This is the accessible text file for GAO report number GAO-06-1025 
entitled 'Kennedy Center: Progress Made on GAO Recommendations, but 
Oversight Challenges Still Exist' which was released on September 21, 
2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Subcommittee on Interior, Environment, and Related 
Agencies, Committee on Appropriations, House of Representatives: 

September 2006: 

Kennedy Center: 

Progress Made on GAO Recommendations, but Oversight Challenges Still 
Exist: 

GAO-06-1025: 

GAO Highlights: 

Highlights of GAO-06-1025, a report to the Subcommittee on Interior, 
Environment, and Related Agencies, Committee on Appropriations, House 
of Representatives 

Why GAO Did This Study: 

In April 2005, GAO recommended that the John F. Kennedy Center for the 
Performing Arts (Kennedy Center) increase oversight of its management 
of federal funds, better comply with fire code, and conform to project 
management best practices. GAO was asked to evaluate (1) the progress 
the Kennedy Center has made in implementing GAO’s April 2005 
recommendations, (2) the status of federally funded capital projects 
and the planned spending of federal funds for capital projects as 
indicated by the Kennedy Center’s most recent comprehensive building 
plan, and (3) the Kennedy Center Board of Trustees’ responsibilities 
for federally funded capital projects and the extent to which the board 
fulfills these responsibilities. To fulfill these objectives, GAO 
examined Kennedy Center documents, visited other arts organizations, 
and interviewed affected parties. 

What GAO Found: 

The Kennedy Center has taken steps to implement GAO’s oversight, fire 
safety, and capital project recommendations but more work remains. For 
example, to increase oversight of its management of federal funds, the 
Kennedy Center contracted with the Smithsonian Institution Office of 
the Inspector General for audits of federal funds used for capital 
projects. In addition, to better comply with fire safety code, the 
Kennedy Center has implemented GAO’s recommendations to obtain a peer 
review of its fire-modeling study and manage the storage of combustible 
materials. As a result of the peer review, the center made changes to 
its fire-modeling study. Finally, to better align with project 
management best practices, the Kennedy Center has implemented GAO’s 
recommendations to design and implement contract, financial, and 
project management policies and procedures and control cost and 
schedule changes in future projects. 

Figure: Kennedy Center's Progress in Implementing GAO's 
Recommendations: 

[See PDF for Image] 

Source: GAO. 

[End of Figure] 

The Kennedy Center’s 2005 comprehensive building plan (CBP)—or long-
term renovation effort—shows that the center will not complete its 
capital renovations within the planned 2008 time frame and budgets. The 
estimated costs for the remaining CBP projects have increased from $48 
million to $58 million since the 2004 CBP, and the center plans to 
defer most terrace-level renovations beyond 2008, the original 
completion date. The 2005 CBP shows that the Family Theater was 
completed on schedule in 2005 with limited cost growth. However, 
despite improved contracting practices, GAO found that the Kennedy 
Center did not fully comply with the Federal Acquisition Regulation 
(FAR) when it used an alternative contracting method. In addition, it 
increased the risk of cost overruns by authorizing Family Theater work 
to begin before establishing the contract’s guaranteed maximum price. 

The Kennedy Center Board of Trustees has delegated to management most 
of its responsibilities for federally funded capital projects, which is 
a typical board action. However, GAO found that several factors limit 
the board’s oversight of federally funded capital projects. The Kennedy 
Center Board of Trustees and its Operations Committee (1) lack 
procedures on how to carry out the board’s responsibilities for 
federally funded projects (2) have experienced low attendance at 
meetings, and (3) lack information needed to evaluate the 
implementation of capital projects. In addition, the Operations 
Committee has met infrequently, which further limits oversight. 

What GAO Recommends: 

GAO recommends that the Kennedy Center comply with the FAR provision 
regarding alternative contracting methods, improve information to the 
board on capital projects, and develop and implement procedures for the 
board on how to carry out its responsibilities for federal funds. The 
Kennedy Center disagreed with our recommendation that it improve 
compliance with the FAR provision, but agreed generally with GAO’s 
other recommendations. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-1025]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Mark Goldstein at (202) 
512-2834 or goldsteinm@gao.gov. 

[End of Section] 

Contents: 

Letter: 

Results in Brief : 

Background: 

The Kennedy Center Has Taken Steps to Implement Our Oversight, Fire 
Safety, and Capital Project Recommendations, but More Work Remains: 

The Kennedy Center Will Not Complete All Planned Capital Renovations 
within CBP Budgets and Time Frames: 

The Kennedy Center Board of Trustees Has Delegated Its Responsibility 
for Federally Funded Capital Projects, but Has Provided Limited 
Oversight: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendixes: 

Appendix I: Scope and Methodology: 

Appendix II: Kennedy Center's Implementation of Our Recommendation to 
Design and Implement Financial Policies and Procedures: 

Appendix III: Comments from the John F. Kennedy Center for the 
Performing Arts: 

GAO Comments: 

Appendix IV: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Staff Acknowledgments: 

Figures: 

Figure 1: Diagram of the Kennedy Center's Plaza-Level Public Spaces and 
Theaters: 

Figure 2: Organization of the Kennedy Center for Selected Positions and 
Offices: 

Figure 3: Kennedy Center's Progress in Implementing Our 
Recommendations: 

Figure 4: Kennedy Center's Progress in Implementing Our Fire Safety 
Recommendations: 

Figure 5: Location of Exit Signage at the Millennium Stages: 

Figure 6: Kennedy Center's Progress in Implementing Our Recommendations 
to Better Align Its Capital Project Management with Best Practices: 

Figure 7: The Kennedy Center's Full Implementation of Financial 
Policies and Procedures in Several Specific Areas: 

Figure 8: Excerpt from The Kennedy Center's 2005 CBP Showing Eisenhower 
Theater Budget Changes from the 2004 CBP and Projected Obligations, in 
Dollars: 

Figure 9: AFI Theater before and after Its Conversion to the Family 
Theater: 

Figure 10: Diagram of the Kennedy Center's Terrace-Level Public Spaces 
and Theaters: 

Figure 11: Intervals between Operations Committee Meetings, January 
1995 through April 2006: 

Figure 12: Attendance Rates at Operations Committee Meetings, January 
1995 through April 2006: 

Figure 13: Budgeted and Actual Costs of Selected Federally Funded 
Kennedy Center Capital Projects: 

Figure 14: Recommendations to the Kennedy Center in Our April 2005 
Report: 

Figure 15: Implementation Status of our Financial Recommendations in 
Several Specific Areas: 

Abbreviations: 

CMAR: construction manager at risk: 

CBP: comprehensive building plan: 

FMO: Facilities Management Office: 

FAR: Federal Acquisition Regulation: 

GMP: guaranteed maximum price: 

GSA: General Services Administration: 

MOU: memorandum of understanding: 

NARA: National Archives and Records Administration: 

NPS: National Park Service: 

OIG: Office of the Inspector General: 

OMB: Office of Management and Budget: 

PMO: Project Management Office: 

September 15, 2006: 

The Honorable Charles Taylor: 
Chairman: 
The Honorable Norman Dicks: 
Ranking Minority Member: 
Subcommittee on Interior, Environment, and Related Agencies: 
Committee on Appropriations: 
House of Representatives: 

The John F. Kennedy Center for the Performing Arts (Kennedy Center) 
opened in 1971 as a national cultural arts center and presidential 
memorial. Every year, millions of people either visit the Kennedy 
Center to view the center and memorial or to attend live performances. 
Since at least 1990, the Kennedy Center facility has needed substantial 
capital repairs. At that time, officials from both the Kennedy 
Center[Footnote 1] and the Department of the Interior's National Park 
Service (National Park Service), which then shared responsibility for 
managing the Kennedy Center, acknowledged that the physical condition 
of the center had seriously deteriorated. 

In 1994, legislation was enacted that gave the Kennedy Center Board of 
Trustees sole responsibility for managing the facility. As part of that 
responsibility, the legislation required the Kennedy Center Board of 
Trustees to develop, and annually update, a comprehensive building 
needs plan. In response, the Kennedy Center developed a comprehensive 
building plan (CBP) in 1995 that included an assessment of the facility 
and identified the capital projects considered necessary to repair the 
center and bring it into compliance with current codes for fire safety 
and disabled access.[Footnote 2] The plan consisted of a long-term 
capital repair and upgrade project that, among other things, envisioned 
the center's meeting or exceeding relevant fire safety regulations by 
2008 and addressing disabled access needs. To implement its CBP, the 
Kennedy Center received almost $216 million[Footnote 3] in federal 
funds during fiscal years 1995 through 2006 for capital repairs and 
alterations. 

For more than a decade, we have identified shortcomings in, and made 
recommendations to improve, the Kennedy Center's construction, 
planning, and management processes: (1) In the 1990s, we reported that 
the Kennedy Center did not have sufficient staff capability to 
effectively manage its capital improvement plans;[Footnote 4] (2) In 
2003, we reported that the Kennedy Center needed to strengthen its 
management and oversight of large construction projects, such as the 
garage expansion and renovation project;[Footnote 5] and (3) In 2004, 
we reported that the Kennedy Center had implemented most of the 
projects in its CBP but would likely not complete its plan by 2008, 
given the number and size of the renovation projects that remained to 
be done, the amount of anticipated future appropriations, and the 
likelihood that project budgets may increase as designs are 
completed.[Footnote 6] Most recently, we reported that although the 
Kennedy Center completed four major renovations, each of these projects 
exceeded budget estimates, some by substantial amounts. We also found 
that the Kennedy Center lacked the comprehensive policies and 
procedures needed to adequately safeguard federal funds and did not 
appear to meet fire safety code requirements. Accordingly, we 
recommended in our April 2005 report that the Kennedy Center increase 
its oversight of federally funded capital projects, better comply with 
fire code, and better align its management of capital projects with 
best practices.[Footnote 7] 

To assist Congress, you requested that we examine the Kennedy Center's 
management and oversight of federally funded capital projects. 
Accordingly, this report evaluates (1) the progress the Kennedy Center 
has made in implementing the recommendations in our April 2005 report; 
(2) the status of federally funded capital projects and the planned 
spending of federal funds for capital projects, as shown in the Kennedy 
Center's most recent comprehensive building plan; and (3) the Kennedy 
Center Board of Trustees' responsibilities for federally funded capital 
projects and the extent to which the board fulfills these 
responsibilities. 

To determine the progress the Kennedy Center has made in implementing 
our April 2005 recommendations to increase oversight of its management 
of federal funds, better comply with fire code, and better align its 
management of capital projects with best practices, we reviewed Kennedy 
Center documents, including a 2005 risk assessment and internal audit 
plan; peer reviews of the center's fire-modeling study; annual CBPs; 
Family Theater contract modifications; and contract, financial, and 
project management policies and procedures. In addition, we spoke with 
management officials at the Kennedy Center, General Services 
Administration (GSA), and National Archives and Records Administration 
(NARA). To determine the status of federally funded capital projects 
and the planned spending of federal funds, as indicated by the Kennedy 
Center's most recent CBP, we reviewed the Kennedy Center's 1995 CPB and 
its 2004 and 2005 updates. Specifically, we examined the changes in the 
2005 CBP that were made since the 2004 CBP and developed a list of 
federally funded projects that the Kennedy Center plans to delay or 
defer and reviewed the Kennedy Center's request for additional funds. 
To determine the Kennedy Center Board of Trustees' responsibilities for 
federally funded capital projects and the extent to which the board 
fulfills these responsibilities, we analyzed various federal laws, 
documents from the Board of Trustees and its Operations 
Committee,[Footnote 8] and the annual updates to the CBP. Specifically, 
to examine the extent to which the board fulfills its responsibilities 
for federally funded capital projects, we reviewed Board of Trustees 
and Operations Committee information packets and meeting minutes from 
January 1995 through April 2006 to determine how a variety of capital 
projects were overseen by the board. These projects included, but are 
not limited to, the Opera House renovation, fire alarm system 
replacement, public space modifications, site improvements project, and 
the Family Theater. In addition, we interviewed current and previous 
trustees from the board and congressional staffers that are designees 
of Kennedy Center trustees. We also spoke with Kennedy Center 
management officials about the status of federally funded capital 
projects. To obtain information on how other boards govern, including 
their responsibilities for capital projects and oversight of public 
funds, we interviewed academics that focus on board governance; 
officials from nonprofit board governance associations, and officials 
from arts organizations that have characteristics similar to the 
Kennedy Center. We conducted our work in Los Angeles, California; New 
York City, New York; and Washington, D.C., between October 2005 and 
August 2006 in accordance with generally accepted government auditing 
standards (see app. I for more information on our scope and 
methodology). 

Results in Brief: 

The Kennedy Center has taken steps to implement our oversight, fire 
safety, and capital project recommendations, but more work is needed to 
fully implement them. Since April 2005, the Kennedy Center has fully or 
partially implemented all of our 12 recommendations related to 
increasing oversight of its management of federal funds, better 
complying with fire code, and better aligning its management of capital 
projects with best practices. Specifically: 

* To increase oversight of its management of federal funds, the Kennedy 
Center has implemented our recommendation to work with an independent 
federal government oversight organization, such as the Smithsonian 
Institution Office of the Inspector General (OIG), for audits of the 
center's use of federal funds. In August 2005, the Kennedy Center hired 
a nongovernmental organization to develop a risk assessment and audit 
plan to assist the Kennedy Center Board of Trustees in overseeing the 
center's management of appropriated funds. In July 2006, the Kennedy 
Center finalized a memorandum of understanding (MOU) with the 
Smithsonian OIG for audits of federal funds used for capital projects. 
In addition, the Kennedy Center has contracted with a nongovernmental 
organization to implement the portion of the audit plan that covers the 
federal funds used for operations and maintenance activities. According 
to a Kennedy Center management official, the Kennedy Center selected a 
nongovernmental organization to audit the federal funds used for 
operations and maintenance activities because this approach was more 
efficient and cost effective than contracting with an independent 
federal government organization. 

* To better comply with fire safety code, the Kennedy Center has 
implemented two of our five recommendations in this area--to (1) obtain 
a peer review of its performance-based fire-modeling study and (2) 
manage the storage of combustible materials. In addition, the center 
has partially implemented three of our fire safety recommendations--to 
(1) install exit signs, (2) correct a fire safety deficiency at the 
Millennium Stages, and (3) ensure that doors in key areas provide 
adequate separation from fire. 

* To better align its management of capital projects with best 
practices, the Kennedy Center has implemented four of our six 
recommendations--to (1) design and implement contract and project 
management policies and procedures, (2) control cost growth and 
schedule changes in future capital projects, (3) design and implement 
comprehensive financial management polices and procedures, and (4) 
establish and enforce a documents retention policy. However, the center 
has only partially implemented the remaining two capital project 
management recommendations--to (1) develop as-built drawings to prevent 
costly unforeseen site conditions and (2) provide more timely and 
accurate information about capital projects to stakeholders and 
Congress. For example, the Kennedy Center has created a policy that 
requires as-built drawings of new construction improvements to the 
building. However, this policy does not require the center to integrate 
the individual new construction as-built drawings into one master set 
of centerwide drawings, nor does it require as-built drawings to be 
updated as additional changes to the center are made. 

The most recent update of the CBP--the project-by-project plan for the 
comprehensive capital renovation of the Kennedy Center covering fiscal 
years 1995 through 2008--shows that the Kennedy Center will not 
complete all planned capital renovations within planned time frames and 
budgets. Although the 2005 CBP is better than previous versions because 
it provides information needed to evaluate the progress of federally 
funded capital projects, its new project-by-project budget 
reconciliations fail to show how changes in project budgets have 
affected the overall CBP budget, making it difficult to determine the 
overall impact of the changes on the CBP budget through 2008. According 
to our analysis, these changes will raise the cost of implementing the 
remainder of the CBP (for fiscal years 2006 through 2008) from $48 
million to $58 million--a 21 percent increase over the 2004 CBP. To 
improve information to Congress and the Kennedy Center Board of 
Trustees, we are recommending that the Kennedy Center identify in the 
CBP the impact of changes to individual project budgets on the plan's 
overall budget. The 2005 CBP further shows that the Family Theater was 
completed on schedule in 2005 with limited cost growth, unlike four 
federally funded capital projects that we reviewed in April 2005. 
According to our analysis, the Kennedy Center improved some of its 
contracting practices in completing the Family Theater project, but did 
not comply with the Federal Acquisition Regulation (FAR) in selecting 
its contracting method. In addition, the Kennedy Center authorized 
contractor work to begin on the Family Theater before establishing a 
guaranteed maximum price for the overall project. Consequently, had any 
cost increases occurred during construction, the Kennedy Center may 
have been obligated to pay for them. To comply with the FAR and prevent 
exposure to cost increases during construction, we are recommending 
that the center comply with the FAR provision regarding alternate 
contracting methods and ensure that contracting costs are agreed to 
before work begins on the project. The 2005 CBP also shows that the 
Eisenhower Theater renovations are scheduled to begin in fiscal year 
2007, but may be delayed. Most terrace-level renovations will not be 
completed by 2008, even though they were originally scheduled for 
fiscal years 2000 through 2005. Finally, in addition to the changes 
identified in the 2005 CBP, more budget increases and project deferrals 
will be necessary before fiscal year 2008, according to Kennedy Center 
management officials. As a result, the Kennedy Center is seeking to 
extend the plan's period of implementation from 2008 to 2012. 

The Kennedy Center Board of Trustees has delegated to management its 
responsibilities for federally funded capital projects, as is typical 
for governing boards; however, it has provided limited oversight for 
these projects. Under the Kennedy Center Act, the Kennedy Center Board 
of Trustees is responsible for developing and annually updating the 
CBP; planning, designing, and constructing capital projects; and 
preparing a budget. Although management performs these 
responsibilities, the board has provided limited oversight of the about 
$121 million appropriated to the center for capital projects since 
2000. For example, for 2000 through 2005, we found no evidence that the 
board had approved the annual updates to the CBP, reviewed management's 
performance in implementing capital projects, or approved the center's 
proposed federal appropriation request, which includes funding for 
capital projects. These actions are all required by the board's 
policies and procedures manual. We also found that the Operations 
Committee, which the board created to help it carry out its 
responsibilities for capital projects, receives the annual updates to 
the CBP after the center's annual capital project budget is finalized, 
limiting the board's ability to ensure that the federally funded 
capital projects proposed in the CBP are in accordance with the 
requirements of the Kennedy Center Act. 

According to our analysis, several factors limit the board's oversight 
of federally funded capital projects. First, the Kennedy Center Board 
of Trustees lacks procedures on how the board and its Operations 
Committee are to carry out the board's responsibilities for federally 
funded capital projects. Second, attendance at meetings of the Kennedy 
Center Board of Trustees and its Operations Committee has been low, and 
extended periods of time have elapsed between meetings of the 
Operations Committee. Since most of the board's responsibilities are 
carried out at board and committee meetings, it is important for the 
board and its committees to hold regular meetings and for board members 
to attend these meetings. Lastly, the board and its Operations 
Committee lack information needed to monitor and evaluate whether all 
federally funded capital projects have been implemented efficiently and 
in accordance with the requirements in the Kennedy Center Act. Without 
information on original budgeted costs, the board and Operations 
Committee cannot hold management accountable for the implementation of 
federally funded capital projects. 

The board's lack of oversight may have contributed to the Kennedy 
Center's problems keeping federally funded capital projects within 
budget estimates--we found in 2005 that several of the Kennedy Center's 
largest federally funded capital projects exceeded budget estimates by 
amounts ranging from 13 to 50 percent. To strengthen the role of the 
Kennedy Center Board of Trustees', we are recommending that the board 
develop and implement procedures on how it is to carry out its 
responsibilities for federally funded capital projects and ensure that 
it receives information on how federal funds have been used for capital 
projects. 

We provided a draft of this report to the Kennedy Center for review and 
comment. In written comments on the draft report, the Kennedy Center 
generally agreed with our findings and two of our three 
recommendations. Specifically, the Kennedy Center agreed to (1) improve 
the CBP in several areas and (2) review and revise, if necessary, 
procedures on how the Operations Committee is to carry out its 
responsibilities and to provide the CBP to the Operations Committee in 
a more timely fashion. The Kennedy Center disagreed with our 
recommendation that it improve compliance with the FAR provision 
regarding alternative contracting methods and that it establish the 
guaranteed maximum government price for a capital project before 
proceeding with construction. We disagree with the Kennedy Center's 
assessment because we continue to believe that construction manager at 
risk is not covered by the FAR and that establishing a guaranteed 
maximum price prior to proceeding with work limits the government's 
risk of cost overruns. Therefore, we are retaining the recommendation. 
See appendix III for the Kennedy Center's comments and our responses. 

Background: 

The Kennedy Center opened in 1971 and is located on 17 acres along the 
Potomac River in Washington, D.C. The center houses numerous theater, 
exhibition, and rehearsal spaces; public halls; educational facilities; 
offices; and meeting rooms in about 1.1 million square feet of space. 
The plaza level is the primary focus for patrons and tourists, 
including three main theaters, the Grand Foyer, the Hall of States, and 
the Hall of Nations. Access to other areas, such as the roof terrace 
level, is provided through the Grand Foyer, Hall of States, and Hall of 
Nations. Figure 1 provides a diagram of the Kennedy Center's plaza 
level. 

Figure 1: Diagram of the Kennedy Center's Plaza-Level Public Spaces and 
Theaters: 

[See PDF for image] 

Sources: Kennedy Center (data) and HAO (photos). 

[End of figure] 

The National Cultural Center Act of 1958 established the National 
Cultural Center as a bureau within the Smithsonian Institution and 
created a board responsible for constructing and administering the 
nation's performing arts center. The John F. Kennedy Center Act of 1964 
renamed the National Cultural Center as the John F. Kennedy Center for 
the Performing Arts. The Kennedy Center is also a nonprofit 
organization with the authority to solicit and accept gifts. In 1972, 
Congress authorized the National Park Service to provide maintenance, 
security, and other services necessary to maintain the building, while 
making the Kennedy Center Board of Trustees responsible for performing 
arts activities at the Kennedy Center. Under this arrangement, the 
Kennedy Center facility incurred a backlog of capital repairs, in part 
because responsibility for identifying and completing capital repairs 
and improvements at the center was unclear. Legislation was enacted in 
1990 that directed the National Park Service and the Board of Trustees 
to enter into a cooperative agreement clarifying their responsibilities 
for the maintenance, repair, and alteration of the center, but the 
parties were unable to reach an agreement. In 1994, legislation was 
enacted that gave the Board of Trustees sole responsibility for 
carrying out capital improvements at the Kennedy Center. One purpose of 
the 1994 legislation was to provide autonomy for the overall management 
of the Kennedy Center, including better control over its capital 
projects, and to renovate the center. 

Under the Kennedy Center Act, the Kennedy Center Board of Trustees 
currently consists of 59 trustees: 23 are ex officio trustees, 
appointed by virtue of the office or position they hold, including 
congressional members, and 36 are general trustees appointed by the 
President of the United States. Each presidentially appointed trustee 
serves a term of 6 years. As the center's chief decision-making body, 
the Kennedy Center Board of Trustees is responsible for maintaining the 
Kennedy Center as a living memorial to President John F. Kennedy and 
executing other functions required of the board under the act. The 
Kennedy Center Act requires the Board of Trustees to develop and 
annually update a CBP; plan, design and construct each capital project 
at the center; and prepare a budget. The board's policies and 
procedures manual, which includes the board's bylaws, states that board 
responsibilities include approving the annual CBP updates, reviewing 
management's performance in implementing capital projects, and 
reviewing and approving the center's annual capital project budget. The 
Kennedy Center Board of Trustees has a number of standing committees, 
including Executive, Audit, Finance, and Operations committees to 
assist with the board's work. The Operations Committee is responsible 
for overseeing the general operations of the center, as well as all 
capital projects. Figure 2 shows the organization of the Kennedy 
Center, which includes the Board of Trustees and the center's 
management structure as it applies to capital projects. 

Figure 2: Organization of the Kennedy Center for Selected Positions and 
Offices: 

[See PDF for image] 

Source: GAO analysis of Kennedy Center data. 

[End of figure] 

As part of its responsibility under the 1994 legislation, the center 
published its first CBP in 1995, describing the goals of a long-term 
renovation effort, including addressing fire safety and disabled access 
code deficiencies, replacing inefficient building systems, and 
improving visitor services. This original building plan anticipated 
that the proposed capital projects would be completed in two stages. 
Projects in the first stage--fiscal years 1995 through 1999--would 
address critical security and life safety measures and improve 
accessibility. Projects undertaken in the second stage--fiscal years 
2000 through 2009[Footnote 9]--would eliminate the backlog of deferred 
capital repair projects. In 1995, the Kennedy Center anticipated 
undertaking critical fire safety projects by the end of fiscal year 
1999. However, to minimize disruption to performances, the Kennedy 
Center changed its approach to making capital improvements. Rather than 
undertaking broad-scale projects that could disrupt the entire center, 
the Kennedy Center chose to renovate the center incrementally while 
keeping the rest of the center open and operating. 

The center receives annual federal appropriations for capital projects 
based on the CBP and also for the operation, maintenance, and security 
of the facility. The funds appropriated for capital projects remain 
available to the Kennedy Center until they are expended. To implement 
its CBP, the Kennedy Center has received about $216 million since 
fiscal year 1995. This includes $35.3 million transferred from the 
National Park Service and the Smithsonian Institution and about $180.5 
million in appropriated funds. In fiscal year 2006, the Kennedy Center 
received $13 million in federal funds for capital improvement projects 
and $17.8 million for the operation, maintenance, and security of the 
facility.[Footnote 10] According to a Kennedy Center official, this 
amount represents about 18 percent of the Kennedy Center's anticipated 
fiscal year 2006 total operating expenses. The Kennedy Center generates 
the majority of its revenues from performances at the center, 
contributions, and investments. The center's federal appropriations are 
not used for performance-related expenses. 

The law governing facility construction or alteration at the Kennedy 
Center requires that the center be in compliance with nationally 
recognized model building codes and other applicable nationally 
recognized fire safety codes to the maximum extent feasible.[Footnote 
11] As is the case for federal agencies, the Kennedy Center is the 
authority that makes the final determination on whether the center is 
complying with the fire safety code.[Footnote 12] The Kennedy Center 
policy on building codes states that, where feasible, the center will 
comply with the International Building Code (2003), International Fire 
Code (2003), and selected provisions of the National Fire Prevention 
Association Life Safety Code (NFPA 101) (2003). 

The John F. Kennedy Center Act Amendments of 1994 amended the Kennedy 
Center Act to designate the center as a federal entity for purposes of 
the Inspector General Act of 1978 (IG Act), as amended. The Kennedy 
Center Act states that only federally appropriated funds are subject to 
the requirements of a federal entity under the IG Act. The Kennedy 
Center Act authorizes the Smithsonian Institution OIG to audit and 
investigate activities of the Kennedy Center involving federal 
appropriated funds, on a reimbursable basis, if requested by the Board 
of Trustees. In July 2006, the Kennedy Center finalized an MOU with the 
Smithsonian OIG for audits of federal funds used for capital projects. 

The Kennedy Center Has Taken Steps to Implement Our Oversight, Fire 
Safety, and Capital Project Recommendations, but More Work Remains: 

Recently, we recommended that the Kennedy Center increase oversight of 
its management of federal funds, ensure the fire safety of the center, 
and better align its management of capital projects with best 
practices.[Footnote 13] While the Kennedy Center has fully or partially 
implemented all 12 of our recommendations, more work is needed to fully 
implement some recommendations in the areas of fire safety and 
management of capital projects. In particular, the Kennedy Center has 
taken steps to (1) address fire code deficiencies at the Millennium 
Stages, such as providing marked exit routes for occupants; (2) ensure 
that doors in key areas provide adequate separation from fire; (3) 
develop as-built drawings of the center; and (4) provide timely and 
accurate information about capital projects to stakeholders (see fig. 
3). 

Figure 3: Kennedy Center's Progress in Implementing Our 
Recommendations: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

The Kennedy Center Has Contracted for Audits of Its Management of 
Federal Fund Expenditures: 

In April 2005, we reported that the Kennedy Center had limited external 
reviews of how it maintains assurance regarding appropriate management 
of federal funds. Specifically, we found that the costs of four 
federally funded Kennedy Center capital projects exceeded the original 
budgeted costs and that a lack of comprehensive policies and procedures 
limited the Kennedy Center's ability to adequately manage federal 
funds. In addition, in April 2005, we reported that the Kennedy Center 
had not reported annually to Congress and the Office of Management and 
Budget (OMB) on its audit and investigative activities as required by 
the IG Act.[Footnote 14] To increase oversight of the Kennedy Center's 
management of federal funds, we recommended in April 2005 that the 
Kennedy Center work with an independent federal government oversight 
organization, such as the Smithsonian Institution OIG, for audits of 
the center's use of federal funds.[Footnote 15] 

In response to our recommendation, the Kennedy Center hired a 
nongovernmental organization in August 2005 to develop a risk 
assessment and audit plan to assist the Kennedy Center Board of 
Trustees in its oversight of the center's management of federal funds. 
Specifically, the risk assessment and audit plan were created for the 
Facilities Management Office (FMO) and Project Management Office (PMO) 
because the Kennedy Center receives federal funds to support the 
activities of both offices. FMO manages operations, maintenance, and 
contracting, and PMO is one of three offices that conduct capital 
projects for the center.[Footnote 16] The risk assessment was designed 
to provide a summary of the center's potential risks for facilities and 
project management, including the specific risks the center faces in 
its use of federal funds. One such risk identified for project 
management is that capital projects could incur cost and time overruns 
if the project budget or schedule does not sufficiently allow for 
contingencies. The nongovernmental organization also prepared an audit 
plan, which was based on the center's potential facilities and project 
management risks. This audit plan was designed to address the key risk 
issues identified in the risk assessment and provide a strategy for 
another organization to review each risk. For example, to address the 
potential for cost and schedule overruns, an audit of the center's 
project management process was proposed. 

On May 16, 2006, the Kennedy Center awarded a contract to a 
nongovernmental organization to implement the audit plans for FMO 
activities. A Kennedy Center official told us that the nongovernmental 
organization began the FMO audit work several days after the contract 
was awarded. On July 25, 2006, the Kennedy Center finalized an MOU for 
the Smithsonian Institution OIG to conduct audits, on a reimbursable 
basis, of PMO activities. Specifically, the Smithsonian Institution OIG 
will conduct two audits on aspects of the center's capital project 
management process. The Smithsonian OIG expects that these two audits 
will take about 1 year. In addition, the Smithsonian Institution OIG 
will submit proposals to the Kennedy Center Board of Trustees for 
subsequent audit coverage. As we reported in April 2005, ongoing 
oversight of the center's use of federal funds is necessary to maintain 
assurance that they are managed appropriately. Therefore, to ensure 
ongoing oversight of the center's use of federal funds, it is important 
that the board examine and pursue future audit proposals from the 
Smithsonian OIG. 

The Kennedy Center Has Taken Some Steps to Implement Our Fire Safety 
Recommendations, but More Work Is Needed: 

In April 2005, we reported that the Kennedy Center did not appear to 
meet some fire safety code requirements. Specifically, we identified 
problems with the performance-based approach the center used to 
overcome a deficiency in the number of emergency exits at the 
center,[Footnote 17] and we identified other code deficiencies in the 
center that were not covered by the performance-based approach. First, 
we found that the Kennedy Center had not fully implemented the 
conditions associated with its performance-based approach, which 
included installing sprinklers at the Millennium Stages and developing 
and implementing a program to manage the storage of scenery, props, and 
other combustible materials. In addition, the Board of Trustees had not 
accepted and adopted the terms of the performance-based approach as 
described in fire code. Since these steps had not been taken, we 
concluded that the performance-based approach was not yet valid for 
satisfying fire code. We also found that the fire-modeling study, on 
which the Kennedy Center's performance-based approach was based, had 
not undergone a peer review. Peer review of modeling studies is a 
common industry practice outlined in fire code. In addition, we 
concluded that a peer review was particularly important for the Kennedy 
Center because the center lacked sufficient on-staff expertise to 
adequately interpret and evaluate the modeling study, and the Kennedy 
Center's fire safety decisions were not subject to external review. 
Other fire code deficiencies remained to be addressed. For example, we 
found that there were no fire-rated doors in some areas that contain 
key emergency systems, and the Millennium Stages did not have two 
different, marked exit routes for occupants or an integrated smoke 
control, sprinkler, and smoke detector system over the stage area, as 
required by fire code. As a result, we recommended that the Kennedy 
Center improve its compliance with applicable fire codes in a number of 
ways (see fig. 4). 

Figure 4: Kennedy Center's Progress in Implementing Our Fire Safety 
Recommendations: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

* The Kennedy Center has implemented our recommendation to obtain a 
peer review of its fire-modeling study. In April 2005, we recommended 
that the Kennedy Center seek a peer review of its fire-modeling study 
of the Grand Foyer, Hall of States, and Hall of Nations to determine if 
the study could be substituted for certain prescriptive fire code 
solutions. In July 2005, the Kennedy Center initiated two separate peer 
reviews, one with GSA and another with a nongovernmental fire 
protection consultant firm. Both peer reviews provided comments and 
expressed concerns about the assumptions used in the center's study. In 
response to the peer reviewers' comments and concerns, the Kennedy 
Center improved and updated its fire-modeling study, which was 
finalized in March 2006. The revised, peer-reviewed modeling study 
concludes that patrons can exit the Kennedy Center before it becomes 
untenable provided that (1) fire protection from the Lower Gift Shop is 
provided and (2) exit signs are installed in the Grand Foyer, Hall of 
States, and Hall of Nations. The Kennedy Center Board of Trustees is 
the authority responsible for determining if a performance-based design 
meets its objectives, as described in fire code. The Chairman of the 
Kennedy Center Board of Trustees stated that after the updated study is 
finalized, the board will determine if it meets design objectives and 
then will formally accept the study and adopt its terms. Although the 
updated study was finalized in March 2006, the Board of Trustees has 
yet to formally accept the study and adopt its terms. The board's 
approval of the assumptions and conditions of the updated study is the 
final step in fully implementing our recommendation. 

* The Kennedy Center has implemented our recommendation to manage the 
storage of combustible materials. In April 2005, we recommended that 
the Kennedy Center meet the objectives of its performance-based study 
by developing and implementing a program to manage the storage of 
scenery, props, and other combustible materials. In April 2005, the 
Kennedy Center developed and implemented a policy to manage fuel load 
by limiting the storage of scenery, stage props, and other combustible 
materials. To implement this policy, a Kennedy Center official conducts 
compliance inspections using a fire and life-safety checklist prior to 
each new show. 

* The Kennedy Center has taken steps to implement our recommendation to 
address the code deficiencies at the Millennium Stages. In April 2005, 
we recommended that the Kennedy Center, in accordance with fire code, 
install an integrated smoke control, sprinkler, and smoke detector 
system over each Millennium Stage area and provide two different, 
marked exit routes for occupants at each Millennium Stage. The Kennedy 
Center believes the Millennium Stages have sufficient fire protection 
systems in place based on the results of its performance model. The 
revised, peer-reviewed modeling study concludes that smoke exhaust and 
sprinkler protection are not needed for the Millennium Stages provided 
the conditions of the revised modeling study are met. The Kennedy 
Center plans to adequately separate the Lower Gift Shop and the plaza- 
level public spaces as part of its life-safety improvements by spring 
2007. Second, a Kennedy Center official said that exit signage is 
temporarily installed to mark the interior exit path during Millennium 
Stage performances and that the center plans to begin installing exit 
signs on the external doors in the Grand Foyer by the end of September 
2006 (see fig. 5). Once the two conditions of the revised modeling 
study have been met, the Kennedy Center will have fully implemented our 
recommendation. 

Figure 5: Location of Exit Signage at the Millennium Stages: 

[See PDF for image] 

Sources: Kennedy Center; GAO. 

[End of figure] 

* The Kennedy Center has taken some steps to implement our 
recommendation to ensure that doors in key areas provide adequate 
separation from fire. In April 2005, we recommended that the Kennedy 
Center comply with fire safety code by ensuring that fire-rated doors 
are installed in key areas to provide adequate separation from fire. In 
March and May 2006, the Kennedy Center had a fire protection inspector 
assess the fire rating of the doors in the fire pump room, Fire Command 
Center and Concert Hall exits. The fire protection inspector found that 
these doors needed some repairs in order to obtain the fire-rating 
label. In response, the Kennedy Center repaired the doors in the fire 
pump room and Fire Command Center and, therefore, the fire protection 
inspector was able to certify that these doors provide adequate 
separation from fire. In addition, the Kennedy Center is making the 
necessary repairs to the doors at the Concert Hall exits to ensure that 
they provide adequate separation from fire. A Kennedy Center official 
stated that he plans to have the Concert Hall exit doors repaired, 
inspected, and labeled as fire-rated by the end of December 2006. Once 
the Concert Hall exit doors have been repaired, inspected, and labeled 
as fire-rated, the Kennedy Center will have fully implemented our 
recommendation. 

The Kennedy Center Has Taken Some Steps to Implement Best Practices to 
Improve Its Capital Project Management, but More Work Is Needed: 

In April 2005, we reported that although the Kennedy Center achieved 
its goal of renovating four key federally funded capital projects, 
costs exceeded budget estimates for each project. Project cost growth 
resulted from modifications made during the renovation process, in 
part, because the Kennedy Center lacked knowledge of the building's 
site conditions. Modifications led to overtime charges paid to meet 
tight construction schedules. In addition, the center may have paid 
more than necessary by negotiating contract modification values after 
work was completed. A lack of comprehensive policies and procedures 
limited the Kennedy Center's ability to adequately safeguard federal 
funds. In addition, the Kennedy Center did not always communicate 
timely or accurate information on project cost growth and schedule 
delays to its board or Congress. In April 2005, we made several 
recommendations to better align the Kennedy Center's capital project 
management with best practices (see fig. 6). 

Figure 6: Kennedy Center's Progress in Implementing Our Recommendations 
to Better Align Its Capital Project Management with Best Practices: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

* The Kennedy Center has implemented our recommendation to design and 
implement contract and project management policies and procedures in 
accordance with prescribed federal guidance. In January 2006, the 
Kennedy Center designed and implemented contract and project management 
policies and procedures to guide various activities related to the 
acquisition of goods and services for its capital improvements program. 
The contract and project policies and procedures were drawn from the 
FAR, which generally applies to federal contracting activities. We did 
not assess the effectiveness of these policies and procedures because 
they were recently implemented. 

* The Kennedy Center has implemented our recommendation to control cost 
growth and schedule changes in the Family Theater by setting more 
flexible construction schedules and improving its management of 
contract modifications. In February 2006, the Kennedy Center 
implemented a contract and project management policy that requires 
contract modification values to be negotiated before work is completed. 
For this report, we performed a limited assessment of the center's 
implementation of this policy based on a review of some Family Theater 
contract modifications. We found that the Family Theater was completed 
on schedule and with limited cost growth. In particular, contractors 
did not proceed with additional work until it was approved by the 
contracting officer, and overtime was not paid to accelerate the 
schedule. The Kennedy Center's progress in setting more flexible 
schedules and improving its management of contract modifications on 
larger federally funded projects, such as the Eisenhower Theater, will 
better indicate whether the center can effectively control cost growth 
and schedule changes. The Kennedy Center estimates that the 
construction period for this project will be from spring 2007 through 
summer 2008. 

* The Kennedy Center has implemented our recommendation to design and 
implement financial policies and procedures to strengthen financial 
management controls in several specific areas (see fig. 7). In January 
2006, the Kennedy Center designed and implemented financial policies 
and procedures for activities funded by federal appropriations. The 
financial policies and procedures were drawn from various laws and 
regulations, including the FAR. Our analysis found that the Kennedy 
Center has implemented our recommendations to ensure that complete, up- 
to-date costs are recognized and used to prepare financial reports and 
that payments to other federal agencies are consistent with the Economy 
Act agreement.[Footnote 18] In addition, the Kennedy Center implemented 
a procedure to ensure that receipt information is recorded and compared 
with field inspection reports to verify the validity of invoices prior 
to payment. The Kennedy Center also developed and effectively 
implemented new policies and procedures to ensure that (1) invoices 
contain sufficient detail to support their accuracy and validity and 
(2) invoices match with inspection reports and previously paid invoices 
to prevent duplicate payments. A more detailed discussion of our 
analysis of the Kennedy Center's implementation of its financial 
policies and procedures can be found in appendix II. 

Figure 7: The Kennedy Center's Full Implementation of Financial 
Policies and Procedures in Several Specific Areas: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

* The Kennedy Center has implemented our recommendation to establish 
and enforce a documents retention policy that allows for accountability 
of the center's federal funds. In June 2006, the Kennedy Center 
established and enforced a documents retention policy and issued a 
procedures manual for federal and nonfederal documents based on 
guidance from several sources, including the Internal Revenue Service, 
NARA, and the Smithsonian Institution. In conjunction with this manual, 
the center developed and implemented a computerized system to assist in 
the storage, retrieval, and destruction of all records. 

* The Kennedy Center has taken some steps to implement our 
recommendation to better develop as-built drawings and better track 
future changes to the center. In January 2006, the Kennedy Center 
created a project management policy that requires as-built drawings of 
any new construction improvements to the building. As-built drawings of 
the new construction will allow the center to better track future 
changes to these areas. However, this policy does not require the 
center to integrate the individual new construction as-built drawings 
into one master set of centerwide drawings nor does it require updating 
as-built drawings as additional changes to the center are made. A 
Kennedy Center official told us that the center agrees that as-built 
drawings of the entire center are needed to prevent costly unforeseen 
site conditions; however, assembling and updating a master set of as- 
built drawings is expensive and not a Kennedy Center priority. 
Nevertheless, since incomplete knowledge of site conditions has 
contributed to cost overruns in the past, it remains important for the 
Kennedy Center to start assembling and consistently updating a 
comprehensive set of as-built drawings of the entire center. 

* The Kennedy Center has taken some steps to implement our 
recommendation to provide timely and accurate information about capital 
projects by detailing their budget, scope, and cost and providing to 
stakeholders an annual reconciliation of the status of all planned, 
delayed, eliminated, and actual projects. We found that the 2005 CBP is 
better than previous versions because it includes the details of, and 
explanations for, project budget changes since the 2004 CBP. The 2005 
CBP also includes the actual and projected obligations for each capital 
project by fiscal year through 2008, the last year of the CBP. Figure 8 
illustrates how the Kennedy Center's 2005 CBP conveys actual and 
projected obligations for the Eisenhower Theater for this period. These 
actions are responsive to our recommendation that the Kennedy Center 
provide more timely and accurate information to Congress and the Board 
of Trustees on the status of all planned and actual projects. 

Figure 8: Excerpt from The Kennedy Center's 2005 CBP Showing Eisenhower 
Theater Budget Changes from the 2004 CBP and Projected Obligations, in 
Dollars: 

[See PDF for image] 

Source: Kennedy Center.  

Note: The Kennedy Center's 2005 CBP section titled "Eisenhower Theater 
Renovation: Comparison with Previous CBP" does not show that the 
numbers indicate dollars. 

[End of figure]

In some instances, we found that the 2005 CBP did not provide timely or 
accurate information about federally funded capital projects. First, 
the 2005 CBP does not include original budgets for several federally 
funded projects, which would be needed to compare actual costs with 
originally budgeted costs to identify project cost overruns. Without 
this information, the Kennedy Center Board of Trustees and Congress 
lack accurate information to monitor and evaluate whether federally 
funded capital projects have been implemented effectively and 
efficiently. Second, the 2005 CBP remains unnecessarily difficult to 
understand. Specifically, it describes its capital renovation efforts 
in two different sections of the report. The first section provides an 
assessment of the different parts of the center and makes 
recommendations for improvement, and the second section lays out 
specific CBP capital projects and budgets. However, there is no 
crosswalk between the recommendations and the federally funded capital 
projects, making it difficult to identify how, or if, each project 
addresses specific facility issues. For example, although the 2005 CBP 
establishes a project numbering system, it does not use the numbering 
system in the other sections of the report to link specific projects to 
the issues discussed, making it difficult to understand how each 
project addresses these issues. 

In addition, the center has not provided accurate or timely information 
to the Kennedy Center Board of Trustees or OMB about the cost of 
federally funded capital projects. The Kennedy Center sends monthly 
reports to OMB that provide detailed information, project by project, 
on budgets and schedules. However, we identified eight capital project 
budgets in the December 2005 OMB reports that do not match the capital 
project budgets in the most recent CBP, which was finalized in December 
2005. For example, the most recent CBP shows that the total projected 
obligations for the Eisenhower Theater are about $15.8 million, whereas 
the OMB report lists the project budget at about $16.8 million. While 
one of these two budget figures may be accurate, it is impossible for 
stakeholders to know which is accurate because the publication date for 
both is the same, December 2005. 

The Kennedy Center Will Not Complete All Planned Capital Renovations 
within CBP Budgets and Time Frames: 

The Kennedy Center's 2005 CBP indicates that the center will need 
additional budget resources to complete the federally funded projects 
remaining in its CBP and that the terrace-level renovations will be 
deferred until after the CBP ends in 2008. However, the 2005 CBP fails 
to calculate the sum of individual project cost changes, making it 
difficult to determine the overall impact of these changes. We found 
that the total budget for the 22 planned, ongoing, or recently 
completed projects in the 2005 CBP has increased by $10 million, or 21 
percent, since 2004, bringing the total cost of the remaining CBP 
projects to $58 million. The 2005 CBP indicates that the Kennedy Center 
completed the Family Theater renovation on schedule in 2005 with 
limited cost growth and plans to begin renovating the Eisenhower 
Theater in 2007. However, the 2005 CBP also indicates that Kennedy 
Center deferred most terrace-level renovations that had originally been 
planned for the CBP, including renovations to the Terrace Theater, 
Theater Lab, States and Nations Galleries, and Atrium. In addition, the 
Kennedy Center has acknowledged, since the 2005 CBP was issued, that 
more budget increases and project deferrals may be necessary before the 
CBP is scheduled to end in 2008. 

Estimated Costs for Remaining CBP Projects Have Increased by $10 
Million, or 21 Percent, Since 2004: 

In accordance with our April 2005 recommendation, the 2005 CBP now 
reconciles the budget changes from the 2004 CBP to the 2005 CBP for the 
22 planned, ongoing, or recently completed projects in the CBP, 
allowing readers to more easily track budget changes for individual 
projects.[Footnote 19] However, these new reconciliations fail to 
calculate the sum of individual project changes, making it difficult to 
determine their overall impact on the CBP budget through 2008. Our 
analysis shows that the cost of the remaining CBP has increased about 
$10 million, or 21 percent, since 2004, bringing the total cost of the 
remainder of the CBP from about $48 million to $58 million for fiscal 
years 2006 through 2008.[Footnote 20] Although the budgets for a number 
of projects have changed since the 2004 CBP, our analysis shows that 
the net increase of about $10 million was generally attributable to 
large increases in the following five projects: 

* The Site Improvements project budget increased by $4.2 million, or 71 
percent, from the 2004 CBP. The 2005 CBP indicated that the Kennedy 
Center needed additional funds to address unforeseen site conditions, 
construction problems, and outstanding contractor claims. Although not 
detailed in the 2005 CBP, outstanding contractor claims on the Site 
Improvements project may cost millions of dollars in federal funds to 
settle, according to a Kennedy Center official. The project includes 
improvements to the service tunnel, plaza, west fascia and safety 
railing, garage, and the streets surrounding the Kennedy Center. 

* The Toilet Room Renovation project budget increased by $2.3 million, 
or 94 percent, from the 2004 CBP. The 2005 CBP indicated that the 
Kennedy Center had expected the project to proceed several years 
earlier than currently scheduled, the planned project costs have since 
escalated, and further increases are anticipated. This project will 
focus on upgrading the toilet rooms throughout the center, including 
finishes, equipment, and flooring of toilet rooms throughout the 
center. 

* The Level A Back-of-House Renovations project budget increased by $2 
million, or 97 percent, from the 2004 CBP. According to the 2005 CBP, 
the budget increased because work was rescheduled to coincide with 
related renovation efforts, such as theater renovations, and changed 
market conditions. This project's goal is to renovate offices, training 
rooms, locker rooms, backstage areas, dressing rooms, wardrobe areas, 
and other miscellaneous nonpublic spaces. 

* The Curtain Wall/Door Replacement project budget increased by $1.5 
million, or 28 percent, from the 2004 CBP. The 2005 CBP indicated that 
the budget grew because of project deferrals, market conditions, and 
extremely high inflation in recent construction costs. This project 
will replace the acoustical glazing on the curtain (nonweight bearing) 
walls for the west plaza level, hall entrances, and roof terrace-level. 

* The Hazardous Materials Abatement project budget increased by about 
$900,000, or 72 percent, from the 2004 CBP. The 2005 CBP indicated that 
the budget increase was due to the asbestos abatement associated with 
the Eisenhower Theater project. Originally, the Kennedy Center planned 
to leave the asbestos undisturbed and unabated, but later decided to 
remove it. The 2005 CBP indicates that the scope of the project 
increased when planning for the Eisenhower Theater revealed a greater 
need for abatement than was previously anticipated. 

Most Plaza-Level Renovations Have Been Completed, but the Eisenhower 
Theater Renovation Is Still in the Planning Stage: 

According to the 2005 CBP, the Kennedy Center still plans to complete 
renovations to the major performance and public spaces located on the 
plaza level within the CBP time frame. The plaza level includes 
interpretive displays about John F. Kennedy and the Kennedy Center and 
consists primarily of four theaters--the Opera House, Concert Hall, 
Eisenhower Theater, and Family Theater (formerly the AFI Theater)--and 
of three main public spaces--the Grand Foyer, Hall of States, and Hall 
of Nations. We reported in 2005 that the Kennedy Center had completed 
renovations to the Concert Hall, Opera House, and plaza-level public 
spaces but that the projects all experienced cost growth because of 
management and construction problems.[Footnote 21] 

The 2005 CBP indicates that the conversion of the AFI Theater into the 
Family Theater was completed in 2005, within established time frames 
and with limited cost growth (see fig. 9). The cost of the project was 
about $9.1 million--an amount that included cost growth, due to change 
orders, that was within the amount allocated for contingency. With 
seating for 320 people, the Family Theater renovation project was 
smaller in scale than other theaters on the plaza level. Kennedy Center 
management officials said that the lower grade finishes of the AFI 
Theater reduced the need to retain acoustic integrity and allowed for 
more detailed investigations during the project's design stage. These 
investigations likely limited the number and severity of unexpected 
site conditions, which contributed to cost overruns for the Concert 
Hall and Opera House renovations. 

Figure 9: AFI Theater before and after Its Conversion to the Family 
Theater: 

[See PDF for image] 

Source: GAO; Kennedy Center. 

[End of figure] 

We also found that the Kennedy Center was more careful in the way it 
handled contract modifications during the construction of the Family 
Theater, which may have contributed further to limiting cost overruns 
on the project. In addition, Kennedy Center management officials said 
that the use of a different contracting approach, called construction 
manager at risk (CMAR), helped the Kennedy Center complete the project 
within budget and on schedule. Under a CMAR arrangement, a construction 
manager is hired as a general contractor to provide services during 
project design and then take over construction as the general 
contractor. We do not believe that the use of CMAR had a significant 
impact on the final cost or timeliness of the Family Theater's 
construction. This is because CMAR contractors increase the price of 
their bid to compensate for the additional risk they take on as part of 
the contract. In addition, we found that the Kennedy Center's use of 
CMAR did not comply with the FAR.[Footnote 22] Specifically, the 
Kennedy Center did not obtain a required deviation from the FAR, and it 
authorized contractor work to begin on the Family Theater before 
establishing the guaranteed maximum price of the project. These actions 
undermined the Kennedy Center's claim of compliance with the FAR. In 
addition, the center's negotiation of prices after work had begun 
placed the government at increased risk of cost overruns. 

The last major project on the plaza level is the renovation of the 
Eisenhower Theater, which will address life safety concerns, upgrade 
finishes, and make the theater accessible to the disabled. With seating 
for a total of 1,100 people in three tiers, the Eisenhower Theater is 
larger than the former AFI Theater. The 2004 CBP indicated that the 
Eisenhower Theater renovation work would begin in fiscal year 2007, 
assuming adequate funding, a schedule that was reiterated in the 2005 
CBP. The project's budget was stable through the 2004 and 2005 CBPs at 
about $15.8 million. However, since December 2005, the project's cost 
has increased $900,000, or 6 percent, because of what the Kennedy 
Center describes as escalating construction costs, among other 
things.[Footnote 23] The 2005 CBP also indicated that the Kennedy 
Center would need to calculate another cost estimate once the schematic 
design is completed. Continued cost growth may hamper the Kennedy 
Center's ability to complete the Eisenhower Theater renovation within 
the CBP's budget and time frame. The President of the Kennedy Center 
told the Board of Trustees' Operations Committee in September 2005 that 
the Eisenhower Theater renovation was then in jeopardy because of 
funding concerns. 

The Kennedy Center Will Not Complete Terrace-Level Renovations by the 
End of the CBP as Planned: 

Although the Kennedy Center's original goal for the CBP was to 
completely renovate the Kennedy Center and meet all life safety and 
accessibility requirements by the end of 2008, we concluded in 2004 
that it was unlikely that the Kennedy Center would be able to meet that 
goal because of increasing project costs and time lines.[Footnote 24] 
Nevertheless, the Kennedy Center indicated in 2004 that it still 
intended to complete the vast majority of the projects in the CBP. 
However, the 2005 CBP shows that the center now plans to defer most 
terrace-level renovations beyond the end of the CBP. The terrace level 
of the Kennedy Center sits above the plaza level and comprises the 
Terrace Theater, the Theater Lab, States and Nations Galleries, Atrium, 
and two restaurants.[Footnote 25] (See fig. 10). 

Figure 10: Diagram of the Kennedy Center's Terrace-Level Public Spaces 
and Theaters: 

[See PDF for image] 

Sources: Kennedy Center; GAO. 

[End of figure] 

According to the 2005 CBP, sprinklers were extended into the Terrace 
Theater in 2005, and the remaining life safety deficiencies will be 
addressed as part of the Roof Terrace Life Safety Project. The 2005 CBP 
does not describe the Roof Terrace Life Safety Project; but allocates 
$4.5 million for the project and schedules the bulk of the work for 
fiscal year 2007. This budget and schedule, however, are likely to 
change, possibly slipping until after 2008. The budget for the Roof 
Terrace Life Safety Project was estimated in 2002, before the scope was 
set or any detailed planning or design work had been conducted. The 
2005 CBP further notes that the Roof Terrace Life Safety Project may be 
deferred to ensure that the Eisenhower Theater renovation can continue 
on schedule. Given the recent cost growth in that project, deferral of 
the Roof Terrace Life Safety Project seems increasingly likely. The 
scope of the Roof Terrace Life Safety Project has still not been set, 
making it difficult to evaluate the feasibility or adequacy of the 
project. The 2005 CBP indicates that the project will extend sprinklers 
to the States and Nations Galleries, protect the Terrace Theater exit 
stairway from fire, and consider other projects unrelated to life 
safety during planning. 

Apart from the Roof Terrace Life Safety Project, the 2005 CBP indicated 
that the Kennedy Center is deferring or placing a low priority on other 
terrace-level projects. Specifically, the Kennedy Center is deferring 
the following projects: 

* Terrace Theater renovation. Originally scheduled for fiscal year 
2005, the major portions of the Terrace Theater renovation have been 
deferred beyond the time frame of the CBP,[Footnote 26] including 
associated renovations to the auditorium, lobby, hallways, backstage 
areas, and some technical systems. With seating for 513 people, the 
Terrace Theater is the largest performance space on the terrace level. 
It was opened in 1978 and is in need of renovation because it does not 
currently offer accessibility for the disabled throughout the 
auditorium and suffers from other deficiencies in acoustics and 
finishes. 

* Theater Lab renovation. Originally scheduled for fiscal year 2001, 
renovations of the Theater Lab--a 398 seat theater--have mostly been 
deferred, including previous plans to address deficiencies related to 
disabled access, acoustics, and support spaces. 

* Terrace-level public spaces. Originally scheduled for fiscal year 
2000, repairs of known architectural and finish deficiencies throughout 
the terrace-level public spaces will not be done as part of the CBP. 
Affected spaces include the States and Nations galleries and the 
atrium. According to the 2005 CBP, the terrace-level public spaces 
suffer from a number of problems--including deteriorated floor tiles, 
poor accessibility to restrooms, inadequate circulation patterns, and 
muddled acoustics--that will only be considered as funding allows. 

Since the 2005 CBP was issued, the Kennedy Center has indicated that 
additional deferrals will be necessary. The President's fiscal year 
2007 budget provides $4.9 million less than was projected in the 2005 
CBP. If this amount becomes the final budget, the Kennedy Center will 
further defer or reduce several projects whose costs have grown, 
including the Curtain/Wall Door Replacement, Toilet Room Renovation, 
and Level A Back-of-House renovation. In addition, the Eisenhower 
Theater renovation's cost growth may necessitate additional deferrals 
to other projects. Because the CBP will not be completed in 2008 as 
planned, the Kennedy Center has hired a consulting firm to survey the 
Kennedy Center and recommend center upgrades that have not yet been 
completed, with a goal of extending the CBP's implementation period to 
2012. A Kennedy Center official told us that projects not completed by 
2008 as planned will be included in this new building survey. 

The Kennedy Center Board of Trustees Has Delegated Its Responsibility 
for Federally Funded Capital Projects, but Has Provided Limited 
Oversight: 

Under the Kennedy Center Act, the Board of Trustees is responsible for 
developing and annually updating the CBP; planning, designing, and 
constructing capital projects; and preparing a budget. Consistent with 
the practices of other governing boards, the Kennedy Center Board of 
Trustees has delegated these responsibilities to management. Although a 
board can delegate responsibilities to management, it remains 
responsible for overseeing management's work. We found that the Kennedy 
Center Board of Trustees provides limited oversight of its federally 
funded capital projects. Specifically, we found no evidence that the 
board, as required by its policies and procedures manual, approves the 
annual updates to the CBP, reviews management's performance in 
implementing capital projects, or approves the annual capital project 
budget. Furthermore, the Kennedy Center Board of Trustees has provided 
limited oversight to ensure that its appropriated funds are used 
efficiently, effectively, and in compliance with applicable laws. Three 
factors limit the board's oversight of federally funded capital 
projects. First, it lacks procedures on how to carry out its 
responsibilities for federal funds. Second, attendance at board and 
Operations Committee meetings has been low, and the Operations 
Committee has met infrequently and at irregular intervals. Third, the 
board does not receive information needed to evaluate whether federally 
funded capital projects have been implemented efficiently. 

The Kennedy Center Board of Trustees Provides Limited Oversight of 
Federally Funded Capital Projects: 

According to the Kennedy Center Act, it is the board's responsibility 
to develop and annually update the CBP, which serves as the center's 
long-term capital planning document. The board has delegated the annual 
update of the CBP to the center's PMO and a consulting firm.[Footnote 
27] Although such delegation is not uncommon for a governing board, we 
found that the Kennedy Center provides limited oversight of its 
federally funded capital projects in a number of ways. Our analysis of 
board meeting minutes and information packets, from January 2000 
through January 2006, and interviews with Kennedy Center officials 
revealed no evidence that the board reviews or approves CBP projects 
and budgets as it is responsible for doing, according to its policies 
and procedures manual. A center official told us that each trustee of 
the board does not receive the CBP: only trustees on the Operations 
Committee are in receipt of this document. The Chairman of the Board 
told us that because of its large size, the board rarely discusses 
policy issues at board meetings. Instead, the chairman stated, full 
board meetings are used as a forum for announcements about upcoming 
programs and events. Without an opportunity to review the CBP, the 
board cannot ensure that federally funded capital projects planned for 
construction at the center are in accordance with the requirements of 
the Kennedy Center Act and that the expenditure of federal funds is 
reasonable. 

Both the Kennedy Center Act and the board's policies and procedures 
manual assign budgeting responsibilities to the board for 
appropriations. Under the act, the board is responsible for preparing a 
budget in accordance with specified federal statutes, and under the 
manual, the board is responsible for approving the Kennedy Center's 
budget, which includes private and federal funds. The President of the 
Kennedy Center stated that management verbally presents the proposed 
federal appropriation request to the board, which is the federal 
portion of the center's budget, for approval. In addition, the 
President of the Kennedy Center told us that the Operations Committee 
also approves the proposed federal appropriation request for the 
center's capital projects and operations and maintenance. However, in 
our analysis of board and Operations Committee meeting minutes from 
January 1998 through September 2005, we found no evidence that the 
board or its Operations Committee had approved the center's proposed 
federal appropriation request. For example, in the September 2005 
Operations Committee meeting minutes, a Kennedy Center official 
reported to the trustees of the Operations Committee that the center's 
fiscal year 2007 request for appropriations had already been submitted 
to OMB. In addition, the Chairman of the Board of Trustees and the 
Chairman of the Operations Committee told us that they were not certain 
if the board approved the federal portion of the center's budget. 
However, although this report does not include a review of the center's 
private funds, our analysis of board meeting minutes found that the 
Kennedy Center Board of Trustees approves the center's budget for trust 
funds. 

In contrast, we found that the Smithsonian Institution Board of 
Regents--which also oversees federal appropriations for capital 
projects and trust funds, oversees several arts organizations, and has 
its board membership defined by legislation--does review and approve 
the federal portion of its budget.[Footnote 28] Our analysis of 
Smithsonian Institution Board of Regents meeting minutes found that 
this board first reviews the Smithsonian Institution's budget request 
for appropriated funds. Next, the Board of Regents votes to approve the 
budget request before it is presented to OMB. Finally, the resolution 
made by the Board of Regents states that any changes made to this 
federal request for appropriated funds can be made only with the 
approval of the Board of Regents or the Executive Committee. Since the 
Smithsonian Institution Board of Regents has been authorized to plan 
and construct numerous facilities with federal funds, the board's 
review and approval of the Smithsonian Institution's federal budget 
request is important to ensure that the request for the money is 
consistent with its responsibilities under the law. 

According to the Kennedy Center board's policies and procedures manual, 
it is the board's responsibility to "formulate the organization's 
policies and review management's performance in achieving them," as 
well as, "assist the Chairman in selecting, monitoring, appraising, 
advising, stimulating, and rewarding the President." However, in our 
analysis of board and Operations Committee meeting minutes, as well as 
in interviews with members of management and board members, we found no 
evidence that the board formally evaluates management's performance or 
monitors the president's implementation of federally funded capital 
projects. In addition, the Operations Committee, which receives most of 
the information on capital projects, does not receive the information 
it needs to evaluate federally funded capital projects. For example, 
the Operations Committee does not receive key indicators, such as the 
original versus the actual budget and schedule, to determine if all 
federally funded capital projects are implemented on time and within 
budget. The President of the Kennedy Center told us that he annually 
writes his self-assessment and presents it to the Chairman of the Board 
and to the Personnel Committee. However, the President of the Kennedy 
Center and the Chairman of the Board told us that there are no formal 
evaluation criteria. In particular, there is no standard or goal to 
measure the president's performance in implementing federally funded 
capital projects. In lieu of formal criteria, the Chairman of the Board 
told us that he uses his intuition to assess the president's overall 
performance, including the president's implementation of capital 
projects. 

In contrast, a Smithsonian Institution official said that the 
Smithsonian Institution Board of Regents evaluates the secretary's 
performance annually. According to this official, the secretary, with 
the Board of Regents' approval, sets goals each year that include the 
secretary's ability to complete capital projects on time and within 
budget. At the end of the year, the Board of Regents rates the 
secretary's performance, comparing outcomes with the secretary's 
established goals. In addition, several experts on nonprofit boards 
noted that a formal, periodic, and comprehensive evaluation of a 
nonprofit organization's chief executive is needed to ensure that the 
organization's goals are reached. Furthermore, a routine evaluation of 
a chief executive's work allows the board to see if its decisions are 
being properly executed by management. The board and chief executive 
need to agree on the purpose and process of a formal performance 
evaluation, including the primary criteria to be used for review, such 
as the chief executive's annual goals and objectives for the 
organization. 

Several Factors Limit the Board's Oversight of Federally Funded Capital 
Projects: 

Like other organizations that receive federal funds, the Kennedy Center 
Board of Trustees must ensure that appropriated funds are used as 
productively as possible, achieve intended goals and objectives, and 
are spent in compliance with applicable laws. However, several factors 
limit the Kennedy Center Board of Trustees' oversight for federally 
funded capital projects. 

The Board and Its Operations Committee Lack Procedures on How to Carry 
Out Their Responsibilities for Federally Funded Capital Projects: 

The Kennedy Center Act generally describes the board's responsibilities 
for capital projects, such as its duty to maintain the functionality of 
the center at current standards of life, safety, security, and 
accessibility. Although, the act is not specific about how the board is 
to carry out its responsibility for federally funded capital projects, 
it authorizes the board to create bylaws, rules, or regulations, as it 
deems necessary, to administer its responsibilities under the Kennedy 
Center Act. When the Kennedy Center Act was amended in 1994 to give the 
board sole responsibility for capital projects, the board used this 
authority to create the Operations Committee--a committee of the board-
-to help it carry out this responsibility. 

The board's policies and procedures manual provides information on the 
board's responsibilities, the center's organizational structure, and 
performance activities. In addition, the board has created bylaws that 
describe the general duties of board members, officers of the board, 
and a certain number of committees of the board. However, neither the 
manual nor the bylaws describe how the board or its Operations 
Committee is to administer its responsibility under the Kennedy Center 
Act for federally funded capital projects. This lack of procedures 
hinders the board and its Operations Committee in assessing whether 
federal funds for capital projects have been spent efficiently, 
effectively, and legally. In addition, a board expert stated that 
committees need clear direction to perform well and to avoid confusion 
and conflict over their responsibilities and the amount of authority 
delegated to them. This board expert also stated that carefully written 
policies are needed to help avoid unnecessary confusion and conflicts. 

The board's lack of procedures for carrying out its Kennedy Center Act 
responsibilities relating to federally funded capital projects has led 
to a number of different interpretations by Kennedy Center trustees and 
a management official on how the board accomplishes its 
responsibilities for federally funded capital projects and on the 
Operations Committee's overall responsibility. For example, the board 
has created and relies on the Operations Committee to assist in the 
oversight of federal funds spent for capital projects. Although a 
Kennedy Center management official, a previous trustee, and a current 
trustee stated that the Operations Committee had some jurisdiction over 
capital projects, they did not agree on the committee's 
responsibilities and how it accomplishes its responsibilities. The 
previous trustee stated that the responsibility of the Operations 
Committee is to keep Members of Congress that are trustees abreast of 
how capital projects are progressing. The current trustee stated that 
the Operations Committee's responsibility is strictly one of oversight 
for capital projects and that any policies relating to capital projects 
are made by the board's Executive Committee. The Kennedy Center 
management official stated that the Operations Committee's 
responsibility is to make policies relating to capital projects and 
oversee the implementation of these policies. Furthermore, we reported 
in 1998 that the Operations Committee provided policy guidance, 
resolved the most serious issues requiring board input, and functioned 
as the eyes and ears of center operations. 

Board Meeting Attendance Rates Have Been Low, and the Operations 
Committee Has Not Met Regularly: 

Since most of a board's responsibilities are carried out at board and 
committee meetings, it is important for a board and its committees to 
hold meetings regularly and for board members to attend these meetings. 
However, we found that attendance at board and Operations Committee 
meetings has been low and that the Operations Committee has met 
infrequently and at irregular intervals. Low attendance rates and 
infrequent committee meetings limit the board's ability to monitor and 
review management's implementation of federally funded capital 
projects. 

Despite congressional and board efforts to develop more active trustees 
and increase attendance rates, trustee attendance rates at regularly 
scheduled board meetings have been low. In 1994, when Congress amended 
the Kennedy Center Act and gave the board sole responsibility for 
capital projects, it also reduced the term length of trustees from 10 
to 6 years. Congress believed that the shorter term would result in the 
selection of trustees who would be more active members of the board. 
Despite this change, the percentage of trustees attending each board 
meeting from 1995 through 2005 has ranged between 29 and 58 percent. 
The Executive Committee first tried in 1997 to improve attendance at 
board meetings by reducing the annual number of meetings from four to 
three because of low attendance. Then in 2000, a private consulting 
firm, hired by the Kennedy Center, found that the board's governance 
could be strengthened by creating mechanisms to ensure more balanced 
involvement from all trustees. The consulting firm recommended that the 
center use attendance at meetings as a requirement for retaining board 
membership. In response, the board instituted an attendance policy that 
requested trustees to attend a minimum of three full board or committee 
meetings annually to retain their trustee status. However, despite 
these efforts, attendance rates at board meetings have never been above 
58 percent. Trustees told us that the volunteer nature of board 
membership and the geographic location of members' residences have led 
to poor attendance rates. Another trustee said that many trustees see 
their appointments as "honorific" and that their main responsibilities 
are to make donations to and raise funds for the center. The trustee 
further stated that the majority of decisions are made by the president 
and not by the board. 

In analyzing attendance rates for meetings of the Smithsonian 
Institution Board of Regents, we found that from January 2000 through 
September 2005, the median attendance rate at board meetings was 69 
percent and ranged from about 47 percent to 94 percent (i.e., one-half 
of these meetings had attendance rates above 69 percent). In contrast, 
from April 2000 through September 2005, the median attendance rate at 
regularly scheduled Kennedy Center Board of Trustees meetings was 49 
percent and ranged from about 37 percent to 58 percent. 

In addition, we found that some Kennedy Center trustees send designees 
to represent them at board and committee meetings. Board experts with 
whom we spoke expressed different opinions about trustees sending 
designees to represent them at board and committee meetings. For 
example, some experts stated that sending a designee to a board or 
committee meeting is not conducive to board governance and is contrary 
to volunteerism. However, another expert told us that there could be 
situations in which the use of a designee would be appropriate, 
provided the designee's responsibility and authority is clarified in 
the board's bylaws. We found that it is unclear what responsibility and 
authority designees have for carrying out the board's responsibilities 
under the Kennedy Center Act. Currently, neither the board's policies 
and procedures manual nor its bylaws address designees' responsibility 
or authority. We found that the Lincoln Center for the Performing Arts-
-which is also a performing arts organization with a governing board of 
comparable size--has defined the responsibility and authority of its 
Board of Directors and of designees in its bylaws. For example, the 
bylaws state that any Lincoln Center board member entitled to a vote at 
a meeting may appoint any other person to act as such member's proxy in 
that member's capacity. In addition, each designee's authority shall be 
revocable at the pleasure of the member who appointed the designee, and 
the designee can serve no longer than 11 months from date of 
appointment unless otherwise stated by the member. 

The Operations Committee has also met infrequently, and attendance at 
its meetings has been low. In 1994, when the board was given 
responsibility for the center's capital projects, the board created the 
Operations Committee to ensure the appropriate use of federal funds 
spent for capital projects at the Kennedy Center. However, the 
Operations Committee's ability to ensure the appropriate use of federal 
funds has been hindered by the infrequent meetings and low trustee 
attendance rates. From 1995 to 1998, the Operations Committee met three 
times a year. However, from 1998 through 2005, the Operations Committee 
met inconsistently and infrequently, even though several federally 
funded capital projects were in progress at the Kennedy Center (see 
fig. 11). For example, during the most recent period without a 
committee meeting, which lasted about 12 months, center management 
obligated about $21 million for 13 federally funded capital projects. 
The Operations Committee Chairman told us that currently the committee 
meets twice a year and that this is sufficient to oversee capital 
projects. 

Figure 11: Intervals between Operations Committee Meetings, January 
1995 through April 2006: 

[See PDF for image] 

Source: GAO analysis of Kennedy Center Operations Committee meeting 
minutes. 

[End of figure] 

In addition, trustee attendance rates at Operations Committee meetings 
have been low. From January 1995 through April 2006, there were 18 
Operations Committee meetings, of which attendance records were 
available for 13. Of these 13 meetings, 10 had attendance rates of 50 
percent or less (see fig. 12). A former Operations Committee Chairman 
stated that, because the Operations Committee was composed of ex- 
officio congressional members, it was difficult to schedule a time when 
members could be present. 

Figure 12: Attendance Rates at Operations Committee Meetings, January 
1995 through April 2006: 

[See PDF for image] 

Source: GAO analysis of Operations Committee information packets. 

Note: The Operations Committee met 18 times from January 1995 through 
April 2006. However, attendance data were available for only 13 of 
these meetings, as indicated in figure 12. 

[End of Figure] 

Lack of Information Has Prevented the Board and Its Operations 
Committee from Monitoring the Implementation of Federally Funded 
Capital Projects: 

In general, to measure if a capital project has been successfully 
implemented, a board or committee would need information on (1) the 
actual cost of the project versus the budgeted cost, (2) the actual 
schedule of the project versus the original schedule, and (3) if the 
project provided the benefits intended.[Footnote 29] Providing these 
types of information to the board pressures the project team to meet 
the established cost, schedule, and performance goals for the project. 

Although the Operations Committee receives some of this information on 
federally funded capital projects, we found that it lacks key 
information needed to ensure that the project team is implementing 
capital projects within cost and schedule goals. The Operations 
Committee is to meet twice a year, and its trustees receive an 
information packet before each meeting. In reviewing meeting packets 
for January 2000 through September 2005, we found that these packets 
generally included information on ongoing federally funded capital 
projects, such as the amount of previous, actual, and projected 
obligations for each capital project, by fiscal year, and a description 
for each capital project. This information is useful to understand 
current and future obligations for each project. However, the meeting 
packets did not include the baseline cost and schedule estimates that 
would indicate if an ongoing project is within the budget or on 
schedule. Without baseline cost and schedule estimates, the Operations 
Committee and subsequently the board cannot identify project cost 
growth or schedule changes. For example, our analysis found that during 
a January 2003 Operations Committee meeting, a Kennedy Center official 
stated that the site improvement project would not require more than 
$40 million in federal funds. However, in April 2005, an Operations 
Committee information packet indicated that the center had obligated 
approximately $49.8 million for the site improvement project. The most 
recent CBP states that the total anticipated federal portion of the 
project's cost will be about $54.7 million, or about $15 million more 
in federal funds than center management officials told the Operations 
Committee in 2003. Although the Operations Committee had received 
information anticipating that additional funds would be needed for the 
site improvement project, it did not simultaneously receive information 
on the project's original budgeted cost, which would have indicated the 
degree of cost growth on the project. Without information on original 
budgeted costs, the committee cannot hold management accountable for 
the successful implementation of capital projects paid for with federal 
funds. 

The President of the Kennedy Center stated that the Operations 
Committee does receive information on capital projects that enables it 
to compare actual costs with budgeted costs and schedules. However, our 
analysis of Operations Committee meeting packets from January 1998 
through September 2005 found no indication that Operations Committee 
members received information for comparing the actual cost with the 
original budgeted cost. Additionally, although the center's most recent 
Operations Committee packet, dated April 2006, contains the original 
budgeted costs for 6 capital projects, this information is missing for 
the remaining 17 capital projects listed. Thus, although this packet 
provides improved budget information to stakeholders, it does not allow 
trustees to monitor the implementation of all federally funded capital 
projects. In addition, when we spoke with the Operations Committee 
Chairman about the board's use of budgeted versus actual information, 
he stated that he leaves it up to management to ensure that costs are 
within established budgets. 

As we have reported previously, the implementation of a capital 
project's success is determined primarily by whether the project was 
completed on schedule, within budget, and provided the benefits 
intended.[Footnote 30] Without this information the Operations 
Committee is unable to assist the board in its oversight of the federal 
funds spent for capital projects. For example, in April 2005, we 
reported that since 2003, each of the three federally funded capital 
projects that we reviewed had experienced cost overruns, one as great 
as 50 percent (see fig. 13). However, we did not find any evidence that 
the board or its Operations Committee was informed of these cost 
overruns, such as the Opera House's $4 million cost increase. For 
example, two trustees that served on the board during the 
implementation of these projects told us that they did not know of any 
capital projects that had cost overruns. One of these trustees said 
that the Opera House renovation was on budget. 

Figure 13: Budgeted and Actual Costs of Selected Federally Funded 
Kennedy Center Capital Projects: 

[See PDF for image] 

Source: GAO analysis of Kennedy Center data. 

[End of figure] 

In addition to the information packets, the Operations Committee 
receives the center's annual CBP. Previously, we mentioned that the 
center's 2005 CBP is better than previous versions because it includes 
the details of, and explanations for, project budget changes since the 
2004 CBP. The 2005 CBP also includes the actual and projected 
obligations for each capital project, by fiscal year, through the end 
of the CBP in 2008. However, the 2005 CBP does not provide original 
project budgets for all capital projects. Therefore there is no way to 
quantify how well the project's implementation matched the center's 
original comprehensive plan. In addition, we found that trustees of the 
Operations Committees did not receive the most recent CBP in a timely 
manner. For example, the Operations Committee received the most recent 
CBP in January 2006, about 4 months after the center's fiscal year 2007 
budget was submitted to OMB. Without an opportunity to review the CBP 
before the budget is submitted to OMB, the committee cannot ensure that 
federally funded capital projects planned for construction at the 
center are authorized by the Kennedy Center Act. 

Conclusions: 

We have made numerous recommendations to the Kennedy Center within the 
past 9 years to improve its use and oversight of the federal funds that 
it receives, and the Kennedy Center has made significant improvements. 
Specifically, the Kennedy Center has made considerable progress over 
the past year in implementing our recommendations to improve fire 
safety and project management and to better align its activities with 
capital project best practices. Nevertheless, although some of our 
recommendations have not been fully implemented, it is critical that 
the Kennedy Center fully implement our recommendations and ensure that 
these changes become permanent. 

Changes to the Kennedy Center's contracting practices and CBP provide 
good illustrations of the progress that the Kennedy Center has made and 
the work that remains. Since 1993, when we first began reporting on its 
capital improvement plan, the Kennedy Center has made a number of 
important improvements to its contracting management practices and to 
the CBP. For example, in 2005, the Kennedy Center added project-by- 
project reconciliations to the CBP as recommended in order to 
illustrate changes in project budgets and schedules over time. However, 
the Kennedy Center placed federal funds at risk by not fully complying 
with the FAR, and the CBP does not yet fully disclose the overall 
financial impact of project changes. During a time when the Kennedy 
Center is deferring many of its terrace-level renovations, the price of 
the CBP's implementation is growing because of steep increases in the 
costs of some of the remaining projects. While many of the key facts 
are included in the 2005 CBP, putting the whole picture together 
requires gathering and analyzing information from previous and current 
versions of the CBP to ascertain how budget changes to individual 
projects affect the overall CBP budget through 2008. 

Much of our Kennedy Center work has found insufficient oversight for 
federally funded capital projects. Although the board has delegated 
much of the day-to-day work of running the center to the center 
management, the board retains ultimate responsibility for safeguarding 
funds and holding the center management accountable for its actions. 
Yet the board is providing limited oversight of its federal funds spent 
on capital projects; it does not approve CBP updates, does not review 
management's performance in implementing capital projects in a 
structured way, and does not meet regularly. It may be telling that the 
board provides more oversight of its nonappropriated funds, including 
programming revenue and investment income. More detailed, transparent, 
and timely information on how federal funds have been budgeted and 
spent would allow the board to hold center managers accountable for 
completing federally funded capital projects on time and within budget 
estimates. 

Recommendations for Executive Action: 

1. To improve compliance with the FAR, the Chairman of the Board of 
Trustees should direct the President of the Kennedy Center to properly 
obtain the required FAR deviation when using the construction manager 
at risk contracting method. In addition, the Kennedy Center should 
establish the guaranteed maximum government price for a capital project 
before proceeding with construction. 

2. To improve the information the Kennedy Center provides to Congress 
and the Board of Trustees, the Chairman of the Board of Trustees should 
direct the President of the Kennedy Center to improve the Comprehensive 
Building Plan by taking the following two actions: 

* Clearly identify the overall impact that changes to individual 
project budgets from the previous year will have on the overall plan's 
budget. 

* Clarify which federally funded projects the Kennedy Center intends to 
complete as part of the plan and which ones will be deferred. In doing 
so, establish clear scope and budget estimates for the Roof Terrace 
Life Safety project for the 2006 update of the Comprehensive Building 
Plan. 

3. To strengthen the Kennedy Center Board of Trustees' role in 
overseeing federally funded capital projects and to improve the board's 
ability to carry out its responsibilities under the Kennedy Center Act, 
we recommend that the Chairman and Trustees of the Board take the 
following two actions: 

* Develop and implement procedures on how the board and its Operations 
Committee are to carry out their duties under the Kennedy Center Act 
and their responsibilities for overseeing federal funds, including a 
clarification of the roles and responsibilities of the Operations 
Committee; 

* Ensure that the board receives detailed, transparent, and timely 
information on how federal funds for capital projects have been 
budgeted and spent on capital projects, such as information on original 
versus actual project budgets and schedules. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to the Kennedy Center for its review 
and comment. The Kennedy Center provided written comments, which appear 
in appendix III, together with our responses. In general, the Kennedy 
Center agreed with the draft report's findings and with two of the 
report's three recommendations. The Kennedy Center agreed to (1) 
improve the CBP in several areas and (2) review and revise, if 
necessary, procedures on how the Operations Committee is to carry out 
its responsibilities and to provide the CBP to the Operations Committee 
in a more timely fashion. The Kennedy Center disagreed with our 
recommendation to better comply with a provision of the FAR and 
establish the guaranteed maximum government price for a capital project 
before proceeding with construction. However, based on our discussions 
with a GSA official, we are retaining the recommendation. The CMAR 
contracting method is not covered by the FAR and, consequently, 
requires a deviation. We also believe that the Kennedy Center could 
have limited the government's risk of cost overruns by establishing the 
guaranteed maximum price for the project before authorizing the 
contractor to begin. The Kennedy Center provided technical comments and 
clarifications, which we have incorporated as appropriate throughout 
this report. 

As arranged with your offices, unless you publicly announce its 
contents earlier, we plan no further distribution of this report until 
30 days after the date of this letter. At that time, we will send 
copies to interested congressional committees, the Chairman of the 
Kennedy Center Board of Trustees, and the President of the Kennedy 
Center. We will also make copies available to others on request. In 
addition, the report will be available at no charge on the GAO Web site 
at [Hyperlink, http://www.gao.gov]. 

If you or your staff has any questions, please contact me at (202) 512- 
2834 or goldsteinm@gao.gov. Contact points for our Offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this report. See appendix IV for a list of the major 
contributors to this report. 

Signed by: 

Mark L. Goldstein: 
Director, Physical Infrastructure Issues: 

[End of section] 

Appendix I: Scope and Methodology: 

This report responds to your request that we conduct a study on The 
John F. Kennedy Center for the Performing Arts' (Kennedy Center) 
management and oversight of federal funds spent for Kennedy Center 
projects. Our objectives were to determine (1) the progress the Kennedy 
Center has made in implementing the recommendations in our April 2005 
report, (2) the status of capital projects and the planned spending of 
federal funds for capital projects as indicated by the Kennedy Center's 
most recent comprehensive building plan, and (3) the Kennedy Center 
Board of Trustees' responsibilities for federally funded capital 
projects and the extent to which the board fulfills these 
responsibilities.[Footnote 31] 

To determine the progress Kennedy Center has made in implementing the 
recommendations in our April 2005 report, we interviewed Kennedy Center 
management officials and reviewed Kennedy Center documents (see fig. 14 
for a list of our April 2005 recommendations). Specifically, to assess 
the steps taken to implement the first of these recommendations--that 
the Chairman of the Kennedy Center Board of Trustees increase oversight 
of its management of federal funds by working with an independent 
federal government oversight organization--we analyzed the Kennedy 
Center's risk assessment and internal audit plan for the ongoing 
oversight of the center's use of federal funds. In addition, we 
interviewed Kennedy Center management officials to determine how the 
Kennedy Center intends to implement its internal audit plan. We also 
reviewed the John F. Kennedy Center Act, as amended, and the Inspector 
General Act of 1978, as amended. 

Figure 14: Recommendations to the Kennedy Center in Our April 2005 
Report: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

To assess the steps taken by the Chairman of the Kennedy Center Board 
of Trustees to implement our April 2005 recommendations on fire safety, 
we analyzed the two peer reviews of the Kennedy Center's fire-modeling 
study used as a substitute for prescriptive code solutions that were 
conducted by the General Services Administration (GSA) and a nonfederal 
entity. Additionally, we interviewed Kennedy Center management and GSA 
officials to determine the actions taken to implement recommendations 
from the two peer reviews. To further asses the steps taken to ensure 
fire safety, we reviewed the Kennedy Center's policy and procedure for 
managing the storage of combustible materials; reviewed the Kennedy 
Center's inventory of doors in key areas that needed to be fire rated; 
and toured the Kennedy Center to visually examine the exit signage 
installed at the Millennium Stages during a performance. We also 
interviewed a Kennedy Center management official to determine how the 
Kennedy Center implements its combustibles policy and procedure; the 
time frame for inspecting and installing fire-rated doors in key areas; 
and the installation of exit signs in the Grand Foyer at the Millennium 
Stages. 

To assess the steps taken by the Chairman of the Kennedy Center Board 
of Trustees to implement our April 2005 recommendations on managing 
capital projects, we interviewed Kennedy Center management officials 
and analyzed Kennedy Center documents. Specifically, to determine how 
the Kennedy Center provides more timely and accurate information about 
capital projects to stakeholders, we reviewed the Kennedy Center's 2004 
and 2005 comprehensive building plans (CBP); fiscal year 2007 budget 
justification to Congress; information packets and minutes from Board 
of Trustees and Operations Committee meetings (for 2004 through 2006); 
and the monthly reports the Kennedy Center sends to the Office of 
Management and Budget (OMB) that provide information on capital 
projects. To evaluate the steps taken by the Kennedy Center to control 
cost growth and schedule changes in future capital projects, we 
conducted a limited assessment of Family Theater contract 
modifications. The contract modifications we reviewed each had cost 
changes over $15,000 and in total represented about 58 percent of all 
cost changes for this project. We examined these contract modifications 
to evaluate whether the contractors' proposals were fair and 
reasonable; the Kennedy Center had established the scope and cost for 
the modifications before directing the contractor to proceed with the 
work; and the Kennedy Center paid overtime to accelerate the project's 
schedule. To obtain information on the construction manager at risk 
(CMAR) method of delivery, we reviewed the Federal Acquisition 
Regulation (FAR), GSA policy, and industry standards. We contacted GSA 
officials and an industry official. To assess the steps taken by the 
Kennedy Center to strengthen financial management controls, we analyzed 
the Kennedy Center's contract, financial, and project management 
policies and procedures as they relate to the recommendations in our 
April 2005 report. In addition, we discussed with Kennedy Center 
management officials the time frame for implementation and the federal 
guidance used for the development of its contract, financial, and 
project management policies and procedures. While we did not assess the 
implementation of the Kennedy Center's contract and project management 
policies and procedures because they were recently implemented, we were 
able to assess the adequacy of the Kennedy Center's financial policies 
and procedures that relate to our specific financial recommendations. 
We reviewed the financial policies and procedures and spoke with 
management officials to verify that the policies and procedures 
contained guidance to address our recommendations. Specifically, we 
reviewed receipt information contained on recent invoice certification 
forms, and we also reviewed invoices paid from the Project Management 
Office contractor files where we had noted exceptions in our April 2005 
report. To determine the status of the Kennedy Center's document 
retention policy, we interviewed Kennedy Center management officials to 
discuss the steps taken to establish and enforce a policy. In addition, 
we spoke with National Archives and Records Administration (NARA) 
officials about the requirements for a federal records management 
policy, and we reviewed legislation and regulations relating to NARA. 
To determine the status of the Kennedy Center's steps to better track 
future changes to the center, we spoke with Kennedy Center management 
officials and reviewed the center's project management policy that 
addresses as-built plans. 

To determine the status of capital projects and the planned spending of 
federal funds for capital projects as indicated by the Kennedy Center's 
most recent CBP, we reviewed the Kennedy Center's initial 1995 CBP and 
its 2004 and 2005 updates to the plan. Specifically, we examined the 
changes in the 2005 CBP made since the 2004 CBP and developed a list of 
projects the Kennedy Center plans to delay or defer and the additional 
funds needed. To determine the accuracy of some of the data in the 2005 
CBP, we reviewed the monthly reports the Kennedy Center sends to OMB; 
the Kennedy Center's fiscal year 2007 budget justification to Congress; 
and the President's fiscal year 2007 budget for the Kennedy Center. In 
addition, we spoke with Kennedy Center management officials to obtain 
justifications for the projects it intends to delay or defer. 

To determine the Kennedy Center Board of Trustees' responsibilities for 
federally funded capital projects and the extent to which the board 
fulfills these responsibilities, we analyzed Board of Trustees and 
Operations Committee documents; appropriation laws; the John F. Kennedy 
Center Act, as amended; the CBP and its various updates; and the 
monthly reports the Kennedy Center sends to OMB. Specifically, to 
examine the extent to which the board fulfills its responsibilities for 
federally funded capital projects we reviewed Board of Trustees and 
Committee information packets and meeting minutes from January 1995 
through April 2006 to determine how a variety of capital projects were 
overseen by the board. These projects included, but are not limited to, 
the Opera House renovation, fire alarm system replacement, public space 
modifications, site improvements project, and Family Theater. In 
addition, we interviewed current and previous trustees from the board 
and its Operations and Executive Committees. We spoke with two previous 
and four current trustees about the board's responsibilities for 
overseeing federal funds, including the types of information used to 
make decisions on capital projects. In addition, we spoke with 
congressional staffers that are designees for two Kennedy Center 
Trustees and the President of the Kennedy Center. We selected trustees 
for interviews by first constructing a list of trustees that served on 
the board from 1995 to 2006. We choose 1995 because it was the year 
that Congress transferred responsibility for capital projects from the 
National Park Service to the Kennedy Center Board of Trustees. From 
this list, we selected previous and current trustees of the board and 
its Operations and Executive Committees who were either chairpersons or 
had not missed more than one board meeting per year of their tenure. In 
addition, we interviewed Kennedy Center executives to understand 
management's role in the supervision of capital project costs and 
schedules and management's responsibilities to the Board of Trustees. 

We calculated Board of Trustees and Operations Committee attendance 
rates and meeting frequencies using the information packets, which 
included meeting minutes, sent to trustees before scheduled board and 
committee meetings from January 1995 through April 2006. For the Board 
of Trustees meetings, we calculated attendance rates by comparing the 
number of trustees present at each regularly scheduled meeting with the 
total number of trustees designated under the Kennedy Center Act. For 
Operations Committee meetings, we calculated attendance rates by 
comparing the number of trustees present at each meeting with the 
information packet distribution list and the board's policies and 
procedures manual. We calculated Operations Committee meeting 
attendance rates for the 13 of 18 meetings for which we had 
distribution lists. To ensure that the Kennedy Center provided us with 
all of the Board of Trustees and Operations Committee information 
packets and meeting minutes from January 1995 through April 2006, we 
cross referenced the materials we received against a list that was 
verified for a previous GAO report[Footnote 32] and against the Board 
of Trustees' annual list of scheduled meetings. We are confident that 
we have accounted for all Board of Trustees and Operations Committee 
information packets and meeting minutes from 1995 through 2006 and 
therefore believe that the attendance rate and meeting frequency data 
are reliable for the purposes of this report. To calculate attendance 
rates for the Smithsonian Institution Board of Regents, from January 
2000 to September 2005, we compared the number of regents present and 
absent at each regularly scheduled board meeting with the total number 
of regents set forth in law relating to the Smithsonian Institution. In 
some instances, we found that the number of regents attending and 
absent from meetings did not match the number of regents set forth in 
the law. For example, there were times when a vacancy on the board 
occurred while legislation to appoint a regent was pending. In these 
instances, we had Smithsonian Institution officials verify that during 
some board meetings, the number of regents attending and absent from 
these meetings did not match the number of regents set forth in law. 
Therefore, we believe that the attendance rate data are reliable for 
the purposes of this report. 

To obtain information on board governance practices, we interviewed 
academics, board organizations, and officials of other arts 
organizations. We reviewed relevant articles on board governance to 
select the academic and board organizations. To obtain information on 
how other boards govern, including their responsibilities for 
overseeing capital projects, we interviewed officials and reviewed 
documents from other arts organizations, including the Lincoln Center 
for the Performing Arts, the Los Angeles Music Center, the National 
Gallery of Art, and the Smithsonian Institution. We selected these 
organizations because they all have some features in common with the 
Kennedy Center, including authorizing legislation; capital projects; 
board member composition; organizational mission; and federal funding. 

We conducted our work in Los Angeles, California; New York City, New 
York and Washington, D.C., between October 2005 and August 2006 in 
accordance with generally accepted government auditing standards. 

[End of section] 

Appendix II: Kennedy Center's Implementation of Our Recommendation to 
Design and Implement Financial Policies and Procedures: 

In April 2005, we recommended that the Kennedy Center strengthen 
financial management controls by designing and implementing financial 
policies and procedures in accordance with prescribed federal guidance. 
Specifically, we recommended that the financial policies and procedures 
address several areas, as detailed in figure 15. In January 2006, the 
Kennedy Center designed and implemented financial policies and 
procedures for activities funded by federal appropriations. The 
financial policies and procedures were drawn from various laws and 
regulations including the FAR. As shown in figure 2 and as discussed in 
the remainder of this appendix, the Kennedy Center has fully 
implemented our financial recommendations in several specific areas. 

Figure 15: Implementation Status of our Financial Recommendations in 
Several Specific Areas: 

[See PDF for image] 

Source: GAO. 

[End of figure]  

As figure 15 indicates, we recommended that the Kennedy Center 
recognize and use complete up-to-date costs for construction and other 
services to prepare financial reports and manage project costs. In 
response to our recommendation, the Kennedy Center now submits monthly 
progress reports on its obligations for services and capital federal 
expenditures to OMB. For each capital project, the reports contain the 
month's anticipated, actual, and total up-to-date obligations made with 
federal funds. The center uses a cash basis to report costs in monthly 
financial reports on capital federal expenditures, which is acceptable 
to OMB. Therefore, this recommendation has been implemented. 

In our previous report, we recommended that for Economy Act 
transactions, payments to other federal agencies be for actual costs 
consistent with the Economy Act agreement. In response to our 
recommendation, the Kennedy Center established a policy that requires 
other federal agencies to clearly indicate that they are charging the 
center for actual costs incurred, under an Economy Act agreement. In 
addition, the policy includes an example of a letter that provides 
clear guidance to contracting staff on the language needed to ensure 
that an agency is charging the center for actual costs incurred. 
Therefore, this recommendation has been implemented. 

We recommended that financial policies and procedures ensure that 
receiving reports are prepared when goods or services are received to 
verify the validity of invoices. In response to our recommendation, the 
center's procedures direct staff to enter receiving information on an 
invoice certification form--once the invoice is received--and to 
compare construction invoices to the architect's field inspection 
reports. We examined recent invoice certification forms and found that 
they contained the project title and the period of performance. Each 
invoice certification form we reviewed also included a schedule of 
values detailing (1) the work being billed and (2) the percentage of 
work completed to date. The project title and the period of performance 
provide the information necessary to tie the construction services 
performed to the invoice and to Kennedy Center records. Therefore, this 
recommendation has been implemented. 

We recommended that financial policies and procedures ensure that 
invoices contain sufficient detail to support their accuracy and 
validity. In response to our recommendation, the center's procedures 
direct staff to contact the vendor if additional detail is needed to 
support information on goods or services billed. We reviewed recent 
invoices and found that they now contain sufficient detail to support 
the accuracy and validity of the amounts invoiced. Therefore, this 
recommendation has been implemented. 

Finally, we recommended that the financial policies and procedures 
ensure that invoices are matched against inspection reports and 
previously paid invoices prior to payment to prevent duplicate 
payments. In response to our recommendation, the center's procedures 
direct staff to consider whether goods and services have been billed on 
a previously approved invoice. This procedure also directs staff to 
look for any charges outside the period of billing and provides further 
detail instructing staff on data sources to consider in determining if 
payment has already been made. Therefore, this recommendation has been 
implemented. 

[End of section] 

Appendix III: Comments from the John F. Kennedy Center for the 
Performing Arts: 

Note: GAO comments supplementing those in the report text appear at the 
end of this appendix. 

The John F. Kennedy Center for the Performing Arts: 
Washington, D.C. 20566-0001: 
202 416-8010: 
Fax 202 416-8018: 

August 24, 2006: 

Mr. Mark L. Goldstein: 
Director, Physical Infrastructure Issues: 
United States Government Accountability Office: 
441 G St. NW: 
Washington, DC 20458: 

Dear Mr. Goldstein: 

On behalf of the Trustees and the staff of the John F. Kennedy Center 
for the Performing Arts, I want to thank you and your team from the 
Government Accountability Office for forwarding the draft report, "Some 
Progress Made on GAO Recommendations, but Oversight Challenges Still 
Exist," received August 7, 2006. We appreciate the time and efforts of 
the GAO team that completed this evaluation. 

While there are several specific issues raised in this report that we 
will address in this response, it is important to state at the outset 
that the Kennedy Center has addressed every recommendation made by the 
GAO in April 2005. We acknowledge that, in a few cases, implementation 
of your recommendations will only be completed in the coming months. 
However, comprehensive programs to address GAO's recommendations have 
been initiated in every instance. 

It is also essential to indicate that the Center has made great strides 
in budgeting for and managing capital projects. Over the past two 
years, we have completed six major projects. Every one has been 
completed for less than budgeted amounts. The construction of our new 
Family Theater, with a nine million dollar budget, was the largest of 
these projects and was completed at 5300,000 less than the budgeted 
cost. The Kennedy Center is proud that it has made such great strides 
in its capital project management capability. 

With regards to the specific recommendations for executive action 
included in this draft report: 

1. The Center has been and will continue to be in compliance with the 
FAR. In our opinion; a - FAR deviation is not required when using a 
Construction Manager at Risk (CMAR) contracting method. Prior to 
executing the Family Theater contract, we consulted with GSA, which 
informed us at the time that they do not implement deviations for CMAR 
projects. We also learned that the U.S. Army Corps currently utilizes 
CMAR without processing deviations. We therefore believe that our 
actions conform to current thinking on CMAR contracting methods. 

Simply put, differences of opinion on this subject exist because the 
FAR does not explicitly address CMAR. However, we believe the CMAR 
approach is consistent with tine contracting deliveries outlined in FAR 
16.101 (for incentive contracting) and in FAR 2.101 (for best value 
selection). Furthermore, according to the FAR, the contractor must be 
responsible for performance and cost, with profit and fee tailored to 
the uncertainties involved in the contract performance, all of which 
are consistent with the approach taken under CMAR. 

Regarding the timing for the establishment of the guaranteed maximum 
price (GMP) for a CMAR project, we disagree that the GMP must be 
established prior to initiating construction, and we certainly disagree 
with the assertion that the timing of the Family Theater GMP increased 
the risk of cost overruns. As defined by the American Institute of 
Architects (AIA) Document A121/CMc, the GMP is the sum of the cost of 
the work and the Construction Manager's fee. One of the benefits of a 
CMAR contract is that transparency is enhanced and therefore, because 
the Construction Manager's books, including subcontractor bids, are 
open to the owner, flexibility exists in the exact timing for 
finalizing the GMP. In addition, the Center's authorization to award 
strategic trade contracts prior to finalization of the GMP provided a 
financial benefit to the project, particularly for the steel contract. 
By awarding the contract several months prior to finalizing the GMP, 
prices were locked in and further escalation in a rapidly changing 
market was avoided. Given the extreme escalation that existed in early 
2005, this action was clearly in everyone's best interests and put the 
Center at no additional risk. The Construction Management Association 
of America (CMAA), the source of the "industry standards" referenced by 
GAO, reviewed and endorsed the Center's process, particularly the 
willingness to share the risk with the contractor to save taxpayer 
dollars prior to setting the GMP. 

2. The Center will continue to improve the information provided to 
Congress and the Board of Trustees by: 

* More clearly identifying how changes in project budgets (due to 
changes in scope, appropriations levels and/or economic conditions) 
will affect the overall comprehensive building plan. This information 
is provided in the Operations Committee notebooks, but it will now also 
be included in the comprehensive building plan (CBP). 

* Identifying the projects that will be deferred due to changes in 
scope, appropriations levels or economic conditions. This information 
is provided in the Operations Committee briefings, but will also be 
incorporated into the CBP. 

3. In response to the recommendation to strengthen the Board's 
oversight of federally funded capital projects, the Center will: 

* Review and revise, if necessary, the policies and procedures of the 
Operations Committee to communicate more clearly the responsibilities 
of the Committee. 

* Realign the schedule of the annual updates of the Comprehensive 
Building Plan (CBP) for review and approval by the Operations Committee 
in advance of the budget cycle. 

The format of the information provided to the Operations Committee 
regarding capital project budgets at various stages of the development 
of the projects has already been changed for the next meeting in 
September to communicate in a more transparent fashion the budgets at 
various stages of project development from preliminary estimates to 
final project budgets. 

The details of the report are addressed below. 

Progress in Implementing Oversight, Fire Safety and Capital Project 
Recommendations: 

On Page 14, Figure 3, the report identifies six recommendations as 
being partially complete; the steps taken to complete these 
recommendations are detailed on the following pages. 

1. Work with an independent federal government oversight organization. 

The Center engaged an independent audit firm in May 2006 and the 
Smithsonian Institute Office of the Inspector General (SOIG) in July 
2006 to conduct the recommended audits delineated in the fall 2005 risk 
assessment. More specifically, the risk assessment advised that 
proposed audits of the Facilities Management Office (FMO) should be 
treated as a priority. It was considered to be most expeditious and 
cost effective to expedite implementation of the audit recommendation 
by contracting an independent firm, reporting directly to the Board, to 
conduct those FMO audits. The independent, non-governmental firm could 
be contracted quickly and could begin the audits immediately after 
contract award. As illustration, the audit work was initiated 
approximately sixty days after the solicitation date, whereas, the 
Memorandum of Understanding with the SOIL was not signed until 
approximately five months after the initial meeting. In addition, the 
independent organization, through a variety of on-staff subject matter 
experts, has access to specialized resources that can be tasked to 
conduct the audit without delay. Conversely, the SOIG must hire staff 
specifically for this engagement; therefore it will take some time for 
the SOIL to staff up. In addition, the independent organization is more 
cost effective, as illustrated by the fact that the audits for which 
the SOIG has been engaged will cost significantly (d4% or $91,000) more 
than estimated in the risk assessment. 

In the implementation of this recommendation the Center believes that 
it has acted prudently, expeditiously, and used its limited resources 
most efficiently to enable independent oversight. 

2. Implement fire-modeling peer review recommendations, including 
marked exit routes for occupants at the Millennium Stages. 

The Center has completed implementation of six of the nine 
recommendations contained in the peer-reviewed fire modeling study. The 
status of work on the three remaining recommendations is as follows: 

1. Provide exit signage in the Grand Foyer, Hall of States and Hall of 
Nations: 

Exit signs will be installed at the glass doors leading to the Plaza. A 
design team will be under contract within the next month. Installation 
will proceed as soon as design is complete and a construction contract 
awarded. 

2. Provide a separation between the Lower Gift Shop and the Hall of 
Nations by providing automatic-closing devices on the existing doors. 

These devices are being installed as part of the Motor Lobby Renovation 
Project that is currently underway. The project will be completed in 
the spring of 2007. 

3. Maintain a minimum 1-hour separation between the three main theaters 
and the Grand Foyer. 

The remaining work is part of the Eisenhower Theater Renovation 
Project, which is currently in design, with construction scheduled to 
begin in May 2007. 

3. Install a smoke control system that is integrated with a sprinkler 
system and smoke detectors over the Millennium Stages. 

As noted on Page 19 of the GAO report, the revised, peer-reviewed 
modeling study concludes that smoke exhaust and sprinkler protection 
are not needed on the Millennium Stages provided the recommendations of 
the study are implemented. As discussed above, the Center will have 
fully implemented these recommendations at the completion of the 
Eisenhower Theater Renovation Project. However, the Center believes 
that this GAO recommendation should be closed because there is no code 
requirement to install a smoke control system that is integrated with a 
sprinkler system and smoke detectors over the Millennium Stages. 

4. Ensure that doors in key areas provide adequate separation from 
fire. 

As noted on Page 20 of the GAO report, the Center has engaged 
Underwriters Laboratories (UL) to inspect the doors identified as 
deficient in GAO's 2005 report. Since the initial inspection, repairs 
have been made to the Fire Command Center and Fire Pump Room doors, and 
new fire-rating labels were applied. Doors to the Concert Hall exits 
that do not have existing fire-rated labels will also be certified and 
labeled by UL upon completion of necessary repairs. This work will be 
completed within the next four months. 

5. Develop as-built drawings and better track changes to the Center. 

We agree with GAO that it would be beneficial to create the most 
complete as-built documentation available. However, we differ on the 
methods. While it would be ideal to assemble all existing documents 
into a single set, it is ultimately a convenience that provides no 
additional information to users. We estimate it would cost at least 
$200,000 to achieve this convenience. 

Similarly cost prohibitive is GAO's suggestion of "assembling" new as- 
built documentation where none exists in order to uncover hidden 
conditions, similar to those that have created construction change 
orders in the past. Doing so would cost millions of dollars and take 
public areas out of service for many months at a time. As we stated in 
our response to GAO-05-334, it is not cost effective to discount the 
existing as-built drawings and implement a full destructive 
investigation in order to create as-built drawings. The Center still 
maintains that the creation of such as-built drawings is not cost 
effective. Furthermore, GAO's response in 2005 was: 

...when existing as-built drawings do not exist or are proven to be 
inaccurate, as the Kennedy Center has indicated, it may help reduce the 
risk of cost increase or schedule delays to investigate the actual site 
conditions, which is sometimes destructive to building finishes. .where 
destructive investigation is not feasible, the Center should consider 
incorporating additional cost and schedule contingencies in its budget 
estimates to reflect the increased risk of unforeseen conditions being 
discovered during construction. 

In fact, this is exactly the procedure instituted in the management of 
our capital projects: destructive investigation is conducted when it 
will not impact the aesthetics or functionality of the space and cost 
and schedule contingency is included with every project. Both of these 
procedures were well illustrated in the implementation of the Family 
Theater project and were, in fact, cited in the current report. 

The Center will continue to proceed in this more responsible manner: we 
will address each area with selective destructive investigation, when 
possible, during a project's design phase and maintain a cost and 
schedule contingency for the possibility of encountering unknown 
conditions. In addition, we will collect and document comprehensive 
information on mechanical, electrical, and plumbing systems in the 
current development of the 2006 CBP, adding to our knowledge of 
existing building systems and confirming the accuracy of the existing 
drawings. 

6. Provide more timely and accurate information about capital projects 
to stakeholders. 

The Center will adjust the format and organization of the CBP and will 
include historical budget information in future publications to assist 
in monitoring and evaluating projects. It must be noted, however, that 
the comparison of preliminary cost estimates, sometimes generated years 
before a project is initiated, to the final cost of a project do not 
necessarily indicate ineffective or inefficient management. As is 
conveyed in all Operations Committee materials and in the CBP updates, 
"variability is expected in the project estimates as they progress from 
preliminary project concepts to fully developed project designs. All 
estimates are preliminary and may be revised upon further study." The 
2005 CBP further discusses the complexities associated with project 
budgeting: 

The development of a project budget is an evolving process. The nature 
of public projects is such that the funding cycle is often created over 
a long planning horizon, sometimes as much as five to ten years. This 
situation makes exact budgeting difficult at the time when the project 
funding is requested. .[T]he construction budget in many cases cannot 
be correctly estimated until the preliminary design and investigation 
is complete The construction costs are further refined during the final 
design work Thus, the final project budgets are developed through an 
iterative process. Beyond the basic nature of the development of 
project costs, other outside factors may also affect project costs, 
such as construction market conditions or availability of materials. 
For example, since late 2003 the construction market has experienced a 
steep increase in steel prices and miscellaneous metal costs due to a 
worldwide shortage in steel availability. 

In fact, Downey and Scott, a local Washington D.C. construction 
estimating firm, estimates construction escalation was 15.2% in 2004, 
11% in 2005 and is estimating 7.5% in 2006 and beyond. These factors 
indicate a recent unprecedented spike in market escalation that is well 
above the typical three to four percent utilized for planning five 
years ago. Such escalation was certainly not predictable in 2002, let 
alone in 1995 when the first CBP was written. Therefore, it would only 
be prudent for the Center to increase the budget projections for 
projects that were conceived several years ago, rather than carry 
budget numbers that are known to be unrealistic. 

Several other statements and conclusions in the report also need 
clarification: 

The total project expenditures delineated in the 2005 CBP did increase 
over those in the 2004 CBP, due to a variety of factors. First, the 
2004 plan was based on appropriation levels $7.2 million lower than our 
authorization for the period 2004 to 2007. The 2005 plan reflected 
appropriation levels equal to our full authorization for the period, in 
keeping with our initial budget request for 2007. Second, in response 
to recommendations in the 2005 GAO report, the Center updated its 
budgets to adjust for escalation and provide adequate contingency 
funds. 

The report also states that the cost of the Family Theater Renovation 
"included cost growth within the amounts budgeted for the project." 
This is wholly inaccurate. The project was completed approximately 
$300,000 under budget, therefore there was no cost growth. Change 
orders are a given in any project, therefore should certainly not be 
construed as cost growth. In this project, change orders were in fact 
far less than the contingency provided for the project. 

respect to the statement that the Center will not complete the Terrace- 
level renovations by 2008, we find the conclusion unwarranted and 
perplexing. The Roof Terrace Life Safety Project is proceeding as 
scheduled in the 2005 CBP. The scope of the project was developed in 
April 2006 and is the basis for an architectural contract awarded 
August 11, 2006. The "originally scheduled" dates to which GAO refers 
with respect to other Terrace level spaces, such as the Theater Lab and 
Terrace Theater renovations, are those which were planned in the 1995 
CBP. The assumption that a schedule developed over eleven years ago 
could still be viable in the current economic climate is unreasonable 
and naive for numerous reasons already cited. 

In fact, the most important factor that has prohibited the Kennedy 
Center from completing all of the projects detailed in 1995 by the end 
of FY2008, and the single biggest reason that recent CBPs have differed 
from year to year, is that appropriation levels for the Kennedy Center 
have not matched authorized levels in recent years. This has made 
capital planning extremely difficult. In fact, despite reduced 
appropriation levels in 2005 - 2007, all 1 life safety projects 
delineated in 1995 will be completed by the end of 2008, a confirmation 
of the Center's priorities. During a time of extreme escalation coupled 
with appropriations lower than authorized funding, it is unreasonable 
to criticize the Center for not completing all capital renovations as 
initially planned years ago. 

Furthermore, GAO states that "because the CBP will not be completed in 
2008 as planned, the Kennedy Center has hired a consulting firm to 
survey the Kennedy Center and recommend Center upgrades that have not 
yet been completed with a goal of extending the CBP implementation 
period to 2012." This betrays a fundamental philosophical deviation 
from best practices of facility management. Capital planning should 
never end. If a finite planning period were established, the Center 
would quickly deteriorate to a similar state as in the early 1990's 
when a capital project plan did not exist. The importance of ongoing 
planning was also recognized in the Kennedy Center Act, which directed 
the Board to "develop, and update annually, a comprehensive building 
needs plan," It would be irresponsible for the Center not to continue 
to have a CBP to provide the roadmap for building maintenance in a 
manner consistent with other national Presidential memorials and 
befitting the Nation's largest performing The tone and argument of the 
report suggests that GAO is critical of the notion of ongoing capital 
planning; the Center hopes that is not the case. 

In response to GAO's comment regarding irregularly scheduled Operations 
Committee meetings, the Center made changes after the 2005 report. In 
past years, attempts were made to schedule meetings to accommodate 
Congressional members' schedules and were cancelled if conflicting 
circumstances dictated that attendance would be low. Meetings are no 
longer cancelled. 

However, we do not agree with the attendance calculation method used in 
the report. We are grateful to Congressional members' willingness to 
serve on the Kennedy Center Board and prefer to accommodate the 
numerous demands on their time by allowing them to name a designee to 
attend meetings in their stead. Attendance at meetings by designees 
ensures that Kennedy Center business is reported back to the 
principals. If Congressional members' designees are included in the 
attendance calculations, Operations Committee attendance ranges from 43 
percent to 86 percent. Additionally, lack of attendance at meetings 
does not necessarily indicate that the trustees are not informed or 
engaged. Meetings and conversations occur frequently between staff 
members and trustees, outside the formal trustee and committee 
meetings, to update members and receive their guidance and feedback. In 
addition, all trustees and committee members receive the information 
provided at the meetings as well as minutes of the meetings. 

In short, the Board of the Kennedy Center takes very seriously its 
responsibility to keep our building, a Federal asset and a Presidential 
memorial, in the best condition possible. We continue to work to manage 
our capital projects program more effectively and efficiently. We 
believe that the results from the past two years of projects indicates 
substantial progress. And we appreciate the insight and recommendations 
from the GAO, which will assist us in continuing to strengthen our 
operations. 

Sincerely, 

Signed by: 

Michael M. Kaiser:
President:  

Signed by: 

Stephen A. Schwarzman: 
Chairman: 

The following are GAO's comments on the John F. Kennedy Center for the 
Performing Arts' (Kennedy Center) letter dated August 24, 2006. 

GAO Comments: 

1. We disagree with this interpretation. Construction manager at risk 
is not covered by the FAR; and, consequently, a deviation must be 
authorized and justified in the contract file. We also continue to 
believe that establishing a Guaranteed Maximum Price (GMP) prior to 
proceeding with work limits the government's risk of cost overruns. 
During the audit, we spoke with an official in the GSA Office of the 
Chief Architect who advises GSA staff on construction issues. The GSA 
official said that a GMP should be established in order to effectively 
use the construction manager at risk project delivery method and a 
deviation from the FAR is required. Because the Kennedy Center stated 
in its comments that it consulted with GSA and was told that it did not 
need a deviation for the contract, we reconfirmed the situation with 
GSA and were advised again that a deviation is required because of the 
use of the GMP. 

2. We updated the report to indicate that the Kennedy Center and the 
Smithsonian Office of the Inspector General finalized a memorandum of 
understanding, in July 2006, that establishes audits of federal funds 
used for capital projects. In addition, we incorporated into the 
report, the Kennedy Center's rationale for selecting a nongovernmental 
organization to audit the federal funds used for operations and 
maintenance activities. 

3. The revised, peer-reviewed modeling study concludes that smoke 
exhaust and sprinkler protection are not needed on the Millennium 
Stages, provided that the conditions of the revised modeling study are 
met. Once the two conditions of the revised modeling study have been 
met, the Kennedy Center will have fully implemented our recommendation 
to install smoke exhaust and sprinkler protection at the Millennium 
Stages. 

4. We disagree with the Kennedy Center's approach to this 
recommendation, which is to assemble all existing as-built drawings 
into a single set. The Kennedy Center can accomplish our recommendation 
in a cost-efficient way by integrating the as-built drawings from each 
successive capital project into a master plan for the center and by 
updating the drawings as additional changes to the center are made. 
This would ensure that the Kennedy Center is tracking future changes to 
the center and using the most up-to-date drawings of site conditions. 
Our report notes that it is important for the Kennedy Center to start 
assembling and consistently updating a comprehensive set of as-built 
drawings of the entire center to prevent costly unexpected site 
conditions. 

5. We agree that the difference between a project's original budget and 
the final cost does not, by itself, necessarily indicate ineffective or 
inefficient management. However, we do believe that the Kennedy Center 
Board of Trustees and Congress need information on project cost 
overruns in order to monitor and evaluate whether federally funded 
capital projects have been implemented effectively and efficiently. 

6. We believe our point is accurate and have further clarified the 
report to indicate that the cost of the Family Theater project was 
about $9.1 million, which includes cost growth, due to change orders, 
that was within the amount allocated for contingency. 

7. The most recent Operations Committee meeting was held on April 2006; 
and as of this meeting, the Roof Terrace Life Safety Project scope was 
not developed. In addition, neither our review of Kennedy Center 
documents nor discussions with Kennedy Center officials indicated that 
the scope of the Roof Terrace Life Safety Project was developed. 
Although the Kennedy Center states that the scope of the Roof Terrace 
Life Safety project was developed in April 2006, they did not provide 
the details of this scope in their agency comments. 

8. The Kennedy Center has deferred many of the terrace-level projects 
that were planned for the CBP beyond the scheduled completion of the 
plan in 2008, which significantly reduced the scope of the CBP. 

9. See comment 6. 

10. We agree that an ongoing capital plan is essential for the 
maintenance of the Kennedy Center as a presidential memorial and 
national performing arts center. The report notes that the Kennedy 
Center has hired a consulting firm to survey the center and recommend 
upgrades that have not been completed. This survey will cover years 
2008 through 2012. We added into the report that a Kennedy Center 
official told us that the new survey will include projects listed in 
the CBP that were not completed in 2008 as planned, as well as new 
projects. Therefore, we consider the survey an extension of the 
original CBP. Although the extended CBP may include new projects to 
facilitate ongoing capital planning, it will include deferred projects 
that were originally scheduled to be completed in 2008. 

11. We did not include designees' attendance in our calculations of 
board and Operations Committee attendance rates for several reasons. 
First, membership on the Kennedy Center Board of Trustees is set forth 
in the Kennedy Center Act and does not include designees. Therefore, we 
based our calculations on the attendance records for those persons 
legally serving as trustees. In addition, since designees have no legal 
authority for making decisions, including those with respect to 
federally funded capital projects, we did not consider their 
participation in board and committee meetings. Lastly, in analyzing 
board meeting minutes, we found instances in which a trustee sent more 
than one designee to a meeting. In these cases, attendance rates would 
be inflated if designees were included in the attendance calculations. 
As noted in the report, we found that it is unclear what responsibility 
and authority designees have for carrying out the board's 
responsibilities under the Kennedy Center Act, which limits the board's 
oversight of federally funded capital projects. 

12. We agree that a lack of attendance at board and committee meetings 
does not necessarily indicate that a trustee is not informed or 
engaged. However, during our audit we found, as noted in the report, 
that with respect to capital projects, trustees were not informed of 
project cost overruns, project budgets, or proposed projects. For 
example, as highlighted in the report, in April 2005, we reported that 
since 2003, each of the three federally funded capital projects that we 
reviewed had experienced cost overruns, one as great as 50 percent. 
However, we did not find any evidence that the board or its Operations 
Committee was informed of these cost overruns, such as the Opera 
House's $4 million cost increase. For example, two trustees that served 
on the board during the implementation of these projects told us that 
they did not know of any capital projects that had cost overruns. One 
of these trustees said that the Opera House renovation was on budget. 

[End of section] 

Appendix IV: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Mark Goldstein, (202) 512-2834 Tammy Conquest, (202) 512-2834: 

Staff Acknowledgments: 

In addition to those named above, Michael Armes, Keith Cunningham, 
George Depaoli, Bess Eisenstadt, Craig Fischer, Brandon Haller, John 
Krump, Susan Michal-Smith, Josh Ormond, Julie T. Phillips, and Carrie 
Wilks made key contributions to this report. 

(543150): 

FOOTNOTES 

[1] For this report, the term Kennedy Center refers to the Board of 
Trustees and management officials unless otherwise specified. 

[2] The National Fire Prevention Association Life Safety Code is 
designed to protect building occupants from fire and other hazards. The 
code covers construction, protection, and occupancy features to 
minimize danger to life from fires, smoke, fumes, or panic before 
buildings are vacated. The Americans with Disabilities Act prohibits 
discrimination on the basis of disability in employment, services 
rendered by state and local governments, places of public 
accommodation, transportation, and telecommunications services. 

[3] This amount includes a beginning balance of $35.3 million, which is 
the value of transfers from the National Park Service and the 
Smithsonian Institution, and approximately $180.5 million in federal 
appropriations. 

[4] GAO, Kennedy Center: Information on the Capital Improvement 
Program, GAO/GGD-93-46 (Washington, D.C.: Feb. 9, 1993) and Kennedy 
Center: Information on Facility Management Capability, GAO/GGD-98-56 
(Washington, D.C.: Mar. 25, 1998). 

[5] GAO, Kennedy Center: Improvements Needed to Strengthen the 
Management and Oversight of the Construction Process, GAO-03-823 
(Washington, D.C.: Sept. 5, 2003). 

[6] GAO, Kennedy Center: More Information on Project Status and Budgets 
Needed to Understand the Impact of Future Funding Decisions, GAO-04-933 
(Washington, D.C.: Sept. 15, 2004). 

[7] GAO, Kennedy Center: Stronger Oversight of Fire Safety Issues, 
Construction Projects, and Financial Management Needed, GAO-05-516T 
(Washington, D.C.: Apr. 6, 2005) and GAO-05-334 (Washington, D.C.: Apr. 
22, 2005). 

[8] The Board of Trustees created the Operations Committee to help the 
board carry out its responsibilities for capital projects. 

[9] The 2002 building plan shows projects being completed in fiscal 
year 2008. 

[10] The Kennedy Center's appropriation for fiscal year 2006 is 
contained in the Department of the Interior, Environment, and Related 
Agencies Appropriations Act, P.L. 109-54, 119 Stat. 499, 546 (2005). P. 
L. 109-54 appropriated to the Kennedy Center $13 million for capital 
improvements and $17.8 million for operations and maintenance. However 
two rescissions for fiscal year 2006 will affect the final amounts that 
the Kennedy Center will receive for capital improvements and for 
operations and maintenance. Section 439 of P.L. 109-54, 119 Stat. 499, 
559 (2005) provided for an across-the-board rescission of 0.476 percent 
of the budget authority provided for fiscal year 2006 for any 
discretionary appropriation in the act, which would include the Kennedy 
Center appropriation. The second rescission is an across-the-board 
rescission of budget authority equal to 1 percent for most agencies in 
any other fiscal year appropriation act, which also includes the 
Kennedy Center. See Department of Defense, Emergency Supplemental 
Appropriations to Address Hurricanes in the Gulf of Mexico, and 
Pandemic Influenza Act, 2006, P.L. 109-148, 119 Stat. 2680, 2791 
(2005). 

[11] 40 U.S.C. §3312. 

[12] Under certain laws, the Kennedy Center is treated as a federal 
agency. 

[13] GAO-05-334. 

[14] See IG Act of 1978, as amended, 5 U.S.C. § app. 3, section 8G, and 
2005 and 2006 List of Designated Federal Entities and Federal Entities, 
at 71 Fed. Reg. 24872 (Apr. 27, 2006). 

[15] The Kennedy Center Act provides that only federally appropriated 
funds are subject to the requirements for a federal entity under the IG 
Act of 1978 (5 U.S.C. App. 3). As a federal entity, the Kennedy Center 
is not required to establish an OIG; however, the center is required to 
report annually to Congress and OMB on its audit and investigative 
activities (See IG Act of 1978, as amended, 5 U.S.C. § app. 3, section 
8G, and 2005 and 2006 List of Designated Federal Entities and Federal 
Entities, at 71 Fed. Reg. 24872 (Apr. 27, 2006)). The Kennedy Center 
Act authorizes the Kennedy Center to request the Smithsonian OIG to 
conduct audits related to the expenditure of federal funds on a 
reimbursable basis (20 U.S.C. §76l(d)). 

[16] The Kennedy Center conducts capital projects primarily through 
three offices--Project Management, Contracts, and Finance. The 
Contracts Office is under the Facilities Management Office and 
negotiates, enters into, and manages procurements of products and 
services, including those related to capital projects. 

[17] Fire code allows an entity to provide an alternative to complying 
directly with fire code. This alternative, which allows people to exit 
the building safely in case of fire, is called a performance-based 
approach. 

[18] 31 U.S.C. §§1535 and 1536. 

[19] However, as we previously noted, it is impossible to identify how 
some project budgets have shifted without original budgets. 

[20] The $10 million increase includes about $2.5 million in cost 
growth for projects in fiscal year 2005. 

[21] GAO-05-334. 

[22] The Kennedy Center follows FAR when procuring contracts utilizing 
appropriated funds. If the center elects not to follow FAR, it must 
seek a FAR deviation. FAR Subpart 1.4, Deviations (January 2006). 

[23] The budget for the Eisenhower Theater renovation actually 
increased by about $2.1 million, but about $1.2 million of that 
increase was caused by the Kennedy Center's shifting resources from the 
Hazardous Materials Abatement project to the Eisenhower Theater 
renovation. 

[24] See GAO-04-933. 

[25] We do not address the condition of the restaurants, since they are 
outside the scope of the CBP. 

[26] The Kennedy Center added handrails and sprinklers to the Terrace 
Theater as part of the CBP. 

[27] Although a full architectural/engineering survey by an outside 
consulting firm is planned every 4 to 5 years in accordance with 
typical industry practices, the CBP is updated by the center's PMO 
annually. 

[28] The Smithsonian Institution Board of Regents also approves the 
Institution's budget for nonfederal funds. 

[29] GAO, Executive Guide: Leading Practices in Capital Decision 
Making, GAO/AIMD-99-32 (Washington, D.C.: December 1998). 

[30] GAO/AIMD-99-32. 

[31] For this report, we did not examine the Kennedy Center's use of 
nonfederal funds to finance capital improvements. In particular, we did 
not review the center's use of private funds or bonds in the garage and 
site improvements projects. 

[32] GAO-04-334. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: