This is the accessible text file for GAO report number GAO-06-945 
entitled 'Natural Gas Pipeline Safety: Risk-based Standards Should 
Allow Operators to Better Tailor Reassessments to Pipeline Threats' 
which was released on September 8, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

September 2006: 

Natural Gas Pipeline Safety: 

Risk-Based Standards Should Allow Operators to Better Tailor 
Reassessments to Pipeline Threats: 

GAO-06-945: 

GAO Highlights: 

Highlights of GAO-06-945, a report to congressional committees 

Why GAO Did This Study: 

The Pipeline Safety Improvement Act of 2002 requires that operators (1) 
assess gas transmission pipeline segments in about 20,000 miles of 
highly populated or frequently used areas by 2012 for safety threats, 
such as incorrect operation and corrosion (called baseline 
assessments), (2) remedy defects, and (3) reassess these segments at 
least every 7 years. Under the Pipeline and Hazardous Materials Safety 
Administration’s (PHMSA) regulations, operators must reassess their 
pipeline segments for corrosion at least every 7 years and for all 
safety threats at least every 10, 15, or 20 years, based on industry 
consensus standards—and more frequently if conditions warrant. 
Operators must also carry out other prevention and mitigation measures. 

To meet a requirement in the 2002 act, this study addresses how the 
results of baseline assessments and other information inform us on the 
need to reassess gas transmission pipelines every 7 years and whether 
inspection services and tools are likely to be available to do so, 
among other things. In conducting its work, GAO contacted 52 operators 
that have carried out about two-thirds of the baseline assessments 
conducted to date. 

What GAO Found: 

Periodic reassessments of gas transmission pipelines are useful because 
safety threats can change. However, the 7-year requirement appears to 
be conservative because (1) most operators found few major problems 
during baseline assessments, and (2) serious pipeline incidents 
involving corrosion are rare, among other reasons. Through December 
2005 (latest data available), 76 percent of the operators (182 of 241) 
that had begun baseline assessments reported to PHMSA that their 
pipelines required only minor repairs. These results are encouraging 
because operators are required to assess their riskiest segments first. 
Since operators are also required to repair these problems, the overall 
safety and condition of their pipelines should be enhanced before 
reassessments begin. In addition, PHMSA data suggest that serious gas 
transmission pipeline problems due to corrosion are rare. For example, 
there have been no deaths or injuries as a result of incidents due to 
corrosion since 2001. Of the 52 operators contacted that have 
calculated reassessment intervals, the large majority (20 of 23) told 
GAO that based on conditions identified during baseline assessments, 
they could safely reassess their pipelines for corrosion, every 10, 15, 
or 20 years—as industry consensus standards prescribe unless pipeline 
conditions warrant an earlier assessment. 

Sufficient resources may be available for operators’ reassessment 
activities, but some uncertainty exists. For the most part, the 52 
operators that GAO contacted expect to be able to obtain the services 
and tools needed through 2012. However, they expressed some concern 
about whether enough qualified vendors for the confirmatory and direct 
assessment methods (above-ground inspections followed by excavations) 
would be available. Industry associations and GAO attempted to 
determine the degree to which activity would increase from 2010 to 
2012, when operators begin reassessing pipelines while completing 
baseline assessments. An industry effort showed an increase in 
assessment and reassessment activity, but GAO’s showed a decrease. The 
reasons for the differences are not clear but may be due, in part, to 
differences in the operators contacted and the methodologies used in 
collecting this information. 

Figure: Framework for Assessing and ReAssessing Pipelines for safety 
Threats: 

[See PDF for Image] 

Source: GAO. 

[End of Figure] 

What GAO Recommends: 

The Congress should consider allowing gas transmission pipeline 
operators to reassess their pipelines using risk-based standards. In 
commenting on a draft of this report, the Department of Transportation 
generally agreed with it and the Department of Energy stated that it 
had no comments. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-945]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Katherine Siggerud (202) 
512-2834 or siggerudk@gao.gov. 

[End of Section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

The 7-Year Reassessment Requirement Appears to Be Conservative: 

Sufficient Resources May Be Available for Pipeline Reassessments: 

Conclusions: 

Matter for Congressional Consideration: 

Agency Comments and Our Evaluation: 

Appendixes: 

Appendix I: Impact of Periodic Reassessments on Natural Gas Supply May 
Be Less than Foreseen: 

Appendix II: Scope and Methodology: 

Other Aspects of Our Work: 

Organizations Contacted: 

Appendix III: Contact and Staff Acknowledgments: 

Figures: 

Figure 1: Most Operators Reported That Their Gas Transmission Pipelines 
Are in Good Condition, as of December 2005: 

Figure 2: Reassessments Every 7 Years for Corrosion Supplement Broader 
Periodic Reassessments: 

Figure 3: Operators Contacted Plan to Reassess Nearly All of the 
Mileage in Highly Populated or Frequently Used Areas Using In-line 
Inspection and Direct Assessment Tools: 

Figure 4: Baseline Assessment and Reassessment Activities Are Expected 
to Decrease during the Overlap Period, According to Operators We 
Contacted: 

Figure 5: Baseline and Reassessment Activities Are Expected to Increase 
during the Overlap Period, According to INGAA and AGA: 

Figure 6: GAO and INGAA/AGA Results Show Different Trends in Assessment 
Activity during the Overlap Period: 

Figure 7: Parallel Natural Gas Transmission Pipelines Can Help Maintain 
Product Supply: 

Abbreviations: 

AGA: American Gas Association: 

INGAA: Interstate Natural Gas Association of America: 

PHMSA: Pipeline and Hazardous Materials Safety Administration: 

September 8, 2006: 

Congressional Committees: 

Gas transmission pipelines are one of the nation's safest modes of 
freight transportation: nationwide about three people have died and 
about eight have been injured annually, on average, over the past 
decade because of natural gas pipeline incidents from all 
causes.[Footnote 1] To enhance the safety of gas transmission 
pipelines, the Pipeline Safety Improvement Act of 2002 requires that 
operators of these pipelines develop programs to assess and mitigate 
safety threats, such as leaks or ruptures due to incorrect operation or 
corrosion, to pipeline segments that are located in highly populated 
and frequently used areas, such as parks. Specifically, operators are 
required to perform baseline assessments on one-half of the gas 
transmission pipeline mileage located in these areas by December 2007 
and the remainder by December 2012. Pipeline segments that potentially 
face the greatest risks of failure from leaks or ruptures are to be 
assessed first. 

The 2002 act also requires that operators reassess these pipeline 
segments for safety threats at least every 7 years. Under flexibility 
provided by the act, the federal regulator--the Pipeline and Hazardous 
Materials Safety Administration (PHMSA)--requires that operators 
reassess these pipeline segments for corrosion damage at least every 7 
years in its implementing regulations, because corrosion is the most 
frequent cause of failures that can occur over time.[Footnote 2] It 
also incorporated, as mandatory, voluntary industry consensus standards 
on maximum reassessment intervals into these regulations for other 
types of safety threats. The industry standards require that operators 
reassess gas pipelines at least every 10, 15, or 20 years for all 
safety risks, depending primarily on the condition of the pipelines and 
the pressure under which they operate. If conditions warrant, 
reassessments must occur more frequently. 

The 2002 act required that we assess the 7-year reassessment 
requirement. To do so, we examined (1) the extent to which findings 
from baseline assessments and other information inform us about the 
need to reassess gas transmission pipelines for safety risks at least 
every 7 years and (2) the ability of operators to obtain the services 
and tools needed to perform the reassessments. These two topics are the 
main focus of this report. We also examined the potential impact of 
periodic assessments on the nation's natural gas supply. (See app. I.) 
This report deals mostly with natural gas transmission pipelines, which 
represent the overwhelming majority of gas pipelines.[Footnote 3] 

To understand how the findings from operators' baseline assessments and 
other information inform us about the need to reassess gas transmission 
pipelines at least every 7 years, we reviewed laws, regulations, and 
other PHMSA guidance. We discussed this issue with PHMSA, other federal 
agencies, industry associations, companies that perform research in 
this area, state safety representatives, and safety advocacy groups. We 
also obtained information from 52 gas pipeline operators for which 
baseline assessments and reassessments could have the greatest impact, 
all else being equal: larger and smaller transmission pipelines and 
local distribution companies (pipeline companies that take gas from 
transmission pipelines and distribute it to end users) with the highest 
proportion of pipeline miles in highly populated and frequently used 
areas to total system miles. Overall, these operators have assessed 
about 21 percent of the 20,000 miles of gas transmission pipeline that 
operators have reported as being within highly populated or frequently 
used areas.[Footnote 4] In addition, we analyzed data from PHMSA for 
241 operators that reported, in 2004 and 2005, on the number of 
immediate repairs conducted after completing their baseline 
assessments.[Footnote 5] To determine the extent to which gas 
transmission pipeline operators and local distribution companies will 
likely have the resources to reassess their pipelines at least every 7 
years, we asked operators, inspection tool contractors, and industry 
associations about the availability of equipment, equipment operators, 
and data analysts to interpret results. We also synthesized the 
information from the 52 operators to determine the aggregate level of 
actual and planned assessments and reassessments through 2012 and 
compared our findings with the results from an Interstate Natural Gas 
Association of America and American Gas Association data collection 
effort on the same topic. As part of our work, we assessed the internal 
controls and the reliability of the data elements needed for this 
engagement, and we determined that the data elements were sufficiently 
reliable for our purposes. We performed our work between August 2005 
and August 2006 in accordance with generally accepted government 
auditing standards. (See app. II for additional details on our scope 
and methodology.) 

Results in Brief: 

Periodic reassessments of pipeline threats are beneficial because 
threats--such as the corrosive nature of the gas being transported--can 
change over time. Baseline assessment findings conducted to date and 
the generally safe condition of gas transmission pipelines, suggest 
that the 7-year reassessment requirement appears to be conservative. 
Through December 2005 (latest data available), 76 percent of the 
operators (182 of 241) reporting baseline assessment activity reported 
to PHMSA that their gas transmission pipelines were in good condition 
and free of major defects, requiring only minor repairs. (See fig. 1.) 
Most of the 340 problems reported were concentrated in just seven 
pipelines.[Footnote 6] (These assessments reported by the 241 operators 
covered about 6,700 miles, or about one-third of the nationwide total 
to be assessed by 2012.) Because PHMSA does not require operators to 
identify the nature of the problems, we do not know how many, if any, 
were corrosion related. 

Figure 1: Most Operators Reported That Their Gas Transmission Pipelines 
Are in Good Condition, as of December 2005: 

[See PDF for image] 

Source: GAO presentation of PHMSA data. 

Note: Results of 241 operators that reported to PHMSA that they 
completed 6,700 miles of baseline assessments. Of those operators that 
reported no problems, 82 operate smaller pipeline systems (1 to 49 
miles), 41 operate mid-sized systems (50 to 199 miles) and 59 operate 
larger systems (200 or more miles). 

[End of figure] 

These results are encouraging, since operators are required to assess 
their riskiest segments first and 54 percent of the operators we 
contacted that have begun baseline assessments told us that they had 
not conducted risk-based assessments before the onset of the gas 
integrity management program. This suggests that, overall, operators 
that have thus performed baselines assessments are doing a good job in 
managing corrosion. Furthermore, since operators are required to repair 
these gas transmission pipelines the overall safety and condition of 
the pipeline system should be improved before reassessments begin 
toward the end of the decade. In addition, PHMSA data show corrosion 
incidents are rare: over the past 5-1/2 years (from January 2001 
through early July 2006), there were 26 corrosion-related incidents 
over the 295,000-mile transmission system per year, on average--none of 
which resulted in death or injury.[Footnote 7] 

Of the 52 operators that we contacted, 23 have calculated reassessment 
intervals. Based on conditions identified during baseline assessments, 
20 of these 23 operators indicated that they would reassess their gas 
transmission pipelines at the maximum allowable intervals prescribed by 
industry consensus standards--if the 7-year reassessment requirement 
were not in place.[Footnote 8] Most operators we contacted (42 of 52 or 
81 percent) told us that they prefer following industry consensus 
standards that base reassessment intervals on the characteristics and 
conditions of pipelines and that were developed using historical 
information and research. Although the industry consensus standards 
recognize that corrosion does not occur at a rapid rate, they allow for 
maximum reassessment intervals for time-dependent threats of 10, 15, or 
20 years only if the operator can adequately demonstrate that corrosion 
will not become a threat within the chosen time interval. If not, then 
the reassessment must occur more frequently, perhaps at 7 or even fewer 
years. Federal policy encourages the use of industry consensus 
standards, and PHMSA's implementing regulations incorporate three other 
industry consensus standards. 

PHMSA and state pipeline agencies are conducting inspections that 
should serve as a check as to whether operators have identified threats 
facing these gas transmission pipeline segments and have determined 
appropriate reassessment intervals. Initial results from 137 federal 
and state inspections show that operators are doing well on assessing 
their pipelines and making repairs. PHMSA and state agencies plan to 
inspect all operators' compliance with integrity management, including 
reassessment requirements and complete most of them by 2009 to, among 
other things, ensure that operators continually and appropriately 
assess the conditions of their pipeline segments. Finally, basing 
reassessments for corrosion on risk would be consistent with the risk- 
based approach to improving pipeline safety (called integrity 
management) set out in the 2002 act. We recently reported that PHMSA's 
implementation of the gas integrity management program is designed to 
enhance public safety.[Footnote 9] 

Sufficient resources may be available for operators to reassess their 
gas transmission pipelines, but some uncertainty exists. For the most 
part, the 52 operators and four inspection contractors we contacted 
told us that services and tools needed to conduct assessments have been 
readily available for baseline assessments, and they do not anticipate 
difficulties obtaining these resources in the future. Operators that 
reported both baseline and reassessment schedules told us they plan to 
reassess 42 percent of their pipeline miles in highly populated or 
frequently used areas using in-line inspection.[Footnote 10] Operators 
we contacted said that the in-line inspection industry is well 
established and has the capacity to expand readily. Operators plan to 
use direct assessment or confirmatory direct assessment methods in 
reassessing another 54 percent of their pipeline miles.[Footnote 11] 
However, they told us that expertise in direct assessment methods is 
limited; therefore, they may not be as readily available to all 
operators. Industry associations and we asked operators to estimate the 
number of miles of gas transmission pipeline they planned to assess 
through 2012 in order to determine whether an increase in overall 
assessment activity would occur because of the overlap between 
completing baseline assessments and beginning reassessments from 2010 
through 2012. The results were conflicting: the industry found an 
increase in activity, while we found a decrease. The reasons for these 
contrasting findings are unclear but may be due, in part, to the 
difference in methods used in collecting this information. 

We suggest that the Congress amend the Pipeline Safety Improvement Act 
of 2002 to permit pipeline operators to reassess their gas transmission 
pipeline segments at intervals based on risk factors, technical data, 
and engineering analyses. Such a revision would allow PHMSA to 
establish maximum reassessment intervals, and to require shorter 
reassessment intervals as conditions warrant. 

In commenting on a draft of this report, the Department of 
Transportation generally agreed with the report's findings. The 
Department of Energy had no comments. 

Background: 

The United States has about a 295,000-mile network of gas transmission 
pipelines that are owned and operated by approximately 900 operators. 
These pipelines are important to the nation because they transport 
nearly all the natural gas used, which provides about a quarter of the 
nation's energy supply. Pipelines do not experience many of the safety 
threats faced by other forms of freight transportation because they are 
mostly underground; but they are subject to failures that occur over 
time--such as leaks and ruptures resulting from corrosion[Footnote 12] 
or welding defects--and failures that are independent of time--such as 
damage from excavation, land movement, or incorrect operation. 

For the most part, two types of pipelines transport gas products: (1) 
gas transmission pipelines and (2) local distribution pipelines. Gas 
transmission pipelines typically move gas products over long distances 
from sources to communities and are primarily interstate. They 
typically operate at a higher stress level (higher operating pressure 
in relation to wall strength). By contrast, local distribution 
pipelines receive gas from transmission pipelines and distribute it to 
commercial and residential end users. Local distribution pipelines, 
which are primarily intrastate, typically operate under lower-stress 
conditions. Local distribution companies may also operate small 
portions of transmission pipelines--typically under lower stress--and 
are therefore subject to the assessment and reassessment requirements 
of the Pipeline Safety Improvement Act of 2002.[Footnote 13] 

Before the 2002 act, operators were subject to PHMSA's minimum safety 
standards for the design, construction, testing, inspection, operation, 
and maintenance of gas transmission pipelines; these standards are 
applied to all pipelines. However, this approach does not account for 
differences in the kinds of threats and the degrees of risk that 
pipelines face. For example, pipelines located in the Pacific Northwest 
are more susceptible to damage from geologic hazards, such as land 
movement, than pipelines in some other areas of the country; but 
PHMSA's safety standards do not take these threats into account in a 
systematic way.[Footnote 14] By contrast, the risk-based approach of 
the 2002 act--called the integrity management approach--requires 
pipeline operators to develop programs to systematically identify 
threats and mitigate risks to gas transmission pipeline segments 
located in highly populated or frequently used areas.[Footnote 15] In 
addition to PHMSA's integrity management program, operators must still 
meet the minimum safety standards. 

As of December 2005 (latest data available), 447 gas pipeline operators 
reported to PHMSA that about 20,000 miles of their pipelines (about 7 
percent of all gas transmission pipeline miles) lie in highly populated 
or frequently used areas. Individual operators reported that they have 
as many as about 1,600 miles and as few as 0.02 miles of transmission 
pipeline in these areas. 

Under PHMSA's regulations, gas pipeline operators may use any of three 
primary approaches to conduct baseline assessments on pipeline segments 
lying in highly populated or frequently used areas. 

* In-line inspection: In-line inspection involves running a specialized 
tool through the pipeline to detect and record anomalies, such as metal 
loss and damage. In-line inspection allows operators to determine the 
nature of any problems without either shutting down the pipeline for 
extended periods or potentially damaging the pipeline, as in 
hydrostatic testing (described below). In-line inspection devices can 
be run only from facilities established for launching and retrieving 
them. These launching and retrieval locations may extend beyond highly 
populated or frequently used areas. Operators will typically gather 
information along the entire distance between launching and retrieval 
locations to gain additional safety information; this is called over- 
testing. 

* Direct assessment: Direct assessment is a nonintrusive, above-ground 
instrument inspection that uses two or more types of diagnostic tools, 
such as a close interval survey, at predetermined intervals along the 
pipeline.[Footnote 16] Once the data are analyzed, the operator 
excavates and inspects segments of the pipeline suspected to have 
safety threats. 

* Hydrostatic testing: Hydrostatic testing entails sealing off a 
portion of the pipeline, removing the gas product, filling it with 
water, and increasing the pressure of the water above the rated 
strength of the pipeline to test its integrity. If the pipeline leaks 
or ruptures, the pipeline is excavated to determine the cause of the 
failure. Operators must shut down pipelines to perform hydrostatic 
testing. Also, this form of testing can damage the pipeline due to high 
pressure testing. Finally, operators must be able to dispose of large 
quantities of water in an environmentally responsible manner. 

Under PHMSA's regulations, which incorporate voluntary industry 
consensus standards for managing the system integrity of gas 
pipelines,[Footnote 17] operators must reassess their gas transmission 
pipeline segments for safety threats overall at least every 10, 15, or 
20 years (consistent with industry consensus standards), depending on 
the condition of the pipelines and the stress under which the pipeline 
segments are operated. PHMSA's regulations allow operators to limit the 
statutorily required 7-year reassessment to corrosion damage. In 
performing reassessments to meet the 7-year requirement, operators may 
employ a technique called confirmatory direct assessment. This 
technique is similar to direct assessment; however, operators are 
required to use only one type of assessment tool, rather than at least 
two types required under direct assessment. According to PHMSA, it 
allowed this more limited assessment because the 7-year reassessment 
for corrosion confirms the acceptable integrity of a gas transmission 
pipeline, already ensured by assessments and reassessments for safety 
threats conducted at 10-, 15-, or 20-year intervals under the industry 
consensus standards incorporated in the agency's regulations. (See fig. 
2.) About 2010, operators will be expected to begin reassessing some 
segments of their pipelines for corrosion under the 7-year reassessment 
requirement while they are completing baseline assessments of other 
segments--called "the overlap." 

Figure 2: Reassessments Every 7 Years for Corrosion Supplement Broader 
Periodic Reassessments: 

[See PDF for image] 

Source: GAO. 

Note: Periodic reassessments occur at least every 10, 15, or 20 years. 
Both periodic and 7-year reassessments are supposed to occur more 
frequently if conditions warrant. 

[End of figure] 

It is important to note that the reassessment intervals under the 
industry consensus standards, the 7-year reassessment requirement for 
corrosion, and PHMSA's regulations for time-dependent threats represent 
the maximum number of years between reassessments. If pipeline 
conditions dictate more frequent reassessments--for example, 5 or fewer 
years--then pipeline operators must do so to comply with PHMSA's 
regulations.[Footnote 18] In addition, between reassessments, operators 
must continually ensure that their gas transmission pipelines are safe. 
PHMSA's regulations require all operators--whether or not they are 
located in highly populated or frequently used areas to patrol their 
pipelines, survey for leakage, maintain valves, ensure that corrosion-
preventing cathodic protection is working properly,[Footnote 19] and 
take prevention and mitigation measures to prevent excavation damage. 

PHMSA, within the Department of Transportation, attempts to ensure the 
safe operation of pipelines through regulation, industry consensus 
standards, research, education (e.g., to prevent excavation-related 
damage), oversight of the industry through inspections, and 
enforcement, when safety problems are found. PHMSA employs about 165 
people in its pipeline safety program, about half of whom are pipeline 
inspectors who inspect operators' implementation of integrity 
management programs for gas and hazardous liquid (e.g., oil, gasoline, 
and anhydrous ammonia) pipelines, in addition to other more traditional 
compliance programs. PHMSA currently has 22 inspectors trained to 
conduct integrity management inspections, of which 9 are devoted 
exclusively to the program. In addition, PHMSA expects to be assisted 
by about 180 inspectors in 46 states and the District of Columbia in 
overseeing intrastate natural gas transmission pipelines. 

The 7-Year Reassessment Requirement Appears to Be Conservative: 

Periodic reassessments of pipeline threats are beneficial because 
threats--such as the corrosive nature of the gas being transported--can 
change over time. Baseline assessment findings conducted to date and 
the generally safe condition of gas transmission pipelines suggest that 
the 7-year requirement appears to be conservative. Most operators of 
gas transmission pipelines reported to PHMSA that their baseline 
assessments have disclosed 340 problems for which immediate repairs 
have been made. This is encouraging because these pipeline segments are 
supposed to be the riskiest and few have been systematically assessed 
until now. Regarding the industry safety record, the industry is 
generally safe and no corrosion-related incidents resulting in deaths 
or injuries have occurred in the past 5-1/2 years (from January 2001 
through early July 2006) anywhere in the nation, let alone in highly 
populated or frequently used areas.[Footnote 20] It is therefore likely 
to be safe in most cases to allow longer maximum intervals that 
coincide with industry consensus standards. PHMSA and state pipeline 
agencies plan to inspect all operators' integrity management 
activities, which should serve as a safeguard if longer reassessment 
intervals for corrosion are permitted. 

Most Operators Have Reported That Their Gas Transmission Pipelines Are 
Mostly Free of Serious Problems: 

Through December 2005 (latest data available), 76 percent of the 
operators (182 of 241) reporting baseline assessment activity to PHMSA 
told the agency that their gas transmission pipelines were in good 
condition and free of major defects, requiring only minor repairs. 
(These assessments covered about 6,700 miles, or about one-third of the 
nationwide total to be assessed). The remaining 59 operators reported 
340 problems for which immediate repairs have been completed. (See fig. 
1.) 

Fifty-two operators (21 percent) reported nine or fewer problems for 
which immediate repairs have been completed; and seven operators (3 
percent) reported 10 or more problems. Most of the problems stem from 
the seven operators reporting 10 or more problems and concern only a 
small portion of their gas transmission pipelines. Specifically, these 
seven operators represent nearly 60 percent of the total problems 
requiring immediate repairs, and the problems occurred in only 7 
percent of 6,700 miles of baseline assessments conducted.[Footnote 21] 
Since PHMSA does not require that operators report to it the nature of 
the problems, we do not know how many of the 340 problems, if any, were 
due to corrosion. 

We contacted 52 operators about the baseline assessments they have 
completed and their plans for the rest, and the results were largely 
consistent with the overall data reported to PHMSA. Forty-four of these 
operators have begun baseline assessments, and 37 of these 44 (84 
percent) told us that they found few safety problems that required 
reducing pipeline pressure and performing immediate repairs in response 
to baseline assessments in highly populated or frequently used areas. 
These 44 operators have assessed about 4,100 miles of gas transmission 
pipeline, representing about 61 percent of the 6,700 miles of baseline 
assessment results reported to PHMSA and about 21 percent of the total 
number of pipeline miles in highly populated or frequently used areas 
nationwide. 

It is encouraging that the majority of operators nationwide reported 
few or no problems involving immediate repairs, because (1) operators 
are to assess pipeline segments facing the greatest risk of failure 
from leaks or ruptures first, as required by the 2002 act, and (2) 54 
percent of the operators we contacted (28 of 52) had not conducted risk-
based assessments of their pipeline segments for safety threats prior 
to the integrity management program. 

Although the PHMSA regulations focus the 7-year reassessment 
requirement on corrosion because it is the most frequent cause of time- 
dependent pipeline incidents,[Footnote 22] the industry has had a good 
safety record prior to and during the initial years of integrity 
management. It is not possible to determine which incidents occurred in 
highly populated or frequently used areas from summary historical data 
published by PHMSA. However, nationwide, these incidents are relatively 
rare. Over the past 5½ years (from January 2001 through early July 
2006), there were 143 corrosion-related incidents over the 295,000-mile 
transmission system (26 per year, on average)--none of which resulted 
in death or injury. In addition, according to PHMSA, during the first 2 
years of integrity management (2004 and 2005), operators reported that 
corrosion caused 49 leaks,[Footnote 23] 16 failures, and two incidents 
involving significant property damage, but no fatalities and injuries, 
in highly populated or frequently used areas. 

Both the positive results found during baseline assessments conducted 
to date and the overall good safety industry record suggest that gas 
transmission pipeline operators that have thus far performed baseline 
assessments overall are doing a good job in managing corrosion. 
Further, since operators, are required to identify and repair 
significant problems, the overall safety and condition of the gas 
transmission pipeline system should be enhanced before reassessments 
begin toward the end of the decade. 

Operators Support Baseline Assessments and Reassessments but Prefer a 
Risk-based Reassessment Requirement Over a Fixed One: 

Because many gas transmission pipelines had never been assessed before 
integrity management, operators we contacted pointed out that the new 
knowledge gained through baseline assessments represents one of the 
greatest benefits of the integrity management program. They also 
support reassessments, in part because all operators are subject to the 
same requirements. However, most support a risk-based reassessment 
requirement, consistent with overall integrity management, over the 
fixed 7-year requirement prescribed by the 2002 act. Operators also 
told us they prefer a risk-based reassessment requirement that is based 
on research and historical information. Most operators told us they 
prefer reassessing pipelines based on the characteristics and 
conditions of the pipeline rather than on the 7-year requirement 
prescribed in the 2002 act. About 80 percent of the 52 operators that 
we contacted prefer that reassessment intervals be based on the 
condition and characteristics of the pipeline segment. About half of 
these operators (28) expressed a preference for the industry consensus 
standard developed by the American Society of Mechanical Engineers 
(ASME B31.8S-2004) for setting reassessment intervals for time- 
dependent threats because it incorporates a risk-based approach (for 
pipeline failure) and is based on science and engineering knowledge. 
This standard sets reassessment intervals at a maximum of 10 years for 
high-stress pipeline segments, 15 years for medium-stress segments, and 
20 years for low-stress segments. Maximum reassessment intervals, such 
as those in the industry consensus standard, incorporate such risk 
concepts as built-in safety factors (e.g., wall stress, test pressure, 
or predicted failure) and pipeline conditions. The maximum intervals of 
10, 15, and 20 years are based on worst-case corrosion growth rates. 

The industry consensus standards were developed in 2001 and updated in 
2004 based on, among other things, (1) the experience and expertise of 
engineers, consultants, operators, local distribution companies, and 
pipeline manufacturers; (2) more than 20 technical studies conducted by 
the Gas Technology Institute, ranging from pipeline design factors to 
natural gas pipeline risk management; and (3) other industry consensus 
standards, including the National Association of Corrosion Engineers 
standards, on topics such as corrosion. Contributors have been 
practicing aspects of risk-based assessments for over 10 years. This 
standard serves as a foundation for most sections of PHMSA's integrity 
management regulations. The mechanical engineering society's standard 
was reviewed by the American National Standards Institute.[Footnote 24] 
The institute found that the standard was developed in an environment 
of openness, balance, consensus, and due process and therefore approved 
it as an American National Standard. 

While the mechanical engineering standards are voluntary for the 
industry, PHMSA incorporated them as mandatory in its gas transmission 
integrity management regulations. The mechanical engineering society's 
standard for setting reassessment intervals is not the only industry 
consensus standard in PHMSA's integrity management regulations. The 
regulations incorporate other industry consensus standards for using 
direct assessment for corrosion, calculating pipeline wall strength, 
and for determining temporary reductions in operating pressure. In 
addition, it is federal policy to encourage the use of industry 
consensus standards: the Congress expressed a preference for technical 
standards developed by consensus bodies over agency-unique standards in 
the National Technology Transfer and Advancement Act of 1995. The 
Office of Management and Budget's Circular A-119 provides guidance to 
federal agencies on the use of voluntary consensus standards, including 
the attributes that define such standards. 

Of the 52 operators we contacted, 44 had undertaken baseline 
assessments, and 23 of the 44 have calculated their own reassessment 
intervals.[Footnote 25] Twenty of these 23 operators indicated that, 
based on the conditions they identified during their baseline 
assessments, they would reassess their gas transmission pipelines at 
maximum intervals of 10, 15, or 20 years--as allowed by industry 
consensus standards--if the 7-year reassessment requirement were not in 
place. The remaining three operators told us that they would reassess 
their pipelines at intervals shorter than the industry consensus 
standards but longer than 7 years because of the conditions of their 
pipelines. These results add weight to our assessment that the 7-year 
requirement may be conservative for most pipelines. 

Safeguards Exist if Industry Consensus Standards for Corrosion 
Reassessments Are Allowed: 

Industry consensus standards allow for maximum reassessment intervals 
for time-dependent threats of 10, 15, or 20 years only if the operator 
can adequately demonstrate that corrosion will not become a threat 
within the chosen time interval. If an operator cannot demonstrate that 
corrosion does not pose a threat, (e.g., threats posed by shipping gas 
that is more corrosive then was shipped previously), then the 
reassessment must occur sooner, perhaps at 7 or even 5 or fewer years. 
Furthermore, according to industry consensus standards, it typically 
takes longer than the 10, 15, or 20 years specified in the standard for 
corrosion problems to result in a leak or rupture. 

As a means of ensuring that assessments and reassessments are done 
competently, PHMSA regulations and industry consensus standards require 
that operators develop and document the steps they take to ensure the 
quality of these activities. This includes ensuring that persons 
involved are competent and able to carry out the activities. In 
addition, operators are encouraged to conduct internal audits of their 
quality control approaches and third-party reviews of their entire 
integrity management programs. 

It is important to note that, in addition to periodic reassessments, 
operators must perform prevention and mitigation activities on a 
continual basis. PHMSA regulations require that all operators of gas 
transmission pipelines, including those outside highly populated or 
frequently used areas, patrol their pipelines, survey for leakage, 
maintain valves, ensure that corrosion-preventing cathodic protection 
is working properly, and take other prevention and mitigation measures. 

Finally, PHMSA and the state pipeline agencies are inspecting 
operators' integrity management plans that were mandated by the 2002 
act to provide their gas transmission pipeline reassessment approaches 
and intervals, among other things, to ensure that operators continually 
and appropriately assess the conditions of their pipeline segments in 
highly populated or frequently used areas. These inspections should 
serve as a check on whether operators have identified threats facing 
these pipeline segments and determined appropriate reassessment 
intervals. PHMSA and states have begun inspections and expect to 
complete most of the first round no later than 2009. As of June 2006, 
PHMSA had completed 20 of about 100 inspections and, as of January 
2006, states had begun or had completed 117 of about 670 
inspections.[Footnote 26] Initial results from these inspections show 
that operators are doing well in assessing their pipelines and making 
repairs, but some need to better document their programs. Based on the 
initial inspection results to date, PHMSA and states did not find many 
issues that warranted enforcement actions. 

Sufficient Resources May Be Available for Pipeline Reassessments: 

Although some uncertainty exists, sufficient resources may be available 
for operators to reassess their gas transmission pipelines. Operators 
and inspection contractors we contacted told us that the services and 
tools needed to conduct periodic reassessments will likely be available 
to most operators. However, operators expressed their uncertainty about 
whether qualified direct assessment and confirmatory direct assessment 
contractors will be available. This is important because operators plan 
to use these methods to reassess about half of their pipeline mileage. 

Contractors told us that they will likely have the capacity to meet 
demands, even during periods when baseline assessments and 
reassessments may overlap. The severity of this overlap, however, 
remains unclear. Although operators that we contacted expect baseline 
assessment and reassessment activity to decrease from 2010 through 
2012, an Interstate National Gas Association of America (INGAA) and 
American Gas Association (AGA) polling of their members suggests that 
activity will rise markedly.[Footnote 27] 

Operators Report that Services and Tools Are Likely to Be Available for 
Reassessments: 

Thirty-seven out of 52 operators (71 percent), one in-line inspection 
association, and all four inspection contractors that provide direct 
assessment or in-line inspection tool services that we contacted told 
us that the services and tools needed to conduct periodic reassessments 
will likely be available to most operators.[Footnote 28] All but 3 of 
the operators reported that they plan to rely on contractors to conduct 
all or a portion of their reassessments, and 9 of 52 operators have 
signed, or would like to sign, long-term contracts that extend 
contractor services through a number of years. However, few have 
scheduled reassessments with contractors, as they are several years in 
the future and operators are concentrating on baseline assessments. 

The 48 operators that reported both baseline and reassessment schedules 
told us that they plan to reassess 42 percent of their gas transmission 
pipeline miles in highly populated or frequently used areas, using in- 
line inspection, and 54 percent of their miles using direct assessment 
or confirmatory direct assessment methods.[Footnote 29] (See fig. 3.) 
Operators expect to assess only 4 percent of their pipeline miles using 
hydrostatic testing for several reasons: (1) this form of testing 
requires shutting down their pipelines, (2) other assessment methods 
yield more robust information about the condition of their pipelines, 
(3) hydrostatic testing can weaken or damage pipelines, and (4) large 
quantities of water must be disposed of in an environmentally 
responsible manner. 

Figure 3: Operators Contacted Plan to Reassess Nearly All of the 
Mileage in Highly Populated or Frequently Used Areas Using In-line 
Inspection and Direct Assessment Tools: 

[See PDF for image] 

Source: GAO discussions with 48 operators. 

Note: Some operators may use one type of assessment tool on one portion 
of their gas transmission pipeline and another type of assessment tool 
on another portion. 

[End of figure] 

The Inline Inspection Association and the two in-line inspection 
contractors that we contacted told us that sufficient capacity exists 
within the industry to meet current and future operator demands. 
However, operators and inspection contractors expressed uncertainty 
about whether qualified direct assessment and confirmatory direct 
assessment contractors will be available. This is important because 
operators plan to use these methods to reassess about half of their gas 
transmission pipeline mileage. Unlike the in-line inspection method, 
which is an established and less intrusive practice that 27 of 52 
operators have used on their pipelines at least once prior to the 
integrity management program, two direct assessment contractors told us 
that there is limited expertise in this field. One said that newer 
contractors coming into the market to meet demand may not be qualified. 
The operators planning to use direct assessment for their pipelines are 
generally those with smaller-diameter pipelines that cannot accommodate 
in-line inspection tools.[Footnote 30] At a recent INGAA integrity 
management workshop, in-line inspection and direct assessment 
inspection contractors emphasized that, although they currently have 
the resources to meet operator demand and continue to train new 
inspectors, operators need to plan ahead to ensure resource 
availability for future years, when resources may be more constrained. 
The workshop also highlighted technological developments for assessment 
tools that will make assessments more efficient. Other stakeholders 
have told us that there are new tools being developed that will enable 
smaller-diameter pipelines to accommodate in-line inspection tools. For 
example, the Department of Energy is developing tiny robotic sensors 
that can detect flaws in plastic natural gas pipelines without 
interrupting the flow of gas. 

The Amount of Assessment Activity Occurring in the Overlap Period Is 
Uncertain: 

An industry concern about the 7-year reassessment requirement is that 
operators will be required to conduct reassessments starting no later 
than 2010, while they are still in the 10-year period (2003 through 
2012) for conducting baseline assessments. Industry is concerned that 
this could create a spike in demand for contractor services, and 
operators would have to compete for the limited number of contractors 
to carry out both. As a result, operators might not be able to meet the 
reassessment requirement.[Footnote 31] The information provided by the 
operators that we contacted shows a marked overall increase in 
assessment and reassessment activity in 2010 (a 16 percent increase 
over 2009 activity) and then a gradual decrease of activity through 
2012. (See fig. 4.) Operators expect this decrease because they plan to 
have completed a large number of baseline assessments between 2005 and 
2007 in order to meet the statutory deadline for completing at least 
half of their baseline assessments by December 2007 (3 years before the 
predicted overlap). 

Figure 4: Baseline Assessment and Reassessment Activities Are Expected 
to Decrease during the Overlap Period, According to Operators We 
Contacted: 

[See PDF for image] 

Source: GAO discussions with 52 operators.  

Note: These results are based on information obtained from 47 of 52 
operators we contacted, covering 154,000 miles of gas transmission 
pipeline, 12,000 miles of which are in highly populated or frequently 
used areas. Five operators did not report their reassessment plans. We 
did not ask operators to separate baseline assessments and 
reassessments in areas that are not highly populated or frequently 
used. 

[End of figure] 

In contrast, INGAA and AGA, after polling their members in 2006, found 
a steady overall increase in total expected baseline assessments and 
reassessments during the overlap period. INGAA and AGA found that 
baseline assessments and reassessments would start to increase in 2009 
and rise steadily through 2012.[Footnote 32] (See fig. 5.) Assessment 
activity would increase by 5 percent in 2010 over the 2009 level; in 
2011, by 8 percent over the preceding year; and in 2012, by 10 percent 
over the 2011 level. 

Figure 5: Baseline and Reassessment Activities Are Expected to Increase 
during the Overlap Period, According to INGAA and AGA: 

[See PDF for image] 

Source: GAO analysis of INGAA and AGA results. 

Note: These results are based on responses from 56 operators covering 
180,000 miles of gas transmission pipeline, 11,000 miles of which are 
in frequently used or highly populated areas. 

[End of figure] 

The difference between our findings and those of INGAA and AGA is not 
easy to explain. (See fig. 6.) Both efforts reported on comparable 
numbers of operators (47 for us and 56 for INGAA/AGA) and total 
transmission pipeline miles (154,000 for us and 180,000 for INGAA/AGA). 
To some extent, the difference may be due to the variations in the 
pipeline operators that responded to both efforts. About 72 percent of 
operators we polled were different from those polled by INGAA and AGA. 
However, even where both efforts collected information from the same 
operators, the information was sometimes markedly different. Another 
reason for the difference may be due to methodology. For example, we 
gathered our information through semistructured interviews with a 
systematically selected set of pipeline operators based on larger and 
smaller transmission pipelines and local distribution companies with 
the highest proportion of pipeline miles in highly populated or 
frequently used areas to total system miles, among other things. INGAA 
and AGA gathered their information by sending out a self-administered 
data collection instrument to their members, and reported results based 
on those members who responded. In addition, INGAA and AGA asked 
operators for data somewhat differently from methods we used, which may 
have led to some differences in results. 

Figure 6: GAO and INGAA/AGA Results Show Different Trends in Assessment 
Activity during the Overlap Period: 

[See PDF for image] 

Sources: GAO discussions with 52 operators and GAO analysis of 
INGAA/AGA results. 

Note: See text for possible reasons for the difference in results. 
Readers should not interpret these results to suggest that operators 
are not planning to complete all required baseline assessment 
activities by the end of 2012. 

[End of figure] 

Conclusions: 

Evidence as a result of baseline assessments, the industry's overall 
safety record, the existence of accepted risk-based assessment 
standards, and PHMSA's actions to inspect how operators are identifying 
corrosion threats to their pipelines and setting reassessment intervals 
suggests a risk-based approach to reassessing gas transmission pipeline 
segments for corrosion can achieve the safety objectives of the 2002 
act. Evidence gathered to date suggests that operators that have thus 
performed baseline assessments are doing a good job overall managing 
corrosion. Since the large majority of pipeline operators that we 
contacted had not systematically assessed their transmission pipelines 
for corrosion risks before the onset of the gas integrity management 
program, if corrosion were a rapidly growing problem, we would have 
expected a larger proportion of pipelines to report problems requiring 
immediate repairs. But, this was not the case. Furthermore, adopting a 
risk-based approach to setting reassessment intervals does not 
automatically allow operators to reassess their pipeline segments less 
frequently than under the 7-year requirement. Rather, if conditions 
warrant, an operator would be required to reassess a pipeline segment 
as frequently as needed--perhaps even more frequently than every 7 
years. Finally, a risk-based reassessment requirement would be 
consistent with the overall approach to integrity management that the 
Congress put in place with the 2002 act. 

Safeguards are in place to ensure that gas transmission operators 
determine reassessment intervals competently. PHMSA regulations and 
industry consensus standards require that operators ensure that persons 
involved have the experience and expertise to carry out the activities. 
Operators are also encouraged to conduct internal audits of their 
quality control approaches and third-party reviews of their integrity 
management programs. PHMSA and the state pipeline agencies are 
inspecting operators' compliance with integrity management reassessment 
requirements, among other things, to ensure that operators continually 
and appropriately assess the conditions of their gas transmission 
pipeline segments in highly populated or frequently used areas. 

In summary, the available evidence supports a conclusion that a risk- 
based reassessment approach based on technical data, risk factors, and 
engineering analyses can achieve the 2002 act's safety objectives. Such 
an approach would provide for reassessments to be tailored to the 
corrosion threats faced by the pipeline segment and would not result in 
reassessments that are either too infrequent or premature. Evidence to 
date suggests that gas transmission pipelines are generally in good 
shape based on assessments, following up with immediate repairs and 
safeguards being in place to ensure operators determine reassessments 
appropriately. In our view, it is not necessary to wait until baseline 
assessments and a round of reassessments have been completed before 
considering whether to retain or modify the 7-year reassessment 
requirement. 

Matter for Congressional Consideration: 

To better align reassessments with safety risks, the Congress should 
consider amending section 14 of the Pipeline Safety Improvement Act of 
2002 to permit pipeline operators to reassess their gas transmission 
pipeline segments at intervals based on technical data, risk factors, 
and engineering analyses. Such a revision would allow PHMSA to 
establish maximum reassessment intervals, and to require shorter 
reassessment intervals as conditions warrant. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to the Departments of Transportation 
and Energy for their review and comment. The Department of 
Transportation generally agreed with the report's findings. The 
Department of Energy had no comments. 

We are sending copies of this report to congressional committees and 
subcommittees with responsibility for transportation safety issues; the 
Secretary of Transportation; the Secretary of Energy; the 
Administrator, PHMSA; the Assistant Administrator and Chief Safety 
Officer, PHMSA; the Deputy Secretary for Natural Gas and Petroleum 
Technology, Department of Energy; and the Director, Office of 
Management and Budget. We will also make copies available to others 
upon request. This report will be available at no charge on the GAO Web 
site at [Hyperlink, http://www.gao.gov]. 

If you have any questions about this report, please contact me at (202) 
512-2834 or siggerudk@gao.gov. Contact points for our Offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this report. Staff who made key contributions to this report 
are listed in appendix III. 

Signed by: 

Katherine A. Siggerud: 
Director, Physical Infrastructure Issues: 

Congressional Committees: 

The Honorable Ted Stevens: 
Chairman: 
The Honorable Daniel K. Inouye: 
Co- Chairman: 
Committee on Commerce, Science and Transportation: 
United States Senate: 

The Honorable Don Young: 
Chairman: 
The Honorable James L. Oberstar: 
Ranking Democratic Member: 
Committee on Transportation and Infrastructure: 
House of Representatives: 

The Honorable Joe Barton: 
Chairman: 
The Honorable John D. Dingell: 
Ranking Minority Member: 
Committee on Energy and Commerce: 
House of Representatives: 

[End of section] 

Appendix I: Impact of Periodic Reassessments on Natural Gas Supply May 
Be Less than Foreseen: 

As the Pipeline Safety Improvement Act of 2002 was being considered, 
the Interstate Natural Gas Association of America (INGAA) analyzed the 
possible impact of requiring assessments and periodic reassessments and 
found that significant disruptions in the natural gas supply and 
considerable price increases could occur.[Footnote 33] A more moderate 
impact was predicted in three subsequent analyses--(1) two reviews of 
the INGAA study performed for the Pipeline and Hazardous Materials 
Administration (PHMSA) by the John A. Volpe National Transportation 
Systems Center and by the Department of Energy during the congressional 
debate over the pipeline bill, and (2) a post-act PHMSA evaluation of 
its implementing regulations.[Footnote 34] A waiver provision was 
included in the 2002 act after INGAA's study was completed; this may 
serve as a safety valve if it appears that the natural gas supply may 
be disrupted. Finally, our discussions with 50 natural gas pipeline 
operators also suggest a more moderate potential impact than INGAA 
found. 

INGAA Study Expected Significant Supply Disruptions and Price 
Increases: 

INGAA's study estimated that periodic assessments under integrity 
management could lead to a monthly reduction in natural gas supply of 
about 1 to 3 percent, along with price increases to customers, among 
others, ranging from $382 million to over $1 billion (in 2002 dollars) 
from 2002 through 2010, depending on the frequency of 
assessments.[Footnote 35] Most of this price increase would be due to 
supply disruption and some due to capital expenditures. INGAA 
considered the monthly reduction in supply to be significant because it 
assumed that gas transmission pipelines would be removed from service 
during testing and that some areas of the country would be more 
vulnerable to supply disruptions than others. 

PHMSA-commissioned Reviews and PHMSA's Regulatory Evaluation Predict 
More Moderate Impacts: 

Both Volpe's and the Department of Energy's 2002 reviews of the INGAA 
study concluded that gas transmission pipelines would not be 
significantly affected by periodic assessments. The reviews, however, 
did not attempt to quantify overall estimates of gas disruptions or 
price impacts. Rather, they examined the major assumptions in the INGAA 
study and discussed whether the study's results seemed reasonable. 
PHMSA's final regulatory evaluation, which was completed in 2004 to 
assess the impact of PHMSA's regulations on implementing the 2002 act, 
concluded that transmission pipelines' natural gas supply may be 
somewhat disrupted as a result of assessments and that cost increases 
may occur. However, PHMSA acknowledged that it could not estimate the 
impact of assessments on gas prices. In general, the reviews found that 
the INGAA study's estimates of price impacts represent a worst-case 
scenario because of several overly pessimistic assumptions. For 
example, the INGAA study: 

* underestimated the ability of the pipeline network to mitigate 
disruptions. INGAA assumed that pipeline assessments would generally 
reduce pipeline capacity temporarily, thereby disrupting the supply and 
increasing the price of natural gas. Yet, both Volpe's and the 
Department of Energy's reviews found that the INGAA study did not 
sufficiently account for redundancies in the nation's natural gas 
transmission pipeline network. Redundancies enable operators to 
mitigate potential disruptions during assessments by rerouting gas 
through the network. 

Operators we contacted that have higher-stress gas transmission 
pipelines[Footnote 36] generally indicated that their pipeline 
infrastructure is versatile and includes such redundancies as parallel 
pipelines or looping capabilities that allow gas to flow to customers 
while portions of the pipeline are assessed or repaired.[Footnote 37] 
(See fig. 7.) Operators of lower-stress pipelines[Footnote 38] reported 
that they typically use a set of laterals,[Footnote 39] which feed an 
interconnected gas distribution system and allow them to plan around 
disruptions. In addition, lower-stress operators can use liquid or 
compressed natural gas that is located at their facilities or 
transported by trucks to specified locations. Forty-four of the 50 
natural gas operators (88 percent) that we contacted have some type of 
alternative gas supply, such as storage facilities and other gas 
suppliers, to meet customers' short-term needs. 

Figure 7: Parallel Natural Gas Transmission Pipelines Can Help Maintain 
Product Supply: 

[See PDF for image] 

Source: PHMSA. 

[End of figure] 

* assumed that a large amount of transmission mileage would require 
assessments because of over-testing. The INGAA study concluded that the 
number of gas transmission pipeline miles within highly populated or 
frequently used areas is only about 5 percent of the total mileage in 
the U.S. Nonetheless, the study assumed that over 80 percent of 
mainline interstate pipeline miles would require assessing, because the 
pipeline miles that are located within the highly populated areas are 
scattered throughout the pipeline system, and inspection methods like 
in-line testing can only be inserted and retrieved in certain locations 
that may lie outside highly populated or frequently used locations. As 
a result, the study assumed that operators of these pipelines would 
assess over 1,500 percent more miles than are within the highly 
populated areas. On the basis of comments from industry groups, PHMSA's 
regulatory evaluation assumed that operators would assess about 625 
percent more miles when using in-line inspection testing and about 25 
percent more miles when using hydrostatic testing, but no over-testing 
when using the direct assessment method. Baseline assessment results to 
date seem to support the lower over-testing estimate: as of December 
31, 2005, on the basis of performance reports submitted to PHMSA, 
operators assessed about 650 percent more miles overall than are 
located in highly populated or frequently used areas.[Footnote 40] 

* assumed that only hydrostatic testing would be used on delivery 
laterals. The INGAA study predicted that operators would use only 
hydrostatic testing on lateral gas transmission pipelines because it 
assumed that very few laterals can accommodate in-line testing. Under 
hydrostatic testing, water pressure is used to test the condition of 
pipelines; therefore, all of the capacity of a pipeline segment must be 
removed for a period of time. 

Volpe's review concluded that this particular assumption represents the 
worst possible impact of assessments on lateral pipelines because it 
does not allow for the use of in-line testing or direct assessment. 
Based on discussions with operators and public comments on PHMSA's 
draft regulatory analysis, the PHMSA regulatory evaluation also assumed 
that few operators would use hydrostatic testing. INGAA's study also 
did not address the development of new technologies that could allow in-
line inspection of smaller diameter pipelines. As discussed earlier, 
new technology is being developed. Finally, operators we contacted 
reported that they do not plan to use hydrostatic testing extensively. 
As discussed earlier, only about 4 percent of the mileage will be 
reassessed using hydrostatic testing. This testing will typically be 
over relatively small lengths of pipeline (from 0.8 to 331 miles). 

* did not incorporate the ability of operators to obtain waivers. The 
INGAA study did not consider the possible impact of a waiver provision 
in the 2002 act on maintaining the natural gas supply. This was 
understandable because the waiver provision was added to the bills 
under consideration after the INGAA study was completed. The act allows 
the PHMSA to waive or modify any requirement for operators to conduct 
reassessments when they need to maintain product supply as long as it 
is consistent with pipeline safety.[Footnote 41] Twenty-one of the 50 
natural gas operators (42 percent) that we contacted said that they 
would consider applying for a waiver, if needed, and 23 (46 percent) 
told us that they did not plan to apply for a waiver. Three of the 
operators were uncertain, and the remaining three operators did not 
provide us with a response. Fourteen of the 26 operators that either 
did not plan to apply for a waiver or were unsure about doing so said 
that it is too early to determine the need for applying for waivers. 
They obtained the necessary equipment to conduct assessments or 
developed plans for handling potential natural gas supply 
disruptions.[Footnote 42] 

Operators Contacted Found Assessments Have Had Minimal Impact on 
Supply: 

Pipeline operators we contacted told us that assessments and repairs of 
even their riskiest gas transmission pipelines have not significantly 
disrupted the natural gas supplied to customers, such as local 
distribution companies and power plants. These 50 natural gas 
transmission operators and local distribution companies had assessed 
about 4,100 miles of pipeline in highly populated or frequently used 
areas, as of December 2005 (latest data available)--or about 21 percent 
of the total gas transmission mileage in these areas in the nation and 
about 62 percent of the pipeline mileage located in frequently used or 
highly populated areas assessed to date. Of the 44 operators that have 
begun baseline assessments, 26 (59 percent) indicated that their 
assessments and repairs did not require them to shut down their 
pipelines or reduce their operating pressure. Sixteen operators (36 
percent) reported minor disruptions in their gas supply because they 
temporarily shut down pipelines and reduced operating pressure to 
conduct assessments or repairs. These operators told us that they used 
alternative gas sources, such as liquefied natural gas, to sustain 
their customers' gas supply. The remaining two operators (5 percent) 
were located in regions that have limited excess gas capacity. Both 
operators reported that they could not meet all of the natural gas 
needs of their customers when their pipelines were shut down to perform 
assessments or repairs. Some customers, especially those with 
interruptible contracts,[Footnote 43] did not receive gas from the 
pipelines for several days, but they were able to obtain gas from 
alternative sources. 

Eleven of the 44 operators were located in regions that have limited 
excess gas capacity--the Northeast, the Rocky Mountains, and the 
Southwest--and reported minor supply disruptions. Five of the 11 
operators--all of which operate lower-stress gas transmission 
pipelines--reported that none of these disruptions in natural gas 
supply were caused by assessments or repairs. Four operators reported 
instances in which immediate repairs caused a reduction in operating 
pressure; however, they maintained natural gas supply by relying on 
alternative gas sources.[Footnote 44] Since PHMSA does not require that 
operators report to it the nature of the problems, we do not know how 
many immediate repairs, if any, were due to corrosion. And, as 
previously mentioned, 2 of the 11 operators reported natural gas supply 
disruptions; although they had to shut down their pipelines due to 
assessments or repairs, customers were able to obtain natural gas from 
other sources. 

In early 2006, INGAA and AGA polled their members about their 
experiences with and plans for conducting assessments and reassessments 
during off-peak and peak months.[Footnote 45] Overall, INGAA and AGA 
found that, from 2003 to 2012, members plan to conduct 76 percent of 
their baseline assessments and reassessments on their gas transmission 
pipelines (as measured in miles) during the off-peak spring and summer 
months, 18 percent in the fall, and 6 percent in the winter. According 
to an INGAA official, most of the assessment activity that results in 
temporary reductions in gas supply due to repairs being made will 
likely affect markets regionally. If assessments occur when pipelines 
are constrained for capacity, an increase in delivered gas prices will 
occur. Overall, assessments will only affect small groups of the 
nation's population, but they will have a consumer price impact in 
those affected areas. 

Our findings from these operators, while not necessarily representative 
of all operators, are encouraging. First, these findings do represent a 
sizeable proportion (61 percent) of the mileage assessed to date. 
Second, the segments that operators assessed were supposed to be the 
riskiest segments (those most susceptible to ruptures or leaks) of the 
gas transmission pipelines located in highly populated or frequently 
used areas. If so, there should be fewer repairs needed for subsequent 
baseline assessments of less risky segments, and hence fewer 
disruptions in supply. 

Post-act Industry Polling Found Members Plan to Modify and Repair 
Pipelines, Which May Affect Natural Gas Supply: 

The 2006 INGAA and AGA polling of their members did not explicitly ask 
for the extent to which their members experienced supply disruptions 
because of baseline assessments or repairs. However, INGAA and AGA did 
ask members to identify the amount of pipeline modifications and 
repairs that would be necessary for conducting baseline assessments and 
reassessments, activities that could disrupt supply. Overall, INGAA and 
AGA found that about 50,000 of the 180,000 miles of gas transmission 
pipelines that were reported by responding operators are scheduled for 
or have already undergone (1) modifications to allow in-line inspection 
tools to access pipeline segments (2) repairs to eliminate major 
defects or (3) monitoring for minor problems.[Footnote 46] According to 
a senior INGAA official, assessments and pipeline modifications can 
generally follow a prearranged schedule; however, pipeline repairs are 
unpredictable. Repairs often require pipelines to be shut down, which 
could have an effect on natural gas supply.[Footnote 47] However, PHMSA 
officials report that only the worst pipeline problems require 
pipelines to be shutdown for repair. From 2003 to 2012, 38,000 of the 
50,000 pipeline miles (76 percent) have been scheduled for 
modifications or repairs during the off-peak spring and summer months 
to mitigate supply disruptions.[Footnote 48] 

Department of Energy Expects Little Disruption in the Natural Gas 
Supply: 

Officials from the Office of Oil and Gas within the Department of 
Energy told us that the integrity management program, including the 7- 
year reassessment requirement, is not likely to significantly disrupt 
the natural gas supply. They told us that operators have, among other 
things, sufficient system redundancies, such as parallel lines, to 
maintain product supply. The Department of Energy has completed several 
regional analyses of the possible effects of the disruptions in the 
natural gas supply caused by such events as extreme weather conditions 
(e.g., extended cold periods and hurricanes). It is completing other 
analyses as well. However, because these are being done at the regional 
level, their results are too broad to help inform us about more 
localized and subregional potential disruptions. 

[End of section] 

Appendix II: Scope and Methodology: 

To understand how the findings from operators' baseline assessments 
inform us about the need to reassess gas transmission pipelines at 
least every 7 years, we reviewed the requirements of the Pipeline 
Safety Improvement Act of 2002 and PHMSA's implementing regulations. We 
also reviewed information about setting reassessment intervals for gas 
transmission pipelines, including industry consensus standards for 
maximum reassessment intervals developed by the American Society of 
Mechanical Engineers, and documents obtained from PHMSA, industry, and 
other stakeholders. We discussed this issue with officials from PHMSA, 
other federal agencies, industry associations, companies that perform 
research in this area, state safety representatives, and safety 
advocacy groups. (These organizations are listed at the end of this 
appendix.) 

We also analyzed data from PHMSA on the number of immediate repairs 
reported by operators as a result of baseline assessments conducted 
through December 2005 (latest data available) and the number of natural 
gas pipeline incidents reported to PHMSA. 

We contacted 52 pipeline operators (50 natural gas and 2 hydrogen 
operators) from among the 447 operators that reported that they operate 
gas transmission pipelines in highly populated or frequently used 
areas. Forty-four of these operators have begun baseline assessments. 
We selected those operators for which the baseline assessments and 
reassessments could be expected to have the greatest impact, all else 
being equal: larger and smaller transmission pipelines and local 
distribution companies with the highest proportion of pipeline miles in 
highly populated or frequently used areas to total system miles. We 
also selected operators located in three regions of the country that 
several studies and our stakeholders consider to be vulnerable to 
energy supply disruptions: the Northeast, the Southwest, and the Rocky 
Mountains. 

The 52 operators reported that they have assessed about 4,100 of the 
6,700 miles (61 percent) of pipeline segments, as of December 2005. 
Overall, these operators have assessed about 21 percent of the 20,000 
miles of pipeline that operators have reported as being within highly 
populated or frequently used areas. Because we used a nonprobability 
method of selecting these operators, we cannot project our findings 
nationwide.[Footnote 49] Contacting a larger number of operators or 
selecting them through a statistical sample would not have been 
feasible due to resource and time constraints. Nonetheless, these 52 
operators do represent a substantial portion of the miles assessed to 
date and of the total number of reported miles of pipeline in highly 
populated or frequently used areas. 

For these 52 operators, we conducted semistructured interviews to 
collect qualitative and quantitative information on the degree to which 
they found anomalies during the baseline assessments and, based on 
these results, the frequency with which they would reassess these 
pipeline segments under American Society for Mechanical Engineers 
standards for managing the system integrity of gas pipelines (ASME 
B31.8S-2004) if the 7-year reassessment requirement were not in place. 
As part of our work, we asked operators to identify the steps that they 
take to ensure the quality of their baseline assessments and 
reassessments, such as ensuring that competent persons are involved in 
determining reassessment intervals and conducting periodic internal or 
third-party reviews of their integrity management programs, as 
recommended by PHMSA regulations and industry standards. We relied on 
the operators' professional judgment in reporting on the conditions 
they found during their assessments. 

To determine the extent to which gas transmission pipeline operators 
and local distribution companies will likely have the resources to 
reassess their pipelines, at least every 7 years, we synthesized 
testimonial and documentary evidence obtained from our discussions with 
(1) 52 operators (as described above) and (2) pipeline assessment tool 
contractors, direct assessment vendors, and industry associations on 
the prospective availability of equipment, equipment operators, and 
data analysts to interpret results. We synthesized the information from 
the 52 operators to determine the aggregate level of actual and planned 
assessments and reassessments through 2012. We compared our findings 
with the results from an INGAA/AGA data collection effort, conducted in 
2006, on the same topic. We then discussed our results with INGAA and 
analyzed the data obtained from both efforts to try to understand any 
differences in results. 

To assess the reliability of information provided to us from PHMSA, 
INGAA, and AGA, we performed a number of analyses. For the information 
provided to us from PHMSA, we compared the number of immediate repairs 
operators reported to us to the number of immediate repairs they 
reported to PHMSA. To assess the reliability of the data provided to us 
from INGAA and AGA, we also compared the reported responses of 
operators that were included in INGAA/AGA's and our efforts. In 
addition, we checked the accuracy of INGAA/AGA's calculations. We 
determined that the data were sufficiently reliable for the types of 
analyses we present in this report. 

Other Aspects of Our Work: 

To determine the potential impact of the 7-year reassessment 
requirement on the nation's natural gas supply, we contacted officials 
from PHMSA, the Department of Energy, industry associations, and 
research firms to discuss how the potential shutdown of gas 
transmission pipelines or operation under reduced pressure--as a result 
of baseline assessments, reassessments, and repairs--might affect the 
continued supply of natural gas. We also obtained information from the 
Department of Energy on the results of analyses of the overall 
vulnerability of natural gas supplies in several regions of the nation 
to extreme conditions, such as extreme cold weather. 

Further, we asked the 50 natural gas operators that we contacted about 
the vulnerability of their pipelines to supply disruption and the 
potential impact on customers. This included 11 operators located in 
the three regions of the country that have limited excess supply gas 
capacity. We also discussed how their baseline assessments and any 
resulting repairs have affected their customers to date. Finally, we 
compared operators' experiences in performing assessments, 
reassessments, and repairs to the assumptions made in the 2002 INGAA 
study of the potential effects of the proposed integrity management 
program, two reviews of this study, and PHMSA's final regulatory 
evaluation. The reviews were performed by the John A. Volpe National 
Transportation Systems Center and the Department of Energy at the 
request of PHMSA.[Footnote 50] 

Organizations Contacted: 

In addition to the 52 pipeline operators and four inspection 
contractors that we contacted, we met with or contacted the following 
organizations: 

Department of Transportation: 

Office of Inspector General: 
Pipeline and Hazardous Materials Safety Administration: 

Other Federal Agencies: 

Department of Energy: 
Federal Energy Regulatory Commission: 
National Institute of Standards and Technology: 
National Transportation Safety Board: 

Industry Associations: 

American Gas Association: 
American Public Gas Association: 
Inline Inspection Association: 
Interstate Natural Gas Association of America: 
Midwest Energy Association: 
Northeast Gas Association: 

State Regulatory Associations: 

National Association of Pipeline Safety Representatives: 
National Association of Regulatory Utility Commissioners: 
New Jersey Public Utility Commission: 

Research Firms: 

Energy and Environmental Analysis, Inc. Battelle: 
Gas Technology Institute: 
John A. Volpe National Transportation Systems Center: 
Pipeline Research Council International: 

Technical Experts: 

American Society of Mechanical Engineers: 
American Society for Testing and Materials: 
Kiefner and Associates, Inc. 
National Association of Corrosion Engineers: 

Pipeline Safety Advocacy Groups: 

Common Ground Alliance: 
Cook Inlet Keeper: 
Pipeline Safety Trust: 

[End of section] 

Appendix III: Contact and Staff Acknowledgments: 

GAO Contact: 

Katherine Siggerud (202) 512-2834 or siggerudk@gao.gov: 

Staff Acknowledgments: 

In addition to the above, James Ratzenberger, Assistant Director; 
Timothy Bober; Anne Dilger; Seth Dykes; Timothy Guinane; Brandon 
Haller; Bert Japikse; and Matthew LaTour made key contributions to this 
report. 

(542069): 

FOOTNOTES 

[1] Transmission pipelines move products from sources to communities. 
An incident, for PHMSA reporting purposes, involves a death, an injury 
requiring hospitalization, or property damage (including the value of 
any loss of gas) of $50,000 or more. 

[2] Other types of failures are independent of time, such as damage 
from excavation, land movement, or incorrect operation. 

[3] Other types of gas pipelines transport hydrogen and carbon dioxide. 

[4] It would have been insightful to be able to assess the effects of 
operators' assessment activity in relation to the volume of gas flowing 
through their pipelines and the overall capacity of the pipelines. 
However, this information was not readily available. 

[5] Nationwide, there are about 900 operators, 447 of which have 
reported to PHMSA that they operate pipelines in highly populated or 
frequently used areas. Of these, 241 have reported to PHMSA that they 
have completed some baseline assessments. 

[6] Pipeline operators are required to report the number of scheduled 
and immediate repairs completed. They may have found other problems but 
not have completed the repairs. These repairs are reported only after 
they are completed. 

[7] In the last 10½ years, PHMSA data show that 236 corrosion-related 
incidents occurred, only 2 of which resulted in deaths or injuries. One 
of the incidents resulted in 12 deaths and two injuries. The other 
incident resulted in one injury. Neither incident occurred in a highly 
populated or frequently used area. 

[8] The remaining three operators told us that they could reassess 
their pipelines at intervals shorter than the industry consensus 
standards but longer than 7 years, based on the condition of their 
pipelines. 

[9] For a discussion on the effect of integrity management on public 
safety, see Natural Gas Pipeline Safety: Integrity Management Enhances 
Public Safety, but Consistency of Performance Measures Should Be 
Improved, GAO-06-946 (Washington, D.C.: Sept. 8, 2006). 

[10] In-line inspection involves running a specialized tool through a 
pipeline to detect and record anomalies, such as metal loss and damage. 

[11] Direct assessment and confirmatory direct assessment involve using 
above-ground detection instruments, and then excavating suspected 
problem areas. 

[12] The Federal Highway Administration estimates the average annual 
cost of corrosion to gas and hazardous liquid transmission pipelines at 
$7 billion for, among other things, maintenance and failures. See 
Federal Highway Administration, Tech Brief: Corrosion Costs and 
Preventive Strategies in the United States, study performed by CC 
Technologies, March 2002. 

[13] Gas transmission pipeline operators and local distribution 
companies also operate medium-stress pipelines. 

[14] Under its minimum safety standards, PHMSA requires stronger 
pipelines in more highly populated areas. In addition, operators are 
required to annually evaluate their pipelines for population growth, 
which may cause operators to reduce operating pressure or upgrade 
pipelines. 

[15] The regulatory definition of highly populated or frequently used 
area is involved. Some examples of these areas are (1) an area with 20 
or more buildings that could be affected by a pipeline incident; (2) a 
location where a potential impact of a pipeline rupture contains an 
area or open structure that is occupied by 20 or more people on at 
least 50 days in a 12-month period (e.g., a camp site); and (3) a 
facility occupied by persons that would be difficult to evacuate, such 
as a hospital. 

[16] A close interval survey is used to assess the coating of covered 
pipelines for corrosion damage. 

[17] Standards are technical specifications that pertain to products 
and processes, such as the size, strength, or technical performance of 
a product. National consensus standards are developed by standard- 
setting entities on the basis of an industry consensus. For more 
details about industry consensus standards, see the National 
Association of Corrosion Engineers: Standard Recommended Practice - 
Pipeline External Corrosion Direct Assessment (NACE RP002-2002) and the 
American Society of Mechanical Engineers: Managing the System Integrity 
of Gas Pipelines (ASME B31.8S-2004). 

[18] Pipeline conditions and threats change over time. For example, 
housing may be built around pipelines, possibly increasing the threat 
of excavation damage. Another example is that over time the quality of 
the gas being shipped through the pipeline may change and may be more 
corrosive. 

[19] Cathodic protection involves a small electrical voltage between a 
structure and the ground to control corrosion. 

[20] As noted earlier, an average of three people have died and eight 
have been injured over a 10 1/2-year period, from all causes of natural 
gas transmission pipeline incidents. 

[21] As noted earlier, product flow and pipeline capacity can be useful 
to understand the extent of problems and their effect. However, this 
measurement was not practical. 

[22] Third-party damage is a significant cause of gas transmission 
pipeline incidents. In addition, third-party damage can cause pipeline 
dents that may lead to corrosion. 

[23] Leaks from gas transmission pipelines can allow methane to escape 
into the atmosphere. Methane is a potent greenhouse gas that 
contributes to climate change. See U.S. Environmental Protection 
Agency, Inventory of U.S. Greenhouse Gas Emissions and Sinks: 1990- 
2003, April 2005. 

[24] The American National Standards Institute is a private, nonprofit 
organization whose mission is to promote and facilitate voluntary 
consensus standards and promote their integrity. The Institute does not 
approve the technical merits of proposed national standards. 

[25] The other 21 operators (1) have not calculated reassessment 
intervals; (2) do not intend to, given the prescriptive federal (7 
years) or state (5 years in Texas) reassessment requirements; or (3) 
did not supply us with information on their reassessment intervals. 

[26] See GAO-06-946 for additional information on the results of PHMSA 
and state inspections. 

[27] INGAA represents the natural gas industry, including transmission 
pipeline operators. According to INGAA, it represents virtually all of 
the interstate natural gas transmission pipeline companies operating in 
the United States. Its members transport over 95 percent of the 
nation's natural gas. AGA represents local energy utility companies, 
including pipeline companies, which deliver natural gas to homes, 
businesses, and industries throughout the United States. According to 
AGA, its members account for roughly 83 percent of all natural gas 
delivered by the nation's local natural gas distribution companies. 

[28] We contacted the Inline Inspection Association, two companies 
offering in-line inspection services, and two companies offering direct 
assessment services. In our assessment of the public safety effects of 
integrity management, we reported that 94 percent of the operators we 
contacted had no major concerns about their ability to complete 
baseline assessments. (See GAO-06-946.) The difference in these 
findings may be due to the fact that operators have 10 years to 
complete baseline assessments but must reassess pipeline segments every 
7 years or in a shorter period if conditions warrant. The shorter 
reassessment period could heighten demand for inspection services and 
tools. 

[29] Some operators we contacted reported that the cost of using 
confirmatory direct assessment as compared with other assessment tools 
and the limited time savings before conducting a full assessment as 
reasons for not planning to use this method. 

[30] According to industry estimates, 35 percent of all local 
distribution company pipelines (as measured in miles likely to be 
located in highly populated or frequently used areas) cannot 
accommodate an in-line inspection tool, compared with only about 4 
percent of transmission operators' pipelines. 

[31] The 2002 act allows operators to request a waiver from conducting 
reassessments when inspection tools are not available. PHMSA 
regulations require that operators apply for a waiver when inspection 
tools are not available to conduct assessments within the required 
reassessment period and that the actions the operator is taking in the 
interim ensures the integrity of the pipeline. Environmental 
requirements may also affect the scheduling of assessments, repairs and 
modifications, and the choice of assessment tools. (See app. I.) Few of 
the 52 operators that we contacted mentioned this as a concern. 

[32] Although INGAA, AGA, and we collected information differently on 
the extent that baseline assessments and reassessments would be 
conducted inside and outside highly populated or frequently used areas, 
both efforts collected information on overall baseline assessment and 
reassessment activity. As a result, the overall results of both efforts 
are comparable and are shown in figure 6. 

[33] Prepared for The INGAA Foundation, Inc., by Energy and 
Environmental Analysis, Inc., Consumer Effects of the Anticipated 
Integrity Rule for High Consequence Areas, 2002. 

[34] See, Department of Transportation docket, RSPA-00-7666, Energy 
Impact Statement for Pipeline Integrity Management in High Consequence 
Areas (Gas Transmission Pipelines), March 28, 2002, prepared by John A. 
Volpe National Transportation Systems Center and the U.S. Department of 
Transportation; Comments from U.S. Department of Energy on INGAA's 
Consumer Effects of the Anticipated Integrity Rule for High Consequence 
Areas, April 2, 2002; and Research and Special Programs Administration, 
Final Regulatory Evaluation, Pipeline Integrity Management in High 
Consequence Areas (Gas Transmission Pipelines), March 28, 2002. 

[35] The National Petroleum Council also discussed the supply effects 
of the integrity management program, including that some pipelines may 
be removed from service if it is not economically efficient to repair 
them. The council did not estimate the extent that these abandonments 
might occur or the resulting price increases, if any. See Balancing 
Natural Gas Policy: Fueling the Demands of a Growing Economy Volume V, 
Transmission and Distribution Task Group and LNG Subgroup Report, 
September 2003. 

[36] Higher-stress pipelines operate under pressure at or above 50 
percent of the pressure that will cause a pipeline to deform (called 
yield strength). 

[37] A looping capability involves installing a segment of pipeline 
adjacent to an existing pipeline. The segment of pipeline connects to 
the existing pipeline at both ends of a loop, which allows more gas to 
be moved through the pipeline system. 

[38] Lower-stress pipelines operate pressure at or below 30 percent of 
a pipeline's yield strength. 

[39] A lateral is a segment of a pipeline that branches off of the main 
or transmission line to transport the product to a termination point, 
such as a tank farm or a metering station. 

[40] Over-testing, although not without costs, provides safety benefits 
because additional information is collected about the condition of 
pipelines. The operators' reports do not indicate which inspection 
method was used to conduct the inspections. 

[41] Under PHMSA's regulations, an operator must apply for a waiver at 
least 180 days before the required reassessment interval, unless 
natural gas supply issues make the period impractical. If so, the 
operator must apply as soon as the need for the waiver is known. 

[42] Eleven operators we contacted did not provide reasons for not 
planning to apply for a waiver. One operator reported that it would 
wait for regulatory changes for reassessments before applying for a 
waiver. 

[43] Although interruptible contracts with pipeline operators or local 
distribution companies vary in terms and conditions, they generally 
allow for service interruptions that are caused by system operating 
conditions (e.g., when pipeline pressure is threatened by high rates of 
natural gas consumption), among other things. 

[44] We did not ask operators about the degree to which they reduced 
operating pressure and the reduction in the amount of gas that they 
could deliver. Nevertheless, they were able to use alternative sources 
to maintain product supply while they made repairs to their pipelines. 

[45] According to a Department of Energy official, on-and off-peak 
periods vary based on location. For example, in the South, fall and 
winter months are often off-peak while the reverse is true in northern 
states (e.g., for heating needs). 

[46] In its September 2003 report, cited earlier, the National 
Petroleum Council estimated that conducting baseline assessments over 
10 years, gas transmission pipeline operators will spend about $1.1 
billion annually on replacing existing pipeline infrastructure. 

[47] In March 2006, PHMSA issued a final rule that requires operators 
to use a risk-based approach to determine which onshore gathering 
pipelines are subject to PHMSA's gas pipeline safety rules and which of 
these rules the lines must meet. The application of these rules may 
result in interruption of service to carry out repairs. However, the 
rules do not impose requirements for operators to assess their 
pipelines in the same manner as the integrity management program. 
Therefore, any interruptions caused by the need to carry out repairs 
would be the result of normal operation and maintenance activities. 
Gathering lines collect natural gas from production facilities and 
transport them to transmission or distribution lines. There are about 
15,000 miles of onshore gathering lines nationwide. 

[48] Complying with environmental laws, such as those dealing with 
habitats, may also affect scheduling of modifications and repairs. The 
Pipeline Safety Improvement Act of 2002 required the establishment of a 
federal interagency committee to develop and ensure implementation of a 
coordinated environmental review and permitting process to enable 
operators to complete baseline assessments, including pipeline repairs, 
with minimal adverse effects to the environment such as harming unique 
species or habitat in the specified time periods. The interagency 
committee has established a working group to develop a joint regulatory 
approach to streamlining. In addition, PHMSA has designed and is 
testing a Web-based environmental permit review process to (1) provide 
early electronic notification of proposed pipeline repairs to federal 
agencies and solicit input from state and local agencies involved in 
the review process for pipeline repairs and (2) expedite coordination 
and approval of recommended best practices for operators to use to 
manage environmental damage when repairing their pipelines in 
environmentally important areas. 

[49] Results from nonprobability samples cannot be used to make 
inferences about a population because, in a nonprobability sample, some 
elements of the population being studied have no chance or have an 
unknown chance of being selected as part of the sample. 

[50] As cited in appendix I. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: