hydraulic Components (approximately 
20 K DLHs), Aircraft Landing Gear Components (approximately 2 K DLHs), 
Aircraft Other Components (approximately 6 K DLHs), Aircraft Structural 
Components (approximately 36 K DLHs), Aircraft Rotary (approximately 1 
K DLHs), Aircraft VSTOL (approximately 2 K DLHs), Aircraft Cargo/Tanker 
(approximately 0.02K DLHs,), Aircraft Other (approximately 18 K DLHs), 
Aircraft Structural Components (approximately 0.001K DLHs), Calibration 
(approximately 0.15 K DLHs) and "Other" Commodity (approximately 0.3 K 
DLHs) to Fleet Readiness Center East Site New River, hereby established 
at Marine Corps Air Station New River, Camp Lejeune, NC; and transfer 
all remaining depot maintenance workload and capacity to Fleet 
Readiness Center East, Marine Corps Air Station Cherry Point, NC.

f. Realign Marine Corps Air Station Beaufort, SC, by disestablishing 
Naval Air Depot Jacksonville Detachment Beaufort and transferring all 
depot maintenance workload and capacity to Fleet Readiness Center East 
Site Beaufort, Marine Corps Air Station Beaufort, SC.

g. Realign Naval Air Station Jacksonville, FL, as follows: disestablish 
Naval Air Depot Jacksonville, Naval Air Depot Jacksonville Detachment 
Jacksonville, and Aircraft Intermediate Maintenance Department 
Jacksonville; establish Fleet Readiness Center Southeast, Naval Air 
Station, Jacksonville, FL; relocate depot maintenance workload and 
capacity for Aircraft Avionics/Electronics Components (approximately 8 
K DLHs), Aircraft Hydraulic Components (approximately 6 K DLHs), 
Aircraft Landing Gear Components (approximately 3 K DLHs), Aircraft 
Other Components (approximately 27 K DLHs), and Aircraft Structural 
Components (approximately 9 K DLHs) to Fleet Readiness Center Southeast 
Site Mayport, hereby established at Naval Air Station, Mayport, FL; 
transfer all remaining intermediate and depot maintenance workload and 
capacity to Fleet Readiness Center Southeast, Naval Air Station 
Jacksonville, FL.

h. Realign Naval Air Station Mayport, FL, by disestablishing Aircraft 
Intermediate Maintenance Department, Naval Air Depot Jacksonville 
Detachment Mayport, and Naval Air Warfare Center Aircraft Division 
Lakehurst Voyage Repair Team Detachment Mayport and transferring all 
intermediate maintenance workload and capacity to Fleet Readiness 
Center Southeast Site Mayport, Naval Air Station Mayport, FL.

i. Realign Naval Air Station Lemoore, CA, by disestablishing Aircraft 
Intermediate Maintenance Department Lemoore and Naval Air Depot North 
Island Detachment; establishing Fleet Readiness Center West, Naval Air 
Station Lemoore, CA; and transferring all intermediate and depot 
maintenance workload and capacity to Fleet Readiness Center West, Naval 
Air Station Lemoore, CA.

j. Realign Naval Air Station Fallon, NV, by disestablishing the 
Aircraft Intermediate Maintenance Department Fallon and the Naval Air 
Depot North Island Detachment Fallon; establishing Fleet Readiness 
Center West Site Fallon, Naval Air Station Fallon, NV; and transferring 
all intermediate and depot maintenance workload and capacity to Fleet 
Readiness Center West Site Fallon, Naval Air Station Fallon, NV.

k. Realign Naval Air Warfare Center Weapons Division China Lake, CA, by 
disestablishing the Aircraft Intermediate Maintenance Department and 
relocating its maintenance workload and capacity for Aircraft 
(approximately 3 K DLHs), Aircraft Components (approximately 45 K 
DLHs), Fabrication & Manufacturing (approximately 6 K DLHs) and Support 
Equipment (approximately 16 K DLHs) to Fleet Readiness Center West, 
Naval Air Station Lemoore, CA.

l. Realign Naval Air Station Joint Reserve Base Fort Worth, TX, by 
disestablishing the Aircraft Intermediate Maintenance Department, 
establishing Fleet Readiness Center West Site Fort Worth, Naval Air 
Station Fort Worth, TX, and transferring all intermediate maintenance 
workload and capacity to Fleet Readiness Center West Site Fort Worth, 
Naval Air Station Joint Reserve Base Fort Worth, TX.

m. Realign Naval Air Station Whidbey Island, WA, by disestablishing the 
Aircraft Intermediate Maintenance Department, establishing Fleet 
Readiness Center Northwest, Naval Air Station Whidbey Island, WA, and 
transferring all intermediate maintenance workload and capacity to 
Fleet Readiness Center Northwest, Naval Air Station Whidbey Island, WA.

n.[Footnote 24] (Deleted):

o. Realign Naval Air Station North Island, Naval Base Coronado, CA, as 
follows: disestablish Naval Air Depot North Island, COMSEACONWINGPAC 
(AIMD), and NADEP North Island Detachment North Island; establish Fleet 
Readiness Center Southwest, Naval Air Station North Island, Naval Base 
Coronado, CA; relocate depot maintenance workload and capacity for 
aircraft Avionics/Electronics Components (approximately 6 K DLHs), 
Aircraft Hydraulic Components (approximately 2 K DLHs), Aircraft 
Landing Gear Components (approximately 3 K DLHs), aircraft Other 
Components (approximately 13 K DLHs), and Aircraft Structural 
Components (approximately 4 K DLHs) from Naval Air Depot North Island 
to Fleet Readiness Center Southwest Site Point Mugu, hereby established 
at Naval Air Station Point Mugu, Naval Base Ventura, CA; relocate depot 
maintenance workload and capacity for Aircraft avionics/Electronics 
Components (approximately 26 K DLHs), Aircraft Hydraulic Component 
(approximately 8 K DLHs), Aircraft Landing Gear Components 
(approximately 13 K DLHs), Aircraft Other Components (approximately 55 
K DLHs), Aircraft Structural Components (approximately 16 K DLHs) from 
Naval Air Depot North Island to Fleet Readiness Center Southwest Site 
Miramar, hereby established at Marine Corps Air Station Miramar, CA; 
relocate depot maintenance workload and capacity for Aircraft Avionics/ 
Electronics Components (approximately 8 K DLHs), Aircraft Hydraulic 
Components (approximately 2 K DLHs), Aircraft Landing Gear Components 
(approximately 4 K DLHs), Aircraft Other Components (approximately 17 K 
DLHs), and Aircraft Structural Components (approximately 5 K DLHs) from 
Naval Air Depot North Island to Fleet Readiness Center Southwest Site 
Pendleton, hereby established at Marine Corps Air Station Camp 
Pendleton, CA; relocate depot maintenance workload and capacity for 
Aircraft Avionics/Electronics Components (approximately 6 K DLHs), 
Aircraft Hydraulic Components (approximately 2 K DLHs), Aircraft 
Landing Gear Components (approximately 3 K DLHs), Aircraft Other 
Components (approximately 12 K DLHs), Aircraft Structural Components 
(approximately 3 K DLHs) from Naval Air Depot North Island to Fleet 
Readiness Southwest Site Yuma, hereby established at Marine Corps Air 
Station Yuma, AZ; relocate depot maintenance workload and capacity for 
Aircraft Avionics/Electronics Components (approximately 6 K DLHs), 
Aircraft Hydraulic Components (approximately 2 K DLHs), Aircraft 
Landing Gear Components (approximately 3 K DLHs), Aircraft Other 
Components (approximately 12 K DLHs), and Aircraft Structural 
Components (approximately 3 K DLHs) from Naval Air Depot North Island 
to Fleet Readiness Center West Site Fort Worth, Fort Worth TX; relocate 
depot maintenance workload and capacity for Aircraft Avionics/ 
Electronics Components (approximately 25 K DLHs), Aircraft Hydraulic 
Components (approximately 8 K DLHs), Aircraft Landing Gear Components 
(approximately 13 K DLHs), Aircraft Other Components (approximately 53 
K DLHs), and Aircraft Structural Components (approximately 15 K DLHs), 
from Naval Air Depot North Island to Fleet Readiness Center Northwest, 
Naval Air Station Whidbey Island, WA; and transfer all remaining 
intermediate and depot maintenance workload and capacity to Fleet 
Readiness Center Southwest, Naval Air Station North Island, Naval Base 
Coronado, CA.

p. Realign Naval Air Station Point Mugu, Naval Base Ventura, CA, by 
disestablishing the Aircraft Intermediate Maintenance Department and 
transferring all intermediate maintenance workload and capacity to 
Fleet Readiness Center Southwest Site Point Mugu, Naval Base Ventura, 
CA.

q. Realign Marine Corps Air Station Miramar, CA, by transferring depot 
maintenance workload and capacity for Aircraft Other (approximately 28 
K DLHs) and Aircraft Fighter/Attack (approximately 39 K DLHs) and 
intermediate maintenance workload and capacity for Aircraft Components, 
Aircraft Engines, Fabrication & Manufacturing and Support Equipment 
from Marine Aviation Logistics Squadron (MALS)-11 and 16 to Fleet 
Readiness Center Southwest Site Miramar, Marine Corps Air Station 
Miramar, CA.

r. Realign Marine Corps Air Station Camp Pendleton, CA, by transferring 
depot maintenance workload and capacity for Aircraft Other 
(approximately 22 K DLHs) and Aircraft Rotary (approximately 102 K 
DLHs) and intermediate maintenance workload and capacity for Aircraft 
Components, Aircraft Engines, Fabrication & Manufacturing and Support 
Equipment from MALS-39 to Fleet Readiness Center Southwest Site Camp 
Pendleton, Marine Corps Air Station Camp Pendleton, CA.

s. Realign Marine Corps Air Station Yuma, AZ, by transferring depot 
maintenance workload and capacity for Aircraft Fighter/Attack, Aircraft 
Other and Aircraft Rotary and intermediate maintenance workload and 
capacity for Aircraft Components, Aircraft Engines, Communication/ 
Electronics Equipment, Ordnance Weapons & Missiles, Software and 
Support Equipment from MALS-13 to Fleet Readiness Center Southwest Site 
Yuma, Marine Corps Air Station Yuma, AZ.

[End of section]

Appendix III: Comments from the Department of Defense: 

[See PDF for image]: 

[End of figure]

Acquisition, Technology And Logistics: 

Office Of The Under Secretary Of Defense: 
3000 Defense Pentagon:  
Washington, Dc 20301-3000: 

JUN 20 2007:

Mr. Brian J. Lepore:
Director, Defense Capabilities and Management: 
U.S. Government Accountability Office: 

441 G Street, N.W. Washington, DC 20548:

Dear Mr. Lepore,

This letter is the Department of Defense (DoD) response to the GAO 
draft report, GAO 07-304, "MILITARY BASE CLOSURES: Projected Savings 
from Fleet Readiness Centers Are Likely Overstated and Actions Needed 
to Track Actual Savings and Overcome Certain Challenges" dated May 16, 
2007, (GAO Code 350804). 

The Department concurs with both of the GAO's recommendations in the 
draft report and GAO's recognition that projected savings remain 
substantial, however, it is important to note that the issue regarding 
the treatment of military personnel savings represents a longstanding 
difference of opinion between DoD and GAO. The Department considers 
military personnel reductions attributable to a BRAC recommendation as 
savings that are just as real as savings generated through end-strength 
reductions. While the Department may not reduce overall end-strength, 
the reductions in military personnel for each recommendation at a 
specific location are real. As is the case of monetary savings, 
personnel reductions allow the Department to re-apply these military 
personnel to support new capabilities and to improve operational 
efficiencies.

The Department's comments regarding the draft report are outlined in 
the enclosure. The Department appreciates the work performed by the GAO 
and appreciates the opportunity to comment on the draft report.

Sincerely,

Signed by: 

Philip W. Grone: 
Deputy Under Secretary of Defense: 
(Installations and Environment): 

[See PDF for image]

[End of figure]

Enclosure: As stated: 

Gao Draft Report - Dated May 16, 2007: 
Gao Code 350804/GAO-07-304: 

"Military Base Closures: Projected Savings from Fleet Readiness Centers 
Are Likely Overstated and Actions Needed to Track Actual Savings and 
Overcome Certain Challenges": 

Department Of Defense Comments: 
To The Recommendations: 

Recommendation 1: The GAO recommends that the Secretary of Defense 
direct the Secretary of the Navy to update the business plan for the 
fleet readiness centers (1) to reflect only savings that are directly 
related to implementing the recommendation, and (2) to update projected 
one-time savings when data is available.

Dod Response: DoD concurs. 

Recommendation 2: The GAO recommends that the Secretary of Defense 
direct the Secretary of the Navy to monitor implementation of the 
recommendation to determine the extent that savings already taken from 
the Navy budget are actually achieved. 

Dod Response: DoD concurs. 

Enclosure pg. 1:

[End of section] 

Appendix IV: GAO Contacts and Staff Acknowledgments: 

GAO Contact:

Brian J. Lepore, (202) 512-4523 or leporeb@gao.gov:

Acknowledgments:

In addition to the person named above, Michael Kennedy, Assistant 
Director; Avrum I. Ashery; Pat L Bohan; Grace A. Coleman; Julia C. 
Matta; Charles W. Perdue; Maria-Alaina I. Rambus; and John E. Trubey 
also made major contributions to this report.

FOOTNOTES

[1] The BRAC legislation (Pub. L. No. 101-510, Title XXIX, as amended 
by Pub. L. No. 107-107, Title XXX) provided for an independent 
Commission to review the Secretary of Defense's realignment and closure 
recommendations, and present its findings and conclusions on the 
Secretary's recommendations, along with its own recommendations to the 
President.

[2] Onetime savings are estimated savings to be realized during the 
2006-2011 implementation period. Onetime savings are nonrecurring 
savings that stop at the end of implementation in 2011. 

[3] GAO, Military Bases: Analysis of DOD's 2005 Selection Process and 
Recommendations for Base Closures and Realignments, GAO-05-785 
(Washington, D.C.: July 1, 2005).

[4] 31 U.S.C. § 717.

[5] DOD did not accept the final BRAC Commission estimate because it 
was based on actual versus authorized positions.

[6] Annual recurring savings are expected to occur annually after the 
costs of implementing a BRAC action have been offset by the savings. 

[7] The Navy and Marine Corps currently operate 20 aviation 
intermediate maintenance departments including the Presidential 
Helicopter support at Quantico, 11 Marine aviation logistics squadrons, 
and three Naval Aviation Depot maintenance activities in the United 
States.

[8] GAO-05-785.

[9] The $3.7 billion is the 20-year net present value of the projected 
savings in fiscal year 2005 constant dollars.

[10] The Department of Defense has 6 years (2006-2011) to implement the 
BRAC 2005 recommendations.

[11] Of the approximate $31 million difference, about $4 million is 
inflation.

[12] GAO-05-785.

[13] The shore-based aviation consolidated allowance list inventory is 
a consolidated list of components, repair parts, and consumable items 
and depot-and field-level repairable items required to support planned 
operational and maintenance missions at designated naval and Marine 
Corps air stations.

[14] In fiscal year 2003, the inventory and supply of aircraft 
components and replacement parts had a value of about $4.3 billion.

[15] DOD assumed the cumulative inflation over the 2006-2011 time 
period was 15.37 percent. It ranged from 2.1 percent to 2.6 percent per 
year. 

[16] GAO-05-785.

[17] GAO, DOD's High-Risk Areas: Successful Business Transformation 
Requires Sound Strategic Planning and Sustained Leadership, GAO-05-520T 
(Washington, D.C.: Apr. 13, 2005).

[18] GAO, Depot Maintenance: Management Attention Required to Further 
Improve Workload Allocation Data, GAO-02-95 (Washington, D.C.: Nov. 9, 
2001) and GAO, Depot Maintenance: DOD's 50-50 Reporting Should Be 
Streamlined, GAO-03-1023 (Washington, D.C.: Sept. 15, 2003).

[19] GAO-05-785.

[20] GAO, Human Capital: Key Principles for Effective Strategic 
Workforce Planning, GAO-04-39 (Washington, D.C.: Dec. 11, 2003).

[21] GAO-04-39.

[22] GAO-04-39.

[23] GAO-04-39.

[24] By Motion 165-3A, the Commission struck paragraph "n", which read 
"Realign Naval Support Activity Crane, IN, by relocating the depot 
maintenance workload and capacity for ALQ-99 Electronic Warfare to 
Fleet Readiness Center Northwest, Naval Air Station Whidbey Island, WA."

GAO's Mission:

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. Government Accountability Office

441 G Street NW, Room LM

Washington, D.C. 20548:

To order by Phone:

Voice: (202) 512-6000:

TDD: (202) 512-2537:

Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm

E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director,

NelliganJ@gao.gov

(202) 512-4800

U.S. Government Accountability Office,

441 G Street NW, Room 7149

Washington, D.C. 20548: