This is the accessible text file for GAO report number GAO-07-546 
entitled 'Defense Acquisitions: Status and Challenges of Joint Forces 
Command's Limited Acquisition Authority' which was released on April 
13, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 

GAO: 

April 2007: 

Defense Acquisitions: 

Status and Challenges of Joint Forces Command's Limited Acquisition 
Authority: 

GAO-07-546: 

GAO Highlights: 

Highlights of GAO-07-546, a report to congressional committees 

Why GAO Did This Study: 

Over 3 years ago, Congress granted limited acquisition authority 
(LAA)—subject to delegation by the Secretary of Defense—to U.S. Joint 
Forces Command (JFCOM) for a 3-year period to expedite development and 
acquisition of certain warfighter equipment. Congress directed GAO to 
report on JFCOM LAA implementation. GAO’s report, issued in November 
2005, said JFCOM finished five LAA projects and was working on a sixth 
project, and that JFCOM had experienced difficulty finding funding to 
develop, acquire, and sustain LAA projects. Last year, Congress 
extended LAA through September 2008 and again directed GAO to report on 
LAA. This report updates the status of JFCOM LAA efforts since the 
authority was enacted and key LAA challenges. 

What GAO Found: 

JFCOM has not approved any LAA projects since GAO’s November 2005 
report, and the LAA project that was incomplete as of then remains so. 
The projects generally fall under the category of battle management 
command, control, communications, and intelligence. Research funding 
provided for the six LAA projects has risen from $9 million in 2005 to 
$14 million as of January 2007. No procurement funds had been used for 
these projects as of then. Feedback from the projects’ recipients—the 
warfighter—has been mostly positive about the LAA acquisition process 
and capabilities delivered. 

The Department of Defense (DOD) and JFCOM face several LAA challenges, 
one of which goes to the role of LAA. Shortly after LAA’s enactment, 
the Deputy Secretary of Defense created the JRAC to provide timely 
solutions for joint urgent warfighter needs. GAO analysis indicates 
that JRAC and JFCOM LAA cover similar ground and could overlap even 
more if JRAC is allowed to address needs other than for ongoing named 
operations. JRAC might have also been able to carry out most, if not 
all, of the six LAA projects had it existed when they were approved by 
JFCOM. The following table shows key aspects of the two processes. 

Table: Key Aspects of JFCOM LAA and JRAC Rapid Acquisition Current 
Processes: 

Is it to address joint urgent needs?; JFCOM LAA: Yes; 
JRAC: Yes. 

In what time frae are needs to be met?; JFCOM LAA: Within 2 years; 
JRAC: Within 2 years. 

Can solution already be in development?; JFCOM LAA: Yes; 
JRAC: Yes. 

Must the need be for an ongoing, named operation?; JFCOM LAA: No; 
JRAC: Yes. 

Must the need be to prevent loss of life or mission failure?; JFCOM 
LAA: No; 
JRAC: Yes. 

Is the need to be submitted by a combatant commander?; JFCOM LAA: Yes; 
JRAC: Yes. 

Is there a dollar limit per project for research funding?; JFCOM LAA: 
Yes, estimated to be less than $ 10 million; JRAC: Yes, $365 million or 
less in fiscal year 2000 dollars. 

Is there a dollar limit per project for procurement funding?; JFCOM 
LAA: Yes, estimated to be less $50 million; JRAC: Yes, $2.19 billion or 
less in fiscal year 2000 dollars. 

Source: GAO analysis of JFCOM LAA and JRAC processes. 

[End of table] 

Other challenges relate to how LAA is managed and operated. JFCOM 
officials said funding remains an issue because LAA is an authority 
without budgeted funds. JFCOM LAA staff tries to find funding for 
approved projects from other DOD organizations. When funding could not 
be found, JFCOM funded most of the six LAA projects with funds budgeted 
for other JFCOM work. The search for funding lengthens the time to get 
capabilities to the warfighter. JRAC does not have budgeted funds 
either, but has greater access to funding than JFCOM. Another challenge 
involves uncertainty between JFCOM and the Office of the Secretary of 
Defense regarding what LAA powers were delegated to JFCOM. Until the 
uncertainty is resolved, how JFCOM should carry out LAA efforts will 
remain unclear. 

What GAO Recommends: 

GAO recommends that the Secretary of Defense reassess the role of JFCOM 
LAA in light of changes contemplated for the Joint Rapid Acquisition 
Cell (JRAC) process, to determine whether and how JFCOM LAA should play 
a role in meeting joint urgent needs; to the extent JFCOM LAA is to 
continue to play a role, assess and resolve the challenges identified 
in this report; and inform Congress of the results of the assessment 
and decisions. DOD concurred with GAO’s recommendations. GAO added a 
matter for congressional consideration regarding the timing of the 
congressional decision on the future of JFCOM LAA. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-546]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Paul L. Francis at (202) 
512-4841 or francisp@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

No JFCOM LAA Projects Approved since Prior GAO Report: 

DOD and JFCOM Face Several Challenges with LAA: 

Conclusions: 

Recommendations for Executive Action: 

Matter for Congressional Consideration: 

Agency Comments: 

Appendix I: Scope and Methodology: 

Appendix II: Comments from the Department Of Defense: 

Tables: 

Table 1: JFCOM LAA Proposals Received and Approved by Fiscal Year since 
LAA Was Enacted: 

Table 2: Status of Six Approved LAA Projects: 

Table 3: Warfighter Feedback from GAO Questionnaire about LAA Projects: 

Table 4: GAO Analysis of Key Aspects of the LAA and JRAC Rapid 
Acquisition Current Processes: 

Abbreviations: 

DOD: Department of Defense: 
JFCOM: U.S. Joint Forces Command: 
JRAC: Joint Rapid Acquisition Cell: 
LAA: limited acquisition authority: 

United States Government Accountability Office: 
Washington, DC 20548: 

April 12, 2007: 

The Honorable Carl Levin: 
Chairman: 
The Honorable John McCain: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Ike Skelton: 
Chairman: 
The Honorable Duncan L. Hunter: 
Ranking Minority Member: 
Committee on Armed Services: 
House of Representatives: 

In fiscal year 2004, Congress provided statutory authority by which the 
Secretary of Defense may delegate limited acquisition authority (LAA) 
to the U.S. Joint Forces Command (JFCOM) to enable the commander to 
develop and acquire certain equipment to meet joint warfighting needs. 
The authority, which does not come with associated funding, was enacted 
for a 3-year period through September 30, 2006. When LAA was enacted, 
Congress directed GAO to report on JFCOM's implementation of LAA. Our 
report, issued in November 2005,[Footnote 1] stated that during fiscal 
years 2004 and 2005, JFCOM had undertaken six LAA projects, five of 
which had been completed and a sixth that was ongoing. We also reported 
that JFCOM faced challenges, including finding funding to develop, 
acquire, and sustain LAA projects. Since then, Congress has extended 
LAA[Footnote 2] through the end of September 2008. As part of that 
extension, Congress directed us to report again this year on JFCOM's 
implementation of LAA. As agreed with your staff, we provided briefings 
in December 2006 and January 2007 to satisfy that requirement. We also 
agreed to provide a subsequent written report. Accordingly, this report 
updates the (1) status of JFCOM's LAA efforts since the authority was 
enacted and (2) key challenges facing LAA's continued implementation. 

To address these objectives, we obtained and analyzed key documents and 
interviewed officials from a variety of Department of Defense (DOD) 
organizations. To describe JFCOM's LAA efforts since the authority was 
enacted, we met with JFCOM officials in Norfolk, Virginia, and 
collected relevant documentation. We developed and used a questionnaire 
to obtain feedback from warfighters who had been involved with LAA 
projects and used LAA capabilities in Iraq, Afghanistan, and countries 
in Europe. We interviewed military officials at military facilities in 
Florida, Massachusetts, New Jersey, North Carolina, Virginia, and 
Pennsylvania. To identify key challenges since LAA's enactment, we 
interviewed JFCOM officials, officials representing three organizations 
within the Office of the Under Secretary of Defense (Acquisition, 
Technology, and Logistics), other officials in the Office of the 
Secretary of Defense, Joint Staff/J-8 officials, and officials from the 
Army Rapid Equipping Force about the Army's rapid acquisition process. 
We examined pertinent information about the Joint Rapid Acquisition 
Cell (JRAC), a rapid acquisition process recently created within the 
Office of the Secretary of Defense. However, we did not conduct an in-
depth evaluation of JRAC or the JRAC process. We also obtained and 
analyzed various documents and interviewed officials about JFCOM LAA's 
policy and procedures and communicated with warfighters, contracting 
personnel, and officials with selected project offices about challenges 
with LAA. For additional details on how we performed our review, see 
appendix I. We conducted our work from July 2006 to March 2007 in 
accordance with generally accepted government auditing standards. 

Results in Brief: 

JFCOM has not approved any new LAA projects since our November 2005 
report was issued. The LAA project that was ongoing at that time 
remains ongoing, with additional development remaining. It is unclear 
why LAA activity has slowed down recently, although a JFCOM LAA 
official attributed the slowdown, in part, to the lack of associated 
funding for LAA. Funding otherwise obtained for the six approved LAA 
projects totaled $14 million in research, development, test, and 
evaluation funds as of January 2007--up from $9 million in 2005. No 
procurement funds had been used for these projects as of January 2007. 
JFCOM officials believe that LAA has been beneficial. Rather than have 
warfighters wait for "100 percent" solutions, JFCOM delivered interim 
joint solutions more quickly to meet urgent needs. We contacted 
recipients of capabilities for the five completed projects; the 
recipients who responded for four projects cited a positive experience 
using the LAA process and with the utility and effectiveness of the 
delivered capabilities. Also, DOD officials stated that LAA has been 
valuable in the war on terror. 

DOD and JFCOM face several challenges with LAA's continued 
implementation. One challenge goes to the role of LAA. Specifically, 
the goals of JFCOM's LAA efforts share a number of similarities with 
those of the Office of the Secretary of Defense-created JRAC, which 
came into existence within 10 months of JFCOM's LAA. Both the JFCOM LAA 
and JRAC processes seek to provide timely solutions for joint urgent 
warfighter needs. It is conceivable that most, if not all, of the six 
LAA projects could have been carried out through JRAC. Other challenges 
go to the mechanics of LAA itself. It is an authority, not an 
acquisition program, and comes with no budgeted funds. Although JRAC 
does not have budgeted funds either, it has greater access to funding 
than JFCOM. The JFCOM LAA staff has sometimes invested substantial 
amounts of time to obtain funding for the projects. Finding funding 
adds to the time it takes to get new capabilities to the warfighter. In 
the end, most of the funding to develop and acquire the first six 
projects came from JFCOM's own non-LAA budget, which does not provide 
for any LAA needs. Furthermore, after an LAA capability is delivered, 
an obligation arises to pay for sustaining it over time, but the LAA 
statute does not specifically provide authority to use operations and 
maintenance funding to sustain such projects. Another challenge to the 
mechanics of LAA involves uncertainty as to the exact nature of the LAA 
delegation to JFCOM by the Office of the Secretary of Defense. 
Specifically, while it is clear that a full delegation of LAA was not 
made under the statute, it is unclear exactly what powers were 
delegated to JFCOM and under which legal authorities--the LAA statute 
or other authorities available to the Secretary of Defense--those 
powers were provided. Failure to clarify these issues may impair 
JFCOM's ability to carry out LAA efforts. Last, since our prior report, 
JFCOM has established procedures to systematically assess the 
effectiveness of capabilities fielded from LAA projects, but with no 
LAA projects approved since then, the procedures have not yielded 
additional data. 

We are making recommendations to the Secretary of Defense to reassess 
the role of the JFCOM LAA in light of the expanding JRAC process, and 
determine whether and how JFCOM LAA should play a role in meeting joint 
urgent needs; to the extent JFCOM LAA is to continue to play a role in 
meeting joint urgent needs, assess and resolve, as appropriate, the 
funding, coordination, and delegation challenges identified in this 
report; and inform Congress of the results of the assessment and any 
resultant decisions in time for Congress to consider them in its 
deliberations on the National Defense Authorization Act for Fiscal Year 
2008. 

In written comments on a draft of this report, DOD concurred with our 
recommendations. DOD stated that it would reassess the role of JFCOM 
LAA in light of the expanding JRAC process and consider the other 
issues identified in this report as a part of that effort. DOD expects 
to complete that reassessment by the fourth quarter of 2007. DOD also 
stated that it would inform Congress of the result of that assessment 
and any associated decisions. 

In light of our recommendations, DOD's comments, and the fact that DOD 
has provided Congress with a fiscal year 2008 legislative proposal that 
would make the LAA statute permanent, we have added a matter for 
congressional consideration to this report because we believe that 
Congress might want to delay its consideration of making JFCOM LAA 
permanent until DOD has informed Congress of the results of the 
recommended assessment and any associated decisions. This should not 
impair JFCOM LAA, as DOD plans to complete its assessment by the fourth 
quarter of 2007 and LAA, as currently enacted, extends through 
September 2008. 

Background: 

JFCOM is one of nine DOD combatant commands and has multiple missions, 
including leading joint force transformation within DOD with the aid of 
joint warfighting concepts and capabilities to enhance interoperability 
for the combatant commands. The National Defense Authorization Act for 
Fiscal Year 2004 granted LAA to JFCOM, subject to delegation by the 
Secretary of Defense. The intent behind this LAA is to address measures 
to meet urgent, unanticipated joint warfighting needs are conceived, 
developed, and fielded in an expeditious manner. The LAA statute 
specifically refers to equipment for the following purposes: 

* battle management command, control, communications, and intelligence; 

* any other equipment that the JFCOM commander determines is necessary 
and appropriate to facilitate the use of joint forces in military 
operations or enhance the interoperability of equipment used by the 
various components of joint forces. 

The statute limits the equipment to total expenditures per system 
estimated to be less than $10 million for research, development, test, 
and evaluation, or estimated to be less than $50 million for 
procurement. 

DOD's traditional acquisition process, which involves much larger 
budgets and longer time frames, generally serves to meet less 
immediate, material warfighter needs, that is, 2 years and beyond. 
Frequently, more urgent needs arise, and several rapid acquisition 
processes are available to handle such needs. JFCOM's LAA is one of 
these processes. Another is a process defined in Chairman of the Joint 
Chiefs of Staff Instruction 3470.01,[Footnote 3] which is principally 
managed by JRAC. Like JFCOM's LAA, the JRAC process addresses joint, 
urgent needs. Each military service has its own rapid acquisition 
process, but those processes focus on addressing the urgent needs of 
each respective service, and may not address the joint needs of the 
combatant commands. In addition, the Joint Improvised Explosive Device 
Defeat Organization[Footnote 4] and the U.S. Special Operations 
Command[Footnote 5] have their own acquisition processes. 

No JFCOM LAA Projects Approved since Prior GAO Report: 

Very little has changed with regard to usage of JFCOM's LAA since our 
November 2005 report was issued. It is not clear why the activity on 
LAA has slowed down during the past 19 months, although JFCOM officials 
believe one of the reasons is due to the fact that the authority does 
not have associated funding. Combatant commands are dissuaded from 
using LAA when they find out JFCOM does not already have funding and 
must obtain it for LAA projects, according to a JFCOM LAA official. 
Since LAA's enactment over 3 years ago, JFCOM has received 12 LAA 
proposals and approved 6. Table 1 summarizes the number of proposals 
received and approved since LAA's enactment. 

Table 1: JFCOM LAA Proposals Received and Approved by Fiscal Year since 
LAA Was Enacted: 

Fiscal year: 2004; 
Proposals received: 5; 
Proposals approved: 2. 

Fiscal year: 2005; 
Proposals received: 3; 
Proposals approved: 4[A]. 

Fiscal year: 2006; 
Proposals received: 4; 
Proposals approved: 0. 

Fiscal year: 2007 (through 1/2007); 
Proposals received: 0; 
Proposals approved: 0. 

Total; 
Proposals received: 12; 
Proposals approved: 6. 

Source: JFCOM data and GAO analysis. 

[A] One LAA proposal that was received in fiscal year 2004 was not 
approved until fiscal year 2005. 

[End of table] 

JFCOM has not received any LAA proposals so far in fiscal year 2007. In 
fiscal year 2006, JFCOM received four proposals--three are still under 
consideration and one was referred to JRAC. Fifteen months have elapsed 
since one of the proposals was submitted, but the JFCOM commander has 
not yet decided whether to accept or reject it. JFCOM merged two other 
LAA proposals because they involved the same requested need by two 
combatant commands. Although these two proposals were submitted in 
October 2005 and March 2006, they have not been approved because JFCOM 
officials have been trying to settle on a solution that will be 
compatible with several other non-LAA-related DOD efforts. These 
particular proposals are needed to enable exchange of secure, but 
unclassified, information between U.S. and coalition forces. JFCOM 
forwarded the remaining LAA proposal to JRAC, which approved it as a 
JRAC project. Fielding of this capability began in October 2006. In 
fiscal year 2004, JFCOM rejected two LAA proposals, in part because no 
combatant command would validate them as joint urgent operational 
needs. 

Of the six approved LAA projects in fiscal years 2004 and 2005, five 
were completed and deployed from 2 to 17 months after having been 
approved. A sixth project is ongoing with additional development 
remaining. The total funding obtained for the six projects has 
increased from $9 million in research, development, test, and 
evaluation funds in 2005 to $14 million through January 2007. No 
procurement funds had been used as of January 2007, although the 
ongoing speech translation project has identified a need for 
procurement funding. U.S. Central Command has been the predominant 
recipient of LAA capabilities--the command received capabilities from 
five of the six projects. According to JFCOM, the LAA projects 
accelerated the provision of capabilities to the warfighter by 
providing 60 to 80 percent interim solutions for battlefield problems, 
rather than having the warfighter wait years longer for a 100 percent 
solution. Table 2 summarizes key information about the six projects. 

Table 2: Status of Six Approved LAA Projects: 

Status: Capability; 
LAA project name: Change Detection Work Station: Land mine and 
improvised explosive device detection along convoy routes by using 
visual imagery; 
LAA project name: Command and Control on the Move: Broadband 
communication for commanders while moving over rough terrain or 
dismounted from a vehicle; 
LAA project name: Joint Precision Air Drop System 2,000 Pounds: High-
altitude air drop of logistics support packages where ground delivery 
or an airfield is not available; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: Remote access to classified and unclassified networks while 
away from the headquarters compound; 
LAA project name: Joint Blue Force Situational Awareness[A]: Transfer 
and integration of blue force tracking data from battle management, 
command and control systems to strike aircraft; 
LAA project name: Simultaneous 2-Way Speech Translation: Hands-free 
device for simultaneous translation of American English to Iraqi Arabic 
and vice versa. 

Status: LAA-related cost (research, development, test, and evaluation 
dollars); 
LAA project name: Change Detection Work Station: $550,000; 
LAA project name: Command and Control on the Move: $1.95 million; 
LAA project name: Joint Precision Air Drop System 2,000 Pounds: $2.19 
million; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: $850,000; 
LAA project name: Joint Blue Force Situational Awareness[A]: $3.38 
million; 
LAA project name: Simultaneous 2-Way Speech Translation: $5.3 million. 

Status: Months to complete and field[B]; 
LAA project name: Change Detection Work Station: 5-11; 
LAA project name: Command and Control on the Move: 11-14; 
LAA project name: Joint Precision Air Drop System 2,000 Pounds: 16-17; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: 4-15; 
LAA project name: Joint Blue Force Situational Awareness[A]: 2-5; 
LAA project name: Simultaneous 2-Way Speech Translation: Initial 
fielding in 8-12; project is ongoing. 

Status: Recipient/; command; 
LAA project name: Change Detection Work Station: U.S. Central Command; 
LAA project name: Command and Control on the Move: U.S. Central Command 
first received it, but decided not to field it; U.S. Special Operations 
Command now has portions of the capability; 
LAA project name: Joint Precision Air Drop System 2,000 Pounds: U.S. 
Special Operations Command; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: U.S. Central Command and U.S. European Command; 
LAA project name: Joint Blue Force Situational Awareness[A]: U.S. 
Central Command; 
LAA project name: Simultaneous 2- Way Speech Translation: U.S. Central 
Command. 

Source: JFCOM data and GAO analysis. 

[A] The full name is Joint Translator Forwarder--Rapid Attack 
Information Dissemination Execution Relay-Joint Blue Force Situational 
Awareness. 

[B] The range of months reflects when the initial units of the 
capability were fielded through the time when fielding was completed. 

[End of table] 

In response to a GAO questionnaire directed at recipients of JFCOM LAA 
capabilities, warfighters generally provided positive feedback about 
the process that JFCOM developed and implemented for LAA projects. We 
contacted recipients of the capabilities for the five completed 
projects and recipients responded for four projects. Recipients of 
three capabilities used them in operational missions and were pleased 
with their effectiveness. Three recipients said they would use JFCOM 
LAA again. We did not receive feedback from the recipient of the Joint 
Precision Air Drop System project, and we did not send the 
questionnaire to the recipient of the Simultaneous 2-Way Speech 
Translation project, as it is not yet complete. Table 3 summarizes the 
questionnaire's results. 

Table 3: Warfighter Feedback from GAO Questionnaire about LAA Projects: 

GAO's questions: Was adequate training provided to use the LAA 
capability?; 
LAA project name: Change Detection Work Station: Yes; 
LAA project name: Command and Control on the Move[A]: Not applicable, 
capability not yet fielded; 
LAA project name: Joint Blue Force Situational Awareness[B]: Yes; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: Yes. 

GAO's questions: Were you satisfied with JFCOM's LAA process?; 
LAA project name: Change Detection Work Station: Yes; 
LAA project name: Command and Control on the Move[A]: Yes; 
LAA project name: Joint Blue Force Situational Awareness[B]: Yes; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: Yes. 

GAO's questions: Were you satisfied with the time it took to obtain the 
capability?; 
LAA project name: Change Detection Work Station: Yes; 
LAA project name: Command and Control on the Move[A]: Yes, LAA reduced 
the time to get to operational testing by 6-12 months; 
LAA project name: Joint Blue Force Situational Awareness[B]: Yes, LAA 
provided the fastest procurement of this system; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: Yes. 

GAO's questions: Were you prepared to sustain the capability?; 
LAA project name: Change Detection Work Station: Yes; 
LAA project name: Command and Control on the Move[A]: Not applicable, 
capability not yet fielded; 
LAA project name: Joint Blue Force Situational Awareness[B]: Yes; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: No. 

GAO's questions: Was the capability used operationally?; 
LAA project name: Change Detection Work Station: Yes, used it daily for 
several months; 
LAA project name: Command and Control on the Move[A]: Not applicable, 
capability not yet fielded; 
LAA project name: Joint Blue Force Situational Awareness[B]: Yes, used 
it 24 hours a day, 7 days a week to support global forces; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: Yes, used it as often as four times a week. 

GAO's questions: Was the capability operationally effective?; 
LAA project name: Change Detection Work Station: Yes, it did what it 
was supposed to do, but not what recipient wanted it to do; 
LAA project name: Command and Control on the Move[A]: Not applicable, 
capability not yet fielded; 
LAA project name: Joint Blue Force Situational Awareness[B]: Yes, very 
effective; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: Yes, it's top-notch. 

GAO's questions: What were the advantages of using LAA?; 
LAA project name: Change Detection Work Station: Allowed rapid pursuit 
of the most promising technology to meet the need; 
LAA project name: Command and Control on the Move[A]: LAA's speed and 
ease of ordering greatly accelerated testing the capability; 
LAA project name: Joint Blue Force Situational Awareness[B]: Without 
LAA, the capability would not have been used operationally; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: LAA streamlined the budget process and rapidly provided a much-
needed capability. 

GAO's questions: Would you use LAA again?; 
LAA project name: Change Detection Work Station: Person filling out 
questionnaire said he was not in a position to answer at that time; 
LAA project name: Command and Control on the Move[A]: Yes, most likely; 
LAA project name: Joint Blue Force Situational Awareness[B]: Yes, most 
definitely; 
LAA project name: Joint Task Force Commander Executive Command and 
Control: Yes, without hesitation. 

Source: Warfighters (data); GAO (presentation and analysis). 

[A] The information is from the second recipient of the capability; the 
first recipient decided not to field it. 

[B] The full name is Joint Translator Forwarder-Rapid Attack 
Information Dissemination Execution Relay-Joint Blue Force Situational 
Awareness. 

[End of table] 

Separate from the questionnaire, in February 2007, DOD sent a fiscal 
year 2008 legislative proposal to Congress requesting that the LAA 
statute be made permanent and that the statute add the authority to use 
operations and maintenance funds for sustainment of equipment after its 
acquisition. In that proposal, DOD stated that LAA has been invaluable 
in the war on terror. 

JFCOM officials continue to manage LAA using a multi-phased process 
they developed and formalized in July 2005 and revised in June 
2006.[Footnote 6] JFCOM has drawn on mature technologies for its LAA 
projects. Half of the LAA approved projects originated from existing 
joint technology demonstration programs. According to JFCOM, LAA 
projects also can originate from commercial and government off-the- 
shelf products. An important part of the LAA process is to make sure 
the desired capability does not duplicate capabilities under 
development elsewhere in DOD or that are part of an existing program of 
record. The requested capability can, however, accelerate such 
capabilities. Within the LAA process, JFCOM conducts feasibility 
assessments, including procedures to identify related efforts 
throughout DOD. One effort to avoid duplication involves the JFCOM 
science advisers. Each of the military services has a science adviser 
at JFCOM who checks with the Defense Technical Information Center, a 
repository of technical information in DOD. Another effort involves a 
JFCOM official who coordinates with the Program Executive Office 
Interchange--an initiative that supports Air Force, Army, Marine Corps, 
and Navy command and control program executive offices--to find out if 
any similar efforts exist in the services. Also, JFCOM LAA officials 
said they plan to coordinate with JFCOM's Office of Research and 
Technology Applications to use an online DOD system to research all 
existing programs of record. 

JFCOM does not have dedicated acquisition staff for LAA projects. 
Instead, JFCOM has a staff of one full-time and two part-time 
employees, who broker and facilitate the projects. For contracting and 
acquisition services, JFCOM relies on others within DOD. The Under 
Secretary of Defense (Acquisition, Technology, and Logistics) has 
directed five acquisition organizations from the military services and 
a defense agency to provide assistance in development and acquisition 
to JFCOM LAA on a priority basis. However, JFCOM indicated it is not 
limited to using only these five. 

DOD and JFCOM Face Several Challenges with LAA: 

DOD and JFCOM face several challenges in continuing to implement LAA-- 
one challenge goes to the role of LAA and the other challenges deal 
with how LAA is managed and operated. 

Two Rapid Acquisition Processes Address Similar Joint Needs: 

Ten months after Congress enacted the JFCOM LAA statute, the Deputy 
Secretary of Defense created JRAC to manage a process that also 
addresses the joint, urgent operational needs of combatant commanders. 
The two processes cover similar ground, and given that the JRAC process 
is expected to be expanded soon, they could overlap even more. Table 4 
shows our analysis of the similarities in the two processes. 

Table 4: GAO Analysis of Key Aspects of the LAA and JRAC Rapid 
Acquisition Current Processes: 

GAO's analytical questions about key aspects of the two processes: Is 
it to address joint needs?; 
JFCOM LAA: Yes; 
JRAC: Yes. 

GAO's analytical questions about key aspects of the two processes: Is 
it to address urgent needs?; 
JFCOM LAA: Yes; 
JRAC: Yes. 

GAO's analytical questions about key aspects of the two processes: In 
what time frame are needs to be met?; 
JFCOM LAA: Within 2 years; 
JRAC: Within 2 years. 

GAO's analytical questions about key aspects of the two processes: Can 
the solution be currently in development?; 
JFCOM LAA: Yes, most of the approved projects use technologies assessed 
at high readiness levels; 
JRAC: Yes, most of the approved projects use technologies assessed at 
high readiness levels. 

GAO's analytical questions about key aspects of the two processes: Must 
the need be related to an ongoing, named operation?; 
JFCOM LAA: No; 
JRAC: Yes, currently, but change under consideration. 

GAO's analytical questions about key aspects of the two processes: Must 
the need be immediate to prevent loss of life or mission failure?; 
JFCOM LAA: No; 
JRAC: Yes. 

GAO's analytical questions about key aspects of the two processes: Is 
the need to be submitted by a combatant commander?; 
JFCOM LAA: Yes. However, the JFCOM commander can initiate a project to 
meet a need he identifies; for example, the commander initiated three 
of the six LAA projects, while other combatant commanders validated the 
needs for the other three projects; 
JRAC: Yes. 

GAO's analytical questions about key aspects of the two processes: Is 
there a limit for research, development, test, and evaluation 
expenditures per system?; 
JFCOM LAA: Yes, the expenditure must be estimated to be less than $10 
million; 
JRAC: Yes, the expenditure must be $365 million or less in fiscal year 
2000 dollars. 

GAO's analytical questions about key aspects of the two processes: Is 
there a limit for procurement expenditures per system?; 
JFCOM LAA: Yes, the expenditure must be estimated to be less than $50 
million; 
JRAC: Yes, the expenditure must be $2.19 billion or less in fiscal year 
2000 dollars. 

Source: GAO analysis of JFCOM LAA and JRAC processes. 

[End of table] 

In September 2004, when the Deputy Secretary of Defense created JRAC, 
he stated that the war on terror and recent experiences with Iraqi 
Freedom and Enduring Freedom (in Iraq and Afghanistan) highlighted the 
institutional challenges that DOD faces in providing timely, integrated 
solutions to the warfighter. He said that all too often, DOD 
organizations have been reluctant to take advantage of the authority 
and flexibility that Congress has given them to meet many of these 
needs. To break through institutional barriers to providing timely, 
effective support, the Deputy Secretary directed the Under Secretary of 
Defense (Acquisition, Technology, and Logistics) and the Under 
Secretary of Defense (Comptroller) to establish JRAC, whose mission is 
to facilitate meeting urgent material and logistics requirements that 
combatant commanders certify as operationally critical. He also 
directed the Joint Staff, combatant commands, and each of the military 
services to provide a single point of contact with appropriate 
authority to make commitments of support from the respective 
organizations to JRAC projects. These individuals are expected to be 
thoroughly proficient in their own organization's processes as well as 
empowered to make rapid decisions within the scope of JRAC's mission. 
According to JRAC officials, the JRAC process was initiated instead of 
using the JFCOM LAA process because the Deputy Secretary of Defense 
believed he needed an agent at the highest level of DOD, with 
sufficient visibility and flexibility, to ensure that urgent warfighter 
needs are quickly met. 

In July 2005, the Chairman of the Joint Chiefs of Staff issued 
Instruction 3470.01 to formalize the JRAC process for rapidly 
validating and providing resources for joint, urgent operational needs 
in the year of project execution. This instruction, among other things, 
established policy and procedures to facilitate assessment, validation, 
sourcing, resourcing, and fielding of operationally driven urgent, 
combatant command needs in the year of execution. Generally, these 
needs are considered life-or combat mission-threatening, based on 
unforeseen military requirements that must be resolved in days, weeks, 
or months. These needs must also be considered inherently joint in 
nature, that is, theaterwide combatant command needs spanning multiple 
services. Instruction 3470.01 states that the JRAC process is not 
intended to replace the decision-making processes in DOD's traditional 
acquisition system, nor is it designed to compete with any of the 
military services' or Joint Staff's processes, but to complement them. 
However, our analysis indicates that the JRAC process overlaps with 
JFCOM's LAA process. 

As of April 2007, JRAC had completed 24 projects worth a total of 
$335.5 million, including biometrics identification, jammers, signals 
intelligence, and satellite communication systems. Three JRAC projects 
touched on similar needs addressed by JFCOM LAA projects--foreign 
language translation, blue force tracking, and joint precision air 
drop. The JRAC also had 1 other project, totaling $10.0 million, under 
consideration. 

One of the two main differences between the JFCOM LAA and JRAC 
processes relating to the nature of the need may soon change. According 
to a Joint Staff official, Instruction 3470.01 is being revised and is 
not expected to retain the requirement that the joint urgent 
operational need be for an ongoing named operation. If this particular 
requirement is eliminated, the JFCOM LAA and JRAC processes will 
overlap even more. The revised instruction is expected to be finalized 
in spring 2007. 

Within this environment of competing joint rapid acquisition processes, 
DOD has not established clear procedures or factors to take into 
account to help combatant commands determine which process to use-- 
JFCOM LAA or JRAC. Although JFCOM LAA officials sit on JRAC's advisory 
group, and some coordination takes place, Instruction 3470.01 does not 
specify steps for coordinating between the two processes, and JFCOM's 
LAA procedures do not specifically call for coordinating with JRAC. 
Exemplifying the need for coordination, we analyzed the six approved 
LAA projects and concluded that JRAC might have also been able to 
accomplish most, if not all, of them. Following is the basis for our 
conclusions. The first five projects listed below were approved on or 
before the date Instruction 3470.01 came into existence. 

* Change Detection Work Station: JFCOM officials told us this LAA 
project would have met JRAC's criteria for a project because it clearly 
was for an immediate warfighter need.[Footnote 7] 

* Command and Control on the Move: JFCOM officials said this LAA 
project would not have met JRAC criteria for an immediate warfighter 
need. However, we believe the project might have been justified under 
the JRAC criterion of preventing mission failure if a regional 
combatant command had submitted it as an immediate need. For example, 
if a joint task force commander cannot adequately communicate with the 
troops while on the move or dismounted from a vehicle, this could lead 
to mission failure. In this case, the JFCOM commander validated the 
need as an LAA project. 

* Joint Precision Air Drop System 2,000 Pounds: This LAA project met 
JRAC's criteria as an immediate warfighter need because once JRAC came 
into existence, JRAC obtained funding for the project from the Air 
Force on JFCOM's behalf. 

* Joint Task Force Commander Executive Command and Control: JFCOM 
officials said this project would not have met JRAC's criteria of 
responding to a combat fatality or preventing mission failure. However, 
we believe it might have been justified under the JRAC process to 
prevent mission failure due to the importance for a joint task force 
commander to have remote access to classified and unclassified networks 
while away from the headquarters compound. 

* Joint Blue Force Situational Awareness: JFCOM officials said JRAC 
could have taken on this project because it was to meet a joint, urgent 
operational need that may have met the criteria as an immediate 
warfighter need.[Footnote 8] 

* Simultaneous 2-Way Speech Translation: Although JRAC was in place 
when JFCOM approved this LAA project, JFCOM officials said JRAC 
provided most of the funding and took over the project after it was 
approved as an LAA project. 

For background purposes, the JFCOM LAA and JRAC processes are not the 
only two rapid acquisition processes addressing urgent warfighter needs 
within DOD. The military services have their own processes. However, 
they differ from the JFCOM LAA and JRAC processes in that the services' 
processes focus on service-specific needs, not joint needs. For 
example, the Army Rapid Equipping Force began in fiscal year 2002 and 
was formalized in March 2005.[Footnote 9] Its missions include rapidly 
equipping operational forces to enhance mission capability and soldier 
safety, inserting promising technologies into the current force, and 
providing business process feedback to Army stakeholders. This process 
provides commercial and government off-the-shelf solutions for urgent 
needs, takes an average of 128 days to deliver an initial operational 
capability from the time the request is received, and funds up to 2 
years of sustainment when appropriate. In fiscal year 2006, the Rapid 
Equipping Force had a budget of over $135 million and, since inception, 
has provided 227 types of equipment, totaling over 51,000 individual 
items, for the war on terror. 

The Joint Improvised Explosive Device Defeat Organization addresses 
joint urgent warfighter needs, but its mission specifically focuses on 
supporting the efforts of combatant commanders and their task forces in 
defeating improvised explosive devices. Originally established in June 
2005 as a task force, it was changed to an organization in January 
2006, and operates under the authority, direction, and control of the 
Deputy Secretary of Defense. An official in the organization said it 
generally fields capabilities to the warfighter from 6 to 12 months 
after a request is approved, and funds up to 2 years of sustainment 
once fielded. In fiscal year 2006, the Joint Improvised Explosive 
Device Defeat Organization's budget was $3.49 billion. 

The U.S. Special Operations Command has its own acquisition process as 
well, including a process for rapid acquisitions.[Footnote 10]0 The 
Special Operations Command process differs from the LAA and JRAC 
processes in that it is oriented only toward developing and acquiring 
capabilities for warfighters conducting special operations, and comes 
with associated funding in the DOD budget. Due to the variety of DOD 
rapid acquisition processes, coordination can help to prevent 
duplication of effort and enhance knowledge sharing and resource 
investment. 

JFCOM Experiences Complications with Funding, Delegation, and Analysis 
of Projects' Usefulness: 

Finding Funding for LAA Projects Continues to Be Challenging: 

Finding funding to develop, acquire, and sustain LAA projects was 
identified as a challenge in our prior report and remains so. Because 
LAA is an authority, not a program, LAA does not have budgeted funds. 
After an LAA project is approved, JFCOM LAA staff must obtain funding 
for it. JFCOM officials have to either find other DOD organizations to 
pay for LAA projects or pay for them with funds budgeted for other 
JFCOM work. For example, JFCOM sought and obtained funds from the Naval 
Air Warfare Center Weapons Division, China Lake, California, for the 
Change Detection Work Station project. JFCOM officials said the search 
for funding can take 40 to 50 percent or more of the time it takes to 
process an LAA project. While this keeps projects austere, the long 
search delays getting new capabilities to warfighters in the field. 
When locating funding to develop and acquire[Footnote 11]1 a project 
proved especially difficult, JFCOM funded all or part of it by 
offsetting funds from programs in JFCOM's non-LAA budget, which does 
not include any budgeted LAA funds. JFCOM has provided over half of the 
total funding to develop and acquire the six approved LAA projects. 
However, a JFCOM official expressed that JFCOM is reluctant to continue 
using its non-LAA program funding because of adverse effects on those 
programs. Conversely, JRAC does not have as much difficulty obtaining 
funding for its projects even though it does not have budgeted funds 
either. A JRAC official said a senior executive in the Office of the 
Under Secretary of Defense (Comptroller) is the deputy director of 
JRAC, and pointed out that this aids in identifying and obtaining 
available funding throughout DOD. Furthermore, according to JRAC 
officials, DOD recognized the need for increased financial resources 
and flexibility for urgent warfighter needs because JRAC's 
accomplishments have been attributable to improved access to resources. 
The officials stated that the Office of the Secretary of Defense 
intends to expand on past lessons and institutionalize a budget 
approach with an annual transfer account specifically designed to 
fulfill urgent warfighting needs. 

After a capability has been acquired, an obligation for sustainment is 
created. The LAA statute does not specifically provide the authority to 
sustain a product--that is, use operations and maintenance funding-- 
after deployment, although JFCOM officials believe they can provide 
this support under certain circumstances. To address such needs, JFCOM 
tries to identify another DOD organization to adopt the LAA capability 
for long-term sustainment. JFCOM officials commented that the timing of 
the DOD budget cycle is a primary factor for organizations in dealing 
with the sustainment issue for LAA-fielded projects. The officials said 
that because LAA capabilities are acquired rapidly to respond to urgent 
and emergent needs and typically fall outside the time frames of the 
normal DOD budgeting cycle, finding an organization to sustain an LAA 
project sometimes proves difficult. For example, for one LAA project, 
JFCOM resorted to using its own operations and maintenance funds to 
provide short-term sustainment during the "bridge" period while the 
project was awaiting adoption by another organization. JFCOM's LAA 
policy allows it to fund sustainment of a project for up to 2 years 
from the time the project is approved. However, JFCOM officials believe 
that using JFCOM's operations and maintenance funds for LAA projects is 
only permitted under certain conditions. Specifically, the officials 
said the lack of an operations and maintenance provision in the LAA 
statute only allows the use of JFCOM operations and maintenance funds 
to sustain an LAA capability if that mission is compatible with a pre- 
existing JFCOM mission. When DOD recently sent a legislative proposal 
to Congress requesting that the LAA statute be made permanent, it also 
asked that the statute be revised to allow the use of operations and 
maintenance funding for LAA projects. 

To address the overall funding challenges, JFCOM recently approached 
the Office of the Secretary of Defense (Director, Defense Research and 
Engineering) about obtaining funding for LAA projects. Although 
officials from both offices said there is no statutory restriction on 
including a funding line for LAA in the DOD budget, JFCOM officials 
said they have been unsuccessful in obtaining LAA funding in the past 
because building a justifiable budget request 1 to 2 years in advance, 
which is the norm within the DOD budgeting process, is very difficult 
for specific urgent warfighter needs that come up unexpectedly. 
According to JFCOM officials, the current discussions for funding 
assistance include the use of reprogrammings by the Office of the 
Secretary of Defense on JFCOM's behalf. 

Delegation of LAA to JFCOM Is Unclear: 

Uncertainties exist as to the exact nature of the Office of the 
Secretary of Defense's delegation of LAA to JFCOM. Specifically, it is 
unclear exactly what powers were delegated to JFCOM and under what 
authorities--that is, the LAA statute or other authorities available to 
the Secretary of Defense. Failure to clarify these issues may impair 
JFCOM's ability to carry out LAA efforts. To understand the current 
situation requires briefly revisiting LAA's origins. 

As originally envisioned by the Senate bill, LAA's enactment would have 
required the Secretary of Defense to delegate LAA to the JFCOM 
commander. Prior to enactment, however, the language was changed to 
give the Secretary discretion about whether to delegate the authority. 
The provision for LAA in the fiscal year 2004 Senate National Defense 
Authorization Bill included language that the Secretary of Defense 
"shall delegate" LAA to the commander of the unified combatant command 
for joint warfighting experimentation (currently, JFCOM). The fiscal 
year 2004 House National Defense Authorization Bill had no provision 
for LAA. In conference, the House receded with an amendment that 
changed the language of the Senate bill from "shall delegate" to "may 
delegate," thus providing the Secretary of Defense with the discretion 
to delegate LAA authority to JFCOM. The LAA statute, as enacted, 
provides that the Secretary of Defense may delegate to the [JFCOM] 
commander authority of the Secretary "sufficient to enable the 
commander to develop and acquire" certain described equipment. 

The Secretary of Defense has not provided JFCOM a document specifically 
citing delegation of LAA, in part or in whole. Rather, in June 2004, 
the acting Under Secretary of Defense (Acquisition, Technology, and 
Logistics) issued an acquisition assistance memorandum to the 
Secretaries of the Military Departments, the Chairman of the Joint 
Chiefs of Staff, the Commander of JFCOM, and the Directors of the 
Defense Agencies directing that, "consistent with" the LAA statute (10 
U.S.C. 167a), the JFCOM commander be provided assistance "in developing 
and acquiring the urgent requirements of the Combatant Commanders" for 
the same types of equipment as described in the LAA statute. The memo 
further stated that it did not apply to the development or acquisition 
of a system for which the total research, development, test, and 
evaluation expenditure is estimated to be $10 million or more or for 
which the total procurement expenditure is estimated to be $50 million 
or more--again using the same language as the LAA statue. To help JFCOM 
carry out its efforts, the memorandum identified five service and 
defense agency contracting activities to provide services to JFCOM on a 
priority basis. The memorandum was to be in effect until September 30, 
2006, when LAA was originally to expire. When Congress extended LAA for 
2 years in the fiscal year 2006 National Defense Authorization Act, the 
Under Secretary of Defense issued a new acquisition assistance 
memorandum with the same language as the original one but with extended 
coverage until September 30, 2008. 

JFCOM officials view the LAA statute as consisting of four powers that 
could be delegated. Specifically, 

* the power that expanded JFCOM's mission to allow it to acquire 
capabilities for other combatant commands using research, development, 
test, and evaluation and procurement funds; 

* the power to influence the DOD requirements process; 

* the power to influence the DOD planning, programming, budgeting, and 
execution process; and: 

* the power to sign contracts to develop and acquire LAA systems, that 
is, to have warranted contracting officer authority. 

In our discussions, JFCOM and Office of the Secretary of Defense 
officials agreed that a full delegation of LAA was not made. 
Specifically, they agreed JFCOM was not delegated the power to sign 
contracts for LAA projects, that is, warranted contracting officer 
authority. JFCOM did not see this power as practical given the limited 
duration of LAA. Specifically, JFCOM officials stated that JFCOM did 
not want to set up an infrastructure for warranted contracting officers 
because it would have taken up most of the initial, limited 3-year term 
of LAA, which would have slowed down the command's ability to meet 
urgent warfighter needs as rapidly as possible. As a result, in lieu of 
JFCOM's having been provided warranted contracting officer authority, 
the acquisition assistance memorandum provided for other organizations 
to provide contracting assistance for LAA projects on JFCOM's behalf. 
The Office of the Secretary of Defense and JFCOM officials agreed the 
acquisition memorandum provided JFCOM with the powers to influence the 
requirements process and the planning, programming, budgeting, and 
execution process. It is not clear, however, under what authorities-- 
the LAA statute or other authorities available to the Secretary of 
Defense--these powers were provided, as the acquisition memorandum does 
not specify these powers or their delegation under the LAA statute. 
During the course of our review, Office of the Secretary of Defense 
officials stated that the Secretary of Defense had the authority 
outside of the LAA statute to provide JFCOM with these powers. The 
officials noted, however, that enactment of the LAA statute was the 
impetus for providing the acquisition assistance memorandum to JFCOM 
and, ultimately, the fielding of the LAA capabilities to the warfighter 
under JFCOM's auspices. By way of comparison, JRAC was established by 
the Deputy Secretary of Defense without a new statute. 

Importantly, there is disagreement between JFCOM and the Office of the 
Secretary of Defense over whether the acquisition assistance memorandum 
provided JFCOM with the first power above, that is, to expand JFCOM's 
mission to allow it to directly acquire capabilities for other 
combatant commands. Office of the Secretary of Defense officials stated 
that JFCOM was not provided that power under the acquisition assistance 
memorandum. Rather, they stated JFCOM has been given the power to 
arrange for other DOD organizations to acquire the capabilities. JFCOM 
officials said they could not have legally developed and acquired the 
six LAA capabilities for other combatant commands without the 
delegation of this power. In the end, the acquisition assistance 
memorandum is not clear on this issue either because it does not 
specifically cite this power or how JFCOM is to carry out LAA. 

JFCOM Is Making Progress in Assessing LAA Projects' Effectiveness: 

JFCOM has made progress in the past year or so in tracking LAA projects 
on a quarterly basis. JFCOM officials also said they have solicited 
information from warfighters on the effectiveness of fielded 
capabilities, and have received adequate information for some of them. 
Previously, JFCOM had received anecdotal feedback from warfighters, 
which was limited in scope and detail. JFCOM also has revised the LAA 
process, requiring future LAA proposals to include a plan to assess the 
effectiveness of fielded capabilities and provide regular, written 
feedback to JFCOM. However, since the revision, no LAA projects have 
been approved, so the revised process has not yet resulted in 
additional data. 

Conclusions: 

JFCOM has delivered capabilities under the auspices of LAA, taking 
promising technologies and spinning them out quickly for joint, urgent 
needs in the battlefield. Warfighters generally have had positive 
experiences, not just with the capabilities, but also JFCOM's ability 
to deliver. On the other hand, no new projects have been approved in 
the past 19 months, and the creation of JRAC presents warfighters with 
another avenue for rapidly acquiring similar capabilities. The expected 
expansion of JRAC's coverage would lessen the remaining differences 
between the two authorities. Having two processes addressing similar 
joint urgent needs may have advantages--such as increasing the range of 
efforts to more rapidly field joint capabilities. However, having two 
processes also presents risks--such as lack of coordination and 
duplication of effort--and employing resources efficiently and 
effectively during wartime is important. Regardless of their 
similarities, the two processes have a clear imbalance in access to 
funding. JRAC's access to funding is defined, while JFCOM staff must 
invest substantial time to find funding for its LAA projects, a fact 
that works against the purpose of rapidly providing capabilities for 
urgent needs. Further complicating this joint rapid acquisition picture 
are the differing views on what LAA powers were delegated to JFCOM. 
Such complications make the important and complex task of meeting 
urgent needs more difficult than it has to be. 

Recommendations for Executive Action: 

As DOD considers expanding JRAC's coverage, we recommend that the 
Secretary of Defense take the following three actions: 

* reassess the role of the JFCOM LAA in light of the expanding JRAC 
process, and determine whether and how JFCOM LAA should play a role in 
meeting joint urgent needs; 

* to the extent JFCOM LAA is to continue to play a role in meeting 
joint urgent needs, assess and resolve, as appropriate, the funding, 
coordination, and delegation challenges identified in this report; and: 

* inform Congress of the results of the assessment and any resultant 
decisions in time for Congress to consider them in its deliberations on 
the National Defense Authorization Act for fiscal year 2008. 

Matter for Congressional Consideration: 

In light of our recommendations, DOD's response and the fact that DOD 
has provided Congress with a fiscal year 2008 legislative proposal that 
would make the LAA statute permanent, Congress might want to delay its 
consideration of making JFCOM LAA permanent until DOD has informed 
Congress of the results of the recommended assessment and any 
associated decisions. This should not impair JFCOM LAA, as DOD plans to 
complete its assessment by the fourth quarter of 2007 and LAA, as 
currently enacted, extends through September 2008. 

Agency Comments: 

In written comments on a draft of this report, DOD concurred with our 
recommendations, stating that it would reassess the role of the Joint 
Forces Command's limited acquisition authority in light of the 
expanding Joint Rapid Acquisition Cell process and consider the other 
issues identified in this report as a part of that effort. DOD expects 
to complete that reassessment by the fourth quarter of 2007. DOD also 
stated that it would inform Congress of the result of that assessment 
and any associated decisions. DOD's letter is reprinted in appendix II. 

We plan to provide copies of this report to the Secretary of Defense, 
the Commander of JFCOM, and interested congressional committees. We 
will also make copies available to others upon request. In addition, 
the report will be available at no charge on the GAO Web site at 
http://www.gao.gov. If you or your staff has any questions concerning 
this report, please contact me at (202) 512-4841. Contact points for 
our Offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. Key contributors to the report include 
Bruce H. Thomas, Assistant Director; Lily J. Chin; Joseph E. Dewechter; 
Bonita J.P. Oden; Marie Ahearn; and Ken Patton. 

Signed by: 

Paul L. Francis: 
Director: 
Acquisition and Sourcing Management: 

[End of section] 

Appendix I: Scope and Methodology: 

To provide an update on the U.S. Joint Forces Command (JFCOM) limited 
acquisition authority (LAA) efforts since LAA was enacted, we obtained 
and analyzed information and documentation, and interviewed officials 
from a variety of organizations. For information on all LAA proposals 
and approved projects, as well as current LAA policy and procedures, we 
worked with officials from JFCOM, located in Norfolk, Virginia. For the 
views of warfighters on participating in the LAA process and on the 
utility and effectiveness of fielded LAA capabilities, we developed a 
data collection instrument and obtained information from U.S. Central 
Command and U.S. European Command warfighters, who had been involved in 
and used the capabilities from four of the six LAA projects. Some of 
these warfighters were in theater in Iraq, Afghanistan, and Europe. 
Other warfighters were at the Camp Lejeune Marine Corps Base, North 
Carolina, and at the Fort Bragg Army Base, North Carolina. We also 
collected information and interviewed officials from U.S. Central 
Command headquarters, located in Tampa, Florida. For project offices 
involved in LAA projects, we obtained information and interviewed 
officials for selected LAA projects in the Sequoyah Transition 
Management Office, U.S. Army Communications-Electronics Life Cycle 
Management Command, at Fort Monmouth, New Jersey; in the U.S. Army 
Night Vision and Electronic Sensors Directorate, Army Materiel Command, 
at Fort Belvoir, Virginia; in the Army Research, Development, and 
Engineering Command, Natick Soldier Systems Center, Natick, 
Massachusetts; and in the Joint Systems Integration Command, at 
Suffolk, Virginia. For organizations providing contracting services for 
LAA projects, we obtained information and interviewed officials at the 
Navy Fleet Industrial and Supply Center, in Philadelphia, Pennsylvania, 
and in the U.S. Army Communications-Electronics Life Cycle Management 
Command, at Fort Monmouth, New Jersey. 

To identify key challenges in operating and managing LAA, we obtained 
and analyzed information and documentation, and interviewed officials, 
from JFCOM; and Office of the Secretary of Defense--General Counsel, 
Comptroller, Under Secretary of Defense (Acquisition, Technology, and 
Logistics)/Defense Procurement and Acquisition Policy, Under Secretary 
of Defense (Acquisition, Technology, and Logistics)/Joint Rapid 
Acquisition Cell (JRAC), Under Secretary of Defense (Acquisition, 
Technology, and Logistics)/Director, Defense Research and Engineering, 
and the Joint Staff/J-8, Capabilities and Acquisition Division, which 
are located in Arlington, Virginia. We reviewed and analyzed JFCOM's 
LAA policy and procedures and identified challenges in operating and 
managing LAA. We also obtained and analyzed information from the 
warfighters, contracting organizations, and project offices for any 
challenges they identified or experienced with LAA. In addition, we 
researched and analyzed the LAA statute and its legislative history to 
identify any legal challenges in implementing, operating, and/or 
managing LAA. 

To examine LAA within the context of other DOD rapid acquisition 
processes, we obtained and analyzed information and documentation, and 
interviewed officials, from JFCOM; the Under Secretary of Defense 
(Acquisition, Technology, and Logistics)/Defense Procurement and 
Acquisition Policy; the Under Secretary of Defense (Acquisition, 
Technology, and Logistics)/Director, Defense Research and Engineering; 
the Under Secretary of Defense (Acquisition, Technology, and 
Logistics)/JRAC; the Joint Staff/J-8, Capabilities and Acquisition 
Division; the Joint Improvised Explosive Device Defeat Organization, 
located in Arlington, Virginia; and the U.S. Army Rapid Equipping 
Force, located at Fort Belvoir, Virginia. We also gathered information 
on the rapid acquisition processes for the military services and the 
U.S. Special Operations Command. We compared key aspects of the LAA 
process with those of the JRAC process, including reviewing and 
analyzing the Chairman of the Joint Chiefs of Staff Instruction 3470.01 
for Rapid Validation and Resourcing of Joint Urgent Operational Needs 
in the Year of Execution. We also determined if JRAC might have been 
able to process the six approved LAA projects if the JRAC process had 
existed at the time the projects were approved by JFCOM. Furthermore, 
we reviewed and analyzed the LAA legislative history and the JRAC 
process to identify similarities and differences. However, we did not 
conduct an in-depth evaluation of JRAC or the JRAC process. 

We conducted our work from July 2006 to March 2007 in accordance with 
generally accepted government auditing standards. 

[End of section] 

Appendix II: Comments from the Department Of Defense: 

Office Of The Under Secretary Of Defense: 
3000 Defense Pentagon: 
Washington, DC 20301-3000: 
Acquisition, Technology And Logistics: 

Apr 11 2007: 

Mr. Paul Francis: 
Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, D.C. 20548: 

Dear Mr. Francis: 

This is the Department of Defense (DoD) response to the GAO Draft 
Report, GAO-07-546, `Defense Acquisitions: Status and Challenges of 
Joint Forces Command's Limited Acquisition Authority,' dated March 19, 
2007 (GAO Code 120623). 

We have enclosed comments addressing the three recommendations on pages 
15 and 16 of the draft report. 

My point of contact is Mr. Skip Hawthorne, 703.692.9556, or e-mail: 
skip.hawthorne@osd.mil. 

Sincerely, 

Signed by: 

Shay D. Assad: 
Director, Defense Procurement and Acquisition Policy: 

Enclosure: 
As stated: 

GAO Draft Report-Dated March 19, 2007 GAO Code 120623/GAO-07-546: 

Defense Acquisitions: Status and Challenges of Joint Forces Command's 
Limited Acquisition Authority: 

Department Of Defense Comments Regarding The Draft Report: 

GAO Draft Report Dated March 19, 2007 GAO-07-546 (GAO Codes 120623): 

"Defense Acquisitions: Status And Challenges Of Joint Forces Command's 
Limited Acquisition Authority" 

Department Of Defense Comments To The GAO Recommendations: 

Recommendation 1: The GAO recommended that the Secretary of Defense 
reassess the role of the Joint Forces Command's limited acquisition 
authority (JFCOM LAA) in light of the expanding Joint Rapid Acquisition 
Cell process, and determine whether and how JFCOM LAA should play a 
role in meeting joint urgent needs. (p. 15/GAO Draft Report): 

DOD Response: Concur. The Secretary of Defense will reassess JFCOM's 
Limited Acquisition Authority in light of the expanding Joint Rapid 
Acquisition Cell process. The reassessment of JFCOM's LAA is expected 
to be completed by 4Th quarter 2007. 

Recommendation 2: The GAO recommended that the Secretary of Defense 
assess and resolve, as appropriate, the funding, coordination, and 
delegation challenges identified in this report to the extent JFCOM LAA 
is to continue to play a role in meeting joint urgent needs. (p. 15/GAO 
Draft Report): 

DOD Response: Concur. These issues will be considered in association 
with the reassessment of JFCOM's role in the development of joint 
capabilities, expected to be completed by 4H quarter 2007. 

Recommendation 3: The GAO recommended that the Secretary of Defense 
inform congress of the results of the assessment and any resultant 
decisions in time for Congress to consider them in its deliberations on 
the National Defense Authorization Act for fiscal year 2008. (p. 16/GAO 
Draft Report): 

DOD Response: Concur. The Secretary of Defense will inform Congress of 
the results of its reassessment and any associated decisions. 

[End of section] 

FOOTNOTES 

[1] GAO, Defense Acquisitions: Joint Forces Command's Limited 
Acquisition Authority, GAO-06-240R (Washington, D.C.: Nov. 22, 2005). 

[2] The first LAA statute was enacted under the National Defense 
Authorization Act for Fiscal Year 2004 (Pub. L. No. 108-136 Div. A, 
section 848, Nov. 24, 2003). The extension was enacted under the 
National Defense Authorization Act for Fiscal Year 2006 (Pub. L. No. 
109-163 Div. A, section 846, Jan. 6, 2006). 

[3] Chairman of the Joint Chiefs of Staff Instruction (CJCSI) 3470.01, 
Rapid Validation and Resourcing of Joint Urgent Operational Needs 
(JUONs) in the Year of Execution, July 15, 2005. 

[4] DOD Directive Number 2000.19E, Joint Improvised Explosive Device 
Defeat Organization (JIEDDO), February 14, 2006. 

[5] See Chairman of the Joint Chiefs of Staff Instruction (CJCSI) 
3470.01, Rapid Validation and Resourcing of Joint Urgent Operational 
Needs (JUONs) in the Year of Execution, Enclosure A, July 15, 2005. 

[6] The JFCOM LAA acquisition process consists of multiple phases that 
can be tailored to meet requests as expeditiously as possible. The 
phases are proposal receipt, feasibility assessment, proposal review 
and approval, locating and obtaining funding, contracting, and project 
execution. Descriptions of these phases are in our November 2005 
report. 

[7] In Instruction 3470.01, an immediate warfighter need is defined as 
a subset of joint urgent operational needs, so designated by JRAC, 
which have a materiel or logistics solution that must be resolved 
within 120 days or less. The instruction states that this special 
category will confirm an added emphasis on the timely resolution of 
this urgent operational need and enhanced visibility to the Office of 
the Secretary of Defense and the Deputy Secretary of Defense. According 
to JRAC officials, their interpretation is that a solution for the 
immediate warfighter need is to be developed in less than 120 days, 
which can be delivered to the warfighter in less than 2 years. 

[8] The full name is Joint Translator Forwarder-Rapid Attack 
Information Dissemination Execution Relay-Joint Blue Force Situational 
Awareness. JFCOM LAA funded the Joint Blue Force Situational Awareness 
equipment. 

[9] Department of the Army Memorandum for Director, Rapid Equipping 
Force, March 10, 2005, Concept Plan to Establish the Rapid Equipping 
Force (REF). 

[10] [0] See Chairman of the Joint Chiefs of Staff Instruction (CJCSI) 
3470.01, Rapid Validation and Resourcing of Joint Urgent Operational 
Needs (JUONs) in the Year of Execution, Enclosure A, which refers to 
the U.S. Special Operations Command Directive 71-4, Combat Mission Need 
Statement (CMNS) Process. 

[11] [1] In this case, the term acquire relates to items that were 
acquired with research, development, test, and evaluation funds, as 
opposed to procurement funds. 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: