This is the accessible text file for GAO report number GAO-07-430 
entitled 'Missile Defense: Actions Needed to Improve Information for 
Supporting Future Key Decisions for Boost and Ascent Phase Elements' 
which was released on April 17, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 

GAO: 

April 2007: 

Missile Defense: 

Actions Needed to Improve Information for Supporting Future Key 
Decisions for Boost and Ascent Phase Elements: 

GAO-07-430: 

GAO Highlights: 

Highlights of GAO-07-430, a report to congressional committees 

Why GAO Did This Study: 

The Department of Defense (DOD) has spent about $107 billion since the 
mid-1980s to develop a capability to destroy incoming ballistic 
missiles. DOD has set key decision points for deciding whether to 
further invest in capabilities to destroy missiles during the initial 
phases after launch. In March 2006, DOD issued a report on these 
capabilities in response to two mandates. To satisfy a direction from 
the House Appropriations Committee, GAO agreed to review the report. To 
assist Congress in evaluating DOD’s report and preparing for future 
decisions, GAO studied the extent to which DOD (1) analyzed technical 
and operational issues and (2) presented complete cost information. To 
do so, GAO assessed the report’s methodology, explanation of 
assumptions and their effects on results, and whether DOD followed key 
principles for developing life-cycle costs. 

What GAO Found: 

The report DOD’s Missile Defense Agency (MDA) submitted to Congress in 
March 2006 included some useful technical and operational information 
on boost and ascent phase capabilities by describing these elements, 
listing upcoming decision points, and discussing geographic areas where 
boost and ascent elements could intercept missiles shortly after 
launch. However, the information in the report has several limitations 
because the analysis did not involve key DOD stakeholders such as the 
services and combatant commands in preparing the report and did not 
clearly explain modeling assumptions and their effects on results as 
required by relevant research standards. MDA’s report states that, at 
this time, some data is limited, and operational concepts that discuss 
operations from forward locations have not been fully vetted with the 
services and combatant commands. However, the report did not explain 
how each element’s performance may change if developing technologies do 
not perform as expected. Also, it did not address the challenges in 
establishing bases at the locations cited or provide information on the 
quantity of each element required for various deployment periods. 
Moving forward, DOD has an opportunity to involve stakeholders in 
analyzing operational and technical issues so that senior DOD and 
congressional leaders will have more complete information on which to 
base upcoming program decisions following key tests in 2008 and 2009 
for the Kinetic Energy Interceptor and Airborne Laser boost and ascent 
phase programs. 

MDA’s report provided some cost estimates for developing and fielding 
boost and ascent phase capabilities, but these estimates have several 
limitations and will require refinement before they can serve as a 
basis for DOD and congressional decision makers to compare life-cycle 
costs for the elements. MDA’s report states that there is uncertainty 
in estimating life-cycle costs because the elements are early in 
development. However, based on a comparison of the estimates in the 
report with key principles for developing life-cycle cost estimates, 
GAO found that MDA’s estimates did not include all cost categories, 
including costs to establish and sustain operations at U.S. bases and 
at forward overseas operating locations. Also, MDA’s estimates did not 
calculate costs based on realistic quantities of each element the 
combatant commanders or services would need to conduct the mission. 
Finally, MDA did not conduct a sensitivity analysis to assess the 
effect of key cost drivers on total costs. MDA officials stated that 
further analysis of the costs for each element along with measures to 
assess their confidence would help to better inform DOD and 
congressional decision makers in making investment decisions following 
key tests in 2008 and 2009. 

What GAO Recommends: 

To support future decisions, DOD should include key stakeholders in 
assessing operational issues, report on technical progress, and update 
and verify life-cycle cost estimates in accordance with key principles 
for developing life-cycle costs. In comments on a draft of this report, 
DOD agreed to include stakeholders and assess technical progress but 
did not agree to prepare or report life-cycle costs in accordance with 
key principles. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-430]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Janet A. St. Laurent at 
(202) 512-4402 or stlaurentj@gao.gov; or Paul Francis at (202) 512-2811 
or francisp@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

MDA's March 2006 Report Includes Some Useful Information but Has 
Several Limitations: 

DOD Can Significantly Improve Life-Cycle Cost Estimates to Support 
Future Investment and Budget Decisions for Boost and Ascent Phase 
Capabilities: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Comments from the Department of Defense: 

Appendix III: GAO Contacts and Staff Acknowledgments: 

Related GAO Products: 

Table: 

Table 1: Ballistic Missile Defense Boost and Ascent Phase Elements, Key 
Decision Points, and Their Planned Capability Dates: 

Abbreviations: 

ABL: Airborne Laser: 

BMDS: Ballistic Missile Defense System: 

DOD: Department of Defense: 

FYDP: Future Years Defense Program: 

KEI: Kinetic Energy Interceptor: 

MDA: Missile Defense Agency: 

United States Government Accountability Office: 
Washington, DC 20548: 

April 17, 2007: 

Congressional Committees: 

The new security environment includes some states, such as North Korea, 
that are aggressively pursuing development of long-range missiles and 
weapons of mass destruction. In 2002, President Bush directed that the 
Department of Defense (DOD) proceed with plans to develop and put in 
place an initial set of ballistic missile defense capabilities 
beginning in 2004. DOD has spent about $107 billion since the mid-1980s 
to develop a capability to destroy incoming ballistic missiles in all 
phases of their flight, including the initial phases after launch, 
called the boost and ascent phases.[Footnote 1] The purpose of boost 
and ascent phase elements of a ballistic missile defense system (BMDS) 
is to engage incoming missiles before release of warheads or 
countermeasures. DOD is developing three BMDS boost and ascent phase 
capabilities: Airborne Laser (boost phase only), Kinetic Energy 
Interceptor (boost and ascent phase), and the Aegis Ballistic Missile 
Defense element that will fire the Standard Missile-3 block 2A[Footnote 
2] (ascent phase) from BMDS-capable Aegis surface combatants. According 
to the Missile Defense Agency (MDA), the agency responsible for 
developing an integrated ballistic missile defense system, DOD plans to 
spend $1.6 billion for the Airborne Laser; $800 million for the Kinetic 
Energy Interceptor; and $200 million for the Aegis Standard Missile-3 
Block 2A during fiscal years 2006-08. The long-term costs for these 
elements will be much greater if DOD continues their development and 
fielding. DOD projects the initial boost and ascent phase capabilities 
will not be available until about 2014 through 2020. Congress has 
raised questions about the affordability of pursuing both the Airborne 
Laser and Kinetic Energy Interceptor programs. 

Over the next few years, DOD and Congress will be asked to make 
important program and investment decisions on boost and ascent phase 
capabilities--at a time when the federal government is facing a large 
and growing fiscal imbalance.[Footnote 3] Further, we have identified 
the competing demands of investing in transformational capabilities 
while continuing to invest in legacy systems as one of the most 
significant national defense challenges for the 21st century.[Footnote 
4] MDA has established key decision points at which it will decide 
whether to continue to invest in certain elements of the integrated 
system. For example, one key decision point is the booster flight test 
for the Kinetic Energy Interceptor element, scheduled for 2008, at 
which time a decision will be made on the program's future. A key 
decision point for the Airborne Laser is the lethal shootdown 
demonstration scheduled for 2009.[Footnote 5] Finally, in 2009, MDA 
plans a motor test for the Standard Missile-3 block 2A. 

In March 2006, MDA issued a report on boost and ascent phase 
capabilities in response to two mandates--one in the House 
Appropriations Committee Report on the Defense Appropriations Bill for 
Fiscal Year 2006 and one in the National Defense Authorization Act for 
Fiscal Year 2006. The House Appropriations Committee directed the 
Secretary of Defense to conduct a study on boost and ascent phase 
intercepts including an assessment of operational capabilities, 
quantities of operational assets required for various deployment 
periods, basing options, and an assessment of life-cycle 
costs.[Footnote 6] Life-cycle costs are the total cost to the 
government for a program over its full life, consisting of research and 
development, production, operations, maintenance, and disposal costs 
and are helpful in assessing whether a system's cost is affordable. The 
Department of Defense Authorization Act for Fiscal Year 2006 required 
the Secretary of Defense to conduct an assessment of U.S. missile 
defense programs that are designed to provide capability against threat 
ballistic missiles in the boost/ascent phase. The purpose of the 
assessment was to compare and contrast capabilities, asset 
requirements, and the costs for making the boost and ascent phase 
programs operational.[Footnote 7] MDA, on behalf of DOD, prepared one 
report to satisfy both requirements and sent the report to all four 
defense committees on March 30, 2006. According to MDA officials, that 
report was prepared specifically to satisfy the congressional 
requirements, not for use at any key decision point. 

To satisfy a direction from the House Appropriations Committee report, 
we agreed to review the DOD report including assessing the report's 
methodologies, assumptions, completeness, and results.[Footnote 8] This 
report is our assessment of the March 2006 MDA report and how DOD can 
build on this information to support future key decision points. 
Accordingly, we assessed the extent to which (1) information reported 
by DOD includes analysis of technical and operational issues and 
whether any additional information is needed to support future decision 
making and (2) DOD presented cost information to Congress that is 
complete and transparent. To assess the technical and operational 
information, we analyzed the extent to which the MDA report clearly 
explained technical maturity, modeling assumptions and their effect on 
results, and involved stakeholders in analyses of operational issues-- 
steps which contribute to a sound and complete quality study and are 
embodied in relevant generally accepted research standards[Footnote 9]. 
To assess the cost information in the March 2006 report, we compared 
MDA's cost data with key principles compiled from various DOD and GAO 
sources that describe how to develop accurate and reliable life-cycle 
cost estimates which are to include development, production, and all 
direct and indirect operating and support costs. We discussed the data 
and results of this comparison with DOD officials and identified some 
limitations, which we discuss in this report. We conducted our work 
between June 2006 and February 2007 in accordance with generally 
accepted government auditing standards. See appendix I for a more 
complete description of our scope and methodology. 

This report is one in a series we have issued on ballistic missile 
defense (see the list of related GAO products at the end of this 
report). Some of these reports have focused on assessments of program 
goals and progress in developing each element. For example, our March 
2006 report found that MDA made progress in the development and 
fielding of some elements but that time pressures caused MDA to stray 
from a knowledge-based acquisition strategy.[Footnote 10] This is 
significant because straying from a knowledge-based approach opens the 
door to greater cost and performance risks by not having the right 
information available for decision makers at the right time.[Footnote 
11] Another report focused on DOD's planning to operate BMDS. We 
reported in May 2006 that DOD has not established criteria that would 
have to be met before declaring BMDS operational and that the Future 
Years Defense Program (FYDP), a major source of budget information, 
does not provide complete and transparent data on ballistic missile 
defense operational costs.[Footnote 12] 

Results in Brief: 

MDA's 2006 report to Congress included some useful technical and 
operational information on boost and ascent phase capabilities but the 
information in the report has several limitations. Specifically, MDA's 
report provided some key information on potential boost and ascent 
phase capabilities by describing these elements, listing upcoming 
decision points, and discussing geographic areas where these elements 
could intercept missiles shortly after launch. However, the analysis 
did not involve DOD stakeholders such as the services and combatant 
commands, which will have a key role in operating the elements, and did 
not clearly explain modeling assumptions and their effects on results 
as identified by relevant research standards. For example, the report 
assumed that each element would perform as desired and that the 
elements could be deployed at optimum locations, but it did not explain 
how each element's performance would change if developing technologies 
do not perform as expected. In addition, the report did not address the 
challenges in establishing bases at the locations cited or provide 
information on the quantity of each element required for various 
deployment periods. Two key reasons for these limitations, which the 
report acknowledges, are that some data on the elements are limited at 
this time, and operational concepts that discuss operations from 
forward locations have not been fully vetted with the services and 
combatant commands. However, moving forward, DOD has an opportunity to 
involve stakeholders in analyzing operational and technical issues to 
provide more complete data that senior DOD and congressional leaders 
can use to make informed program decisions following key tests in 2008 
and 2009 for the Kinetic Energy Interceptor and Airborne Laser 
programs. To provide decision makers with information to support boost 
and ascent phase program decisions at future key decision points, we 
are recommending that DOD include all DOD stakeholders in developing 
and analyzing operational issues regarding what is needed to support 
operations at U.S. bases and potential forward locations, provide 
specific information on the technical progress of each element, and use 
the results of these analyses at each key decision point. 

The Missile Defense Agency provided some cost estimates for developing 
and fielding each of the boost and ascent phase capabilities in its 
March 2006 report to Congress; however, these estimates have several 
limitations and will require refinement before they can serve as a 
basis for DOD and congressional decision makers to compare the costs of 
boost and ascent phase alternatives. We compared the report's cost 
estimates with various DOD and GAO sources that describe key principles 
for developing accurate and reliable life-cycle cost estimates. Based 
on our analysis, we found that the estimates provided in the report did 
not include all cost categories, including costs to establish and 
sustain operations at U.S. bases and at forward locations. Also, MDA 
did not calculate costs based on quantities the warfighter would need 
to conduct the mission, or conduct a sensitivity analysis identifying 
the effects of cost drivers. Although the report acknowledges that, at 
this time, there is uncertainty in estimating life-cycle costs for 
these elements, it did not fully disclose the limitations of the cost 
estimates. DOD can significantly improve the completeness of and 
confidence in its cost estimates for boost and ascent phase 
capabilities as it prepares for future investment and budget decisions. 
For example, although MDA did not have the cost estimates in its March 
2006 report independently verified because doing so would have required 
several months, MDA officials agree that independent verification, 
which is another key principle of reliable cost estimates, will be 
critical to support major decision points. We are recommending that DOD 
prepare, periodically update, and independently verify life-cycle cost 
estimates for boost and ascent phase elements in accordance with key 
principles for developing accurate and reliable life-cycle cost 
estimates and that these verified estimates be used for making 
investment decisions and be reported with budget requests. 

In commenting on a draft of this report, DOD agreed with our 
recommendations regarding the need for analysis of technical progress 
and operational issues to support key boost and ascent phase element 
decision points. DOD also partially concurred that an independent life- 
cycle cost estimate may be needed to inform some key decision points 
but said that they may not be needed at others. However, DOD did not 
agree to prepare and periodically update full life-cycle cost estimates 
for each boost and ascent phase element to support key decision points, 
and report independently verified life cycle cost estimates with budget 
requests and FYDP funding plans. In its comments, DOD stated that it 
will direct an independent evaluation of life-cycle costs if 
circumstances warrant or the Director of MDA declares an element mature 
enough to provide a militarily useful capability. However, if, as DOD's 
comments suggest, such costs are not assessed until circumstances 
warrant or MDA's Director makes such a declaration, these costs may not 
be available early enough to help shape important program and 
investment decisions and consider trade-offs among elements. We 
continue to believe our recommendation has merit because the 
development of life-cycle cost estimates that include potential 
operations and support costs would improve the information available to 
decision makers and increase accountability for key decisions that 
could involve billions of dollars at a time when DOD will likely face 
competing demands for resources. Finally, DOD did not agree to report 
independently verified life-cycle cost estimates along with budget 
requests and FYDP funding plans since the development of total life- 
cycle cost estimates for operationalized BMDS capabilities require 
agreement between MDA and the lead military department on the roles and 
responsibilities for fielded missile defense capabilities. However, 
independent verification allows decision makers to gauge whether the 
program is executable. Also, DOD procedures specify that when cost 
estimates are presented to the Office of the Secretary of Defense's 
Cost Analysis Improvement Group, life-cycle cost estimates should be 
compared with the FYDP and differences explained. Therefore, we 
continue to believe that our recommendation has merit because, without 
an independent cost estimate that can be compared to budget requests 
and FYDP funding plans, congressional decision makers may not have all 
the necessary information to assess the full extent of future resource 
requirements if the boost and ascent phase capabilities go forward, or 
assess the completeness of budget requests and FYDP funding plans. 

Background: 

In 2002, the Secretary of Defense created MDA to develop an integrated 
system that would have the ability to intercept incoming missiles in 
all phases of their flight.[Footnote 13] In developing BMDS, MDA is 
using an incremental approach to field militarily useful capabilities 
as they become available. MDA plans to field capabilities in 2-year 
blocks. The configuration of a given block is intended to build on the 
work completed in previous blocks. For example, Block 2006 is intended 
to build on capabilities developed in Block 2004, and is scheduled to 
field capabilities during calendar years 2006-07. 

The integrated BMDS is comprised of various elements, three of which 
are intended to intercept threat missiles in their boost or ascent 
phase. Table 1 below describes each of these elements and shows the MDA 
projected dates for key decision points, initial capability, and tested 
operational capability. 

Table 1: Ballistic Missile Defense Boost and Ascent Phase Elements, Key 
Decision Points, and Their Planned Capability Dates: 

Boost/ascent phase element: Standard Missile-3, block 2A[A]; 
Description: Aegis Ballistic Missile Defense, which employs the 
Standard Missile, is a ship-based system designed to destroy medium, 
intermediate, and certain intercontinental ballistic missiles in the 
ascent and midcourse phases; 
Key decision points: 2009--motor test for the 21-inch diameter missile; 
Initial capability: Block 2012; 
Tested capability: Block 2014. 

Boost/ascent phase element: Kinetic Energy Interceptor (KEI)--land- 
based; 
Description: KEI is being designed to destroy medium, intermediate, and 
intercontinental ballistic missiles during the boost, ascent, and 
midcourse phases of flight. A land-based unit may consist of 5 
launchers, 10 missiles, and fire control and communications equipment; 
Key decision points: 2008--booster flight test; 
Initial capability: Block 2014; 
Tested capability: Block to be decided. 

Boost/ascent phase element: Kinetic Energy Interceptor--sea-based; 
Description: KEI is being designed to destroy medium, intermediate, and 
intercontinental ballistic missiles during the boost, ascent, and 
midcourse phases of flight. DOD is currently studying sea-based 
platform alternatives including surface combatants, submarines, or a 
new platform; 
Key decision points: 2007--platform selection; 2008-- booster flight 
test; 
Initial capability: Block to be decided; 
Tested capability: Block to be decided. 

Boost/ascent phase element: Airborne Laser (ABL); 
Description: ABL is an air-based missile defense system designed to 
destroy all classes of ballistic missiles during the boost phase. ABL 
also has onboard sensor capability designed to detect, track, and 
transmit targeting data; 
Key decision points: 2009--lethal shootdown demonstration; 
Initial capability: Block 2016; 
Tested capability: Block 2018. 

Source: GAO summary of DOD information. 

[A] The Standard Missile is intended to be used on BMDS upgraded Aegis 
cruisers and destroyers. Other versions of the Standard Missile-3 are 
being developed to intercept threat missiles in their midcourse phase. 

[End of table] 

During the past year, Congress requested additional information and 
analyses on the boost and ascent phase elements from DOD. Specifically, 
House Report 109-119 on the Department of Defense Appropriations Bill 
for Fiscal Year 2006 directed the Secretary of Defense to conduct a 
study to review the early engagement of ballistic missiles to include 
boost and ascent phase intercepts and submit the report to the 
congressional defense committees.[Footnote 14] The report was to 
include, but not be limited to: 

* an assessment of the operational capabilities of systems against 
ballistic missiles launched from North Korea or a location in the 
Middle East against the continental United States, Alaska, or Hawaii; 

* an assessment of the quantity of operational assets required for 
deployment periods of 7 days, 30 days, 90 days, and 1 year; 

* basing options; and: 

* an assessment of life-cycle costs[Footnote 15] to include research 
and development efforts, procurement, deployment, operating, and 
infrastructure costs. 

In addition, the National Defense Authorization Act for Fiscal Year 
2006 required the Secretary of Defense to assess missile defense 
programs designed to provide capability against threat ballistic 
missiles in the boost/ascent phase of flight. The purpose of this 
assessment was to compare and contrast: 

* capabilities of those programs (if operational) to defeat ballistic 
missiles from North Korea or a location in the Middle East against the 
continental United States, Alaska, or Hawaii; and: 

* asset requirements and costs for those programs to become operational 
with the capabilities referred to above. 

MDA, on behalf of DOD, prepared one report to satisfy both of the above 
requirements and sent the report to all four defense committees on 
March 30, 2006. The report included technical, operational, and cost 
information for each of the three boost and ascent phase BMDS elements. 
The remainder of this report discusses our assessment of the MDA report 
and how DOD can build on this information to support future key 
decision points. 

MDA's March 2006 Report Includes Some Useful Information but Has 
Several Limitations: 

MDA's March 2006 report to Congress included some useful technical and 
operational information on boost and ascent phase capabilities. 
However, the information in the report has several limitations--such as 
not including stakeholders in the analysis or explaining how 
assumptions affect results. Moving forward, DOD can enhance its ability 
to make informed decisions at future key decision points by including 
stakeholders DOD-wide in conducting analyses to provide complete 
technical and operational information. Otherwise, senior DOD and 
congressional decision makers may be limited in their ability to 
effectively assess the technical progress and operational effects of 
proceeding with one or more boost and ascent phase element. 

Report Provided Some Basic Information about Boost and Ascent Phase 
Elements: 

The March 2006 report to Congress contained some useful technical and 
operational information for Congress. For example, the report included 
a detailed description of the three boost and ascent phase elements, 
which could be useful for those unfamiliar with these elements. 
Additionally, the report listed upcoming knowledge points where DOD 
will review the progress MDA has made toward developing each of the 
boost and ascent phase elements. Further, the report discussed 
geographic areas where boost and ascent phase elements could intercept 
missiles shortly after launch based on desired technical capabilities. 
Also, MDA used a model[Footnote 16] to assess the desired capabilities 
of each BMDS element for the March 2006 report to Congress. Further, 
the modeling environment was used for several past BMDS analyses and 
the results were benchmarked against other models. Finally, MDA 
performed a sensitivity analysis that compared how the results in the 
modeling changed when different assumptions for targets' propellants, 
ascent times, hardness levels, and burn times were used. To provide 
context, the report explained that the boost and ascent phase elements 
are in the early stages of development and that the operational 
concepts are not yet mature. 

MDA's Analyses Have Limitations but DOD Can Improve Information to 
Support Future Decisions: 

The information in the March 2006 report has several limitations 
because the analyses did not involve stakeholders and did not clearly 
explain modeling assumptions and their effects on results as identified 
by relevant research standards. The relevant research standards and our 
prior work have shown that coordination with stakeholders from study 
design through reporting, and clearly explained assumptions and their 
effects on results, can enable DOD officials to make fully informed 
program decisions. As a result, the March 2006 report presents an 
incomplete picture of technical capabilities, such as development 
challenges to be overcome in order to achieve desired performance, and 
it does not clearly explain the effects of operational assumptions, 
such as basing locations, asset quantities, and base support 
requirements. As a step in the right direction, MDA stated that it 
plans to develop criteria to assess the boost/ascent phase elements at 
major decision points in a process involving the combatant commands. 
Although MDA officials told us that they consult stakeholders in a 
variety of forums other than the March 2006 report, they did not 
clearly state whether or how the services or other DOD stakeholders 
would be involved in developing criteria for key decision points or the 
extent to which their analyses would include information on technical 
and operational issues. 

Data Collection and Analysis for the March 2006 Report Did Not Involve 
Key DOD Stakeholders: 

MDA's analyses did not involve soliciting or using information from key 
DOD stakeholders such as the services, combatant commands, and joint 
staff from study design through reporting. For example, officials from 
the Office of the Secretary of Defense for Program Analysis and 
Evaluation and the Defense Intelligence Agency stated there were areas 
where additional information would have improved the fidelity of the 
results. First, the officials stated that there is uncertainty that the 
boost and ascent phase elements would achieve their desired 
capabilities within the timeframe stated in the report. Second, 
officials from both organizations stated that the report could have 
been enhanced by presenting different views of the type and capability 
of threats the United States could face and when these threats could 
realistically be expected to be used by adversaries. Third, officials 
from the Office of the Secretary of Defense for Program Analysis and 
Evaluation said that the MDA report did not distinguish between 
countermeasures that could be used in the near term and countermeasures 
that may be more difficult to implement. MDA officials said that they 
worked with the Office of the Secretary of Defense for Program Analysis 
and Evaluation in conducting analyses before they began work on the 
March 2006 report. MDA also stated that it discussed the draft March 
2006 report with Office of the Secretary of Defense for Program 
Analysis and Evaluation officials and included some of their comments 
in the report's final version. However, without communication with 
stakeholders from study design through reporting, MDA may not have had 
all potential inputs that could have affected how the type, capability, 
and likelihood of countermeasures to the boost and ascent phase 
elements were presented in its report. 

Additionally, MDA did not solicit information from the services, 
combatant commands, or Joint Staff regarding operational issues that 
could have affected information about basing and the quantities of 
elements that could be required to support operations. Although the 
elements have to be located in close proximity to their intended 
targets, and the report discusses placing the elements at specific 
forward overseas locations, the report does not include a basing 
analysis explaining what would need to be done to support operations at 
these locations. Specifically, the report did not include any 
discussion of the infrastructure or security/force protection that will 
be needed for the BMDS elements. Although the report mentions some 
support requirements--such as the Airborne Laser's need for unique 
maintenance and support equipment and skilled personnel to maintain the 
laser--the report did not fully explain how these support requirements 
would be determined, who would provide or fund them, or explain the 
operational effect if this support is not provided. For instance, 
without an adequate forward operating location, the boost and ascent 
phase elements would have to operate from much further away which would 
significantly limit the time an element is in close proximity to 
potential targets. Developing such information with the services, Joint 
Staff, and combatant commands could provide a much more complete 
explanation of operational issues and challenges. The services 
typically perform site analyses to ascertain what support is needed for 
a new weapon system at either a U.S. or overseas location. This 
comprehensive analysis examines a range of issues from fire protection 
to security, to infrastructure, to roads and airfields. In addition, 
U.S. Strategic Command and service officials told us that this type of 
support must be planned for in advance when adding a new system to any 
base, either in the United States or a forward location. 

MDA also did not involve stakeholders in assessing the quantities of 
each element for deployment periods of 7 days, 30 days, 90 days, and 1 
year. The report stated that limited data exist at this time for a full 
assessment of this issue, and service, Joint Staff, and MDA officials 
acknowledged that the quantities of each element used in the report are 
MDA assumed quantities. Service, Joint Staff, and U.S. Strategic 
Command officials stated that they have not completed analyses to 
assess quantities the warfighters may require. We understand that 
operational concepts will continue to evolve and could affect required 
quantities. However, stakeholders such as the services, Joint Staff, or 
combatant commands could have assisted MDA in assessing potential 
quantities required for various deployment periods. In addition, MDA 
did not solicit information from the services, Joint Staff, or 
combatant commands to determine if those organizations were conducting 
force structure analyses for the boost and ascent phase elements. We 
learned that the Navy had done a preliminary analysis in July 2005 and 
that the Joint Staff has begun a capabilities mix study and both 
include, in part, an analysis of quantities. Thus, in preparing for 
future decision points, MDA's analysis could be strengthened by 
including stakeholders to leverage other analyses. For example, MDA 
could have presented a range of scenarios to show how the quantities 
required to intercept adversary missiles could vary depending upon the 
number of sites covered and whether continuous, near-continuous, or 
sporadic coverage is provided. 

Assumptions and Their Effects on Data Presented in the MDA Report Were 
Not Clearly Explained: 

The March 2006 report to Congress did not clearly explain the 
assumptions used in the modeling of the BMDS elements' capabilities and 
did not explain the effects those assumptions may have had on the 
results. First, the model inputs for the technical analysis assumed 
desired rather than demonstrated performance, and the report does not 
fully explain challenges in maturing technologies or how these 
performance predictions could change if the technologies are not 
developed as desired or assumed. For example, although the model MDA 
used is capable of showing different results based on different 
performance assumptions, the report did not explain how the number of 
successful intercepts may change if less than 100 percent of the 
desired technical capabilities are developed as envisioned. Thus the 
results represent the best expected outcome. Second, the report does 
not explain the current status of technical development or the 
challenges in maturing each element's critical technologies as desired 
or assumed in the report. DOD best practices define Technology 
Readiness Levels on a scale of 1-9, and state which level should be 
reached to progress past specific program decision points.[Footnote 17] 
However, the March 2006 report does not explain the current Technology 
Readiness Level for any of the boost and ascent phase elements' 
critical technologies or the extent to which the technology has to 
mature to attain the performance assumed in the report. For example, 
the report does not explain that some of the technologies for the 
Airborne Laser have to improve between 60 percent and 80 percent and 
the report does not discuss any of the challenges MDA faces in doing 
so. 

DOD Can Significantly Improve Life-Cycle Cost Estimates to Support 
Future Investment and Budget Decisions for Boost and Ascent Phase 
Capabilities: 

The March 2006 report to Congress provides cost estimates for each of 
the boost and ascent phase capabilities; however, the cost estimates in 
the report have several limitations that raise questions about their 
usefulness. We compared the report's cost estimates with various DOD 
and GAO sources that describe key principles for developing accurate 
and reliable life-cycle cost estimates.[Footnote 18] Based on our 
analysis, we found that MDA did not include all cost categories, 
calculate costs based on warfighter quantities, and did not conduct a 
sensitivity analysis to assess the effects of cost drivers. Moreover, 
although MDA's report acknowledges uncertainty in the cost estimates, 
the report does not fully disclose the limitations of the cost 
estimates. DOD can significantly improve the completeness of and 
confidence in cost estimates for boost and ascent phase capabilities as 
it prepares for future investment and budget decisions. For example, 
although DOD did not have its cost estimate for its March 2006 report 
independently verified because doing so would have taken several 
months, MDA officials agreed that independently verified cost estimates 
will be critical to support major decision points for boost and ascent 
phase capabilities.[Footnote 19] In addition, as these capabilities 
mature, MDA officials agreed that showing cost estimates over time and 
conducting uncertainty analyses will be needed to support key program 
and investment decisions. 

Cost Estimates Did Not Include All Cost Categories: 

The cost estimates provided in the MDA report included some 
development, production, and operations/support costs for each boost 
and ascent phase element but were not fully developed or verified 
according to key principles for developing life-cycle cost estimates. 
Life-cycle costs are the total cost to the government for a program 
over its full life, including the costs of research and development, 
investment, operating and support, and disposal. 

Based on our comparison of the life-cycle cost estimates in the report 
with key principles for developing life-cycle cost estimates, we found 
that the estimates were incomplete in several ways. First, the cost 
estimates did not include all cost categories, such as costs to 
establish and sustain operations at U.S. bases. Instead, MDA assumed 
that the elements would be placed at existing bases with sufficient 
base support, infrastructure and security; however, some of these costs 
such as infrastructure could be significant. For example, an MDA 
planning document cited about $87 million for infrastructure costs to 
support a ground-based BMDS element (Terminal High Altitude Area 
Defense). Army officials confirmed that training facilities, missile 
storage buildings, and a motor pool were built at a U.S. base 
specifically to support this element and it is likely that similar 
infrastructure would be needed to support the land-based Kinetic Energy 
Interceptor. Additionally, MDA's cost estimates did not include costs 
to establish and sustain operations at forward overseas locations, even 
though the report states that the elements will have to be located in 
close proximity to their targets, and the operational concepts for 
Kinetic Energy Interceptor and Airborne Laser, although in early 
development, state that these elements will be operated from forward 
locations. Again, these are important factors to consider--the Airborne 
Laser operational concept and the MDA report acknowledge that unique 
support will be required to support operations at any forward location 
for the Airborne Laser such as chemical facilities, unique ground 
support equipment, and maintenance. Service, Joint Staff, and U.S. 
Strategic Command officials also said that these elements would have to 
be located forward and could be used as a strategic deterrent in 
peacetime. 

Second, the production and operating cost estimates were not based on 
warfighter quantities, that is, quantities of each element that the 
services and combatant commands may require to provide needed coverage 
of potential targets. MDA assumed a certain quantity of each element. 
For example, MDA officials told us that they assumed 96 Standard 
Missile-3 block 2A missiles because, at the time MDA prepared the 
report, they planned to buy 96 block 1A missiles developed to intercept 
short-range ballistic missiles. However, MDA did not solicit input from 
the services, Joint Staff, or combatant commands on whether they had 
done or begun analyses to determine element quantities. 

Third, MDA did not conduct a sensitivity analysis to identify the 
effects of cost drivers. A sensitivity analysis is a way to identify 
risk by demonstrating how the cost estimates would change in response 
to different values for specific cost drivers. Therefore, a sensitivity 
analysis should be performed when developing cost estimates, and the 
results should be documented and reported to decision makers. This 
means, for example, that MDA could have computed costs with and without 
significant categories of costs such as forward bases to identify the 
effect that adding forward bases would have on operating costs. The 
House Armed Services Committee report on the National Defense 
Authorization Bill for Fiscal Year 2006 recognized that operational 
capabilities and costs must be taken into account when making decisions 
on future funding support. Finally, the cost estimates did not estimate 
costs over time--a process known as time phasing--which can assist 
decision makers with budgetary decisions. The MDA report showed an 
annual cost estimate but did not state for how many years the 
development, production, and operating costs may be incurred. Although 
MDA officials stated they did not prepare time-phased cost estimates in 
order to prepare the report to Congress in a timely manner, they agreed 
that showing cost estimates over time would be important information to 
support investment decisions at key decision points. 

Cost Estimates Were Not Assessed or Independently Verified for MDA's 
2006 Report but MDA Officials See Need to Do So for Key Decision 
Points: 

Key principles for developing life-cycle cost estimates also include 
two steps for assessing the confidence of cost estimates. However, MDA 
did not take these steps to assess the confidence of the estimates 
reported in March 2006. First, the Missile Defense Agency did not 
conduct a risk analysis to assess the level of uncertainty for most of 
the cost estimates in the MDA report. Risk and uncertainty refer to the 
fact that, because a cost estimate is a prediction of the future, it is 
likely that the estimated cost will differ from the actual cost. It is 
useful to perform a risk analysis to quantify the degree of uncertainty 
in the estimates. By using standard computer simulation techniques, an 
overall level of uncertainty can be developed for cost estimates. In 
contrast, MDA officials told us that they could only provide a 
judgmental confidence level for the most of the cost estimates. Second, 
MDA did not have the cost estimates in the report verified by an 
independent organization such as DOD's Cost Analysis Improvement Group 
because doing so would have taken several months. However, MDA 
officials agreed that independent verification of cost estimates would 
be important information to support investment decisions at key 
decision points. According to the key principles that we have 
identified, all life-cycle cost estimates should be independently 
verified to assure accuracy, completeness, and reliability.[Footnote 
20] MDA has recognized the value in independently developed cost 
estimates. In 2003, MDA and the Cost Analysis Improvement Group 
developed a memorandum of understanding that said, in part, the Cost 
Analysis Improvement Group would develop independent cost estimates for 
the approved BMDS and its elements as appropriate during development in 
anticipation of transition to production, but MDA officials said that 
little work was completed under this agreement, which has expired. 

Developing complete cost estimates in which decision makers can have 
confidence is important since life-cycle cost estimates usually form 
the basis for investment decisions and annual budget requests. 
Specifically, life-cycle cost estimates that include all cost 
categories, show costs over time, include warfighter quantities, 
include an assessment of cost drivers, and are independently verified 
are important because accurate life-cycle cost estimates can be used in 
formulating funding requests contained in the President's Budget and 
DOD's future funding plan, the Future Years Defense Program (FYDP) 
submitted to Congress. Therefore, there is a need for DOD to provide 
transparent budget and cost planning information to Congress. In May 
2006, GAO reported that the FYDP, a major source of budget and future 
funding plans, does not provide complete and transparent data on 
ballistic missile defense operational costs because the FYDP's 
structure does not provide a way to identify and aggregate these costs. 
It is important that Congress has confidence in boost and ascent phase 
estimates because Congress has indicated that it is concerned with the 
affordability of pursuing both the Airborne Laser and Kinetic Energy 
Interceptor programs in parallel through 2008. 

As we reported in 2003, DOD assumes increased investment risk by not 
having information available for decision makers at the right time, and 
the level of anticipated spending magnifies this risk.[Footnote 21] 
Otherwise, senior DOD and congressional decision makers may be limited 
in their ability to assess the relative cost of the elements if all 
cost categories are not included and cost drivers are not identified. 
Considering competing demands, this could also limit Congress's ability 
to consider investment decisions or evaluate whether continued 
expenditures are warranted. MDA officials stated that, in developing 
the cost estimates for the March 2006 report, they decided not to 
follow some of the key principles for developing life-cycle cost 
estimates such as time phasing and independent verification of the cost 
estimates in order to complete the report in a timely manner. However, 
the officials also agreed that these key principles are important in 
developing complete, accurate, and reliable life-cycle cost estimates 
for supporting investment decisions at key decision points. Therefore, 
in the future, when preparing cost estimates to be used in support of 
key decision points, MDA could provide decision makers with more 
complete, accurate, and reliable cost estimates by better adhering to 
key principles for developing life-cycle cost estimates. 

Conclusions: 

Our review of MDA's March 2006 report on boost and ascent phase 
elements identified a number limitations but helps to illuminate the 
kind of information that DOD and congressional decision makers will 
need following upcoming tests for boost and ascent phase elements. We 
recognize that the March 2006 report was prepared in response to 
congressional direction rather than to support program decisions. We 
also recognize that, at the time of MDA's report, these elements were 
early in their development and information was incomplete and changing. 
Thus, the focus of our analysis was to identify additional information 
that could enhance future program and investment decisions. 

In particular, the House Armed Services Committee has raised questions 
about the affordability of pursuing both the Kinetic Energy Interceptor 
and the Airborne Laser in parallel through the projected knowledge 
point demonstrations,[Footnote 22] which are now scheduled for 2008 and 
2009 respectively. It is important that these decisions be both well- 
informed and transparent because of the long-term funding consequences. 
DOD and congressional decision makers' ability to assess which elements 
can be fully developed, integrated, and operated relative to the others 
will be enhanced if they have the benefit of information based on more 
rigorous analysis than that contained in MDA's March 2006 report. 
Looking forward, as DOD strengthens its analyses to support future key 
decisions, DOD and congressional decision makers will be able to use 
more complete information to assess force structure, basing, support, 
and infrastructure requirements, as well as technical maturity, budget 
requests, and FYDP spending plans, in deciding whether or not to 
continue developing one, two, or all three boost and ascent phase 
elements and in what quantities. 

Recommendations for Executive Action: 

To provide decision makers with information that enables them to 
clearly understand the technical progress and operational implications 
of each boost and ascent phase element and make fully informed, fact- 
based, program decisions at future key decision points, we recommend 
that the Secretary of Defense direct the Under Secretary of Defense for 
Acquisition, Technology, and Logistics to take the following actions to 
support key decision points for the BMDS boost and ascent phase 
elements: 

* Include all DOD stakeholders (including services, combatant commands, 
Joint Staff) in developing and analyzing operational issues regarding 
what is needed to support operations at U.S. bases and potential 
forward locations, including basing assessments, force structure and 
quantity requirements, infrastructure, security/force protection, 
maintenance, and personnel. 

* Provide specific information on the technical progress of each 
element. Specifically, the analysis should explain current technical 
maturity versus desired technical maturity and capabilities of all 
major components and subsystems, reasonable model inputs on element 
performance, and provide a clear explanation of assumptions and their 
effect on results. 

* Use the results of these analyses at each key decision point. 

To provide decision makers with complete and reliable data on the costs 
of each boost/ascent phase BMDS element to enhance investment and 
budget decisions, we recommend that the Secretary of Defense take the 
following actions: 

* Direct the Under Secretary of Defense for Acquisition, Technology, 
and Logistics to require MDA to prepare and--to support key decision 
points--periodically update a full life-cycle cost estimate for each 
boost/ascent phase element, in accordance with key principles for 
developing accurate and reliable life-cycle cost estimates, that 
includes all operational costs, including costs to establish and 
sustain operations at U.S. bases and forward locations, and that is 
based on warfighter quantities, includes sensitivity analyses, and 
reflects time phasing. 

* Direct an independent group, such as the Cost Analysis Improvement 
Group, to prepare an independent life-cycle cost estimate for each 
capability at each key decision point. 

* Direct MDA and services to report independently verified life-cycle 
cost estimates along with budget requests and FYDP funding plans for 
each boost/ascent phase element. 

Agency Comments and Our Evaluation: 

In written comments on a draft of this report, DOD agreed with our 
recommendations regarding the need for analysis of technical progress 
and operational issues to support key boost and ascent phase element 
decision points. DOD also agreed that an independent life-cycle cost 
estimate may be needed to inform some key decision points while they 
may not be needed at other decision points. However, DOD did not agree 
to prepare and periodically update full life-cycle cost estimates for 
each boost and ascent phase element to support key decision points, and 
report independently verified life cycle cost estimates with budget 
requests and FYDP funding plans. As discussed below, we continue to 
believe our recommendations have merit and that DOD should take the 
additional actions we have recommended to provide a rigorous analytical 
basis for future decisions, enhance the transparency of its analyses, 
and increase accountability for key decisions that could involve 
billions of dollars. The department's comments are reprinted in their 
entirety in appendix II. 

DOD agreed with our recommendations that all DOD stakeholders be 
included in developing and analyzing operational issues, that specific 
information on technical progress be provided to explain current versus 
desired capabilities, and that the results of both analyses be used at 
key decision points. DOD stated in its comments that officials from 
MDA, the military departments, the combatant commanders, and other 
organizations are collaborating to develop an operational BMDS. 
Moreover, the annual BMDS Transition and Transfer Plan is coordinated 
with the service secretaries and other stakeholders and serves as a 
repository for plans, agreements, responsibilities, authorities, and 
issues. DOD also stated that key program decisions are and will 
continue to be informed by detailed technical analysis, including 
assessment of element technical maturity. However, DOD did not clearly 
explain how future decision making will be enhanced or how analyses of 
operational issues will be conducted if, as in the case of the Kinetic 
Energy Interceptor, DOD has not assigned a service responsibility for 
operating the element once it is developed. We continue to believe that 
DOD and congressional decision makers will need more complete 
information on support requirements at upcoming decision points as well 
as a clear comparison of current versus desired technical capabilities 
in deciding whether or not to continue developing one, two, or all 
three boost and ascent phase elements. 

Regarding our recommendations to improve cost estimates used to support 
key investment decisions, DOD partially concurred that independent life-
cycle cost estimates may be required to inform some key decision points 
but stated that other key decision points may not. However, DOD did not 
agree that it should routinely prepare and periodically update a full 
life-cycle cost estimate for each boost and ascent phase element. DOD 
said that it continuously assesses all aspects of its development 
efforts and will direct an independent evaluation of life- cycle costs 
for boost and ascent phase elements if circumstances warrant or if 
MDA's Director declares an element mature enough to provide a 
militarily useful capability. However, if, as DOD's comments suggest, 
such costs are not assessed until circumstances warrant or MDA's 
Director declares an element mature enough to provide a militarily 
useful capability, these costs may not be available early enough to 
help shape important program and investment decisions and consider 
trade-offs among elements. Moreover, DOD's Operating and Support Cost 
Estimating Guide, published by the Cost Analysis Improvement Group, 
states that when the Cost Analysis Improvement Group assists the Office 
of the Secretary of Defense components in their review of program 
costs, one purpose is to determine whether a new system will be 
affordable to operate and support.[Footnote 23] Therefore, such 
analysis must be done early enough to provide cost data that will be 
considered in making a decision to field, produce, or transition an 
element. We continue to believe our recommendation has merit because 
the development of life-cycle cost estimates that include potential 
operations and support costs would improve the information available to 
decision makers and increase accountability for key decisions that 
could involve billions of dollars at a time when DOD will likely face 
competing demands for resources. 

Finally, DOD did not agree to report independently verified life-cycle 
cost estimates along with budget requests and FYDP funding plans for 
each boost and ascent phase element. DOD stated that operations and 
support segments of the budget are organized by functional area rather 
than by weapon system and are dependent on operations and support 
concepts of the employing military department. DOD further stated that 
development of total life-cycle cost estimates for operational BMDS 
capabilities requires agreement between MDA and the lead military 
department on roles and responsibilities for fielded BMDS capabilities 
that transcend the annual transition planning cycle but serve as a 
basis for budget submittals. We recently reported that MDA enjoys 
flexibility in developing BMDS but this flexibility comes at the cost 
of transparency and accountability.[Footnote 24] One purpose of cost 
estimates is to support the budget process by providing estimates of 
the funding required to efficiently execute a program. Also, 
independent verification of cost estimates allows decision makers to 
gauge whether the program is executable. Thus, cost estimating is the 
basis for establishing and defending budgets and is at the heart of the 
affordability issue. This principle is stated in DOD procedures which 
specify that when cost results are presented to the Office of the 
Secretary of Defense Cost Analysis Improvement Group, the program 
office-developed life-cycle cost estimate should be compared with the 
FYDP and differences explained.[Footnote 25] Therefore, we continue to 
believe that our recommendation has merit because, without an 
independent cost estimate that can be compared to budget requests and 
FYDP funding plans, congressional decision makers may not have all the 
necessary information to assess the full extent of future resource 
requirements if the boost and ascent phase capabilities go forward, or 
assess the completeness of the cost estimates that are in the budget 
request and FYDP funding plans. 

We are sending copies of this report to the Secretary of Defense; the 
Commander, U.S. Strategic Command; the Director, Missile Defense 
Agency; Chairman, the Joint Chiefs of Staff; and the Chiefs of Staff of 
the Army, Navy, and Air Force. We will make copies available to others 
upon request. In addition, the report will be available at no charge on 
the GAO Web site at http://www.gao.gov. 

If you or your staff have any questions, please call either Janet St. 
Laurent on (202) 512-4402 or Paul Francis on (202) 512-2811. Contact 
points for our Offices of Congressional Relations and Public Affairs 
may be found on the last page of this report. Staff members who made 
key contributions to this report are listed in appendix III. 

Signed by: 

Janet A. St. Laurent: 
Director, Defense Capabilities and Management: 

Signed by: 

Paul L. Francis: 
Director, Acquisition, Sourcing, and Management: 

List of Committees: 

The Honorable Carl Levin: 
Chairman: 
The Honorable John McCain: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Daniel K. Inouye: 
Chairman: 
The Honorable Ted Stevens: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Ike Skelton: 
Chairman: 
The Honorable Duncan L. Hunter: 
Ranking Minority Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable John P. Murtha: 
Chairman: 
The Honorable C. W. Bill Young: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

[End of section] 

Appendix I: Scope and Methodology: 

During this review, we focused on assessing the analytical approach the 
Missile Defense Agency (MDA) used to develop its March 2006 report to 
Congress, as well as the methodology for developing the cost estimates 
for each of the three Ballistic Missile Defense System (BMDS) boost and 
ascent phase elements. 

To assess the extent to which the Department of Defense (DOD) is 
developing technical and operational information useful for oversight 
and that will support decision making at key points, we compared the 
analytical approach DOD used to develop its March 2006 report with 
generally accepted research standards that are relevant for defense 
studies such as this, that define a sound and complete study, and that 
cover all phases of a study--design, execution, and presentation of 
results. The following were our sources for these standards: 

* GAO, Government Auditing Standards: 2003 Revision, GAO-03-673G 
(Washington, D.C.: June 2003); 

* GAO, Designing Evaluations, GAO/PEMD-10.1.4 (Washington, D.C.: March 
1991); 

* GAO, Dimensions of Quality, GAO/QTM-94-1 (Washington, D.C.: February 
2004); 

* RAND Corporation, RAND Standards for High-Quality Research and 
Analysis (Santa Monica, Calif.: June 2004); 

* Air Force, Office of Aerospace Studies, Analysts Handbook: On 
Understanding the Nature of Analysis (January 2000); 

* Air Force, Office of Aerospace Studies, Air Force Analysis Handbook, 
A Guide for Performing Analysis Studies: For Analysis of Alternatives 
or Functional Solution Analysis (July 2004); 

* Department of Defense, DOD Modeling and Simulation (M&S) 
Verification, Validation, Accreditation (VV&A), Instruction 5000.61 
(Washington, D.C.: May 2003); 

* Department of Defense, Data Collection, Development, and Management 
in Support of Strategic Analysis, Directive 8260.1 (Washington, D.C.: 
Dec. 2, 2003); and: 

* Department of Defense, Implementation of Data Collection, 
Development, and Management for Strategic Analyses, Instruction 8260.2 
(Washington, D.C.: Jan. 21, 2003). 

For a more complete description of these standards and how we 
identified them, see GAO-06-938, appendix I.[Footnote 26] In applying 
these standards, we focused on the extent to which stakeholders were 
involved in study design and analysis as well as the extent to which 
assumptions were reasonable and their effects on results were clearly 
explained. We assessed MDA briefings that explained the modeling used 
for the technical analysis projecting the elements' capabilities. To 
assess the basis for the assumed performance parameters used to model 
each element's performance, we traced and verified a nonprobability 
sample of these parameters to their source documentation and concluded 
that they were generally supported. To evaluate the DOD report's 
characterization of threats, we reviewed Defense Intelligence Agency 
documents and discussed the type and capability of threats and expected 
BMDS capabilities with officials from the Office of the Secretary of 
Defense for Program Analysis and Evaluation and the Defense 
Intelligence Agency. In addition, to gain an understanding of the 
extent to which DOD has assessed warfighter quantities for the boost 
and ascent phase elements, the development of operational concepts, and 
operational implications of employing the boost and ascent phase 
elements at forward locations, we evaluated DOD and service guidance on 
assessing sites and support for new weapon systems and discussed these 
issues with officials from the Joint Staff; U.S. Army Headquarters and 
Space and Missile Defense Command; U.S. Strategic Command; the office 
of the Chief of Naval Operations Surface Warfare Directorate, Ballistic 
Missile Defense Division; Air Combat Command; and the office of the 
Secretary of the Air Force for Acquisition, Global Power Directorate. 
Finally, we discussed the results of all our analyses with officials in 
the Joint Staff; U.S. Strategic Command; the Army's Space and Missile 
Defense Command; Office of the Secretary of Defense for Acquisition, 
Technology, and Logistics; Missile Defense Agency; the office of the 
Chief of Naval Operations Surface Warfare Directorate, Ballistic 
Missile Defense Division; the office of the Secretary of the Air Force 
for Acquisition Global Power Directorate; and Air Combat Command. 

To assess the extent to which DOD presented cost information to 
Congress that is complete and transparent, we first assessed how MDA 
developed its estimates and then compared the method by which those 
estimates were prepared to key principles compiled from various DOD and 
GAO sources that describe how to develop accurate and reliable life- 
cycle cost estimates to determine their completeness and the extent to 
which DOD took steps to assess confidence in the estimates. The 
following were our sources for compiling the cost criteria: 

* Department of Defense, Assistant Secretary of Defense (Program 
Analysis and Evaluation), Cost Analysis Guidance and Procedures, DOD 
Manual 5000.4-M (December 1992); 

* Department of Defense, Office of the Secretary of Defense Cost 
Analysis Improvement Group, Operating and Support Cost Estimating Guide 
(May 1992); 

* Department of Defense, Defense Acquisition University, Defense 
Acquisition Guidebook (online at http://akss.dau.mil/dag); 

* Department of Defense, Defense Acquisition University, Introduction 
to Cost Analysis (April 2006); 

* Air Force, Office of Aerospace Studies, Air Force Analysis Handbook: 
A Guide for Performing Analysis Studies for Analysis of Alternatives or 
Functional Solution Analysis (July 2004); 

* Air Force, Base Support and Expeditionary Site Planning, Air Force 
Instruction 10-404 (March 2004); and: 

* GAO, GAO Cost Assessment Guide (currently under development). 

In addition, we met with DOD officials from MDA, U.S. Strategic 
Command, the Joint Staff, Army, Navy and Air Force to determine the 
extent to which they were involved in developing the cost estimates for 
the DOD report. Finally, we corroborated our methodology and results 
with officials from the Office of the Under Secretary of Defense, 
Program, Analysis and Evaluation (Cost Analysis Improvement Group) and 
the Office of the Under Secretary of Defense (Comptroller) and they 
agreed that our methodology for examining the report's cost estimates 
was reasonable and consistent with key principles for developing 
accurate and reliable life-cycle cost estimates. We identified some 
data limitations with the cost estimates which we discuss in this 
report. 

We provided a draft of this report to DOD for its review and 
incorporated its comments where appropriate. Our review was conducted 
between June 2006 and February 2007 in accordance with generally 
accepted government auditing standards. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
3000 Defense Pentagon Washington, DC 20301-3000: 
Acquisition, Technology And Logistics: 

Mar 28 8 2007: 

Ms. Janet St. Laurent: 
Director, Defense Capabilities and Management: 
U. S. Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

Dear Ms. St. Laurent: 

This is the Department of Defense (DoD) response to the GAO Draft 
Report GAO-07-430, "Missile Defense: Actions Needed to Improve 
Information for Supporting Future Key Decisions for Boost and Ascent 
Phase Elements," dated February 28, 2007 (GAO Code 350861). 

The DoD concurs with three, partially concurs with one, and non-concurs 
with two of the draft report's recommendations. The rationale for our 
position is included in the enclosure. 

We appreciate the opportunity to comment on the draft report. My point 
of contact for this effort is Mr. David Crim, (703) 697-5385, 
David.Crim@osd.mil: 

Sincerely, 

Signed by: 

Dave G. Ahern: 
Director: 
Portfolio Systems Acquisition: 

Enclosure: 
As stated: 

GAO Draft Report - Dated February 28, 2007 GAO Code 350861/GAO-07-430: 

"Missile Defense: Actions Needed to Improve Information for Supporting 
Future Key Decisions for Boost and Ascent Phase Elements" 

Department Of Defense Comments To The Recommendation: 

Recommendation 1: The GAO recommended that the Secretary of Defense 
direct the Under Secretary of Defense for Acquisition, Technology, and 
Logistics to include all DoD stakeholders (including services, 
combatant commands, Joint Staff) in developing and analyzing 
operational issues regarding what is needed to support operations at 
U.S. bases and potential forward locations, including basing 
assessments, force structure and quantity requirements, infrastructure, 
security/force protection; maintenance, and personnel, for the 
Ballistic Missile Defense System (BMDS) boost and ascent phase 
elements. (Page 21/GAO Draft Report): 

DoD Response: Concur. As reported in the DoD Report to Congress on 
Transition of Ballistic Missile Defense Programs to the Military 
Departments for 2007, the DoD has made significant progress in planning 
for the transition of operating and support responsibilities and 
authorities for elements of the BMDS to the Military Departments. 
Members of the Missile Defense Agency (MDA), the Military Departments, 
the Combatant Commands, the Joint Staff, and the Office of the 
Secretary of Defense are collaborating by way of an Integrated Product 
Team (IPT) to operationalize the BMDS. This Transition and Transfer IPT 
produces an annual DoD document referred to as the BMDS Transition and 
Transfer Plan (T&TP) that serves as a repository for plans, agreements, 
responsibilities, authorities, and issues. The T&TP is submitted by MDA 
to USD(AT&L) annually on March l, and then coordinated with Service 
Secretaries and other stakeholders, and, with regards to 
operationalizing the BMDS, serves as the basis for MDA and Service 
budget formulation. 

Recommendation 2: The GAO recommended that the Secretary of Defense 
direct the Under Secretary of Defense for Acquisition, Technology, and 
Logistics to provide specific information on the technical progress of 
each BMDS boost and ascent phase element to support key decision 
points. Specifically, the analysis should explain current technical 
maturity of all major components and subsystems in comparison to 
desired technical maturity, reasonable model inputs on element 
performance, and a clear explanation of assumptions and their effect on 
results. (Page 21/GAO Draft Report): 

DoD Response: Concur. Key program decisions are and will continue to be 
informed by detailed technical analysis, including assessments of 
element technical maturity, and any sensitivity of element performance 
estimates to the models and simulations used. 

Recommendation 3: The GAO recommended that the Secretary of Defense 
direct the Under Secretary of Defense for Acquisition, Technology, and 
Logistics to use the results of these analyses at each key decision 
point for the BMDS boost and ascent phase elements. (Page 21 /GAO Draft 
Report): 

DoD Response: Concur. Key program decisions are and will continue to be 
informed by detailed technical analysis, including assessments of 
element technical maturity, and any sensitivity of element performance 
estimates to the models and simulations used. 

Recommendation 4: The GAO recommended that the Secretary of Defense 
direct the Under Secretary of Defense for Acquisition, Technology, and 
Logistics to require the Missile Defense Agency (MDA) to prepare and 
periodically update a full life cycle cost estimate for each boost/ 
ascent phase element, in accordance with key principles for developing 
accurate and reliable life cycle cost estimates, that includes all 
operational costs, including costs to establish and sustain operations 
at U.S. bases and forward locations, is based on warfighter quantities, 
includes sensitivity analyses, and reflects time phasing. (Pages 21-22/ 
GAO Draft Report): 

DoD Response: Non-concur. As noted in the DoD Report to Congress on 
Transition of Ballistic Missile Defense Programs to the Military 
Departments for 2007, DoD guidance directs that BMDS elements be 
managed in three phases: development; transition, and procurement and 
operations. The Director, MDA is to manage the BMDS through the 
development and transition phases, baseline the capability and 
configuration of each element and capability block, and define 
interoperability standards. The Military Departments provide forces, as 
needed, to support fielding of early and or contingency capability. 
During early fielding and the transition phase, responsibilities are 
shared by MDA and the Military Departments; specific responsibilities 
and authorities are documented in the T&TP, agreed to by MDA and the 
Military Departments, and subsequently programmed for by the applicable 
Department or Agency. Beyond early fielding and or transition, and 
after an appropriate milestone decision, the Military Departments will 
provide resources to procure and support the transitioned elements as 
programs in their own right and as reflected by the planned force 
structure. DoD continuously assesses all aspects of its developments 
and will direct an independent evaluation of life cycle costs for boost 
and ascent phase elements if circumstances warrant or the Director, MDA 
declares an element mature enough to provide a militarily useful 
capability. In making this declaration, the Director, MDA will rely on 
all data available, including available cost estimates. These estimates 
will be refined in conjunction with designated lead Military 
Departments as part of the Transition and Transfer IPT and documented 
in the T&TP plan. 

Recommendation 5: The GAO recommended that the Secretary of Defense 
direct an independent group, such as the Cost Analysis Improvement 
Group, to prepare an independent Life Cycle Cost Estimate for each 
capability at each key decision point. Pages 21-22/GAO Draft Report): 

DoD Response: Partially concur. While some of the key decision points 
may require independent life cycle cost estimates, others may not. As 
noted in the DoD Response to Recommendation 4 above, the Director, MDA 
may declare an element mature enough to provide a militarily useful 
capability. Based upon this recommendation, DoD will determine if that 
capability is ready to begin early fielding or proceed to a milestone 
review. DoD stakeholders will rely on independent life cycle cost 
estimates to inform these and other key decisions as applicable. 

Recommendation 6: The GAO recommended that the Secretary of Defense 
direct MDA and the Military Services to report independently verified 
life cycle cost estimates along with budget requests and Future Years 
Defense Plan (FYDP) funding plans for each boost/ascent phase element. 
(Pages 21-22/GAO Draft Report): 

DoD Response: Non-concur. Operations and support segments of the budget 
are organized by functional area rather than by weapon system. The 
functional areas are characterized by personnel, unit-level 
consumption, various levels of maintenance, sustaining support, and 
indirect support costs. Although the costs of certain elements (such as 
personnel) can often be identified explicitly, other elements may be 
common to more than one weapon system and are dependent on operations 
and support concepts of the employing Military Department. The cost of 
these latter elements may be allocated among respective systems and 
support organizations. Development of total life cycle cost estimates 
for operationalized BMDS capabilities requires agreement between MDA 
and lead Military Departments on roles and responsibilities for fielded 
missile defense capabilities. The T&TP, updated annually or as 
significant changes warrant, constitutes a "snapshot" of a work-in- 
progress intended to capture current BMDS capability transition status, 
roles, responsibilities, and future transition plans for the components 
and elements of the BMDS. The annual snapshot is taken with the 
intention of clarifying roles and responsibilities and documenting 
agreements between the Military Departments and MDA. These agreements 
cover responsibilities, deliverables, funding, and schedules that 
transcend the annual BMDS transition plan cycle. The T&TP is submitted 
early enough in the Programming Planning and Budgeting Cycle so that it 
can be used by MDA and the Services as a basis for their BMDS budget 
submittals and to provide needed insights into estimated life cycle 
costs of BMDS capabilities. 

[End of section] 

Appendix III: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Janet A. St. Laurent, (202) 512-4402, stlaurentj@gao.gov: 

Paul L. Francis, (202) 512-2811, francisp@gao.gov: 

Acknowledgments: 

In addition to the individuals named above, Barbara H. Haynes and 
Gwendolyn R. Jaffe, Assistant Directors; Brenda M. Waterfield; Todd 
Dice; Jeffrey R. Hubbard; Nabajyoti Barkakati; Hai V. Tran; Ron La Due 
Lake; and Susan C. Ditto made key contributions to this report. 

[End of section] 

Related GAO Products: 

Defense Transportation: Study Limitations Raise Questions about the 
Adequacy and Completeness of the Mobility Capabilities Study and 
Report. GAO-06-938. Washington, D.C.: September 20, 2006. 

Defense Management: Actions Needed to Improve Operational Planning and 
Visibility of Costs for Ballistic Missile Defense. GAO-06-473. 
Washington, D.C.: May 31, 2006. 

Defense Acquisitions: Missile Defense Agency Fields Initial Capability 
but Falls Short of Original Goal. GAO-06-327. Washington, D.C.: March 
15, 2006. 

Defense Acquisitions: Actions Needed to Ensure Adequate Funding for 
Operation and Sustainment of the Ballistic Missile Defense System. GAO- 
05-817. Washington, D.C.: September 6, 2005. 

Military Transformation: Actions Needed by DOD to More Clearly Identify 
New Triad Spending and Develop a Long-term Investment Approach. GAO-05- 
962R. Washington, D.C.: August 4, 2005. 

Military Transformation: Actions Needed by DOD to More Clearly Identify 
New Triad Spending and Develop a Long-term Investment Approach. GAO-05- 
540. Washington, D.C.: June 30, 2005. 

Defense Acquisitions: Status of Ballistic Missile Defense Program in 
2004. GAO-05-243. Washington, D.C.: March 31, 2005. 

Future Years Defense Program: Actions Needed to Improve Transparency of 
DOD's Projected Resource Needs. GAO-04-514. Washington, D.C.: May 7, 
2004. 

Missile Defense: Actions Are Needed to Enhance Testing and 
Accountability. GAO-04-409. Washington, D.C.: April 23, 2004. 

Missile Defense: Actions Being Taken to Address Testing 
Recommendations, but Updated Assessment Needed. GAO-04-254. Washington, 
D.C.: February 26, 2004. 

Missile Defense: Additional Knowledge Needed in Developing System for 
Intercepting Long-Range Missiles. GAO-03-600. Washington, D.C.: August 
21, 2003. 

Missile Defense: Alternate Approaches to Space Tracking and 
Surveillance System Need to Be Considered. GAO-03-597. Washington, 
D.C.: May 23, 2003. 

Missile Defense: Knowledge-Based Practices Are Being Adopted, but Risks 
Remain. GAO-03-441. Washington, D.C.: April 30, 2003. 

Missile Defense: Knowledge-Based Decision Making Needed to Reduce Risks 
in Developing Airborne Laser. GAO-02-631. Washington, D.C.: July 12, 
2002. 

Missile Defense: Review of Results and Limitations of an Early National 
Missile Defense Flight Test. GAO-02-124. Washington, D.C.: February 28, 
2002. 

Missile Defense: Cost Increases Call for Analysis of How Many New 
Patriot Missiles to Buy. GAO/NSIAD-00-153. Washington, D.C.: June 29, 
2000. 

Missile Defense: Schedule for Navy Theater Wide Program Should Be 
Revised to Reduce Risk. GAO/NSIAD-00-121. Washington, D.C.: May 31, 
2000. 

FOOTNOTES 

[1] The boost phase is the period immediately after launch when the 
missile's booster stages are still thrusting. Next is the ascent phase 
which ends when the ballistic missile completes deployment of reentry 
vehicles and possible decoys. 

[2] Other versions of the Standard Missile-3 are being developed to 
intercept threat missiles in their midcourse phase. 

[3] GAO, Budget Process: Long-term Focus Is Critical, GAO-04-585T 
(Washington, D.C.: Mar. 23, 2004). 

[4] GAO, 21st Century Challenges: Reexamining the Base of the Federal 
Government, GAO-05-325SP (Washington, D.C.: February 2005). 

[5] Although there are other interim decision points leading up to the 
lethal shootdown demonstration, MDA officials stated that the 2009 key 
decision point is one where decisions may be made about the future of 
the Airborne Laser program. 

[6] H.R. Rep. No. 109-119 (2005). 

[7] Pub.L. No. 109-163, § 231 (2005). 

[8] While the House Appropriations Committee report originally directed 
us to conduct a joint study with DOD, we agreed with the Defense 
Subcommittee, House Appropriations Committee that, in lieu of a joint 
study, we would assess the Missile Defense Agency's March 2006 report 
on boost and ascent phase capabilities. 

[9] In a September 2006 report, GAO identified frequently occurring, 
generally accepted research standards that are relevant for defense 
studies and define a sound and complete study. GAO, Defense 
Transportation: Study Limitations Raise Questions about the Adequacy 
and Completeness of the Mobility Capabilities Study and Report, GAO-06-
938 (Washington, D.C.: Sept. 20, 2006). Also, see app. I for a more 
complete description of our scope and methodology. 

[10] GAO, Defense Acquisitions: Missile Defense Agency Fields Initial 
Capability but Falls Short of Original Goals, GAO-06-327 (Washington, 
D.C.: Mar. 15, 2006). 

[11] GAO, Missile Defense: Knowledge-Based Practices Are Being Adopted, 
but Risks Remain, GAO-03-441 (Washington, D.C.: Apr. 30, 2003). 

[12] GAO, Defense Management: Actions Needed to Improve Operational 
Planning and Visibility of Costs for Ballistic Missile Defense, GAO-06-
473 (Washington, D.C.: May 31, 2006). 

[13] The boost phase is the period immediately after launch when the 
missile's booster stages are still thrusting and typically lasts 3-5 
minutes for intercontinental ballistic missiles. The ascent phase is 
when the booster stages have stopped thrusting and dropped away leaving 
a warhead and possible decoys. The midcourse phase, lasting for about 
20 minutes, begins after the missile has stopped accelerating and the 
warhead travels through space on a predictable path. The final or 
terminal phase begins when the warhead reenters the atmosphere and 
lasts approximately a minute or less. 

[14] H.R. Rep. No. 109-119 (2005). 

[15] For most major acquisition programs, DOD prepares a life-cycle 
cost estimate that is independently verified for major program reviews. 
A life-cycle cost includes all costs associated with a weapon system's 
research and development, investment, which includes military 
construction, operations and support, and disposal. 

[16] The model, called WILMA, supports quantitative evaluation of 
ballistic missile defense system performance in terms of probabilities 
of success. 

[17] Technology Readiness Levels are measured on a scale of 1-9, 
beginning with paper studies of a technology's feasibility (level 1) 
and culminating with a technology fully integrated into a completed 
product (level 9). 

[18] The criteria for developing accurate and reliable life-cycle cost 
estimates were compiled from several sources including the DOD Manual 
5000.4-M Cost Analysis Guidance and Procedures, the Defense Acquisition 
Guidebook, and an exposure draft of GAO's Cost Assessment Guide. See 
app. I for a more complete description of our scope and methodology. 

[19] As we reported in GAO-05-817, independent cost estimates are 
normally first required for Milestone B, the decision to enter system 
development and demonstration. GAO, Defense Acquisitions: Actions 
needed to Ensure Adequate Funding for Operation and Sustainment of the 
Ballistic Missile Defense System, GAO-05-817 (Washington, D.C.: Sept. 
6, 2005). However, because BMDS elements do not enter DOD's acquisition 
cycle until Milestone C, the requirements under Section 2434 of Title 
10 may not be applied to the BMDS until the transition phase that leads 
to the transfer to a military service. However, developing cost 
estimates using the key principles that we describe for developing 
accurate and reliable life-cycle cost estimates would provide useful 
information to DOD decision makers and Congress. 

[20] As we reported in GAO-05-817, independent cost estimates are 
normally first required for Milestone B, the decision to enter system 
development and demonstration. However, because BMDS elements do not 
enter DOD's acquisition cycle until Milestone C, the requirements under 
Section 2434 of Title 10 may not be applied to the BMDS until the 
transition phase that leads to the transfer to a military service. 
However, developing cost estimates using the key principles that we 
describe for developing accurate and reliable life-cycle cost estimates 
would provide useful information to DOD decision makers and Congress. 

[21] GAO-03-441. 

[22] H.R. Rep. No. 109-452 (2006). 

[23] DOD, Office of the Secretary of Defense Cost Analysis Improvement 
Group, Operating and Support Cost Estimating Guide (May 1992). 

[24] GAO, Defense Acquisitions: Missile Defense Acquisition Strategy 
Generates Results but Delivers Less at a Higher Cost, GAO-07-387 
(Washington, D.C.: Mar. 15, 2007). 

[25] DOD, Assistant Secretary of Defense (Program Analysis and 
Evaluation), Cost Analysis Guidance and Procedures, DOD 5000.4-M 
(December 1992). 

[26] GAO, Defense Transportation: Study Limitations Raise Questions 
about the Adequacy and Completeness of the Mobility Capabilities Study 
and Report, GAO-06-938 (Washington, D.C.: Sept. 20, 2006). 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: