This is the accessible text file for GAO report number GAO-06-580 
entitled 'Information Technology: Customs Has Made Progress on 
Automated Commercial Environmental System, but It Faces Long-Standing 
Management Challenges and New Risks' which was released on May 31, 
2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 

GAO: 

May 2006: 

Information Technology: 

Customs Has Made Progress on Automated Commercial Environment System, 
but It Faces Long-Standing Management Challenges and New Risks: 

GAO-06-580: 

Contents: 

GAO Highlights: 

Highlights of GAO-06-580, a report to Subcommittees on Homeland 
Security, Senate and House Committees on Appropriations. 

Why GAO Did This Study: 

The Department of Homeland Security (DHS) is conducting a multiyear, 
multibillion-dollar acquisition of a new trade processing system, 
planned to support the movement of legitimate imports and exports and 
strengthen border security. By congressional mandate, plans for 
expenditure of appropriated funds on this system, the Automated 
Commercial Environment (ACE), must meet certain conditions, including 
GAO review. This study addresses whether the fiscal year 2006 plan 
satisfies these conditions; it also describes the status of DHS’s 
efforts to implement prior GAO recommendations for improving ACE 
management, and provides observations about the plan and DHS’s 
management of the program. 

What GAO Found: 

The fiscal year 2006 ACE expenditure plan, including related program 
documentation and program officials’ statements, either satisfied or 
partially satisfied the legislative conditions imposed by the Congress; 
however, more can be done to better address several aspects of these 
conditions. In addition, DHS has addressed some recommendations that 
GAO has previously made, but progress has been slow in addressing 
several recommendations aimed at strengthening ACE management. For 
example, DHS has more to do to implement the recommendation that it 
establish an ACE accountability framework that, among other things, 
ensures that expenditure plans report progress against commitments made 
in prior plans. Implementing a performance and accountability framework 
is important for ensuring that promised capabilities and benefits are 
delivered on time and within budget. In addition, describing progress 
against past commitments is essential to permit meaningful 
congressional oversight. 

Among GAO’s observations about the ACE program and its management are 
several related to the need to effectively set and use performance 
goals and measures. Although the program set performance goals, these 
targets were not always realistic. For example, in fiscal year 2005, 
the program set a target that 11 percent of all Customs and Border 
Protection (CBP) employees would use ACE. However, this target does not 
reflect the fact that many CBP employees will never need to use the 
system. Additionally, the program has established 6 program goals, 11 
business results, 23 benefits, and 17 performance measures, but the 
relationships among these are not fully defined or adequately aligned 
with each other. For example, not every goal has defined benefits, and 
not every benefit has an associated performance measure. Without 
realistic ACE performance measures and targets that are aligned with 
the overall program goals and desired results, DHS will be challenged 
in its efforts to establish an accountability framework for ACE that 
will help to ensure that the program delivers its expected benefits. 

In addition, DHS plans to develop several increments, referred to as 
“releases,” concurrently; in the past, such concurrency has led to cost 
overruns and schedule delays because releases contended for the same 
resources, and resources that were to be used on later releases were 
diverted to earlier ones. However, because of DHS’s belief that such 
concurrent development will allow it to deliver ACE functionality 
sooner, it is reintroducing the same problems that resulted in past 
shortfalls. 

What GAO Recommends: 

To help ensure the success of ACE, GAO recommends, among other things, 
that DHS develop realistic ACE performance measures and targets; align 
these with ACE program goals, benefits, and desired business outcomes; 
and minimize concurrent development of ACE releases. DHS agreed with 
GAO’s recommendations and described actions that it has under way and 
planned to address them. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-580]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Randolph C. Hite at (202) 
512-3429 or hiter@gao.gov. 

[End of Section] 

Letter: 

Compliance with Legislative Conditions: 

Status of Our Open Recommendations: 

Observations about ACE Management: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments: 

Appendix I: Briefing to Subcommittees on Homeland Security, House and 
Senate Committees on Appropriations: 

Appendix II: Comments from the Department of Homeland Security: 

Appendix III: Contact and Staff Acknowledgments: 

Abbreviations: 

ACE: Automated Commercial Environment: 

CBP: Customs and Border Protection: 

CBPMO: Customs and Border Protection Modernization Office: 

CIO: chief information officer: 

CMU: Carnegie Mellon University: 

DHS: Department of Homeland Security: 

EA: enterprise architecture: 

EVM: earned value management: 

IT: information technology: 

IV&V: independent verification and validation: 

OMB: Office of Management and Budget: 

ORR: operational readiness review: 

SA-CMM®: Software Acquisition Capability Maturity Model: 

SEI: Software Engineering Institute: 

US-VISIT: United States Visitor and Immigrant Status Indicator 
Technology: 

United States Government Accountability Office: 

Washington, DC 20548: 

May 31, 2006: 

The Honorable Judd Gregg: 
Chairman: 
The Honorable Robert C. Byrd: 
Ranking Minority Member: 
Subcommittee on Homeland Security: 
Committee on Appropriations: 
United States Senate: 

The Honorable Harold Rogers: 
Chairman: 
The Honorable Martin Olav Sabo: 
Ranking Minority Member: 
Subcommittee on Homeland Security: 
Committee on Appropriations: 
House of Representatives: 

In February 2006, U.S. Customs and Border Protection (CBP), within the 
Department of Homeland Security (DHS), submitted to the Congress its 
fiscal year 2006 expenditure plan for the Automated Commercial 
Environment (ACE) program. ACE is to be CBP's new import and export 
processing system. The program's goals include: 

* supporting border security by enhancing analysis and information 
sharing with other government agencies and: 

* streamlining time-consuming and labor-intensive tasks for CBP 
personnel and the trade community through the provision of a single Web-
based interface. 

DHS currently plans to acquire and deploy ACE in 11 increments, 
referred to as "releases," in approximately 8.5 years. The first three 
releases are deployed and operating, and the fourth release is being 
deployed. Other releases are in various states of definition and 
development. For the ACE life-cycle, the risk-adjusted cost estimate is 
about $2.8 billion; through fiscal year 2005, ACE-appropriated funding 
has been about $1.6 billion. 

The Department of Homeland Security Appropriations Act of 2006 
[Footnote 1] appropriates about $320 million for ACE. The act states 
that DHS may not obligate any funds for ACE until it submits for 
approval to the House and Senate Committees on Appropriations a plan 
for expenditure that: 

1. meets the capital planning and investment control review 
requirements established by the Office of Management and Budget (OMB), 
including Circular A-11, part 7;[Footnote 2] 

2. complies with DHS's enterprise architecture; 

3. complies with the acquisition rules, requirements, guidelines, and 
systems-acquisition management practices of the federal government; 

4. includes a certification by the DHS Chief Information Officer that 
an independent verification and validation agent is currently under 
contract; 

5. is reviewed and approved by the DHS Investment Review Board 
(IRB),[Footnote 3] the Secretary of Homeland Security, and OMB; and: 

6. is reviewed by GAO. 

As required by the act, we reviewed the ACE fiscal year 2006 
expenditure plan. Our objectives were to (1) determine whether the 
expenditure plan satisfies certain legislative conditions, (2) 
determine the status of our open ACE recommendations, and (3) provide 
any other observations about the expenditure plan and DHS's management 
of the ACE program. 

On March 10, 2006, we briefed your offices on the results of this 
review. This report transmits the results of our work. The full 
briefing, including our scope and methodology, can be found in appendix 
I. 

Compliance with Legislative Conditions: 

The legislative conditions that the Congress placed on the use of 
fiscal year 2006 ACE appropriated funds have been either partially or 
fully satisfied by the latest expenditure plan and related program 
documentation and activities. However, more can be done to better 
address several aspects of these conditions. For example: 

One legislative condition states that the plan should meet OMB's 
capital planning and investment control review requirements, which 
include addressing security and privacy issues. However, a privacy 
impact assessment[Footnote 4] for ACE has been in draft for several 
months and is not yet approved. Another capital planning and investment 
control review requirement is that performance goals and measures be 
provided in the business case for ACE. Although CBP describes selected 
performance goals and measures, the goals (i.e., targets) are not 
always realistic (we provide further discussion of this issue later in 
this report). 

According to another legislative condition, the expenditure plan must 
comply with DHS's enterprise architecture. However, DHS does not have a 
documented methodology for evaluating programs for compliance with its 
enterprise architecture, other than relying on the professional 
expertise of its staff. 

According to a third legislative condition, the DHS Chief Information 
Officer is to certify that an independent verification and validation 
(IV&V) agent is under contract. Although DHS satisfied this condition, 
the scope of the IV&V contractor's activities is not consistent with 
the operative industry standard, which states that IV&V should extend 
to key system products and development processes.[Footnote 5] 

Status of Our Open Recommendations: 

CBP has addressed some recommendations, while progress has been slow on 
others. Each recommendation, along with the status of actions to 
address it, is summarized below. 

Ensure that future expenditure plans are based on cost estimates that 
are reconciled with independent cost estimates. 

Complete.[Footnote 6] In October 2005, CBP, with contractor support, 
compared the program plan cost estimate with the independent cost 
estimate. According to the analysis performed, the two estimates are 
consistent. 

Develop and implement a rigorous and analytically verifiable cost 
estimating program that embodies the tenets of effective estimating, as 
defined in the institutional and project-specific estimating models 
developed by the Software Engineering Institute (SEI).[Footnote 7] 

In progress. CBP has taken steps such as (1) hiring a contractor to 
develop cost estimates (including contract task order cost estimates) 
that are independent of CBP's estimates, and (2) tasking a support 
contractor with evaluating both the independent and CBP estimates 
against the criteria defined by SEI. According to the results of the 
support contractor's evaluation, the independent estimates satisfied 
the SEI criteria; CBP's estimates largely satisfied the criteria. 

However, according to the support contractor, CBP's cost estimating had 
limitations. First, the CBP estimate did not adequately consider past 
projects in its cost and schedule estimates. In addition, the CBP 
estimate was an aggregation of estimates developed separately for three 
ACE components, each according to a different cost estimating 
methodology; the support contractor advised against this approach, 
recommending that component estimates be based on the same methodology. 

Immediately develop and implement a human capital management strategy 
that provides both near-and long-term solutions to program office human 
capital capacity limitations, and report quarterly to the 
Appropriations Committees on the progress of efforts to do so. 

In progress. CBP has expanded its contractor and government workforce 
dedicated to the ACE program by merging staff assigned to trade-related 
legacy systems with the ACE program staff. In addition, it is beginning 
to use subject matter experts from existing field operations advisory 
boards to help program officials define requirements for future 
releases. However, it does not have a documented human capital strategy 
covering its ACE program. 

Have future ACE expenditure plans specifically address any proposals or 
plans, whether tentative or approved, for extending and using ACE 
infrastructure to support other homeland security applications, 
including any impact on ACE of such proposals and plans. 

In progress. The expenditure plan describes steps both planned and 
under way to ensure that ACE infrastructure supports both ACE and other 
homeland security applications. For example, it states that both ACE 
and the United States Visitor and Immigrant Status Indicator 
Technology[Footnote 8] (US-VISIT) program should conform to the DHS 
enterprise architecture, which is to define standard shared services 
that the two systems can request. Such a services oriented architecture 
is intended to promote reuse, as well as reducing overlap and 
duplication. 

Define measures, and collect and use associated metrics, for 
determining whether prior and future program management improvements 
are successful. 

In progress. CBP continues to make changes that are intended to improve 
overall program management, but it has not consistently defined 
measures to determine whether the changes are successful. For example, 
CBP has reorganized its Office of Information Technology; this 
reorganization is intended to improve program management by providing 
(1) enhanced government oversight of ACE development, (2) better 
definition of requirements for future ACE releases, and (3) faster and 
cheaper delivery of ACE capabilities. However, program officials told 
us that they have not established measures or targets for determining 
whether the reorganization is providing these benefits. 

Define and implement an ACE accountability framework that fulfills 
several conditions: 

1. The framework should cover all program commitment areas, including 
key expected or estimated system (a) capabilities, use, and quality; 
(b) benefits and mission value; (c) costs; and (d) milestones and 
schedules. 

In progress. CBP has prepared an initial version of an accountability 
framework that it intends to improve as it proceeds. The framework is 
built around measuring progress against costs, milestones, schedules, 
and risks for select releases; however, the benefit measurement has not 
been well defined, and the performance targets are not always 
realistic. 

2. The framework should ensure currency, relevance, and completeness of 
all program commitments made to the Congress in expenditure plans. 

In progress. The fiscal year 2006 expenditure plan includes inaccurate, 
dated, and incomplete information and omits other relevant information. 
For example, the plan did not include information regarding CBP's 
decision to eliminate the dependencies among the screening and 
targeting releases and the cargo releases, and to take advantage of the 
capabilities of its existing Automated Targeting System.[Footnote 9] 

3. The framework should ensure reliable data that are relevant to 
measuring progress against commitments. 

In progress. The data that CBP uses to measure progress against 
commitments are not consistently reliable. For example, data in the 
defect tracking system show that defects in Release 4 (which is now 
operational) have not been closed; however, program officials told us 
that many of these defects have been resolved. 

4. The framework should ensure that future expenditure plans report 
progress against commitments contained in prior expenditure plans. 

In progress. The current expenditure plan does not adequately describe 
progress against commitments made in previous plans. For example, the 
plan provides a summary of the funding requested in each of the 
previous six expenditure plans, but it does not provide information on 
whether these funding amounts were actually expended or obligated as 
planned. 

5. The framework should ensure that criteria for exiting key readiness 
milestones adequately consider indicators of system maturity, such as 
the severity of open defects. 

In progress. ACE milestone exit criteria provide for addressing the 
risk associated with severe defects that are unresolved. Using these 
criteria, CBP passed several release milestones with severe defects 
still open. However, CBP officials were unable to provide us with any 
documentation on how they assessed the inherent risks of passing these 
milestones with open severe defects. 

6. The framework should ensure clear and unambiguous delineation of the 
respective roles and responsibilities of the government and the prime 
contractor. 

Complete. The current ACE program plan describes general roles and 
responsibilities for the government and the prime contractor. More 
detailed roles have been documented in a roles and responsibilities 
matrix that assigns primary responsibility for each activity. 

Report quarterly to the House and Senate Appropriations Committees on 
efforts to address our open recommendations. 

In progress. CBP submitted quarterly reports to both Committees on its 
efforts to address our open recommendations; however, progress in 
addressing our recommendations was not always reported accurately. 

Observations about ACE Management: 

We have several observations about the development of ACE releases, as 
well as several more concerning the performance of ACE releases that 
are deployed and operating. 

ACE development: Steps have been taken to address a past pattern of ACE 
release shortfalls, but new release management weaknesses are emerging. 

As we have previously observed, CBP established a pattern of borrowing 
resources from future releases to address problems with the quality of 
earlier releases; this led to schedule delays and cost overruns. This 
pattern has continued with the most recently deployed cargo release, 
which developed problems that caused delays with a subsequent screening 
and targeting release.[Footnote 10] CBP took steps to mitigate this 
problem by eliminating the dependencies between the cargo releases and 
the screening and targeting releases. 

However, CBP's planned schedule for developing additional releases 
includes a significant level of concurrence, because of CBP's interest 
in delivering ACE functionality sooner. Such concurrence between ACE 
release activities has led to cost overruns and schedule delays in the 
past. Thus, the revised ACE plans and actions are potentially 
reintroducing the same problems that produced past shortfalls. 

We made several specific observations related to these weaknesses, 
including the following: 

On two recent releases, key milestones were passed despite unresolved 
severe defects. Officials told us that the risk of proceeding did not 
outweigh the need to get the releases to users, and thereby gaining 
user acceptance and feedback. However, the risks were not documented 
and formally managed. 

Concurrence in developing early ACE releases caused schedule slips and 
cost overruns. Despite these experiences, CBP has established a risky 
plan that involves considerable overlap across the development 
schedules for three future releases. 

Although the use of earned value management (EVM) is an OMB 
requirement, it was not being used to manage the development of two 
recent releases.[Footnote 11] For example, CBP discontinued use of EVM 
on one release because this method was not familiar to staff who were 
transferred to work on the program. 

ACE operations: Operational performance has been mixed, and mission 
impact is unclear. 

ACE releases one through four are in operation. To date, these 
releases' operational performance has been uneven. For example, ACE has 
largely been meeting its goals for being available and responsive in 
processing virtually all daily transactions, and has decreased truck 
processing times at some ports. However, ACE is not being used by as 
many CBP and trade personnel as was expected, and truck processing 
times at other ports have increased. Moreover, overall user 
satisfaction has been low. 

In addition, ACE goals, expected mission benefits, and performance 
measures are not fully defined and adequately aligned with each other. 
For example, not every goal has defined benefits, every benefit is 
defined only in terms of efficiency gains, not every benefit has an 
associated business result, and not every benefit and business result 
has associated performance measures. 

Further, where performance measures have been defined, the associated 
targets are not always realistic. For example, the performance target 
in fiscal year 2005 for ACE usage was that 11 percent of all CBP 
employees would use ACE. However, that many CBP employees will never 
need to use the system. This performance target does not reflect that. 

Because performance measures are not always realistic or aligned with 
program goals and benefits, it is unclear whether ACE has realized--or 
will realize--the mission value that it was intended to bring to CBP's 
and other agencies' trade-and border security-related operations. 

Conclusions: 

The legislative conditions that the Congress placed on the use of 
fiscal year 2006 ACE appropriated funds have been either partially or 
fully satisfied by the latest expenditure plan and related program 
documentation and activities. Nevertheless, more can be done to better 
address several aspects of these conditions, such as ensuring that the 
program's privacy impact assessment is approved, measuring ACE 
performance and results, ensuring architectural alignment, and 
employing effective IV&V practices. Given that the legislative 
conditions are collectively intended to promote accountability and 
increase the chances of program success, it is important that each 
receives DHS's full attention. 

Also important to ACE's success is the swift and complete 
implementation of the recommendations that we have previously made to 
complement the legislative conditions and improve program management, 
performance, and accountability. In this regard, some recommendations 
have been addressed, while progress has been slow on others, such as: 

* accurately reporting to the Appropriations Committees on CBP's 
progress in implementing our prior recommendations; 

* developing and implementing a strategic approach to meeting the 
program's human capital needs; 

* using criteria for exiting key milestones that adequately consider 
indicators of system maturity, such as severity of open defects and the 
associated risks; and: 

* developing and implementing a performance and accountability 
framework for ensuring that promised capabilities and benefits are 
delivered on time and within budget. 

To its credit, CBP has taken several steps to stem the pattern of cost, 
schedule, and performance shortfalls that it experienced on early ACE 
releases. However, future releases are unlikely to realize the impact 
of these steps because revised ACE plans and actions are reintroducing 
the same pattern that led to early release shortfalls. This pattern 
includes not formally and transparently considering, and proactively 
addressing, the risks associated with passing key release milestones 
with known severe defects; building considerable overlap and 
concurrence in the development schedules of releases that will contend 
for the same resources; and not performing EVM on all releases. If this 
pattern continues, the prospects for a successful program will be 
diminished. 

Although availability and responsiveness targets are largely being met 
and long-standing help desk limitations are being addressed, the 
prospects for a successful program nevertheless remain unclear. The 
true measure of ACE's success is arguably the mission value that it 
brings to CBP's and other agencies' trade-and border security-related 
operations and users. Such value depends both on the operational 
performance of ACE and on CBP's ability to demonstrate that this 
performance is achieving program goals, delivering expected benefits, 
and producing desired business results. At this juncture, however, 
neither the system's performance nor its value is clear because of 
several factors: the operational performance of deployed releases has 
been mixed; users' satisfaction has been low; the relationships among 
goals, benefits, and desired business outcomes are not evident; and the 
range of measures needed to create a complete and realistic picture of 
ACE's performance is missing. 

In summary, a number of ACE activities have been and are being done 
well; these have contributed to the program's progress to date and will 
go a long way in determining the program's ultimate success. However, 
it will be important for CBP to effectively address long-standing ACE 
management challenges along with emerging problems. Until it does so, 
ACE will remain a risky program. 

Recommendations for Executive Action: 

To assist CBP in managing ACE--and increasing the chances that it will 
deliver required capabilities on time and within budget, demonstrating 
promised mission benefits and results--we recommend that the Secretary 
of Homeland Security direct the appropriate departmental officials to 
fully address those legislative conditions associated with having an 
approved privacy impact assessment and ensuring architectural 
alignment. 

We also recommend that the Secretary, through CBP's Acting 
Commissioner, direct the Assistant Commissioner for Information and 
Technology to: 

* fully address those legislative conditions associated with measuring 
ACE performance and results and employing effective IV&V practices; 

* accurately report to the appropriations committees on CBP's progress 
in implementing our prior recommendations; 

* include in the June 30, 2006, quarterly update report to the 
appropriations committees a strategy for managing ACE human capital 
needs and the ACE framework for managing performance and ensuring 
accountability; 

* document key milestone decisions in a way that reflects the risks 
associated with proceeding with unresolved severe defects and provides 
for mitigating these risks; 

* minimize the degree of overlap and concurrence across ongoing and 
future ACE releases, and capture and mitigate the associated risks of 
any residual concurrence; 

* use EVM in the development of all existing and future releases; 

* develop the range of realistic ACE performance measures and targets 
needed to support an outcome-based, results-oriented accountability 
framework, including user satisfaction with ACE; and: 

* explicitly align ACE program goals, benefits, desired business 
outcomes, and performance measures. 

Agency Comments: 

In written comments on a draft of this report signed by the Director, 
Departmental GAO/OIG Liaison, DHS agreed with our findings concerning 
progress in addressing our prior recommendations, and it agreed with 
the recommendations in this report. DHS also described actions that it 
has under way and planned to address the recommendations. The 
department's comments are reprinted in appendix II. 

We are sending copies of this report to the Chairmen and Ranking 
Minority Members of other Senate and House committees and subcommittees 
that have authorization and oversight responsibilities for homeland 
security. We are also sending copies to the DHS Secretary, the CBP 
Commissioner and, upon their request, to other interested parties. In 
addition, the report will be available at no charge on the GAO Web site 
at [Hyperlink, http://www.gao.gov]. 

Should you or your offices have any questions on matters discussed in 
this report, please contact me at (202) 512-3459 or at hiter@gao.gov. 
Contact points for our Offices of Congressional Relations and Public 
Affairs may be found on the last page of this report. Other contacts 
and key contributors to this report are listed in appendix III. 

Signed by: 

Randolph C. Hite: 
Director, Information Technology Architecture and Systems Issues: 

[End of section] 

Appendix I: Briefing to Subcommittees on Homeland Security, House and 
Senate Committees on Appropriations: 

Information Technology: Customs Has Made Progress on Automated 
Commercial Environment System, but it Faces Long-Standing Management 
Challenges and New Risks: 

Briefing to the Staffs of the Subcommittees on Homeland Security, 
Senate and House Committees on Appropriations: 

March 10, 2006: 

Briefing Overview: 

Introduction: 
Objectives: 
Results in Brief: 
Background: 
Results: 
* Legislative Conditions: 
* Status of Recommendations: 
* Observations: 
Conclusions: 
Recommendations: 
Agency Comments: 
Attachment 1: Scope and Methodology: 

Introduction: 

The Department of Homeland Security's (DHS) Customs and Border 
Protection (CBP)[Footnote 12] is about 5 years into its trade 
processing modernization program, known as the Automated Commercial 
Environment (ACE). The goals of ACE are as follows: 

Support border security by enhancing analysis and information sharing 
with other government agencies to deal with increasing new security 
threats to our nation. Provide CBP personnel with the technology and 
information needed to decide, before a shipment reaches the border, 
what should be targeted[Footnote 13] because it is a security threat, 
and what should be expedited because it complies with U.S. laws. 

Provide an integrated, fully automated information system to enable the 
efficient collection, processing, and analysis of commercial import and 
export data. Streamline time-consuming and labor-intensive tasks for 
CBP personnel and the trade community, through a single, Web-based 
interface, reducing costs for the government and the trade community. 

Enable users to process, view, and manage their accounts nationally, 
and obtain historical information on cargo, conveyances, and crew, 
based on screening and targeting rules. 

Enable CBP to comply with legislative mandates to improve efficiency/ 
effectiveness and provide better customer service to U.S. citizens. 

The Department of Homeland Security Appropriations Act, 2006,[Footnote 
14] appropriates about $320 million for ACE and states that DHS may not 
obligate any funds for ACE until it submits for approval to the House 
and Senate Committees on Appropriations a plan for expenditure that: 

1. meets the capital planning and investment control review 
requirements established by the Office of Management and Budget (OMB), 
including Circular A-11, part 7;[Footnote 15]: 

2. complies with DHS's enterprise architecture; 

3. complies with the acquisition rules, requirements, guidelines, and 
systems acquisition management practices of the federal government; 

4. includes a certification by the Chief Information Officer of DHS 
that an independent verification and validation agent is currently 
under contract; 

5. is reviewed and approved by the DHS Investment Review Board 
(IRB),[Footnote 16] the Secretary of Homeland Security, and OMB; and: 

6. is reviewed by GAO. 

On February 2, 2006, DHS submitted its fiscal year 2006 expenditure 
plan for $316.8 million to the House and Senate Appropriations 
Subcommittees on Homeland Security. 

DHS currently plans to acquire and deploy ACE in 11 increments, 
referred to as releases. The first three releases are fully deployed 
and operating, and the fourth release is being deployed. Other releases 
are in various stages of definition and development. 

Objectives: 

As agreed, our objectives were to: 

* determine whether the ACE fiscal year 2006 expenditure plan satisfies 
the legislative conditions, 

* determine the status of our open recommendations on ACE, and: 

* provide any other observations about the expenditure plan and DHS's 
management of the ACE program. 

We conducted our work at CBP headquarters and contractor facilities in 
the Washington, D.C., metropolitan area, as well as at the port in 
Blaine, Washington, from July 2005 through March 2006, in accordance 
with generally accepted government auditing standards. Details of our 
scope and methodology are provided in attachment 1. 

Results in Brief: 

Objective 1: Satisfaction of legislative conditions: 

The legislative conditions that the Congress placed on the use of 
fiscal year 2006 ACE appropriated funds have been either partially or 
fully satisfied by the latest expenditure plan and related program 
documentation and activities. Nevertheless, more can be done to better 
address several aspects of these conditions, such as having an approved 
privacy impact assessment, measuring ACE performance and results, 
ensuring architectural alignment, and employing effective independent 
verification and validation (IV&V) practices. The following table 
summarizes the status of each of the legislative conditions. 

Legislative condition; Status. 

1. Meets the capital planning and investment control review 
requirements established by OMB, including OMB Circular A-11, part 7; 
Status: Partially satisfied[A]. 

2. Complies with DHS's enterprise architecture; 
Status: Partially satisfied. 

3. Complies with the acquisition rules, requirements, guidelines, and 
systems acquisition management practices of the federal government; 
Status: Satisfied[B]. 

4. Includes a certification by the Chief Information Officer of DHS 
that an independent verification and validation agent is currently 
under contract; 
Status: Satisfied. 

5. Is reviewed and approved by the DHS Investment Review Board, 
Secretary of Homeland Security, and OMB; 
Status: Satisfied. 

6. Is reviewed by GAO; 
Status: Satisfied. 

Source: GAO. 

[A]Partially satisfied means that the plan, in combination with 
supporting documentation, either satisfied; or provided for satisfying 
many, but not all, key aspects of the condition that we reviewed. 

[B]Satisfied means that the plan, in combination with supporting 
documentation, either satisfied or provided for satisfying every aspect 
of the condition that we reviewed. 

[End of Table]

Objective 2: Status of actions to implement our open recommendations: 

Some recommendations have been addressed, while progress has been slow 
on others, such as: 

* accurately reporting to the Appropriations Committees on CBP's 
progress in implementing our prior recommendations; 

* developing and implementing a strategic approach to meeting the 
program's human capital needs; 

* using criteria for exiting key milestones that adequately consider 
indicators of system maturity, such as severity of open defects and the 
associated risks; and: 

* developing and implementing a performance and accountability 
framework for ensuring that promised capabilities and benefits are 
delivered on time and within budget. 

The following table summarizes the status of each of the open 
recommendations. 
 
GAO recommendation: 1. Ensure that future expenditure plans are based 
on cost estimates that are reconciled with independent cost estimates: 
Number of months open: 7 months[[A]]; 
Status: Complete [[B] , C]. 

GAO recommendation: 2. Develop and implement a rigorous and 
analytically verifiable cost estimating program: 
Number of months open: 46 months; 
Status: in progress[[D]]. 

GAO recommendation: 3. Immediately develop and implement a human 
capital management strategy that provides both near-and long-term 
solutions; develop and implement missing human capital practices: 
Number of months open: 46 months; 
Status: In progress. 

GAO recommendation: 4. Have future ACE expenditure plans specifically 
address any proposals or plans for extending and using ACE 
infrastructure to support other homeland security applications: 
Number of months open: 36 months 
Status: In progress. 

GAO recommendation: 5. Define measures, and collect and use associated 
metrics, for determining whether prior and future program management 
improvements are successful: 
Number of months open: 22 months 
Status: In progress. 

GAO recommendation: 6. Define and implement an ACE accountability 
framework that ensures:  

GAO recommendation: 6a. coverage of all program commitment areas, 
including key expected or estimated system (1) capabilities, use, and 
quality; (2) benefits and mission value; (3) costs; and (4) milestones 
and schedules: 
Number of months open: 12 months 
Status: In progress. 

GAO recommendation: 6b. currency, relevance, and completeness of all 
such commitments made to the Congress in expenditure plans: 
Number of months open: 12 months 
Status: In progress. 

GAO recommendation: 6c. reliable data relevant to measuring progress 
against committments; 
Number of months open: 12 months; 
Status: In progress. 

GAO recommendation: 6d. reporting in future expenditure plans progress 
against commitments contained in prior expenditure plans: 
Number of months open: 12 months; 
Status: In progress. 

GAO recommendation: 6e. use of criteria for exiting key readiness 
milestones that adequately consider indicators of system maturity, such 
as severity of open defects:  
Number of months open: 12 months; 
Status: In progress. 

GAO recommendation: 6f. clear and unambiguous delineation of the 
respective roles and responsibilities of the government and the prime 
contractor:  
Number of months open: 12 months; 
Status: Complete. 

GAO recommendation: 7. Report quarterly to the House and Senate 
Appropriations Committees on efforts to address open GAO 
recommendations:  
Number of months open: 22 months; 
Status: In progress. 

Source: GAO. 

[A] Recommendation was also completed with respect to the fiscal year 
2005 expenditure plan 

[B] With respect to the fiscal year 2006 expenditure plan 

[C] Complete means that actions have been taken to fully implement the 
recommendation 

[D] In progress means that actions are under way to implement the 
recommendation 

[End of table] 

Objective 3: Observations: 

Steps have been taken to address past pattern of ACE release 
shortfalls, but new release management weaknesses are emerging. 

* Release 4 pilot revealed performance problems that caused the pilot 
period to be extended and the pilot scope to be reduced. 

* Release 4 operational readiness review was passed despite unresolved 
severe defects, and Release 4 is now being deployed. 

* Release 4 quality problems and enhancement needs have led to changes 
in how ACE release requirements are defined. 

* Release 4 problems delayed Screening 1 and led to a revised strategy 
for delivering all screening and targeting releases. 

* Screening 1 key milestones were passed despite unresolved severe 
defects. 

* Past pattern of cost, schedule, and performance shortfalls with 
Releases 2, 3, and 4 makes new strategy of concurrently developing 
Releases 5, 6, and 7 risky. 

* Earned value management (EVM), a technique for measuring progress 
toward meeting deliverables, is not being used to manage Screening 1 
and Release 5. 

ACE's operational performance has been mixed, and mission impact is 
unclear. 

* Availability and responsiveness performance targets are largely being 
met. 

* Processing times for trucks crossing the border at key ports vary. 

* Long-standing help desk limitations are being addressed. 

* Usage by CBP and the trade is lower than expected. 

* User satisfaction was reported as low. 

* Performance targets are not always realistic. 

* Goals, expected mission benefits, and performance measures are not 
adequately aligned. 

To assist CBP in managing ACE and increasing the chances that it will 
deliver required capabilities on time and within budget and demonstrate 
promised mission benefits and results, we are recommending that DHS: 

* fully address legislative conditions associated with having an 
approved privacy impact assessment, measuring ACE performance and 
results, ensuring architectural alignment, and employing effective IV&V 
practices; 

* accurately report to the Appropriations Committees on CBP's progress 
in implementing our prior recommendations; 

* include in the June 30, 2006, quarterly update report to the 
Appropriations Committees a strategy for managing ACE human capital 
needs and the ACE framework for managing performance and ensuring 
accountability; 

* document key milestone decisions in a way that reflects the risks 
associated with proceeding with unresolved severe defects and provides 
for mitigating these risks; 

* minimize the degree of overlap and concurrency across ongoing and 
future ACE releases, and capture and mitigate the associated risks of 
any residual concurrency; 

* use EVM in the development of all existing and future releases; 

* develop the range of realistic ACE performance measures and targets 
needed to support an outcome-based, results-oriented accountability 
framework, including user satisfaction with ACE; and: 

* explicitly align ACE program goals, benefits, desired business 
outcomes, and performance measures. 

In their oral comments on a draft of this briefing, DHS and CBP 
officials, including the Executive Director of Cargo Management 
Systems, CBP, generally agreed with our findings, conclusions, and 
recommendations and stated that the presentation was fair and balanced. 
They also provided clarifying information that we incorporated as 
appropriate in this briefing. 

Background: 

ACE-Related Business Functions: 

ACE is to support eight major CBP business areas. 

1. Release[Footnote 17] Processing: Processing of cargo for import or 
export; tracking of conveyances, cargo, and crew; and processing of in-
bond, warehouse, Foreign Trade Zone, and special import and export 
entries. 

2. Entry[Footnote 18] Processing: Liquidation and closeout of entries 
and entry summaries related to imports, and processing of protests and 
decisions. 

3. Finance: Recording of revenue, performance of fund accounting, and 
maintenance of the general ledger. 

4. Account Relationships: Maintenance of trade accounts, their bonds 
and CBP-issued licenses, and their activity. 

5. Legal and Policy: Management of import and export legal, regulatory, 
policies and procedures, and rulings issues. 

6. Enforcement: Enforcement of laws, regulations, policies and 
procedures, and rulings governing the import and export of cargo, 
conveyances, and crew. 

7. Business Intelligence: Gathering and reporting data, such as 
references for import and export transactions, for use in making 
admissibility and release decisions. 

8. Risk: Decision making about admissibility and compliance of cargo 
using risk-based mitigation, screening,[Footnote 19] and 
targeting.[Footnote 20] 

ACE Technical Architecture: 

The ACE technical architecture is to consist of layers or tiers of 
computer technology: 

* The Client Tier includes user workstations and external system 
interfaces. 

* The Presentation Tier provides the mechanisms for the user 
workstations and external systems to access ACE. 

* The Integration Services Tier provides the middleware for integrating 
and routing information between ACE software applications and legacy 
systems. 

* The Applications Tier includes the ACE software applications 
comprising commercial products (e.g., SAP[Footnote 21]) and custom-
developed software that provide the functionality supporting CBP 
business processes. 

* The Data Tier provides the data management and warehousing services 
for ACE, including database backup, restore, recovery, and space 
management. 

Security and data privacy are to be embedded in all five layers. 

Figure1: Simplified View of ACE Technical Architecture: 

[See PDF for image] 

Source: GAO analysis based on CBP data. 

[End of figure] 

Acquisition Strategy: 

CBP is the component agency within DHS that is responsible for ACE. 
Currently, CBP is headed by an Acting Commissioner. Within CBP, the ACE 
program is located within the Office of Information Technology, which 
is headed by the Assistant Commissioner for Information and Technology. 

ACE is being acquired and implemented through a series of incremental 
releases. On April 27, 2001, CBP awarded a contract to IBM Global 
Services to develop and implement ACE. IBM and its subcontractors are 
collectively called the ACE Support Team (formerly called e-Customs 
Partnership). 

CBP currently plans to acquire the 11 ACE releases in about 8.5 years. 
Screening 2 is to be acquired in two "drops," or subreleases; Release 5 
is to be acquired in two drops; Release 6 is to be acquired in three 
drops; and Release 7 is to be acquired in two drops. 

Summary of ACE Releases: 

Figure 2: Planned Schedule for ACE: 

[See PDF for Image] 

[End of Figure] 

The following presents the functionality provided by the 11 ACE 
releases, their status, and associated plans. 

Release 1 (ACE Foundation): Provide information technology (IT) 
infrastructure-computer hardware and system software-to support 
subsequent system releases. This release was deployed in October 2003 
and is operating. 

Release 2 (Account Creation): Give initial group of CBP national 
account managers[Footnote 22] and importers access to account 
information, such as trade activity. This release was deployed in 
October 2003 and is operating. 

Release 3 (Periodic Payment): Provide additional account managers and 
importers, as well as brokers and carriers,[Footnote 23] access to 
account information; provide initial financial transaction processing 
and CBP revenue collection capability, allowing importers and their 
brokers to make monthly payments of duties and fees. This release was 
deployed in July 2004 and is operating. 

Release 4 (e-Manifest: Trucks): Provide electronic truck 
manifest[Footnote 24] processing and interfacing to legacy enforcement 
systems and databases. As discussed later, this release is operating at 
39 truck border crossings as of March 8, 2006. Additional enhancement 
releases for Release 4 have been deployed since May 2005. 

Screening 1 (Screening Foundation): Establish the foundation for 
screening cargo and conveyances by centralizing criteria and results 
into a single standard database; allow users to define and maintain 
data sources and business rules. This release is scheduled for 
deployment beginning in March 2006. 

Screening 2 (Targeting Foundation): Establish the foundation for 
advanced targeting capabilities by enabling CBP's National Targeting 
Center to search multiple databases for relevant facts and actionable 
intelligence. This release is scheduled for deployment in two drops: 

* Screening 2 Targeting Platform (TP): Provide a platform to collect 
and search relevant data and other information from multiple databases. 
This drop is scheduled for deployment beginning in June 2006. 

* Screening 2 Targeting Foundation (TF): Build on the targeting 
platform to add new data sources, enhance screening business rules, and 
provide reporting capabilities. This drop is scheduled for deployment 
beginning in October 2006; however, CBP deployed a prototype to the 
National Targeting Center as part of an effort to gather detailed 
requirements. 

Release 5 (Entry Summary, Accounts, and Revenue): Leverage SAP 
technologies to enhance and expand accounts management, financial 
management, and entry summary functionality. This release is being 
developed in two drops: 

* Master Data and Enhanced Accounts (Drop A1): Use SAP to deliver 
enhanced account creation and maintenance functionality and expand the 
types of accounts managed in ACE. This drop is scheduled for deployment 
beginning in May 2007. 

* Entry Summary and Revenue (Drop A2): Expand ACE to encompass entry 
summary, interfaces with participating government agencies, calculation 
of duties and fees, reconciliation processing, and refunds. This drop 
is scheduled for deployment beginning in July 2008. 

Screening 3 (Advanced Targeting Capabilities): Provide enhanced 
screening for reconciliation, intermodal manifest, Food and Drug 
Administration data, and in-bond, warehouse, and Foreign Trade Zone 
authorized movements; integrate additional data sources into targeting 
capability; and provide risk management capability. This release is 
scheduled for deployment beginning in February 2007. 

Screening 4 (Full Screening and Targeting): Provide full screening and 
targeting functionality supporting all modes of transportation and all 
transactions within the cargo management life cycle, including enhanced 
screening and targeting capability with additional technologies. This 
release is scheduled for deployment beginning in December 2008. 

Release 6 (e-Manifest: All Modes and Cargo Security): Provide 
electronic manifest capability for rail, air, and sea shipments; 
provide a multimodal manifest;[Footnote 25] enable full tracking of 
cargo, conveyances, individuals, and equipment; and enhance enforcement 
processes for rail, air, and sea. This release is planned for 
development in three drops: 

E-Manifest: Rail and Sea (Drop M1): Extend the electronic manifest 
functionality to rail and sea shipments; convert rail, sea, and truck 
electronic manifests into the multimodal manifest. Drop M1 is scheduled 
for deployment beginning in July 2008. 

E-Manifest: Air (Drop M2): Provide the electronic manifest capability 
to air shipments, and bring all modes of transportation into the 
multimodal manifest. Drop M2 is scheduled for deployment beginning in 
October 2007. 

E-Manifest: Enhanced Tracking (Drop M3): Provide the capability to 
track cargo, conveyances, individuals, and equipment, providing more 
timely and accurate shipment status information. Drop M3 is scheduled 
for deployment beginning in June 2009. 

Release 7 (Exports and Cargo Control): Implement the remaining accounts 
management, revenue, manifest, and release and export functionality. 
This release is planned for development in two drops: 

* ESAR: Drawback, Protest, and IASS (Drop A3): Provide the import 
activity summary statement (IASS),[Footnote 26] drawback functionality, 
and enhanced protest; provide on-line processing for trade account 
applications. Drop A3 is scheduled for deployment beginning in December 
2009. 

* E-Manifest: Final Exports and Manifest (Drop M4): Extend the 
electronic manifest for mail, pipeline, and hand carry; provide for 
electronic export processing. Drop M4 is scheduled for deployment 
beginning in December 2009. 

Deployment Status: 

As of March 8, 2006, ACE, Releases 1 through 4 capabilities have been 
deployed to 39 of the 99 truck ports (see table). 

Table 3: 

[See PDF for Image] 

[End of Table] 

ACE Satisfaction of Modernization Act Requirements: 

ACE is intended to support CBP satisfaction of the provisions of Title 
VI of the North American Free Trade Agreement, commonly known as the 
Modernization Act. Subtitle B of the Modernization Act contains the 
various automation provisions that were intended to enable the 
government to modernize international trade processes and permit CBP to 
adopt an informed compliance approach with industry. The following 
table illustrates how each ACE release is to fulfill the requirements 
of Subtitle B. 

Figure 3: ACE Satisfaction of Modernization Act Requirements: 

[See PDF for Image] 

Source: CBP. 

[End of Figure] 

Contract Tasks: 


Thus far, CBP has executed 21 contract task orders-12 have been 
completed and 9 are active. 

Table 4: Status and Description; of Completed Task Orders. 

[See PDF for Image] 

[End of table] 

Nine contract task orders are active. 

Table 5: Status and Description of Active Task Orders. 

[See PDF For Image] 

[End of table] 

Chronology of Seven ACE Expenditure Plans: 

Since March 2001, seven ACE expenditure plans have been 
submitted.[Footnote 27] Collectively, the seven plans have identified a 
total of $1,698.1 million in funding. 

On March 26, 2001, CBP submitted to its appropriations committees the 
first expenditure plan seeking $45 million for the modernization 
contract to sustain Customs and Border Protection Modernization Office 
(CBPMO) operations, including contractor support. The appropriations 
committees subsequently approved the use of $45 million, bringing the 
total ACE funding to $50 million. 

On February 1, 2002, the second expenditure plan sought $206.9 million 
to sustain CBPMO operations; define, design, develop, and deploy 
Increment 1, Release 1 (now Releases 1 and 2); and identify 
requirements for Increment 2 (now part of Releases 5, 6, and 7 and 
Screenings 1 and 2). The appropriations committees subsequently 
approved the use of $188.6 million, bringing total ACE funding to 
$238.6 million. 

On May 24, 2002, the third expenditure plan sought $190.2 million to 
define, design, develop, and implement Increment 1, Release 2 (now 
Releases 3 and 4). The appropriations committees subsequently approved 
the use of $190.2 million, bringing the total ACE funding to $428.8 
million. 

On November 22, 2002, the fourth expenditure plan sought $314 million 
to operate and maintain Increment 1 (now Releases 1, 2, 3, and 4); to 
design and develop Increment 2, Release 1 (now part of Releases 5, 6, 
and 7 and Screening 1); and to define requirements and plan Increment 3 
(now part of Releases 5, 6, and 7 and Screenings 2, 3, and 4). The 
appropriations committees subsequently approved the use of $314 
million, bringing total ACE funding to $742.8 million. 

On January 21, 2004, the fifth expenditure plan sought $318.7 million 
to implement ACE infrastructure; to support, operate, and maintain ACE; 
and to define and design Release 6 (now part of Releases 5, 6, and 7) 
and Selectivity 2 (now Screening 2 and 3). The appropriations 
committees subsequently approved the use of $316.8 million, bringing 
total ACE funding to $1,059.6 million. 

On November 8, 2004, the sixth expenditure plan sought $321.7 million 
for design and development of Release 5 and Screening 2, definition of 
Screening 3, ACE program management, architecture and engineering, and 
operations and maintenance. The appropriations committees subsequently 
approved the use of $321.7 million, bringing total ACE funding to 
$1,381.3 million. 

* On February 02, 2006, CBP submitted its seventh expenditure plan, 
seeking $316.8 million for detailed design and development of Release 
5, development of Release 6, deployment of Screening 2, development and 
deployment of Screening 3, program management and operations, and ACE 
operations, maintenance, and infrastructure implementation. 

Summary of Funding: 

Table 6: Summary of the ACE Fiscal Year 2006 Expenditure Plan: 

[See PDF for Image] 

Source: CBP.

[A] Millions of dollars. 

[End of table] 

The plan does not include management reserve funding. As of December 
15, 2005, the program had about $33.8 million in unused management 
reserve funding from prior years.

ACE Testing and Related Milestones. 

Development of each ACE release includes system integration and system 
acceptance testing, followed by a pilot period that includes user 
acceptance testing. Generally, the purpose of these tests is to ensure 
that the system meets defined system requirements or satisfies user 
needs. The associated readiness reviews are to ensure that the system 
is ready to proceed to the next stage of testing or operation. 

Tests and their related milestones are described in the following 
table. 

[See PDF for Image] 

Source: eCP. 

[A] Generally, the identified milestone review comes at the conclusion 
of the related test. 

[End of table] 

Defect Categories. 

Defects identified during testing and operation of the system are 
classified into one of four severity categories, as described below. 

[See PDF for Image] 

[End of Table] 

Previous GAO Observations: 

Since 2001, we have reviewed CBP's six prior expenditure plans and made 
a number of observations that relate to cost overruns, schedule delays, 
quality limitations, and program management shortcomings. Among other 
things, we observed the following: 

* Release 1 and 2 testing revealed a sufficient volume and significance 
of system defects to result in schedule delays.[Footnote 28]: 

* Following cost overruns and schedule delays with Release 1, steps 
were taken to avoid future problems, but the means for measuring the 
success of the actions was not in place.: 

* Delays in Release 2 began a pattern of increased reliance on 
concurrent activities, which in turn caused future release delays and 
cost overruns.[Footnote 29]: 

* Release 3 testing and pilot activities were delayed and produced 
system defect trends that raised questions about decisions to pass key 
milestones and about the state of system maturity.[2] 

* Release 4 test phases were delayed and overlapped, and tests revealed 
a higher than expected volume and significance of defects, which again 
raised questions about decisions to pass key milestones and about the 
state of system maturity.': 

* Progress toward activating ACE importer accounts had not met 
expectations.[Footnote 30]: 

Objective 1: Legislative Conditions Capital Planning Requirements: 

DHS and OMB satisfied or partially satisfied each of its legislative 
conditions; GAO satisfied its legislative condition. 

Condition 1. The plan is to meet the capital planning and investment 
control review requirements established by OMB, including Circular A- 
11, part 7, which establishes policy for planning, budgeting, 
acquisition, and management of federal capital assets. The plan, in 
conjunction with related program documentation and program officials' 
statements, partially satisfied the condition. 

The table that follows provides examples of the results of our 
analysis. 

Table: Legislative Conditions: 

[See PDF for Image] 

[End of Table]

Objective 1: Legislative Conditions Enterprise Architecture Compliance: 

Condition 2. The plan is to comply with DHS's enterprise architecture 
(EA). The plan, including related program documentation and program 
officials' statements, partially satisfied this condition. 

The DHS Enterprise Architecture Board, supported by the Enterprise 
Architecture Center of Excellence, is responsible for ensuring that 
projects demonstrate adequate technical and strategic compliance with 
the department's EA. 

In May 2005, CBP requested that the DHS Enterprise Architecture Board 
evaluate its analysis of ACE's alignment with the department's EA. 
Using the ACE fiscal year 2006 business case, the ACE program plan, and 
other documentation, the Center of Excellence evaluated alignment with 
version 2.0 of the DHS EA business model, data architecture, technical 
reference model, and transition strategy. In July 2005, the center 
approved CBP's analysis and recommended that the request for program 
alignment be approved. The Enterprise Architecture Board subsequently 
concurred with the center's recommendation. 

DHS required CBP to provide documentation to support ACE's alignment 
with aspects of the EA such as the business architecture, the data 
model, the transition strategy, and the technical reference model. 
However, DHS officials told us that they do not have a documented 
methodology for evaluating programs for compliance with the DHS EA, 
other than relying on the professional expertise of the members of the 
Center of Excellence. Moreover, no analysis or documentation was 
produced by the evaluators that could be used to verify the degree of 
alignment. 

Condition 3. The plan is to comply with the acquisition rules, 
requirements, guidelines, and systems acquisition management practices 
of the federal government. The plan, in conjunction with related 
program documentation, satisfied this condition. 

The Software Acquisition Capability Maturity Model (SA-CMMO), developed 
by Carnegie Mellon University's Software Engineering Institute (SEI), 
is consistent with the acquisition guidelines and systems acquisition 
management practices of the federal government, and it provides a 
management framework that defines acquisition practices for such 
process areas as acquisition planning, solicitation, requirements 
development and management, project management, contract tracking and 
oversight, and evaluation. 

In November 2003, SEI assessed ACE acquisition management processes and 
practices against the SA-CMM and assigned a level 2 rating, indicating 
that CBP had instituted basic acquisition management processes and 
controls in the following areas: acquisition planning, solicitation, 
requirements development and management, project management, contract 
tracking and oversight, and evaluation. 

Independent Verification and Validation: 

Condition 4. The DHS Chief Information Officer (CIO) is to certify that 
an independent verification and validation (IV&V) agent is under 
contract. DHS satisfied this condition. 

On January 26, 2006, the DHS CIO certified that an IV&V agent is under 
contract for the ACE program. However, the CIO also reported that the 
contractor's approach needs to be improved. For example, the CIO said 
that the contractor needs to address ACE satisfaction of quality 
standards and user needs. 

Further, the scope of the contractor's activities is not consistent 
with the operative industry standard, which states that IV&V should 
extend to key system products and development processes.[Footnote 31] 
CBP's IV&V contract, awarded in December 2004, recognizes the 
importance of this scope of activities by requiring the contractor to 
implement a program consistent with this standard. 

In fiscal year 2005, CBP expended approximately $310,000 on IV&V. 
However, these resources have been used to assess certain program 
management processes, such as ACE help desk activities and progress in 
hiring Office of Information Technology staff. They have not been used 
to, for example, examine the development of ACE requirements or the 
quality of ACE software releases. 

According to CBP officials, the scope of the IV&V contractor's 
activities has not included ACE product quality because they believe 
that such verification and validation activities would duplicate the 
program's own quality assurance and testing activities. While we agree 
that the IV&V agent should not duplicate work that is already performed 
by an entity that is independent of the program's cost and schedule 
processes, both the DHS CIO and the IV&V agent's statement of work have 
directed that product quality be addressed. For fiscal year 2006, CBP 
plans to spend $856,000 on IV&V. 

Review by DHS and OMB: 

Condition 5. The plan is to be reviewed and approved by the DHS 
Investment Review Board (IRB), the Secretary of Homeland Security, and 
OMB. DHS and OMB satisfied this condition. 

On November 21, 2005, the DHS IRB reviewed the ACE program. The Under 
Secretary for Management approved the expenditure plan on behalf of the 
Secretary of Homeland Security on February 2, 2006. 

OMB approved the plan on December 30, 2005. 

Review by GAO: 

Condition 6. GAO is to review the plan. We satisfied this condition. 
Our review was completed on March 10, 2006. 

Open Recommendations: 

CBP has implemented one of our seven open recommendations, and 
implementation of the remaining six is in progress. The status of each 
of these recommendations is summarized below. 

Table: Open Recommendations: 

[See PDF for Image] 

[A] Recommendation was also completed with respect to the fiscal year 
2005 expenditure plan 

[B] With respect to the fiscal year 2006 expenditure plan 

[C] Complete means that actions have been taken to fully implement the 
recommendation 

[D] In progress means that actions are under way to implement the 
recommendation 

[End of Table] 

Independent Cost Estimates: 

Open recommendation 1: Ensure that future expenditure plans are based 
on cost estimates that are reconciled with independent cost estimates. 

Status: Complete[Footnote 32]: 

The cost estimate in the fiscal year 2006 expenditure plan is based on 
the estimates in the current ACE program plan. Cl3P, with contractor 
support, compared the program plan cost estimate with the independent 
cost estimate. According to the analysis performed, the two estimates 
are consistent. The analysis was completed in October 2005, about 3 
months before the fiscal year 2006 expenditure plan was submitted to 
the Appropriations Committees. 

Effective Cost Estimating: 

Open recommendation 2: Develop and implement a rigorous and 
analytically verifiable cost estimating program that embodies the 
tenets of effective estimating as defined in SEI's institutional and 
project-specific estimating models.[Footnote 33]: 

Status: In progress: 

CBP has defined and documented processes for estimating program costs 
for the expenditure plan (including management reserve costs). It has 
also hired a contractor to develop cost estimates, including contract 
task order cost estimates, that are independent of CBP's estimates. 
Further, to ensure sufficiency and completeness of the estimates, CBP 
tasked a support contractor with evaluating both the independent and 
the CBP estimates against the criteria defined by SEI. 

According to the results of the support contractor's evaluation, the 
independent estimates satisfied all seven of the SEI criteria, and 
CBP's estimates satisfied six of the criteria and partially satisfied 
the remaining one. For the partially satisfied criterion, the 
evaluation found that the CBP estimate did not adequately consider past 
projects in its cost and schedule estimates. 

In addition, the support contractor found that CBP's estimate was the 
aggregation of three ACE component estimates, each of which was 
developed by the group responsible for a given component using 
different cost estimating methodologies. As a result, the support 
contractor recommended that CBP ensure that component estimates be 
based on the same methodology. 

Human Capital Strategy: 

Open recommendation 3: Immediately develop and implement a human 
capital management strategy that provides both near-and long-term 
solutions to program office human capital capacity limitations, and 
report quarterly to the Appropriations Committees on the progress of 
efforts to do so. 

Status: In progress: 

CBP does not have a documented human capital strategy covering its ACE 
program. As we have previously reported, such a strategy should provide 
for defining the positions needed (including core competencies) to 
perform core program functions; assessing and inventorying current 
workforce skills and abilities; assessing any gaps between needed and 
existing workforce levels and capabilities; and filling identified gaps 
via such means as new staff, training existing staff, and augmenting 
staff with contractor support. 

In lieu of a documented human capital strategy, CBP officials told us 
that they have taken various steps to bolster their ACE workforce as 
part of a less formal strategy. For example: 

* CBP expanded its contractor and government workforce dedicated to the 
ACE program by merging staff assigned to trade-related legacy systems 
with the ACE program staff-creating a Cargo Management Systems Program 
Office. According to the officials, this merger has enabled them to 
leverage the knowledge of staff who have been working with cargo 
systems for the past 10 to 20 years, and thus increased the level of 
expertise available to ACE. 

* CBP recently trained staff working on a major release on earned value 
management. 

* CBP began using subject matter experts from existing field operations 
advisory boards to help program officials define requirements for 
future releases. 

Further, CBP has reported quarterly to the appropriations committees on 
its human capital goals and objectives for ACE. 

Nevertheless, CBP officials acknowledged that they have not developed 
and followed a formal strategy that systematically compares competency- 
based staffing needs to on-board capabilities and defines and 
implements long-term and short-term plans for closing any shortfalls 
and associated strategies. Further, they have not reported to the 
appropriations committees on these shortfalls. They stated that they 
intend to develop a formal human capital strategy, and in doing so, 
will reflect the activities that they have already taken. 

Extending ACE Infrastructure: 

Open Recommendation 4: Have future ACE expenditure plans specifically 
address any proposals or plans, whether tentative or approved, for 
extending and using ACE infrastructure to support other homeland 
security applications, including any impact on ACE of such proposals 
and plans. 

Status: In progress: 

The expenditure plan describes steps under way and planned to leverage 
ACE's relationship with other homeland security applications. According 
to the plan, 

ACE and US-VISIT[Footnote 34] conform to the DHS enterprise 
architecture, which is to define standard shared services that the two 
systems can request. Such a services oriented architecture is intended 
to promote reuse and reduce overlap and duplication. According to CBP 
officials, they are currently exploring shared services areas. 

* ACE and US-VISIT have begun to use a common infrastructure to deploy 
and operate their systems. For example, in locations where ACE and US- 
VISIT have been fully deployed, such as at the port of Blaine, 
Washington, the two systems operate on the same network and the same 
workstations. 

However, the plan does not discuss the impact to ACE (e.g., cost and 
schedule) with regard to these efforts and plans. 

Besides what is described in the plan, ACE officials told us that they 
meet once a month with US-VISIT officials to share lessons learned on 
program management topics, such as risk management, change management, 
and configuration management. 

Measuring Success: 

Open recommendation 5: Define measures, and collect and use associated 
metrics, for determining whether prior and future program management 
improvements are successful. 

Status: In progress: 

CBP continues to make changes that are intended to improve overall 
program management. 

* CBP has merged aspects of its Office of Information Technology that 
managed trade-related legacy systems with its former ACE program 
office, thereby creating the Cargo Management Systems Program Office. 
This reorganization, according to CBP, is to result in (1) enhanced 
government oversight of ACE development, (2) better definition of 
requirements for future releases, and (3) faster and cheaper delivery 
of ACE capabilities. However, program officials told us that they have 
not established measures or targets for determining whether the 
reorganization is providing these benefits. 

CBP eliminated the dependencies between the screening and targeting 
releases and the cargo releases by leveraging its existing Automated 
Targeting System in delivering ACE screening and targeting 
capabilities. (This topic is discussed in further detail in the 
observations section.) It has also established measures for determining 
the impact of this change, including saving the program $10 million in 
life-cycle costs and allowing the screening and targeting releases to 
be fully deployed 1 year ahead of schedule. 

Accountability Framework: 

Open recommendation 6: Define and implement an ACE accountability 
framework that fulfills several conditions: 

a. Covers all program commitment areas, including key expected or 
estimated system (a) capabilities, use, and quality, (b) benefits and 
mission value; (c) costs, and (d) milestones and schedules. 

Status: In progress: 

CBP has prepared an initial version of an accountability framework that 
program officials said they intend to improve, but have nevertheless 
begun using. This framework is built around measuring progress against 
costs, milestones and schedules, and risks for select releases. It is 
also intended to permit measurement at different levels of aggregation, 
and for whatever incremental periods of time desired (e.g., monthly). 
However, as we discuss later, the benefit commitments have not been 
well defined and the performance targets are not always realistic. 

b. Ensures currency, relevance, and completeness of all program 
commitments made to the Congress in expenditure plans. 

Status: In progress: 

The fiscal year 2006 expenditure plan continues to include inaccurate, 
dated, and incomplete information and to omit other relevant 
information. 

The plan did not include information regarding CBP's decision to 
eliminate the dependencies among the screening and targeting releases 
and the cargo releases and to leverage its existing Automated Targeting 
System capabilities, nor did the plan reflect the $10 million cost 
reduction and the 1 year schedule acceleration that this change is 
intended to produce. 

The plan includes milestone completion dates for Releases 5, 6, and 7 
and Screening 1 that are not accurate. For example, the expenditure 
plan shows that the preliminary design review for Release 5, drops A1 
and A2, was scheduled to occur in August 2005; however, it did not 
occur until November 2005. Similarly, although the plan states that the 
critical design review for Release 6, drop M1, was scheduled to occur 
in November 2005, it is currently scheduled to take place August 2006. 

According to CBP officials, they did not update the plan because they 
wanted to provide it to the Appropriations Committees as soon as 
possible. They also stated that they use the congressional quarterly 
reports to provide the Appropriations Committees with more current, 
relevant, and complete information about ACE. However, these quarterly 
reports are generally submitted 3 to 4 months after the end of each 
quarter. 

c. Ensures reliable data relevant to measuring progress against 
commitments. 

Status: In progress: 

The data that CBP uses to measure progress against commitments are not 
consistently reliable. For example: 

* Data in the defect tracking system show that Release 4 is operating 
with long-standing defects and that new defects have not been closed. 
For example, as of January 18, 2006, the system showed that a number of 
defects were open: 

Number: 12: 
Severity: 2: 

Number: 4: 
Severity: 3: 

Number: 3: 
Severity: 4: 

Program officials told us that many of these defects are in fact 
resolved. However, the defect tracking system does not accurately 
reflect this status for two reasons: 

* staff were using multiple systems to track defects and these systems 
were not always reconciled; and: 

* newer staff were inexperienced in using the defect tracking system. 

According to program officials, they are manually reconciling the data 
between the multiple systems, and plan to implement a new system that 
will track all defects in one central system. 

d. Ensure future expenditure plans report progress against commitments 
contained in prior expenditure plans. 

Status: In progress: 

The fiscal year 2006 expenditure plan does not adequately describe 
progress against commitments made in previous plans. For example: 

* The plan provides a summary of the funding requested in each of the 
previous six expenditure plans. However, it does not provide 
information on whether these funding amounts were actually expended or 
obligated as planned. 

* The plan includes a new schedule for ACE releases, but it does not 
report progress relative to the schedule presented in the fiscal year 
2005 plan. 

* The plan does not explain the extent to which Release 5 design and 
development planned in the fiscal year 2005 plan was actually 
accomplished. 

e. Ensure criteria for exiting key readiness milestones adequately 
consider indicators of system maturity, such as severity of open 
defects. 

Status: In progress: 

According to CBP officials, ACE milestone exit criteria provide for 
considering the risk associated with having unresolved severe defects. 
Specifically, the criteria state that critical and severe defects must 
be resolved or there must be a plan in place to resolve them. Using 
these criteria, CBP passed several release milestones with severe 
defects still open: 

* Release 4 operational readiness review was passed with 9 severe 
defects open, 

* Screening 1 test readiness review was passed with 3 severe defects 
open, and: 

* Screening 1 production readiness review was passed with 2 severe 
defects open. 

In making these decisions, CBP officials told us that they considered 
the associated risk and concluded that the risk was acceptable. In 
particular, they stated that it was more important to get the releases 
in the hands of users and thereby gain user acceptance and receive user 
feedback sooner than it was to first resolve the defects. 

However, CBP officials were unable to provide us with any documentation 
on how the inherent risks of passing these milestones with open severe 
defects were assessed, and the ACE risk inventory does not include any 
risks associated with these decisions. 

f. Ensures clear and unambiguous delineation of the respective roles 
and responsibilities of the government and the prime contractor. 

Status: Complete. 

The current version of the ACE program plan describes general roles and 
responsibilities for the government and the prime contractor. More 
detailed roles and responsibilities of CBP, the prime contractor, and 
the support contractors have been documented in a roles and 
responsibilities matrix that assigns primary responsibility for each 
activity, such as testing, training, and maintenance. In addition, the 
task orders describe the specific responsibilities and expectations of 
the contractors. 

Implementation Reporting: 

Open recommendation 7: Report quarterly to the House and Senate 
Appropriations Committees on efforts to address open GAO 
recommendations. 

Status: In progress: 

CBP submitted reports to both Committees on its efforts to address open 
GAO recommendations for the quarters ending March 31, 2005; June 30, 
2005; and September 30, 2005. CBP also plans to submit a report for the 
quarter ending December 31, 2005. 

However, progress in addressing our recommendations was not always 
reported accurately. For example, CBP reported that it will review the 
expenditure plan throughout the approval process to ensure that it 
incorporates the most current program commitments. However, it did not. 
Additionally, in the September 2005 report, CBP stated that the fiscal 
year 2006 expenditure plan would have a section that describes progress 
made against program commitments made in all prior expenditure plans. 
However, the expenditure plan does not include this information. 

Objective 3: Development Observations: 

Steps have been taken to address past pattern of ACE release 
shortfalls, but new release management weaknesses are emerging. 

As we have observed in our previous reviews, CBP established a pattern 
of addressing quality problems with earlier releases by borrowing 
resources from future releases, which led to schedule delays and cost 
overruns. This pattern has continued with Release 4, which developed 
problems that caused delays with Screening 1. CBP has taken steps to 
mitigate this problem by eliminating the dependencies between the cargo 
releases and the screening and targeting releases. 

However, CBP's planned schedule for developing Releases 5, 6, and 7 
includes a significant level of concurrency, because of CBP's interest 
in delivering ACE functionality sooner. As we have reported in the 
past, such concurrency between release activities has led to cost 
overruns and schedule delays. Thus, the revised ACE plans and actions 
are potentially reintroducing the same problems that resulted in 
shortfalls in the past. 

Release 4 Pilot Problems: 

Release 4 pilot revealed performance problems that caused the pilot 
period to be extended and the pilot scope to be reduced. 

The Release 4 pilot was intended to ensure that the release met its 
requirements before it was deployed to all truck ports. Examples of 
pilot activities include training of CBP and trade personnel in how to 
use the release and conducting user acceptance testing. As planned, the 
pilot was to be conducted at two truck ports-Blaine, Washington, and 
Buffalo, New York-and the testing was to occur during a 10 week period. 
The pilot was to conclude with the operational readiness review on 
February 23, 2005. 

However, the pilot only occurred at Blaine, the pilot period covered 17 
weeks, and the operational readiness review did not occur until April 
14, 2005. The following are significant events that occurred during the 
pilot. 

* During the initial days of the pilot, Release 4 slowed truck 
processing. To address this, users identified needed system 
enhancements, primarily intended to reduce the number of steps required 
to process trucks. As a result, the pilot was suspended 11 days after 
it began so that the enhancements could be developed and implemented. 

The pilot resumed about 5 weeks after it was suspended. However, new 
problems were encountered, such as slow system response times and 
screen freezes. Additionally, the release was not properly displaying 
alerts for potential criminals or terrorists. As a result, the pilot 
was again suspended about 6 weeks after it was resumed. 

The pilot resumed about 3 weeks after the second suspension. On April 
14, 2005, about 7 weeks later than planned, Release 4 passed 
operational readiness review. 

Because of the ongoing problems with Release 4 in Blaine, CBP cancelled 
its plans to include Buffalo in the pilot. 

A comparison of the planned versus actual pilot schedules is summarized 
in the following figure. 

Figure: Planned versus Actual Time Frame for Release 4 Pilot Programs: 

[See PDF for image] 

[End of figure] 

Release 4 Milestone Reviews and Quality Problems: 

Release 4 operational readiness review was passed despite unresolved 
severe defects, and Release 4 is now being deployed. 

CBP's criteria for passing key milestones-such as the Release 4 
operational readiness review (ORR)-stipulate that all critical and 
severe defects must either be resolved or there must be plans in place 
to resolve the defect. As noted earlier, we have recommended that any 
decisions to pass key milestones adequately consider indicators of 
system maturity, such as open severe defects. 

At the time of the Release 4 operational readiness review, CBP reported 
that 9 severe defects remained open, and that it had plans in place to 
resolve each of these defects. Of these 9, one was subsequently 
cancelled, 4 were closed within approximately 6 weeks of ORR, 3 were 
closed several months after ORR, and 1 remains open about 10 months 
later. According to program officials, the remaining open defect has 
been lowered from severe to moderate status, but the change has yet to 
be reflected in the defect tracking system. 

CBP officials told us that they considered the risk associated with 
passing ORR with these 9 severe defects, and concluded that the risk 
was acceptable. In particular, they indicated that it was important to 
get Release 4 in the hands of users and thereby gain user acceptance 
and receive user feedback sooner. 

However, it is important to note that deploying a system with known 
operational problems, while likely to encourage user feedback, may 
actually limit user acceptance, particularly given the number of 
Release 4 enhancements needed. (The next section discusses these 
enhancements.) 

Further, CBP officials were unable to provide us with any documentation 
on how the inherent risks of passing this milestone with open severe 
defects were assessed, and the ACE risk inventory does not include any 
risks associated with this decision. 

Since ORR, Release 4 has been deployed to 38 truck ports on the 
northern and southern U.S. borders; by December 2006, CBP plans to 
deploy Release 4 to the remaining 60 truck ports. 

4 Definition Limitations and Enhancements: 

Release 4 quality problems and enhancement needs have led to changes in 
how ACE release requirements are defined. 

Inadequate requirements definition was a major reason for the problems 
and delays encountered during the Release 4 pilot in Blaine. 
Specifically, program officials told us that the requirements 
definition process did not fully identify the key functionality 
contained in the legacy system that ACE needed to provide. Also, the 
process did not adequately consider the capabilities that ACE would 
need to provide in an actual operational environment. For example, 
Release 4 requirements did not reflect the large volumes of 
transactions common in an operational setting, such as documenting 
notifications of potential security violations. 

According to program officials, the requirements definition process was 
insufficient in part because personnel involved in defining 
requirements did not have sufficient experience with the legacy systems 
that ACE was to replace and/or interface with. Moreover, they said that 
although Release 4 met the requirements that were defined for it in 
2001, since then CBP's mission and operations have changed, creating 
the need to introduce additional system requirements. 

To address these limitations, the number and scope of release 
enhancements (subreleases) have been larger than anticipated. To date, 
CBP has implemented two enhancement releases that add, for example, 
performance enhancements to transaction processing and improvements to 
the usability of reports. Although CBP has yet to determine the total 
number of enhancement subreleases that will be developed for Release 4, 
program officials stated that more are needed. 

To improve requirements definition for future releases, CBP has changed 
its requirements definition process. For instance, program officials 
said that they are: 

* leveraging existing field operations advisory boards to augment 
program staff defining the requirements for future releases, 

* using contractors to analyze legacy system functionality to ensure 
that ACE requirements reflect it, and: 

* regularly involving key representatives from the trade community to 
more fully define ACE requirements and help ensure that ACE meets 
users' needs. 

Impacts on Screening 1: 

Release 4 problems delayed Screening 1 and led to a revised strategy 
for delivering all screening and targeting releases. 

The Release 4 problems caused delays in developing and testing 
Screening 1 because resources that were to be used on Screening 1 were 
diverted to Release 4. For example: 

* The test environment's availability to support Screening 1 was 
delayed about 11 weeks because it was still supporting Release 4. 

* The staff targeted for Screening 1 development and test activities 
were being held on Release 4 longer than planned. 

As a result, the combined critical design review/test readiness review 
for Screening 1 was delayed by 60 days. As we have previously reported, 
this diversion of resources from future releases to address problems on 
prior releases has been a pattern on ACE for many years, owing largely 
to the concurrency in the development of releases and the releases' 
dependency on the same resources. 

To correct this pattern, as well as to leverage existing targeting 
functionality, CBP decided to take two steps: 

* to "decouple" all screening and targeting releases from ACE's cargo 
releases and: 

* to use its existing system, the Automated Targeting System (and 
associated resources), to deliver needed screening and targeting 
capabilities. 

In addition to addressing the pattern of delays caused by the releases 
competing for the same resources, CBP estimates that these changes will 
save the program $10 million and allow the screening and targeting 
releases to be fully deployed 1 year ahead of schedule. 

Screening 1 Milestone Reviews and Quality Problems 

Screening 1 key milestones were passed despite unresolved severe 
defects. 

As previously noted, CBP's criteria for passing key milestones, such as 
the test readiness review and production readiness review for Screening 
1, stipulate that all critical and severe defects must either be 
resolved or have work-off plans in place. Also, we have recommended 
that any decisions to pass key milestones adequately consider 
indicators of system maturity, such as open severe defects. 

A number of severe defects were open at the time of these milestones: 

* At the test readiness review on November 14, 2005, CBP reported that 
three severe defects were open. 

* At the production readiness review on December 22, 2005, CBP reported 
that two severe defects were open. 

According to CBP officials, these key milestones were passed because 
work-off plans were in place for resolving each severe defect. Thus, in 
their view the risk of proceeding did not outweigh the need to get 
Screening 1 to the users and thereby gain user acceptance and receive 
user feedback sooner. 

However, deploying a system with known operational problems, while 
likely to encourage user feedback, may actually limit user acceptance. 
Further, CBP officials were unable to provide us with any documentation 
on how the inherent risks of passing these milestones with open severe 
defects were assessed, and the ACE risk inventory does not include any 
associated risks. 

Screening 1 is scheduled for deployment beginning on March 23, 2006. 

Concurrent Development Risks: 

Past pattern of development problems with Releases 2, 3, and 4 makes 
new strategy of concurrently developing Releases 5, 6, and 7 risky. 

As we have previously reported,[Footnote 35] concurrent development of 
system components introduces risks that can adversely impact program 
cost and schedules. According to ACE contractors, these risks can 
include limited understanding of requirements before design and 
development activities begin, uncertainty regarding the timely 
availability of commercial hardware and software products, and 
increased near-term funding requirements. Other risks include 
contention for limited resources (such as key personnel, as well as 
development and testing equipment and facilities) and dependencies 
among releases not being met. 

Concurrency in developing early ACE releases caused schedule slips and 
cost overruns. As we previously reported, overlapping the development 
of Releases 2 and 3 caused delays in Release 3 and resulted in Releases 
1 through 4 costing more than planned. 

Factors contributing to the schedule slips and cost overruns include 
the following: 

* Additional resources were needed to eliminate Release 1 and 2 
defects. 

* Unavailable testing and development environments extended Release 3 
and 4 schedules. 

* Increased scope of Releases 3 and 4 to include Release 2 deferred 
requirements. 

Despite these experiences, CBP established a new ACE program plan in 
July 2005 that involves considerable overlap across the development 
schedules for Releases 5 and 6 and for Releases 6 and 7. According to 
CBP, the additional risk introduced by this concurrency is outweighed 
by the potential for delivering ACE functionality sooner. 

However, performance to date in meeting the highly concurrent 
milestones in the July 2005 program plan shows that delays are already 
occurring that are introducing even more schedule overlap and thus 
program risk. For example, both Releases 5 and 6 have experienced 
significant design-related delays, as shown by the table below. These 
delays have in turn increased the amount of development overlap across 
Releases 5, 6 and 7, as shown by the next slide, which compares the 
July 2005 and January 2006 schedules for these releases. 

Table: Delays in Meeting Release 5 and 6 Design-Related Milestones: 

[See PDF for Image] 

[End of table] 

Figure: Original versus Revised Schedules for Developing Releases 5, 6, 
and 7: 

[See PDF for Image] 

Source: GAO analysis of CBP data. 

[End of Figure] 

The risk associated with this concurrency in development schedules is 
exacerbated by several factors. 

* Releases/drops have extensive data and resource (e.g., testing 
environments) dependencies. For example, Release 6, drop M1, which is 
to provide electronic manifest capabilities to rail and sea ports, is 
dependent on the data that will be provided by Release 5, drop A1, 
which is to add trade account types and corresponding data. Further, 
CBP officials have said that Release 5, drop A2, and Release 6, drop 
M1, must be tested together in the same testing environment. Therefore, 
if either of the drops is delayed, the other will be delayed as well. 

* Just as delays on drops have already increased contention for 
resources, further delays could introduce additional contention. 

* Release 5, 6, and 7 include the vast majority of ACE's functionality 
(87 percent) and are to produce the more significant mission benefits. 

Earned Value Management Not Being Used: 

Earned value management is not being used to manage Screening 1 and 
Release 5. 

CBP has not used earned value management (EVM) to manage Release 5 and 
Screening 1. EVM is a management tool for measuring program progress by 
comparing, during a given period of time, the value of work 
accomplished with the amount of work expected to be accomplished; this 
comparison permits performance to be evaluated based on calculated 
variances from the planned cost and schedule. EVM is both an industry 
accepted practice and an OMB requirement. 

For Screening 1, CBP discontinued use of EVM in June 2005, when it made 
the decision to decouple the screening and targeting releases from the 
cargo releases. At that time, it decided to take advantage of the 
functionality of its legacy targeting system, Automated Targeting 
System (ATS), as well as the expertise of ATS staff. According to CBP 
officials, when ATS staff began working on Screening 1, they were 
unfamiliar with EVM and therefore did not use it. CBP officials stated 
that in lieu of EVM, they monitored the actual costs of work performed. 

In addition, CBP has not used EVM for Release 5, which has been under 
development for 22 months and for which $29.5 million has reportedly 
been expended. According to CBP officials, use of EVM was not possible 
because the revision of the Release 5 scope and strategy delayed 
definition of requirements and prevented cost and schedule baselines 
from being established. Therefore, Release 5 work had to be conducted 
under intermittent authorizations to proceed, which did not have 
measurable baselines. 

To respond to these EVM limitations, according to program officials, 
Screening 1 staff have now been trained on EVM. They also agreed that 
prior Release 5 work should have been managed by measurable baselines. 
They said that they plan to use EVM for future Release 5 work once 
fiscal year 2006 funds become available. In addition, they said that 
they intend to establish baselines for any work performed under 
authorizations to proceed, and appropriate performance metrics will be 
applied. 

Objective 3: Operation Observations: 

ACE's operational performance has been mixed, and mission impact is 
unclear. 

As described earlier, ACE Releases 1 to 4 are in operation. To date, 
these releases' operational performance has been uneven. For example, 
ACE has largely been meeting its goals for being available and 
responsive in processing virtually all daily transactions, and it has 
decreased truck processing times at some ports. However, ACE is not 
being used by as many CBP and trade personnel as was expected, and 
truck processing times at other ports have increased. Moreover, overall 
user satisfaction has been low. 

In addition, ACE goals, expected mission benefits, and performance 
measures are not fully defined and adequately aligned. Where 
performance measures have been defined, the associated targets are not 
always realistic. As a result, it is unclear whether ACE has realized 
or will realize the mission value that it was intended to bring to 
CBP's and other agencies' trade-and border security-related operations. 

Availability Targets Largely Met: 

Availability and responsiveness targets are largely being met. 

CBP has defined ACE availability in terms of the percentage of 
transactions that are to be executed successfully each day. According 
to a service level agreement between the ACE Support Team and CBP, 99.9 
percent of all ACE transactions on any given day are to be successful. 
The ACE Support Team reports that ACE met this requirement on all but 
22 days between January 1, 2005, and January 27, 2006. 

For each of the 22 days that the system did not meet the agreement, the 
ACE Support Team identified and corrected the root cause. For example, 
outages were caused by: 

* a server accidentally being shut down by data center personnel, 

* a software error that disabled a transaction function, and: 

* a network switch that malfunctioned. 

To address these causes, the ACE Support Team instituted new data 
center procedures, deleted ACE code that caused the transaction error, 
and established methods for identifying network problems sooner. 

Another service level agreement between the ACE Support Team and CBP 
requires the system to execute all transactions within 6 seconds 95 
percent of the time. The ACE Support Team reports that ACE met this 
requirement on all but 16 days between January 1, 2005, and January 27, 
2006, and no incidents have been reported since August 5, 2005. 

For each of the 16 days that the system did not meet the agreement, the 
ACE Support Team identified the root cause. For instance: 

* eight incidents were due to a problem with a program that measures 
network performance, which has since been addressed through changes to 
operational procedures, and: 

* one incident was caused by an improperly configured server that has 
since been reconfigured. 

Truck Processing Times Vary: 

Processing times for trucks crossing the border at key ports vary. 

CBP has identified more efficient truck processing at the ports as an 
expected ACE benefit. To ascertain whether the benefit is being 
realized, it also defined truck processing time as the performance 
measure to be used, and it set a performance target of reducing 
processing times at the ports by 6 percent in fiscal year 2005. 

However, at the two ports for which CBP established baselines to 
measure truck processing against performance targets in fiscal year 
2005, CBP reports that truck processing times have actually increased. 
For example: 

* At Pembina, North Dakota, by the end of fiscal year 2005, processing 
time had increased by about 14 percent. CBP officials attributed this 
increase to a lack of user proficiency and confidence with ACE. 

* At Nogales, Arizona, by the end of fiscal year 2005, processing time 
had increased by about 70 percent. CBP officials attributed this 
increase to ACE-related changes to booth operations, such as the new 
requirement to enter empty trucks in the system. 

According to CBP officials, widespread truck processing efficiency 
gains will not be realized until a majority of truck manifests are 
submitted electronically, which is not expected to occur until use of 
electronic manifests becomes a requirement in early fall 2006. 
Nevertheless, since fiscal year 2005, CBP reports that some ports have 
experienced processing improvements. For example: 

* At the Ambassador Bridge in Detroit, Michigan, processing time 
decreased by approximately 27 percent between October 3 and December 
15, 2005. CBP officials attributed this decrease to improvements in the 
quality of training and a new user interface toolbar feature. 

Help Desk Improvements: 

Long-standing help desk limitations are being addressed. 

According to an independent technology research firm,[Footnote 36] 
effective help desk services include providing users timely updates on 
the status of their requests; conducting user satisfaction surveys; and 
establishing, collecting, and reporting operational metrics, such as 
the number of requests resolved during the initial call to the help 
desk. 

The current ACE help desk does not perform all the practices associated 
with an effective help desk. To its credit, the existing help desk 
does, for example, monitor and measure such activities as the number of 
requests that are resolved during the initial call to the help desk, 
the number of calls that are not received because the user hangs up, 
and the average time it takes to answer a help desk call. However, it 
does not: 

* collect data and inform users on the status of their help desk 
requests or: 

* survey users on their satisfaction with help desk services. 

CBP has long recognized the limitations of the ACE help desk. In 
January 2003, it decided to implement a new system that would provide 
greater help desk capabilities. However, the first phase of the new 
system was not implemented until about 3 years later (February 2006). 
According to CBP officials, the delay was due to competing demands for 
limited resources. 

* The first phase is to enable users to check the status of their 
existing requests and to resolve certain problems without calling the 
help desk. In addition, the new system is to automatically e-mail users 
with a notification of resolution, which is to provide a link to a 
customer satisfaction survey. 

* The second phase is to include more advanced functionality such as 
allowing users to open and update their own help requests. CBP is 
working to develop a schedule for the second phase. 

In addition to the new help desk service, CBP has established an ACE 
Portal Support Center to provide additional support to CBP and the 
trade community on nontechnical issues: for example, submitting and 
processing electronic truck manifests, setting up and using accounts, 
generating reports, and resetting passwords. 

Usage Lower Than Expected: 

Usage by CBP and the trade is lower than expected. 

CBP and trade usage of deployed ACE releases has been lower than 
expected. Specifically: 

* The goal for fiscal year 2005 was for 11 percent of CBP employees to 
use ACE. However, as of the end of the fiscal year, 8 percent were 
using it. According to CBP officials, they are rethinking this goal to 
recognize that not all CBP employees have a need to use ACE. 

* The goal for fiscal year 2005 was for 20 percent of all monthly 
payments of fees and duties to be collected using ACE. However, as of 
the end of fiscal year 2005, ACE collected about 11 percent of the 
total fees and duties. To increase ACE use in paying fees and duties, 
CBP has: 

- eliminated its requirement for importers paying their way to be 
members of the Customs-Trade Partnership against Terrorism (this 
organization is focused on developing, enhancing, and maintaining 
effective security practices throughout the trade industry) and: 

- eliminated some of the paperwork and other requirements that have 
since been deemed unnecessary. 

The following graph depicts the expected and actual percentage of ACE- 
collected fees and duties for fiscal year 2005. 

Figure: Fiscal Year 2005 Expected versus Actual Percentage of Duties 
and Fees Collected Using ACE: 

[See PDF for Image] 

Source: GAO analysis of ACE data. 

[End of Figure] 

The goal for fiscal year 2005 was for 5 percent of all 
manifests[Footnote 37] to be filed electronically using ACE. However, 
the actual percentage filed in this manner was less than 1 percent. CBP 
officials attributed this low percentage to the trade community's 
reluctance to invest resources to change, and the fact that electronic 
manifests must be submitted in advance of truck's arrival. They also 
said that even though the goal for fiscal year 2006 is 20 percent, 
significant increase in electronic manifests is unlikely to occur until 
it is mandatory for the trade to use this method, which is not expected 
to occur until early fall 2006. 

The following table shows CBP's progress towards reaching its fiscal 
year 2005 and 2006 electronic manifest goals. 

Table: CBP's Limited Progress Towards Reaching Fiscal Year 2005 and 
2006. 

[See PDF for Image] 

Source: GAO analysis of CBP data.  

[End of table] 

User Satisfaction Low: 

User satisfaction was reported as low. 

In February and March of 2005, a CBP user satisfaction survey was 
conducted that covered, among other things, CBP IT systems, including 
ACE. Of the 187 respondents, 39 percent indicated that they are 
dissatisfied or very dissatisfied with ACE. The reason most often given 
for this response was that the system was not easy to use. For example, 
according to the survey responses, ACE required officers to navigate 
through several screens in order to process each truck. 

Other ACE user concerns identified include the following: 

* Passwords did not allow users to access the system. 

* Response times were slow. 

* Initial training of users was not adequate. 

In response to the ACE survey results, CBP officials are developing a 
prioritized list of recommendations for improving user satisfaction, as 
well as a strategy for surveying CBP and trade users at several ports 
at which Release 4 has been deployed. The goal is to gain further 
insights into users' satisfaction and to identify potential areas for 
improvement. According to CBP, they plan to start surveying the ports 
in the spring of 2006. 

Performance Targets Not Realistic: 

Performance targets are not always realistic. 

Meaningful measurement of operational performance requires, among other 
things, realistic performance targets against which to gauge results. 
However, defined ACE performance targets are not always realistic. For 
example: 

* The performance target in fiscal year 2005 for ACE usage was that 11 
percent of all CBP employees would use ACE. However, many CBP employees 
will never need to use the system. Thus, the defined performance target 
does not reflect this. CBP officials stated that they plan to redefine 
this measure to focus on CBP employees who have a reason to use ACE. 

* The performance target for fiscal year 2005 for truck processing was 
a 6 percent decrease in truck processing times at each port. However, 
each port varies in terms of truck volumes, operational hours, cargo 
and antiterrorism activities, and port policies. A single performance 
goal for every port does not recognize these differences. 

* According to CBP officials, the fiscal year 2005 and 2006 targets for 
processing electronic manifests (5 and 20 percent, respectively) were 
arbitrarily set. They stated that until electronic filing of manifests 
is required which is expected to take place in early fall 2006-it is 
unlikely that there will be any significant increase in the rate of 
electronic submissions. 

Benefits and Measures Not Aligned: 

Goals, expected mission benefits, and performance measures are not 
fully defined and adequately aligned. 

The Clinger-Cohen Act and associated OMB guidance[Footnote 38] require 
the use of effective IT management practices, including measuring the 
contributions of IT investments to achieving agency mission outcomes. 
To this end, OMB requires[Footnote 39] that agencies should, among 
other things, 

* establish program performance goals and expected benefits; 

* develop outcome-based performance measures to assess actual program 
performance (i.e., achievements) against expected benefits; and: 

* ensure that goals, expected benefits, and performance measures are 
properly aligned. 

CBP has defined ACE goals, expected benefits, desired business results, 
and performance measures. The six ACE goals cited earlier are 
summarized below. 

* Support border security through enhanced analysis and interagency 
information sharing. 

* Provide information to enable decisions before a shipment reaches the 
border as to what to target and what to expedite. 

* Enable efficient collection, processing, and analysis of commercial 
import and export data. 

* Streamline time-consuming, labor-intensive tasks for CBP and the 
trade. 

* Enable national account management and informed, rule-based screening 
and targeting. 

* Comply with legislative mandates to improve efficiency/effectiveness 
and provide better customer service. 

CBP has also identified 23 ACE benefits, all of which relate to gains 
in efficiency. Examples of these benefits are as follows: 

* importer account profile efficiency gains, 

* forms processing efficiency gains, 

* driver verification efficiency gains, and: 

* cargo release efficiency gains. 

CBP has also identified 11 ACE desired business results. Examples are 
as follows: 

* improved accuracy and timeliness of information to support threat 
assessment decisions, 

* detected unfair/illegal trade activities, 

* increased compliance rates, and: 

* improved responsiveness and adaptability to policy, statutory, and 
regulatory changes and trade volume increases. 

Page 130 GAO-06-580 Customs Modernization: 

In addition, CBP has defined 17 performance measures. Examples are as 
follows: 

* percentage of internal CBP population using ACE functionality to 
manage trade information, 

* percentage of total duties and fees paid through periodic monthly 
statements, and: 

* percentage reduction of truck processing time. 

However, the relationships among these program goals, benefits, 
business results, and performance measures have not been clearly 
established and are not always apparent. Further, not every goal has 
defined benefits, every benefit is defined only in terms of efficiency 
gains, not every benefit has an associated business result, and not 
every benefit and business result have associated performance measures. 
For example: 

* The two ACE goals focused on homeland security do not align with any 
stated ACE benefit. 

* The ACE benefit of greater efficiency in processing forms does not 
clearly align to any performance measures. 

* The desired business result related to improved threat assessment 
decisions does not align to any ACE benefit or performance measure. 

* There are 23 ACE benefits but only 17 measures for gauging 
performance relative to these benefits. 

The following table illustrates the lack of clearly defined 
relationships among ACE benefits, desired business results, and 
performance measures for Releases 2, 3, and 4. 

Table: Operation Observations. 

[See PDF for Image] 

[End of table] 

Conclusions: 

The legislative conditions that the Congress placed on the use of 
fiscal year 2006 ACE appropriated funds have either been partially or 
fully satisfied by the latest expenditure plan and related program 
documentation and activities. Nevertheless, more can be done to better 
address several aspects of these conditions, such as having an approved 
privacy impact assessment, measuring ACE performance and results, 
ensuring architectural alignment, and employing effective IV&V 
practices. Given that the legislative conditions are collectively 
intended to promote accountability and increase the chances of program 
success, it is important that each receives DHS's full attention. 

Also important to ACE's success is the swift and complete 
implementation of the recommendations that we have previously made to 
complement the legislative conditions and improve program management, 
performance, and accountability. In this regard, some recommendations 
have been addressed, while progress has been slow on others, such as: 

* accurately reporting to the Appropriations Committees on CBP's 
progress in implementing our prior recommendations; 

* developing and implementing a strategic approach to meeting the 
program's human capital needs; 

* using criteria for exiting key milestones that adequately consider 
indicators of system maturity, such as severity of open defects and the 
associated risks; and: 

* developing and implementing a performance and accountability 
framework for ensuring that promised capabilities and benefits are 
delivered on time and within budget. 

To its credit, CBP has taken several steps to stem the pattern of cost, 
schedule, and performance shortfalls that it experienced on early ACE 
releases. However, future releases are unlikely to realize the impact 
of these steps because revised ACE plans and actions are reintroducing 
the same pattern that led to early release shortfalls. This pattern 
includes not formally and transparently considering and proactively 
addressing the risks associated with passing key release milestones 
with known severe defects, building considerable overlap and 
concurrency in the development schedules of releases that will contend 
for the same resources, and not performing EVM on all releases. If this 
pattern continues, the prospects for a successful program will be 
diminished. 

Although availability and responsiveness targets are largely being met 
and long-standing help desk limitations are being addressed, the 
prospects for a successful program nevertheless remain unclear. The 
true measure of ACE's success is arguably the mission value that it 
brings to CBP's and other agencies' trade-and border security-related 
operations and users. Such value depends both on the operational 
performance of ACE and on CBP's ability to demonstrate that this 
performance is achieving program goals, delivering expected benefits, 
and producing desired business results. At this juncture, however, 
neither the system's performance nor its value is clear because of 
several factors: the operational performance of deployed releases has 
been mixed; users' satisfaction has been low; the relationships among 
goals, benefits, and desired business outcomes are not evident; and the 
range of measures needed to create a complete and realistic picture of 
ACE's performance is missing. 

In summary, a number of ACE activities have been and are being done 
well; these have contributed to the program's progress to date and will 
go a long way in determining the program's ultimate success. However, 
CBP needs to effectively address long-standing ACE management 
challenges along with emerging problems. Until it does so, ACE will 
remain a risky program. 

Recommendations: 

To assist CBP in managing ACE and increasing the chances that it will 
deliver required capabilities on time and within budget and demonstrate 
promised mission benefits and results, we recommend that the DHS 
Secretary direct the appropriate departmental officials to fully 
address those legislative conditions associated with having an approved 
privacy impact assessment and ensuring architectural alignment. 

We also recommend that the DHS Secretary, through CBP's Acting 
Commissioner, direct the Assistant Commissioner for Information and 
Technology to: 

* fully address those legislative conditions associated with measuring 
ACE performance and results and employing effective IV&V practices; 

* accurately report to the Appropriations Committees on CBP's progress 
in implementing our prior recommendations; 

* include in the June 30, 2006, quarterly update report to the 
Appropriations Committees a strategy for managing ACE human capital 
needs and the ACE framework for managing performance and ensuring 
accountability; 

* document key milestone decisions in a way that reflects the risks 
associated with proceeding with unresolved severe defects and provides 
for mitigating these risks; 

* minimize the degree of overlap and concurrency across ongoing and 
future ACE releases, and capture and mitigate the associated risks of 
any residual concurrency; 

* use EVM in the development of all existing and future releases; 

* develop the range of realistic ACE performance measures and targets 
needed to support an outcome-based, results-oriented accountability 
framework, including user satisfaction with ACE; and: 

* explicitly align ACE program goals, benefits, desired business 
outcomes, and performance measures. 

Agency Comments: 

In their oral comments on a draft of this briefing, DHS and CBP 
officials, including the Executive Director of Cargo Management 
Systems, CBP, generally agreed with our findings, conclusions, and 
recommendations and stated that the presentation was fair and balanced. 
They also provided clarifying information that we incorporated as 
appropriate in this briefing. 

Attachment 1: Scope and Methodology: 

Scope and Methodology: 

To accomplish our objectives, we analyzed the ACE fiscal year 2006 
expenditure plan and supporting documentation, comparing them to 
relevant federal requirements and guidance, applicable best practices, 
and our prior recommendations. We also interviewed DHS and CBP 
officials, ACE program contractors, and officials at the port of 
Blaine, Washington. In particular, we reviewed: 

* DHS and CBP investment management practices, using OMB A-11, part 7; 

* DHS and CBP certification activities for ensuring ACE compliance with 
the DHS enterprise architecture; 

* DHS and CBP acquisition management efforts, using SEI's SA-CMM; 

* CBP cost estimating program and cost estimates, using SEI's 
institutional and project-specific estimating guidelines; 

* independent verification and validation (IV&V) activities using the 
Institute of Electrical and Electronics Engineers Standard for Software 
Verification and Validation; 

* CBP actions to coordinate ACE with US-VISIT program documentation; 

* CBP's reorganization documentation, including the new organizational 
charts and roles and responsibilities matrix; 

* ACE's accountability framework; 

* ACE's performance using service level agreements; 

* ACE's quality, using the ACE Support Team defect data and testing 
results for Release 4 and Screening 1; 

* cost and schedule data and program commitments from program 
management documentation; 

* CBP's progress toward increasing usage of ACE, against established 
targets; 

* level of user satisfaction, against survey scores, and: 

* reliability of performance measures, by mapping the measures to 
benefits. 

For DHS-, CBP-, and contractor-provided data that our reporting 
commitments did not permit us to substantiate, we have made appropriate 
attribution indicating the data's source. 

We conducted our work at CBP headquarters and contractor facilities in 
the Washington, D.C., metropolitan area and at the port of Blaine, 
Washington, from July 2005 through March 2006, in accordance with 
generally accepted government auditing standards. 

[End of Slide Presentation] 

[End of section] 

Appendix II: Comments from the Department of Homeland Security: 

Homeland Security: 

May 9, 2006: 

Mr. Randolph C. Hite: 
Director: 
Information Technology Architecture and System Issues: 
U.S. Government Accountability Office: 
441 G Street, NW: 
Washington, DC 20548: 

Dear Mr. Hite: 

Thank you for the opportunity to review and comment on the Government 
Accountability Office's (GAO's) draft report GAO-06-580 entitled 
INFORMATION TECHNOLOGY. Customs Has Made Progress on Automated 
Commercial Environment System, but it Faces Long-Standing Management 
Challenges and New Risks. 

The U.S. Customs and Border Protection (CBP) agrees with the status of 
open recommendations and new recommendations for CBP executive action. 
The report indicates that an earlier recommendation regarding the roles 
and responsibilities of the government and prime contractor has been 
satisfied. The report also indicates that a previous recommendation on 
reconciling Modernization expenditure plans with independent cost 
estimates has been successfully satisfied for the second consecutive 
year. CBP will continue using independent cost estimates to develop 
future expenditure plans. 

CBP is committed to fully addressing the remaining open recommendations 
regarding: (1) cost estimating; (2) human capital management; (3) use 
of the Automated Commercial Environment (ACE) for other Department of 
Homeland Security (DHS) applications; (4) program management metrics 
and measurements; and (5) implementation of an accountability 
framework, including (a) coverage of all program commitment areas, (b) 
currency and completeness of commitments made in expenditure plans, (c) 
reliable data, (d) reporting on progress against commitments in future 
expenditure plans, (e) establishing milestone exit criteria that 
account for system maturity; and (6) quarterly reporting to Congress. 
CBP notes that recommendations 1 and 3, aspects of recommendation 5, 
and recommendation 6 are related to normal programmatic processes, and 
as such, will likely remain open for the life of the program. CBP would 
suggest that these recommendations not continue to be held as open 
findings, but that they be continuously monitored through status 
updates in quarterly reports to Congress on ACE. 

CBP continues to follow established plans for developing and deploying 
ACE capabilities that are enhancing cargo security while also 
facilitating the flow of legitimate trade across our borders. Solid 
program management and reporting systems have enabled the ACE program 
to operate within 10 percent of the program baseline and within 
approved program funding. CBP acknowledges the nine new recommendations 
by the GAO in the draft report and intends to address them as part of 
continuing efforts to enhance processes for balancing quality, cost, 
and schedule, and maintain visibility of, and accountability for, 
program commitments. The following is a summary of the agency's 
progress toward, and plans for addressing, each of the nine new 
recommendations detailed in the draft report. 

Recommendation 1: Fully address those legislative conditions associated 
with having an approved privacy impact assessment and ensuring 
architectural alignment. 

Response: CBP is committed to fully satisfying all legislative 
conditions for the approval of Modernization expenditure plans. CBP is 
taking steps to address the two subordinate elements of the 
recommendation, as follows: 

* The ACE Privacy Impact Assessment (PIA) has been updated based on 
input from the DHS Privacy Office and the Federal Motor Carrier Safety 
Administration (FMCSA). CBP provided a revised draft of the PIA to the 
DHS Privacy Office on May 1, 2006 and will continue to work with that 
staff to bring the matter to closure. 

* CBP will work with DHS to ensure that an appropriate methodology is 
used to evaluate the compliance of ACE with the DHS Enterprise 
Architecture (EA) as part of the FY 2007 Modernization Expenditure Plan 
development process. 

Recommendation 2: Fully address those legislative conditions associated 
with measuring ACE performance and results and employing effective 
Independent Verification and Validation (IV&V) practices. 

Response: Consistent with its commitment to fully satisfy all 
legislative conditions for the approval of Modernization expenditure 
plans, CBP is addressing the two subordinate elements of the 
recommendation as follows: 

* CBP will align and fully define program goals, benefits, business 
results, and performance measures. CBP's approach for this effort, 
which will be completed by July 1, 2006, and certified as complete by 
the CBP Commissioner, is outlined below in the responses to 
recommendations 8 and 9. 

* Beginning October 2005, CBP took steps to align Modernization program 
IV&V efforts more closely with the Institute of Electrical and 
Electronic Engineers (IEEE) 1012-2004 Standard for Software 
Verification and Validation. To further align with this standard, CBP 
will complete and implement Version 2.0 of the IV&V Implementation and 
Management Plan by June 1, 2006. Implementation of version 2.0 of the 
subject plan will ensure IV&V efforts are aligned with the IEEE 1012- 
2004 standard and address satisfaction of quality: 

standards for all ACE products, as well as user needs, as defined 
through requirements, use cases, and design documents. 

Recommendation 3: Accurately report to the Appropriations Committees on 
CBP's progress in implementing our prior recommendations. 

Response: CBP will continue to report on progress toward addressing 
open GAO recommendations through quarterly status updates to the 
Appropriations and Authorization Committees. CBP intends to meet with 
GAO representatives to ensure that quarterly status reports accurately 
reflect a common understanding of the intent of each new and previous 
recommendation, as well as critical success factors for fully 
satisfying each recommendation. CBP will provide ACE third and fourth 
quarter reports, including the status of prior recommendations, to the 
Appropriations and Authorization Committees by September 1, 2006, and 
December 1, 2006, respectively. 

Recommendation 4: Include in the June 30, 2006, quarterly update report 
to the Appropriations Committees a strategy for managing ACE human 
capital needs and the ACE framework for managing performance and 
ensuring accountability. 

Response: Based on the Office of Information Technology (OIT) Strategic 
Human Capital Management Plan, which is now under development, the ACE 
program office will develop a complementary plan that maps OIT human 
capital strategies to the ACE program, and as such, provides a strategy 
for managing ACE human capital needs. By July 1, 2006, OIT will achieve 
certification by the Acting CBP Commissioner that the OIT Strategic 
Human Capital Management Plan is complete and mapped to the ACE 
program. 

The December 31, 2005, quarterly report on ACE, as well as the March 
31, 2006, quarterly report, now under review, includes a copy of the 
accountability framework that is being used as the basis for tracking 
progress against program commitments. CBP will include, as part of the 
third quarter report on ACE, a copy of the aforementioned 
accountability framework and an outline of the key elements of the plan 
for managing ACE human capital needs. CBP representatives intend to 
meet with their GAO counterparts to ensure that the agency fully 
understands the intent of the foregoing recommendation and the actions 
that will be required to satisfy this intent. CBP plans to provide the 
ACE third quarter report, including the strategy for managing ACE human 
capital needs and the ACE framework for managing performance and 
accountability, to the Appropriations and Authorization Committees by 
September 1, 2006. 

Recommendation 5: Document key milestone decisions in a way that 
reflect the risks associated with proceeding with unresolved severe 
defects and provide for mitigating these risks. 

Response: The ACE program office has strengthened the Software 
Development Lifecycle (SDLC) gate review process by ensuring that 
specific risk assessment and acceptance at each review is a requirement 
for proceeding to the next stage of the SDLC. In addition, the ACE Risk 
and Issue: 

Management Process has been updated to account for the need to identify 
risks associated with proceeding beyond SDLC gate reviews. Under the 
updated process, the designated ACE risk manager is working with 
project teams to identify appropriate risks, mitigation plans, and 
impact assessments prior to gate reviews so that gate review decisions 
will be based on documentation that includes risks and their associated 
impact. Documented risks are entered into ACE program office risk 
management software to ensure that CBP has visibility of these risks 
and can take action to mitigate them as appropriate. In addition, CBP 
is working with the DHS Chief Information Officer to certify that each 
release is ready to proceed beyond the Critical Design Review and 
Production Readiness Review. The ACE program office will implement the 
strengthened SDLC gate review process at the next scheduled SDLC gate 
review. 

Recommendation 6: Minimize the degree of overlap and concurrency across 
ongoing and future ACE releases, and capture and mitigate the 
associated risks of any residual concurrency. 

Response: As noted in the draft GAO report, CBP has taken steps to 
"decouple" Screening and Targeting (S&T) releases from ACE secure cargo 
management releases, and will augment the Automated Targeting System 
with new S&T capabilities. This approach will reduce system development 
interdependencies between ACE S&T and secure cargo management 
capabilities. CBP has also taken specific action in three areas to 
reduce potential contention for common resources across ACE releases. 
First, CBP has conducted extensive planning to ensure that development 
milestones eliminate contention for computer hardware environments 
needed for development, integration, testing, and training activities. 
Second, CBP is centrally managing underlying ACE shared software 
services to maximize efficient use of resources, enhance responsiveness 
to workload peaks, and provide consistent technical management 
approaches across releases. Third, CBP has divided ACE releases into 
smaller groups of capabilities or "drops," which, in turn, will be 
packaged into "deliveries" of ACE that can include capabilities from 
more than one release. Managing ACE deliveries allows hardware 
environments, system testing, integration with legacy systems, 
training, and deployment activities, as well as required staffing, to 
be managed across releases, thereby improving planning and reducing 
resource contention. 

CBP has in place a solid program for managing remaining concurrent 
project and program activities and associated risks. Key elements of 
this program management foundation include the following: 

* Requirements Traceability Matrix (RTM): The RTM provides a complete 
view of all ACE release and task order requirements, as well as the 
interrelationships between these requirements, thus minimizing the 
potential for duplicative efforts. 

* Integrated Master Schedule (IMS) for ACE secure cargo management 
capabilities: The IMS provides (1) the visibility of all project 
release/delivery schedules and project interdependencies; (2) a 
centralized repository for information on all gate reviews, milestones, 
and project schedules; (3) comprehensive schedule information on the 
use and availability of computer hardware "environments" that helps 
reduce delays by ensuring environments are available when needed for 
development efforts; (4) a calculated critical path for the entire 
program that shows which activities are critical to staying on 
schedule; (5) a view of all measurable project activity at the project 
work package level; and (6) a view of what deliverables and/or 
milestones are on track for timely completion or are behind schedule. 
When status updates to the IMS place key program milestones at risk, 
the IMS automatically notifies the ACE program office scheduling team 
via e-mail. This feature allows program office staff members to 
actively monitor program milestones and computer hardware environment 
dependencies. Collectively, IMS capabilities provide a valuable tool 
for evaluating the progress of the program and determining where 
corrective actions may be required. 

* Bi-weekly integration meetings: OIT directors and senior managers of 
the prime contractor meet bi-weekly to discuss program issues and 
concerns. 

* Monthly Program Management Reviews (PMRs): OIT conducts monthly PMRs 
to review the ACE Accountability Framework report, which details the 
status of all ACE task orders and releases relative to program 
commitments. 

* Active Risk Manager (ARM): ARM, a leading software tool used across 
industry and government, provides visibility of program risks and 
issues and attendant mitigation plans. OIT uses ARM to track and manage 
all identified program risks for the ACE program. The process for 
identifying risks is reviewed and revised, as appropriate, to further 
strengthen the risk identification process and ensure that it will 
successfully lead to the identification of risks associated with 
concurrent activities across the program. 

* Risk Issue Forum (RIF): Monthly RIF meetings are conducted to 
evaluate the status and impacts of risks and issues; take steps to 
mitigate risks and issues, as appropriate; and determine whether new 
risks and issues should be tracked across the program. 

* Cost and schedule risk analysis: The ACE program office identifies. 
potential program risks as part of the cost and schedule analysis that 
is completed for each ACE Program Plan and Modernization Expenditure 
Plan update. A sensitivity analysis is conducted to quantify these 
risks and ensure that sufficient management reserve will be available 
should the risk materialize. The output of cost and schedule analysis 
are risk-adjusted cost and schedule estimates that are used to ensure 
that sufficient time and funding are available within the program 
baseline to allow for successful development of ACE. Each risk 
identified as part of the cost and schedule risk analysis is entered 
into the aforementioned ARM tool and actively managed to diminish the 
probability that a risk will materialize. 

* Earned Value Management (EVM): As discussed below in the response to 
recommendation 7, EVM is a key tool for managing the development of ACE 
releases. EVM provides early warning signals of potential problems as 
well as the basis for making course corrections across the program. 

Recommendation 7: Use EVM in the development of all existing and future 
releases. 

Response CBP is currently using EVM for the development of e-Manifest: 
Trucks (Release 4) production baseline enhancements and Targeting 
Foundation (S2). CBP plans to use EVM in the development of all future 
releases, and to effect the implementation of EVM within 45 days after 
task order award to the prime contractor. CBP intends to implement use 
of EVM for e-Manifest: All Modes and Cargo Security (Release 6), e- 
Manifest: Rail and Sea (M1), by May 31, 2006. The agency projects that 
EVM will be implemented for Entry Summary, Accounts, and Revenue (ESAR) 
(Release 5) Master Data and Enhanced Accounts (Al) and Entry Summary 
and Revenue (A2) by June 30, 2006. Contract negotiations for Advanced 
Targeting (S3) began in April 2006. CBP projects that EVM will be 
implemented for ESAR Master Data and Enhanced Accounts (A 1) and Entry 
Summary and Revenue (A2) by June 30, 2006. 

Recommendation 8: Develop the range of realistic ACE performance 
measures and targets needed to support an outcome-based, results- 
oriented accountability framework, including user satisfaction with 
ACE. 

Response: CBP is committed to aligning and fully defining program 
goals, benefits, business results, and performance measures. Toward 
this end, CBP will update the performance measurement framework for 
ACE, which is the basis for the overall ACE performance measurement 
program. The updated framework will demonstrate the relationship 
between CBP objectives and Desired Business Results (DBRs). Through 
validation of DBRs and supporting performance measures, CBP will 
institute a more realistic, appropriate, and comprehensive performance 
measurement framework that includes assessments of user satisfaction, 
CBP operational efficiency, and trade facilitation benefits. Based on 
these performance measures, CBP will institutionalize data collection 
on a monthly basis and report results against performance measures 
through management reports such as the ACE Accountability Framework. 
CBP expects to develop ACE performance measures by July 1, 2006. 

Recommendation 9: Explicitly align ACE program goals, benefits, and 
desired business outcomes, and performance measures. 

Response: As discussed above in response to recommendation 8, CBP will 
align ACE program goals, benefits, DBRs, and performance measures by 
(1) adapting the Federal Enterprise Architecture and CBP Performance 
Reference Model framework for ACE performance measures, including DBRs; 
and (2) revising specific performance objectives to ensure they are 
realistic and aligned with DBRs. The foregoing planned efforts are 
expected to further clarify the mission impact of ACE and provide a 
solid foundation for evaluating progress against commitments. CBP 
expects to align ACE program goals, benefits, and desired business 
outcomes, and performance measures by July 1, 2006. 

Mindful of the imperative to detect terrorist efforts to exploit our 
Nation's supply chain, while also facilitating legitimate trade, CBP is 
focused on ensuring that ACE will meet high standards for usability and 
operational effectiveness within cost and on schedule. CBP looks 
forward to working with GAO to address previous and new GAO 
recommendations, and will continue efforts to make transparent the 
agency's progress toward satisfying these recommendations. 

Thank you again for the opportunity to comment on this draft report and 
we look forward to working with you on future homeland security issues. 

Sincerely, 

Signed by: 

Steven J. Pecinovsky: 
Director: 
Departmental GAO/OIG Liaison Office: 

[End of section] 

Appendix III: Contact and Staff Acknowledgments: 

GAO Contact: 

Randolph C. Hite, (202) 512-3459: 

Staff Acknowledgments: 

In addition to the person named above, Justin Booth, Barbara Collier, 
William Cook, Neil Doherty, Michael Marshlick, Shannin O'Neill, Tomas 
Ramirez, and Jennifer Vitalbo made key contributions to this report. 

FOOTNOTES 

[1] Pub. L. 109-90 (Oct. 18, 2005). 

[2] OMB Circular A-11 establishes policy for planning, budgeting, 
acquisition, and management of federal capital assets. 

[3] The purpose of the Investment Review Board is to integrate capital 
planning and investment control, along with the budgeting, acquisition, 
and management of investments. It is also to ensure that spending on 
investments directly supports and furthers the mission, and that this 
spending provides optimal benefits and capabilities to stakeholders and 
customers. 

[4] The purpose of a privacy impact assessment is to ensure that there 
is no collection, storage, access, use, or dissemination of 
identifiable personal or business information that is not both needed 
and permitted. 

[5] Institute of Electrical and Electronics Engineers Computer Society, 
Standard for Software Verification and Validation 1012-1998 (June 8, 
2005). 

[6] CBP's implementation of this recommendation is complete with 
respect to the fiscal year 2006 expenditure plan. 

[7] SEI's institutional and project-specific estimating guidelines are 
defined respectively in Robert E. Park, Checklists and Criteria for 
Evaluating the Cost and Schedule Estimating Capabilities of Software 
Organizations, CMU/SEI-95-SR-005, and A Manager's Checklist for 
Validating Software Cost and Schedule Estimates, CMU/SEI-95-SR-004 
(Pittsburgh, Pa.: Carnegie Mellon University Software Engineering 
Institute, 1995). 

[8] US-VISIT is a governmentwide program to collect, maintain, and 
share information on foreign nationals for enhancing national security 
and facilitating legitimate trade and travel, while adhering to U.S. 
privacy laws and policies. 

[9] The Automated Targeting System is a DHS system that targets 
containers for inspection based on a perceived level of risk. 

[10] Screening is the method of determining high-risk people or 
shipments before their arrival at a port. Targeting is the risk-based 
determination of whether a shipment should undergo additional 
documentary review or physical inspection. 

[11] Earned value management is a tool for measuring program progress 
by comparing the value of work accomplished during a given period with 
that of the work expected in that period; this comparison permits 
performance to be evaluated based on calculated variances from the 
planned cost and schedule. 

[12] CBP was formed from the former U.S. Customs Service and other 
entities with border protection responsibility. 

[13] Targeting capabilities are currently being provided by DHS's 
Automated Targeting System. This system targets containers for 
inspection based on a perceived level of risk. ACE is intended to 
leverage these capabilities. 

[14] Pub. L. 109-90 (Oct. 18, 2005). 

[15] OMB Circular A-11 establishes policy for planning, budgeting, 
acquisition, and management of federal capital assets. 

[16]The purpose of the Investment Review Board is to integrate capital 
planning and investment control, budgeting, acquisition, and management 
of investments. It is also to ensure that spending on investments 
directly supports and furthers the mission and that this spending 
provides optimal benefits and capabilities to stakeholders and 
customers. 

[17]A release is the act of CBP permitting imported merchandise to 
enter the United States. 

[18] An entry is the documentation required to be submitted to CBP in 
order for it to permit imported merchandise to enter the United States. 

[19] Screening is the method of determining high-risk people or 
shipments before their arrival at a port. 

[20] Targeting is the risk-based determination of whether a shipment 
should undergo additional documentary review or physical inspection. 

[21] SAP is a commercial enterprise resource planning software product 
that has multiple modules, each performing separate but integrated 
business functions. ACE will use SAP to support many of its business 
processes and functions. CBP's Modernization Office is also using SAP 
as part of a joint project with its Office of Finance to support 
financial management, procurement, property management, cost 
accounting, and general ledger processes. 

[22] CBP national account managers work with the largest importers. 

[23] Brokers obtain licenses from CBP to conduct business on behalf of 
the importers by filling out paperwork and obtaining a bond; carriers 
are individuals or organizations engaged in transporting goods for 
hire. 

[24] Manifests are lists of passengers or invoices of cargo for a 
vehicle, such as a truck, ship, or plane. 

[25] The multimodal manifest involves the processing and tracking of 
cargo as it transfers between different modes of transportation, such 
as cargo that arrives by ship, is transferred to a truck, and then is 
loaded onto an airplane. 

[26] An import activity summary statement is a summary of an importer's 
shipment activities over a specific period of time that is transmitted 
electronically to CBP on a periodic basis by importers and brokers. 

[27] In March 2001, appropriations committees approved the use of $5 
million in stopgap funding to fund program management office 
operations. 


[28] GAO, Information Technology. Early Releases of Customs Trade 
System Operating, but Pattern of Cost and Schedule Problems Needs to Be 
Addressed, GAO-04-719 (Washington, D.C.: May 14, 2004). 

[29] GAO, Information Technology. Customs Automated Commercial 
Environment Progressing, but Need for Management Improvements 
Continues, GAO-05-267 (Washington, D.C.: Mar. 14, 2005). 

[30] GAO-05-267. 

[31] IEEE Computer Society, Standard for Software Verification and 
Validation 1012-1998 (June 8, 2005). 

[32]With respect to the fiscal year 2006 expenditure plan. 

[33] For these models, see Robert E. Park, Checklists and Criteria for 
Evaluating the Cost and Schedule Estimating Capabilities of Software 
Organizations (Pittsburgh, Pennsylvania: SEI, Carnegie Mellon 
University, 1995); A Manager's Checklist for Validating Software Cost 
and Schedule Estimates (Pittsburgh, Pennsylvania: SEI, Carnegie Mellon 
University, 1995). 

[34] United States Visitor and Immigrant Status Indicator Technology 
(US- VISIT) is a governmentwide program to collect, maintain, and share 
information on foreign nationals for enhancing national security and 
facilitating legitimate trade and travel, while adhering to U.S. 
privacy laws and policies. 

[35] GAO-04-719. 

[36]Chip Gliedman, Thirty-One Best Practices for the Service Desk 
(Forrester Research, Inc., 2005). 

[37] Electronic manifests provide truck information such as driver/ 
passenger data, vehicle data, and shipment details to CBP officers. 

[38] Clinger-Cohen Act of 1996, 40 U.S.C. 1101-11703; and OMB Circular 
A-130, Management of Federal Information Resources (Nov. 30, 2000). 

[39] OMB Circular No. A-11, Part 7 (revised June 2005). 
GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: