This is the accessible text file for GAO report number GAO-04-759 
entitled 'Defense Acquisitions: Space-Based Radar Effort Needs 
Additional Knowledge before Starting Development' which was released on 
July 19, 2004.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to Congressional Committees: 

United States Government Accountability Office: 

GAO: 

July 2004: 

Defense Acquisitions: 

Space-Based Radar Effort Needs Additional Knowledge before Starting 
Development: 

GAO-04-759: 

GAO Highlights: 

Highlights of GAO-04-759, a report to congressional committees: 

Why GAO Did This Study: 

Missing among the Department of Defense’s (DOD) portfolio of systems is 
a capability to track stationary and moving enemy vehicles on land or 
at sea in any type of weather, day or night, from space. To meet this 
need, DOD and the intelligence community are collaborating on the 
ambitious Space-Based Radar (SBR) program. By leveraging the newest 
generation of radar technologies, the SBR concept promises to deliver 
high-quality data to a wide array of users. DOD intends to start 
product development in 2006 and to field SBR satellites as quickly as 
possible so that warfighters, the intelligence community, and national 
decision makers can gain a better understanding of what adversaries are 
doing in specific locations around the world. GAO reviewed the SBR 
program to assess DOD’s progress in attaining the knowledge it needs by 
2006 in terms of customer needs (or requirements) and resources.

What GAO Found: 

Although SBR is 2 years away from product development, the program 
already faces major challenges. DOD officials say SBR will likely be 
the most expensive and technically challenging space system ever built 
by DOD. The acquisition time frame is much shorter than what has been 
achieved in the past for other complex satellite systems. Finally, DOD 
is setting precedence by taking the lead on developing SBR with the 
intelligence community as a partner. Most DOD space programs that GAO 
has reviewed in the past several decades were hampered by schedule and 
cost growth and performance shortfalls. Problems were largely rooted in 
a failure to match requirements with resources when starting product 
development. Commitments were made without knowing whether technologies 
being pursued would work as intended. To avoid these problems, leading 
commercial firms have adopted a knowledge-based model that enables 
decision makers to be reasonably certain about their products at 
critical junctures and helps them make informed investment decisions.

Although DOD has taken positive steps to strengthen the involvement of 
senior leaders within DOD and the intelligence community in setting 
requirements, SBR’s concept of operations has not been approved and 
signed by requirements boards for either of the two partners. Without 
documentation and formal approval, it is unclear who will be held 
accountable for setting requirements or how disagreements among SBR’s 
partners will be resolved when DOD moves SBR into ensuing phases of 
acquisition.

DOD has adopted noteworthy practices to gain knowledge about SBR’s 
resources. These include maximizing the use of systems engineering to 
close gaps between requirements and resources; estimating all of SBR’s 
costs; exploring alternatives for SBR if the Transformational 
Communications Architecture (TCA)—the communications infrastructure 
that is expected to relay SBR data across a network of users—incurs 
schedule and performance shortfalls; and asking contractors to propose 
multiple operations concepts for SBR with or without TCA. Despite these 
accomplishments, DOD is at risk of knowledge gaps. SBR’s critical 
technologies will not be mature when product development starts, as 
called for by best practices. One of TCA’s primary components may not 
be ready in time to support SBR data. These knowledge gaps make it 
harder for DOD to reliably estimate how much time and money are needed 
to complete SBR’s development. If TCA is delayed, DOD’s alternatives 
may involve reducing SBR’s capabilities or significantly increasing 
program cost. Without sufficient knowledge, DOD may not be able to 
determine by the time SBR’s product development starts in 2006 whether 
space-based radar is best suited to tracking moving targets on land or 
at sea or whether air-based radar would provide enough capabilities at 
far less cost. More specific analyses would help DOD weigh the merits 
of various alternatives and assess how much to invest in the SBR 
acquisition program versus air platforms with similar capabilities.

What GAO Recommends: 

GAO recommends that, before committing to SBR’s acquisition program in 
2006, DOD and its intelligence partners close gaps in the requirements 
approval process in terms of documenting decisions and be prepared to 
add time and money or make trade-offs with other DOD space programs to 
address SBR’s requirements and resources. DOD generally agreed with our 
findings and partially agreed with our recommendations.

www.gao.gov/cgi-bin/getrpt?GAO-04-759

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Katherine V. Schinasi at 
(202) 512-4841 or schinasik@gao.gov.

[End of section]

Contents: 

Letter: 

Scope and Methodology: 

Results in Brief: 

Background: 

Gaining Knowledge about Requirements and Resources before Product 
Development Is Important for Space Acquisition Success: 

DOD Moving Forward on Acquiring Critical Knowledge but Gaps Remain in 
Approval for SBR Requirements: 

DOD Taking Proactive Steps to Gain Knowledge about Resources, but 
Critical Gaps May Remain at Product Development: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: TRL Scale for Assessing Critical Technologies: 

Appendix II: Comments from the Department of Defense: 

Tables: 

Table 1: Knowledge Provided by SBR's Initial Capabilities Document and 
Concept of Operations: 

Table 2: Technology Readiness Levels of SBR Critical Technologies: 

Figures: 

Figure 1: SBR's Acquisition Schedule (in fiscal years): 

Figure 2: SBR's Oversight Structure: 

Figure 3: Requirements-Setting Can Impact Acquisition Process: 

Abbreviations: 

AOA: analysis of alternatives: 

DOD: Department of Defense: 

R&D: research and development: 

SBR: Space-Based Radar: 

TCA: Transformational Communications Architecture: 

TRL: Technology Readiness Level: 

United States Government Accountability Office: 

Washington, DC 20548: 

July 23, 2004: 

The Honorable John Warner: 
Chairman: 
The Honorable Carl Levin: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Ted Stevens: 
Chairman: 
The Honorable Daniel Inouye: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Duncan Hunter: 
Chairman: 
The Honorable Ike Skelton: 
Ranking Minority Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable Jerry Lewis: 
Chairman: 
The Honorable John P. Murtha: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

The Department of Defense (DOD) currently has ground-based and 
air-based radars but no capability to track moving targets from space. 
To meet a need for persistent global observation, DOD and the 
intelligence community are working together to develop the Space-Based 
Radar (SBR) system to find, identify, track, and monitor ground and sea 
targets--mobile or immobile--under all-weather conditions and on a 
near-continual basis across large swaths of the earth's surface. SBR is 
to enhance information gathering by providing intelligence, 
surveillance, and reconnaissance data in a meaningful and timely 
manner.

This is an ambitious program for DOD. DOD's initial total cost estimate 
for SBR is about $28.6 billion from fiscal year 2003 to 2024. And 
although the technologies for tracking moving targets from space are 
still in development, DOD is scheduling almost 7 years between the 
start of product development and launch of the first SBR satellite--a 
time frame that is considerably shorter than what has been achieved in 
the past for other complex satellite systems. DOD would like to field 
SBR satellites as quickly as possible because it believes that SBR 
represents a major leap forward in providing the warfighters, 
intelligence community, and national decision makers with significant 
tactical, operational, and strategic advantages over potential 
adversaries. For example, DOD envisions that SBR will be able to see 
deep inside enemy territory without risk to personnel or resources and 
that it will operate over areas where conventional airborne 
surveillance systems are at risk from the enemy's surface-to-air 
missiles, which can travel increasingly longer ranges. DOD also 
envisions that SBR will generate high-quality radar imagery of targets 
and terrain and interface with ground, air, and other space systems so 
that users can gain a better understanding of what is occurring in 
specific locations.

DOD is in the early exploratory phase of the SBR program--a period when 
it gathers knowledge about its needs, or requirements, and explores the 
feasibility of meeting those requirements. DOD expects to begin product 
development in fiscal year 2006; at which point it will make a 
commitment to invest in a formal acquisition program for SBR. Our past 
work has shown that successful weapon system programs are able to match 
their needs to their resources--that is, money, technology, and time--
before product development. With achievable requirements and commitment 
of sufficient investment to complete development, programs are better 
able to deliver products at cost and on schedule. Most space programs 
over the past several decades have not been able to achieve a match 
between needs and resources before product development and have 
incurred significant cost and schedule increases due in part to the 
need to rework technologies in the later stages of their acquisition.

We conducted our review of the SBR program on the initiative of the 
Comptroller General. Given SBR's overall importance to DOD and the 
intelligence community, we reviewed the SBR program to assess DOD's 
progress in attaining the knowledge it needs by 2006 in terms of 
(1) requirements and (2) resources--technology, communications 
infrastructure, and funding.

We are addressing this report to you because of your jurisdiction over 
weapon systems acquisition.

Scope and Methodology: 

To assess DOD's progress in attaining the knowledge it needs before the 
start of product development, we examined the resources (technology, 
communications infrastructure, and funding) committed and planned for 
the program as well as the users' needs for an SBR system. We 
considered DOD's plans for maturing the critical technologies when we 
obtained technology-readiness information for each critical technology 
(as well as its mature backup technology) against best practice 
standards to determine if they will be sufficiently mature when DOD 
plans to start product development. We also reviewed the SBR risk 
management plans and concept development contract information. We 
discussed these documents and issues with representatives from Air 
Force Space Command, Peterson Air Force Base, Colorado; and the SBR 
Joint Program Office, Space and Missile Systems Center, Los Angeles Air 
Force Base, California.

To determine SBR's role in a larger DOD architecture, we met with 
officials from the Joint Chiefs of Staff, Washington, D.C; and the Air 
Force Directorate of Space Acquisitions, Arlington, Virginia. We also 
consulted past GAO reports to determine the relationship between SBR 
and the Transformational Communications Architecture.

To determine the scope and completeness of the analysis of alternatives 
and its follow-on study to identify the optimal ways to gather 
information on ground moving targets from radars based in space versus 
air, we met with officials from Air Force Space Command; DOD Office of 
the Director, Program Analysis and Evaluation, Washington, D.C; Air 
Force Directorate of Requirements for Space, Crystal City, Virginia; 
and the Air Force Studies and Analyses Agency, Arlington, Virginia. We 
also talked with an official from the Air Force Office of Aerospace 
Studies, Kirtland Air Force Base, New Mexico.

We discussed overarching programmatic issues--including the level of 
coordination between DOD and the intelligence community--with 
representatives from the Air Force Directorate of Space Acquisitions. 
We were not able to obtain meetings with members of the Mission 
Requirements Board (a board within the intelligence community 
responsible for approving program requirements) or the intelligence 
agencies to discuss their stake in the SBR program.

We performed our work from November 2003 through June 2004 in 
accordance with generally accepted government auditing standards.

Results in Brief: 

DOD has inserted a great deal of management and stakeholder involvement 
into developing SBR so that it can gain greater knowledge about 
requirements before product development than it has in past programs. 
Senior-level officials from DOD, the military services, and the 
intelligence community are heading up three new SBR oversight groups to 
discuss what can and cannot be accomplished in terms of the desired 
time frame, available funding, and achievable technologies. The groups 
have so far attained informal agreement on requirements. However, this 
commitment has not been formalized, and it is unclear as to whether or 
how it will be formalized. Moreover, it is also unclear how 
disagreements that may occur later on among SBR's partners will be 
resolved. Given the varied interests of SBR's partners and past 
problems with securing agreement on requirements for space 
programs,[Footnote 1] it is important that DOD build on the positive 
steps it has already taken and find ways to formalize commitment to 
requirements as well as SBR's concept of operations.

DOD is also taking positive steps in its effort to gain knowledge about 
SBR's resources. These steps include strengthening systems engineering 
applications; estimating not just direct costs but all of SBR's life-
cycle costs; exploring alternatives for SBR if the new Transformational 
Communications Architecture (TCA), the infrastructure that is to help 
relay SBR data, falls short of its schedule and performance goals; and 
asking concept development contractors to propose multiple design 
concepts for SBR with or without TCA. Despite these accomplishments, 
however, decision makers will have significant knowledge gaps about 
SBR's resources if SBR's product development phase starts when 
currently planned. This is because DOD intends to start product 
development in fiscal year 2006 even though the two critical 
technologies that would enable the tracking of surface-moving targets 
and the timely delivery of imagery data will not have been tested in 
space or even in a relevant environment. Without the knowledge derived 
from such tests, DOD cannot adequately assess whether the technologies 
will work as intended, making it harder to reliably estimate how much 
time and money is needed to complete development. Adding to SBR's 
overall risk are uncertainties as to whether TCA will be available to 
transmit SBR's vast volumes of radar data and imagery. Although DOD has 
plans underway to develop alternatives for SBR if TCA is delayed, the 
primary alternatives would involve either reducing SBR's capabilities 
or significantly increasing program cost. Lastly, DOD and the Air Force 
may not have sufficient knowledge to make a corporate decision as to 
how much it should invest in space-based radar capabilities versus 
air-based capabilities at the time it makes a commitment to the formal 
SBR acquisition in 2006. While the Air Force has undertaken two 
analyses of the SBR investment, neither presents a comprehensive 
assessment as to whether space-or air-based radar platforms (or a 
combination of both) are better suited for tracking moving targets on 
land or at sea, nor does either analysis weigh the capabilities and 
costs of each suitable radar option in space and in the air.

Before committing to SBR's acquisition program in 2006, we recommend 
that senior-level officials in DOD and the intelligence community close 
gaps in the requirements-setting process in terms of documenting 
decisions and establishing a formal mechanism for addressing unresolved 
issues or how changes to approved requirements will be assessed. We 
recommend that DOD's space acquisition policy be modified to identify 
the requirements-setting process when DOD partners with the 
intelligence community on space programs. We recommend that DOD delay 
approval to commit funding to product development for SBR until 
technologies are matured to higher levels, but if DOD determines that 
the SBR program should proceed to product development with less than 
mature technologies, we recommend that DOD be prepared to add time and 
money or make trade-offs with other DOD space programs to address SBR's 
requirements and resources. DOD generally agreed with our findings and 
our recommendation to strengthen its study of SBR alternatives. DOD 
partially agreed with our recommendations to strengthen its requirement 
setting process for SBR and to demonstrate SBR technologies in a 
relevant or operational environment before committing to product 
development. DOD did not agree with our recommendation to modify its 
acquisition policy to strengthen requirements setting. In commenting on 
our recommendations, DOD cited concerns about supplanting current 
requirements setting processes. Our recommendation does not advocate 
replacing this process, but rather strengthening it to provide more 
transparency, discipline, and accountability.

Background: 

SBR represents the first time that DOD has taken the lead on developing 
a major national security space capability with the intelligence 
community as a partner. Because of this partnership, SBR's acquisition 
process is more complex than that used for typical DOD programs. While 
DOD and the intelligence community will likely use all the data that 
SBR produces, their priorities differ. DOD's warfighting community is 
particularly interested in tracking targets moving over land or sea as 
well as other objects of interest. The intelligence community is more 
focused on obtaining detailed global imagery and combining it with 
other data for advanced processing. SBR is expected to meet both needs 
and be fully integrated with other space and non-space systems, 
including TCA, which is to transmit SBR's data to receivers in the air, 
at sea, or on the ground.

A key advantage of radar in space is having the ability to "see" 
through clouds and sand storms and any type of weather, day or night. 
Radar-equipped aircrafts, on the other hand, require U.S. air dominance 
to collect radar information and must steer clear of hostile areas--the 
result being limited radar coverage. The SBR concept offers other added 
features, including electronic steering of the radar signal toward a 
particular area and capturing high volumes of very fine resolution 
radar images of targets and terrain. With the ability to perform these 
functions almost simultaneously, SBR is expected to help analysts gain 
a better understanding of what is occurring in specific locations.

To help meet some of its goals, DOD plans to leverage key technologies 
that were developed in the late 1990s to demonstrate a space-based 
radar capability. According to DOD officials, contractors developed 
some satellite hardware and prototype components under the 
Discoverer II program, which began in 1998 and was to identify and 
validate by 2008 the capability of tracking mobile ground targets from 
space. Discoverer II, comprising two radar demonstration satellites, 
was a joint initiative by the Air Force, DOD's Defense Advanced 
Research Projects Agency, and the intelligence community's National 
Reconnaissance Office. DOD officials told us that the Discoverer II 
program had reached the preliminary design review phase when it was 
cancelled in 2000 because of cost and schedule uncertainties, poorly 
explained requirements, and the lack of a coherent vision to transition 
the system to operational use.

The Secretary of Defense concluded that space-based radar could provide 
a military advantage and in 2001 approved SBR as a new major defense 
acquisition program, delegating it to the Air Force. In July 2003, an 
independent cost assessment team consisting of representatives from DOD 
and the intelligence community estimated that $28.6 billion would be 
needed to pay for SBR's life-cycle costs--development, production, 
launch, and operation. The program entered the study phase in August 
2003. The Air Force has requested $328 million for SBR in fiscal year 
2005 and has programmed about $4 billion for the program from 
fiscal years 2005 to 2009. Given concerns about affordability and 
readiness, the Fiscal Year 2005 Defense Appropriations Conference 
Report reduced funding for SBR to $75 million, with the direction to 
return this effort back to the technology development phase. In 2003, 
Congress reduced the Air Force's $274 million budget request for SBR by 
$100 million due to concerns about technology maturity and schedule. 
DOD has scheduled the start of product development for mid-fiscal year 
2006, with production starting at the end of fiscal year 2008 and the 
first satellite to be launched at the end of fiscal year 2012. Figure 1 
shows SBR's acquisition schedule in fiscal years.

Figure 1: SBR's Acquisition Schedule (in fiscal years): 

[See PDF for image]

[End of figure]

Gaining Knowledge about Requirements and Resources before Product 
Development Is Important for Space Acquisition Success: 

In the past several decades, DOD's space acquisitions have experienced 
problems that have driven up costs by hundreds of millions, 
even billions, of dollars; have stretched schedules by years; and have 
increased performance risks. In some cases, capabilities have not been 
delivered to the warfighter after decades of development. Our reports 
have shown that these problems, common among many weapon acquisitions, 
are largely rooted in a failure to match the customer's requirements 
(desired capabilities) with the developer's resources (technical 
knowledge, timing, and funding) when starting an acquisition program.

In particular, our past work has shown that for space systems, product 
development was often started based on a rigid set of requirements that 
proved to be unachievable within a reasonable development time frame. 
Other cases involved unstable requirements. In some cases where 
requirements had been identified and approved, even more requirements 
were added after the program began. When technology did not perform as 
planned, adding resources in terms of time and money became the primary 
option for solving problems because the customer's expectations about 
the product's performance capabilities already had been set.

The path traditionally taken by space programs--and other DOD weapon 
system programs--stands in sharp contrast to that taken by leading 
commercial firms. Our extensive body of work shows that leading 
companies use a product development model that helps reduce risks and 
increase knowledge when developing new products. This best practices 
model enables decision makers to be reasonably certain about their 
products at critical junctures during development and helps them make 
informed investment decisions. This knowledge-based process can be 
broken down into three cumulative knowledge points.

* Knowledge point 1: A match must be made between the customer's 
requirements and the developer's available resources before product 
development starts. As noted earlier, DOD plans to start SBR product 
development in 2006.

* Knowledge point 2: The product's design must be stable and must meet 
performance requirements before initial manufacturing begins.

* Knowledge point 3: The product must be producible within cost, 
schedule, and quality targets and demonstrated to be reliable before 
production begins.

Systems engineering is a technical management tool that provides the 
knowledge necessary at knowledge point 1 to translate requirements into 
specific, achievable capabilities. With systems engineering knowledge 
in hand, acquisition decision makers and developers can work together 
to close gaps between requirements and available resources--well before 
product development starts. Some gaps can be resolved by the 
developer's investments, while others can be closed by finding 
technical or design alternatives. Remaining gaps--capabilities the 
developer does not have or cannot get without increasing the price and 
timing of the product beyond what decision makers will accept--must be 
resolved through trade-offs and negotiations. Effective use of this 
tool enables decision makers to move on to knowledge point 2 and to 
produce a stable product design.

DOD has recently issued a new acquisition policy for space systems, 
partly intended to address past acquisition problems and provide 
capability to users quicker. However, we recently reported that the 
policy is not likely to achieve these goals because it allows programs 
to continue to develop technologies after product development starts. 
Our past work has shown that this approach makes it more difficult to 
estimate cost and schedule at the onset of product development and 
increases the likelihood that programs will encounter technical 
problems that could disrupt design and production and require more time 
and money to address than anticipated. Over the long run, the extra 
investment required to address these problems could reduce funding for 
developing other technological advances, slow the overall modernization 
effort, delay capabilities for the warfighter, and force unplanned--and 
possibly unnecessary--trade-offs between space and other weapon system 
programs. By contrast, DOD's revised policy for other weapon 
acquisitions encourages programs to mature technologies to the point of 
being tested in an operational environment before beginning product 
development. We recommended that DOD modify its policy to separate 
technology development from product development so that needs can be 
matched with available technology, time, and money at the start of a 
new program.

We also reported that DOD's space acquisition policy does not require 
DOD to commit to setting aside funding for space acquisitions. Hence, 
there is no guarantee that the resources needed to meet requirements 
will be there on any individual program when needed. This makes it 
difficult for DOD as a whole to make corporate-level and trade-off 
decisions--which will likely be needed when DOD begins the SBR 
acquisition because (1) costs are significantly increasing for other 
critical space systems such as the Space-Based Infrared System High, 
the Transformational Satellite, and the Evolved Expendable Launch 
Vehicle and (2) DOD is planning to undertake additional new programs, 
such as the Space-Based Space Surveillance system and a new version of 
the Global Positioning System.

DOD is revising its new space acquisition policy partly to address 
these issues; however, the revision was not available for review at the 
time of this review.

DOD Moving Forward on Acquiring Critical Knowledge but Gaps Remain in 
Approval for SBR Requirements: 

DOD has bolstered the SBR acquisition program by increasing senior 
leader and stakeholder involvement in setting requirements. However, 
DOD is not fully documenting commitments made during the requirements 
approval process before progressing to the next acquisition phase, nor 
has it established a process to resolve potential disagreements that 
may occur after approval. Clouding the approval of requirements is that 
DOD's current space acquisition policy does not provide specific 
guidance for acquisitions that involve partnerships between DOD and the 
intelligence community.

SBR Managed by New Executive Oversight Structure: 

Providing senior-level oversight are three new groups created expressly 
for the SBR program: the Executive Steering Group, which advises the 
Requirements/Capabilities Group and the Joint Senior Acquisition Group. 
Members of these groups come from DOD, National Reconnaissance Office, 
and National Geospatial-Intelligence Agency. All key stakeholders are 
expected to have open and honest discussions about what can and cannot 
be done within desired time frames, budgetary constraints, and 
achievable technologies. Figure 2 shows how these groups work with 
SBR's joint program office and requirements review boards for DOD and 
the intelligence community.

Figure 2: SBR's Oversight Structure: 

[See PDF for image]

[End of figure]

A primary benefit of having an oversight structure for the SBR program, 
which involves many decision makers from across multiple organizations, 
is that the right people are involved in the decision-making process 
and can work together to lock in their requirements. The intent is to 
avoid problems of the past in which a program incurs cost, schedule, 
and performance risks because decision makers continue to negotiate and 
make trade-offs even after designers and engineers have started 
technology development and design work. Figure 3 shows the likely 
outcomes if requirements are poorly defined and are not approved or, in 
the case of SBR, if requirements are adequately defined and approved 
early in the study phase.

Figure 3: Requirements-Setting Can Impact Acquisition Process: 

[See PDF for image]

[End of figure]

SBR's Requirements-Setting Process Lacks Formal Approval and 
Documentation: 

DOD officials reported to us that the oversight groups have achieved 
informal consensus on requirements for SBR. However, this approval has 
not been formalized and it is unclear as to whether and how it might be 
formalized. Moreover, it is unclear how disagreements that may occur 
after initial approval will be resolved.

Regardless of how many stakeholders have been invited to join in 
decision making or how much expertise is included in SBR's oversight 
function, overall success of the SBR program hinges in part on whether 
the requirements are clear, stable, and achievable and whether DOD and 
the intelligence community demonstrate commitment and accountability by 
formally approving the requirements. In an acquisition decision 
memorandum, the Under Secretary of the Air Force requested that DOD and 
the intelligence community approve the initial capabilities document 
and concept of operations before the request for proposals was released 
in January 2004 for concept development contracts. DOD officials told 
us that the Joint Requirements Oversight Council and the intelligence 
community's Mission Requirements Board approved the initial 
capabilities document, and there are memoranda documenting these 
decisions. The Joint Requirements Oversight Council reviewed the 
concept of operations, provided comments, but did not approve it. 
According to DOD officials, during a meeting of the SBR Executive 
Steering Group, high-level officials from the intelligence community 
verbally approved the concept of operations, but there is no 
documentation recording this approval.

Agreement is critical because DOD and the intelligence community are 
placing different emphasis on desired capabilities for SBR. An 
independent assessment of the SBR program determined that requirements 
were adequate to enter the study phase, which started in August 2003, 
but cautioned that the requirements needed to be converged among all 
stakeholders and users. Table 1 shows the type of knowledge that 
decision makers expect to gain from the initial capabilities document 
and the concept of operations.

Table 1: Knowledge Provided by SBR's Initial Capabilities Document and 
Concept of Operations: 

Document: Initial capabilities document; 
Key knowledge provided: 
* Identifies current gaps in capability, 
* Identifies the overall desired capabilities of the SBR system; 
* Lists users' performance requirements for SBR; 
* Identifies the functional relationships between users; 
* Specifies the desired capability for DOD's capability development 
document, which is prepared at the end of the study phase; 
* Identifies validated requirements. 

Document: Concept of operations; 
Key knowledge provided: 
* Describes the components of the SBR system; 
* Identifies how SBR information is to be processed and disseminated to 
the warfighters and others; 
* Describes how SBR fits into architectures involving other space and 
non-space systems in meeting requirements; 
* Identifies external threats to SBR and the perceived operational 
environment. 

Sources: DOD (data); GAO (analysis).

[End of table]

A defined requirements approval process helps decision makers resolve 
disagreements that may occur and ensure they will remain committed to 
their decisions after formal approval. Based on our past reports on 
uncovering problems and our best practice work, we believe that the 
steps in a formal approval process include: 

* explaining how decision makers' requirements and comments are 
obtained and addressed;

* identifying the officials and/or the organizations responsible for 
taking specific approval action;

* establishing a mechanism and time frame for providing approval or 
disapproval;

* establishing a system for addressing unresolved issues as they relate 
to key program documentation; and: 

* assessing changes to approved requirements based on their effect on 
the program's cost and schedule.

While DOD has taken steps to increase senior leader and stakeholder 
involvement in setting requirements and addressing acquisition issues, 
DOD is not fully documenting commitments made during the requirements 
approval process, nor has it established a process to resolve potential 
disagreements that may occur after approval.

DOD Taking Proactive Steps to Gain Knowledge about Resources, but 
Critical Gaps May Remain at Product Development: 

DOD is also taking positive steps to attain the knowledge needed to 
understand what resources will be needed to develop SBR's capabilities 
and to mitigate risks. These include: 

* relying on systems engineering to translate requirements into 
specific, achievable capabilities and to close gaps between 
requirements and resources;

* adopting a more comprehensive cost estimating technique to identify 
SBR's life-cycle costs;

* exploring alternatives for SBR if TCA--the infrastructure that DOD is 
depending on to transmit SBR's data--incurs schedule slips; and: 

* asking two concept development contractors to each propose at least 
two different operations concepts for SBR with and without TCA.

However, the path that SBR is on has potential for knowledge gaps when 
making investment decisions, the types of gaps that have hampered other 
space programs in the past. Specifically, it is expected that some 
critical SBR technologies will not be mature when product development 
starts, that is, not tested in a relevant or operational environment. 
Typical outcomes of this lack of knowledge are significant cost and 
schedule increases because of the need to fix problems later in 
development. Furthermore, TCA, a new, more robust communications 
infrastructure that could transmit SBR's imagery data much more quickly 
than the current infrastructure, is facing uncertainties. Specifically, 
one of TCA's primary components, the Transformational Satellite, may 
not be ready in time to support SBR.[Footnote 2] Without mature 
technologies and faced with a possible slip in the Transformational 
Satellite's schedule, DOD will be less able to accurately estimate 
total system costs before the start of product development. In 
addition, DOD and the Air Force may not have knowledge needed to make 
corporate level trade-offs between SBR and other air-based radar 
systems at the time it plans to make a commitment to invest in the SBR 
acquisition program. DOD has undertaken an analysis to weigh the merits 
of space-based radar. At this time, it is not known whether this 
analysis will be a detailed examination of the capabilities and costs 
of each individual radar option and combined with other radar platforms 
or whether the analysis will be a less rigorous examination of the mix 
of radar options.

DOD Taking Positive Steps to Build Foundation of Knowledge about 
SBR Resources: 

DOD is planning to aggressively address technology, affordability, and 
integration issues by, in part, instituting robust systems engineering 
processes and procedures. Systems engineering is a technical management 
tool for gaining information on a broad array of activities related to 
the development of a system. For SBR, DOD plans to perform systems 
engineering work on requirements and their allocation, interface 
definitions, trade studies, risk management, performance analysis and 
modeling, environmental and safety planning, test planning, program 
protection planning, information assurance, and configuration control. 
Applying systems engineering to these activities would give DOD the 
insight and knowledge it needs to better manage the program, including 
ways to reduce risk and ensure the viability of concepts and 
requirements.

DOD has also decided to take a more comprehensive approach to 
estimating SBR's life-cycle costs. According to the SBR program 
director, this marks the first time DOD has willingly presented all 
related costs to develop, acquire, produce, maintain, operate, and 
sustain the system. DOD officials stated that they wanted to identify 
not just direct costs, but also costs for associated infrastructure 
such as the costs related to modifying the ground system that will be 
used to support SBR as well as other systems. According to DOD, about 
$8 billion of the $28.6 billion life-cycle cost estimate represents 
costs that in the past, would not have been included in space program 
total cost estimates. Taking steps to more comprehensively identify SBR 
and SBR related costs is a positive step and will help DOD manage its 
portfolio of space programs.

Although DOD hopes to rely on TCA to support SBR data transmissions, it 
is taking a proactive approach to identify and assess the viability of 
TCA alternatives. First, in April 2004, DOD awarded two 2-year 
contracts for concept development efforts that call for the 
identification of alternatives to TCA. For each alternative identified, 
the contractor is to conduct an assessment of the cost, risk, and 
effect on SBR's performance. DOD officials told us that when SBR 
initiates product development in 2006, it would know whether TCA will 
be available to support SBR or whether to pursue a TCA alternative. In 
addition, DOD also awarded two contracts totaling $510,000 for a 
yearlong study to propose several alternatives to TCA capable of 
supporting SBR's communications requirements and to analyze the 
viability of such alternatives. These actions have put DOD in a better 
position to ensure the program is successful.

The two 2-year contracts that DOD awarded in April 2004 also require 
that at least two different viable SBR operations concepts be proposed. 
DOD is expecting each contractor to fully develop the alternative 
operations concepts. These alternative concepts could involve using 
unique radar processing techniques. According to DOD, it will work with 
each of the contractors to pare down the alternatives to a single best 
concept for each contractor. For the remainder of the contract 
performance period, the contractors would focus their attention on 
fleshing out the details associated with these concepts. This approach 
will put DOD in a better position when the time comes to select a 
single contractor to design the SBR system.

Technologies Will Not Be Mature at Product Development Start: 

DOD officials have said that SBR will likely be the most technically 
challenging, software-intensive, and complex space system ever built by 
DOD. The two key pieces of hardware needed to give SBR a radar 
capability from space--the electronically scanned array (which steers 
the radar signal to an area of interest) and the on-board processor 
(the radar-processing unit aboard SBR)--face the highest amount of 
risk. The electronically scanned array can scan multiple areas of 
interest virtually simultaneously, allowing for simplified satellite 
design over conventional technology offering mechanical slew radar. The 
on-board processor is expected to allow the processing radar data to 
assure the timely and thorough delivery of imagery data that will be 
downlinked for transmission to the warfighter.

To minimize the potential for technology development problems after the 
start of product development, DOD uses an analytical tool to assess 
technology maturity for many weapon system acquisition programs. 
Called Technology Readiness Levels (TRL), this tool associates a TRL 
with different levels of demonstrated performance, ranging from paper 
studies to actual application of the technology in its final form. The 
value of using a tool based on demonstrated performance is that it can 
presage the likely consequences of incorporating a technology at a 
given level of maturity into a product's development, enabling decision 
makers to make informed choices. Our previous reviews have found the 
use of TRLs, which range from 1 to 9, to be a best practice. (See app. 
I for a description of the TRL levels.) 

The critical technologies that will support the SBR program currently 
range from TRL 3 to 5. A TRL 3 means that most of the work performed so 
far has been based on analytical and laboratory studies. At a TRL 5, 
the basic technology components are integrated and tested in a 
simulated or laboratory environment. Table 2 shows the current TRL for 
each of SBR's critical technologies and the expected TRL at product 
development start in 2006. In general, the program office's key risk 
reduction efforts are scheduled to mature these technologies to TRL 5 
by the middle of fiscal year 2006. These efforts include the awarding 
of research and development contracts to three payload contractors for 
efforts to continue to develop and mature these components (the 
electronically scanned array and on-board processor). The period of 
performance of each contract is about 2.5 years.

Table 2: Technology Readiness Levels of SBR Critical Technologies: 

Critical technology: Electronically scanned array; 
Current TRL level[A]: 4; 
Expected TRL level: 5; 
Fiscal year[B]: 2006.

Critical technology: On-board processor; 
Current TRL level[A]: 3; 
Expected TRL level: 5; 
Fiscal year[B]: 2006.

Critical technology: Signal processing algorithms (for moving target 
indication); 
Current TRL level[A]: 4-5; 
Expected TRL level: 5; 
Fiscal year[B]: 2006.

Critical technology: Information management system; 
Current TRL level[A]: 3; 
Expected TRL level: 5; 
Fiscal year[B]: 2006.

Critical technology: Moving target indication exploitation hardware 
and software; 
Current TRL level[A]: 3-4; 
Expected TRL level: 5; 
Fiscal year[B]: 2006. 

Sources: DOD (data); GAO (analysis).

[A] A TRL range is shown because of varying maturities between the 
viable suppliers.

[B] Even if the SBR program office chooses to pursue a different SBR 
concept alternative, these technologies still would be considered 
critical; however, the specific technology readiness date could be 
different for each proposed alternative.

[End of table]

To mature the electronically scanned array and on-board processor 
technologies from a TRL 3/4 to 5, the contractors plan to conduct 
various developmental and integrative tasks in about 3 years. For 
example, one contractor plans to conduct 18 tasks to develop the 
electronically scanned array and 8 tasks to integrate the on-board 
processor with other system components. In addition, the development of 
the integrated circuits and programmable microcircuits that support the 
on-board processor requires extensive tests and evaluations and the 
radiation-hardening requirement further complicates the development. 
Given the challenges of the state-of-the-art technologies being 
developed and the algorithms involved, the testing programs must be 
rigorous and transparent and the results fully documented. We have 
determined that the time allotted to mature the SBR technologies to TRL 
5 is ambitious given the tasks that need to be accomplished. 
Furthermore, the development of the signal processing algorithms and 
communications downlink involves significant software development. 
Based on our past experience of software assessments in other programs, 
the establishment of a structured testing regime for software 
development has always been underestimated.

By planning to start product development in fiscal year 2006 with 
technologies at TRL 5, DOD is very likely to continue designing the 
system and to conduct other program activities at the same time it 
builds representative models of key technologies and tests them in an 
environment that simulates space conditions (such as a vacuum chamber). 
This approach is common with DOD space acquisitions but has a 
problematic history. Our past work[Footnote 3] has shown that it can 
lead to significant cost and schedule increases because of the need to 
fix problems later in development. A continuing problem is that 
software needs are poorly understood at the beginning of a program. We 
have previously recommended that DOD not allow technologies to enter 
into a weapon system's product development until they are assessed at a 
TRL 7, meaning a prototype has been demonstrated in an operational 
environment.[Footnote 4] DOD has accepted lower TRL thresholds for 
space programs because testing in an operational environment--in space, 
for example, or even in a relevant environment--is difficult and 
costly. However, DOD's new space acquisition policy does not identify 
what the minimum TRL level should be before starting product 
development for space programs, how risks should be mitigated if 
technologies are included in programs without full testing, or how 
lower TRL levels affect the confidence of cost and schedule estimates. 
Moreover, the policy does not address the option of maturing 
technologies outside a program and pulling them in once they prove to 
be viable.

One way to mitigate technology risk is to rely on backup technologies, 
should newer technologies prove to be problematic during product 
development. According to DOD officials, there are backup technologies 
that are more mature for each of SBR's critical technologies. The 
backups are the same technologies but rely on a previous and more 
mature version. Using previous versions of these technologies would 
result in a lower level of desired performance--such as a reduced area 
collection rate, a reduction in the total number of targets collected 
per satellite per day, increased product delivery time frames to the 
user, an increased weight of the spacecraft, and higher cost. For 
example, more mature versions of the electronically scanned array exist 
and if used, would result in a reduction in its performance level. In 
addition, some previous versions of SBR technologies have not been 
demonstrated or tested in space. But according to DOD officials, even 
with backup technologies, the total performance of the SBR system can 
be maintained through systems engineering trades. DOD says it has been 
able to leverage some of the key technologies (such as the 
electronically scanned array) that were under development during the 
previous effort, Discoverer II, to demonstrate a space-based radar 
capability.

Communications Infrastructure May Not Be Ready in Time to Support SBR: 

Current plans call for TCA to transmit SBR's large volume of data to 
ground-, air-, ship-, and space-based systems. However, one of TCA's 
primary components, the Transformational Satellite--which will use 
technologies that DOD has never before tried in space--is facing 
uncertainties in its scheduled 2011 launch. DOD started product 
development for the Transformational Satellite in December 2003 even 
though technologies were immature. If the Transformational Satellite 
falters but SBR launches as expected in 2012, then DOD will have a 
fully operational, new-generation satellite that is missing its primary 
means of data transmission. Recognizing the challenges, DOD is to 
decide by November 2004 whether to move forward or delay the 
Transformational Satellite's acquisition program and instead procure 
another Advanced Extremely High Frequency satellite, which already are 
under development and are based on mature technologies.

Our analysis shows that alternatives to TCA may involve a greater 
reliance on processing aboard the SBR satellites, thereby increasing 
software development efforts. This approach would reduce the volume of 
data requiring transmission, allowing conventional satellite systems, 
such as the Advanced Extremely High Frequency satellites, to handle the 
transmission. Another likely alternative is to have SBR satellites 
transmit only selected portions of data, again, so that the Advanced 
Extremely High Frequency satellite could handle the lower volume of 
information. Finally, a dedicated system of satellites could be fielded 
for the sole purpose of transmitting SBR data, significantly increasing 
program cost and raising affordability issues. Currently, DOD is 
working closely with officials from the Transformational Satellite 
program office to evaluate the relative merits of various alternatives 
and to document the interfaces needed between SBR and the 
Transformational Satellite for each alternative. During the course of 
our audit work, SBR program officials met weekly with the 
Transformational Satellite program's integrated product teams and were 
coordinating efforts on a memorandum of agreement on requirements 
development, joint engineering practices, and studies of air-and space-
based options.

SBR's Cost Estimate Unlikely to Be Realistic Because of Multiple 
Uncertainties: 

Based on a notional constellation of nine (plus one spare) satellites 
operating in low-earth orbit, an independent cost assessment in 2003 
put SBR's cost at the $28.6 billion mark, making SBR the most expensive 
DOD space system ever built. When this initial cost estimate is revised 
in 2006, before SBR's product development starts, DOD is to have 
decided a number of issues, such as how many satellites are to be 
acquired, what their capabilities will be, and at what altitude(s) the 
satellites are to operate. This system refinement allows DOD to develop 
a more realistic total system cost estimate--a critical knowledge point 
if a successful match between requirements and resources is to be made. 
However, if DOD begins product development with less than mature 
technologies and without knowing the availability of TCA, accurate cost 
estimates for SBR will be much more difficult to prepare. We have 
previously reported that improving the reliability of cost estimates is 
critical[Footnote 5] and affords DOD decision makers with the 
appropriate information to decide whether a weapon system is worth the 
overall investment and whether the time is right to proceed with such 
an investment. Once a total cost is known, DOD needs to secure the 
funding so it can design, produce, operate, and sustain the system.

DOD may also lack knowledge needed to make a corporate-level decision 
as to how much it should invest in SBR versus air platforms with 
similar capabilities at the time it begins the SBR acquisition program. 
In November 2003, the Air Force completed an analysis of alternatives 
(AOA) for SBR, which was supposed to evaluate whether space-or 
air-based radar platforms (such as manned and unmanned aircraft with 
radar capabilities) or a combination of both are better suited for 
tracking moving targets on land or at sea and analyze the capabilities 
and costs of each suitable option. However, DOD officials raised a 
concern that the AOA only weighed the merits of various space-based 
solutions. The Air Force decided to undertake a follow-on study to 
explore the optimal ways to gather information on ground moving targets 
from radars based in space versus air. The plan is to also use this 
follow-on study as part of DOD's preparations for submitting a fiscal 
year 2006 budget to Congress to secure funding for SBR and other radar 
systems on air platforms. A more thorough AOA, completed before the 
start of the study phase, might conceivably have determined that 
air-based radar could provide many or most of the capabilities promised 
by space-based radar but at a fraction of the cost. Moreover, this type 
of analysis could help DOD officials better decide whether SBR should 
be initiated at a later date, when critical technologies will have been 
matured, or when the communications infrastructure to support SBR will 
be available.

DOD officials have mentioned other ongoing studies that are examining 
the optimal mix between SBR and other platforms for specific 
capabilities, such as ground-moving target indication. However, it is 
unclear as to the extent these studies will be factored into the SBR 
product development start decision.

Conclusions: 

DOD has recently embarked on a discovery and exploration phase for its 
SBR program. During this period, it is critical for programs to work 
toward closing knowledge gaps about requirements, technologies, 
funding, and other resources so they can be positioned to succeed when 
DOD decides to commit to making significant investments. For SBR, this 
would mean testing technologies to the point of knowing they can work 
as intended before starting program development, securing agreement on 
requirements with the intelligence community, and fully assessing the 
cost and benefits and risks of relying on TCA and alternatives, 
including different mixes of air and space-based platforms. DOD is 
taking positive steps toward this end, but without maturing critical 
technologies or securing formal commitment on requirements, it will not 
be able to assure decision makers that the program can be completed 
within cost and schedule estimates. Should DOD decide to proceed on a 
path that leaves open important questions, including those about 
technologies, then it should do so with (1) assessments of technical 
risks and what additional resources (in terms of time and money) would 
be needed to address problems that may occur during development as well 
as what trade-offs would need to be made with other space programs 
should DOD need to invest additional resources in SBR, and (2) a formal 
commitment for providing additional resources if problems do occur.

Recommendations for Executive Action: 

To better ensure that DOD and its intelligence community partners 
obtain the additional knowledge they need to determine whether and when 
to begin the SBR acquisition program, we recommend that the Secretary 
of Defense direct the Under Secretary of the Air Force to: 

* Direct the SBR Executive Steering Group to ensure that outcomes from 
the requirements management process are formally approved and 
documented as the program proceeds through product development before 
an investment is made beyond technology and concept development for the 
SBR program. This group should identify how key document review 
comments are to be obtained and addressed and identify all the 
officials and/or organizations responsible for taking specific approval 
action. In addition, the group should establish a mechanism and time 
frame for providing approval/disapproval. Finally, the group should 
establish a formal mechanism for addressing unresolved issues as they 
relate to key program documentation, as well as how changes to approved 
requirements will be assessed.

* Modify DOD's space acquisition policy to reflect protocols for 
setting requirements when DOD undertakes programs in partnership with 
the intelligence community.

* Delay approval to commit funding to product development (key decision 
point B) for SBR until technologies have been demonstrated in a 
relevant or operational environment so DOD can more reliably estimate 
the resources needed to complete the program. If the Under Secretary 
determines that the program should go forward with less mature 
technologies, then we recommend that the Under Secretary (1) undertake 
an assessment of the backup technologies that may lessen capability and 
add cost to the program and the additional time and money that may be 
required to meet SBR's performance objectives to address those risks, 
(2) undertake an assessment of trade-offs that may need to be made with 
other space programs to assure SBR's successful outcome, and (3) secure 
formal commitments from DOD to provide funding for total estimated 
costs as well as costs estimated to address potential technical risks.

* Strengthen the ongoing study of options for tracking ground-moving 
targets by ensuring this work includes: (1) a full range of air and 
space options; (2) measures of effectiveness that would help justify 
choosing SBR over air options; and (3) the possibility of having to 
rely on TCA alternatives for space options. This work should also 
consider the results of analyses being conducted by other DOD entities 
on tracking ground-moving targets.

Agency Comments and Our Evaluation: 

We received written comments on a draft of this report from the Deputy 
Under Secretary of Defense (Programs, Requirements, and Resources) 
within the Office of the Under Secretary of Defense for Intelligence. 
DOD generally agreed with our findings and our recommendation to 
strengthen its study of SBR alternatives. DOD partially agreed with our 
recommendations to strengthen its requirement setting process for SBR 
and to demonstrate SBR technologies in a relevant or operational 
environment before committing to product development. DOD did not agree 
with our recommendation to modify its acquisition policy to strengthen 
requirements setting.

In commenting on our recommendations, DOD agreed in principle with the 
need to extensively define, analyze, and validate requirements for SBR, 
but it did not believe this necessitated a different requirements 
setting process than the one that is in place for SBR or changes to its 
space acquisition policy or that additional controls were needed within 
the program's study phase. To clarify, our recommendation was not 
intended to construct a new requirements setting process or supplant 
activities undertaken by the Joint Requirements Oversight Council or 
the Mission Requirements Board, as DOD asserts. Rather, we recommend 
that DOD build on the positive requirements setting procedures it has 
already put in place by instituting controls and mechanisms that ensure 
transparency, discipline, and accountability with requirements 
setting. As noted in our report, while DOD has taken steps to increase 
senior leader and stakeholder involvement in requirements setting, it 
is not fully documenting commitments made during the requirements 
approval process, nor has it established a process to resolve potential 
disagreements that may occur after approval. It is important that this 
discipline be instilled in the study phase and throughout the SBR 
effort. As noted in previous reports, many space programs have not been 
executed within cost and schedule estimates because of an inability to 
establish firm requirements and to make and enforce trade-off 
decisions. For SBR, the potential for difficulty in requirements 
setting is higher because of the distinct needs of the intelligence 
community and DOD's desire to integrate SBR with other radar platforms. 
Moreover, revising the acquisition policy to clearly communicate 
protocols that should be followed when DOD undertakes space programs in 
the future involving diverse users--such as the intelligence community, 
military services, industry, and/or other agencies--would further help 
DOD to rationalize requirements setting and to solidify relationships 
with users, which DOD reported was a top SBR management issue.

In regard to our recommendation to delay product development until SBR 
technologies are sufficiently matured, DOD stated that it has planned 
for critical and most other enabling technologies to be demonstrated at 
least at the component level in a relevant environment on the ground. 
DOD also stated that where technically feasible and fiscally feasible, 
it planned to pursue on-orbit demonstrations. It also stated it has 
taken some actions relating to our recommendation such as accounting 
for technical risks in the costing and budgeting process. DOD asserted, 
however, that our recommendation encourages pursuit of older, more 
proven, technologies. We recommended that DOD pursue relevant or 
operational environment demonstrations of all critical technologies and 
even an integrated system before committing to a formal acquisition 
program because this practice enables a program to align customer 
expectations with resources, and therefore minimize problems that could 
hurt a program in its design and production phase and drive up costs 
and schedule. Further, we agree that continuing to develop leading edge 
technology is important for space system capabilities. However, history 
has shown and we have repeatedly reported that conducting technology 
development within a product environment consistently delays the 
delivery of capability to the user, robs other programs of necessary 
funds through unanticipated cost overruns, and, consequently, can 
result in money wasted and fewer units produced than originally stated 
as necessary. A technology development environment is more forgiving 
and less costly than a delivery-oriented acquisition program 
environment. Events such as test "failures," new discoveries, and time 
spent in attaining knowledge are considered normal in this environment. 
Further, judgments of technology maturity have proven to be 
insufficient as the basis for accurate estimates of program risks as it 
relates to cost, schedule, and capability. Lastly, our report noted 
that DOD was taking positive actions to gain knowledge about technology 
readiness, including strengthening systems engineering, undertaking 
risk assessments, and assessing various technical concepts. Given the 
potential cost of the program, our recommendation focuses on taking 
these steps further by assessing what trade-offs may need to be made 
with other space programs should the program encounter technical 
problems that require more time and money than anticipated and securing 
commitments to provide resources needed to address such problems.

DOD's detailed comments are provided in appendix II.

We plan to provide copies of this report to the Secretary of Defense, 
the Secretary of the Air Force, and interested congressional 
committees. We will make copies available to others upon request. In 
addition, the report will be available on the GAO Web site at http://
www.gao.gov.

If you or your staff has any questions concerning this report, please 
contact me at (202) 512-4841 or Arthur Gallegos at (303) 572-7368. 
Other key contributors to the report include Tony Beckham, Cristina 
Chaplain, Lily Chin, Maria Durant, Nancy Rothlisberger, and Hai V. 
Tran.

Signed by: 

Katherine V. Schinasi:
Managing Director: 
Acquisition and Sourcing Management: 

[End of section]

Appendix I: TRL Scale for Assessing Critical Technologies: 

TRL: Basic principles observed and reported; 
TRL description: Lowest level of technology readiness. Scientific 
research begins to be translated into applied research and development 
(R&D). Examples might include paper studies.

TRL: Technology concept and/or application formulated; 
TRL description: Invention begins. Once basic principles are observed, 
practical applications can be invented. Examples are still limited to 
paper studies.

TRL: Analytical and experimental critical function and/or 
characteristic proof of concept; 
TRL description: Active R&D is initiated. This includes analytical 
studies and laboratory studies to physically validate analytical 
predictions of separate elements of the technology. Examples include 
components that are not yet integrated or representative.

TRL: Component and/or breadboard validation in laboratory environment; 
TRL description: Basic technological components are integrated to 
establish that they will work together. This is relatively "low 
fidelity" compared to the eventual system. Examples include integration 
of "ad hoc" hardware in a laboratory.

TRL: Component and/or breadboard validation in relevant environment; 
TRL description: Fidelity of breadboard technology increases 
significantly. Basic technological components are integrated with 
reasonably realistic supporting elements so that the technology can be 
tested in simulated environment. Examples include "high fidelity" 
laboratory integration of components.

TRL: System/subsystem model or prototype demonstration in a relevant 
environment; 
TRL description: Representative model or prototype system, which is 
well beyond the breadboard tested for level 5, is tested in a relevant 
environment. Represents a major step up in a technology's demonstrated 
readiness. Examples include testing a prototype in a high- fidelity 
laboratory environment or in a simulated operational environment.

TRL: System prototype demonstration in an operational environment; 
TRL description: Prototype near, or at, planned operational system. 
Represents a major step up from TRL 6, requiring demonstration of an 
actual system prototype in an operational environment such as an 
aircraft, vehicle, or space.

TRL: Actual system completed and qualified through test and 
demonstration; 
TRL description: Technology has been proven to work in its final form 
and under expected conditions. In almost all cases, this TRL represents 
the end of true system development. Examples include Developmental Test 
and Evaluation of the system in its intended weapon system to determine 
if it meets design specifications.

TRL: Actual system proven through successful mission operations; 
TRL description: Actual application of the technology in its final 
form and under mission conditions, such as those encountered in 
Operational Test and Evaluation. Examples include using the system 
under operational mission conditions. 

Source: DOD Interim Defense Acquisition Guidebook, app.6 (Oct. 30, 
2002).

[End of table]

[End of section]

Appendix II: Comments from the Department of Defense: 

Note: GAO comments supplementing those in the report text appear at the 
end of this appendix.

OFFICE OF THE UNDER SECRETARY OF DEFENSE: 
5000 DEFENSE PENTAGON: 
WASHINGTON, DC 20301-5000:

INTELLIGENCE:

Ms. Katherine V. Schinasi: 
Managing Director: 
Acquisition and Sourcing Management: 
U.S. General Accounting Office:
441 G Street, N.W.: 
Washington, D.C. 20548:

Dear Ms. Schinasi,

This is the Department of Defense (DoD) response to the GAO draft 
report, 'DEFENSE ACQUISITIONS: Space-Based Radar Effort Needs 
Additional Knowledge Before Starting Development,' dated May 25, 2004 
(GAO Code 120267/GAO-04-759). This report did an excellent and thorough 
job reviewing the Space Based Radar (SBR) program and we agree with 
many of your findings and comments; however we can only partially 
concur with the entire report, particularly your recommended actions. 
Detailed responses to these recommendations are provided in the 
attachment.

In summary, the recommendation to provide more formal documentation to 
the requirements process assumes that DoD and the Intelligence 
Community (IC) have committed to SBR as a joint (i.e., DoD/IC) program, 
which is not the case. The current SBR acquisition strategy requires an 
iterative process of reviewing several concept design proposals from 
multiple vendors to determine whether a single space radar system can 
satisfy the broad spectrum of DoD and IC requirements. This does not 
alleviate the need to extensively define, analyze, and validate 
requirements; however a process outside of, and more formalized than, 
the one currently in place is not required. Also, a modification of the 
space acquisition policy is not required specifically for this program. 
As far as your recommendation to delay funding for product development 
until SBR technologies have been demonstrated in an operational 
environment, we have planned for critical and most other enabling 
technologies to be demonstrated at least at the component level in a 
relevant environment on the ground. Where technically and fiscally 
possible and technically warranted, the JPO is pursuing on-orbit 
demonstrations. Nevertheless, we cannot accept your recommendation to 
employ a more mature technology which would produce "a lower level of 
desired performance." The SBR Joint Program Office has established a 
risk reduction and technology readiness process which ensures extensive 
testing and validation of related technologies. In addition, we are 
planning a classified demonstration which will prove the utility of 
SBR-like capabilities. If your staff has not been briefed on this 
project, we can arrange for appropriately cleared personnel from your 
office to receive this briefing. Finally, while the Air Force-conducted 
Analysis of Alternatives clearly demonstrates the utility of SBR (in a 
variety of constellations) to satisfy warfighting needs, more studies 
are required to analyze contributions of airborne assets in a variety 
of scenarios and to further refine SBR and Moving Target Indicator 
(MTI) contributions to intelligence problems. These studies are either 
underway or in various stages of completion, and both DoD and the IC 
are extensively involved. In addition, the relationship and 
dependencies of SBR and TCA are understood. The Joint Staff has tasked 
additional study of this relationship for formal review as part of the 
Joint Requirements Oversight Council process. Communications 
alternatives to TCA are an integral part of the SBR Phase A studies.

Again, I commend your staff on a professional effort, both in their 
investigation, in their dealings with DoD personnel, and in the 
preparation of the final report. My point of contact for this effort is 
Mr. Brian P. Levengood, 703-607-0423. Please contact him if you have 
any questions or comments.

Signed by:

Letitia A. Long:
Deputy Under Secretary of Defense: 
(Programs, Requirements, & Resources):

GAO DRAFT REPORT -DATED MAY 26, 2004 GAO CODE 120267/GAO-04-759:

"DEFENSE ACQUISITIONS: SPACE-BASED RADAR EFFORT NEEDS ADDITIONAL 
KNOWLEDGE BEFORE STARTING DEVELOPMENT":

DEPARTMENT OF DEFENSE COMMENTS TO THE RECOMMENDATIONS:

RECOMMENDATION 1: The GAO recommended that the Secretary of Defense 
direct the Under Secretary of the Air Force to direct the Space-Based 
Radar (SBR) Executive Steering Group to ensure that outcomes from the 
requirements management process are formally approved and documented as 
the program proceeds through product development before an investment 
is made beyond technology and concept development for the SBR program. 
The Steering Group should identify how key document review comments are 
to be obtained and addressed and identify all the officials and/or 
organizations responsible for taking specific approval action. The 
Steering Group should also establish a mechanism and time frame for 
providing approval/disapproval of requirements and a formal mechanism 
for addressing unresolved issues as they relate to key program 
documentation, as well as how changes to approve requirements will be 
addressed. (p. 17/GAO Draft Report):

DOD RESPONSE: Partially Concur. If the SBR concept development phase 
results in a satellite design and constellation that satisfactorily 
provides the capabilities needed to satisfy both Department of Defense 
(DoD) and Intelligence Community (IC) requirements, a more formal 
process, with appropriate supporting documentation may be required as 
the acquisition progresses beyond Key Decision Point (KDP) B. The 
current acquisition process (now in Phase A) includes requirements from 
both the DoD and the IC to ascertain whether a single satellite system 
can satisfy the broad spectrum of cross-community needs. It is 
imperative that the respective requirements validation processes (the 
Joint Requirements Oversight Council (JROC) for DoD, and the Mission 
Requirements Board (MRB) for the IC) function in accordance with their 
charters. The process put in place specifically to review and approve 
requirements for SBR (Requirements and Capabilities Group (RCG) and the 
Executive Steering Group (ESG)) was designed to build on the existing 
requirements validation process, not to replace it or usurp any JROC or 
MRB authorities. The inference drawn in the GAO report that the 
apparent informality of the Executive Steering Group process renders 
that process ineffective in providing direction and stability for SBR 
requirements is not correct. The senior level representation of the ESG 
(e.g., Under Secretary of Defense, Deputy Director of Central 
Intelligence, Directors of Defense Agencies, Under Secretary of the Air 
Force, etc.), militates against reversals of requirements and strategic 
direction that have been adjudicated and approved by this group. The 
Under Secretary of the Air Force has stood up the National Security 
Space Office organization to provide valuable staff support and 
integration of several functional areas and will provide documentation 
of SBR ESG findings. The GAO report also points out that the Initial 
Capabilities Document (ICD) was approved by the JROC and MRB through 
memoranda, but that neither provided written approval of the Concept of 
Operations (CONOPS). In accordance with Title X, DoD Instructions, and 
DCI Instructions; neither the JROC nor the MRB have formal approval 
authority over acquisition program CONOPS. However, the JROC does 
routinely review CONOPS as part of the supporting documentation for 
capability documents and, in response to the Under Secretary of the Air 
Force's request, noted their support for using the current CONOPS for 
Phase A "Concept Development" in formal memoranda, JROCM 221-03. There 
is a concerted and cooperative effort between the DoD and IC to come to 
a convergence of capability needs using the RCG process to draft the 
Capabilities Development Document (CDD). The CDD is the formal 
statement of capability needs required for a KDP B decision to enter 
Phase B "Development." In accordance with CJCSI 3170 and DCID 1/10, the 
final draft CDD will be submitted to the JROC and MRB prior to KDP B 
for formal review, comment adjudication, and approval.

We believe the processes in place to validate requirements for the DoD 
and IC are adequate and should not be replaced. Further, the SBR-unique 
process is sufficient, when acting in concert with the JROC and MRB, to 
adjudicate any differences and to support Phase A of the SBR 
acquisition process. We partially concur with your recommendation that 
a joint single SBR acquisition may require a more formalized, document-
supported process beyond Phase A.

RECOMMENDATION 2: The GAO recommended that the Secretary of Defense 
direct the Under Secretary of the Air Force to modify DOD's space 
acquisition policy to reflect protocols for setting requirements when 
DOD undertakes programs in partnership with the intelligence community. 
(p. 17/GAO Draft Report):

DOD RESPONSE: Non-Concur. The Under Secretary of the Air Force also 
acts as the Director of the National Reconnaissance Office (NRO). The 
National Security Space (NSS) Acquisition Policy (03-01) combines 
elements of the DoD acquisition process with those used by the NRO. 
This process outlined in NSS 03-01 also requires Key Decision Points 
and Defense Space Acquisition Boards which include IC participation. 
Further, the term "partnership" throughout the GAO report implies a 
programmatic commitment which does not currently exist. SBR is wholly 
funded in the Defense budget (primarily in the Air Force Tactical 
Intelligence and Related Activities and partially in the Joint Military 
Intelligence Program). We believe that, even if the IC agreed to a co-
funding arrangement for SBR, NSS 03-01 sets out procedures which do not 
need to be modified specifically for SBR. NSS 03-01 supports the steps 
already underway to improve joint requirements protocol. An example is 
that NSS Acquisition Policy 03-01 embraces the new Joint Capabilities 
Integration and Development System (JCIDS) concept as outlined in CJCSI 
3170.01d, which talks extensively about working closer with the 
Intelligence Community MRB. Under this construct, the JROC reviews 
programs at the request of the USecAF (as DOD Space Milestone Decision 
Authority (MDA)) or the MRB. When national intelligence capabilities 
exist, capabilities integration and development efforts by the 
Intelligence Community are encouraged to follow a parallel path between 
the defense and national intelligence communities with resulting 
capabilities documents validated and approved by the JROC and the 
Director of Central Intelligence MRB.

Further, the Functional Capability Boards Principal Membership roster 
includes positions for, when appropriate, Defense Intelligence Agency 
representatives, the Under Secretary of the Air Force (as the DOD Space 
Milestone Decision Authority), the Under Secretary of Defense for 
Intelligence, and MRB Executive Staff. JCIDS products (e.g., ICD, CDD, 
CPD) are required as part of the DSAB/KDP process described in NSS 03-
01. Further, the dual responsibilities of the USecAF/DNRO facilitate 
management of SBR acquisition while protecting DoD and IC equities and 
providing the capabilities required to satisfy the cross-community 
requirements.

RECOMMENDATION 3: The GAO recommended that the Secretary of Defense 
direct the Under Secretary of the Air Force to delay approval to commit 
funding to product development (key decision point B) for SBR until 
technologies have been demonstrated in a relevant or operational 
environment so DOD can more reliably estimate the resources needed to 
complete the program. If the Under Secretary determines that the 
program should go forward with less mature technologies, then we 
recommend that the Under Secretary: (1) undertake an assessment of the 
backup technologies which may lessen capability and add cost to the 
program and the additional time and money that may be required to meet 
SBR's performance objectives to address those risks; (2) undertake an 
assessment of trade-offs that may need to be made with other space 
programs to assure SBR's successful outcome; and (3) secure formal 
commitments from DOD to provide funding for total estimated costs as 
well as costs estimated to address potential technical risks. 
(p. 17/GAO Draft Report):

DOD RESPONSE: Partially Concur. We agree that SBR product development 
should not proceed until technologies have been sufficiently 
demonstrated; however, The Secretary of Defense need not direct the 
Under Secretary of the Air Force to delay approval of KDP-B to meet GAO 
recommended technology maturity levels, because the current program 
baseline already includes demonstration of all critical and most other 
enabling technologies in a relevant or operational environment prior to 
KDP-B. Further, while NSS Acquisition Policy 03-01 does state that 
technology development is part of Phase B, this phase is primarily 
focused on risk reduction; component level technology development is 
finished by PDR. These risk reductions activities are similar to the 
DoDI 5000.2 Phase B activities to reduce integration and manufacturing 
risks. In addition, technology maturity is assessed at each KDP:

"At each KDP, the program office should identify the key technology 
components of the system and provide their assessment of the maturity 
of each key component using the Technology Readiness Level (TRL) method 
identified in the Interim DoD Acquisition Guidebook. The IPAT will 
review the program office assessment and determine if, in their view, 
all key technology components of the program have been identified. The 
IPA will also provide its own independent assessment of the maturity of 
the key components using the TRL method. The intent is not to require a 
specific TRL for each key component in order to proceed into the next 
acquisition phase, but to instead allow for the DoD Space MDA to be 
made knowledgeable of the state of key component maturity so 
appropriate direction can be given in the ADM for additional technology 
maturation/risk reduction activities."

The GAO Report recommends that we pursue lower risk technology which 
admittedly "would result in a lower level of desired performance." 
(p.14) Concepts developed under Phase A should maximize capability and 
employ technological advances, but they must be affordable and 
producible, not technically feasible at some future date. We believe 
the Technology Readiness Level processes in place will ensure that. If 
the MDA, based on the findings and recommendations of the Independent 
Cost Assessment Team, Independent Program Assessment Team, and the 
larger Defense Space Acquisition Board process, is not convinced the 
technology is mature, he will provide the appropriate direction to the 
program to ensure maturation occurs, including possibly delaying entry 
into the next phase until ready or directing the program to conduct 
additional reviews to assess maturity within a given timeframe.

Key and critical and most other enabling technologies will be 
demonstrated at least at the component level in a relevant environment 
on the ground. Select technologies have been identified for 
demonstration in a relevant environment at a system or subsystem level, 
and, where technically and fiscally possible and technically warranted, 
the JPO is pursuing on-orbit demonstrations. A classified program plans 
to demonstrate certain aspects of an SBR MTI capability. Appropriately 
cleared members of your staff are invited to receive this briefing.

The SBR Program is putting a major focus on technology maturity to 
mitigate the performance, schedule and cost risks represented by the 
critical and most other enabling technologies. Going back as far as the 
Discoverer II (DII) activities and continuing through the recently 
completed Concept Definition activities and the on-going Phase A 
activities, the SBR Program has, and is continuing, to invest heavily 
in technology maturation. One example of continued technology 
maturation is the Electronically Scanned Array (ESA) Technology 
development that was initiated under DII activities, and has been 
leveraged since then by the JPO. To ensure that the risks remaining are 
accounted for in the costing and budgeting process, the cost estimating 
approach includes discrete technology related development risks and 
more general cost estimating uncertainties due to technical and 
schedule issues. Our cost estimating approach has been validated by the 
OSD CAIG at the 18 Mar 04 USECAF SBR Cost Review.

(1) The SBR JPO is aggressively pursuing technology paths that will 
best satisfy SBR requirements. At the same time, the JPO is maintaining 
back up technologies, which have been proven on other programs, to 
ensure there are mitigation paths if the desired technologies run into 
issues. Phase A also includes a robust systems engineering effort which 
will maintain technology focus and ensure overall performance does not 
suffer even if the JPO has to sub-optimize with older backup 
technologies. The technology maturity assessment process described in 
NSS Acquisition Policy 03-01 will ensure an objective assessment of the 
most appropriate technology path for program execution. The JPO cost 
and schedule estimates will be updated for KDP-B to reflect the chosen 
path.

(2) According to analysis thus far, a delay in the deployment of TCA is 
something SBR could absorb without substantial impact. Since the ADM 
was released by Mr. Teets on 19 Aug 2003, SBR JPO has been evaluating 
an extensive trade space for its communications architecture during its 
deployment period. Deliverables due by KDP-B include one schema that 
incorporates TCA and another that allows SBR to function independently 
during its deployment phase. Current trades for SBR's initial 
deployment period include leveraging residual national resources and 
future MILSATCOM assets or incorporating RF downlink capabilities 
directly from SBR for dissemination in theater or through the future 
Global Information Grid. Furthermore, the prime contractors for SBR are 
incorporating and expanding on the ongoing analysis done by the JPO.

(3) Both the independent program assessment team and the independent 
cost assessment team stated that the FYDP funding was adequate for 
Phase A efforts. The on-going Phase A efforts with industry will result 
in more detailed technical and programmatic baseline definition. This 
more detailed definition will support KDP-B, the generation of an 
acquisition program baseline, and updated cost estimates and supporting 
budgets.

We agree that SBR contains some technology risk, but we believe we can 
reduce this risk sufficiently to proceed with our desired SBR 
capabilities without reducing performance at this point in the program. 
Therefore, we can only partially concur with this recommendation.

RECOMMENDATION 4: The GAO recommended that the Secretary of Defense 
direct the Under Secretary of the Air Force to strengthen ongoing study 
of options for tracking ground-moving targets by ensuring this work 
includes: (1) a full range of air and space options; (2) measures of 
effectiveness that would help justify choosing SBR over air options; 
and (3) the possibility of having to rely on Transformational 
Communications Architecture alternatives for space options. 
(P. 17/GAO Draft Report):

DOD RESPONSE: Concur. We agree that SBR studies must include air/space 
options, comparable measures of effectiveness, and communications 
considerations. We believe that studies currently underway incorporate 
these criteria; however, not all of these studies are being performed 
under the auspices of the Under Secretary of the Air Force. Therefore, 
direction from the Secretary of Defense to the Under Secretary of the 
Air Force to incorporate these criteria would be redundant in some 
cases and not relevant in others. The Air Force Analysis of 
Alternatives proved the utility of SBR to warfighter requirements, and 
it also included airborne collectors in certain scenarios; however, it 
was not chartered to and did not undertake an extensive evaluation of 
specific airborne platforms in cooperative collection operations. For 
this reason, a follow-on Air Force study as well as an OSD Programs 
Analysis and Evaluation Study are looking more specifically at aircraft 
contributions. In addition, the IC continues to work with the National 
Geospatial Intelligence Agency to ascertain the contribution of MTI to
intelligence problems. We concur that measures of effectiveness are 
critical in understanding the relative contributions of each collection 
asset and will critically review the results of these ongoing studies 
to ensure valid comparisons are being made. The relationship of SBR and 
TCA are of concern to DoD, and the JROC has recently sanctioned a study 
to analyze the interdependencies and impacts of SBR and TCA remaining 
in synch. SBR's key dependency on TCA is an area that will require 
close monitoring and review prior to a KDP B decision. The JROC will 
rely heavily on the Battlespace Awareness and Net Centric Functional 
Capability Boards to provide a joint assessment of related trade 
analysis conducted during Phase A. SBR Phase A studies, as directed by 
USecAF, are looking at a number of communications alternatives to TCA. 
The SBR program has a flexible communication strategy intended to 
reduce dependencies on any specific TCA implementation at this early 
stage (Phase A) of the program. Initial SBR constellation 
configurations are not expected to be fully dependent on 
Transformational Communications. Specific risk mitigation alternatives 
have been identified in order to facilitate SBR operations during the 
initial SBR deployment phase while the TCA is also being deployed.

GAO's Comments: 

The following are GAO's comments on the Department of Defense's letter 
dated June 29, 2004.

1. DOD stated that DOD does not require formal approval for the 
concepts of operations from the Joint Requirements Oversight Council or 
the Mission Requirements Board, but noted that the Joint Requirements 
Oversight Council communicated agreement in a memo. As we reported, the 
Under Secretary of the Air Force requested that both DOD and the 
intelligence community approve the initial capabilities document and 
concept of operations in light of the complexity of SBR's acquisition 
process, the partnership with the intelligence community, and the 
proposed integration with other radar platforms.

2. DOD stated that it is not engaged in a partnership with the 
intelligence community on SBR, as our report states. Specifically, DOD 
stated that SBR is wholly funded in the defense budget and that a 
programmatic commitment with the intelligence community does not exist. 
DOD's SBR System Acquisition Strategy was signed by senior-level 
officials from DOD, National Reconnaissance Office, and the National 
Geospatial-Intelligence Agency and approved on January 14, 2004. This 
strategy states that the Air Force, in close partnership with the 
National Reconnaissance Office and National Geospatial-Intelligence 
Agency, is responsible for leading development of an SBR capability. 
This strategy further identifies the responsibilities related to SBR 
that each mission partner (National Reconnaissance Office and National 
Geospatial-Intelligence Agency) is supposed to carry out. We disagree 
with DOD's assertion that these organizations must provide funding to 
SBR in order to consummate a partnership. Because SBR is being 
justified on the basis of the system's ability to provide intelligence, 
surveillance, and reconnaissance products to both DOD and the 
intelligence community, the part of the budget used is not relevant to 
our finding.

To clarify, we did not recommend that DOD pursue lower risk 
technologies that would result in lower levels of desired performance. 
Instead, we reported that DOD might have to resort to using backup 
technologies if the current ones prove to be problematic during product 
development. We recommended that DOD should assess the cost to the 
program of having to use the backup technologies DOD has already 
identified in terms of time and money.

[End of section]

FOOTNOTES

[1] U.S. General Accounting Office, Military Space Operations: Common 
Problems and Their Effects on Satellite and Related Acquisitions, GAO-
03-825R (Washington, D.C.: June 2, 2003).

[2] U.S. General Accounting Office, Space Acquisitions: Committing 
Prematurely to the Transformational Satellite Program Elevates Risks 
for Poor Cost, Schedule, and Performance Outcomes, GAO-04-71R 
(Washington, D.C.: Dec. 4, 2003).

[3] U.S. General Accounting Office, Military Space Operations: Common 
Problems and Their Effects on Satellite and Related Acquisitions, GAO-
03-825R (Washington, D.C.: June 2, 2003).

[4] U.S. General Accounting Office, Best Practices: Better Management 
of Technology Development Can Improve Weapon System Outcomes, GAO/
NSIAD-99-162 (Washington, D.C.: July 30, 1999).

[5] U.S. General Accounting Office, Defense Acquisitions: Improvements 
Needed in Space Systems Acquisition Management Policy, GAO-03-1073 
(Washington, D.C.: Sept. 15, 2003).

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office

441 G Street NW, Room LM

Washington, D.C. 20548: 

To order by Phone: 

	

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm

E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director,

NelliganJ@gao.gov

(202) 512-4800

U.S. Government Accountability Office,

441 G Street NW, Room 7149

Washington, D.C. 20548: