This is the accessible text file for GAO report number GAO-05-459 
entitled 'Department of Energy: Improved Oversight Could Better Ensure 
Opportunities for Small Business Subcontracting' which was released on 
May 24, 2005. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 

GAO: 

May 2005: 

Department of Energy: 

Improved Oversight Could Better Ensure Opportunities for Small Business 
Subcontracting: 

GAO-05-459: 

GAO Highlights: 

Highlights of GAO-05-459, a report to congressional committees: 

Why GAO Did This Study: 

Federal policy requires that small businesses receive the maximum 
practicable subcontracting opportunity for providing goods and services 
to large businesses that contract directly with federal agencies. The 
Department of Energy (DOE) annually directs almost $20 billion to the 
34 “facility management contractors” of which $3.3 billion was 
redirected to small business subcontractors in fiscal year 2004. DOE 
negotiates annual small business subcontracting goals with individual 
contractors and monitors their achievements. GAO was asked to (1) 
determine the usefulness of the data that DOE uses to monitor 
subcontracting performance and (2) discuss the actions that DOE has 
taken to address any problems with the contractors’ subcontracting 
efforts. 

What GAO Found: 

DOE’s facility management contractors’ small business subcontracting 
achievements—reported as a percentage of their total subcontracted 
dollars—are not useful for monitoring purposes because the reported 
data overstates subcontracting achievements in two ways: (1) All of the 
contractor-reported data incorrectly excluded some large-business 
subcontracts, beyond what federal reporting guidelines allow. Excluding 
these subcontracts made the percentage of subcontracted dollars going 
to small businesses appear larger than it would have, if such 
subcontracts were not incorrectly excluded. If these subcontracts had 
been included, some contractors said it was likely they would have 
requested lower goals. (2) Even when all relevant subcontracts are 
included, the contractor-reported data can still overstate contractors’ 
subcontracting achievements. Because a contractor could decide to 
subcontract only a small amount of its total federal contract, the 
portion of subcontracted dollars going to small businesses could, by 
comparison, appear misleadingly large. As a result, contractor-reported 
data is not useful to DOE in determining its contractors’ actual small 
business subcontracting achievements or adequately assessing whether 
small businesses are receiving maximum practicable subcontracting 
opportunities. 

DOE has not taken adequate steps to address known problems with the 
contractor-reported data. Because the data showed that the department 
was meeting its subcontracting goals, DOE officials were not inclined 
to closely monitor contractors’ practices for calculating their 
subcontracting goals and achievements. DOE officials were aware in 2002 
that the contractors were not following federal guidelines on which 
subcontracts to include when developing goals. DOE’s Small Business 
Office did provide clarifying information on the requirements, but DOE 
officials failed to ensure that the guidelines were being followed, and 
problems continued. In March 2005, DOE issued additional guidance, but 
it is uncertain whether DOE will ensure that the guidance is followed. 
These oversight problems occurred, in part, because DOE has not clearly 
defined the roles, responsibilities, and needed interaction of the 
various headquarters and field organizations that collectively oversee 
the contractors’ small business subcontracting efforts. 

Data on 13 facility management contractors’ reported fiscal year 2004 
small business subcontracting achievements, which incorrectly excluded 
certain subcontracts: 

Number of contractors: 13 (100%). 

Number of contractors that reported achieving their subcontracting 
goals: 12 (92%). 

Number of contractors achieving their goals if all appropriate 
subcontracts were included: 4 (31%). 

Source: GAO analysis of facility management contractor data. 

Note: Details on selection of these 13 facility management contractors 
can be found in appendix II of the report. 

[End of table]

What GAO Recommends: 

GAO recommends that DOE (1) ensure that facility management contractors 
are following federal guidelines for reporting subcontracting 
achievements; (2) for internal management purposes, calculate 
contractors’ achievements as a percent of the annual contract funding; 
and (3) issue guidance to clarify oversight responsibilities. In 
commenting on the report, DOE agreed with ensuring that reporting 
guidelines are being followed and clarifying oversight 
responsibilities. DOE disagreed with calculating the achievement data 
as a percent of contract funding, but we believe doing so would improve 
oversight. 

www.gao.gov/cgi-bin/getrpt?GAO-05-459. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Gene Aloise at (202) 512-
3841 or aloisee@gao.gov. 

[End of section]

Contents: 

Letter: 

Results in Brief: 

Background: 

Data Reported by Facility Management Contractors Is Not Useful for 
DOE's Monitoring of Their Small Business Subcontracting Performance: 

DOE Oversight of Small Business Subcontracting by Facility Management 
Contractors Was Not Adequate to Address Identified Problems with 
Contractor-Reported Data: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments: 

Appendix I: DOE Facility Management Contractors' Annual Small Business 
Subcontracting Goals and Achievements: 

Appendix II: Scope and Methodology: 

Determining the Usefulness of the Facility Management Contractor- 
Reported Data: 

Determining Actions Taken by DOE to Address Problems: 

Appendix III: Comments from the Department of Energy45: 

GAO Comments: 

Appendix IV: GAO Contacts and Staff Acknowledgment53: 

Tables: 

Table 1: Subcontracting Dollars that DOE Facility Management 
Contractors Reported Directing to Small Businesses in Fiscal Years 2001 
through 2004: 

Table 2: Types of Subcontracts Incorrectly Excluded from the 34 
Facility Management Contractors' Calculations of Fiscal Year 2004 Small 
Business Subcontracting Achievements: 

Table 3: Fiscal Year 2004 Small Business Subcontracting Goals, Reported 
Achievements, and Recalculated Achievements for 13 Facility Management 
Contractors: 

Table 4: Comparison of Fiscal Year 2004 Reported Small Business 
Subcontracting Achievements with Achievements Recalculated as a Percent 
of Annual Amount Funded on the Facility Management Contract: 

Abbreviations: 

DOE: Department of Energy: 

NASA: National Aeronautics and Space Administration: 

NNSA: National Nuclear Security Administration: 

SBA: Small Business Administration: 

United States Government Accountability Office: 

Washington, DC 20548: 

May 13, 2005: 

The Honorable Pete V. Domenici: 
Chairman: 
The Honorable Jeff Bingaman: 
Ranking Member: 
Committee on Energy and Natural Resources: 
United States Senate: 

The Honorable Olympia J. Snowe: 
Chair: 
The Honorable John F. Kerry: 
Ranking Member: 
Committee on Small Business and Entrepreneurship: 
United States Senate: 

The Small Business Act, as amended by the Small Business 
Reauthorization Act of 1997, established a federal policy that small 
businesses shall have the maximum practicable opportunity to 
participate in providing goods and services to the federal government 
and its direct contractors, consistent with efficient contract 
performance. Directing federal dollars to small businesses can produce 
cost savings, increase competition, encourage greater innovation, and 
enhance small business capacity. The policy of the federal government 
is to encourage contracting with small businesses--both prime 
contracts, which would be contracts directly between small businesses 
and federal agencies, and subcontracts, which would be between federal 
prime contractors and small businesses. 

The Department of Energy (DOE), the largest civilian contracting agency 
in the federal government, spent $22.4 billion on contracts in fiscal 
year 2004. The majority of this amount--$18.9 billion--was spent on 
large contracts for managing DOE's laboratories, production facilities, 
and environmental restoration sites located in various states across 
the nation. Under these "facility management contracts," a contractor 
is responsible for performing, managing, and integrating work at a DOE 
site, often subcontracting specific portions of the work to other 
businesses. In fiscal year 2004, DOE's 34 facility management 
contractors subcontracted out about $6.5 billion, of which about $3.3 
billion went to small businesses. 

Federal regulations require that DOE's facility management contractors 
develop small business subcontracting plans that set forth a strategy 
for providing the maximum practicable opportunities for small 
businesses to participate as subcontractors in the work that the 
facility management contractors oversee at DOE sites. The Small 
Business Administration (SBA) provides guidelines for how contractors 
should develop small business subcontracting plans and goals. These 
guidelines describe the procedures that contractors should use to 
officially report their small business subcontracting goals and 
achievements. In reporting, contractors must express the dollars going 
to their small business subcontractors as a percentage of the total 
dollars going to all of their subcontractors--including both large and 
small businesses as well as government agencies and nonprofit 
organizations. Contractors generally must report on all of their 
subcontracts, although SBA guidelines allow two exclusions: (1) 
subcontracts performed outside of the U.S. or its territories and (2) 
subcontracts with an affiliate organization, such as a subsidiary 
company or a parent company. 

To meet government-wide small business subcontracting goals, SBA 
negotiates annual subcontracting goals with each federal agency. The 
goal that DOE's Office of Small and Disadvantaged Business Utilization 
(referred to in this report as DOE's Small Business Office) has 
negotiated with SBA is for 50 percent of its total subcontracting 
dollars to be directed to small businesses each year. To meet this 
goal, DOE contracting officers located at the various agency sites 
negotiate annual goals with individual facility management contractors 
and, with the assistance of small business program managers, monitor 
contractors' compliance with subcontracting plans as well as progress 
toward achieving annual small business subcontracting goals. 

Despite the efforts of SBA to meet government-wide annual 
subcontracting goals, there have been continuing concerns that small 
businesses were not being provided the maximum practicable opportunity 
to provide goods and services to the federal government and its 
contractors. In March of 2002, the President announced a Small Business 
Agenda that proposed steps toward creating a more dynamic environment 
where small businesses could flourish, including ways to improve the 
access of small businesses to federal contracting opportunities. One of 
the strategies was to strengthen federal agency oversight of its 
contractors' efforts to comply with small business subcontracting 
plans. 

In this context, you asked us to review the small business 
subcontracting achievements of DOE's facility management contractors. 
This report discusses (1) the usefulness of the data reported by DOE 
facility management contractors for monitoring contractor performance 
in small business subcontracting and (2) the actions that DOE has taken 
to address any problems identified with its facility management 
contractors' small business subcontracting efforts. 

To determine the usefulness of the data reported by DOE facility 
management contractors on their small business subcontracting goals and 
achievements, we received and analyzed data on fiscal year 2001 through 
2004 subcontracting goals and achievements from DOE's 34 facility 
management contractors, as well as information on how the contractors 
developed their goals and calculated their achievements. To assess the 
reliability of the data that the contractors provided about their 
achievements, we obtained and analyzed information from all 34 
contractors about their methods for compiling subcontracting 
achievement data and steps they took to ensure the accuracy and 
completeness of these data. We also visited 13 of the 34 facility 
management contractors, which we selected based on the contractors' 
association with the department's three largest component 
organizations--Environmental Management, Science, and National Nuclear 
Security Administration (NNSA)--and on the geographic location of DOE 
sites. During these site visits, we obtained and analyzed supporting 
documents for small business subcontracts reported in the contractors' 
fiscal year 2004 achievements, and we obtained documentation on the 
dollar value of any subcontracts that the contractors excluded from 
their reported achievements for that year. A more detailed description 
of our scope and methodology is presented in appendix II. We performed 
our work from June 2004 to April 2005 in accordance with generally 
accepted government auditing standards. 

Results in Brief: 

The subcontracting data reported by DOE's facility management 
contractors is not useful for monitoring whether they are meeting small 
business subcontracting goals. All contractor-reported data incorrectly 
excluded some subcontracts, beyond what SBA guidelines allow, thereby 
overstating contractors' reported small business subcontracting 
achievements. Excluding these subcontracts reduced the facility 
management contractors' total reported subcontracting dollars without 
reducing the reported amount that went to small businesses. As a 
result, the reported percentage of subcontracting dollars that went to 
small business appeared larger than it would have if such subcontracts 
were not incorrectly excluded. When we added the incorrectly excluded 
subcontracts (about $887 million) back into selected contractors' 
reported achievements, 9 out of the 13 selected contractors would have 
fallen short of their subcontracting goals, although 12 had reported 
achieving their goals. However, if these subcontracts had been 
included, some contractors said it was likely they would have requested 
lower goals. In addition, even when all relevant subcontracts are 
included, the contractor-reported data are misleading because they can 
make the small business subcontracting results appear higher than they 
actually are. This happens because the contractors calculate their 
small business subcontracting achievements as a percentage of the total 
amount of their subcontracted dollars. Because the total amount of 
their subcontracted dollars could be very small, the portion going to 
small businesses could appear as a misleadingly large percentage. As a 
result, the contractor-reported data do not provide a true picture of 
the contractors' performance. Therefore, the department cannot 
meaningfully use the data to monitor performance and determine whether 
the contractors are affording small business subcontractors the maximum 
practicable opportunity to provide goods and services to the facility 
management contractors, as required by the policy set out by the Small 
Business Act. 

DOE has not taken adequate steps to address the problems with the small 
business subcontracting data reported by its facility management 
contractors, resulting in a lack of assurance that facility management 
contractors are providing maximum practicable opportunities for small 
business subcontracting. Because achievement data reported by the 
facility management contractors showed that DOE was meeting the small 
business subcontracting goal it established with SBA, DOE officials 
were not inclined to closely monitor facility management contractors' 
subcontracting practices or take adequate steps to address even known 
problems with the achievement data. In some cases, DOE's contracting 
officers approved facility management contractors' small business 
subcontracting plans, even though those plans specified practices for 
calculating goals and achievements that were not consistent with SBA 
guidelines. In other cases, officials in DOE's Small Business Office 
knew of, but did not adequately address, problems with subcontracting 
achievement data until we raised concerns about the data. Further, DOE 
officials were aware in 2002 that the facility management contractors 
were not consistently following SBA guidelines concerning which 
subcontracts to include when developing small business subcontracting 
goals. Although DOE's Small Business Office then provided clarifying 
information on the requirements, these problems continued. In March 
2005, DOE issued additional guidance, but it is uncertain whether DOE 
will ensure that the guidance is followed. As a result of these 
oversight problems, DOE had not ensured that its facility management 
contractors were providing maximum practicable opportunities for small 
businesses. These problems occurred, in part, because DOE has not 
clearly defined the roles, responsibilities, and needed interaction of 
the various headquarters and field organizations that must work 
together to provide oversight of the small business subcontracting 
program. 

To improve the overall effectiveness of DOE's small business 
subcontracting program, we are recommending that the Secretary of 
Energy take steps to (1) ensure that DOE has useful data for managing 
the small business subcontracting program and (2) improve oversight of 
the subcontracting program by ensuring that roles and responsibilities 
are clearly defined. 

DOE agreed with our recommendations that the department strengthen 
oversight of its small business subcontracting program by clarifying 
oversight roles and responsibilities and by ensuring that facility 
management contractors follow a consistent practice for calculating and 
reporting their small business subcontracting goals and achievements. 
However, DOE disagreed with our recommendation that, for internal 
program management purposes, the department use data on its 
contractors' subcontracting achievements, calculated as a percentage of 
the dollars obligated to their prime contract. DOE maintained that it 
should continue to use subcontracting data, calculated as a percentage 
of the total dollars subcontracted, as reported to SBA. While we agree 
that DOE's contractors should continue to report their subcontracting 
achievements as SBA requires, we continue to believe that, for internal 
management purposes, the data do not provide a true picture of 
contractor performance. Without a true picture of performance, DOE 
cannot effectively oversee that performance to determine whether its 
facility management contractors are providing the maximum practicable 
subcontracting opportunities to small businesses. 

Background: 

DOE has major sites and facilities around the country where the 
department carries out its missions, including developing, maintaining, 
and securing the nation's nuclear weapons capability; cleaning up the 
nuclear and hazardous wastes resulting from more than 50 years of 
weapons production; and conducting basic energy and scientific 
research, such as mapping the human genome. DOE relies on facility 
management contractors to operate its facilities and accomplish its 
missions. This mission work is carried out under the direction of the 
National Nuclear Security Administration (NNSA) and DOE's program 
offices, including the offices of Environmental Management and Science. 

SBA develops regulations and provides guidance for federal agencies and 
their contractors to follow in carrying out the federal policy to 
provide maximum practicable contracting opportunities for small 
businesses, consistent with efficient contract performance.[Footnote 1] 
Under the Small Business Act and federal regulations, any large 
business with a federal prime contract that has a value over $500,000 
(or $1 million for construction contracts) and that has subcontracting 
possibilities, must have a small business subcontracting plan, 
including annual goals for directing subcontracting dollars to small 
businesses. SBA has also issued specific guidance for developing annual 
subcontracting goals and reporting achievements to SBA.[Footnote 2] 
Although there is no specified percentage goal for small business 
subcontracting in law or regulations, SBA's government-wide goal is 
that 40 percent of federal subcontracted dollars be directed to small 
businesses.[Footnote 3]

DOE's facility management contractors carry out the SBA requirements by 
developing subcontracting plans and annual goals, and reporting their 
achievements to DOE and SBA.[Footnote 4] Facility management 
contractors use the following process: 

* Develop small business subcontracting plans. Facility management 
contractors generally develop small business subcontracting plans as 
part of the overall proposal submitted in response to a DOE request for 
proposals on a new contract or upon extension or renewal of an existing 
contract. The subcontracting plan includes information on the types of 
work to be subcontracted and how, and to what extent, the contractor 
would provide subcontracting opportunities for small businesses. The 
proposed subcontracting plans are reviewed as part of the overall 
proposal and are then incorporated into the contract when it is 
awarded. 

* Develop annual small business subcontracting goals. Generally, the 
facility management contractors perform "make-or-buy" analyses to 
determine how much of their work will be subcontracted rather than 
performed by the contractors' own employees. For the portion of the 
work the facility management contractor intends to subcontract, the 
facility management contractors develop small business subcontracting 
goals each year, after considering the proposed funding for the 
contracts, upcoming subcontracting opportunities, and the potential for 
small businesses to perform the subcontracting work. After an agreement 
is reached on the proposed goals, the goals are incorporated into the 
contract. 

* Report small business subcontracting achievements. Facility 
management contractors are required to report their small business 
subcontracting achievements to SBA twice each fiscal year--as of the 
ends of March and September. SBA guidelines specify that small business 
subcontracting achievements should be calculated as a percentage of 
total dollars subcontracted. Facility management contractors also 
report this achievement information to DOE.[Footnote 5]

DOE's Small Business Office negotiates the department's annual small 
business subcontracting goals with SBA, coordinates outreach efforts 
with the small business community, and works with NNSA and DOE's 
program offices to establish and monitor annual goals. DOE's Office of 
Procurement and Assistance Management and NNSA's Office of Acquisition 
and Supply Management establish policies and guidance for conducting 
procurements according to federal and departmental regulations, and 
they maintain the information systems on the department's prime 
contracts, including annual dollars provided to each facility 
management contractor. NNSA and DOE's program offices, such as 
Environmental Management and Science, are responsible for providing 
program oversight and direction to the contractors. 

In addition to the oversight responsibilities shared among DOE's 
various headquarters and field organizations, SBA has a role in the 
oversight of facility management contractors' small business 
subcontracting efforts. SBA officials in regional offices generally 
review proposed subcontracting plans and proposed annual small business 
goals. Regional SBA officials also review the reports on small business 
subcontracting achievements submitted by facility management 
contractors, and they may review large proposed subcontracts to 
determine if there are potential opportunities for small businesses. 
SBA regional offices also perform periodic compliance reviews of 
individual contractor's small business subcontracting efforts, 
including validating the data reported by the contractors to ensure 
that the contractor is following SBA guidelines.[Footnote 6]

Data Reported by Facility Management Contractors Is Not Useful for 
DOE's Monitoring of Their Small Business Subcontracting Performance: 

The data that DOE uses to monitor its facility management contractors' 
performance in small business subcontracting generally shows that the 
contractors have exceeded their annual subcontracting goals. However, 
these data are not useful for monitoring purposes for two reasons. 
First, the data reported by the facility management contractors 
frequently overstated their subcontracting achievements, by failing to 
account for all of their subcontracts, as required by SBA reporting 
guidelines. As a result, the percent of total subcontracting dollars 
going to small businesses appeared larger than if the contractors had 
been following SBA's reporting guidelines. Second, even if the facility 
management contractors were correctly reporting their small business 
subcontracting achievements, the method for calculating those 
achievements does not provide a true picture of contractors' 
performance. The method can make a contractor appear to be performing 
well--for example, by directing 80 percent of subcontracting dollars 
annually to small businesses--when, in fact, that percentage is based 
on a small amount of dollars. When small business subcontracting 
dollars are recalculated as a percent of the annual funding on the 
facility management contract, the contractor's actual achievement can 
turn out to be relatively low. Because contractor-reported data does 
not provide a true picture of the contractors' performance, the 
department cannot meaningfully use the data to monitor performance and 
determine whether the contractors are providing small business 
subcontractors with the maximum practicable opportunity to provide 
goods and services to the facility management contractors, as required 
by the policy set out by the Small Business Act. 

Contractor-Reported Data on Small Business Subcontracting Achievements 
Frequently Overstated Performance: 

The contractor-reported data that DOE uses to monitor facility 
management contractors' performance in small business subcontracting 
generally showed that contractors exceeded their annual small business 
subcontracting goals in fiscal years 2001 through 2004. In fiscal year 
2004, for example, 29 of the 34 facility management contractors 
reported exceeding their annual goals when they directed 33 to 88 
percent of their subcontracting dollars to small businesses. These 
contractors reported exceeding their goals by as much as 28 percent, 
whereas the contractors that reported falling short of their goals for 
that year did so by as much as 26 percent. Whether or not individual 
contractors achieved their goals, the 34 contractors collectively 
reported directing nearly $3.3 billion[Footnote 7] to small business 
subcontractors in fiscal year 2004, representing a 27 percent increase 
over the amount they had directed to small businesses in fiscal year 
2001 (see table 1). Additional information on the facility management 
contractors' subcontracting goals and achievements for fiscal years 
2001 through 2004 is presented in appendix I. 

Table 1: Subcontracting Dollars that DOE Facility Management 
Contractors Reported Directing to Small Businesses in Fiscal Years 2001 
through 2004: 

Fiscal year: 2001; 
Small business subcontracting dollars: $2,574,701,477. 

Fiscal year: 2002; 
Small business subcontracting dollars: $3,076,546,419. 

Fiscal year: 2003; 
Small business subcontracting dollars: $3,071,831,243. 

Fiscal year: 2004; 
Small business subcontracting dollars: $3,281,485,994. 

Source: GAO analysis of DOE and facility management contractor data. 

[End of table]

Although facility management contractors generally reported exceeding 
their subcontracting goals, the data are not useful for monitoring the 
contractors' performance, because the contractors' achievements were 
frequently overstated. When calculating subcontracting achievements, 
SBA guidelines allow contractors to exclude from their calculations 
only those subcontracts performed outside of the U.S. or its 
territories and subcontracts with affiliate organizations, such as a 
subsidiary or parent company[Footnote 8]. However, in fiscal year 2004, 
all 34 of the contractors' reported achievements incorrectly excluded 
other types of subcontracts, beyond what SBA guidelines allow (see 
table 2). The facility management contractors we visited generally told 
us it was their normal practice to make these types of exclusions. In 
making these types of exclusions, the contractors said they were 
following their past practices or that DOE contracting officers had 
approved the additional exclusions. For example, officials representing 
one of these contractors pointed out that, in excluding subcontracts 
from the calculation of their subcontracting achievements beyond what 
SBA guidance allows, their company was following the subcontracting 
plan approved by DOE. The contractor officials said that they would not 
have made these exclusions, if DOE had not permitted them, nor would 
they have negotiated as high a subcontracting goal under those 
circumstances. 

Table 2: Types of Subcontracts Incorrectly Excluded from the 34 
Facility Management Contractors' Calculations of Fiscal Year 2004 Small 
Business Subcontracting Achievements: 

Type of subcontracts incorrectly excluded from calculations of small 
business subcontracting achievements: Purchases from other government 
agencies, nonprofit organizations, or other facility management 
contractors; 
Number of facility management contractors[A]: 29. 

Type of subcontracts incorrectly excluded from calculations of small 
business subcontracting achievements: Utility purchases; 
Number of facility management contractors[A]: 26. 

Type of subcontracts incorrectly excluded from calculations of small 
business subcontracting achievements: Credit card transactions; 
Number of facility management contractors[A]: 22. 

Type of subcontracts incorrectly excluded from calculations of small 
business subcontracting achievements: Purchases from sources directed 
by DOE or mandated by law; 
Number of facility management contractors[A]: 14. 

Type of subcontracts incorrectly excluded from calculations of small 
business subcontracting achievements: Selected blanket purchasing 
agreements[B]; 
Number of facility management contractors[A]: 10. 

Type of subcontracts incorrectly excluded from calculations of small 
business subcontracting achievements: Lease agreements; 
Number of facility management contractors[A]: 8. 

Source: GAO analysis of facility management contractor data. 

[A] For a given type of subcontract, the remainder of the 34 
contractors not reflected in this column had either included the 
subcontract type in their reported achievements or did not have any 
subcontracts of that type in fiscal year 2004. 

[B] Blanket purchasing agreements reflect purchases made through DOE's 
integrated contractor purchasing team or through the General Services 
Administration's federal supply schedule. 

[End of table]

Facility management contractors' practice of incorrectly excluding 
certain subcontracts from achievement calculations resulted in 
overstating their reported subcontracting achievements by making the 
achievements appear larger than they would have appeared, if only the 
appropriate exclusions had been made in the calculation. For SBA- 
reporting purposes, contractors calculate their subcontracting 
achievements by expressing the dollars that they directed to small 
business subcontracts as a percentage of the total amount they 
subcontracted. However, because they incorrectly excluded subcontracts 
that generally did not go to small businesses--such as subcontracts 
with other facility management contractors--the facility management 
contractors incorrectly reduced the total amount that was subcontracted 
(the denominator), without affecting the total amount going to small 
businesses (the numerator). As a result, the percentage of total 
subcontracted dollars going to small businesses appeared larger than it 
actually was. 

The effect of making incorrect exclusions on achievement calculations 
is significant. At the 13 facility management contractors we visited, 
we analyzed the fiscal year 2004 dollar amounts associated with the 
subcontracts that were incorrectly excluded from the calculation of 
their reported subcontracting achievements. These excluded subcontracts 
totaled about $887 million. For these 13 contractors, the practice of 
incorrectly excluding subcontracts from their reported achievements 
resulted in overstating the percentage achievements by as much as 27 
percent. Moreover, although 12 of the 13 contractors had appeared, from 
their reported achievements, to be meeting or exceeding their 
subcontracting goals, when the achievements were recalculated by adding 
the incorrectly excluded subcontracts back into the calculation, only 4 
contractors would have achieved their goals. The remaining 9 
contractors would have fallen short of their subcontracting goals, by 
as much as $31.1 million, or about 19 percent. According to contractor 
officials, it is also likely that these contractors would not have 
agreed to as high of a subcontracting goal, if they had to include 
these subcontracts (see table 3).[Footnote 9]

Table 3: Fiscal Year 2004 Small Business Subcontracting Goals, Reported 
Achievements, and Recalculated Achievements for 13 Facility Management 
Contractors: 

Fiscal year 2004 (percent). 

Battelle Memorial, Pacific Northwest National Laboratory, Wash; 
Subcontracting goal: 55.0%; 
Reported subcontracting achievement: 60.8%; 
Recalculated achievement[A]: 42.9%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (12.1%). 

Bechtel Hanford, Hanford Site, Wash; 
Subcontracting goal: 50.0%; 
Reported subcontracting achievement: 65.0%; 
Recalculated achievement[A]: 64.7%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: 14.7%. 

Bechtel Jacobs, Oak Ridge Site, Tenn; 
Subcontracting goal: 28.0%; 
Reported subcontracting achievement: 38.9%; 
Recalculated achievement[A]: 36.4%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: 8.4%. 

Bechtel National, Waste Treatment Plant, Wash; 
Subcontracting goal: 46.0%; 
Reported subcontracting achievement: 65.2%; 
Recalculated achievement[A]: 38.1%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (7.9%). 

Bechtel Nevada, Nevada Test Site, Nev; 
Subcontracting goal: 62.0%; 
Reported subcontracting achievement: 70.6%; 
Recalculated achievement[A]: 58.1%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (3.9%). 

Bechtel SAIC, Yucca Mountain Project, Nev; 
Subcontracting goal: 55.0%; 
Reported subcontracting achievement: 57.0%; 
Recalculated achievement[A]: 36.4%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (18.6%). 

BWXT Y-12, Y-12 National Security Complex, Tenn; 
Subcontracting goal: 63.0%; 
Reported subcontracting achievement: 66.7%; 
Recalculated achievement[A]: 56.5%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (6.5%). 

CH2M Hill Hanford, Hanford Site, Wash; 
Subcontracting goal: 48.0%; 
Reported subcontracting achievement: 59.9%; 
Recalculated achievement[A]: 42.6%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (5.4%). 

Fluor Hanford, Hanford Site, Wash; 
Subcontracting goal: 40.0%; 
Reported subcontracting achievement: 52.1%; 
Recalculated achievement[A]: 44.6%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: 4.6%. 

Lockheed Martin, Sandia National Laboratories, N. Mex; 
Subcontracting goal: 50.0%; 
Reported subcontracting achievement: 49.9[C]%; 
Recalculated achievement[A]: 46.0%%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (4.0%). 

University of California, Lawrence Livermore National Laboratory, 
Calif; 
Subcontracting goal: 35.0%; 
Reported subcontracting achievement: 39.2%; 
Recalculated achievement[A]: 31.6%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (3.4%). 

University of California, Los Alamos National Laboratory, N. Mex; 
Subcontracting goal: 42.0%; 
Reported subcontracting achievement: 44.0%; 
Recalculated achievement[A]: 39.3%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: (2.7%). 

UT Battelle, Oak Ridge National Laboratory, Tenn; 
Subcontracting goal: 48.0%; 
Reported subcontracting achievement: 62.7%; 
Recalculated achievement[A]: 50.3%; 
Extent to which the recalculated achievement differed from the 
subcontracting goal[B]: 2.3%. 

Source: GAO analysis of facility management contractor data. 

Note: Details on selection of these 13 facility management contractors 
can be found in appendix II. 

[A] Recalculated achievements include the subcontracts that had been 
incorrectly excluded from the reported achievements. 

[B] Numbers in parentheses are negative and represent the percentage by 
which the contractor would have fallen short of subcontracting goals. 

[C] Although the fiscal year 2004 small business subcontracting 
achievement reported by the facility management contractor at the 
Sandia National Laboratories fell short of that contractor's 
subcontracting goal by less than 0.1 percent of total subcontracted 
dollars (or approximately $591,000), the contractor directed the 
largest subcontracting dollar amounts to small businesses of the 34 
facility management contractors in 3 of the 4 years of our study, 
including fiscal year 2004. That year, for example, the contractor 
directed about $486 million to small businesses out of the $974 million 
it subcontracted--$115 million more in subcontract dollars to small 
businesses than the second highest facility management contractor. 

[End of table]

The fiscal year 2004 small business subcontracting achievements 
reported by many of the remaining 21 contractors that we did not visit 
during our study also are likely overstated, although we did not 
document the extent of the overstatement. Based on information these 
contractors reported to us, all 21 contractors had incorrectly excluded 
subcontracts from the calculations of fiscal year 2004 subcontracting 
achievements. This practice will almost always result in overstating 
actual achievements, because the subcontracts excluded from the 
calculations are generally not awarded to small businesses. 

Small Business Subcontracting Reporting Method Does Not Provide a True 
Picture of Facility Management Contractors' Performance: 

The method that facility management contractors use to calculate their 
small business subcontracting achievements for SBA reporting purposes 
does not present a true picture of a contractor's small business 
subcontracting because achievements are not calculated in relation to 
the total value of the facility management contract. Rather, the method 
for calculating small business subcontracting achievements is based on 
a quantity determined by the facility management contractors--namely, 
the portion of total work under their DOE contract that they intend to 
subcontract out. Thus, a contractor can appear to be performing well-- 
i.e., directing 80 percent of its subcontracting dollars to small 
businesses--but that percentage is not very informative about the 
actual amount of subcontracting occurring with small businesses. 

In our view, calculating small business subcontracting achievements in 
this manner invariably presents a misleading picture. For example, in 
fiscal year 2004, contractors at two of DOE's weapons production 
facilities reported substantially different small business 
subcontracting achievements--one reported directing 80 percent of its 
subcontracting dollars to small businesses (or $92.6 million) while the 
other reported 57 percent (or $109.9 million). However, these 
percentages hide the fact that the first contractor subcontracted out 
proportionally less of the work of the facility management contract 
than the second contractor, despite the fact that both facility 
management contracts were similar in size. Recalculating the 
subcontracting achievements as a percentage of the amount of funding 
directed by DOE to each facility management contract for the year 
reveals that the actual subcontracting achievements were quite similar-
-21 and 23 percent respectively of the contracts' annual funding. Thus, 
the contractor that appeared, from the data that DOE uses, to be 
significantly outperforming the other was actually devoting a slightly 
smaller portion of its facility management contract dollars to small 
business subcontracting. 

Recalculating the subcontracting achievement data as a percent of the 
annual amount funded by DOE for each facility management contract 
provides a very different picture of the contractors' performance. Some 
contractors that appeared to be outperforming most other contractors 
were ranked near the bottom of the list when their achievements were 
measured as a percent of the annual funding on their contract. For 
example, the reported subcontracting achievement in fiscal year 2004 of 
the contractor at the Princeton Plasma Physics Laboratory appeared to 
be the second highest among the 34 contractors. However, after we 
recalculated the achievements as a percentage of annual contract 
funding, the contractor's performance dropped significantly to 28th out 
of 34 contractors (see table 4). Conversely, 6 of the 17 contractors 
that were in the bottom half of the rankings of reported subcontracting 
achievements moved to the top half, after we recalculated the 
achievements as a percent of the annual amount funded on each facility 
management contract. 

Table 4: Comparison of Fiscal Year 2004 Reported Small Business 
Subcontracting Achievements with Achievements Recalculated as a Percent 
of Annual Amount Funded on the Facility Management Contract: 

Facility management contractor and location: Washington TRU Solutions, 
Waste Isolation Pilot Plant, N. Mex; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 88.0; 
Rank of reported achievements from highest (1) to lowest (34): 1; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 27.9; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 5. 

Facility management contractor and location: Princeton University, 
Princeton Plasma Physics Laboratory, N.J; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 83.2; 
Rank of reported achievements from highest (1) to lowest (34): 2; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 12.8; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 28. 

Facility management contractor and location: BWXT Pantex, Pantex 
Facility, Tex; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 80.3; 
Rank of reported achievements from highest (1) to lowest (34): 3; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 21.2; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 9. 

Facility management contractor and location: Bechtel Nevada, Nevada 
Test Site, Nev; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 70.6; 
Rank of reported achievements from highest (1) to lowest (34): 4; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 20.5; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 10. 

Facility management contractor and location: BWXT Y-12, Y-12 National 
Security Complex, Tenn; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 66.7; 
Rank of reported achievements from highest (1) to lowest (34): 5; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 17.0; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 16. 

Facility management contractor and location: Midwest Research 
Institute, National Renewable Energy Laboratory, Colo; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 66.6; 
Rank of reported achievements from highest (1) to lowest (34): 6; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 22.7; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 7. 

Facility management contractor and location: West Valley Nuclear 
Services Company, West Valley Demonstration Project, N.Y; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 66.5; 
Rank of reported achievements from highest (1) to lowest (34): 7; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 28.6; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 4. 

Facility management contractor and location: Bechtel National, Waste 
Treatment Plant, Wash; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 65.2; 
Rank of reported achievements from highest (1) to lowest (34): 8; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 29.1; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 3. 

Facility management contractor and location: Bechtel Hanford, Hanford 
Site, Wash; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 65.0; 
Rank of reported achievements from highest (1) to lowest (34): 9; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 29.2; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 2. 

Facility management contractor and location: Universities Research 
Association, Fermi National Accelerator Laboratory, Ill; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 63.5; 
Rank of reported achievements from highest (1) to lowest (34): 10; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 14.3; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 24. 

Facility management contractor and location: UT Battelle, Oak Ridge 
National Laboratory, Tenn; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 62.7; 
Rank of reported achievements from highest (1) to lowest (34): 11; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 17.0; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 17. 

Facility management contractor and location: Battelle Memorial, Pacific 
Northwest National Laboratory, Wash; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 60.8; 
Rank of reported achievements from highest (1) to lowest (34): 12; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 14.8; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 23. 

Facility management contractor and location: CH2M Hill Hanford, Hanford 
Site, Wash; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 59.9; 
Rank of reported achievements from highest (1) to lowest (34): 13; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 30.3; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 1. 

Facility management contractor and location: Stanford University, 
Stanford Linear Accelerator Center, Calif; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 59.3; 
Rank of reported achievements from highest (1) to lowest (34): 14; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 15.7; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 22. 

Facility management contractor and location: Bechtel BWXT Idaho, Idaho 
National Laboratory, Idaho; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 58.2; 
Rank of reported achievements from highest (1) to lowest (34): 15; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 12.7; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 29. 

Facility management contractor and location: Westinghouse Savannah 
River, Savannah River Site, S.C; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 58.0; 
Rank of reported achievements from highest (1) to lowest (34): 16; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 7.5; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 34. 

Facility management contractor and location: Brookhaven Science 
Associates, Brookhaven National Laboratory, N.Y; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 57.5; 
Rank of reported achievements from highest (1) to lowest (34): 17; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 13.8; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 26. 

Facility management contractor and location: Bechtel SAIC, Yucca 
Mountain Project, Nev; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 57.0; 
Rank of reported achievements from highest (1) to lowest (34): 18; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 20.3; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 11. 

Facility management contractor and location: Honeywell Federal 
Manufacturing & Technologies, Kansas City Plant, Mo; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 56.8; 
Rank of reported achievements from highest (1) to lowest (34): 19; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 23.2; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 6. 

Facility management contractor and location: Iowa State University, 
Ames Laboratory, Iowa; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 56.7; 
Rank of reported achievements from highest (1) to lowest (34): 20; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 9.5; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 33. 

Facility management contractor and location: Fluor Hanford, Hanford 
Site, Wash; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 52.1; 
Rank of reported achievements from highest (1) to lowest (34): 21; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 13.9; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 25. 

Facility management contractor and location: Southeastern Universities 
Research Association, Thomas Jefferson National Accelerator Facility, 
Va; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 50.1; 
Rank of reported achievements from highest (1) to lowest (34): 22; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 16.4; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 19. 

Facility management contractor and location: Lockheed Martin, Sandia 
National Laboratories, N. Mex; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 49.9; 
Rank of reported achievements from highest (1) to lowest (34): 23; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 21.5; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 8. 

Facility management contractor and location: University of Chicago, 
Argonne National Laboratory, Ill; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 46.0; 
Rank of reported achievements from highest (1) to lowest (34): 24; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 12.0; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 30. 

Facility management contractor and location: University of California, 
Los Alamos National Laboratory, N. Mex; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 44.0; 
Rank of reported achievements from highest (1) to lowest (34): 25; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 19.8; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 12. 

Facility management contractor and location: Bechtel Bettis, Bettis 
Atomic Power Laboratory, Pa; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 39.4; 
Rank of reported achievements from highest (1) to lowest (34): 26; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 16.5; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 18. 

Facility management contractor and location: University of California, 
Lawrence Livermore National Laboratory, Calif; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 39.2; 
Rank of reported achievements from highest (1) to lowest (34): 27; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 12.9; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 27. 

Facility management contractor and location: Bechtel Jacobs, Oak Ridge 
Site, Tenn; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 38.9; 
Rank of reported achievements from highest (1) to lowest (34): 28; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 17.8; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 14. 

Facility management contractor and location: DynMcDermott Petroleum 
Operations, Strategic Petroleum Reserve, La; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 38.8; 
Rank of reported achievements from highest (1) to lowest (34): 29; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 16.1; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 20. 

Facility management contractor and location: University of California, 
Lawrence Berkeley National Laboratory, Calif; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 37.4; 
Rank of reported achievements from highest (1) to lowest (34): 30; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 16.0; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 21. 

Facility management contractor and location: KAPL, Inc., Knolls Atomic 
Power Laboratory, N.Y; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 36.4; 
Rank of reported achievements from highest (1) to lowest (34): 31; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 11.2; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 32. 

Facility management contractor and location: CH2M Hill Mound, Mound 
Site, Ohio; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 36.1; 
Rank of reported achievements from highest (1) to lowest (34): 32; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 12.0; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 31. 

Facility management contractor and location: Fluor Fernald, Fernald 
Closure Project, Ohio; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 33.5; 
Rank of reported achievements from highest (1) to lowest (34): 33; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 17.7; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 15. 

Facility management contractor and location: Kaiser-Hill, Rocky Flats 
Closure Project, Colo; 
Reported subcontracting achievements (percent of total dollars 
subcontracted): 33.3; 
Rank of reported achievements from highest (1) to lowest (34): 34; 
Recalculated subcontracting achievements (percent of annual amount 
funded on the facility management contract): 17.8; 
Rank of recalculated achievements from highest achievement (1) to 
lowest (34): 13. 

Source: GAO analysis of DOE and facility management contractor data. 

Note: Any apparent tie situations are due to rounding of the 
achievement data. Ranks in the table reflect the actual rank-order. 
Both the reported and the recalculated subcontracting achievements 
presented in this table have not been adjusted to include any 
subcontracts that the facility management contractors incorrectly 
excluded from their calculations, because we did not have information 
on the dollar value of the incorrectly excluded subcontracts for all 34 
contractors. 

[End of table]

While a contractor may be subcontracting a smaller percentage of its 
facility management contract to small businesses than other facility 
management contractors, there can be several reasons for differences in 
contractors' small business subcontracting achievements, which should 
be examined before concluding that a particular contractor is 
underperforming. For example, DOE and contractor officials told us that 
the type of work contractors perform at DOE sites is an important 
factor in determining the potential for small business subcontracting. 
Our analysis of the 34 facility management contractors' fiscal year 
2004 small business subcontracting achievements suggests that this may 
be true. We found that the 16 contractors primarily involved in 
environmental cleanup or weapons production at DOE sites generally 
directed a greater percentage of their contracts' annual funding to 
small business subcontracting than the 16 contractors at DOE research 
laboratories.[Footnote 10] Contractor and DOE officials said that 
opportunities for small business subcontractors tend to be more limited 
at research laboratories than other types of DOE facilities, because 
research activities are often integrated, and fragmenting those 
activities among several contractors could negatively impact the work. 
Officials said that other types of work, such as facility construction 
or cleanup projects, generally have more subcontracting potential and 
can often be structured at such a scale that small businesses could 
perform the work. 

Contract performance goals can also affect opportunities for small 
business subcontracting. For example, small business subcontracting 
opportunities diminished somewhat at an environmental cleanup site in 
Oak Ridge, Tennessee, after DOE and the facility management contractor, 
Bechtel Jacobs, renegotiated the contract to include more aggressive 
time lines and cost limitations for completing the work. In response to 
the changes in its contract, Bechtel Jacobs began subcontracting less 
of the work, including work that small business subcontractors had 
previously performed. DOE and contractor officials told us that the 
company wanted more control over the work to better ensure meeting the 
new time lines and cost limitations. Officials from local small 
businesses that subcontract with Bechtel Jacobs said that while they 
did not disagree with Bechtel Jacobs's strategy for dealing with the 
changes to its contract, the small businesses had to adapt to a new 
business environment in which less subcontracting work would be 
available under that facility management contract. 

Although differences in the type of work and contract performance goals 
may account for some of the differences in facility management 
contractors' performance in small business subcontracting, there may be 
other reasons for those differences. For example, contractor officials 
said that the timing of projects or changes in the annual funding for a 
facility management contract could affect opportunities for small 
businesses to participate in work that is generally conducive to small 
business subcontracting. In addition, contractors at sites with similar 
missions and similar types of work can vary substantially in the amount 
of funding that they direct to small business subcontractors. For 
example, contractors at the Sandia and Los Alamos National Laboratories 
in New Mexico ranked highly among the 34 facility management 
contractors--8th and 12th, respectively--in the percentage of their 
contracts' annual funding that they directed to small businesses in 
fiscal year 2004. In contrast, the contractor at the Lawrence Livermore 
National Laboratory in California, which conducts work similar to that 
of the two New Mexico laboratories, ranked much lower--27th among the 
34 contractors. Contractor and DOE officials with whom we met suggested 
reasons for such differences in performances, for example, differences 
in the availability of small businesses that are capable of providing 
the needed goods and services or differences in the facility management 
contractors' commitment to providing small businesses with the maximum 
practicable opportunity to participate in the work. 

Furthermore, actions by DOE to increase its direct, or prime, 
contracting with small businesses may reduce the subcontracting 
opportunities available for small businesses. For example, in an effort 
to increase the amount of prime contract dollars going to small 
businesses, in 2003, DOE redirected around $30 million of work from the 
facility management contract for managing and operating the Strategic 
Petroleum Reserve in Louisiana and awarded it as a separate prime 
contract to a small business. Before DOE redirected the work, a 
contractor official said that the facility management contractor 
responsible for performing the work had been subcontracting most of it 
to small businesses. The official further stated that, as a result, DOE 
and the facility management contractor negotiated a lower small 
business subcontracting goal for fiscal year 2004 of 27.7 percent of 
the total dollars subcontracted, representing a 21.3 percent drop from 
the 49 percent goal at the end of fiscal year 2003. Although the 
facility management contractor exceeded its subcontracting goal in 
fiscal year 2004, the total dollars available for subcontracting 
decreased by around 12 percent ($6.1 million), and the portion going to 
small businesses decreased by 9.3 percent ($1.8 million). 

Because the subcontracting achievement data that DOE relies on does not 
provide a true picture of the facility management contractors' 
performance in small business subcontracting, the department cannot 
meaningfully use those data to monitor performance. Without data 
providing a truer picture of contractors' performance, DOE lacks a 
basis for knowing whether differences in performance truly exist. 
Moreover, the department also lacks a basis for understanding whether 
differences in performance are legitimate--such as stemming from the 
types of work performed under a facility management contract--or are 
the result of differences in contractors' level of commitment to small 
business subcontracting. 

Having recognized potential weaknesses in contractor-reported 
achievement data, at least one federal agency we contacted is taking a 
more innovative approach for using data to monitor subcontracting 
efforts.[Footnote 11] The National Aeronautics and Space Administration 
(NASA), for internal management purposes, calculates small business 
subcontracting goals and achievements for its prime contractors as a 
percentage of the annual funding for the prime contracts. NASA's small 
business office said it uses this method to oversee contractor 
performance because it (1) presents a truer picture of actual 
achievements and (2) provides a better basis to evaluate a contractor's 
maximum practicable opportunity to subcontract with small businesses. 
This office said the data the contractors report to SBA can be 
misleading, in that a large percentage achievement can be reported even 
though a relatively small amount of dollars may actually be going to 
small business subcontracts. 

Although DOE continues to base its facility management contractors' 
subcontracting goals on the total dollars subcontracted, for at least 
one of those contractors, the department's Environmental Management 
program plans to use a small business subcontracting approach that is 
similar to NASA's approach. During a recent solicitation for bids for 
an environmental cleanup contract at the Hanford Site's River Corridor 
Project in Washington State, the program's solicitation specified that 
the winning bidder must subcontract 60 percent of work under the 
approximately $2 billion contract, with half of that directed to small 
businesses, or potentially about $600 million over the 7-year life of 
the contract. According to proposal documents, Environmental Management 
took this approach in part because of input from small businesses and 
because it would better ensure that small businesses had an opportunity 
to participate in a significant portion of the work under the contract. 

DOE Oversight of Small Business Subcontracting by Facility Management 
Contractors Was Not Adequate to Address Identified Problems with 
Contractor-Reported Data: 

DOE had not taken adequate steps to address known problems with the 
small business subcontracting achievement data reported by its facility 
management contractors. Because misleading achievement data gave the 
appearance of a successful small business subcontracting program, DOE 
officials did not closely monitor facility management contractors' 
subcontracting practices or follow through to ensure that the 
contractors complied with SBA reporting guidelines. DOE's reliance on 
misleading data also resulted in a lack of assurance that the facility 
management contractors were providing the maximum practicable 
opportunities for small business subcontracting. The inadequate 
oversight was due, in part, to a lack of clear guidance on how DOE's 
various headquarters and field organizations should coordinate and 
integrate their efforts to effectively oversee the small business 
subcontracting program. 

Reliance on Misleading Data Undermined DOE's Oversight: 

DOE knew there were problems with the data reported by the facility 
management contractors but did not take adequate corrective action. 
This had several undesirable consequences: (1) it created the false 
impression that DOE was meeting its small business subcontracting 
goals, (2) it caused errors in recognizing and rewarding contractor 
performance, and (3) it undermined efforts to ensure that facility 
management contractors were providing the maximum practicable 
subcontracting opportunities for small businesses. 

False impression that DOE was meeting its small business subcontracting 
goals. The misleading data that DOE was using gave the appearance of a 
successful small business subcontracting program. As a result, DOE 
officials were not inclined to closely monitor facility management 
contractors' subcontracting practices or to fully address known 
problems with the achievement data. DOE officials in the small business 
and procurement offices told us that they recognized in 2002 that the 
facility management contractors were not consistently following SBA 
guidelines on what subcontracts could be excluded when calculating 
small business subcontracting goals and achievements. In April 2002, 
DOE's Small Business Office provided clarifying information in an e- 
mail message to small business program managers both in the DOE program 
offices and the facility management contractors. The information 
emphasized the importance of consistently following SBA guidelines. 
Although DOE provided subsequent training for small business program 
managers, DOE officials did not take adequate steps to ensure that the 
contractors were correctly applying SBA guidelines. Based on our 
analysis of fiscal year 2004 subcontracting practices, none of the 34 
facility management contractors fully complied with the SBA guidelines. 

In some cases, DOE actually approved the incorrect reporting practices 
by its facility management contractors. For example, we found 10 
instances where DOE had reviewed and approved subcontracting plans that 
specifically called for incorrectly excluding subcontracts from the 
calculations of small business subcontracting goals and achievements. 
In two other cases, the facility management contractors specified 
incorrect exclusions in annual planning documents for fiscal year 2004. 
DOE uses these planning documents to evaluate overall contractor 
performance for the year. DOE contracting officers told us that they 
had approved or allowed the incorrect practices because they did not 
believe these subcontracts could practically go to small businesses 
anyway. For example, the facility management contractors may have had 
existing long-term subcontracts with large businesses to provide 
information technology assistance, building maintenance, or other site 
support services. 

Recent program reviews by DOE's Small Business Office were also not 
sufficient to identify and rectify these incorrect practices. In 
September 2002, the Secretary directed the Small Business Office to 
develop a strategic plan for providing maximum practicable 
opportunities to small businesses, including subcontracting by facility 
management contractors. As part of its May 2003 strategic plan, the 
Small Business Office stated that it would periodically review the 
small business subcontracting efforts of the facility management 
contractors. During fiscal year 2004, the Small Business Office 
performed reviews of the small business subcontracting programs at five 
of DOE's facility management contractors. These reviews focused 
primarily on determining if the small business subcontracting plans 
contained the information required by federal regulations and whether 
the contractors met their annual small business subcontracting goals. 
The reviews did not evaluate how the facility management contractors 
were developing the annual small business subcontracting goals or 
whether all appropriate subcontracts were included in the goal and 
achievement calculations. DOE Small Business Office officials told us 
that, based on the results of our work, they are considering revising 
their review methodology to include these steps. 

In March 2005, near the end of our review, DOE and NNSA procurement 
organizations issued additional guidance on small business contracting 
goals. The guidance stressed that the accuracy of contractor-reported 
data was vital to the credibility of the department's performance in 
small business subcontracting. The guidance emphasized that, in 
calculating and reporting small business subcontracting goals and 
achievements, contractors could exclude only the subcontract types 
allowed by SBA guidelines. The guidance further states that contracting 
officers shall ensure that facility management contractors are aware of 
these procedures and do not apply additional exclusions when developing 
their subcontracting goals. However, given DOE's oversight of these 
practices in the past, it remains to be seen whether DOE will now 
follow through and ensure that facility management contractors comply 
with this guidance. 

Errors in recognizing and rewarding contractor performance. DOE's Small 
Business Office established a Secretarial Small Business Awards program 
to recognize and acknowledge outstanding performance on an annual 
basis. One of these awards--the facility management contractor small 
business achievement award--is presented each year to the facility 
management contractor with the highest percentage increase in 
subcontract awards to small businesses from the previous year. 

We reviewed the facility management contractor small business 
achievement awards DOE presented in fiscal years 2003 and 2004. 
Although the fiscal year 2003 award appears to be appropriate, the 
fiscal year 2004 award went to a facility management contractor who 
directed fewer dollars to small businesses from one year to the next. 
Specifically, the data DOE used to make the determination showed that 
the percentage of subcontracting dollars going to small businesses 
increased from 61 percent in fiscal year 2002 to 66 percent in fiscal 
year 2003, a 5 percentage point increase. However, during the same 
period, the total dollars subcontracted by the facility management 
contractor dropped from $60.7 million to $52.1 million, and the 
subcontracting dollars directed to small businesses dropped from $36.8 
million to $34.4 million. If DOE had measured the change in the 
contractor's small business subcontracting achievements by comparing 
them with the annual funding on the facility management contract, DOE 
officials would have discovered that the contractor's performance 
actually declined by about 7 percent during the period (from 19.7 
percent of annual funding on the contract to 13.0 percent). DOE Small 
Business Office officials told us that they based this award on 
increases in the percentage of subcontracting dollars going to small 
businesses rather than changes in the total dollars directed to small 
businesses. Officials said using changes in total dollars directed to 
small businesses would not be fair to all the contractors because the 
facility management contractors with multibillion dollar annual funding 
on their contracts would have an advantage in showing increased dollars 
to small businesses. While we agree that using dollars to compare the 
performance among contractors could favor those with greater annual 
funding, relying solely on the percentage of subcontracted dollars 
going to small businesses may result in rewarding declining 
performance, as demonstrated above. 

Undermined efforts to ensure maximum practicable opportunities for 
small businesses. DOE's reliance on misleading data created an 
environment in which DOE officials were not inclined to closely monitor 
the small business subcontracting program. For example, DOE allowed 
facility management contractors to incorrectly exclude subcontracts 
when calculating their small business subcontracting achievements, 
which led to the incorrect perception that they were achieving their 
subcontracting goals. Without accurate and consistent data on the 
subcontracting efforts of the facility management contractors, DOE has 
no way of determining whether a facility management contractor is 
providing the maximum practicable opportunity for small businesses. 

Another consequence of these program weaknesses is a perception among 
members of the small business community that DOE's facility management 
contractors could do better at providing opportunities for meaningful 
subcontracting work. This perception has led to distrust and criticism 
of DOE's facility management contractors by small business associations 
and advocates. For example, during a May 2004 congressional hearing on 
DOE's direct contracting with small businesses, small business advocacy 
groups raised concerns about whether the level of subcontracting by DOE 
facility management contractors reflected maximum practicable 
opportunities.[Footnote 12] Additionally, small business associations 
have expressed concerns about what they perceive as unfair treatment by 
DOE facility management contractors, such as using small business 
subcontractors to perform work that provides little opportunity for the 
small business to develop technical capabilities. Small business 
advocacy groups that we contacted said that if DOE held the facility 
management contractors more accountable for achieving small business 
subcontracting results, such as by using data that provided a truer 
picture of actual performance, the small business groups would have a 
basis for greater confidence in DOE's small business subcontracting 
program. 

Oversight Responsibilities for the Small Business Subcontracting 
Program Were Not Clearly Defined or Integrated: 

DOE officials did not address problems with the small business 
subcontracting program, in part, because the various headquarters and 
field organizations that must work together to provide oversight of the 
small business subcontracting program did not do so effectively. 
Oversight of facility management contractors' small business 
subcontracting efforts includes reviewing and approving facility 
management contractors' small business subcontracting plans and annual 
goals, monitoring the contractors' progress toward achieving small 
business subcontracting goals, and taking action when necessary to 
ensure that the contractors meet their small business subcontracting 
goals. 

Although DOE contracting officers have final responsibility for 
providing direction to the facility management contractors on all 
aspects of DOE contracts, other DOE headquarters and field offices, 
such as the Small Business Office and the program offices, share 
responsibilities for monitoring and overseeing the small business 
subcontracting activities of facility management contractors. DOE 
contracting officers, usually located at DOE field locations, have 
primary responsibility for communicating with facility management 
contractors on all aspects of the contracts, including the contractors' 
small business subcontracting efforts.[Footnote 13] DOE's Small 
Business Office has the overall responsibility for managing the 
department's small business programs and monitoring performance toward 
meeting annual goals. Since the Small Business Office has no direct 
authority over DOE's facility management contractors, it coordinates 
the subcontracting program efforts by using small business program 
managers within DOE's program offices and field locations. The small 
business program managers at the field locations review subcontracting 
plans and annual goals, and they provide input to the contracting 
officers. 

Effective oversight requires more than just carrying out these 
activities, but also collectively ensuring that the activities identify 
and correct problems and that program goals are achieved. Effective 
oversight was not happening, in part, because DOE guidance does not 
clearly define the roles, responsibilities, and needed interaction of 
the various headquarters and field organizations involved. DOE guidance 
on the small business program clearly defines only the roles of the 
contracting officer, which include review of small business 
subcontracting plans, annual goals, and reported achievements. The 
guidance also states that the contracting officer is responsible for 
ensuring that facility management contractors comply with the SBA 
guidelines on which subcontracts may be excluded from their 
subcontracting goals and achievements. However, the guidance does not 
clearly define roles or responsibilities for the Small Business Office, 
small business program managers, or others who need to coordinate their 
efforts to achieve department goals.[Footnote 14] Absent this guidance, 
we found that the collective efforts of these officials were not 
sufficient to identify and correct the problems discussed in this 
report or to ensure that program goals were being achieved. 

Conclusions: 

Creating opportunities for small businesses to participate in providing 
goods and services to DOE's facility management contractors supports 
federal policy and produces benefits for both DOE and the small 
business community. Because about 85 percent of DOE's funding currently 
goes to its facility management contractors, none of which are small 
businesses, the small business subcontracting efforts of those facility 
management contractors are of even greater importance to DOE. However, 
misleading data has created the false impression that DOE is meeting 
its small business subcontracting goals, undermined DOE's oversight of 
subcontracting efforts, and generated mistrust among members of the 
small business community. Furthermore, DOE actions to date have not 
adequately addressed problems with misleading data. Until the problems 
with contractor-reported achievement data are resolved and the program 
oversight issues are addressed, DOE cannot ensure that the federal 
policy of providing the maximum practicable opportunity for small 
businesses is being achieved. 

Recommendations for Executive Action: 

To ensure that facility management contractors comply with SBA 
guidelines and follow a consistent practice for calculating and 
reporting small business subcontracting goals and achievements, we 
recommend that the Secretary of Energy direct the appropriate officials 
responsible for DOE's Small Business Office and procurement 
organizations to ensure, through regular oversight and review 
activities, that facility management contractors comply with DOE's 
March 2005 guidance on small business procurement goals. 

To ensure that DOE has useful data for managing its small business 
subcontracting program and for measuring and comparing contractors' 
performance in pursuing the maximum practicable opportunity for small 
business subcontracting, we recommend the Secretary of Energy direct 
the appropriate officials responsible for DOE's Small Business Office 
and procurement organizations to use, for internal management purposes, 
data on facility management contractors' annual small business 
subcontracting achievements calculated as a percentage of the obligated 
dollars facility management contractors received that year on their 
contract with DOE. 

To improve DOE's oversight of the small business subcontracting program 
and to provide the maximum practicable opportunity for small businesses 
to subcontract at DOE sites, we recommend that the Secretary of Energy 
take steps to strengthen oversight of the program, including issuing 
guidance clarifying the roles, responsibilities, and necessary 
interactions among DOE small business office, program office, and 
procurement officials responsible for managing the small business 
subcontracting program. 

Agency Comments: 

We provided a draft of this report to DOE for review and comment. In 
written comments the Secretary of Energy generally agreed with the 
report and two of the recommendations but disagreed with one of the 
recommendations. The department agreed with our recommendation to 
strengthen oversight of its small business subcontracting program. DOE 
said that it is in the process of revising existing guidance to clarify 
oversight roles and responsibilities and the necessary coordination and 
integration of oversight efforts between DOE headquarters and field 
organizations. 

The department also agreed with our recommendation to ensure that the 
facility management contractors follow a consistent practice for 
calculating and reporting their small business subcontracting goals and 
achievements, as outlined in DOE's March 2005 guidance. In its 
comments, DOE outlined several steps it had taken to provide training, 
clarifying information, and guidance on the importance of accurate and 
consistent small business subcontracting data. However, effective 
oversight requires more than providing guidance and training. We 
believe that regular review and oversight activities will also be 
necessary to verify that contractors are complying with the guidance. 

Regarding our recommendation that the department use data on its 
facility management contractors' small business subcontracting 
achievements--recalculated as a percentage of the dollars obligated on 
their prime contract--to internally manage its program, DOE disagreed 
with the recommendation and proposed to continue calculating the 
achievements as a percentage of the total dollars subcontracted. While 
we agree that DOE should continue to follow SBA guidance for SBA 
reporting purposes, we continue to believe that this calculation method 
fails to provide a true picture of the facility management contractors' 
small business subcontracting performance, which is necessary for 
effective oversight. As our report clearly demonstrated, the method can 
overstate the performance of contractors that devote a relatively small 
portion of their total contract to subcontracting. Thus, to ensure that 
DOE is providing the maximum practicable subcontracting opportunities 
to small businesses, for internal program management purposes, the 
department should use subcontracting achievement data calculated as a 
percentage of the facility management contract obligations. As 
described in our report, one of the department's programs intends to 
use this approach to internally manage the small business 
subcontracting goals and achievements for the $2 billion contract to 
clean up the Hanford Site's River Corridor in Washington State. 

DOE also provided technical comments on the facts presented in the 
report, which we incorporated as appropriate. DOE's comments and our 
responses are presented in appendix III. 

We conducted our review from June 2004 to April 2005, in accordance 
with generally accepted government auditing standards. Appendix II 
provides details on our scope and methodology. 

As arranged with your offices, unless you publicly announce its 
contents earlier, we plan no further distribution of this report until 
30 days after the date of this letter. At that time, we will send 
copies to the Secretary of Energy. We will also make copies available 
to others on request. In addition, the report will be available at no 
charge on the GAO Web site at http://www.gao.gov. 

If you or your staff have any questions on this report, please call me 
at (202) 512-3841. Other staff contributing to this report are listed 
in appendix IV. 

Signed by: 

Gene Aloise: 
Director, Natural Resources and Environment: 

[End of section]

Appendix I: DOE Facility Management Contractors' Annual Small Business 
Subcontracting Goals and Achievements: 

Facility management, contractor, and location: Battelle Memorial, 
Pacific Northwest National Laboratory, Wash. 

Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 47%; 
Subcontracting dollars to small businesses: $54,357,833; 
Total dollars subcontracted: $104,872,886; 
Subcontracting achievement (percent of total dollars subcontracted): 
51.8%; 
Annual funding received on the facility management contract: 
$421,791,076; 
Recalculated subcontracting achievement (percent of annual funding): 
12.9%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 47%; 
Subcontracting dollars to small businesses: $59,788,116; 
Total dollars subcontracted: $131,556,970; 
Subcontracting achievement (percent of total dollars subcontracted): 
45.5%; 
Annual funding received on the facility management contract: 
$470,448,150; 
Recalculated subcontracting achievement (percent of annual funding): 
12.7%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 47%; 
Subcontracting dollars to small businesses: $75,350,321; 
Total dollars subcontracted: $114,311,713; 
Subcontracting achievement (percent of total dollars subcontracted): 
65.9%; 
Annual funding received on the facility management contract: 
$555,727,382; 
Recalculated subcontracting achievement (percent of annual funding): 
13.6%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $81,388,171; 
Total dollars subcontracted: $133,912,552; 
Subcontracting achievement (percent of total dollars subcontracted): 
60.8%; 
Annual funding received on the facility management contract: 
$550,910,993; 
Recalculated subcontracting achievement (percent of annual funding): 
14.8%. 

Facility management, contractor, and location: Bechtel Bettis, Bettis 
Atomic Power Laboratory, Pa. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 30%; 
Subcontracting dollars to small businesses: $53,093,888; 
Total dollars subcontracted: $162,362,210; 
Subcontracting achievement (percent of total dollars subcontracted): 
32.7%; 
Annual funding received on the facility management contract: 
$342,340,000; 
Recalculated subcontracting achievement (percent of annual funding): 
15.5%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 30%; 
Subcontracting dollars to small businesses: $71,145,858; 
Total dollars subcontracted: $136,485,213; 
Subcontracting achievement (percent of total dollars subcontracted): 
52.1%; 
Annual funding received on the facility management contract: 
$343,972,000; 
Recalculated subcontracting achievement (percent of annual funding): 
20.7%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 30%; 
Subcontracting dollars to small businesses: $55,542,807; 
Total dollars subcontracted: $135,949,919; 
Subcontracting achievement (percent of total dollars subcontracted): 
40.9%; 
Annual funding received on the facility management contract: 
$334,771,000; 
Recalculated subcontracting achievement (percent of annual funding): 
16.6%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 35%; 
Subcontracting dollars to small businesses: $62,811,750; 
Total dollars subcontracted: $159,372,044; 
Subcontracting achievement (percent of total dollars subcontracted): 
39.4%; 
Annual funding received on the facility management contract: 
$381,767,479; 
Recalculated subcontracting achievement (percent of annual funding): 
16.5%. 

Facility management, contractor, and location: Bechtel BWXT Idaho, 
Idaho National Laboratory, Idaho
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 70%; 
Subcontracting dollars to small businesses: $123,469,383; 
Total dollars subcontracted: $171,069,181; 
Subcontracting achievement (percent of total dollars subcontracted): 
72.2%; 
Annual funding received on the facility management contract: 
$643,793,953; 
Recalculated subcontracting achievement (percent of annual funding): 
19.2%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $103,106,547; 
Total dollars subcontracted: $153,887,715; 
Subcontracting achievement (percent of total dollars subcontracted): 
67%; 
Annual funding received on the facility management contract: 
$681,960,071; 
Recalculated subcontracting achievement (percent of annual funding): 
15.1%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $100,852,558; 
Total dollars subcontracted: $155,992,132; 
Subcontracting achievement (percent of total dollars subcontracted): 
64.7%; 
Annual funding received on the facility management contract: 
$809,719,475; 
Recalculated subcontracting achievement (percent of annual funding): 
12.5%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $98,794,079; 
Total dollars subcontracted: $169,798,501; 
Subcontracting achievement (percent of total dollars subcontracted): 
58.2%; 
Annual funding received on the facility management contract: 
$775,716,116; 
Recalculated subcontracting achievement (percent of annual funding): 
12.7%. 

Facility management, contractor, and location: Bechtel Hanford, Hanford 
Site, Wash. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $18,287,757; 
Total dollars subcontracted: $34,632,902; 
Subcontracting achievement (percent of total dollars subcontracted): 
52.8%; 
Annual funding received on the facility management contract: 
$131,770,462; 
Recalculated subcontracting achievement (percent of annual funding): 
13.9%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $15,967,088; 
Total dollars subcontracted: $36,927,958; 
Subcontracting achievement (percent of total dollars subcontracted): 
43.2%; 
Annual funding received on the facility management contract: 
$127,488,208; 
Recalculated subcontracting achievement (percent of annual funding): 
12.5%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $13,210,454; 
Total dollars subcontracted: $35,202,892; 
Subcontracting achievement (percent of total dollars subcontracted): 
37.5%; 
Annual funding received on the facility management contract: 
$110,244,402; 
Recalculated subcontracting achievement (percent of annual funding): 
12%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $38,940,166; 
Total dollars subcontracted: $59,915,369; 
Subcontracting achievement (percent of total dollars subcontracted): 
65%; 
Annual funding received on the facility management contract: 
$133,563,675; 
Recalculated subcontracting achievement (percent of annual funding): 
29.2%. 

Facility management, contractor, and location: Bechtel Jacobs, Oak 
Ridge Site, Tenn. 

Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $134,014,921; 
Total dollars subcontracted: $292,351,969; 
Subcontracting achievement (percent of total dollars subcontracted): 
45.8%; 
Annual funding received on the facility management contract: 
$488,503,515; 
Recalculated subcontracting achievement (percent of annual funding): 
27.4%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 34%; 
Subcontracting dollars to small businesses: $142,094,257; 
Total dollars subcontracted: $335,397,251; 
Subcontracting achievement (percent of total dollars subcontracted): 
42.4%; 
Annual funding received on the facility management contract: 
$476,330,731; 
Recalculated subcontracting achievement (percent of annual funding): 
29.8%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 38%; 
Subcontracting dollars to small businesses: $140,783,155; 
Total dollars subcontracted: $358,596,321; 
Subcontracting achievement (percent of total dollars subcontracted): 
39.3%; 
Annual funding received on the facility management contract: 
$489,003,276; 
Recalculated subcontracting achievement (percent of annual funding): 
28.8%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 28%; 
Subcontracting dollars to small businesses: $116,441,561; 
Total dollars subcontracted: $299,533,583; 
Subcontracting achievement (percent of total dollars subcontracted): 
38.9%; 
Annual funding received on the facility management contract: 
$653,252,083; 
Recalculated subcontracting achievement (percent of annual funding): 
17.8%. 

Facility management, contractor, and location: Bechtel National, Waste 
Treatment Plant, Wash. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $34,590,534; 
Total dollars subcontracted: $53,276,882; 
Subcontracting achievement (percent of total dollars subcontracted): 
64.9%; 
Annual funding received on the facility management contract: 
$339,471,427; 
Recalculated subcontracting achievement (percent of annual funding): 
10.2%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $122,452,585; 
Total dollars subcontracted: $217,707,111; 
Subcontracting achievement (percent of total dollars subcontracted): 
56.3%; 
Annual funding received on the facility management contract: 
$646,035,709; 
Recalculated subcontracting achievement (percent of annual funding): 
19%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $167,633,416; 
Total dollars subcontracted: $290,642,324; 
Subcontracting achievement (percent of total dollars subcontracted): 
57.7%; 
Annual funding received on the facility management contract: 
$653,965,320; 
Recalculated subcontracting achievement (percent of annual funding): 
25.6%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $196,320,937; 
Total dollars subcontracted: $301,003,381; 
Subcontracting achievement (percent of total dollars subcontracted): 
65.2%; 
Annual funding received on the facility management contract: 
$675,301,802; 
Recalculated subcontracting achievement (percent of annual funding): 
29.1%. 

Facility management, contractor, and location: Bechtel Nevada, Nevada 
Test Site, Nev. 

Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $54,888,245; 
Total dollars subcontracted: $85,069,821; 
Subcontracting achievement (percent of total dollars subcontracted): 
64.5%; 
Annual funding received on the facility management contract: 
$287,008,003; 
Recalculated subcontracting achievement (percent of annual funding): 
19.1%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $56,746,250; 
Total dollars subcontracted: $83,089,259; 
Subcontracting achievement (percent of total dollars subcontracted): 
68.3%; 
Annual funding received on the facility management contract: 
$409,298,787; 
Recalculated subcontracting achievement (percent of annual funding): 
13.9%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 62%; 
Subcontracting dollars to small businesses: $83,639,885; 
Total dollars subcontracted: $121,103,349; 
Subcontracting achievement (percent of total dollars subcontracted): 
69.1%; 
Annual funding received on the facility management contract: 
$434,472,175; 
Recalculated subcontracting achievement (percent of annual funding): 
19.3%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 62%; 
Subcontracting dollars to small businesses: $95,085,821; 
Total dollars subcontracted: $134,734,610; 
Subcontracting achievement (percent of total dollars subcontracted): 
70.6%; 
Annual funding received on the facility management contract: 
$464,972,914; 
Recalculated subcontracting achievement (percent of annual funding): 
20.5%. 

Facility management, contractor, and location: Bechtel SAIC, Yucca 
Mountain Project, Nev. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $22,607,401; 
Total dollars subcontracted: $42,993,104; 
Subcontracting achievement (percent of total dollars subcontracted): 
52.6%; 
Annual funding received on the facility management contract: 
$173,504,003; 
Recalculated subcontracting achievement (percent of annual funding): 
13%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $36,779,883; 
Total dollars subcontracted: $60,749,142; 
Subcontracting achievement (percent of total dollars subcontracted): 
60.5%; 
Annual funding received on the facility management contract: 
$187,150,369; 
Recalculated subcontracting achievement (percent of annual funding): 
19.7%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $34,363,154; 
Total dollars subcontracted: $52,122,410; 
Subcontracting achievement (percent of total dollars subcontracted): 
65.9%; 
Annual funding received on the facility management contract: 
$265,198,002; 
Recalculated subcontracting achievement (percent of annual funding): 
13%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $60,965,967; 
Total dollars subcontracted: $106,904,609; 
Subcontracting achievement (percent of total dollars subcontracted): 
57%; 
Annual funding received on the facility management contract: 
$300,692,496; 
Recalculated subcontracting achievement (percent of annual funding): 
20.3%. 

Facility management, contractor, and location: Brookhaven Science 
Associates, Brookhaven National Laboratory, N.Y. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $55,169,181; 
Total dollars subcontracted: $96,259,669; 
Subcontracting achievement (percent of total dollars subcontracted): 
57.3%; 
Annual funding received on the facility management contract: 
$453,190,513; 
Recalculated subcontracting achievement (percent of annual funding): 
12.2%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $69,726,716; 
Total dollars subcontracted: $127,327,687; 
Subcontracting achievement (percent of total dollars subcontracted): 
54.8%; 
Annual funding received on the facility management contract: 
$460,076,142; 
Recalculated subcontracting achievement (percent of annual funding): 
15.2%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $62,610,576; 
Total dollars subcontracted: $108,708,417; 
Subcontracting achievement (percent of total dollars subcontracted): 
57.6%; 
Annual funding received on the facility management contract: 
$440,919,419; 
Recalculated subcontracting achievement (percent of annual funding): 
14.2%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $58,257,687; 
Total dollars subcontracted: $101,331,077; 
Subcontracting achievement (percent of total dollars subcontracted): 
57.5%; 
Annual funding received on the facility management contract: 
$422,891,497; 
Recalculated subcontracting achievement (percent of annual funding): 
13.8%. 

Facility management, contractor, and location: BWXT Pantex, Pantex 
Facility, Tex. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $36,294,115; 
Total dollars subcontracted: $57,583,576; 
Subcontracting achievement (percent of total dollars subcontracted): 
63%; 
Annual funding received on the facility management contract: 
$329,219,350; 
Recalculated subcontracting achievement (percent of annual funding): 
11%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $72,514,853; 
Total dollars subcontracted: $97,829,311; 
Subcontracting achievement (percent of total dollars subcontracted): 
74.1%; 
Annual funding received on the facility management contract: 
$404,242,527; 
Recalculated subcontracting achievement (percent of annual funding): 
17.9%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $74,018,228; 
Total dollars subcontracted: $99,218,150; 
Subcontracting achievement (percent of total dollars subcontracted): 
74.6%; 
Annual funding received on the facility management contract: 
$424,131,223; 
Recalculated subcontracting achievement (percent of annual funding): 
17.5%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $92,587,654; 
Total dollars subcontracted: $115,264,030; 
Subcontracting achievement (percent of total dollars subcontracted): 
80.3%; 
Annual funding received on the facility management contract: 
$437,236,858; 
Recalculated subcontracting achievement (percent of annual funding): 
21.2%. 

Facility management, contractor, and location: BWXT Y-12, Y-12 National 
Security Complex, Tenn. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 40%; 
Subcontracting dollars to small businesses: $69,072,392; 
Total dollars subcontracted: $130,070,576; 
Subcontracting achievement (percent of total dollars subcontracted): 
53.1%; 
Annual funding received on the facility management contract: 
$889,855,250; 
Recalculated subcontracting achievement (percent of annual funding): 
7.8%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $88,579,725; 
Total dollars subcontracted: $139,672,095; 
Subcontracting achievement (percent of total dollars subcontracted): 
63.4%; 
Annual funding received on the facility management contract: 
$574,888,585; 
Recalculated subcontracting achievement (percent of annual funding): 
15.4%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $86,985,976; 
Total dollars subcontracted: $140,627,195; 
Subcontracting achievement (percent of total dollars subcontracted): 
61.9%; 
Annual funding received on the facility management contract: 
$707,392,050; 
Recalculated subcontracting achievement (percent of annual funding): 
12.3%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 63%; 
Subcontracting dollars to small businesses: $114,442,560; 
Total dollars subcontracted: $171,568,241; 
Subcontracting achievement (percent of total dollars subcontracted): 
66.7%; 
Annual funding received on the facility management contract: 
$675,042,163; 
Recalculated subcontracting achievement (percent of annual funding): 
17%. 

Facility management, contractor, and location: CH2M Hill Hanford, 
Hanford Site, Wash. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 32%; 
Subcontracting dollars to small businesses: $36,726,618; 
Total dollars subcontracted: $106,629,667; 
Subcontracting achievement (percent of total dollars subcontracted): 
34.4%; 
Annual funding received on the facility management contract: 
$380,827,936; 
Recalculated subcontracting achievement (percent of annual funding): 
9.6%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 36%; 
Subcontracting dollars to small businesses: $59,584,936; 
Total dollars subcontracted: $92,552,044; 
Subcontracting achievement (percent of total dollars subcontracted): 
64.4%; 
Annual funding received on the facility management contract: 
$277,569,297; 
Recalculated subcontracting achievement (percent of annual funding): 
21.5%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $55,134,273; 
Total dollars subcontracted: $114,819,210; 
Subcontracting achievement (percent of total dollars subcontracted): 
48%; 
Annual funding received on the facility management contract: 
$363,753,927; 
Recalculated subcontracting achievement (percent of annual funding): 
15.2%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $103,529,585; 
Total dollars subcontracted: $172,878,788; 
Subcontracting achievement (percent of total dollars subcontracted): 
59.9%; 
Annual funding received on the facility management contract: 
$342,276,389; 
Recalculated subcontracting achievement (percent of annual funding): 
30.3%. 

Facility management, contractor, and location: CH2M Hill Mound, Mound 
Site, Ohioa 
Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 62%; 
Subcontracting dollars to small businesses: $10,158,519; 
Total dollars subcontracted: $20,966,482; 
Subcontracting achievement (percent of total dollars subcontracted): 
48.5%; 
Annual funding received on the facility management contract: 
$85,566,434; 
Recalculated subcontracting achievement (percent of annual funding): 
11.9%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 62%; 
Subcontracting dollars to small businesses: $12,064,809; 
Total dollars subcontracted: $33,408,204; 
Subcontracting achievement (percent of total dollars subcontracted): 
36.1%; 
Annual funding received on the facility management contract: 
$100,904,523; 
Recalculated subcontracting achievement (percent of annual funding): 
12%. 

Facility management, contractor, and location: DynMcDermott Petroleum 
Operations, Strategic Petroleum Reserve, La. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $24,470,589; 
Total dollars subcontracted: $51,250,166; 
Subcontracting achievement (percent of total dollars subcontracted): 
47.8%; 
Annual funding received on the facility management contract: 
$119,355,167; 
Recalculated subcontracting achievement (percent of annual funding): 
20.5%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 47%; 
Subcontracting dollars to small businesses: $37,801,131; 
Total dollars subcontracted: $79,267,315; 
Subcontracting achievement (percent of total dollars subcontracted): 
47.7%; 
Annual funding received on the facility management contract: 
$158,111,114; 
Recalculated subcontracting achievement (percent of annual funding): 
23.9%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 49.0b%; 
Subcontracting dollars to small businesses: $19,475,303; 
Total dollars subcontracted: $51,608,283; 
Subcontracting achievement (percent of total dollars subcontracted): 
37.7%; 
Annual funding received on the facility management contract: 
$156,520,402; 
Recalculated subcontracting achievement (percent of annual funding): 
12.4%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 27.7b%; 
Subcontracting dollars to small businesses: $17,655,913; 
Total dollars subcontracted: $45,487,040; 
Subcontracting achievement (percent of total dollars subcontracted): 
38.8%; 
Annual funding received on the facility management contract: 
$109,940,228; 
Recalculated subcontracting achievement (percent of annual funding): 
16.1%. 

Facility management, contractor, and location: Fluor Fernald, Fernald 
Closure Project, Ohio 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $25,068,949; 
Total dollars subcontracted: $64,304,653; 
Subcontracting achievement (percent of total dollars subcontracted): 
39%; 
Annual funding received on the facility management contract: 
$287,185,818; 
Recalculated subcontracting achievement (percent of annual funding): 
8.7%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $59,830,146; 
Total dollars subcontracted: $108,034,504; 
Subcontracting achievement (percent of total dollars subcontracted): 
55.4%; 
Annual funding received on the facility management contract: 
$227,425,087; 
Recalculated subcontracting achievement (percent of annual funding): 
26.3%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 36%; 
Subcontracting dollars to small businesses: $68,038,876; 
Total dollars subcontracted: $170,975,046; 
Subcontracting achievement (percent of total dollars subcontracted): 
39.8%; 
Annual funding received on the facility management contract: 
$317,787,501; 
Recalculated subcontracting achievement (percent of annual funding): 
21.4%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 36.8%; 
Subcontracting dollars to small businesses: $57,402,853; 
Total dollars subcontracted: $171,172,293; 
Subcontracting achievement (percent of total dollars subcontracted): 
33.5%; 
Annual funding received on the facility management contract: 
$323,951,180; 
Recalculated subcontracting achievement (percent of annual funding): 
17.7%. 

Facility management, contractor, and location: Fluor Hanford, Hanford 
Site, Wash. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 38%; 
Subcontracting dollars to small businesses: $88,065,808; 
Total dollars subcontracted: $165,445,464; 
Subcontracting achievement (percent of total dollars subcontracted): 
53.2%; 
Annual funding received on the facility management contract: 
$634,136,465; 
Recalculated subcontracting achievement (percent of annual funding): 
13.9%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $76,600,234; 
Total dollars subcontracted: $158,177,744; 
Subcontracting achievement (percent of total dollars subcontracted): 
48.4%; 
Annual funding received on the facility management contract: 
$646,094,972; 
Recalculated subcontracting achievement (percent of annual funding): 
11.9%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 34%; 
Subcontracting dollars to small businesses: $93,676,386; 
Total dollars subcontracted: $169,044,664; 
Subcontracting achievement (percent of total dollars subcontracted): 
55.4%; 
Annual funding received on the facility management contract: 
$663,332,198; 
Recalculated subcontracting achievement (percent of annual funding): 
14.1%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 40%; 
Subcontracting dollars to small businesses: $97,261,252; 
Total dollars subcontracted: $186,626,708; 
Subcontracting achievement (percent of total dollars subcontracted): 
52.1%; 
Annual funding received on the facility management contract: 
$702,003,969; 
Recalculated subcontracting achievement (percent of annual funding): 
13.9%. 

Facility management, contractor, and location: Honeywell Federal 
Manufacturing & Technologies, Kansas City Plant, Mo. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 39.6%; 
Subcontracting dollars to small businesses: $79,894,524; 
Total dollars subcontracted: $156,636,154; 
Subcontracting achievement (percent of total dollars subcontracted): 
51%; 
Annual funding received on the facility management contract: 
$461,742,878; 
Recalculated subcontracting achievement (percent of annual funding): 
17.3%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 43.6%; 
Subcontracting dollars to small businesses: $78,418,650; 
Total dollars subcontracted: $150,710,281; 
Subcontracting achievement (percent of total dollars subcontracted): 
52%; 
Annual funding received on the facility management contract: 
$444,906,343; 
Recalculated subcontracting achievement (percent of annual funding): 
17.6%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $95,707,764; 
Total dollars subcontracted: $163,478,172; 
Subcontracting achievement (percent of total dollars subcontracted): 
58.5%; 
Annual funding received on the facility management contract: 
$477,229,514; 
Recalculated subcontracting achievement (percent of annual funding): 
20.1%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 50.4%; 
Subcontracting dollars to small businesses: $109,887,925; 
Total dollars subcontracted: $193,471,624; 
Subcontracting achievement (percent of total dollars subcontracted): 
56.8%; 
Annual funding received on the facility management contract: 
$473,410,852; 
Recalculated subcontracting achievement (percent of annual funding): 
23.2%. 

Facility management, contractor, and location: Iowa State University, 
Ames Laboratory, Iowa 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $2,646,192; 
Total dollars subcontracted: $4,101,321; 
Subcontracting achievement (percent of total dollars subcontracted): 
64.5%; 
Annual funding received on the facility management contract: 
$24,840,396; 
Recalculated subcontracting achievement (percent of annual funding): 
10.7%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $3,454,193; 
Total dollars subcontracted: $5,279,121; 
Subcontracting achievement (percent of total dollars subcontracted): 
65.4%; 
Annual funding received on the facility management contract: 
$30,371,174; 
Recalculated subcontracting achievement (percent of annual funding): 
11.4%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $2,752,123; 
Total dollars subcontracted: $4,557,186; 
Subcontracting achievement (percent of total dollars subcontracted): 
60.4%; 
Annual funding received on the facility management contract: 
$23,839,727; 
Recalculated subcontracting achievement (percent of annual funding): 
11.5%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $3,012,140; 
Total dollars subcontracted: $5,311,183; 
Subcontracting achievement (percent of total dollars subcontracted): 
56.7%; 
Annual funding received on the facility management contract: 
$31,619,046; 
Recalculated subcontracting achievement (percent of annual funding): 
9.5%. 

Facility management, contractor, and location: Kaiser-Hill, Rocky Flats 
Closure Project, Colo. 

Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 28%; 
Subcontracting dollars to small businesses: $162,257,410; 
Total dollars subcontracted: $563,299,072; 
Subcontracting achievement (percent of total dollars subcontracted): 
28.8%; 
Annual funding received on the facility management contract: 
$628,143,478; 
Recalculated subcontracting achievement (percent of annual funding): 
25.8%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 28%; 
Subcontracting dollars to small businesses: $264,673,600; 
Total dollars subcontracted: $584,969,258; 
Subcontracting achievement (percent of total dollars subcontracted): 
45.3%; 
Annual funding received on the facility management contract: 
$650,955,392; 
Recalculated subcontracting achievement (percent of annual funding): 
40.7%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 32%; 
Subcontracting dollars to small businesses: $176,490,595; 
Total dollars subcontracted: $500,214,847; 
Subcontracting achievement (percent of total dollars subcontracted): 
35.3%; 
Annual funding received on the facility management contract: 
$676,926,087; 
Recalculated subcontracting achievement (percent of annual funding): 
26.1%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 32%; 
Subcontracting dollars to small businesses: $115,112,878; 
Total dollars subcontracted: $346,231,264; 
Subcontracting achievement (percent of total dollars subcontracted): 
33.3%; 
Annual funding received on the facility management contract: 
$645,566,636; 
Recalculated subcontracting achievement (percent of annual funding): 
17.8%. 

Facility management, contractor, and location: KAPL, Inc., Knolls 
Atomic Power Laboratory, N.Y. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 30%; 
Subcontracting dollars to small businesses: $41,862,997; 
Total dollars subcontracted: $120,798,260; 
Subcontracting achievement (percent of total dollars subcontracted): 
34.7%; 
Annual funding received on the facility management contract: 
$269,009,235; 
Recalculated subcontracting achievement (percent of annual funding): 
15.6%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 30%; 
Subcontracting dollars to small businesses: $32,610,006; 
Total dollars subcontracted: $109,724,015; 
Subcontracting achievement (percent of total dollars subcontracted): 
29.7%; 
Annual funding received on the facility management contract: 
$258,475,000; 
Recalculated subcontracting achievement (percent of annual funding): 
12.6%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 30%; 
Subcontracting dollars to small businesses: $33,006,151; 
Total dollars subcontracted: $105,297,202; 
Subcontracting achievement (percent of total dollars subcontracted): 
31.4%; 
Annual funding received on the facility management contract: 
$277,624,659; 
Recalculated subcontracting achievement (percent of annual funding): 
11.9%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 30%; 
Subcontracting dollars to small businesses: $46,460,851; 
Total dollars subcontracted: $127,753,113; 
Subcontracting achievement (percent of total dollars subcontracted): 
36.4%; 
Annual funding received on the facility management contract: 
$416,417,286; 
Recalculated subcontracting achievement (percent of annual funding): 
11.2%. 

Facility management, contractor, and location: Lockheed Martin, Sandia 
National Laboratories, N. Mex. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $360,026,522; 
Total dollars subcontracted: $517,397,711; 
Subcontracting achievement (percent of total dollars subcontracted): 
69.6%; 
Annual funding received on the facility management contract: 
$1,612,890,671; 
Recalculated subcontracting achievement (percent of annual funding): 
22.3%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $387,917,485; 
Total dollars subcontracted: $694,278,857; 
Subcontracting achievement (percent of total dollars subcontracted): 
55.9%; 
Annual funding received on the facility management contract: 
$1,851,953,436; 
Recalculated subcontracting achievement (percent of annual funding): 
21%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $458,883,711; 
Total dollars subcontracted: $866,283,746; 
Subcontracting achievement (percent of total dollars subcontracted): 
53%; 
Annual funding received on the facility management contract: 
$2,027,314,032; 
Recalculated subcontracting achievement (percent of annual funding): 
22.6%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $486,348,399; 
Total dollars subcontracted: $973,878,609; 
Subcontracting achievement (percent of total dollars subcontracted): 
49.9%; 
Annual funding received on the facility management contract: 
$2,259,983,950; 
Recalculated subcontracting achievement (percent of annual funding): 
21.5%. 

Facility management, contractor, and location: Midwest Research 
Institute, National Renewable Energy Laboratory, Colo. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $56,987,818; 
Total dollars subcontracted: $81,181,977; 
Subcontracting achievement (percent of total dollars subcontracted): 
70.2%; 
Annual funding received on the facility management contract: 
$214,696,696; 
Recalculated subcontracting achievement (percent of annual funding): 
26.5%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $46,934,755; 
Total dollars subcontracted: $70,828,281; 
Subcontracting achievement (percent of total dollars subcontracted): 
66.3%; 
Annual funding received on the facility management contract: 
$211,027,075; 
Recalculated subcontracting achievement (percent of annual funding): 
22.2%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $52,932,233; 
Total dollars subcontracted: $81,724,746; 
Subcontracting achievement (percent of total dollars subcontracted): 
64.8%; 
Annual funding received on the facility management contract: 
$229,855,701; 
Recalculated subcontracting achievement (percent of annual funding): 
23%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $48,276,350; 
Total dollars subcontracted: $72,503,042; 
Subcontracting achievement (percent of total dollars subcontracted): 
66.6%; 
Annual funding received on the facility management contract: 
$212,381,970; 
Recalculated subcontracting achievement (percent of annual funding): 
22.7%. 

Facility management, contractor, and location: Princeton University, 
Princeton Plasma Physics Laboratory, N.J. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 52%; 
Subcontracting dollars to small businesses: $9,925,776; 
Total dollars subcontracted: $14,701,621; 
Subcontracting achievement (percent of total dollars subcontracted): 
67.5%; 
Annual funding received on the facility management contract: 
$74,149,076; 
Recalculated subcontracting achievement (percent of annual funding): 
13.4%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 52%; 
Subcontracting dollars to small businesses: $8,043,427; 
Total dollars subcontracted: $10,670,803; 
Subcontracting achievement (percent of total dollars subcontracted): 
75.4%; 
Annual funding received on the facility management contract: 
$74,716,992; 
Recalculated subcontracting achievement (percent of annual funding): 
10.8%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $5,928,245; 
Total dollars subcontracted: $7,905,233; 
Subcontracting achievement (percent of total dollars subcontracted): 
75%; 
Annual funding received on the facility management contract: 
$68,961,918; 
Recalculated subcontracting achievement (percent of annual funding): 
8.6%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $9,901,358; 
Total dollars subcontracted: $11,895,244; 
Subcontracting achievement (percent of total dollars subcontracted): 
83.2%; 
Annual funding received on the facility management contract: 
$77,635,828; 
Recalculated subcontracting achievement (percent of annual funding): 
12.8%. 

Facility management, contractor, and location: Southeastern 
Universities Research Association, Thomas Jefferson National 
Accelerator Facility, Va. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $22,966,248; 
Total dollars subcontracted: $36,869,558; 
Subcontracting achievement (percent of total dollars subcontracted): 
62.3%; 
Annual funding received on the facility management contract: 
$106,312,598; 
Recalculated subcontracting achievement (percent of annual funding): 
21.6%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $23,663,361; 
Total dollars subcontracted: $41,217,369; 
Subcontracting achievement (percent of total dollars subcontracted): 
57.4%; 
Annual funding received on the facility management contract: 
$108,275,952; 
Recalculated subcontracting achievement (percent of annual funding): 
21.9%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $16,561,882; 
Total dollars subcontracted: $25,653,401; 
Subcontracting achievement (percent of total dollars subcontracted): 
64.6%; 
Annual funding received on the facility management contract: 
$98,731,409; 
Recalculated subcontracting achievement (percent of annual funding): 
16.8%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $18,697,871; 
Total dollars subcontracted: $37,285,236; 
Subcontracting achievement (percent of total dollars subcontracted): 
50.1%; 
Annual funding received on the facility management contract: 
$113,896,732; 
Recalculated subcontracting achievement (percent of annual funding): 
16.4%. 

Facility management, contractor, and location: Stanford University, 
Stanford Linear Accelerator Center, Calif. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $31,172,615; 
Total dollars subcontracted: $51,630,433; 
Subcontracting achievement (percent of total dollars subcontracted): 
60.4%; 
Annual funding received on the facility management contract: 
$204,122,243; 
Recalculated subcontracting achievement (percent of annual funding): 
15.3%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 56%; 
Subcontracting dollars to small businesses: $28,252,330; 
Total dollars subcontracted: $51,405,657; 
Subcontracting achievement (percent of total dollars subcontracted): 
55%; 
Annual funding received on the facility management contract: 
$210,650,537; 
Recalculated subcontracting achievement (percent of annual funding): 
13.4%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 57.5%; 
Subcontracting dollars to small businesses: $39,451,555; 
Total dollars subcontracted: $62,778,071; 
Subcontracting achievement (percent of total dollars subcontracted): 
62.8%; 
Annual funding received on the facility management contract: 
$230,864,436; 
Recalculated subcontracting achievement (percent of annual funding): 
17.1%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 56%; 
Subcontracting dollars to small businesses: $39,419,478; 
Total dollars subcontracted: $66,461,098; 
Subcontracting achievement (percent of total dollars subcontracted): 
59.3%; 
Annual funding received on the facility management contract: 
$250,900,104; 
Recalculated subcontracting achievement (percent of annual funding): 
15.7%. 

Facility management, contractor, and location: Universities Research 
Association, Fermi National Accelerator Laboratory, Ill. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $44,450,000; 
Total dollars subcontracted: $91,872,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
48.4%; 
Annual funding received on the facility management contract: 
$307,997,017; 
Recalculated subcontracting achievement (percent of annual funding): 
14.4%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $45,862,000; 
Total dollars subcontracted: $87,820,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
52.2%; 
Annual funding received on the facility management contract: 
$309,200,090; 
Recalculated subcontracting achievement (percent of annual funding): 
14.8%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $39,552,000; 
Total dollars subcontracted: $77,990,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
50.7%; 
Annual funding received on the facility management contract: 
$316,292,588; 
Recalculated subcontracting achievement (percent of annual funding): 
12.5%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $45,284,000; 
Total dollars subcontracted: $71,268,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
63.5%; 
Annual funding received on the facility management contract: 
$316,519,364; 
Recalculated subcontracting achievement (percent of annual funding): 
14.3%. 

Facility management, contractor, and location: University of 
California, Lawrence Berkeley National Laboratory, Calif. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 51.8%; 
Subcontracting dollars to small businesses: $60,364,815; 
Total dollars subcontracted: $129,655,264; 
Subcontracting achievement (percent of total dollars subcontracted): 
46.6%; 
Annual funding received on the facility management contract: 
$471,669,387; 
Recalculated subcontracting achievement (percent of annual funding): 
12.8%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 51.8%; 
Subcontracting dollars to small businesses: $61,485,715; 
Total dollars subcontracted: $157,523,278; 
Subcontracting achievement (percent of total dollars subcontracted): 
39%; 
Annual funding received on the facility management contract: 
$471,786,072; 
Recalculated subcontracting achievement (percent of annual funding): 
13%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 34%; 
Subcontracting dollars to small businesses: $48,337,720; 
Total dollars subcontracted: $114,788,499; 
Subcontracting achievement (percent of total dollars subcontracted): 
42.1%; 
Annual funding received on the facility management contract: 
$456,533,356; 
Recalculated subcontracting achievement (percent of annual funding): 
10.6%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 32%; 
Subcontracting dollars to small businesses: $63,686,742; 
Total dollars subcontracted: $170,154,503; 
Subcontracting achievement (percent of total dollars subcontracted): 
37.4%; 
Annual funding received on the facility management contract: 
$397,451,166; 
Recalculated subcontracting achievement (percent of annual funding): 
16%. 

Facility management, contractor, and location: University of 
California, Lawrence Livermore National Laboratory, Calif. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $168,927,591; 
Total dollars subcontracted: $423,235,849; 
Subcontracting achievement (percent of total dollars subcontracted): 
39.9%; 
Annual funding received on the facility management contract: 
$1,389,055,837; 
Recalculated subcontracting achievement (percent of annual funding): 
12.2%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $182,167,689; 
Total dollars subcontracted: $497,929,164; 
Subcontracting achievement (percent of total dollars subcontracted): 
36.6%; 
Annual funding received on the facility management contract: 
$1,562,149,121; 
Recalculated subcontracting achievement (percent of annual funding): 
11.7%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 35%; 
Subcontracting dollars to small businesses: $175,743,871; 
Total dollars subcontracted: $470,886,313; 
Subcontracting achievement (percent of total dollars subcontracted): 
37.3%; 
Annual funding received on the facility management contract: 
$1,556,259,049; 
Recalculated subcontracting achievement (percent of annual funding): 
11.3%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 35%; 
Subcontracting dollars to small businesses: $204,297,721; 
Total dollars subcontracted: $520,668,966; 
Subcontracting achievement (percent of total dollars subcontracted): 
39.2%; 
Annual funding received on the facility management contract: 
$1,589,252,698; 
Recalculated subcontracting achievement (percent of annual funding): 
12.9%. 

Facility management, contractor, and location: University of 
California, Los Alamos National Laboratory, N. Mex. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 35%; 
Subcontracting dollars to small businesses: $314,500,000; 
Total dollars subcontracted: $846,300,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
37.2%; 
Annual funding received on the facility management contract: 
$2,056,138,764; 
Recalculated subcontracting achievement (percent of annual funding): 
15.3%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 42%; 
Subcontracting dollars to small businesses: $431,300,000; 
Total dollars subcontracted: $1,072,100,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
40.2%; 
Annual funding received on the facility management contract: 
$1,968,726,402; 
Recalculated subcontracting achievement (percent of annual funding): 
21.9%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 42%; 
Subcontracting dollars to small businesses: $370,700,000; 
Total dollars subcontracted: $854,600,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
43.4%; 
Annual funding received on the facility management contract: 
$1,984,708,594; 
Recalculated subcontracting achievement (percent of annual funding): 
18.7%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 42%; 
Subcontracting dollars to small businesses: $371,100,000; 
Total dollars subcontracted: $843,200,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
44%; 
Annual funding received on the facility management contract: 
$1,876,507,610; 
Recalculated subcontracting achievement (percent of annual funding): 
19.8%. 

Facility management, contractor, and location: University of Chicago, 
Argonne National Laboratory, Ill. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $66,709,921; 
Total dollars subcontracted: $127,394,963; 
Subcontracting achievement (percent of total dollars subcontracted): 
52.4%; 
Annual funding received on the facility management contract: 
$498,328,731; 
Recalculated subcontracting achievement (percent of annual funding): 
13.4%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $66,089,187; 
Total dollars subcontracted: $120,411,075; 
Subcontracting achievement (percent of total dollars subcontracted): 
54.9%; 
Annual funding received on the facility management contract: 
$530,767,915; 
Recalculated subcontracting achievement (percent of annual funding): 
12.5%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $65,525,795; 
Total dollars subcontracted: $120,451,914; 
Subcontracting achievement (percent of total dollars subcontracted): 
54.4%; 
Annual funding received on the facility management contract: 
$525,415,187; 
Recalculated subcontracting achievement (percent of annual funding): 
12.5%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $70,362,618; 
Total dollars subcontracted: $152,980,199; 
Subcontracting achievement (percent of total dollars subcontracted): 
46%; 
Annual funding received on the facility management contract: 
$585,987,022; 
Recalculated subcontracting achievement (percent of annual funding): 
12%. 

Facility management, contractor, and location: UT Battelle, Oak Ridge 
National Laboratory, Tenn. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $68,303,840; 
Total dollars subcontracted: $141,080,341; 
Subcontracting achievement (percent of total dollars subcontracted): 
48.4%; 
Annual funding received on the facility management contract: 
$667,887,413; 
Recalculated subcontracting achievement (percent of annual funding): 
10.2%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 43%; 
Subcontracting dollars to small businesses: $91,435,096; 
Total dollars subcontracted: $185,694,443; 
Subcontracting achievement (percent of total dollars subcontracted): 
49.2%; 
Annual funding received on the facility management contract: 
$849,633,299; 
Recalculated subcontracting achievement (percent of annual funding): 
10.8%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $118,547,793; 
Total dollars subcontracted: $219,013,040; 
Subcontracting achievement (percent of total dollars subcontracted): 
54.1%; 
Annual funding received on the facility management contract: 
$807,960,210; 
Recalculated subcontracting achievement (percent of annual funding): 
14.7%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $170,389,081; 
Total dollars subcontracted: $271,744,455; 
Subcontracting achievement (percent of total dollars subcontracted): 
62.7%; 
Annual funding received on the facility management contract: 
$1,005,411,132; 
Recalculated subcontracting achievement (percent of annual funding): 
17%. 

Facility management, contractor, and location: Washington TRU 
Solutions, Waste Isolation Pilot Plant, N. Mex. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 75%; 
Subcontracting dollars to small businesses: $20,291,938; 
Total dollars subcontracted: $26,456,431; 
Subcontracting achievement (percent of total dollars subcontracted): 
76.7%; 
Annual funding received on the facility management contract: 
$111,360,499; 
Recalculated subcontracting achievement (percent of annual funding): 
18.2%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 75%; 
Subcontracting dollars to small businesses: $33,534,321; 
Total dollars subcontracted: $44,576,023; 
Subcontracting achievement (percent of total dollars subcontracted): 
75.2%; 
Annual funding received on the facility management contract: 
$118,905,751; 
Recalculated subcontracting achievement (percent of annual funding): 
28.2%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 75%; 
Subcontracting dollars to small businesses: $38,629,035; 
Total dollars subcontracted: $45,053,723; 
Subcontracting achievement (percent of total dollars subcontracted): 
85.7%; 
Annual funding received on the facility management contract: 
$124,985,758; 
Recalculated subcontracting achievement (percent of annual funding): 
30.9%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 60%; 
Subcontracting dollars to small businesses: $39,136,122; 
Total dollars subcontracted: $44,500,492; 
Subcontracting achievement (percent of total dollars subcontracted): 
88%; 
Annual funding received on the facility management contract: 
$140,432,118; 
Recalculated subcontracting achievement (percent of annual funding): 
27.9%. 

Facility management, contractor, and location: West Valley Nuclear 
Services, West Valley Demonstration Project, N.Y. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 46%; 
Subcontracting dollars to small businesses: $22,445,717; 
Total dollars subcontracted: $36,359,853; 
Subcontracting achievement (percent of total dollars subcontracted): 
61.7%; 
Annual funding received on the facility management contract: 
$95,636,099; 
Recalculated subcontracting achievement (percent of annual funding): 
23.5%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $32,013,652; 
Total dollars subcontracted: $45,896,861; 
Subcontracting achievement (percent of total dollars subcontracted): 
69.8%; 
Annual funding received on the facility management contract: 
$91,345,339; 
Recalculated subcontracting achievement (percent of annual funding): 
35.1%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 55%; 
Subcontracting dollars to small businesses: $21,906,883; 
Total dollars subcontracted: $37,503,459; 
Subcontracting achievement (percent of total dollars subcontracted): 
58.4%; 
Annual funding received on the facility management contract: 
$95,835,513; 
Recalculated subcontracting achievement (percent of annual funding): 
22.9%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 45%; 
Subcontracting dollars to small businesses: $26,661,695; 
Total dollars subcontracted: $40,088,050; 
Subcontracting achievement (percent of total dollars subcontracted): 
66.5%; 
Annual funding received on the facility management contract: 
$93,272,276; 
Recalculated subcontracting achievement (percent of annual funding): 
28.6%. 

Facility management, contractor, and location: Westinghouse Savannah 
River, Savannah River Site, S.C. 
Fiscal year: FY 2001; 
Subcontracting goal (percent of total dollars subcontracted): 50%; 
Subcontracting dollars to small businesses: $193,000,000; 
Total dollars subcontracted: $367,000,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
52.6%; 
Annual funding received on the facility management contract: 
$1,498,224,335; 
Recalculated subcontracting achievement (percent of annual funding): 
12.9%; 

Fiscal year: FY 2002; 
Subcontracting goal (percent of total dollars subcontracted): 48%; 
Subcontracting dollars to small businesses: $171,800,000; 
Total dollars subcontracted: $298,000,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
57.7%; 
Annual funding received on the facility management contract: 
$1,419,323,559; 
Recalculated subcontracting achievement (percent of annual funding): 
12.1%; 

Fiscal year: FY 2003; 
Subcontracting goal (percent of total dollars subcontracted): 51%; 
Subcontracting dollars to small businesses: $169,700,000; 
Total dollars subcontracted: $291,000,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
58.3%; 
Annual funding received on the facility management contract: 
$1,478,654,637; 
Recalculated subcontracting achievement (percent of annual funding): 
11.5%; 

Fiscal year: FY 2004; 
Subcontracting goal (percent of total dollars subcontracted): 51%; 
Subcontracting dollars to small businesses: $109,500,000; 
Total dollars subcontracted: $188,900,000; 
Subcontracting achievement (percent of total dollars subcontracted): 
58%; 
Annual funding received on the facility management contract: 
$1,452,022,082; 
Recalculated subcontracting achievement (percent of annual funding): 
7.5%. 

Source: GAO analysis of DOE and facility management contractor data. 

Note: The subcontracting achievements--both as a percent of total 
dollars subcontracted and as a percent of annual funding--presented in 
this table have not been adjusted to include any subcontracts that the 
facility management contractors incorrectly excluded from their 
calculations because we did not know the dollar value of the 
incorrectly excluded subcontracts for all 34 contractors. 

[A] We omitted subcontracting goal and achievement data for DOE's Mound 
Site in Ohio for fiscal years 2001 and 2002, because the contractor 
that managed and operated the site in 2001 and 2002 is not the same 
contractor that did so from 2003 through the duration of our study. 
While we included subcontracting achievement data from the previous 
contractor in the aggregated data for all facility management 
contractors in table 1, we did not include those data in this appendix 
because the fiscal year 2001 and 2002 data for the Mound Site came from 
a different source than the rest of the subcontracting goal and 
achievement data in this appendix. As a result, we had not assessed the 
reliability of the fiscal year 2001 and 2002 data for the Mound Site to 
be able to publish the contractor-level subcontracting goal and 
achievement data. 

[B] The facility management contractor managing and operating the 
Strategic Petroleum Reserve had a small business subcontracting goal of 
47.0 percent for the first half of fiscal year 2003, but the goal was 
increased to 49.0 percent for the second half of the fiscal year, after 
the contractor was awarded a new facility management contract with DOE 
for the same site, and they negotiated a new subcontracting goal. 
However, for fiscal year 2004, the contractor's subcontracting goal 
dropped to 27.7 percent. According to a contractor official, DOE and 
the contractor renegotiated the lower goal after DOE removed about $30 
million of work from the facility management contract in fiscal year 
2003. The facility management contractor had been subcontracting a 
majority of that work to small business subcontractors. 

[End of table]

[End of section]

Appendix II: Scope and Methodology: 

We determined (1) the usefulness of the data reported by the Department 
of Energy's (DOE) facility management contractors for monitoring 
contractor performance in small business subcontracting and (2) the 
actions that DOE has taken to address any problems identified with its 
facility management contractors' small business subcontracting efforts. 
To conduct our work, we contacted DOE and contractor officials, as well 
as representatives from the Small Business Administration (SBA) and 
from small-business advocacy groups. We also collected data from all 34 
of DOE's facility management contracts on their subcontracting 
activities and took steps to assess the reliability of the contractors' 
data, which included reviews of subcontracting files at 13 of the 34 
contractors. 

Determining the Usefulness of the Facility Management Contractor- 
Reported Data: 

To determine the usefulness of the facility management contractor- 
reported data for DOE monitoring purposes, we requested data from DOE's 
34 facility management contractors on their annual small business 
subcontracting goals and achievements. Specifically, we asked the 
contractors to provide the subcontracting percentage-goals that they 
negotiated with DOE for fiscal years 2001 through 2004, as well as the 
dollar figures comprising those percentages, including the total 
dollars to be subcontracted during the year and the portion of 
subcontracting dollars they expected would go to small 
businesses.[Footnote 15] We also asked the contractors to provide us 
with their subcontracting percentage achievements for fiscal years 2001 
through 2004 and the dollar figures comprising those percentages-- 
namely, the total dollars that were subcontracted and the small 
business subcontracting dollars. (Selected subcontracting goal and 
achievement data appear in app. I.) Additionally, in our data request, 
we asked the contractors to identify the types of subcontracts that 
they included or excluded from their small business subcontracting 
goals and achievements for fiscal year 2004. Furthermore, we requested 
copies of the contractors' small business subcontracting plans that 
were in effect during fiscal year 2004. 

We used a data collection instrument to obtain data from the facility 
management contractors on their fiscal year 2001 through 2004 small 
business subcontracting goals and achievements. In the data collection 
instrument, we provided tables for the contractors to enter their 
subcontracting information, and we included instructions on how to 
complete the tables. The data collection instrument also included a 
series of questions on various aspects of the reliability of the data 
they provided, as part of our assessment of data reliability described 
later in this appendix. 

Because we received the requested information from all 34 of DOE's 
facility management contractors, we did not rely on results from any 
subset of those contractors to conduct our analysis and, therefore, no 
sampling error is associated with our work. However, data gathering 
methods, such as the ones we used, may introduce error into the data 
that is not associated with statistical sampling, commonly referred to 
as nonsampling errors. For example, difficulties in how a particular 
instruction was interpreted, in the availability of the information 
requested, and in how the data were entered into the tables could 
introduce unwanted variation into the data collected. We took steps in 
the development of the data collection instrument to minimize these 
nonsampling errors. For example, we pretested a draft of the data 
collection instrument with 3 facility management contractors. In 
addition, we provided the draft to 5 knowledgeable small business and 
procurement officials in DOE headquarters. Within GAO the data 
collection instrument was reviewed by the Office of General Counsel and 
by experts in federal contracting and research methodology. We modified 
the data collection instrument as appropriate to reflect the comments 
and suggestions of the contractor, DOE, and GAO reviewers, and sent the 
data collection instrument to all 34 of DOE's facility management 
contractors. We received responses from all 34 contractors. 

We then assessed the reliability of the subcontracting data we received 
from each of the 34 facility management contractors. To assess the data 
reliability, we (1) analyzed the contractors' responses to the data 
reliability questions that were included in the data collection 
instrument and (2) conducted a more detailed review of subcontract 
files at 13 of the 34 contractors. 

First, we reviewed the contractors' responses to the series of data 
reliability questions in the data collection instrument, which 
addressed such areas as data entry, data access, quality control 
procedures, and data accuracy and completeness. Follow-up questions 
were added as necessary. In consultation with a GAO expert in research 
methodology, we analyzed the contractors' responses for weaknesses in 
data reliability that would make their data unusable for analysis and 
reporting purposes. In their responses, 7 of the 34 contractors 
discussed minor limitations to their data control processes that might 
affect how the data should be interpreted. For example, 3 contractors 
stated that their subcontracting data was both accurate and complete, 
while noting that it was such to the extent that they could make it. 
Another contractor reported that the data it provided for fiscal years 
2001 and 2002 may be less accurate than the data for fiscal years 2003 
and 2004, because prior to 2003, the contractor did not require that 
its small business subcontractors self-certify or provide documents 
that verify their small business status. 

Second, we visited a nonprobability sample[Footnote 16] of 13 of the 34 
facility management contractors to conduct a more detailed assessment 
of the reliability of the fiscal year 2004 subcontracting achievement 
data that they provided in response to our data collection instrument. 
We used several criteria to select facility management contractors for 
site visits, including a contractors' association with DOE's three 
largest component organizations--Environmental Management, the National 
Nuclear Security Administration (NNSA), and the Office of Science--as 
well as geographic location, and the type of work performed under the 
facility management contract. The three DOE component organizations we 
focused on control 30 of DOE's 34 facility management contracts, and 
their annual budgets account for over 70 percent of DOE's overall 
budget. In selecting NNSA contractors, we chose both research 
laboratories and weapons production facilities, to ensure inclusion of 
the types of work that NNSA uses to carry out its missions. In 
addition, to obtain geographically diverse cases, we selected 
contractors from four states in the Western U.S.--California, Nevada, 
New Mexico, and Washington--and one Eastern state, Tennessee. Nearly 
one-half of the 34 DOE facility management contractors are located 
within these five states. 

Based on these selection criteria, we made visits to the following 13 
facility management contractors: 

Battelle Memorial, Pacific Northwest National Laboratory, Wash; 
Bechtel Hanford, Hanford Site, Wash; 
Bechtel Jacobs, Oak Ridge Site, Tenn; 
Bechtel National, Waste Treatment Plant, Wash;
Bechtel Nevada, Nevada Test Site, Nev; 
Bechtel SAIC, Yucca Mountain Project, Nev; 
BWXT Y-12, Y-12 National Security Complex, Tenn; 
CH2M Hill Hanford, Hanford Site, Wash; 
Fluor Hanford, Hanford Site, Wash; 
Lockheed Martin, Sandia National Laboratories, N. Mex; 
University of California, Lawrence Livermore National Laboratory, 
Calif; 
University of California, Los Alamos National Laboratory, N. Mex; 
and UT Battelle, Oak Ridge National Laboratory, Tenn. 

Collectively, these 13 contractors had subcontracts worth about $4.2 
billion in fiscal year 2004 (or 64.2 percent of the total 
subcontracting dollars for all 34 facility management contractors). Of 
that amount, over $2.1 billion went to small businesses, accounting for 
nearly two-thirds of the almost $3.3 billion in subcontract dollars 
that the 34 contractors directed to small businesses that year. 

During our visits to these 13 facility management contractors, we 
looked at the reliability of the fiscal year 2004 small business 
subcontracting achievement data that the contractors provided in the 
data collection instrument. Even though our data covered fiscal years 
2001 through 2004, for our more detailed review of data reliability, we 
focused on fiscal year 2004, because we performed most of our analyses 
on data from that year. 

Although individual contractors may manage thousands of small business 
subcontracts in a given year, for each of the 13 contractors, we chose 
separate nonprobability samples of 5 small business subcontracts--for a 
total of 65 subcontracts--that the facility management contractors had 
included in the fiscal year 2004 small business subcontracting 
achievements. We selected each nonprobability sample from a complete 
list of the contractors' fiscal year 2004 small business subcontracts, 
which we obtained prior to visiting the contractors. The criteria we 
used for selecting contracts was the subcontract amount and the goods 
and services provided. We selected subcontracts that received among the 
largest dollar commitments in fiscal year 2004 and that encompassed a 
variety of the types of goods and services provided by small business 
subcontractors. In total, the 65 subcontracts in our nonprobability 
samples accounted for 17.2 percent ($368.1 million) of the $2.1 billion 
dollars committed to small business subcontracts in fiscal year 2004 by 
the 13 facility management contractors. 

At each contractor's facility, we reviewed documents for each of the 
five subcontracts, in order to verify the dollar commitments to those 
subcontracts in fiscal year 2004, that the contractor included in their 
response to the data collection instrument. We also reviewed any 
documents certifying the small business status of those subcontractors 
at the time the subcontracts were awarded. In addition, to understand 
the effect of excluding certain subcontracts from the contractors' 
small business subcontracting achievement calculations, these 13 
contractors provided us with data on the dollar amount of their 
excluded subcontracts in fiscal year 2004. 

For all 65 of the small business subcontracts we reviewed, we were able 
to verify through documents in the subcontract files that the amount of 
dollars committed to the selected subcontracts in fiscal year 2004 
equaled the dollar amounts that the facility management contractors had 
taken credit for when reporting their small business subcontracting 
achievements for that year. Also, for 63 of the selected subcontracts, 
we were able to find documents that certified the subcontractor's 
status as a small business at the time the subcontract was awarded. 
However, for the 2 remaining subcontracts--which were from 2 different 
facility management contractors--documents showed that the 
subcontractors had been classified as large businesses at the time the 
subcontract was awarded.[Footnote 17] Therefore, these 2 subcontracts 
should not have been reflected in those contractors' fiscal year 2004 
subcontracting achievements as small business subcontracts. Because 
this only occurred with 3 percent of the 65 subcontracts (representing 
5.7 percent of the total $368.1 million value of those subcontracts), 
we did not consider it to be a material weakness of the subcontracting 
achievement data. In both instances where facility management 
contractors had mistakenly included a large business subcontract in 
their small business subcontracting achievements, the contractors 
subsequently restated their fiscal year 2004 subcontracting 
achievements.[Footnote 18] The subcontracting achievement data included 
in this report reflect the restated amounts. 

Based on all of our efforts to assess data reliability, we believe that 
the data are sufficiently reliable for characterizing the 34 facility 
management contractors' fiscal year 2004 small business subcontracting 
achievements. 

Determining Actions Taken by DOE to Address Problems: 

To determine the actions that DOE has taken to address any problems 
identified with its facility management contractors' small business 
subcontracting efforts, we visited officials at the nonprobability 
sample of 13 of the 34 facility management contractors previously 
described. We also met with the field-based DOE small business 
officials and contracting officers responsible for overseeing the 
facility management contractors' performance in small business 
subcontracting. 

In addition to our site visits, in DOE's headquarters we interviewed 
officials from DOE's Small Business Office and small business officials 
from the major component organizations, as well as DOE and NNSA 
procurement officials, to learn about their role and actions for 
overseeing the facility management contractors' small business 
subcontracting efforts. From these officials, we obtained policy 
guidance, results of field reviews, and other documents related to DOE 
and NNSA's oversight activities. We also interviewed headquarters and 
field-based officials from SBA's Office of Government Contracting to 
further understand SBA guidelines for contractor reporting of small 
business subcontracting data. Furthermore, we spoke with 
representatives from three small business advocacy groups--the East 
Tennessee Environmental Business Association, the New Mexico 8(a) and 
Minority Business Association, and the Small Environmental Business 
Action Coalition. 

We conducted our work from June 2004 to April 2005 in accordance with 
generally accepted government auditing standards. 

[End of section]

Appendix III: Comments from the Department of Energy: 

Note: GAO comments supplementing those in the report text appear at the 
end of this appendix. 

The Secretary of Energy: 
Washington, DC 20585:

May 3, 2005:

Mr. William R. Swick, Assistant Director: 
Natural Resources and Environment: 
U.S. Government Accountability Office: 
701 5th Avenue, Suite 2700:
Seattle, Washington 98104:

Dear Mr. Swick:

The Department of Energy (DOE) has reviewed the draft report entitled 
Department of Energy: Improved Oversight Could Better Ensure 
Opportunities for Small Business Subcontracting (GAO-05-459).

The attached comments reflect DOE's position with regard to the report 
findings and recommendations. The comments fall into three categories: 
"technical comments," "substantive comments," and Recommendations for 
Executive Action. We respectfully request that the substantive comments 
and the Recommendation for Executive Action be included in the appendix 
to the final report and that the technical comments be used to make 
needed corrections to the report.

As regards the specific recommendations of the report, DOE concurs with 
the recommendations. With regard to recommendations one and three for 
strengthening oversight of the subcontracting program and for ensuring 
regular oversight and reviews of facility management contractors, DOE 
has begun the process of implementing these recommendations through the 
issuance of several documents and directives. In reference to 
recommendation two, the department proposes to continue to capture its 
award information based on the guidance provided by SBA that reflects 
small business subcontract awards as a percentage of the subcontract 
base; and not of the total contract.

In June of this year we will be hosting the 6Th Annual DOE Small 
Business Conference and will be providing training for all small 
business and contracting staff as well as DOE contractors in attendance 
on small business procurement goals.

Should you have any questions regarding the DOE response, please 
contact:

Ms. Theresa Speake, Director of the Office of Small and Disadvantaged 
Business Utilization at (202) 586-8383.

Sincerely,

Signed by: 

Samuel W. Bodman:

Enclosure:

DOE COMMENTS ON GAO DRAFT REPORT (05-459)
DEPARTMENT OF ENERGY: IMPROVED OVERSIGHT COULD BETTER DENSURE 
OPPORTUNITIES FOR SMALL BUSINESS SUBCONTRACTING:

Substantive Comments:

On the Highlights Page the GAO has stated that "DOE has not taken 
adequate steps to address known problems with the contractor-reported 
data." They further state that DOE officials became aware in 2002 that 
contractors were not following federal guidelines...[and] failed to 
ensure that the guidelines were being followed..." Additionally, the 
GAO states that "DOE has not clearly defined the roles, 
responsibilities and needed interaction of the various headquarters and 
field organizations...."

DOE has taken numerous actions to address these issues. Specifically, 
these actions include the provision of written guidance by the OSDBU to 
the field in mid 2002, numerous meetings with both internal procurement 
and small business staff and external contractors to specifically 
discuss small business goaling and reporting requirements beginning in 
August of 2003 and running through December 2004. In May of 2004 DOE 
issued Acquisition Letter 2004-03 which improving the accuracy of small 
business information including conforming to the SBA document, Goaling 
Guidelines for the Small Business Preference programs for Prime and 
Subcontract Federal Procurement Goals & Achievements. In December of 
2004, a video was prepared (which is available on-line) providing 
information on small business subcontracting, including the 
establishment of subcontract bases, subcontracting goals and specific 
requirements for subcontracting plans as established in FAR 19.704. 

To ensure the accuracy of contractor-reported data and the 
implementation of these guidelines, OSDBU has completed subcontract 
reviews of five DOE prime contractors and has planned additional 
reviews. 

2) On pages 8 & 9 the GAO has stated that "...even if the facility 
management correctly reporting their small business contracting 
achievements, the methods for calculating those achievements does not 
provide a true picture of contractors' performance. The method can make 
the contractor appear to be performing well--for example, by directing 
80 percent subcontracting dollars annually to small businesses-when, in 
fact, that percentage is based on a small amount of dollars."

The Small Business Act and the Federal Acquisition Regulations that 
cover all Federal agencies/departments do not require a specific level 
of subcontracting for each subcontracting plan. The contractor is 
responsible for determining the level of work it will perform and the 
level it will subcontract. Once a subcontracting base is determined, 
small business goals become applicable against that level of work.

Since we compute the goals as percentage rather than dollars available 
for awards, any percentage of its total available subcontracting 
dollars to small business is in fact a true reflection of the 
contractors' actual performance.

3) On page 11, the GAO states that 13 contractors incorrectly excluded 
subcontracts from their reported achievements resulting in overstating 
those achievements by as much as $214 million, or 27 percent.

DOE is concerned that this statement could lead the reader to conclude 
that the dollars reported were not actually awarded to small business 
as claimed, which is not accurate. The dollar awards for small business 
are actual; although the percentage may vary because of the actual 
subcontract baseline. DOE requests that the GAO either remove the 
dollar reference or restructure the sentence to ensure that it 
clarifies that the dollars reported as awarded are actual.

4) On Page 10, the GAO states that all 34 of the contractors reported 
achievements incorrectly excluded other types of subcontracts, beyond 
what SBA guidelines allow. The statement goes on to state that 
"...contractors we visited generally told us it was their normal 
practice to make these types of exclusions... and that ...they were 
following their past practices...."

It should be noted that for the ten years prior to Fiscal Year 2000, 
the Department's facility management contractors' subcontracting 
activities were considered as prime contracts for the purpose of small 
business goaling and, therefore, had different exclusions than if they 
were subcontracts. These past practices support the reporting of 
exclusions as disclosed by these contractors to the GAO.

DOE has, however, noted in its most recent Acquisition Letter 2005-06 
that "DOE shall comply with the SBA's Goaling Guideline..." that spells 
out the specific exclusions for each type of contract. Furthermore the 
Acquisition Letter specifically identifies the two exclusions listed on 
the Standard Form SF 294 and SF 295 forms used for reporting 
subcontracts.

5) On page 20 the GAO attributes problems with DOE taking steps to take 
action to address known problems with subcontracting achievements to 
the inadequate oversight "...due, in part, to a lack of clear guidance 
on how DOE's various headquarters and field organizations should 
coordinate and integrate their efforts to effectively oversee the small 
business subcontracting programs."

DOE has an existing Acquisition Letter 2004-03 that addresses 
procedures that may not be sufficiently clear with regard to the 
coordination and integration of small business efforts between 
headquarters and the field. That Acquisition Letter is currently in the 
process of being rewritten to better define the role and 
responsibilities of the various parties. Additionally, training of 
small business managers and contracting officers throughout DOE is 
being planned for the DOE 6th Annual Small Business Conference to be 
held on June 12-15, 2005. Finally, all small business managers 
throughout the department (both at headquarters and in the field) are 
being provided a "desk manual" that contains all the applicable laws 
and regulations required for small business goaling, reporting and 
monitoring.

6) On Page 22 and 23 the GAO states that "In March 2005, near the end 
of our review, DOE and NNSA procurement organizations issued additional 
guidance on small business contracting goals. It remains to be seen 
whether DOE will now follow through and ensure that facility management 
contractors comply with this guidance."

DOE has established a process to establish its subcontracting goals as 
negotiated with SBA, and plans to follow through with its 
implementation.

7) In several places in the report the GAO states that, "more small 
business subcontracting is always better."

Whereas we agree with the GAO in principle that more subcontracting is 
always desirable, it is important to note that each contract varies 
significantly and requires its own separate review to determine what 
opportunities are available in a given year as well as determining the 
best contracting method to support the mission.

Technical Comment:

1) References to the Fiscal Year 2004 subcontract data are premature. 
No data has been submitted by the prime contractors to DOE or to the 
new eSRS system; therefore, DOE does not have this information and 
cannot verify the data in the report. Once the data is received, DOE 
will be able to respond as to its conformance with SBA's "baseline 
guidelines" issued in July 2003.

Recommendations for Executive Action:

1) Secretary of Energy direct the appropriate officials responsible for 
the DOE's Small Business Office and procurement organizations to 
ensure, through regular oversight and review activities, that facility 
management contractors comply with DOE's March 2005 guidance on small 
business procurement goals.

We note that DOE's Secretarial policy statement encourages the 
expansion of procurement opportunities for small business policy. As a 
result, the Department continues to enhance small business 
participation in both prime and subcontracting opportunities.

2) Secretary of Energy direct the appropriate officials responsible for 
the DOE's Small Business Office and procurement organizations to use, 
for internal management purposes, data on facility management 
contractors' annual small business subcontracting achievements 
calculated as a percentage of the obligated dollars facility management 
contractors received that year on their contract with DOE.

DOE disagrees with this recommendation. The department proposes to 
continue to capture its award information based on the guidance 
provided by SBA that reflects small business subcontract awards as a 
percentage of the subcontract base; and not of the total contract.

3) Secretary of Energy take steps to strengthen oversight of the 
program, including issuing guidance clarifying the roles, 
responsibilities, and necessary interactions among DOE small business 
office, program office, and procurement officials responsible for 
managing the small business subcontracting program.

DOE agrees with this recommendation. 

The following are GAO's comments on the Department of Energy's letter 
dated May 3, 2005. 

GAO Comments: 

1. We acknowledge in the draft report and highlights page that DOE had 
taken steps to address the problems with contractor-reported data, 
including issuing clarifying information in 2002 and additional 
guidance in March 2005. However, we stated that these steps had not 
been adequate to ensure that the facility management contractors were 
complying with the guidance. The draft report also stated that the 
reviews of the five facility management contractors performed by DOE's 
Small Business Office did not include an evaluation of whether the 
facility management contractors were following SBA guidelines for 
developing small business subcontracting goals. 

2. We agree that the Small Business Act and the Federal Acquisition 
Regulation do not require a specific level of subcontracting and that 
individual contractors determine the amount of work that will be 
subcontracted. The draft report reflects these two statements. However, 
we also stated in the draft report that if a contractor determines that 
only a small percentage of the work will be subcontracted, calculation 
of small business subcontracting achievements as a percentage of that 
percentage can be misleading. 

3. We agree and modified the final report. 

4. We modified the final report to acknowledge that prior to fiscal 
year 2000, DOE was able to include the small business subcontracting 
achievements of its facility management contractors toward the 
department's small business prime contracting goals. However, while it 
may have been an acceptable past practice for the facility management 
contractors to exclude more subcontracts under these conditions, the 
practice should have been discontinued in fiscal year 2000. 

5. In the draft report, we acknowledged that DOE is in the process of 
revising existing guidance to clarify oversight roles and 
responsibilities and the necessary coordination and integration of 
oversight efforts between DOE headquarters and field organizations. 

6. In the draft report, we stated that effective oversight of facility 
management contractors' practices for calculating and reporting their 
small business subcontracting goals and achievements will require more 
than providing guidance and training. We believe that regular oversight 
activities will also be necessary to verify that contractors are 
complying with this guidance. 

7. Our draft report does not state that "more small business 
subcontracting is always better." The draft report does discuss federal 
policy, set out in the Small Business Act, that small businesses shall 
have the maximum practicable opportunity to provide goods and services 
to the federal government and its contractors, consistent with 
efficient contract performance. The draft report also states that there 
can be several reasons for differences in contractors' small business 
subcontracting achievements, including type of work, contract 
performance goals, and changes in the annual funding for a contract. 

8. We disagree that the fiscal year 2004 subcontracting achievement 
data are premature. Although the facility management contractors have 
not yet submitted their fiscal year 2004 subcontracting reports to DOE, 
we obtained this data directly from the 34 facility management 
contractors so that we could include the most recent results in our 
report. We obtained fiscal year 2004 data after the end of the fiscal 
year so that it would reflect the final subcontracting activities for 
the year. We assessed the reliability of the data for accuracy and 
completeness (see app. II). In addition, in March 2005, we provided a 
statement of facts to the contractors for their review to ensure the 
accuracy of the information. 

9. DOE disagreed with our recommendation that, for internal management 
purposes, the department use data on its contractors' subcontracting 
achievements, calculated as a percentage of the dollars obligated to 
their prime contract with DOE. While the contractors should continue to 
report their subcontracting achievements as SBA requires, we continue 
to believe that, for internal management purposes, the data do not 
provide a true picture of their performance, which is necessary for the 
department to perform effective oversight. 

[End of section]

Appendix IV: GAO Contacts and Staff Acknowledgment: 

GAO Contacts: 

Gene Aloise, (202) 512-3841; 
William R. Swick, (206) 287-4851: 

Acknowledgments: 

In addition to the individuals named above, Carole Blackwell, Ellen 
Chu, John Delicath, Doreen Feldman, Dominic Nadarski, Judy Pagano, 
Laina Poon, Jeff Rueckhaus, and Ginny Vanderlinde made key 
contributions to this report. 

FOOTNOTES

[1] Federal subcontracting requirements pertain to small businesses 
both as an overall category and in terms of the various subcategories 
of small businesses that are defined in federal law, such as small 
disadvantaged businesses, women-or veteran-owned small businesses, and 
small businesses located in historically underutilized business zones. 
For this report, we examined DOE facility management contractors' 
activities in subcontracting with small businesses, as an overall 
category. We did not examine their subcontracting activities with 
respect to any of the subcategories of small businesses. 

[2] Small Business Administration, Office of Government Contracting, 
Goaling Guidelines for the Small Business Preference Programs: For 
Prime and Subcontract Federal Procurement Goals and Achievements 
(Washington, D.C.: July 3, 2003). 

[3] To meet this 40 percent government-wide goal, SBA negotiates annual 
subcontracting goals with each federal agency. The goal that SBA 
negotiated with DOE for fiscal years 2004 and 2005 is that 50 percent 
of subcontracted dollars be directed to small businesses. 

[4] For the 10 years prior to fiscal year 2000, the Office of Federal 
Procurement Policy within the Office of Management and Budget had 
allowed DOE to include in its small business prime contracting 
achievements, the subcontracting dollars awarded to small businesses by 
its facility management contractors. For a discussion of the change in 
policy starting with fiscal year 2000, see Department of Energy: 
Achieving Small Business Prime Contracting Goals Involves Both 
Potential Benefits and Risks, GAO-04-738T (Washington, D.C.: May 18, 
2004). 

[5] Large business subcontractors of DOE's facility management 
contractors are subject to the same requirements for small business 
subcontracting plans and annual goals. Although the facility management 
contractors are not allowed to include the small business 
subcontracting achievements of these "lower-tier" subcontractors in 
their reported achievements, SBA guidelines allow DOE to include these 
lower-tier subcontracting achievements toward the department's small 
business subcontracting goals. 

[6] GAO has reported on SBA compliance reviews in the past. See Small 
Business Subcontracting Report Validation Can Be Improved, GAO-02-166R 
(Washington, D.C.: Dec. 13, 2001). 

[7] The $3.3 billion includes only dollars directed by the facility 
management contractors to small businesses with which they had a direct 
contractual relationship. The figure does not account for the dollars 
directed to small businesses by the approximately 592 large business 
subcontractors of DOE's facility management contractors that also had 
their own small business subcontracting plans in fiscal year 2004. 
These dollars were not within the scope of our review because we 
focused on the achievements of the 34 facility management contractors. 

[8] Except for these types of subcontracts, SBA guidelines for 
contractor reporting of small business subcontracting achievements 
require that reports include all subcontracts awarded by the prime 
contractor. Section 19.701 of the Federal Acquisition Regulation (FAR) 
defines "subcontract" to mean "any agreement (other than one involving 
an employer-employee relationship) entered into by a Government prime 
contractor or subcontractor calling for supplies and/or services 
required for performance of the contract, contract modification, or 
subcontract." According to a contracting program manager in SBA's 
Office of Government Contracting, electricity and other utilities, 
whether or not they are obtained through a formal procurement process, 
would be considered a subcontract under the FAR. 

[9] The facility management contractors at the 13 sites we visited 
provided us with the dollar amounts associated with subcontracts 
excluded from their fiscal year 2004 small business subcontracting goal 
and achievement calculations. After the facility management contractors 
reviewed a statement of facts that we provided to them to ensure the 
accuracy of the information, several of the contractors responded that 
they would have negotiated lower goals if they had included all of the 
appropriate subcontracts in their calculations. 

[10] On average, facility management contractors at the DOE 
Environmental Management program's cleanup sites and at the NNSA's 
weapons production facilities directed to small businesses 20.4 percent 
of their contracts' annual funding. In contrast, contractors managing 
and operating research laboratories for NNSA and DOE directed to small 
businesses an average of 15.4 percent of their facility management 
contracts' annual funding. These calculations do not include the 
achievements of facility management contractors at the Yucca Mountain 
Project or the Strategic Petroleum Reserve, because their missions and 
the type of work performed there do not coincide with the two 
categories of DOE and NNSA facilities identified above. 

[11] We examined limited aspects of the subcontracting program managed 
by small business officials at the National Aeronautics and Space 
Administration (NASA), because DOE and NASA share some similarities in 
their approach to accomplishing their respective missions. For example, 
both NASA and DOE contract extensively to carry out their missions, 
accomplished in part through work at the agencies' contractor-operated 
research facilities. 

[12] U.S. Government Printing Office, DOE Contracting with Small 
Business: Hearing Before the Committee on Energy and Natural Resources, 
United States Senate, S. Hrg. 108-610 (Washington, D.C.: May 18, 2004). 

[13] In addition, contracting officers usually review upcoming 
subcontract procurements exceeding a specified dollar amount to 
determine if facility management contractors have given adequate 
consideration to small business opportunities. 

[14] In addition to DOE guidance on small business programs, NNSA has 
issued policy guidance on small business that defines requirements and 
responsibilities but has limited information on how various 
organizations should coordinate oversight efforts for small business 
subcontracting. 

[15] Although contractors are required to establish annual 
subcontracting goals for various subcategories of small businesses, 
such as small disadvantaged or women-owned small businesses, during our 
study, we only examined small business subcontracting as an overall 
category. We did not examine the contractors' subcontracting activities 
with respect to any subcategories. 

[16] Results from a nonprobability sample cannot be used to make 
inferences about a population, because in a nonprobability sample, some 
elements of the population being studied have no chance or an unknown 
chance of being selected as part of the sample. 

[17] In addition to the two facility management contractors, one other 
facility management contractor informed us, prior to the site visit, 
that one of the five subcontracts in the nonprobability sample had 
turned out to be awarded to a large business. The contractor said that, 
as a result, they were restating their reported small business 
subcontracting achievement data. Therefore, we selected an additional 
subcontract to complete the nonprobability sample of five, before 
beginning our review of this contractor's subcontracting files. 

[18] Following our reliability assessment, one contractor reported that 
it encountered other problems with potential miscoding of large 
business subcontracts as small in the data system that the contractor 
uses to calculate its small business subcontracting achievements. A 
contractor official said that the contractor is implementing corrective 
actions, such as requiring its procurement staff to manually enter 
subcontractors' business size information into the contractor's 
procurement data system. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office

441 G Street NW, Room LM

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm

E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director,

NelliganJ@gao.gov

(202) 512-4800

U.S. Government Accountability Office,

441 G Street NW, Room 7149

Washington, D.C. 20548: