This is the accessible text file for GAO report number GAO-03-768 
entitled 'Business Systems Modernization: IRS Has Made Significant 
Progress in Improving Its Management Controls, but Risks Remain' which 
was released on June 27, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to Congressional Committees:

June 2003:

Business Systems Modernization:

IRS Has Made Significant Progress in Improving Its Management Controls, 
but Risks Remain:

GAO-03-768:

GAO Highlights:

Highlights of GAO-03-768, a report to congressional committees 

Why GAO Did This Study:

As required by law, the Internal Revenue Service (IRS), in November 
2002 and March 2003, submitted to the congressional appropriations 
committees its initial and revised fiscal year 2003 expenditure plans, 
respectively, requesting about $378 million for the Business Systems 
Modernization (BSM) program. 

GAO reviewed the plans to (1) determine whether the plans were 
prepared in accordance with the law, (2) determine what progress IRS 
had made in implementing modernization management controls and 
capabilities, and (3) provide any other observations about the plans 
and IRS’s BSM program.

What GAO Found:

IRS’s initial (November 2002) and revised (March 2003) fiscal year 
2003 expenditure plans were prepared in accordance with the law. IRS 
made significant progress in improving its modernization management 
controls and capabilities and implementing GAO’s recommendations. For 
example: 

* IRS implemented 20 of 23 commitments and is implementing the 
remaining 3 commitments that address previously reported weaknesses 
and recommendations. Significant among these efforts were IRS’s 
achievements in improving its software acquisition practices. 

* IRS deployed 3 modernized systems that are currently providing 
benefits that (1) improve telecommunications infrastructure, including 
telephone call management, call routing, and customer self-service; 
(2) provide off-the-shelf software to IRS revenue agents to allow them 
to accurately compute complex corporate transactions; and (3) improve 
customer self-service by providing instant refund status information 
and instructions for resolving refund problems via the Internet.

* IRS also took steps to balance the scope and pace of the BSM program 
with the management capacity of IRS and its prime contractor. These 
steps included reassessing the portfolio of projects that IRS had 
planned to proceed with during the remainder of fiscal year 2002 and 
reducing the planned scope and pace of the BSM program for fiscal year 
2003. 

Although significant progress has been made, certain controls and 
capabilities for modernization have not yet been fully implemented, 
including human capital management and validation of cost and schedule 
estimates. Weaknesses in these controls and capabilities contributed, 
in part, to cost, schedule, and performance shortfalls in the BSM 
program. For example, in the revised fiscal year 2003 expenditure 
plan, IRS disclosed that 75 percent of program-level initiatives and 
acquisition project milestones had cost increases and/or schedule 
delays exceeding 10 percent of the estimated cost and duration 
specified in the fiscal year 2002 expenditure plan. Schedule delays 
affect the delivery of benefits. For example, (1) the opportunity for 
Form 1040EZ filers to enjoy faster refunds, as promised by the first 
release of the project that is to replace IRS’s master files of 
taxpayer information, has been delayed for an additional 13 months and 
(2) schedule delays for the first release of the e-Services project 
will defer the provision of easy-to-use electronic products and 
services targeted at tax practitioners who inform, educate, and 
provide services to the taxpaying public.

What GAO Recommends:

GAO recommends that the Commissioner of Internal Revenue direct the 
Chief Information Officer (CIO) to continue improvements in IRS’s 
modernization management controls. GAO also recommends that the 
Commissioner direct the CIO to promptly update the enterprise 
transition strategy to conform to other changes in IRS’s enterprise 
architecture and establish and implement a process for determining the 
type of task order to be awarded in acquiring modernized systems. The 
Commissioner agreed with GAO’s findings and commented on actions to 
address the recommendations.

www.gao.gov/cgi-bin/getrpt?GAO-03-768.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Robert F. Dacey at 
(202) 512-3317 or daceyr@gao.gov

[End of section]

Letter:

Recommendations for Executive Action:

Agency Comments:

Appendixes:

Appendix I: Briefing Slides from the December 18, 2002, Briefing to the
Senate and House Appropriations Subcommittee Staffs:

Appendix II: Briefing Slides from the April 14, 2003, Briefing to the
Senate and House Appropriations Subcommittee Staffs:

Appendix III: Comments from the Internal Revenue Service:

Appendix IV: GAO Contacts and Staff Acknowledgments:

GAO Contact:

Staff Acknowledgments:

BSM: Business Systems Modernization:

CIO: Chief Information Officer :

IRS: Internal Revenue Service:

OMB: Office of Management and Budget:

PRIME: PRIME Systems Integration Support contractor:

Letter June 27, 2003:

The Honorable Richard Shelby 
Chairman 
The Honorable Patty Murray 
Ranking Member 
Subcommittee on Transportation, Treasury and General Government 
Committee on Appropriations 
United States Senate:

The Honorable Ernest J. Istook, Jr. 
Chairman 
The Honorable John W. Olver 
Ranking Minority Member 
Subcommittee on Transportation, Treasury and Independent Agencies 
Committee on Appropriations 
House of Representatives:

As required by law, the Internal Revenue Service (IRS), in November 
2002 and March 2003, submitted to the congressional appropriations 
committees its initial and revised fiscal year 2003 expenditure plans, 
respectively, requesting about $378 million from its Business Systems 
Modernization (BSM) fund. Our objectives in reviewing the plans were to 
(1) determine whether the plans satisfied the conditions specified in 
the law,[Footnote 1] (2) determine what progress IRS had made in 
implementing modernization management controls and capabilities, and 
(3) provide any other observations about the initial and revised plans 
and IRS's BSM program.

On December 18, 2002, and April 14, 2003, we briefed your respective 
offices on the results of our reviews. This report transmits the 
materials used at those briefings and reiterates the recommendations 
that we made to the then-Acting Commissioner of Internal Revenue that 
we specified in our December 2002 briefing.[Footnote 2] The full 
briefing materials, including our scope and methodology, are reprinted 
in appendixes I and II.

In summary, we made the following four major points in our December 
2002 briefing on the results of our review of IRS's initial expenditure 
plan for fiscal year 2003:

* IRS's initial expenditure plan satisfied each of the six legislative 
conditions.

* IRS had made significant progress in improving its modernization 
management controls and capabilities and implementing our 
recommendations. For example, IRS had implemented 20 of 23 commitments 
and is in the process of implementing the remaining 3 commitments that 
address previously reported weaknesses and recommendations. 
Significant among these efforts was IRS's achievements in improving its 
software acquisition practices.

* IRS also had taken steps to balance the scope and pace of the BSM 
program with the management capacity of IRS and the PRIME Systems 
Integration Support contractor (PRIME). In accordance with our 
recommendation, IRS completed a reassessment of the fiscal year 2002 
BSM program in May 2002 and took actions to better balance the system 
acquisition workload with the management capacity. Specifically, IRS 
(1) deferred the start of five new projects until fiscal years 2003 and 
2004 to reduce IRS/PRIME resource demands, (2) reapplied a portion of 
these deferred financial resources toward PRIME management processes 
and support of the federally funded research and development center to 
accelerate correcting modernization management control weaknesses, and 
(3) increased its own efforts and executive focus on management process 
improvement.

* Although significant progress had been made, certain modernization 
management controls and capabilities--related to configuration 
management,[Footnote 3] enterprise transition strategy,[Footnote 4] 
human capital management, and cost and schedule estimate validation--
had not yet been fully implemented. Weaknesses in these controls and 
capabilities increase the risk of cost, schedule, and performance 
shortfalls in the BSM program.

We also made the following five observations related to the BSM program 
and the initial fiscal year 2003 expenditure plan:

* The number of project milestones experiencing cost and schedule 
changes was increasing.

* BSM was entering a critical, high-risk phase as the scope and 
complexity of the program continued to grow.

* Opportunities for using performance-based contracts in acquiring 
modernized systems were increasing.

* IRS had improved the format of its expenditure plan.

* Internal IRS costs of the BSM program, paid from other IRS 
appropriations, were expected to increase, but were not tracked or 
known.

In our April 2003 briefing on the results of our review of IRS's 
revised fiscal year 2003 expenditure plan, we reported that IRS had 
deployed three modernized systems that provide benefits that 
(1) improve telecommunications infrastructure, including telephone 
call management, call routing, and customer self-service; (2) provide 
off-the-shelf software to IRS revenue agents to allow them to 
accurately compute complex corporate transactions; and (3) improve 
customer self-service by providing instant refund status information 
and instructions for resolving refund problems via the Internet.

In addition, we made the following four major points in the April 2003 
briefing:

* IRS's revised plan satisfied the conditions specified under the law.

* IRS continued to take steps to balance the pace of the program with 
management capacity by reducing the planned scope of the BSM program 
for fiscal year 2003. Between November 2002 and March 2003, IRS 
deferred four new project releases, discontinued two ongoing project 
releases, absorbed one new release into an ongoing project release, and 
transferred one ongoing project to another appropriation. Moreover, IRS 
reduced the scope of BSM program-level initiatives and core 
infrastructure projects. As a result, IRS reduced the initial BSM 
funding request for fiscal year 2003 by about $72 million.

* Most initiatives/project milestones continued to experience cost 
increases and/or schedule delays. In the revised fiscal year 2003 
expenditure plan, IRS disclosed that 75 percent of program-level 
initiatives and acquisition project milestones had cost increases and/
or schedule delays exceeding 10 percent of the estimated cost and 
duration specified in the fiscal year 2002 expenditure plan.

* Schedule delays affected the delivery of benefits. For example, (1) 
the opportunity for the first set of taxpayers (single, Form 1040EZ 
filers) to enjoy faster refunds, as promised by the first release of 
the project that is to replace IRS's master files of taxpayer 
information, has been delayed an additional 13 months; (2) schedule 
slippages for the first release of the e-Services project will delay 
the provision of easy-to-use electronic products and services targeted 
at tax practitioners that inform, educate, and provide services to the 
taxpaying public; and (3) remediation of material weaknesses may be 
delayed.

Recommendations for Executive Action:

To improve IRS's modernization management controls and capabilities, we 
recommend that the Commissioner of Internal Revenue direct the Chief 
Information Officer (CIO) to complete actions to:

* institutionalize configuration management procedures for the Business 
Systems Modernization Office;

* implement plans for obtaining, developing, and retaining requisite 
human capital resources; and:

* implement effective procedures for validating contractor-developed 
cost and schedule estimates.

In addition, we recommend that the Commissioner of Internal Revenue 
direct the CIO to:

* promptly update the enterprise transition strategy to conform to 
other changes in IRS's enterprise architecture and:

* establish and implement a process for determining the type of task 
order to be awarded in acquiring modernized systems.

Agency Comments:

In providing written comments on a draft of this report, the 
Commissioner of Internal Revenue agreed with this report's findings and 
commented on the actions IRS is taking to implement our 
recommendations. The Commissioner's comments are reprinted in appendix 
III.

:

We are sending copies of this report to the Chairmen and Ranking 
Minority Members of other Senate and House committees and subcommittees 
that have appropriations, authorization, and oversight 
responsibilities for the Internal Revenue Service. We are also sending 
copies to the Commissioner of Internal Revenue, the Secretary of the 
Treasury, the Chairman of the IRS Oversight Board, and the Director of 
the Office of Management and Budget. Copies are also available at no 
charge on the GAO Web site at http://www.gao.gov.

Should you or your offices have questions on matters discussed in this 
report, please contact me at (202) 512-3317. I can also be reached by 
E-mail at daceyr@gao.gov. Key contributors to this report are listed in 
appendix IV.

Sincerely,

Robert F. Dacey 
Director, Information Security Issues:

Signed by Robert F. Dacey:

[End of section]

Appendixes :

Appendix I: Briefing Slides from the December 18, 2002, Briefing to the 
Senate and House Appropriations Subcommittee Staffs:

[See PDF for image]

[End of figure]

[End of section]

Appendix II: Briefing Slides from the April 14, 2003, Briefing to the 
Senate and House Appropriations Subcommittee Staffs:

[See PDF for image]

[End of figure]

[End of section]

Appendix III: Comments from the Internal Revenue Service:

DEPARTMENT OF THE TREASURY INTERNAL REVENUE SERVICE WASHINGTON, D.C. 
20224:

COMMISSIONER:

June 19, 2003:

Mr. Robert F. Dacey:

Director, Information Security Issues U.S. General Accounting Office:

441 G Street N.W. Washington, DC 20548:

Dear Mr. Dacey:

I have reviewed the General Accounting Office (GAO) draft report 
entitled IRS has Made Significant Progress In Improving its Management 
Controls But Risks Remain, (GAO-03-768, June 2003). We are pleased that 
the GAO:

* Validated that we satisfied the six legislative conditions as 
specified in Congressional appropriations;

* Acknowledged the significant improvements made in the modernization 
management controls and capabilities and our implementation of past 
recommendations;

* Confirmed that we are balancing the scope and pace of the BSM program 
with the management capacity of the IRS and the PRIME contractor; and * 
Acknowledged that the deployment of three modernized systems provides 
benefits to taxpayers and to our employees.

We agree with your report's findings. Both the IRS and the PRIME have 
appointed senior executives to coordinate within and across our 
respective organizations to ensure that we give priority to completing 
your recommendations. We believe this focus was a key factor in 
achieving our Level 2 rating in the Software Engineering Institute's 
Software Acquisition - Capability Maturity Model (SA-CMM). We are the 
first federal civilian agency and multi-project program to achieve a 
Level 2 rating distinction. The PRIME contractor is the first company 
in the world to achieve SA-CMM Level 3.

We will continue to provide the GAO with monthly dashboard reports on 
our progress in maturing these and other management processes, as we 
have been doing for the past 15 months. We will continue our bi-weekly 
meetings on specific modernization topics.

I would like to briefly comment on each of the five recommendations in 
your report.

* Institutionalize configuration management procedures for the Business 
Systems Modernization Office (BSMO): We continue to make progress in 
this area by improving the speed with which we address change requests, 
the quality of impact assessments on change requests, and reporting on 
the causes for change requests. We are undertaking internal assessments 
of the effectiveness of Configuration Management (CM) procedures on 
each project to ensure broad program compliance. We established a MITS-
wide Change Control Board about six months ago to reflect the critical 
connection that BSM has with the rest of our systems maintenance and 
operations.

* Implement plans for obtaining, developing, and retaining requisite 
human capital resources: One of the reasons I established a new Deputy 
Commissioner for Operations was to give attention to our human capital 
practices. In addition, we have made good progress in BSMO by 
increasing the quantity and quality of its staff to provide better 
services. Last February, the BSM program, in concert with the 
Department of Treasury, rolled out the first phase of a new Human 
Resources system to more than 18,000 IRS employees.

* Implement effective procedures for validating contractor-developed 
cost and schedule estimates: We are working with the PRIME contractor 
to develop and deploy best practice estimating capabilities consistent 
with:

Carnegie Mellon University's Software Engineering Institute (SEI). In 
fact, we briefed your staff on our progress just last week. 
Unfortunately, though critical to improving our cost and schedule 
estimates, implementing these capabilities is taking longer than we had 
hoped, but our progress to date is good.

* Promptly update the enterprise transition strategy to conform to other 
changes in IRS' enterprise architecture: The Core Business Systems 
Executive Steering Committee (CBS ESC), BSM's top-level governance 
council, approved Release 2.1 of the BSM Enterprise Architecture last 
week. This release brings the enterprise transition strategy to being 
reasonably current. Of course, it will need to be adjusted as we work 
through our FY04 and FY05 plans in the coming months.

* Establish and implement a process for determining the type of task 
order to be awarded in acquiring modernized systems: All new BSM 
contracts for applications software development of over $1 million are 
now incentive-based. We are working with the PRIME in a Contracting 
Executive Council to institutionalize best contracting processes across 
the whole program.

We appreciate your continued support, and the valuable assistance and 
guidance from your staff. If you have any questions, or if you would 
like to discuss this response in more detail, please contact Fred 
Forman, Associate Commissioner for Business Systems Modernization, at 
(202) 622-3378.

Sincerely,

Mark W. Everson:

Signed by Mark W. Everson:

[End of section]

Appendix IV: GAO Contacts and Staff Acknowledgments:

GAO Contact:

Gregory C. Wilshusen (202) 512-6244:

Staff Acknowledgments:

In addition to the individual named above, other key contributors were 
Bernard R. Anderson, Timothy D. Hopkins, and Chetna Lal.

:

(310190):

:

:

FOOTNOTES

[1] BSM funds are unavailable until IRS submits to congressional 
appropriations committees for approval a modernization expenditure plan 
that (1) meets the Office of Management and Budget's (OMB) capital 
planning and investment control review requirements; (2) complies with 
IRS's enterprise architecture; (3) conforms with IRS's enterprise life-
cycle methodology; (4) is approved by IRS, the Department of the 
Treasury, and OMB; (5) is reviewed by GAO; and (6) complies with 
federal acquisition rules, requirements, guidelines, and systems 
acquisition management practices. See P.L. 108-7 (Feb. 20, 2003), and 
intervening continuing resolutions for fiscal year 2003 funding, and 
P.L. 107-67 (Nov. 12, 2001), for fiscal year 2002 funding.

[2] Since the time of our briefings, a new Commissioner of Internal 
Revenue has been confirmed.

[3] Configuration management is the means for ensuring the integrity 
and consistency of system modernization program and project products 
throughout their life cycles. Through effective configuration 
management, for example, integration among related projects and 
alignment between projects and the enterprise architecture can be 
achieved.

[4] An enterprise transition strategy describes how an organization 
will migrate from its current operating environment to its future 
operating environment.