This is the accessible text file for GAO report number GAO-04-498 
entitled 'Air Force Depot Maintenance: Improved Pricing and Cost 
Reduction Practices Needed' which was released on June 17, 2004.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to the Chairman, Subcommittee on Defense, Committee on 
Appropriations, House of Representatives: 

June 2004: 

AIR FORCE DEPOT MAINTENANCE: 

Improved Pricing and Cost Reduction Practices Needed: 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-04-498]: 

GAO Highlights: 

Highlights of GAO-04-498, a report to the Chairman, Subcommittee on 
Defense, Committee on Appropriations, House of Representatives 

Why GAO Did This Study: 

The Air Force depot maintenance activity group in-house operations 
generate about $5 billion in annual revenue principally by repairing 
aircraft, missiles, engines, and other assets. In doing so, the group 
operates under the working capital fund concept, where customers are to 
be charged the anticipated costs of providing goods and services to 
them. The group’s average price for in-house work almost doubled 
between fiscal years 2000 and 2004 from $119.99 per hour to $237.84 per 
hour. GAO was asked to determine (1) what factors were primarily 
responsible for the price increase, (2) if the prices charged recovered 
the reported actual costs of performing the work, and (3) if the Air 
Force has taken effective steps to improve efficiency and control the 
activity group’s costs.

What GAO Found: 

GAO identified five primary factors that showed why the Air Force depot 
maintenance activity group’s average price increased from $119.99 per 
direct labor hour of work in fiscal year 2000 to $237.84 per hour in 
fiscal year 2004. An increase in material costs accounted for about 67 
percent of the total increase and was by far the most significant 
factor. The Air Force has identified some of the causes of the higher 
material costs such as aging aircraft, but has yet to complete an 
effective and comprehensive analysis of material cost increases. As a 
result, it (1) cannot quantify the extent to which individual causes 
contributed to higher costs and (2) does not know if it has identified 
all of the major causes.

GAO’s analysis of the other four factors showed that (1) the increase 
in labor costs was due largely to events beyond the group’s control, 
such as annual salary increases, (2) the increase in business 
operations costs was due partly to costs related to implementing a new 
accounting system, (3) a surcharge intended to recoup anticipated 
losses on work carried over from the previous fiscal year may have been 
unnecessary, and (4) a surcharge intended to generate additional cash 
in fiscal year 2004 for the Air Force Working Capital Fund was 
unnecessary. GAO’s analysis showed that due in part to these surcharges 
(1) the Air Force Working Capital Fund, which includes the depot 
maintenance and several other activity groups, had a $2.5 billion cash 
balance as of January 31, 2004 and (2) this balance was more than $1.3 
billion higher than the maximum level allowed by DOD policy. Either the 
Office of the Secretary of Defense or the Congress could use this 
unneeded cash to satisfy other requirements. DOD officials told us that 
they are exploring options on what to do with the excess cash.

GAO’s analysis of the group’s financial reports showed that prices 
charged customers were not set high enough to recover about $1.1 
billion of the group’s reported costs for fiscal years 2000 through 
2003. The activity group is required by DOD policy to set prices to 
recoup the cost of doing work. However, Air Force officials informed us 
that the prices were artificially constrained to help ensure that the 
group’s customers would be able to get needed work done with the amount 
of funds provided to them through the budget process. The Air Force 
changed its sales price development philosophy to bring prices charged 
customers in fiscal year 2004 more in line with operating costs. In 
addition, the Air Force allowed out-of-cycle price increases in fiscal 
years 2002 and 2003 to alleviate projected losses.

Further, the Air Force Materiel Command has not been successful in its 
efforts to control costs. Although several promising initiatives are 
underway, the Command has not (1) developed a successful methodology 
for analyzing the reasons for the rapid material cost increase and (2) 
effectively utilized an established data repository for sharing cost-
saving ideas among the three air logistics centers on process 
improvements and to demonstrate whether its cost savings initiatives 
have been successful.

What GAO Recommends: 

GAO is making recommendations to the Air Force to (1) set prices so 
that the depot maintenance activity group recovers all estimated costs 
and (2) control the activity group’s costs and improve the coordination 
and information on initiatives. GAO is also making a recommendation to 
the Department of Defense to reduce excess cash in the Air Force 
Working Capital Fund. GAO is also suggesting that the Congress consider 
taking action to reduce the amount of excess cash in the Air Force 
Working Capital Fund if DOD does not adequately reduce the cash 
balance. DOD concurred with all the recommendations. 

www.gao.gov/cgi-bin/getrpt?GAO-04-498.

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Gregory D. Kutz at (202) 
512-9505 or Kutzg@gao.gov or William M. Solis at (202) 512-8365.

[End of section]

Contents: 

Letter: 

Results in Brief: 

Background: 

Factors Causing Prices to Increase: 

Prices Charged Customers Were Not Set High Enough to Recover Costs: 

Air Force Depot Maintenance Needs More Systematic and Effective 
Processes for Controlling Costs: 

Conclusions: 

Matter for Congressional Consideration: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendixes: 

Appendix I: Scope and Methodology: 

Appendix II: Comments from the Department of Defense: 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Acknowledgments: 

Tables: 

Table 1: Factors Responsible for the Increase in the Air Force Depot 
Maintenance Activity Group's Composite Hourly Sales Price between 
Fiscal Years 2000 and 2004: 

Table 2: Air Force Depot Maintenance Activity Group's Budgeted Labor 
Expense Rates for Fiscal Years 2000 through 2004: 

Table 3: Activity Group's Reported Losses and Additional Funds Received 
to Recoup Losses from Fiscal Years 2000 to 2003: 

Table 4: Air Logistics Centers' Revised Fiscal Year 2003 Sales Prices 
for Selected Workloads due to Out-of-Cycle Price Increases: 

Figure: 

Figure 1: Comparison of the Air Force Depot Maintenance Activity Group's 
Budgeted and Reported Actual Material Expense Rates for Fiscal Years 
2000 through 2004: 

Letter June 17, 2004: 

The Honorable Jerry Lewis: 
Chairman, Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

Dear Mr. Chairman: 

The Air Force depot maintenance activity group supports combat 
readiness by providing services necessary to keep Air Force units 
operating worldwide. The group's in-house operations[Footnote 1] 
generate about $5 billion in annual revenue principally by repairing 
and overhauling a wide range of assets, including fighter aircraft such 
as the F-15, intercontinental ballistic missiles such as the Minuteman 
and Peacekeeper missiles, jet aircraft engines, electronics, avionics, 
software, and inventory items for the military services, other 
government agencies, and foreign governments. For example, in fiscal 
year 2002, the Air Force reported that the depot maintenance activity 
group's three air logistics centers' in-house operations performed 
major modifications on 852 aircraft, overhauled 515 aircraft engines, 
and repaired 352,995 inventory items. In doing so, the group operates 
under the working capital fund concept, where customers are to be 
charged for the anticipated full cost of goods and services. The group 
performs its in-house operations primarily at the three air logistics 
centers--the Oklahoma City Air Logistics Center, Tinker Air Force Base, 
Oklahoma; the Ogden Air Logistics Center, Hill Air Force Base, Utah; 
and the Warner Robins Air Logistics Center, Robins Air Force Base, 
Georgia.

The activity group's average price for in-house work almost doubled 
between fiscal years 2000 and 2004. Specifically, according to the 
activity group's budget documents, the average price per direct labor 
hour of work accomplished (composite sales rate)[Footnote 2] increased 
from $119.99 per hour for fiscal year 2000 to $237.84 per hour for 
fiscal year 2004, or about 98 percent.[Footnote 3] Because the activity 
group's customers are expected to request about 20.8 million hours of 
in-house work in fiscal year 2004, this means that customers will have 
to pay about $4.9 billion for work that they would have paid about $2.5 
billion in fiscal year 2000.

As requested and agreed to with your office, this report discusses 
three issues related to this large price increase. Our objectives were 
to determine (1) what factors were primarily responsible for the price 
increase, (2) if the prices charged customers during fiscal year 2000 
through fiscal year 2003 recovered the reported actual costs of 
performing the work, and (3) if the Air Force has taken effective steps 
to improve efficiency and control the activity group's costs. Our 
review was performed from June 2003 through April 2004 in accordance 
with U.S. generally accepted government auditing standards. Most of the 
financial information in this report is budget data obtained from 
official Air Force budget documents. The accounting data used in this 
report was obtained from official Air Force accounting reports. 
Although we did not validate the accuracy of the underlying 
transactions that made up the summary level data, the budget and 
accounting information is used by the Air Force, the Department of 
Defense (DOD), and congressional committees to make decisions regarding 
the amount of funds customers receive to purchase goods and services 
from the depot maintenance activity group. Further details on our scope 
and methodology can be found in appendix I. We requested comments on a 
draft of this report from the Secretary of Defense or his designee. 
Written comments from the Deputy Comptroller for Program Budget are 
reprinted in appendix II.

Results in Brief: 

Our work showed that the sales price increase was due primarily to the 
following five factors, in descending order of significance: (1) higher 
material costs, (2) higher labor costs, (3) higher business operations 
costs (non-labor, non-material overhead costs), (4) a surcharge 
intended to recoup anticipated losses on work carried over from the 
previous fiscal year (carryover surcharge), and (5) a surcharge to 
generate additional cash (cash surcharge). By far the most significant 
of these factors was higher material costs, which accounted for about 
67 percent of the total increase. Air Force depot maintenance officials 
provided anecdotal evidence to show that the higher material costs were 
caused at least partly by (1) the need to replace component parts more 
frequently because of both safety concerns and the aging of aircraft 
and engines and (2) increases in the prices that the depot maintenance 
activity group must pay its suppliers for component parts. However, 
because Air Force depot maintenance officials have yet to complete an 
effective and comprehensive analysis to determine the underlying causes 
of why material costs have increased, they cannot fully quantify the 
impact of the causes that they have identified and do not know if they 
have identified all of the major causes.

Our analysis of the other four factors showed that (1) the increase in 
labor costs was caused largely by things that were beyond the activity 
group's control, such as annual salary increases and health care costs 
for federal employees, (2) the increase in business operations costs 
was for such things as the repair and modernization of equipment and 
facilities and costs related to the implementation of a new accounting 
system, (3) the fiscal year 2004 carryover surcharge was probably too 
high and may have been unnecessary, and (4) the fiscal year 2004 cash 
surcharge was unnecessary. Our analysis also showed that due in part to 
these surcharges, the Air Force Working Capital Fund--which includes 
the depot maintenance activity group and several other activity groups-
-had a cash balance of $2.5 billion as of January 31, 2004, which was 
more than $1.3 billion higher than the maximum level allowed by DOD 
policy. Either the Office of the Secretary of Defense or the Congress 
could use this unneeded cash to satisfy other requirements.

Our analysis of the activity group's financial reports also showed that 
prices charged customers were not set high enough to recover about $1.1 
billion of the group's reported costs for fiscal years 2000 through 
2003. The activity group, like other working capital fund activities, 
is required by DOD policy to set the prices it charges customers to 
recoup the cost of doing the work. However, Air Force officials 
informed us that the prices were artificially constrained to help 
ensure that the activity group's customers would be able to get needed 
work done with the amount of funds provided to them through the budget 
process. In part, because the sales prices were set too low during this 
period, the activity group lost $1.1 billion. To recoup the losses, 
customers paid about $1 billion of their existing funds (primarily 
operation and maintenance funds) during fiscal years 2000, 2001, and 
2002. The $1 billion was billed and collected by the activity group and 
was not included in the prices. The Air Force changed its sales price 
development philosophy in 2002 in an effort to bring prices charged 
customers in fiscal year 2004 more in line with operating costs. In 
addition, the Air Force allowed out-of-cycle price increases in fiscal 
years 2002 and 2003 to alleviate projected losses.

The Air Force has not taken effective steps to control the activity 
group's costs. Although several promising initiatives are underway, our 
analysis showed that the Air Force Materiel Command has been unable to 
develop an effective methodology for identifying and analyzing the 
reasons for material cost increases. In addition, the Command has also 
not effectively utilized the data repository established to enable the 
three centers to share cost-saving ideas and to demonstrate whether its 
cost saving initiatives have been successful.

We are making a recommendation to the Secretary of Defense to take 
action to reduce the amount of excess cash in the Air Force Working 
Capital Fund. We are also making recommendations to the Air Force to 
(1) follow DOD's requirement to set prices so that the depot 
maintenance activity group recovers all estimated costs, (2) develop 
and complete a viable, systematic methodology for analyzing material 
cost variances, and (3) enter all process improvement initiatives and 
related data into the data repository so that the Air Force can track 
the costs and savings associated with the initiatives to determine 
whether they have been effective. We also suggest that the Congress 
consider taking action to reduce the amount of excess cash in the Air 
Force Working Capital Fund if DOD does not reduce the cash balance to 
the 7 to 10 day requirement. In its comments on a draft of this report, 
DOD concurred with all the recommendations. DOD has reduced the excess 
cash in the Air Force Working Capital Fund by transferring $1.1 billion 
of the excess cash out of the Fund in April 2004. However, the Air 
Force Working Capital Fund still had about $400 million of excess cash 
as of the end of April 2004. We still suggest that the Congress 
continue to monitor the working capital fund cash balances and take 
action to reduce the amount of excess cash if the balances continue to 
be in excess of amounts necessary.

Background: 

The Air Force depot maintenance activity group is part of the Air Force 
Working Capital Fund, a revolving fund that relies on sales revenue 
rather than direct congressional appropriations to finance its 
operations. DOD policy requires working capital fund activity groups to 
(1) establish sales prices that allow them to recover their expected 
costs from their customers and (2) operate on a break-even basis over 
time--that is, not make a profit nor incur a loss. DOD policy also 
requires the activity group to establish its sales prices prior to the 
start of each fiscal year and to apply these predetermined or 
"stabilized" prices to most orders received during the year--regardless 
of when the work is actually accomplished or what costs are actually 
incurred. For the depot maintenance activity group, DOD policy also 
requires the group to recoup unbudgeted losses of $10 million or more 
in the year in which they occurred. In the case of losses that occur in 
the fourth quarter, the losses are to be recovered in the first quarter 
of the next fiscal year.

Developing accurate prices is challenging since the process to 
determine the prices begins about 2 years in advance of when the work 
is actually received and performed. In essence, the activity group's 
budget development has to coincide with the development of its 
customers' budgets so that they both use the same set of assumptions. 
To develop prices, the activity group estimates (1) labor, material, 
overhead, and other costs based on anticipated demand for work as 
projected by customers, (2) total direct labor hours for each type of 
work performed, such as aircraft, engines, and repairable inventory 
items, (3) the workforce's productivity, and (4) savings due to 
productivity and other cost avoidance initiatives. In order for an 
activity group to operate on a break-even basis, it is extremely 
important that the activity group accurately estimate the work it will 
perform and the costs of performing the work. Higher-than-expected 
costs or lower-than-expected customer demand for goods and services can 
cause the activity group to incur losses. Conversely, lower-than-
expected costs or higher-than-expected customer demand for goods and 
services can result in profits. With sales prices based on assumptions 
that are made as long as 2 years before the prices go into effect, some 
variance between expected and actual costs is inevitable.

The Activity Group's Financial Reports Are Not Accurate: 

We have previously reported that DOD has had long-standing problems in 
preparing accurate working capital fund financial reports. The DOD 
Inspector General and/or the Air Force Audit Agency have not been able 
to express an opinion on the reliability of the working capital fund's 
financial statements for fiscal years 1993 through 2003. The auditors 
reported that the financial information was unreliable and financial 
systems and processes, as well as associated internal control 
structures, were inadequate to produce reliable financial information. 
The Air Force recognized that the existing legacy depot maintenance 
accounting systems that were designed in the 1960s and 1970s did not 
produce usable, complete, reliable, timely, consistent, and auditable 
information. According to the Air Force, among other things, these 
systems (1) were not transaction driven, (2) did not capture costs at 
the task level, and (3) did not produce accurate financial statements.

To help improve the depot maintenance activity group's financial 
management operations, in January 1998, the Assistant Secretary of the 
Air Force for Financial Management approved the implementation of the 
Depot Maintenance Accounting and Production System--which includes an 
accounting system called the Defense Industrial Financial Management 
System (DIFMS) that originally belonged to the Navy--at the depots 
located at the air logistics centers. According to the Air Force, this 
system is designed to provide the accurate task-level cost data that 
are needed to support (1) financial analysis and cost management and 
(2) the development of prices that more accurately reflect the cost of 
providing goods and services to customers. The Air Force is in the 
process of implementing this system and plans to complete the 
implementation during fiscal year 2004.

Factors Causing Prices to Increase: 

We identified five factors that accounted for about 95 percent of the 
sales price increase from $119.99 per direct labor hour[Footnote 4] in 
fiscal year 2000 to $237.84 per hour in fiscal year 2004.[Footnote 5] 
By far the most significant of these factors was material costs, which 
accounted for about 67 percent of the total increase. Air Force depot 
maintenance officials have yet to complete an effective and 
comprehensive analysis to determine the underlying causes of the 
material cost increases. Our analysis of the other four factors 
identified a variety of underlying causes, some of which were beyond 
the activity group's control, such as rising health care costs and 
maintenance and modernization of equipment and facilities. However, our 
analysis of the two factors that involved surcharges determined that 
the carryover surcharge (based on anticipated losses on work carried 
over from the previous fiscal year) was probably too high for fiscal 
year 2004 and may have been unnecessary, while the fiscal year 2004 
cash surcharge was unnecessary and should not have been added to the 
depot's composite hourly sales price. Details on the five factors 
follow.

* Higher budgeted material costs accounted for about 67 percent of the 
total increase in the composite hourly sales price. Air Force depot 
maintenance officials provided anecdotal evidence to show that the 
higher material costs were caused at least partly by (1) the need to 
replace component parts more frequently because of both safety concerns 
and the aging of aircraft and engines and (2) increases in the prices 
that the depot maintenance activity group must pay its suppliers for 
component parts. However, because Air Force depot maintenance officials 
have not completed a comprehensive analysis to determine the underlying 
causes of why their material costs have increased, they cannot quantify 
the impact of the identified causes and are unsure if they have 
identified all of the major causes.

* Higher budgeted labor costs accounted for about 10 percent of the 
increase in the activity group's composite hourly sales price. Our 
analysis showed that the higher labor costs were caused largely by 
factors beyond the activity group's control, such as annual salary 
increases for federal employees and rising health care costs.

* Higher non-labor, non-material overhead costs, which the Air Force 
calls business operations costs, accounted for about 8 percent of the 
total increase. Our analysis showed that the primary causes were (1) 
costs related to the implementation of a new accounting system and (2) 
the fact that the fiscal year 2004 budget provided significant 
increases in several areas where expenditures had been constrained for 
several years, such as the maintenance and modernization of equipment 
and facilities.

* An increase in the surcharge included in the composite hourly sales 
prices to recoup anticipated losses on work carried over from the 
previous fiscal year (carryover surcharge) accounted for about 7 
percent of the total increase in the sales price. Our analysis showed 
that the fiscal year 2004 carryover surcharge was probably too high and 
may have been unnecessary.

* An increase in the surcharge included in the composite hourly sales 
prices to generate additional cash (cash surcharge) accounted for about 
3 percent of the total increase in the sales price. Our analysis also 
showed that the fiscal year 2004 cash surcharge was unnecessary because 
the Air Force Working Capital Fund's $2.5 billion cash balance as of 
January 31, 2004, was already more than $1.3 billion higher than the 
maximum level allowed by DOD policy. Either the Office of the Secretary 
of Defense or the Congress could use this unneeded cash to satisfy 
other requirements.

Table 1 shows the impact these factors had on the group's composite 
sales price. As table 1 also shows, about 5 percent of the price 
increase was due to factors we either did not identify or could not 
quantify.

Table 1: Factors Responsible for the Increase in the Air Force Depot 
Maintenance Activity Group's Composite Hourly Sales Price between 
Fiscal Years 2000 and 2004: 

Factor: Higher material costs; 
Impact on the composite sales price: $78.50; 
Percent of total: 67%.

Factor: Higher labor costs; 
Impact on the composite sales price: 11.86; 
Percent of total: 10%.

Factor: Higher business operations costs; 
Impact on the composite sales price: 9.64; 
Percent of total: 8%.

Factor: Higher carryover surcharge; 
Impact on the composite sales price: 8.00; 
Percent of total: 7%.

Factor: Higher cash surcharge; 
Impact on the composite sales price: 3.55; 
Percent of total: 3%.

Factor: Other; 
Impact on the composite sales price: 6.30; 
Percent of total: 5%.

Total increase; 
Impact on the composite sales price: $117.85; 
Percent of total: 100%. 

Source: Air Force Materiel Command.

[End of table]

Spiraling Material Costs Are Primary Cause of Price Increases, but 
Further Analysis Is Needed to Fully Identify Underlying Causes: 

As shown in table 1, although many factors contributed to the increase 
that occurred in the composite hourly sales price for fiscal years 2000 
through 2004, higher budgeted material costs were, by far, the most 
significant. Further, our analysis showed that higher budgeted material 
costs had an even greater impact on some workloads. For example, the 
sales price for the repair of E-3 airborne warning and control system 
(AWACS) aircraft increased from $119.69 per hour in fiscal year 2000 to 
$330.06 per hour in fiscal year 2004, about 176 percent, and the price 
for the repair of F108-100 engines used in the KC-135 aircraft 
increased from $183,240 per engine in fiscal year 2000 to $1,214,124 
per engine in fiscal year 2004, about 563 percent. Figure 1 shows the 
activity group's budgeted and reported actual material costs per direct 
labor hour of work accomplished (material expense rate) for fiscal 
years 2000 through 2004. While Air Force depot maintenance officials 
can provide anecdotal evidence on why the activity group's overall 
material costs have increased, they have yet to complete an effective 
and comprehensive analysis to determine why material costs have 
increased.

Figure 1: Comparison of the Air Force Depot Maintenance Activity 
Group's Budgeted and Reported Actual Material Expense Rates for Fiscal 
Years 2000 through 2004: 

[See PDF for image]

Note: Based on Air Force Materiel Command data.

[A] Reported actual material expense rate for fiscal year 2004 is as of 
December 31, 2003.

[End of figure]

The Air Force Has Identified Some of the Causes of Material Cost 
Increases: 

Air Force depot maintenance officials believe the activity group's 
higher material costs can be attributed, to a large extent, to 
increased material usage that has been caused by (1) the aging of the 
Air Force's aircraft and engine inventory and (2) safety concerns. 
Further, they can provide anecdotal evidence to support their views. 
For example: 

* Material costs related to the F-15 aircraft, which is more than 30 
years old, have increased significantly over the past several years, in 
part, due to its age. For example, the Air Force is in the process of 
replacing the aircraft's structural surfaces with a material--called 
gridlock--that is more expensive than the material that was used in the 
past to make structural repairs. According to Air Force officials at 
the air logistics center making the repairs, the new material is not 
prone to the problems that plagued the old material. As a result, the 
new material should allow for longer intervals between structural 
surface repairs and reduce structural repair costs in the future. For 
fiscal year 2003, the gridlock material added $24.5 million to the 
estimated cost of material to be used to repair the F-15 and $20.47 to 
the hourly rate charged customers for maintenance work on the aircraft.

* Due primarily to actions taken in response to safety concerns, the 
depot maintenance activity group raised the sales price for the repair 
of F101-GE-102 high-pressure turbine rotor assemblies from $144,464 in 
fiscal year 2003 to $261,872 in fiscal year 2004, an increase of 
$117,408 or 81 percent. From 1999 through 2002, three F-16 aircraft 
crashed due to engine failures caused by metal fatigue on the engine's 
high-pressure turbine rotor. To address this safety problem, the 
Oklahoma City air logistics center began replacing the rotors on 
similar aircraft engines more frequently and started using more 
expensive rotors that were made of a stronger, more heat resistant 
metal alloy.

Depot maintenance officials have also determined that another major 
cause of their higher material costs is price growth. The activity 
group pays various suppliers for component parts[Footnote 6] that it 
uses to repair aircraft, engines, and other items. Depot maintenance 
officials stated that their analysis showed that the amount they had to 
pay for repairable component parts in fiscal year 2003 was about 9 
percent higher than the price they had to pay for the same component 
parts in fiscal year 2002. Similarly, the activity group's fiscal year 
2004 budget and, in turn, its fiscal year 2004 prices were based on the 
assumption that the prices it would have to pay its suppliers for 
repairable component parts would increase an additional 14 percent.

Another major cause of the activity group's higher material costs 
relates to the workloads that were transferred from two closing air 
logistics centers (Sacramento and San Antonio) to the three remaining 
centers (Ogden, Oklahoma City, and Warner Robins) in the late 1990s. 
Depot maintenance officials acknowledged that when workloads were moved 
from the closing air logistics centers to the remaining centers in the 
late 1990s, millions of dollars of material were also transferred. 
Officials at one center acknowledged that this material was never 
recorded in the center's accounting records. When the maintenance shops 
needed component parts to accomplish the transferred workloads, they 
used the transferred material and did not record an expense in their 
financial records. This caused their reported material expenses to be 
understated in fiscal year 2000. However, since most of the transferred 
material has now been consumed, they now have to record the new 
material being purchased as expenses in their financial records. 
Consequently, part of what appears to be higher material costs is a 
more accurate reflection of actual costs.

Efforts to Develop an Effective and Systematic Methodology for 
Analyzing Material Cost Variances Have Been Ongoing for Several Years: 

In August 2000, we reported[Footnote 7] that the Air Force depot 
maintenance activity group did not have an effective, systematic 
process for identifying and analyzing variances between planned and 
actual material costs. The report noted that such an analysis is 
frequently used for manufacturing processes to determine if material 
usage has increased and, if so, to determine the impact on material 
costs. The report also pointed out that such an analysis could be used 
to validate Air Force officials' view that increased material usage is 
caused by external factors beyond the Air Force Materiel Command's 
control, such as the aging of the Air Force's aircraft and engine 
inventory. The report recommended that the Secretary of the Air Force 
direct the Commander, Air Force Materiel Command, to develop a 
systematic process to identify and analyze variances between depot 
maintenance activities' planned and actual material usage. In its 
comments on our report, the Department of Defense concurred with our 
recommendation and stated, among other things, that the Air Force 
Materiel Command planned to develop a database that could be used to 
analyze material usage.

As summarized below, the Air Force Materiel Command has subsequently 
taken numerous actions to gain a better understanding of its material 
cost and usage increases.

* From September through November 2000, material analysis teams were 
established at Air Force Materiel Command headquarters and at each air 
logistics center.

* In November 2000, Air Force Materiel Command headquarters developed a 
material analysis plan that (1) identified some of the material 
problems that would be addressed by the material analysis teams and (2) 
indicated that one of the key functions of the material analysis teams 
would be to link ongoing and planned material studies--thereby helping 
to reduce duplication of effort and increase coordination on ongoing 
studies.

* From January 2001 through February 2002, Air Force Materiel Command 
conducted a comprehensive analysis of the material cost and usage 
increases that occurred between fiscal years 1999 and 2000. However, 
for a variety of reasons, the Command concluded that its analysis of 
these data was inadequate; for example, because it did not include all 
work. Consequently, from March 2002 through November 2003, the Command 
developed a database to facilitate its material analyses.

In November 2003, the Air Force Materiel Command initiated an analysis 
of the material cost and usage increases that occurred between fiscal 
years 2002 and 2003. Air Force Materiel Command officials believe, and 
we agree, that the revised methodology for analyzing material cost 
variances should provide more reliable results than the one they used 
to analyze the depot maintenance activity group's fiscal year 1999 and 
fiscal year 2000 material cost and usage data. However, when they 
completed their preliminary analysis, they determined that additional 
work was needed on their methodology. According to the activity group's 
fiscal year 2005 budget estimate, the revised model should be fully 
functional in November 2004.

Labor Cost Contributed to Price Increases: 

As shown in table 1, higher budgeted labor costs per direct labor hour 
of work accomplished (labor expense rate) accounted for $11.86, or 
about 10 percent, of the total increase that occurred in the activity 
group's composite sales price between fiscal years 2000 and 2004. This 
increase, which is shown in table 2, was due to both an increase in the 
budgeted average cost of civilian labor and a decline in budgeted 
productivity.

Table 2: Air Force Depot Maintenance Activity Group's Budgeted Labor 
Expense Rates for Fiscal Years 2000 through 2004: 

Budgeted labor rate; 
Fiscal year: 2000: $53.32; 
Fiscal year: 2001: $52.64; 
Fiscal year: 2002: $56.55; 
Fiscal year: 2003: $63.58; 
Fiscal year: 2004: $65.18; 
Increase: $11.86.

Source: Air Force Materiel Command.

[End of table]

Although the increase in the labor expense rate was the second most 
significant reason for the composite sales price's increase during this 
period, the labor costs' relative impact on the overall composite sales 
price declined significantly during this 5-year period. Specifically, 
in fiscal year 2000, the budgeted labor expense rate ($53.32) was $5.49 
higher than the budgeted material expense rate ($47.83), but by fiscal 
year 2004, it was more than $60 per hour less.

Further, our analysis showed that about 61 percent of the higher labor 
cost was due to factors that are largely beyond the activity group's 
control, such as annual cost-of-living increases and increased costs 
for health benefits for federal employees. Specifically, our analysis 
showed that about $7.25 of the $11.86 increase in the budgeted labor 
expense rate was due to an increase in the average cost of civilian 
labor from about $57,434 per work year per employee in fiscal year 2000 
to about $65,132 in fiscal year 2004. This increase, in turn, was due 
to two factors: (1) budget estimates for the average annual cost of 
employee compensation (for basic salary and such variables as holiday 
and overtime pay) increased by $5,649 per work year per employee, or 
about 3 percent per year, and (2) budget estimates for the average 
annual cost of employee benefits (employer contributions for such 
things as health and life insurance) increased by about $2,049, or 
about 5 percent per year.

The rest of the increase in the budgeted labor expense rate--about 
$4.61 per hour--was the result of a 7 percent decline in budget 
estimates for worker productivity. Our analysis showed that this 
decline was not the result of an actual decline in reported actual 
worker productivity, but rather was due to overly optimistic 
productivity assumptions for fiscal years 2000 through 2003 and what 
appears to be an overly pessimistic productivity assumption for fiscal 
year 2004.

Specifically, our analysis showed that (1) the activity group's 
reported actual productivity increased about 4 percent between fiscal 
year 2000 and fiscal year 2003, but was consistently less than the 
budget estimate and (2) the fiscal year 2004 budget estimate was based 
on the assumption that the fiscal year 2004 productivity would be 3 
percent less than the reported actual level for fiscal year 2003.

When we asked Air Force Materiel Command officials why the activity 
group's fiscal year 2004 budget estimate was based on the assumption 
that the workforce's productivity would decline, they acknowledged that 
the budget assumption was probably too pessimistic. However, they also 
stated that they still believe that several initiatives that the 
Command is implementing will cause some decline in reported actual 
productivity during fiscal year 2004. For example, they indicated that 
the workforce's overall productivity is likely to decline, at least in 
the short term, because they plan to add about 167 overhead positions 
in order to implement a more effective process improvement strategy, 
improve the activity group's management of its infrastructure, and 
develop a methodology and tool to improve financial forecasting.

We attempted to review reported actual productivity data for the first 
part of fiscal year 2004 to determine if the fiscal year 2004 budget 
estimate was based on an overly pessimistic productivity assumption. 
However, we were unable to do so because, as of February 2004, problems 
related to the implementation of a new accounting system prevented the 
activity group from producing reliable productivity data. This data 
reliability problem is discussed later in this report.

Business Operations Costs Contributed to Price Increase, Especially 
between Fiscal Years 2003 and 2004: 

Business operations costs are non-labor, non-material overhead costs 
for such things as the repair and modernization of equipment and 
facilities and accounting automated data processing services. An 
increase in business operations costs accounted for $9.64, or about 8 
percent, of the total sales price increase as shown in table 1. Most 
($7.99, or 83 percent) of this increase occurred between the fiscal 
year 2003 and fiscal year 2004 budget estimates. An Air Force Materiel 
Command official stated that the large increase in business operations 
funding for fiscal year 2004 was due largely to the Air Force's 
realization that infrastructure support and other essential support 
services had been budgeted too low for several years and needed to be a 
higher priority in fiscal year 2004. For example, Air Force 
Headquarters reduced business operations cost projections that were 
included in the activity group's initial fiscal year 2003 budget 
estimate by about $92 million because of concern about the projected 
large price increase and a desire to hold down costs, if possible. This 
reduction, in turn, forced the activity group to cut back on certain 
requirements, such as the repair and modernization of facilities and 
equipment. The Air Force Materiel Command official stated that the 
fiscal year 2004 budget estimate considered the years of deferred 
maintenance and modernization and allowed for significant increases in 
these areas.

Another major cause of the large increase in business operations costs 
from fiscal year 2000 to 2004 is the activity group's ongoing 
conversion of its legacy accounting systems to the Depot Maintenance 
Accounting and Production System. According to Air Force depot 
maintenance officials, this conversion is the primary reason why 
budgeted costs for automated data processing and software support 
increased from about $63.6 million in 2000 to about $115.5 million in 
2004. Similarly, Air Force depot maintenance officials stated that the 
decision to phase out their old legacy systems is the primary reason 
why depreciation costs for automated data systems and equipment 
increased from about $92.2 million in fiscal year 2000 to about $122.7 
million in fiscal year 2004.

Work Carried Over from Previous Fiscal Year Contributed to Price 
Increase: 

During periods of increasing costs, the depot maintenance activity 
group generally incurs financial losses on work that is carried over 
from one fiscal year to the next. The reason for this is that DOD's 
stabilized price policy requires working capital fund activities to 
establish sales prices prior to the start of each fiscal year and to 
apply these predetermined or "stabilized" prices to most orders 
received during the year--regardless of when the work is accomplished 
or what costs are actually incurred. In other words, the activity group 
generally incurs financial losses on its "carryover" work because (1) 
the cost of doing the work generally goes up from one year to the next 
and (2) the stabilized price policy prevents the activity group from 
increasing its prices to cover the higher costs. If losses are expected 
on carryover work, the activity group adds a surcharge to the price of 
its new work in order to recoup the losses that are anticipated on its 
carryover work. Conversely, in the rare instance where costs are 
expected to decrease from one year to the next, a negative surcharge 
can be added.

As shown in table 1, about $8.00, or 7 percent, of the increase in the 
depot maintenance activity group's composite hourly sales price can be 
attributed to an increase in the carryover surcharge. Our analysis 
showed that the fiscal year 2004 carryover surcharge added about $164 
million to activity group customers' fiscal year 2004 depot maintenance 
costs. Our analysis also indicated that the fiscal year 2004 carryover 
surcharge was probably too high and may have been unnecessary. 
Specifically, since most of the work carried over from fiscal year 2003 
should have been accomplished during the first quarter of fiscal year 
2004 and most of the work on fiscal year 2004 orders (which had the 
carryover surcharge) should have been accomplished in subsequent 
quarters, carryover losses should have occurred during the first 
quarter of fiscal year 2004. However, the activity group reported a 
profit of about $80 million for the first quarter. When we discussed 
this inconsistency with depot maintenance officials, they agreed that 
most of the carryover losses should have occurred in the first quarter, 
but they also indicated that they did not know if the reported profit 
(1) indicated that the carryover surcharge was unnecessary or (2) was 
unreliable due to problems related to the implementation of a new 
accounting system which, as discussed later in this report, has 
adversely affected the reliability of the activity group's reported 
accounting data.

Fiscal Year 2004 Cash Surcharge Will Generate Excess Cash: 

Working capital funds are required to maintain cash balances[Footnote 
8] that are sufficient to finance the operations of their activity 
groups, but are not to tie up resources. DOD policy[Footnote 9] 
requires working capital funds to maintain cash balances at sufficient 
levels to cover 7 to 10 days of operational costs and 6 months of 
capital disbursements. For the Air Force Working Capital Fund, which 
includes several activity groups including depot maintenance and the 
U.S. Transportation Command, this equates to a cash balance of between 
$924 million and $1,221 million. It is important to note that (1) this 
cash requirement applies to the total working capital fund and (2) 
there is no requirement for individual activity groups to maintain a 
specific cash balance (for example, a cash surplus in one activity 
group can offset a deficit in another).

If projections of cash disbursements and collections indicate that cash 
balances will drop below prescribed levels, the Air Force Working 
Capital Fund can generate additional cash by adding a surcharge to one 
or more of its activity groups' composite sales prices. Additionally, 
if for some reason the cash balance becomes too low and there is a 
possibility of an Antideficiency Act[Footnote 10] violation, the 
working capital funds are required to generate additional cash. One way 
to raise cash is by advance billing customers for work not yet 
performed. Conversely, if the cash balances are too high, customer 
prices can be reduced or possibly either the Office of the Secretary 
of Defense or the Congress can transfer the unneeded funds to other 
appropriations to either reduce budget requests or finance additional 
requirements.

About $3.55, or 3 percent, of the increase in the depot maintenance 
activity group's composite hourly sales price can be attributed to an 
increase in the cash surcharge. Our work showed that Air Force 
Headquarters decided to include a cash surcharge in the depot 
maintenance activity group's fiscal year 2004 sales price. Our work 
also showed that the depot maintenance activity group's fiscal year 
2004 cash surcharge is unnecessary and, more importantly, that the Air 
Force Working Capital Fund will have a substantial amount of excess 
cash on hand at the end of fiscal year 2004 unless either the Office of 
the Secretary of Defense or the Congress uses this unneeded cash to 
satisfy other requirements. As noted previously, DOD policy guidance 
requires the Air Force Working Capital Fund to maintain a cash balance 
of 7 to 10 days of operational costs and 6 months of capital 
disbursements, which equates to $924 million and about $1.2 billion. 
Our analysis showed that the Air Force Working Capital Fund's end-of-
month cash balance was at least $2.2 billion for each of the first 4 
months of fiscal year 2004 and was more than $2.5 billion as of January 
31, 2004. The $2.5 billion amount was more than $1.3 billion higher 
than the maximum allowed by DOD policy. Most of the excess cash was 
generated by the work performed by the U.S. Transportation Command, 
whose cash is included in the Air Force Working Capital Fund.

When we contacted Office of the Secretary of Defense officials in March 
2004 about the Air Force Working Capital Fund's excess cash, in 
general, and the depot maintenance activity group's fiscal year 2004 
cash surcharge, in particular, they stated that they allowed the Air 
Force to include a cash surcharge in its depot maintenance activity 
group's fiscal year 2004 sales prices because (1) problems related to 
ongoing efforts to implement a new accounting system made the 
reliability of the activity group's accounting data questionable and 
(2) uncertainty related to ongoing actions to remove contract depot 
maintenance operations from the Air Force Working Capital Fund made it 
difficult to reliably project future cash collections and 
disbursements. However, they also acknowledged that the Air Force 
Working Capital Fund has had a substantial amount of excess cash 
throughout fiscal year 2004 and stated that they would be exploring 
possible uses for the excess cash over the next few months.

Prices Charged Customers Were Not Set High Enough to Recover Costs: 

Prices that the depot maintenance activity group charged customers were 
not set high enough to recover the group's reported costs of performing 
the work. Air Force officials at the three air logistics centers and 
the Air Force Materiel Command informed us that the activity group's 
prices were not set high enough because the Air Force artificially 
constrained the activity group's prices for fiscal years 2000 through 
2003 by not including all anticipated costs in the prices. In part, 
because the sales prices were set too low during this period, the 
activity group reported losing about $1.1 billion, as shown in table 3.

Table 3: Activity Group's Reported Losses and Additional Funds Received 
to Recoup Losses from Fiscal Years 2000 to 2003: 

Dollars in millions.

2000; 
Reported actual profit or (loss) before additional funds received: 
($369); 
Additional funds received to recoup losses: $266.

2001; 
Reported actual profit or (loss) before additional funds received: 
($310); 
Additional funds received to recoup losses: $224.

2002; 
Reported actual profit or (loss) before additional funds received: 
($279); 
Additional funds received to recoup losses: $516.

2003; 
Reported actual profit or (loss) before additional funds received: 
($117); 
Additional funds received to recoup losses: $0.

Total; 
Reported actual profit or (loss) before additional funds received: 
($1,075); 
Additional funds received to recoup losses: $1,006.  

Source: Air Force budget reports.

[End of table]

To help recoup the losses, the activity group billed and collected more 
than $1 billion from customers outside the pricing structure. As a 
result, the effective prices actually paid by customers were 
significantly higher during fiscal years 2000, 2001, and 2002.

The Air Force changed its sales price development philosophy in 2002 in 
an effort to bring prices charged customers in fiscal year 2004 more in 
line with operating costs. In addition, the Air Force allowed out-of-
cycle price increases in fiscal years 2002 and 2003 to alleviate 
projected losses. Even though the activity group made out-of-cycle 
price increases, the activity group still reported losses for those two 
fiscal years.

Customer Sales Prices Constrained: 

Air Force officials told us the prices were constrained to help ensure 
that the activity group's customers would be able to get needed work 
done with the amount of funds provided them through the budget process. 
Our work at the air logistics centers showed that customer sales prices 
were in fact constrained. For example, at one center we found that 
sales prices for work on inventory items performed by the avionics shop 
were constrained by not including all estimated costs of materials to 
be used in accomplishing the work. In developing its fiscal year 2003 
customer prices, this shop estimated that its material costs would be 
about $160 million. However, because of the pricing constraints levied 
by the Air Force, the avionics shop was only allowed to include about 
$123 million of material costs in its prices, a difference of about $37 
million. However, constraining prices is contrary to DOD policy (DOD 
Financial Management Regulation, 7000.14-R, Volume 2B, Chapter 9) that 
requires activity groups to set prices to recover the full cost of 
providing goods and services to customers so that the working capital 
fund activity group would operate on a break-even basis--that is, not 
make a profit or incur a loss.

Air Force Changed Its Sales Price Development Philosophy: 

During fiscal year 2002, Air Force headquarters reversed its philosophy 
of constraining customer sales prices when it was developing the depot 
maintenance activity group's fiscal year 2004 prices to reduce the risk 
of future financial losses. In addition, the Air Force allowed the 
activity group to impose out-of-cycle customer price increases in 
fiscal years 2002 and 2003 to lessen projected losses resulting, in 
part, from its price constraining philosophy that had been in place 
when these fiscal year prices were developed for the budget. 
Specifically, in June 2002, the Office of the Assistant Secretary of 
the Air Force directed the Air Force Materiel Command to direct each 
air logistics center to increase the sales (repair) prices on 20 
inventory items that it estimated were going to lose the most dollars. 
These price increases were effective beginning July 1, 2002--the last 
quarter of fiscal year 2002. Our analysis of data provided by the three 
air logistics centers showed that this action increased the activity 
group's revenue by about $23 million, thus avoiding additional losses 
by this same amount.

By authority of the same June 2002 directive, the three air logistics 
centers were also directed to increase their fiscal year 2003 sales 
prices to avoid an estimated $443 million loss that was being projected 
for fiscal year 2003 at that time. This out-of-cycle increase resulted 
in the prices charged customers increasing from $179.42 an hour to 
$199.66 an hour, approximately $20 per hour. The air logistics centers 
were not provided guidance regarding how the price increase was to be 
applied to their individual workloads. One center applied the increase 
"across the board" to all workloads. Another center applied the 
increase primarily to its aircraft workload. The third center applied 
the increase primarily to its aircraft workload and also increased the 
sales price for one of its engines. As shown in table 4, how this 
increase was implemented had a profound impact on some of the fiscal 
year 2003 prices charged customers, resulting in price increases 
significantly higher than the average $20 per hour. In some cases the 
prices increased by more than 50 percent.

Table 4: Air Logistics Centers' Revised Fiscal Year 2003 Sales Prices 
for Selected Workloads due to Out-of-Cycle Price Increases: 

Workload: F110-100B engine; Original fiscal year 2003 sales price[A]: 
$1,325,410.00; Revised fiscal year: 2003 sales price[A]: $1,808,900.00; 
Dollar increase: $483,490.00; Percent increase: 37.

Workload: B-1 aircraft; 
Original fiscal year 2003 sales price[A]: $200.77; 
Revised fiscal year: 2003 sales price[A]: $332.23; 
Dollar increase: $131.46; 
Percent increase: 65%. 

Workload: B-52 aircraft; 
Original fiscal year 2003 sales price[A]: $159.70; 
Revised fiscal year: 2003 sales price[A]: $215.50; 
Dollar increase: $55.80; 
Percent increase: 35%. 

Workload: KC-135 aircraft; 
Original fiscal year 2003 sales price[A]: $174.80; 
Revised fiscal year: 2003 sales price[A]: $199.81; 
Dollar increase: $25.01; 
Percent increase: 14%. 

Workload: E-3 aircraft; 
Original fiscal year 2003 sales price[A]: $194.72; 
Revised fiscal year: 2003 sales price[A]: $317.28; 
Dollar increase: $122.56; 
Percent increase: 63%. 

Workload: F-15 aircraft; 
Original fiscal year 2003 sales price[A]: $202.15; 
Revised fiscal year: 2003 sales price[A]: $285.98; 
Dollar increase: $83.83; 
Percent increase: 42%. 

Workload: C-5 aircraft; 
Original fiscal year 2003 sales price[A]: $203.00; 
Revised fiscal year: 2003 sales price[A]: $236.98; 
Dollar increase: $33.98; 
Percent increase: 17%. 

Workload: C-130 aircraft; 
Original fiscal year 2003 sales price[A]: $115.83; 
Revised fiscal year: 2003 sales price[A]: $136.92; 
Dollar increase: $21.09; 
Percent increase: 18%. 

Workload: C-141 aircraft; 
Original fiscal year 2003 sales price[A]: $249.11; 
Revised fiscal year: 2003 sales price[A]: $383.03; 
Dollar increase: $133.92; 
Percent increase: 54%. 

Source: Air Force air logistics centers.

[A] Aircraft sales prices are charged per hour, whereas the sales price 
for engine work is per engine.

[End of table]

The $20 per hour average sales price increase for fiscal year 2003 was 
intended to make the activity group break even at the end of fiscal 
year 2003 based on projected losses at the time the decision was made 
to increase prices. Even though sales prices were increased--
significantly in some cases as shown in table 4--the activity group 
still reported a financial loss at the end of the fiscal year. 
According to an Air Force Materiel Command official, when the estimated 
price increase was developed they did not consider that some of the 
revenue from the fiscal year 2003 price increase would be realized in 
fiscal year 2004 because of work started and/or accepted in fiscal year 
2003 that had to be carried over and completed in fiscal year 2004.

Further, we found that the amount of the reported loss at the end of 
fiscal year 2003 was questionable. Based on our analysis of the 
financial data and discussions with activity group officials, the Air 
Force's implementation of the new accounting system, DIFMS, resulted in 
wide swings in the group's reported net operating results during fiscal 
year 2003. For example, one air logistics center's net operating 
results went from a $1 million loss to a $94 million loss over a period 
of 1 month due to the implementation of DIFMS. Another center reported 
a profit throughout most of fiscal year 2003, including a reported 
profit of $137 million at the end of August 2003. However, the center 
ended the fiscal year with a reported loss of $17 million--a $154 
million shift in 1 month--due to the implementation of the new 
accounting system. Air Force officials told us that implementing DIFMS 
was a major effort and were aware of system implementation problems and 
were working to resolve them.

Air Force Depot Maintenance Needs More Systematic and Effective 
Processes for Controlling Costs: 

The Air Force lacks systematic and effective processes for controlling 
costs. In an effort to better control cost growth, the Air Force 
Materiel Command has (1) been trying since 2000 to develop a systematic 
methodology to better understand the reasons for the rapidly increasing 
material costs and (2) implemented a depot maintenance process 
improvement program. Although these efforts represent a positive step 
in trying to better understand and control its depot maintenance costs, 
the Command has not (1) completed a successful methodology for 
analyzing the reasons for the rapid material cost increases and (2) 
entered data into a data repository[Footnote 11] that is to be used to 
share cost-saving ideas among the three air logistics centers on 
process improvements and track the costs and savings for these 
improvements. These actions are necessary in order for management to 
control the increasing depot maintenance costs.

Efforts to Develop an Effective and Systematic Methodology for 
Analyzing Material Cost Variances Have Been Ongoing for Several Years: 

In August 2000, we reported[Footnote 12] that the Air Force depot 
maintenance activity group did not have an effective, systematic 
process for identifying and analyzing variances between planned and 
actual material costs. In its comments on our report, the DOD concurred 
with our recommendation and stated, among other things, that the Air 
Force Materiel Command planned to develop a database that could be used 
to analyze material usage. However, as discussed earlier in this 
report, the Command still has not completed the methodology for 
analyzing material cost increases.

It is imperative that the Air Force Materiel Command complete this 
methodology for analyzing material costs since material costs have 
increased significantly over the past few years. Specifically, budgeted 
material costs for fiscal year 2004 are about $2.8 billion and are 
expected to account for about 57 percent of the activity group's total 
fiscal year 2004 costs. A second reason is the fact that, as discussed 
previously, higher material costs account for about 67 percent of the 
total sales rate increase that occurred between fiscal years 2000 and 
2004.

Air Logistics Centers Initiated Process Improvement Initiatives: 

The Air Force has recognized the need to make its depot maintenance 
activities more effective and efficient by incorporating best business 
practices that commercial companies used. The three air logistics 
centers undertook various process improvement initiatives designed to 
improve the efficiency and effectiveness of their operations. However, 
as discussed in the next section, the activity group does not have an 
effective mechanism for tracking costs and documenting savings that may 
have resulted from these initiatives. According to Air Force depot 
maintenance documentation, these initiatives are intended to eliminate 
waste or non-value-added processes for selected business lines, thereby 
reducing the number of flow days,[Footnote 13] improving the usage of 
available workspace, and reducing the overtime worked. In implementing 
these initiatives, Air Force officials visited over 35 private industry 
companies to gather information to improve their processes. For 
example, officials at the Oklahoma City Air Logistics Center consulted 
with Standard Aero (San Antonio), Inc. to reengineer its constant speed 
drive repair process. According to the center's documentation, this 
initiative, to date, has reduced flow days by 20, reduced the part 
rejection rate by 25 percent, and resulted in an additional $2.9 
million in revenue over pre-2002 levels. When we visited Standard Aero 
(San Antonio), Inc. we found that these efficiencies were obtained by 
applying a cellular approach[Footnote 14] to depot maintenance repair 
work that differed significantly from the traditional functional 
approach.[Footnote 15] Other process improvement initiatives included 
the following.

* The Oklahoma City Air Logistics Center's initiative for the KC-135 
aircraft cut in half the number of aircraft awaiting scheduled depot 
maintenance according to center documentation and officials. Further, 
the center reported that this effort reduced the number of flow days 
from 421 days in fiscal year 2000 to 221 days in fiscal year 2003 with 
a goal to have it down to 178 days by fiscal year 2005. This initiative 
(1) included the renovation of nine depot maintenance docks and the 
associated support areas and (2) implemented the "continuous flow" 
concept that consists of having as many aspects of the job in one area 
as possible and arranged so that the work flows from one step to the 
next without unnecessary movement to create more effective cells of 
productivity. Project officials noted that these changes have enabled 
the center to become much more efficient and put the needed aircraft 
back into the warfighter's hands more quickly.

* The Ogden Air Logistics Center reported that its central gearbox 
initiative--which is one of six projects initiated to improve the 
processes it uses to repair brakes, gearboxes, pylons, struts, 
actuators, and wheels--has increased both the efficiency and 
effectiveness of the gearbox repair process. Specifically, according to 
the center's process improvement manager, the gearbox project has 
allowed the center to (1) reduce gearbox's average shop flow days from 
90 days to 52 days, (2) reduce the average number of gearbox assemblies 
in work at any given time from 46 to 21, and (3) reduce the gearbox's 
average labor standard from 236 hours per gear box to 68 hours. The 
initiative is also expected to reduce annual direct labor costs by 
about $5 million, beginning in fiscal year 2005. The process 
improvement manager stated that the Ogden Air Logistics Center achieved 
the reduction in labor costs by streamlining processes under the 
cellular repair concept, which eliminated bottlenecks in staging areas 
and cut out wasteful, unneeded repair steps.

Air Force Materiel Command Has Not Effectively Implemented Its Data 
Repository for Process Improvement Initiatives: 

The Air Force Materiel Command has not effectively implemented its data 
repository, which is a key part of its Process Improvement Program. 
Because the air logistics centers did not enter all the process 
improvement initiative data into the data repository, the Command (1) 
has been unable to properly document and implement a shared, standard 
process improvement program to continuously measure, analyze, and 
improve its depot maintenance processes and (2) does not have an 
effective mechanism for tracking costs and documenting savings that 
could have resulted from these initiatives.

Recognizing the need for better oversight of its process improvement 
efforts, the Air Force Materiel Command issued Instruction 21-137 on 
August 20, 2003, which established the policies and procedures for 
process improvements within all maintenance divisions at the centers. 
The instruction points out that process improvement within the Command 
is vital to becoming "World Class Depots providing the world's best 
warfighter support." It goes on to add that leveraging process 
improvement initiatives across the command requires standardized 
guidance, integration, and tracking. Accordingly, the instruction 
established a standard methodology by which the three centers would 
accomplish process improvement and become "World Class." This was to be 
done by documenting and implementing a shared, standard process 
improvement program to continuously measure, analyze, and improve the 
Command depot maintenance processes. A key component was the 
establishment of the Command data repository to enable the Command to 
track process improvement results and to share the lessons learned 
among the centers. As of October 2003, the data repository contained 
108 process improvement initiatives.

We found three problems with the implementation of this instruction and 
the creation of the Command data repository. First, we found that 
several large process improvement initiatives were not included in the 
data repository. For example, the process improvement projects that 
make up the Oklahoma City Air Logistics Center's initiative to 
transform the largest industrial facility in the DOD--its building 
3001--into a world class depot maintenance facility were not included 
in the Command data repository. According to Command Depot Maintenance 
Transformation officials, this initiative is beyond what they were 
targeting to document and capture in the data repository, but they 
agreed that the individual projects resulting from this initiative 
should be included. These officials also acknowledged that the major 
projects that currently make up their F-15 Trailblazer initiative--to 
evaluate, test, and redefine business processes for repairing the Air 
Force's F-15 aircraft--were not in the data repository. Air Force 
Materiel Command officials stated that the projects from these two 
large initiatives need to be included in the data repository in order 
for the Command to oversee the process improvement initiatives at each 
of the centers. The officials added that they plan to add these 
initiatives to the data repository as they become better defined. The 
Command officials also stated that the data repository has not been as 
fully used as envisioned and that not all process improvement 
initiatives have been entered as required by the Air Force Materiel 
Command Instruction 21-137.

Second, while the Air Force Materiel Command created a data repository 
of ongoing initiatives to provide needed oversight of its improvement 
initiatives, the information in the data repository has not proved 
useful because in many cases the centers failed to fill in the data 
fields for each initiative. As a result, we found that some of the 
required data fields were missing important information needed to 
centrally manage the process improvement initiatives. For example, 51 
of the 108 initiatives had no title clearly describing the initiative. 
Another important required data field to identify the root causes of 
the problem to be corrected or improved was not completed for 54 of the 
108 initiatives. Command officials agreed that the data repository has 
not been as useful as envisioned because many of the initiatives 
entered have not been fully documented since the centers have not 
completed the needed or required data fields.

Third, the Air Force Materiel Command Instruction 21-137 also requires 
that the process improvement results be recorded and tracked in the 
Command data repository including the costs and benefits associated 
with each initiative. However, the Command's input guidance to record 
process improvements in the data repository does not require that the 
data fields for costs, return on investment, and quantifiable results 
be completed. This contradicts the Command Instruction 21-137, which 
requires this information. As a result, we found the following: 

* Cost information to implement the initiative was not recorded in the 
data repository for 89 of the 108 initiatives. Of the 19 initiatives 
containing some cost information, only 10 initiatives had recorded 
costs totaling $6,328,000. The remaining 10 initiatives had recorded 
costs as "minimal" or "not applicable." 

* Return on investment information--such as dollar savings--was not 
recorded in the data repository for 93 of the 108 initiatives. Of the 
15 initiatives containing some return on investment information, only 
two initiatives had recorded a return on investment totaling $828,000. 
The remaining 13 initiatives had recorded return on investment 
information with no dollar savings identified or as not applicable.

* Quantifiable results information--such as flow days reduced--was not 
recorded in the data repository for 64 of the 108 initiatives. We 
analyzed the recorded information for the remaining initiatives 
containing quantifiable results and found that they did report 
improvements such as reducing the number of flow days and man days and 
improving the usage of available workspace.

An official at one air logistics center pointed out that in addition to 
reporting their improvement initiatives in the Command data repository, 
they maintain their projects on two additional local databases. Since 
none of these databases can communicate with one another, each database 
is separately maintained and updated by the program managers and the 
process improvement office. This is difficult to do in a timely manner 
and leads to differences among the databases. The center has approved a 
process improvement initiative to standardize these databases. 
Additionally, a Command depot maintenance transformation official 
stated that in preparing for a presentation to the Command's depot 
maintenance management team he had to contact the three air logistics 
centers directly to obtain complete project information for his 
presentation. He emphasized that this would not have been necessary if 
the three centers had been updating the data repository with complete 
and useful information as required. Without complete and useful 
information, the data repository cannot serve as an effective tool for 
management to oversee these initiatives and the Command runs the risk 
of the centers duplicating efforts and developing stovepipe processes 
that hinder the Command's efforts to provide world class depot 
maintenance services.

Conclusions: 

The Air Force depot maintenance activity group has not always operated 
like a business entity and thus, has not achieved the goals envisioned 
under the working capital fund concept--that is, to operate like a 
business by developing and using effective methods to control operating 
costs, charging customers prices that recover operating costs, and 
ensuring that established management tools to measure the results of 
operational improvement efforts are used as intended. Specifically, the 
group has been unable to develop an analytical methodology to 
effectively identify the causes of and take corrective actions, as 
appropriate, on its continuously upward spiraling material costs. 
Further, working capital fund activities are to establish sales prices 
that allow them to recover their expected costs from their customers. 
However, the activity group intentionally set its sales prices lower 
than what was required to recover its operating costs and, as a result, 
incurred operating losses. Although several promising improvement 
initiatives are underway at the three centers, these efforts are stove 
piped and management has been unable to clearly show that the benefits 
of the initiatives exceed their costs.

Matter for Congressional Consideration: 

The congressional defense committees have shown interest in the amount 
of cash in the Defense Working Capital Fund in past years. The Air 
Force Working Capital Fund cash balance has exceeded the maximum cash 
requirement by over $1.3 billion for each of the first four months of 
fiscal year 2004. If DOD does not take action to reduce the cash 
balance to the 7 to 10 day requirement, the Congress may wish to take 
action to reduce the amount of excess cash in the Air Force Working 
Capital Fund.

Recommendations for Executive Action: 

To improve the business operations of the Air Force Working Capital 
Fund including cash management and the setting of prices and efforts to 
control costs of the depot maintenance activity group, we are making 
two recommendations to the Secretary of Defense and four 
recommendations to the Secretary of the Air Force.

We recommend that the Secretary of Defense: 

* take action to reduce the amount of excess cash in the Air Force 
Working Capital Fund.

* direct the Secretary of the Air Force to develop prices that cover 
the total costs of providing goods and services to customers and not 
constrain prices as has been done in the past.

We recommend that the Secretary of the Air Force direct the Commander, 
Air Force Materiel Command to: 

* develop and complete a viable, systematic methodology for analyzing 
material cost variances that encompasses both the price paid for 
material and material usage that would enable the Air Force Materiel 
Command to better understand the underlying causes of the rapidly 
increasing material costs and take actions to control material costs, 
as appropriate.

* hold the air logistics centers' managers accountable for compliance 
with the Command's mandatory Instruction 21-137 requiring the centers 
to enter all initiatives and related data into the data repository 
completely and accurately. This should include initiative information 
on costs, return on investment, and quantifiable results for all 
process improvement initiatives. At a minimum, the Command needs to 
issue a memorandum to the air logistics centers reiterating their 
responsibilities for compliance with the instruction.

* periodically review the data contained in the data repository to (1) 
determine whether the data provided by the air logistics centers is 
complete and useful and (2) identify ways to consolidate initiatives 
and share lessons learned from the initiatives with the three centers.

* summarize and determine the actual savings and/or real benefits as 
compared to the costs from the improvement initiatives already 
contained in the repository.

Agency Comments and Our Evaluation: 

DOD provided written comments on a draft of this report. In its 
comments, DOD concurred with the six recommendations in the draft 
report and is taking action to implement them. In fact, DOD has already 
taken action to help eliminate the excess cash in the Air Force Working 
Capital Fund by transferring $1.1 billion of the excess cash to the 
Army and Navy Operation and Maintenance appropriation accounts in April 
2004. However, the Air Force Working Capital Fund had about $400 
million of excess cash as of the end of April 2004. Recognizing that 
cash balances fluctuate from month to month, we continue to believe 
that it would be appropriate for the Congress to monitor the working 
capital fund cash balances and take action to reduce the amount of 
excess cash if the balances continue to be in excess of amounts 
necessary. Concerning our recommendation on the Air Force developing 
prices that cover the total costs of providing goods and services to 
customers, DOD stated that the DOD Comptroller will perform a more 
intensive review of the Air Force depot maintenance billing rates to 
ensure that the proposed pricing structure is adequate to cover the 
costs of operations.

We are sending copies of this report to the Chairmen and Ranking 
Minority Members of the Senate Committee on Armed Services; the 
Subcommittee on Readiness and Management Support, Senate Committee on 
Armed Services; the Subcommittee on Defense, Senate Committee on 
Appropriations; the House Committee on Armed Services; the Subcommittee 
on Readiness, House Committee on Armed Services; and the Ranking 
Minority Member, Subcommittee on Defense, House Committee on 
Appropriations. We are also sending copies to the Secretary of Defense, 
Secretary of the Air Force, and other interested parties. Copies will 
be made available to others upon request. Should you or your staff have 
any questions concerning this report, please contact Gregory D. Kutz, 
Director, at (202) 512-9505 or [Hyperlink, kutzg@gao.gov] or William M. 
Solis, Director, at (202) 512-8365 or [Hyperlink, solisw@gao.gov]. An 
additional contact and key contributors to this report are listed in 
appendix III.

Sincerely yours,

Signed by: 

Gregory D. Kutz, 
Director, Financial Management and Assurance: 

Signed by: 

William M. Solis, Director, Defense Capabilities and Management: 

[End of section]

Appendixes: 

Appendix I: Scope and Methodology: 

To determine what factors were primarily responsible for causing the 
composite sales price to increase from $119.99 per hour in fiscal year 
2000 to $237.84 per hour in fiscal year 2004, we obtained and analyzed 
budget documents that provided information on cost factors, such as 
material costs, overhead costs, and salaries used in developing the 
prices. We determined which factors caused the prices to increase the 
most and discussed the reasons for the price increases with officials 
at the Air Force Materiel Command and the three air logistics centers. 
In addition, we obtained information on the impact of the price 
increases on certain aircraft and engines such as the F-15 and E-3 
aircraft. We also reviewed and analyzed the Air Force February 2002 
report on depot maintenance material usage and cost analysis study to 
determine why prices have increased. Finally, we met with Air Force 
Materiel Command officials to determine what actions they were taking 
to identify the causes for increasing material costs--a significant 
factor causing prices to increase--since the Air Force issued its 
February 2002 report.

To determine if the prices charged customers during fiscal year 2000 
through fiscal year 2003 recovered the reported actual costs of 
performing the work, we obtained and analyzed budget documents and 
accounting data that provided information on budgeted and actual 
revenue, direct costs, overhead costs, and net operating losses. When 
the activity group reported losses, we met with officials to determine 
(1) why the prices charged customers did not recover costs incurred in 
providing them the goods and services and (2) how the Air Force 
recovered these losses.

To determine if the Air Force has taken effective steps to improve 
efficiency and control the activity group's costs, we obtained the 
Command's depot maintenance database that contained 108 initiatives 
aimed at improving depot maintenance operations. We analyzed the 
database to determine if each initiative had information on the (1) 
cost to implement the initiative and (2) the amount of dollar savings 
associated with implementing the initiative. Information on cost and 
savings is critical to determine if the initiative is cost beneficial. 
We also analyzed the database to determine if there was sufficient 
information that would enable the air logistics centers to share 
information with each other on the initiatives thereby reducing or 
eliminating redundant efforts. We also met with officials from Air 
Force Materiel Command and the air logistics centers to discuss (1) 
process improvement initiatives, especially information on initiative 
costs, savings, and the sharing of information and (2) whether all 
initiatives were included in the database.

We performed our work at the headquarters, Office of the Under 
Secretary of Defense (Comptroller) and the Office of the Secretary of 
the Air Force, Washington, D.C.; Air Force Materiel Command, Ohio; the 
Oklahoma City Air Logistics Center, Tinker Air Force Base, Oklahoma; 
the Ogden Air Logistics Center, Hill Air Force Base, Utah; and the 
Warner Robins Air Logistics Center, Robins Air Force Base, Georgia. We 
also visited Standard Aero (San Antonio) Inc. and discussed with 
company officials the Oklahoma City Air Logistics Center's initiative 
to reengineer its constant speed drive repair process. We did not 
verify the accuracy of the accounting and budget information used in 
the tables in this report, all of which was provided by the Air Force 
in then-year dollars. We conducted our work from June 2003 through 
April 2004 in accordance with U.S. generally accepted government 
auditing standards. We requested comments on a draft of this report 
from the Secretary of Defense or his designee. DOD provided written 
comments, and these comments are presented in the Agency Comments and 
Our Evaluation section of this report and are reprinted in appendix II.

[End of section]

Appendix II: Comments from the Department of Defense: 

COMPTROLLER:

UNDER SECRETARY OF DEFENSE: 
1100 DEFENSE: 
PENTAGON 
WASHINGTON, DC 20301-1100:

MAY 10:

Mr. Gregory Kutz, 
Director, 
Financial Management and Assurance: 

Mr. William Solis, 
Director, 
Defense Capabilities and Management:
U.S. General Accounting Office:

Washington D.C. 20548:

Dear Mr. Kutz and Mr. Solis:

This is the Department of Defense (DoD) response to the General 
Accounting Office (GAO) draft report, "AIR FORCE DEPOT MAINTENANCE: 
IMPROVED PRICING AND COST REDUCTION PRACTICES NEEDED" dated April 14, 
2004 (GAO Code 04-498). I concur with the recommendations identified in 
the draft report and am taking action to comply with them. Additional 
comments are provided in the enclosure.

While the report identifies significant problems in estimating cost and 
establishing pricing for this activity group, our internal reviews have 
indicated that FY 2004 pricing and performance shows significant 
improvements over past practices.

Enclosure As stated:

Signed by: 

John P. Roth:

Deputy Comptroller for Program Budget:

GAO DRAFT REPORT DATED APRIL 14, 2004 GAO-04-489 (GAO CODE 192098):

"AIR FORCE DEPOT MAINTENANCE: IMPROVED PRICING AND COST REDUCTION 
PRATICES NEEDED":

DEPARTMENT OF DEFENSE COMMENTS TO THE GAO RECOMMENDATIONS:

RECOMMENDATION 1: The GAO recommended that the Secretary of Defense 
take action to reduce the amount of excess cash in the Air Force 
Working Capital Fund. (p. 38/GAO Draft Report):

DOD RESPONSE: Concur. The Department periodically reviews DWCF cash 
balances and takes appropriate action to correct both excess cash 
balances and cash shortfalls in its DWCF activities. In April 2004 the 
Department took steps to eliminate excess cash balances in the Air 
Force Working Capital Fund by transferring excess cash balances to 
Service Operation and Maintenance appropriations.

RECOMMENDATION 2: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Air Force to develop prices that cover the 
total costs of providing goods and services to customers and not 
constrain prices as has been done in the past. (p. 38/Draft Report):

DOD RESPONSE: Concur. In our instructions for the upcoming FY 2006 
budget review the Air Force will be directed to comply with this 
recommendation. Additionally, OSD (Comptroller) will perform a more 
intensive review of the Air Force Depot Maintenance billing rates to 
ensure that their proposed pricing structure is adequate to cover the 
total cost of operations.

RECOMMENDATION 3: The GAO recommended that the Secretary of the Air 
Force direct the Commander, Air Force Materiel Command, to develop and 
complete a viable, systematic methodology for analyzing material cost 
variances that encompasses both the price paid for material and 
materiel usage that would enable the Air Force Materiel Command to 
better understand the underlying causes of the rapidly increasing 
material costs and take actions to control material costs, as 
appropriate. (p. 38/Draft Report):

DOD RESPONSE: Concur.	The Air Force completed implementation of their 
cost accounting system at the end of FY 2003 and is currently 
conducting reviewing the data to determine if additional corrective 
actions are required. The Air Force will continue to brief OSD (C) 
quarterly on this issue.

RECOMMENDATION 4: The GAO recommended that the Secretary of the Air 
Force direct the Commander, Air Force Materiel Command, to hold the Air 
Logistics Center managers accountable for compliance with the Command's 
mandatory Instruction 21-137 requiring the centers to enter all 
initiatives and related data 
into the data repository completely and accurately. The GAO suggests 
that this include the initiative information on costs, return on 
investment, and quantifiable results for all process improvement 
initiatives. At a minimum, the GAO states that the Command needs to 
issue a memorandum to the Air Logistics Centers reiterating their 
responsibilities for compliance with the instructions. (p. 39/Draft 
Report):

DOD RESPONSE: Concur. Starting with FY 2004 data the Air Force will 
hold the Air Logistics Center managers accountable for compliance with 
Air Force Instruction 21-137.

RECOMMENDATION 5: The GAO recommended that the Secretary of the Air 
Force direct the Commander, Air Force Materiel Command, to periodically 
review the data contained in the data repository to (1) determine 
whether the data provided by the Air Logistic Centers is complete and 
useful and (2) identify ways to consolidate initiatives and share 
lessons learned from the initiatives with the three centers. (p. 39/
Draft Report):

DOD RESPONSE: Concur. The Air Force will establish a schedule to 
periodically review the data repository and brief OSD (C) quarterly on 
the status of this initiative.

RECOMMENDATION 6: The GAO recommended that the Secretary of the Air 
Force direct the Commander, Air Force Materiel Command, to summarize 
and determine the actual savings and/or real benefits as compared to 
the costs from the improvement initiatives already contained in the 
repository. (p. 39/Draft Report):

DOD RESPONSE: Beginning with the FY 2006 Budget review the Air Force 
will brief OSD (C) quarterly on the status of this initiative.

Enclosure to Memo, GAO Draft Report, Page 2 of 2:

[End of section]

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Greg Pugnetti, (703) 695-6922: 

Acknowledgments: 

Staff who made key contributions to this report were Francine 
DelVecchio, Karl Gustafson, Keith E. McDaniel, Christopher Rice, Harold 
P. Santarelli, Ron Tobias, and Eddie Uyekawa.

(192098): 

FOOTNOTES

[1] In providing goods and services to customers, the Air Force depot 
maintenance activity group performs work in-house at its depots using 
federal employees or through contracts with private industry or other 
government agencies. The Air Force is removing the contract portion of 
the activity group from the working capital fund. 

[2] The composite sales rate is the average price that customers must 
pay for a direct labor hour of work and is used for budgeting purposes. 
The average price includes labor, material, and overhead costs. For 
actual work performed, the activity group develops individual sales 
prices, such as the price per hour to perform repair work on the F-15 
aircraft, and bills customers based on those individual prices.

[3] Using the Gross Domestic Product price index updated in January 
2004, if the fiscal year 2000 composite sales rate is converted to 
fiscal year 2004 dollars, the composite sales rate would be $128.53, 
and the increase would be 85 percent.

[4] Unless otherwise indicated, the use of the term "direct labor hour" 
in this report will refer to a direct product standard hour, which is 
the amount of acceptable quality work that can be accomplished in 1 
hour by a qualified worker, following prescribed methods, working at a 
normal pace, and experiencing normal fatigue and delays.

[5] Using the Gross Domestic Product price index updated in January 
2004, if the fiscal year 2000 composite rate is converted to fiscal 
year 2004 dollars, the composite rate would be $128.53 and the increase 
would be 85 percent.

[6] The Air Force depot maintenance activity group uses two types of 
component parts: (1) repairable items which are generally managed by 
the Air Force supply management activity group and include parts that 
are repaired when they become broken and (2) non-repairable items which 
are discarded when they become broken and which are generally managed 
by the Defense Logistics Agency.

[7] U.S. General Accounting Office, Air Force Depot Maintenance: 
Budgeting Difficulties and Operational Inefficiencies GAO/AIMD/NSIAD-
00-185 (Washington, D.C.: Aug. 15, 2000).

[8] The cash balance is the fund balance with Treasury which is the 
cash on hand at Treasury used to pay liabilities when due.

[9] DOD Financial Management Regulation 7000.14-R, Volume 2B, Chapter 
9.

[10] The Antideficiency Act, 31 U.S.C. 1341(a)(1) provides that no 
officer or employee of the government shall make or authorize an 
expenditure or obligation exceeding the amount of an appropriation of 
funds available for the expenditure or obligation.

[11] The Air Force Materiel Command Instruction 21-137, Depot 
Maintenance Process Improvement, August 20, 2003, established a 
standard Command database and all process improvement initiatives and 
results must be recorded and tracked in this database. This database 
has standardized data fields and metrics input forms to ensure data are 
entered in a consistent manner. 

[12] U.S. General Accounting Office, Air Force Depot Maintenance: 
Budgeting Difficulties and Operational Inefficiencies, GAO/AIMD/NSIAD-
00-185 (Washington, D.C.: Aug. 15, 2000).

[13] The number of days it takes an item to go from initial inspection 
to delivery back to the warfighter.

[14] An approach that arranges the work into cells that have the 
equipment and workstations in a sequence that supports a smooth flow of 
materials and components through the process, with minimal transport or 
delay (such as, equipment is located where needed to perform the work). 


[15] A traditional manufacturing approach that is organized 
functionally with similar machines in one area (such as, all molding 
machines in the molding department and any molding work is transported 
to that location).

GAO's Mission: 

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: