This is the accessible text file for GAO report number GAO-03-823 
entitled 'Kennedy Center: Improvements Needed to Strengthen the 
Management and Oversight of the Construction Process' which was 
released on September 10, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

On November 16, 2003, this document was revised to add various 
footnote references missing in the text of the body of the document.

Report to the Subcommittee on Economic Development, Public Buildings, 
and Emergency Management, Committee on Transportation and 
Infrastructure, House of Representatives:

September 2003:

Kennedy Center:

Improvements Needed to Strengthen the Management and Oversight of the 
Construction Process:

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-03-823] GAO-03-823:

GAO Highlights:

Highlights of GAO-03-823, a report to the Chairman and Ranking 
Minority Member, Subcommittee on Economic Development, Public 
Buildings, and Emergency Management, Committee on Transportation and 
Infrastructure, House of Representatives 

Why GAO Did This Study:

In the mid-1990s, John F. Kennedy Center for the Performing Arts 
(Kennedy Center) officials recognized a need for additional parking 
and better site access. As a precursor to a planned project to 
construct an 8-acre plaza and two additional buildings at the site, 
the Kennedy Center is currently in the process of constructing a 
garage expansion and site improvement project. GAO did this study 
because of congressional concerns over project delays and costs as 
well as challenges that the Kennedy Center faces as it pursues this 
major construction effort. GAO’s objectives were to (1) compare the 
garage expansion and site improvement project’s current costs, time 
frames, and scope with the estimates provided to congressional 
stakeholders in 1997 and 1998 and (2) identify what challenges the 
Kennedy Center faces in managing large construction projects.

What GAO Found:

As of July 2003, Kennedy Center officials estimated that the garage 
expansion and site improvement project would cost $88 million, the 
garage expansion will be completed in December 2003, the site 
improvements will be completed in summer 2004, and the project will 
include 525 parking spaces and various traffic flow improvements. 
These estimates vary substantially from estimates that Kennedy Center 
officials provided to congressional stakeholders in 1997 and 1998. At 
that time, Kennedy Center officials estimated that the project would 
cost $28 million, would be completed by August 2000, and would include 
between 900 and 1,000 parking spaces. According to Kennedy Center 
officials, the initial estimates were preliminary in nature and were 
based on some unrealistic assumptions. They acknowledged that they 
should have done a better job of informing Congress of the preliminary 
nature of the estimates and the subsequent events in the project’s 
planning and bidding phases that affected the costs, time frames, and 
scope. Kennedy Center officials said that they now hold monthly 
meetings with Congress about the status of ongoing projects. 

The Kennedy Center faces certain challenges in managing large 
construction projects. Specifically, the Kennedy Center lacks (1) 
adequate policies and procedures to guide the planning and management 
of the construction process, (2) some timely construction data on 
schedules and costs for effectively overseeing construction projects 
and measuring results, and (3) key human capital resources and 
expertise that would be highly beneficial in managing the construction 
process. Kennedy Center officials are now working to address these 
challenges. Although making improvements in these areas is no 
guarantee of project success, these types of improvements would 
strengthen the construction program and reduce risk by providing 
greater effectiveness in managing and overseeing projects and 
measuring results. 

What GAO Recommends:

GAO recommends that the Kennedy Center

* develop comprehensive project management policies and procedures to 
guide the construction process,
* ensure development and use of timely data to oversee construction 
projects, and 
* ensure that needs for human capital expertise are met. 
In commenting on a draft of this report, Kennedy Center officials 
generally agreed with GAO’s findings and recommendations. 

www.gao.gov/cgi-bin/getrpt?GAO-03-823.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Mark L. Goldstein, 
(202) 512-2834, or goldsteinm@gao.gov.

[End of section]

Contents: 

Letter: 

Results in Brief: 

Background: 

Garage Expansion and Site Improvement Project Estimates: 

Kennedy Center Faces Challenges in Managing Its Construction Program: 

Conclusions: 

Recommendations: 

Kennedy Center Comments: 

Objectives, Scope, and Methodology: 

Appendixes:

Appendix I: Kennedy Center’s Projected Revenue from Parking Spaces
Constructed in the Garage Expansion: 

Appendix II: Agency Comments from the John F. Kennedy Center for the
Performing Arts: 

Tables:  

Table 1: Summary of the Kennedy Center’s Garage Expansion and
Site Improvement Project’s Estimated Cost, Scope, and Schedule: 

Table 2: Project Scope of the Kennedy Center Site Improvements 9
Figure Figure 1: The John F. Kennedy Center for the Performing Arts’
Building and Site: 

Figure: 

Figure 1: The John F. Kennedy Center for the Performing Arts' Building 
and Site: 

Letter September 5, 2003:

The Honorable Steven C. LaTourette 
Chairman 
The Honorable Eleanor Holmes Norton 
Ranking Minority Member 
Subcommittee on Economic Development, Public Buildings, and Emergency 
Management 
Committee on Transportation and Infrastructure 
House of Representatives:

This report responds to your request that we review certain aspects of 
the John F. Kennedy Center for the Performing Arts' (Kennedy Center) 
garage expansion and site improvement project. The Kennedy Center 
facility, which opened in 1971 in Washington, D.C., was established as 
both a national cultural arts center and a memorial to the 35TH 
President. In 1994, responsibility for management of the Kennedy Center 
facility was transferred from the Department of the Interior to the 
Kennedy Center, which has a Board of Trustees and a management staff 
headed by the Kennedy Center President. In the mid-1990s, on the basis 
of a survey of patrons, Kennedy Center officials sought to provide 
additional parking and improve access to the Kennedy Center site. To 
address these needs, the Kennedy Center is currently constructing a 
garage expansion and site improvement project that will create 525 new 
parking spaces and, among other things, make improvements to the 
sidewalks, roads, and landscaping and to the marble walkways and 
exterior wall coverings. In addition, over the next 10 years, the 
Kennedy Center plans to pursue a major expansion that includes the 
following: an 8-acre plaza that is intended to improve pedestrian 
access and link the center to the surrounding area, two new buildings 
to house administrative offices and arts education programs, facilities 
for free outdoor performances, and exhibition space to educate the 
public about the history of performing arts in America.

As agreed with your offices, our objectives were to (1) compare the 
garage expansion and site improvement project's most recent costs, time 
frames for completion, and scope with the estimates provided to 
Congress in 1997 and 1998 and (2) determine what challenges, if any, 
the Kennedy Center faces in managing large construction projects. To do 
this work, we analyzed project documents; examined existing policies 
and procedures, the organization structure, and construction data 
systems; and interviewed Kennedy Center and U.S. Army Corps of 
Engineers officials.

Results in Brief:

As of July 2003, Kennedy Center officials estimated that the garage 
expansion portion of the project would cost $45 million, including 
revenue bond issuance costs and capitalized interest payments; be 
completed in December 2003; and include 525 parking spaces. These 
officials estimated that the site improvement portion of the project 
would cost $43 million; be completed in the summer of 2004; and include 
various improvements to the sidewalks, roads, and landscaping at the 
Kennedy Center site. These estimates vary substantially from estimates 
that Kennedy Center officials provided to Congress in 1997 and 1998. At 
that time, Kennedy Center officials estimated that the garage expansion 
would cost $25 million and include between 900 and 1,000 parking 
spaces, and that the site improvements would cost $3 million and 
include construction of a new front-entry driveway. According to 
Kennedy Center officials, the initial garage expansion estimates were 
preliminary in nature and were based on some unrealistic assumptions 
related to comparable construction projects, failure to consider the 
need for year-round operations, and construction market conditions. In 
addition, Kennedy Center officials said that the final scope of the 
site improvements increased significantly from the early estimates 
because they decided to accelerate the scheduling of some planned 
repairs in hopes of expediting the work and reducing the number of 
contractors, thus simplifying project coordination efforts. These 
officials acknowledged that they should have done a better job of 
informing Congress of the preliminary nature of the estimates and the 
subsequent events in the planning and bidding phases of the project 
that affected the costs, time frames, and scope. Kennedy Center 
officials said they are now holding monthly meetings with congressional 
stakeholders regarding the status of Kennedy Center projects.

The Kennedy Center faces certain challenges in managing large 
construction projects. Specifically, the Kennedy Center lacks (1) 
adequate policies and procedures for guiding the planning and 
management of the construction process, (2) some timely construction 
data on schedules and costs for effectively overseeing construction 
projects and measuring results, and (3) key human capital resources and 
expertise that would be highly beneficial in managing the construction 
process. Although it was difficult to determine the extent to which 
these challenges have hindered the Kennedy Center's efforts on the 
garage expansion and site improvement project, having adequate policies 
and procedures, timely data, and qualified human capital would help to 
strengthen the Kennedy Center's construction program and reduce risks. 
Addressing these challenges will become increasingly important as the 
Kennedy Center undertakes the larger, more costly and complex plaza and 
buildings project. The critical importance of having quality guidance, 
data, and human capital was highlighted by the National Research 
Council in a 2000 report on federal organizations, such as the Kennedy 
Center, that contract out for construction management services to 
acquire and build facilities.[Footnote 1] The council found that having 
adequate plans, policies, and procedures; timely and reliable data; and 
in-house staff with sufficient skills was necessary for effective 
management and oversight of all phases of a construction project. We 
are making recommendations to the Kennedy Center President and Board of 
Trustees that are aimed at improving the policies and procedures, data, 
and human capital efforts for the Kennedy Center's major construction 
projects.

In commenting on a draft of this report, the Kennedy Center generally 
agreed with our findings and recommendations. Kennedy Center officials 
stated that they found many of the recommendations helpful and that 
they have initiated efforts to address them. Further, these officials 
provided additional comments to clarify information regarding the 
project estimates, project management data, and human capital 
resources, which we have incorporated throughout the report. (See app. 
II for Kennedy Center comments.):

Background:

The John F. Kennedy Center for the Performing Arts, which was 
established in 1964 as both a national cultural arts center and a 
memorial to the 35TH President, opened in September 1971 as an 
independently administered bureau of the Smithsonian Institution. 
Shortly thereafter, in 1972, the Secretary of the Interior, through the 
National Park Service, assumed responsibility for maintenance and all 
other services related to the administration of the Kennedy Center 
facility. In 1994, legislation was enacted that transferred 
responsibility for operations and maintenance of the facility to the 
Kennedy Center Board of Trustees.[Footnote 2] The 1994 legislation also 
required the Kennedy Center to develop and update annually a 
comprehensive building needs plan that details the condition of the 
Kennedy Center facility and planned renovations. The Kennedy Center 
receives annual appropriations to fund operations and maintenance as 
well as construction. For example, in fiscal year 2003, Congress 
appropriated $16.2 million for the Kennedy Center's operations and 
maintenance and $17.5 million for construction.[Footnote 3] The Kennedy 
Center has other sources of funds to finance capital improvements in 
addition to annual appropriations, such as charitable donations and the 
ability to borrow funds. The John F. Kennedy Center Act, as amended, 
provides that no changes may be made to the grounds of the Kennedy 
Center without the approval of Congress and the Secretary of the 
Interior. The John F. Kennedy Center Parking Improvement Act of 1997 
gave the Kennedy Center approval to design and construct the parking 
garage expansion and site improvements.[Footnote 4]

The garage expansion is being funded through a loan from the District 
of Columbia, which issued revenue bonds to provide the related 
funding,[Footnote 5] and the site improvements are being funded through 
annual appropriations. To maintain a separation between the 
appropriated and nonappropriated funds, the Kennedy Center arranged for 
separate construction management and general contractors for the two 
parts of the project--the parking garage expansion and the site 
improvements. The Kennedy Center also maintains separate accounting for 
the garage expansion and the site improvements. To assist in the 
construction of the garage expansion, the Kennedy Center has hired a 
construction management firm. For the site improvements, the Kennedy 
Center is using construction-contracting services available to federal 
entities through a Corps of Engineers indefinite-delivery, indefinite-
quantity contract. The Corps of Engineers is also providing limited 
management assistance to the project. Figure 1 shows the Kennedy Center 
building and adjacent area.

Figure 1: The John F. Kennedy Center for the Performing Arts' Building 
and Site: 

[See PDF for image]

Note: The garage expansion and site improvement project provides 
additional parking beneath terraces A, C, and D and improves the 
sidewalks, roads, and landscaping at the Kennedy Center site. Terraces 
A, C, and D are new structures; terrace B was part of the original 
structure.

[End of figure]

Garage Expansion and Site Improvement Project Estimates:

As of July 2003, Kennedy Center officials estimated the cost of the 
garage expansion and site improvement project at $88 million. This 
estimate includes $43 million for the site improvements and $45 million 
for the garage expansion, including revenue bond issuance costs and 
capitalized interest payments. The garage expansion is to include 525 
new parking spaces. The site improvements are designed to improve 
vehicle and pedestrian access to the Kennedy Center and include repairs 
and changes to the sidewalks, roads, and landscaping surrounding the 
Kennedy Center site. Regarding the garage expansion, 104 spaces are 
open and operating, and the remainder will open in December 2003. 
Kennedy Center officials estimated that the site improvements will be 
completed in the summer of 2004.

These current estimates reflect changes made after the 2001 contract 
award and include such things as an approximately 1-year increase in 
time frames and a $3.3 million, or 15 percent, increase in the garage 
expansion costs since the time of award. These increases were primarily 
due to (1) changes to the project design required by the National 
Capital Planning Commission and the Commission of Fine Arts; (2) large 
amounts of snow and rain during the winter and spring of 2003 that 
caused project delays; and (3) unforeseen site conditions, such as 
deteriorated concrete and greater-than-expected amounts of soil 
contamination. Kennedy Center officials told us that the site contains 
petroleum and coal-tar contamination. Although the Kennedy Center 
performed a soil test before construction began, the extent of the 
contamination was greater than expected. The costs associated with 
removing this soil contamination account for over half of the 15 
percent increase over the awarded base contract amounts.

The July 2003 estimates of the project's costs, time frames, and scope 
vary substantially from estimates that the Kennedy Center provided to 
Congress in 1997 and 1998. At that time, Kennedy Center officials 
estimated that the garage expansion would cost $25 million and would 
include 900 to 1,000 parking spaces, and that the site improvements 
would cost $3 million and include construction of a new front-entry 
driveway. Kennedy Center officials estimated that the project would be 
completed by August 2000. Table 1 summarizes the differences between 
the current and the 1997 and 1998 estimates of the project cost, scope, 
and schedule.

Table 1: Summary of the Kennedy Center's Garage Expansion and Site 
Improvement Project's Estimated Cost, Scope, and Schedule:

Garage expansion: 

Cost; 1997 and 1998 estimates: $25 million; Current estimate: $45 
million.

Scope; 1997 and 1998 estimates: 900 to 1,000 spaces; Current estimate: 
525 spaces.

Schedule; 1997 and 1998 estimates: August 2000; Current estimate: 
December 2003.

Site improvements: 

Cost; 1997 and 1998 estimates: $3 million; Current estimate: $43 
million.

Scope; 1997 and 1998 estimates: Construction of new front-entry 
driveway; Current estimate: Multiple improvements to the surrounding 
sidewalks, roadways, and landscaping and to the marble exterior wall 
coverings and walkways.

Schedule; 1997 and 1998 estimates: August 2000; Current estimate: 
Summer 2004.

Source: The John F. Kennedy Center for the Performing Arts.

[End of table]

In addition, at the time that the Kennedy Center officials were 
planning the garage expansion and site improvement project, they were 
also planning to construct a large format movie theater at an 
additional cost of $7 million to $10 million. This portion of the 
project was later dropped due to cost considerations. It was 
anticipated that repayment of the loan from the District of Columbia 
would come, in part, from parking fees and movie theater revenue. 
Kennedy Center officials recognize that the reduction in planned 
parking spaces from approximately 1,000 to 525, as well as elimination 
of the movie theater revenue, will result in a reduced amount of 
revenue available for loan payments. However, they said they are 
confident that given planned increases in parking prices over the next 
30 years, they will still be able to pay off the loan with revenue from 
the new parking spaces. A table of the Kennedy Center's projected 
parking revenue is included in appendix I. Kennedy Center officials 
told us that they have reevaluated some planned capital projects, and 
that making these changes allowed them to expand the scope of the site 
improvements portion of the project. These officials said that they 
decided to (1) eliminate two projects involving the installation of a 
mezzanine in the Grand Foyer and windows in the building facade; (2) 
delay the construction of a curtain wall; and (3) construct planned 
repairs to elevators and an expansion of the sprinkler and fire 
suppression systems in phases, rather than simultaneously.

Furthermore, in commenting on a draft of this report, Kennedy Center 
officials noted that the scope of the site improvements has increased 
substantially since the 1997 estimate, and that the scope now includes 
repairs and improvements to pedestrian walkways, the underground 
building service tunnel, garage exhaust systems, and the marble 
walkways and exterior wall coverings. Table 2 shows the scope of the 
components of the current site improvements. Kennedy Center officials 
said that they were initially planning on making these repairs at a 
later date. However, by including them with the site improvements, they 
hoped to expedite the work, achieve a more uniform architectural 
design, and reduce the number of contractors involved, thereby simplify 
scheduling and coordination efforts. Kennedy Center officials said 
these scope changes account for $38.6 million of the difference between 
the $88 million actual cost and the $28 million 1997 estimate.

Table 2: Project Scope of the Kennedy Center Site Improvements:

Component: Site improvements; Description: These improvements involve a 
reconfiguration of the access roadway to reduce traffic congestion. The 
new design provides additional security, new drop-off points in front 
of the main entrances, additional garage entrances and exits, and 
direct access to the Potomac Expressway from the Kennedy Center site. 
Pedestrian access will also be improved by replacing the steep ramp 
with a monumental stairway and a fully accessible walkway. The site is 
being relandscaped to accommodate these changes. 

Component: Service tunnel, service drive, and loading dock; 
Description: These repairs entail adding structural reinforcement to 
portions of the service tunnel roof to accommodate the new roadway 
above the plaza. In addition, mechanical work is required to reroute 
the supply and exhaust systems that currently service the entire 
building. Finally, the design includes a secured exit out of the 
service tunnel, thereby making the service tunnel suitable for high-
level dignitary visits. 

Component: Existing garage repairs and mechanical systems; 
Description: This component includes the repair and replacement of 
exhaust fans and underground ducts and the installation of carbon 
monoxide monitors tied into the existing garage exhaust system. It also 
includes new signage and new striping in the existing garage. 

Component: Plaza repairs; Description: These repairs include replacing 
the marble around the exterior of the building with granite pavers, 
plumbing repairs, and replacing all of the drains and waterproofing. 

Component: West fascia; Description: These repairs entail removing and 
replacing 63 marble panels, repairing the front planter, and installing 
a new safety rail. 

Source: The John F. Kennedy Center for the Performing Arts.

[End of table]

Kennedy Center officials were unable to provide a detailed explanation 
of how they arrived at the preliminary 1997 and 1998 cost and schedule 
estimates because they had experienced high staff turnover since the 
estimates were developed, and records were either not available or not 
retained. Despite this fact, these officials said that it appeared that 
the estimates were based on some unrealistic assumptions. For example, 
they said the initial estimates:

* were incorrectly based on construction costs of garages outside the 
District of Columbia, which was a poor comparison because they are less 
expensive to construct;

* did not adequately consider the need to keep the Kennedy Center open 
365 days per year, which had an effect on construction phasing and 
coordination issues and subsequently on the estimated costs and time 
frames; and:

* did not account for the unusually expensive, busy, and competitive 
construction market conditions during this period.

Furthermore, the project was delayed for approximately 2 years as 
Kennedy Center officials worked through multiple efforts to design and 
bid the project and reduce project costs. For example, as part of the 
National Capital Planning Commission and the Commission of Fine Arts 
project review process, the Kennedy Center was required to redesign 
some portions of the project to comply with their decisions regarding 
design elements, finishes, landscaping, and the elimination of planned 
valet parking on top of the semi-elliptical terrace.[Footnote 6] In 
addition, budget constraints led the Kennedy Center to undertake 
various efforts in an attempt to lower the project cost, such as (1) 
redesigning portions of the project, (2) performing value engineering 
to identify and eliminate unnecessary costs, and (3) rebidding the 
project after initial contractor bids far exceeded the Kennedy Center's 
expectations and it was unsuccessful in negotiating with the lowest 
bidder. Kennedy Center officials acknowledged that they should have 
better informed Congress of the preliminary nature of the 1997 and 1998 
estimates and the subsequent events in the planning and bidding phases 
of the project that affected the project's costs, time frames, and 
scope. As a result, these officials said that they now have monthly 
meetings with congressional stakeholders to discuss the status of 
ongoing construction projects.

Kennedy Center Faces Challenges in Managing Its Construction Program:

In addition to problems associated with the planning and bidding phases 
of the project, we found that the Kennedy Center faces a number of 
challenges in managing large construction projects. The Kennedy Center 
lacks (1) adequate policies and procedures to guide the planning and 
management of the construction process, (2) some timely construction 
data on schedules and costs for effectively overseeing construction 
projects and measuring results, and (3) key human capital resources and 
expertise that would be highly beneficial in managing the construction 
process. More specifically:

* Policies and procedures. Although the Kennedy Center had some limited 
construction-related guidance, such as safety plans developed by the 
construction management contractor, it does not have formal, written 
project management policies and procedures to help guide and administer 
construction projects. A typical project management guide would include 
policies and procedures on the organization of the project, quality 
control and assurance standards, project execution procedures, and 
requirements for day-to-day administration of contracts, all of which 
would help to ensure overall project oversight. Other federal agencies 
that manage construction projects, such as the General Services 
Administration, the Department of State, and the Architect of the 
Capitol, use such guidance.

* Timely construction data. The Kennedy Center does not always receive 
timely construction data on schedules and costs. These data are 
necessary for monitoring construction costs and measuring results, such 
as estimated total project costs. For example, the Kennedy Center's 
construction manager told us that he provided cash flow reports only 
when requested, and that, at times, he provided the reports at a rate 
of once every 3 months, instead of on a monthly basis as required by 
the contract. In addition, the Kennedy Center decided to waive the 
submission of key timely written project management reports from the 
construction manager and to rely instead on weekly meetings. In 
commenting on a draft of this report, Kennedy Center officials said 
that they had received timely scheduling data on the garage project, on 
a weekly and monthly basis, at various meetings. However, these 
meetings were no substitute for timely written reports, which are 
typically used in construction project management and would have 
provided additional detailed information on schedules and costs that 
could have been helpful in project oversight. Kennedy Center officials 
agree that they should have obtained monthly project management reports 
and are now doing so.

* Human capital resources and expertise. Kennedy Center officials lack 
key human capital resources and expertise that would be highly 
beneficial in managing the construction process. For example, the 
Kennedy Center experienced significant turnover in both in-house staff 
and contractor personnel during the design stages of the project, which 
has contributed to reduced institutional knowledge of the project and 
has increased the time necessary to finalize design decisions. In 
addition, two key management positions were left vacant for an extended 
period. The project executive position became vacant in September 2001. 
The person in this position is responsible for directing and managing 
all capital repair and construction projects. Kennedy Center officials 
had decided not to fill the project executive position, but instead to 
have the executive vice president assume those duties. However, Kennedy 
Center officials said that given the complexities and scale of the 
upcoming plaza and buildings project, they now plan to fill this 
position and have the person report to the executive vice president. 
Also, the contracting officer position became vacant in the summer of 
2002, and Kennedy Center officials told us that because of difficulties 
in finding a qualified candidate, they did not fill this position until 
March 2003. The President of the Kennedy Center told us he recognized 
that the Kennedy Center continues to lack adequate staff or expertise 
to manage its upcoming plaza and buildings project, and he detailed 
plans to address these shortcomings. In commenting on a draft of this 
report, Kennedy Center officials noted that they are in the process of 
filling the positions of director of capital projects and project 
manager, have engaged an architect and developer firm, and now feel 
that they do have sufficient staff and expertise.

These construction management challenges are not new to the Kennedy 
Center. In September 1995, a Kennedy Center consultant reported that 
there were no clear lines of responsibility within the existing 
facility management structure, and that job descriptions were not 
clearly defined.[Footnote 7] In addition, the consultant's report also 
noted the following: "An organized system should be developed for 
managing information concerning the facility operations to be used to 
monitor performance against established standards." Regarding human 
capital, we reported in 1993 that the Kennedy Center lacked a federal 
contracting officer, architects, engineers, or other professional 
occupations associated with capital projects.[Footnote 8] We concluded 
that the Kennedy Center did not have sufficient capability to 
effectively manage large-capital construction projects. In commenting 
on a draft of this report, Kennedy Center officials told us that since 
1993, they have added a contracting department of five full-time 
positions and an entire project management department consisting of 
nine employees--six full-time Kennedy Center employees, including four 
project managers and two support personnel, plus three contract 
employees. In addition, these officials said that full job descriptions 
have been developed for all positions.

Although it is difficult to determine the extent to which these 
challenges have hindered the Kennedy Center's efforts on the garage 
expansion and site improvement project to date, having adequate 
policies and procedures, timely construction data, and additional 
qualified human capital--even though the Kennedy Center has enhanced 
its facility management staff since our earlier reports--would help to 
strengthen the construction program and reduce risk. Addressing these 
challenges will become increasingly important as the Kennedy Center 
undertakes the larger, more costly, and more complex plaza and 
buildings project. The critical importance of having quality guidance, 
data, and human capital was highlighted by the National Research 
Council's 2000 report on federal organizations, such as the Kennedy 
Center, that contract out for construction management services to 
acquire and build facilities. The council found that, among other 
things, these organizations should have (1) plans, policies, and 
procedures to define project goals and develop strategies and methods 
for achieving those goals; (2) detailed data to monitor progress and 
assess risks; and (3) in-house staff with sufficient management, 
financial, and technical skills necessary for effective oversight of 
all phases of the project. Effective policies and procedures would 
provide a road map for project managers on how best to estimate project 
costs, administer the contract, and define the roles and 
responsibilities of project staff. Timely data would allow project 
managers to effectively oversee project status and measure results to 
gauge effectiveness. Qualified human capital and expertise would 
improve efforts to control project costs, time frames, and scope. 
Kennedy Center officials acknowledged the importance of focusing on 
these areas. In commenting on a draft of this report, these officials 
said that they have initiated efforts to improve these areas of 
concern, including (1) contacting the Federal Facilities Council for 
assistance with updating and improving construction management policies 
and procedures, (2) requesting monthly written project management 
reports, and (3) hiring additional in-house and contractor staff to 
assist in the upcoming plaza and buildings project.

Conclusions:

Changes in costs, time frames, and scope are not unusual in large 
construction projects. However, in the case of the Kennedy Center 
garage expansion and site improvement project, early estimates proved 
to be especially problematic and were based on unrealistic assumptions. 
Furthermore, if the Kennedy Center continues to operate without 
adequate construction polices and procedures, timely schedule and cost 
data, and qualified human capital, the success of its future plaza and 
buildings project will be at risk. Although making improvements in 
these areas is no guarantee of project success, such improvements would 
strengthen the construction program and reduce risk by providing 
greater effectiveness in managing and overseeing future projects and 
measuring results.

Recommendations:

To help improve the Kennedy Center's ability to manage and oversee its 
construction program, we recommend that the President of the Kennedy 
Center, in conjunction with the Chairman of the Board of Trustees,

* develop comprehensive project management policies and procedures to 
guide the planning and execution of the construction process,

* ensure development and use of timely data to oversee construction 
projects and measure results, and:

* ensure that the needs for human capital expertise are met.

Kennedy Center Comments:

We provided a draft copy of this report to the Chairman of the Kennedy 
Center Board of Trustees and the President of the Kennedy Center. On 
June 20, 2003, the Kennedy Center President provided us with written 
comments on behalf of the trustees and staff (see app. II). Kennedy 
Center officials generally agreed with our findings and 
recommendations. They said that they found the recommendations helpful, 
and that they have initiated efforts to address them. Further, these 
officials provided additional comments to clarify information regarding 
the project estimates, project management data, and human capital 
resources, which we have incorporated throughout the report as 
appropriate.

Objectives, Scope, and Methodology:

To meet our first objective of comparing the garage expansion and site 
improvement project's most recent estimates on costs, time frames for 
completion, and scope with estimates previously provided to Congress in 
1997 and 1998, we analyzed Kennedy Center construction project 
documents, such as contracts, estimates, and plans. To gain a better 
understanding of the construction project, we accompanied a Kennedy 
Center official on a tour of the construction site during which the 
official pointed out the major components and features of the project. 
In addition, we interviewed officials with the Kennedy Center, the 
construction management contractor, the architectural firm involved 
with the project, and the U.S. Army Corps of Engineers. To meet our 
second objective of determining what challenges, if any, the Kennedy 
Center faces in managing large construction projects, we examined the 
Kennedy Center construction process, including existing policies and 
procedures, organization structure, and construction data systems. For 
background information, we reviewed applicable statutes relating to the 
Kennedy Center and considered previous GAO work and industry 
construction management practices.

We did our work between January and July 2003 in accordance with 
generally accepted government auditing standards.

:

As agreed with your offices, unless you publicly announce its contents 
earlier, we plan no further distribution of this report until 30 days 
after its issue date. At that time, we will send copies of this report 
to the appropriate congressional committees, the Chairman of the 
Kennedy Center Board of Trustees, and the President of the Kennedy 
Center. We will make copies available to others on request. In 
addition, this report will be available at no charge on the GAO Web 
site at [Hyperlink, http://www.gao.gov] http://www.gao.gov.

If you or your staff have any questions, please contact me on (202) 
512-2834 or at [Hyperlink, goldsteinm@gao.gov] goldsteinm@gao.gov. 
Major contributors to this report were Casey L. Brown, Terrell Dorn, 
and Thomas G. Keightley.

Mark L. Goldstein 
Acting Director, Physical Infrastructure Issues:

Signed by Mark L. Goldstein: 

[End of section]

Appendixes: 

Appendix I: Kennedy Center's Projected Revenue from Parking Spaces 
Constructed in the Garage Expansion: 

Fiscal year: 2004; Parking rate per space: $15; Number of parking 
spaces: 525; Projected capacity factor: 0.8; Annual revenue: 
$2,299,500; Debt service (principal plus interest): $3,830,124; Excess 
(deficit): ($1,530,624).

Fiscal year: 2005; Parking rate per space: 15; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
3,161,813; Debt service (principal plus interest): 2,345,932; Excess 
(deficit): 815,881.

Fiscal year: 2006; Parking rate per space: 16; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
3,372,600; Debt service (principal plus interest): 2,347,134; Excess 
(deficit): 1,025,466.

Fiscal year: 2007; Parking rate per space: 16; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
3,372,600; Debt service (principal plus interest): 810,765; Excess 
(deficit): 2,561,835.

Fiscal year: 2008; Parking rate per space: 17; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
3,583,388; Debt service (principal plus interest): 2,327,825; Excess 
(deficit): 1,255,563.

Fiscal year: 2009; Parking rate per space: 17; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
3,583,388; Debt service (principal plus interest): 3,906,706; Excess 
(deficit): (323,319).

Fiscal year: 2010; Parking rate per space: 18; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
3,794,175; Debt service (principal plus interest): 2,353,108; Excess 
(deficit): 1,441,067.

Fiscal year: 2011; Parking rate per space: 18; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
3,794,175; Debt service (principal plus interest): 2,354,248; Excess 
(deficit): 1,439,927.

Fiscal year: 2012; Parking rate per space: 19; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
4,004,963; Debt service (principal plus interest): 706,533; Excess 
(deficit): 3,298,430.

Fiscal year: 2013; Parking rate per space: 19; Number of parking 
spaces: 525; Projected capacity factor: 1.1; Annual revenue: 
4,004,963; Debt service (principal plus interest): 2,333,685; Excess 
(deficit): 1,671,278.

Fiscal year: 2014; Parking rate per space: 20; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
4,982,250; Debt service (principal plus interest): 2,333,633; Excess 
(deficit): 2,648,617.

Fiscal year: 2015; Parking rate per space: 20; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
4,982,250; Debt service (principal plus interest): 4,060,521; Excess 
(deficit): 921,729.

Fiscal year: 2016; Parking rate per space: 21; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
5,231,363; Debt service (principal plus interest): 2,362,280; Excess 
(deficit): 2,869,083.

Fiscal year: 2017; Parking rate per space: 22; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
5,480,475; Debt service (principal plus interest): 2,367,424; Excess 
(deficit): 3,113,051.

Fiscal year: 2018; Parking rate per space: 22; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
5,480,475; Debt service (principal plus interest): 539,607; Excess 
(deficit): 4,940,868.

Fiscal year: 2019; Parking rate per space: 23; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
5,729,588; Debt service (principal plus interest): 2,335,932; Excess 
(deficit): 3,393,656.

Fiscal year: 2020; Parking rate per space: 24; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
5,978,700; Debt service (principal plus interest): 2,332,691; Excess 
(deficit): 3,646,009.

Fiscal year: 2021; Parking rate per space: 24; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
5,978,700; Debt service (principal plus interest): 4,275,310; Excess 
(deficit): 1,703,390.

Fiscal year: 2022; Parking rate per space: 25; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
6,227,813; Debt service (principal plus interest): 2,376,286; Excess 
(deficit): 3,851,527.

Fiscal year: 2023; Parking rate per space: 26; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
6,476,925; Debt service (principal plus interest): 2,379,500; Excess 
(deficit): 4,097,425.

Fiscal year: 2024; Parking rate per space: 27; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
6,726,038; Debt service (principal plus interest): 311,664; Excess 
(deficit): 6,414,374.

Fiscal year: 2025; Parking rate per space: 28; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
6,975,150; Debt service (principal plus interest): 2,337,920; Excess 
(deficit): 4,637,230.

Fiscal year: 2026; Parking rate per space: 29; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
7,224,263; Debt service (principal plus interest): 4,513,050; Excess 
(deficit): 2,711,213.

Fiscal year: 2027; Parking rate per space: 30; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
7,473,375; Debt service (principal plus interest): 2,395,916; Excess 
(deficit): 5,077,459.

Fiscal year: 2028; Parking rate per space: 30; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
7,473,375; Debt service (principal plus interest): 2,394,620; Excess 
(deficit): 5,078,755.

Fiscal year: 2029; Parking rate per space: 31; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
7,722,488; Debt service (principal plus interest): 58,953; Excess 
(deficit): 7,663,535.

Fiscal year: 2030; Parking rate per space: 32; Number of parking 
spaces: 525; Projected capacity factor: 1.3; Annual revenue: 
7,971,600; Debt service (principal plus interest): 2,343,953; Excess 
(deficit): 5,627,647.

Fiscal year: Total: Annual revenue: 
$143,086,388; Debt service (principal plus interest): $63,035,320; 
Excess (deficit): $80,051,068.

Source: The John F. Kennedy Center for the Performing Arts.

Note: The information in this appendix was provided by the John F. 
Kennedy Center for the Performing Arts and does not contain any GAO 
analysis.

[End of table]

[End of section]

Appendix II: Agency Comments from the John F. Kennedy Center for the 
Performing Arts:

The John E Kennedy Center for the Performing Arts:

June 20, 2003:

Mr. Mark L. Goldstein:

Acting Director, Physical Infrastructure Issues United States General 
Accounting Office:

WASHINGTON, D.C. 20566-0001 202 416-8010:

FAX 202 416-8018:

Dear Mr. Goldstein:

On behalf of the Trustees and staff of the John F. Kennedy Center for 
the Performing Arts, I want to thank you and your team from the General 
Accounting Office for forwarding the draft report, " Kennedy Center: 
Improvements Needed to Strengthen Management and Oversight of the 
Construction Process." This document will assist us in our continuing 
efforts to improve all aspects of Kennedy Center management.

We found many of the observations and recommendations helpful and have 
already initiated substantial efforts to address these points. In 
particular, we have already contacted the Federal Facilities Council to 
ask for assistance with updating and strengthening our construction 
management policies and procedures guide. We have also identified and 
solicited the management reports you have recommended we receive from 
our construction manager. And, finally, we have either hired or 
initiated the hiring process for the personnel you recommended we 
engage to strengthen our construction management with particular focus 
on the upcoming Plaza Project.

While we found the report illuminating, there are several key areas 
addressed by the report we wish to clarify.

1. The comparison of the actual construction costs for the garage 
expansion and the site work versus the original Congressional testimony 
of 1997 suggests that the project as conceived in 1996 and the one 
actually implemented were one and the same. In fact, the site work 
actually implemented is substantially more complex and far-reaching 
than the simple road re-design contemplated in the original testimony. 
During the design development phase of the project, it was decided to 
expand the scope of work for the site improvements to improve security 
and health and safety for our 3,000,000 annual visitors and our staff 
and to speed traffic flow. These additional project elements include:

* improving pedestrian access by replacing the steep ramp with a 
monumental stairway and a fully accessible walkway:

* making structural modifications and repairs to the service tunnel to 
reinforce the tunnel to accommodate the new roadway above the plaza and 
adding a secured exit at the south end of the service tunnel to make it 
a secure and useable means of entrance to the building by the secret 
service for high-level dignitary visits:

* making repairs to the existing garage and its mechanical systems to 
repair and replace exhaust fans and underground ducts and install 
carbon monoxide monitors tied into the existing garage exhaust system:

* making extensive repairs to the plaza, including the replacement of 
the marble walking surface with granite pavers, plumbing repair and 
replacement of all drains and waterproofing:

* removing and replacing 63 marble panels on the west fascia and 
installing a safety rail on the west terrace:

These enhancements account for $38.6 million of the difference between 
the $87 million actual cost and the $28 million testified to in 1997. 
In addition, the original testimony did not include capitalized 
financing costs currently estimated at $7.5 million.

Once construction started, the garage expansion has proceeded on 
schedule, with the exception of some delays due to a particularly harsh 
and wet winter and spring and significant amounts of contaminated soil 
discovered during construction.

The number of additional spaces estimated during the initial design of 
the garage expansion included the use of the surface of the terraces 
(Figure 1, areas A, C, and D in the report) as parking area, providing 
359 exterior spaces. The use of the terraces for this purpose was 
eliminated at the request of the Commission of Fine Arts. The design 
does continue to provide us with the ability to add car stackers in the 
north and south additions, which could add 150 additional parking 
spaces.

It should also be noted that over the term of the bonds the income 
anticipated from the 525 additional parking spaces will generate a 
significant positive cash flow after all construction costs are paid, 
including principal and interest due on the bonds.

2. With respect to project information, we always received timely 
scheduling data on the garage project, weekly and monthly. At the 
beginning of the project, cash flow projections did not change from 
month to month and therefore did not call 
for monthly updates. Once change orders were initiated due to 
unforeseen soil conditions and poor weather, changes in cash flow 
projections were received regularly. While the monthly project 
management reports should have been solicited, and are now being 
received regularly, the weekly progress meetings provided detailed 
information on scheduling and pending problems which could result in 
change orders in a more timely manner.

3. The two new buildings included in the anticipated Plaza Project are 
summarized as housing 'administrative offices and arts education 
programs.' I think it is important that all those who read this report 
understand that the project will also include an outdoor facility for 
free public performances, substantial rehearsal 
facilities that will be open to the public, and major exhibitions that 
allow members of the public to learn about the history of the 
performing arts in America and to participate in the arts by conducting 
an orchestra, designing sets and costumes and performing other 
`backstage' tasks. The new Kennedy Center campus will give visitors an 
arts experience available no other place in the world.

4. 1 am correctly cited with reference to my May 7, 2003 letter to the 
GAO recognizing that the Kennedy Center lacks adequate staff or 
expertise to manage the Plaza Project. Omitted from this report, 
however, were my plans, delineated in my letter, to address this 
shortcoming. In fact, we are currently in the process of filling the 
position of Director of Capital Projects. In addition, we have followed 
a plan suggested by the United States Department of Transportation for 
the staffing of the Plaza Project and have already engaged an architect 
after an extensive search process, engaged in a panel process and hired 
a developer firm that will provide comprehensive project management 
services as the Kennedy Center's Owner's Representative, and have 
initiated interviews for the position of Project Manager, an in-house 
expert who will serve as an in-house liaison between Center staff and 
the project team. I am now satisfied that we do have the staff and 
expertise in place to complement the team assembled by the Department 
of Transportation.

As a point of information, since the consultant study of 1995 and the 
GAO study of 1993, both cited in the report, the Kennedy Center has 
added a contracting department of five full time positions and an 
entire project management department consisting of a total of six full 
time employees, including four project managers and two support 
personnel, plus three contract employees. Full job descriptions have 
been developed for all positions. In addition to overseeing the garage 
expansion and site work, this department has successfully managed the 
refurbishment of the Grand Foyer, including the installation of 
interactive exhibits, the renovation of the Opera House, the redesign 
of a gift shop, the installation of a new Fire Alarm system, the 
abatement of asbestos and several other smaller projects in the past 
three years.

Once again, we appreciate the time, effort and thoughtfulness of the 
GAO team that completed this project and look forward to using the 
recommendations provided to assist with the Kennedy Center's 
construction management process.

Sincerely,

Michael M. Kaiser 
President:

Signed by Michael M. Kaiser: 

[End of section]

(543062):

FOOTNOTES

[1] National Research Council, Outsourcing Management Functions for the 
Acquisition of Federal Facilities (Washington, D.C.: National Academy 
Press, 2000). The council is the working arm of the National Academy of 
Sciences and the National Academy of Engineering, and it carries out 
studies to advise the federal government.

[2] The Kennedy Center Board of Trustees is composed of 36 general 
trustees who must be U.S. citizens and who are appointed by the 
President of the United States, 13 trustees designated ex-officio 
representatives of the executive branch and other government branches, 
and 10 congressional representative trustees. Each appointed trustee 
serves a term of 6 years.

[3] P.L. 108-7, 117 Stat. 11, 267, 550-551 (2003).

[4] 20 U.S.C. 76i(b). 

[5] On December 15, 1999, the District of Columbia issued $34 million 
in District of Columbia revenue bonds and loaned the proceeds to the 
Kennedy Center for the purpose of constructing the garage expansion. 
The bonds are secured by parking revenues from the garage expansion. 
Payments of principal and interest on the bonds are insured by the 
Ambac Assurance Corporation.

[6] In general, the National Capital Planning Commission and the 
Commission of Fine Arts review every federal development project in the 
National Capital Region and approve or deny the location and design of 
new construction; exterior additions and renovations; grading and 
landscaping; street and road extensions; and parking modifications at 
all federal buildings, museums, memorials, and monuments.

[7] Wiss, Janney, Elstner Associates, Inc., Trammell Crow Company, and 
Environmental Systems Design, Inc., Facility Management Assessment, 
Phase I (Washington, D.C.: September 1995).

[8] U.S. General Accounting Office, Kennedy Center: Information on the 
Capital Improvement Program, GAO/GGD-93-46 (Washington, D.C.: Feb. 9, 
1993). 

GAO's Mission:

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to daily E-mail alert for newly 
released products" under the GAO Reports heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548:

To order by Phone: 	

	Voice: (202) 512-6000:

	TDD: (202) 512-2537:

	Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: