This is the accessible text file for GAO report number GAO-03-287 
entitled '2000 Census: Coverage Measurement Programs’ Results, Costs, 
and Lessons Learned' which was released on January 29, 2003.



This text file was formatted by the U.S. General Accounting Office 

(GAO) to be accessible to users with visual impairments, as part of a 

longer term project to improve GAO products’ accessibility. Every 

attempt has been made to maintain the structural and data integrity of 

the original printed product. Accessibility features, such as text 

descriptions of tables, consecutively numbered footnotes placed at the 

end of the file, and the text of agency comment letters, are provided 

but may not exactly duplicate the presentation or format of the printed 

version. The portable document format (PDF) file is an exact electronic 

replica of the printed version. We welcome your feedback. Please E-mail 

your comments regarding the contents or accessibility features of this 

document to Webmaster@gao.gov.



Report to the Chairman, Subcommittee on Civil Service, Census, and 

Agency Organization, Committee on Government Reform, House of 

Representatives:



January 2003:



2000 Census:



Coverage Measurement Programs’ Results, Costs, and Lessons Learned:



GAO-03-287:



GAO Highlights:



Highlights of GAO-03-287, a report to

Chairman, Subcommittee on Civil Service,

Census, and Agency Organization,

Committee on Government Reform,

House of Representatives



2000 CENSUS

Coverage Measurement Programs’

Results, Costs, and Lessons Learned



Why GAO Did This Study:



To help measure the quality of the 2000 Census and to possibly adjust

for any errors, the U.S. Census Bureau (Bureau) conducted the

Accuracy and Coverage Evaluation (A.C.E.) program. However, after

obligating around $207 million for A.C.E. and its predecessor

program, Integrated Coverage Measurement (I.C.M.), from fiscal

years 1996 through 2001, the Bureau did not use either program

to adjust the census numbers. Concerned about the amount of

money the Bureau spent on I.C.M. and A.C.E. programs and what was

produced in return, the subcommittee asked us to review

the objectives and results of the programs, the costs of consultants,

and how best to track future

coverage measurement activities.



What GAO found:



As shown below, the two programs the Bureau employed to measure the

quality of the 2000 Census population data did not meet their 

objectives.



Coverage Measurement Programs Did Not Achieve Objectives

Program/objectives.



[See PDF for Image]

[End of Figure]



The A.C.E. program achieved results other than those laid out in the

Bureau’s formal objectives that highlight important lessons learned. 

They

include (1) developing a coverage measurement methodology that is both

operationally and technically feasible, (2) determining the level of 

geography at which coverage measurement is intended, (3) keeping 

stakeholders, particularly Congress, informed of the Bureau’s plans, 

and (4) adequately testing coverage measurement methodologies. It will 

be important for the Bureau to consider these as its current plans for 

the 2010 Census include coverage evaluation to measure the accuracy of 

the census but not necessarily to adjust the results.

Of the roughly $207 million the Bureau obligated for I.C.M./A.C.E. 

programs

from fiscal years 1996 through 2001, we identified about $22.3 million 

that

was obligated for contracts involving over 170 vendors. We could not

identify any obligations prior to 1996 in part because the Bureau 

included

them with its general research and development efforts and did not 

assign

the I.C.M./A.C.E. operations unique project codes in its financial

management system. To track these costs in the future, it will be 

important

for the Bureau to (1) have a financial management system that has 

specific

project codes to capture coverage measurement costs, (2) establish 

the

project codes as early in the planning process as possible, and (3) 

monitor

the usage of the codes to ensure that they are properly charged.



What GAO Recommends:



The Secretary of Commerce should direct the Bureau to (1) work with

Congress and other stakeholders and soon decide on whether and

how coverage measurement will be used in 2010, (2) adopt lessons

learned from its 2000 Census experience, and (3) ensure that its

financial management systems can capture and report program

activities early and that projects’ costs are monitored. The Bureau

agreed with our recommendations but noted that for the 2000 Census,

it followed the steps we identified as lessons learned. It also took

exception to how we presented our conclusions concerning its ability

to properly classify certain costs.



To view the full report, including the scope

and methodology, click on the link above.

For more information, contact Patricia A.

Dalton at (202) 512-6806 or

daltonp@gao.gov



Contents:



Letter:



Results in Brief:



Background:



Scope and Methodology:



Coverage Measurement

Programs for the 2000 Census

Did Not Meet Bureau Objectives:



I.C.M./A.C.E. Contractor Costs Are Not Complete:



Tracking Future Coverage Measurement Costs:



Conclusions:



Recommendations for Executive Action:



Agency Comments and Our Evaluation:



Appendix:



Appendix I: Comments from the Department of Commerce:



Related GAO Products:



Tables :



Table 1: Coverage Measurement Programs Did Not Achieve Objectives:



Table 2: Census 2000 I.C.M./A.C.E. Contractor Costs for Fiscal Years 

1996 through 2001 (Dollars in thousands):



Letter January 29, 2003:



The Honorable Dave Weldon, M.D.

Chairman

Subcommittee on Civil Service,

Census, and Agency Organization

Committee on Government Reform

House of Representatives:



Dear Mr. Chairman:



To assess the quality of population data for the 2000 Census and to 

possibly adjust for any errors, the U.S. Census Bureau (Bureau) 

conducted the Accuracy and Coverage Evaluation (A.C.E.) program. The 

A.C.E. program was first included in Bureau program documents in 

November 1998 and funded for fiscal years 2000 through 2002 with 

proposed funding through December 31, 2002. Its predecessor, Integrated 

Coverage Measurement (I.C.M.), began in May 1995 and was funded by the 

Bureau for fiscal years 1996 through 1999. The Bureau obligated about 

$207 million to both programs from fiscal years 1996 through 

2001,[Footnote 1] which was about 3 percent of the $6.5 billion total 

estimated cost of the 2000 Census. However, neither program was used to 

adjust the 2000 Census population count.



Concerned about the amount of money the Bureau spent on both programs 

as well as what was received in return for its investment, you and 

former Vice Chairman Dan Miller asked us to examine (1) the Bureau’s 

objectives for the I.C.M./A.C.E. programs and the extent to which those 

objectives were met, (2) the cost of consultants and technical studies, 

and (3) ways to track the costs of coverage measurement activities in 

future censuses. This report responds to that request.



In October 2002, we issued a report that provides additional 

information on the cost of the I.C.M./A.C.E. programs.[Footnote 2] Both 

reports are part of our ongoing series on the results of the 2000 

Census and the lessons learned for planning a more cost-effective 

census in 2010. (See the Related GAO Products section at the end of 

this report for the assessments issued to date.):



Results in Brief:



The coverage measurement programs the Census Bureau planned for the 

2000 Census--I.C.M. and its successor, A.C.E.--did not meet their 

intended objectives. Although the Bureau designed I.C.M. to measure 

census coverage; generate data for apportionment, redistricting, and 

federal programs using statistical sampling and estimation; and produce 

a “one-number” census based on statistical sampling and estimation, the 

Bureau abandoned the program following a Supreme Court ruling that the 

Census Act prohibited the use of statistical sampling to generate 

population data for reapportioning the House of 

Representatives.[Footnote 3] Because its replacement--A.C.E.--did not 

provide a reliable measure of census accuracy in time to meet legally 

mandated deadlines for releasing redistricting data, the Bureau decided 

against using it to adjust the census data for nonapportionment 

purposes.



The difficulties the Bureau encountered in trying to implement I.C.M. 

and A.C.E. underscore the importance of (1) developing a coverage 

measurement methodology that is both technically and operationally 

feasible, (2) determining the level of geography at which coverage 

measurement is intended, (3) keeping stakeholders, particularly 

Congress, informed of the Bureau’s plans, and (4) adequate testing. It 

will be important for the Bureau to address these lessons learned as 

its planning efforts for the 2010 Census continue. Those plans 

currently call for a coverage measurement program to evaluate the 

accuracy of the census, whereas the issue of whether coverage 

measurement will be used to adjust the numbers has not yet been 

resolved.



Concerning the cost of contracts, including the consultants and 

technical studies related to the I.C.M./A.C.E. programs, we identified 

about 

$22.3 million of obligated amounts for over 170 vendors for fiscal year 

1996 through fiscal year 2001 from unaudited Bureau financial 

management reports. This amount does not represent the complete 

contract costs for the I.C.M./A.C.E. programs for three reasons. First, 

the Bureau considered costs from earlier years to be part of its 

general research and development efforts and did not assign unique 

project codes to identify I.C.M./A.C.E. programs and related costs in 

its financial management system. Second, although $182,000 of fiscal 

year 1996 obligated costs were identified in the Bureau’s financial 

management systems as contract costs for an I.C.M. special test, the 

Bureau did not consider these costs as part of the I.C.M./A.C.E. 

programs and classified these costs as general research. We disagreed 

with the Bureau on this point and have included this amount in our 

report as part of the I.C.M./A.C.E. contract costs that we could 

identify from Bureau records. Finally, certain costs, such as program 

evaluations, were Bureau-wide in nature, and the portion attributable 

to I.C.M./A.C.E could not be separated out.



The Bureau’s ability to track future costs of coverage measurement 

activities is primarily dependent on its ability to (1) ensure that its 

financial management system accurately and completely captures the 

accounting and reporting of project codes, (2) design its project codes 

to capture coverage measurement activities as early in the planning 

process as possible, even though the activities’ names may change as 

the programs evolve, and (3) correctly charge the project codes 

established.



Although the Bureau has never used the results of its coverage 

measurement programs to adjust census numbers, we believe that an 

evaluation of the accuracy of the census is essential given the 

importance of the data, the need to know the nature of any errors, and 

the cost of the census overall. Whether the results of the evaluation 

should be used to adjust the census is still an open question, the 

answer to which should involve discussions between the Bureau, 

Congress, and other stakeholders, and be based on detailed data and a 

convincing demonstration of the feasibility of the Bureau’s proposed 

approach. Regardless of the outcome of the decision, it is critical 

that it be made soon so that the Bureau can proceed with its planning. 

The longer the Bureau goes without a firm decision on the role of 

coverage measurement, the greater the risk of wasted resources and 

disappointing results. In light of the challenges facing the Bureau as 

it prepares for the next decennial census in 2010, we recommend that 

the Secretary of Commerce direct the U.S. Census Bureau to:



* in conjunction with Congress and other stakeholders, decide soon on 

whether and how coverage measurement will be used in the 2010 Census;



* consider incorporating lessons learned from its coverage measurement 

experience during the 2000 Census, such as (1) demonstrating both the 

operational and technical feasibility of its coverage measurement 

methods, (2) determining the level of geography at which coverage can 

be reliably measured, (3) keeping Congress and other stakeholders 

informed of its plans, and (4) adequately testing coverage measurement 

prior to full implementation; and:



* ensure that the Bureau’s financial management systems can capture and 

report program activities early in the decennial process and that 

project costs are monitored for accuracy and completeness.



The Secretary of Commerce forwarded written comments from the Bureau of 

the Census on a draft of this report (see app. I). The Bureau agreed 

with our recommendations noting that they were important steps that 

should be followed in the development of a coverage measurement 

methodology for the 2010 Census. However, the Bureau maintained that 

most of these steps such as keeping Congress and other stakeholders 

informed of its plans were followed for the 2000 Census. We disagree 

because, as noted in the report, the lack of information contributed to 

stakeholders’ skepticism surrounding the Bureau’s plans. The Bureau 

also took exception to the way we presented our conclusions concerning 

its ability to properly classify certain costs associated with the 

development of the Bureau’s coverage measurement programs. Our 

perspective on the Bureau’s position is detailed in the “Agency 

Comments and Our Evaluation” section at the end of this report.



Background:



The Bureau puts forth tremendous effort to conduct a complete and 

accurate count of the nation’s population. However, some degree of 

error in the form of persons missed or counted more than once is 

inevitable because of limitations in census-taking methods. Because 

census results are used, among other purposes, to apportion Congress, 

redraw congressional districts, and allocate federal aid to state and 

local governments, the size and demographic composition of these 

coverage errors have become increasingly sensitive since the Bureau was 

first able to generate detailed data on them during the 1980 Census. 

However, the Bureau has never used the results of its coverage 

measurements to correct estimated coverage errors.



The Bureau first attempted to measure the accuracy of the census in the 

1940s when it compared the census numbers to birth and death 

certificates and other administrative data using a procedure called 

demographic analysis. Modern coverage measurement began with the 1980 

Census when the Bureau compared census figures to the results of an 

independent sample survey of the population. Using statistical methods, 

the Bureau generated detailed measures of the differences among 

undercounts of particular ethnic, racial, and other groups. In the 

months that followed, many lawsuits were filed, most contending that 

the results of the 1980 coverage measurement should have been used to 

adjust the census. However, the Bureau designed the evaluation to 

measure errors, not to correct the census results, and the Director of 

the Census Bureau decided against adopting the adjusted numbers, as 

they were deemed flawed due to missing and inaccurate data.



The quality of the coverage measurement data improved for the 1990 

Census, and the Bureau recommended statistically adjusting the results. 

However, the Secretary of Commerce determined that the evidence to 

support an adjustment was inconclusive and decided not to adjust the 

1990 Census. The adjustment decision was complicated by the fact that 

the 1990 Census figures had already been released when the coverage 

measurement results became available in the spring of 1991. The 

Secretary of Commerce was concerned that two sets of numbers--the 

actual census results and the adjusted figures--could create confusion 

and might allow political considerations to play a part in choosing 

between sets of numbers when the outcome of the choices, such as 

congressional apportionment, could be known in advance of a decision.



Scope and Methodology:



To determine the objectives of 2000 Census I.C.M./A.C.E. programs and 

their results, we reviewed Bureau and other documents that included 

Federal Register notices; Census Operational Plans; reports to 

Congress; internal memorandums; research and feasibility studies; and 

reports of the Executive Steering Committee for Accuracy and Coverage 

Policy (ESCAP) I and II, which assessed the results of the A.C.E. 

program and recommended how they should be used.



To determine costs for consultants and technical studies for 2000 

Census I.C.M./A.C.E. programs, we focused on object class code 25 from 

the financial management reports to obtain contract data. With Bureau 

assistance, we identified I.C.M./A.C.E. project accounts and analyzed 

amounts by fiscal year using the financial management reports generated 

by the Department of Commerce’s Administrative Management System 

(CAMS). We reviewed and analyzed obligated and expended data for all 

coverage measurement programs that existed during the 2000 Census for 

fiscal years 1991 to 2003. We did not audit financial data provided by 

the Bureau.



To determine ways to track future costs, we reviewed current Bureau 

financial management reports and considered established standards of 

accounting, auditing, and internal controls.



In addition, we met with key Bureau officials to discuss the results of 

our analysis and obtain their observations and perspectives. The 

limitations we encountered in the scope of our work on this assignment 

are as follows.



* We were unable to determine the complete contractual and technical 

studies costs of the I.C.M./A.C.E. programs because the Bureau 

considered any I.C.M./A.C.E.-related costs from fiscal years 1991 

through 1995 as part of its general research and development programs 

and thus did not separately track these costs. Although some costs were 

tracked in fiscal year 1996, the Bureau still considered these costs as 

research and development and did not include these costs as I.C.M./

A.C.E. program costs.



* We were unable to identify I.C.M./A.C.E. portions of costs from 

projects that covered the entire census, such as the 2000 Census 

Evaluation program.



* We did not evaluate the propriety of contracts for I.C.M./A.C.E. 

programs.



Our work was performed in Washington, D.C., and at U.S. Census Bureau 

headquarters in Suitland, Maryland, from June 2002 through October 2002 

in accordance with generally accepted government auditing standards. On 

January 7, 2003, the Secretary of Commerce provided written comments on 

a draft of this report. We address these comments in the “Agency 

Comments and Our Evaluation” section, and have reprinted them in 

appendix I.



Coverage Measurement

Programs for the 2000 Census

Did Not Meet Bureau Objectives:



In planning the 2000 Census, the Bureau developed a new coverage 

measurement program, I.C.M., that was designed to address the major 

shortcomings of the 1990 coverage measurement program. However, as 

shown in table 1, much like similar programs in earlier censuses, the 

Bureau did not use I.C.M. and its successor program, A.C.E., to adjust 

the census because of legal challenges, technical obstacles, and the 

inability to resolve uncertainties in the data in time to meet the 

deadlines for releasing the data.



Table 1: Coverage Measurement Programs Did Not Achieve Objectives:



[See PDF]

[End of Figure]



Source: GAO.



Note: This table reflects GAO’s analysis of U.S. Census Bureau data.



[End of table]



The Bureau Canceled

I.C.M. in Response to a

Supreme Court Ruling:



In designing I.C.M., the Bureau’s goal was to produce a single, 

consolidated count or “one-number” census and thus avoid the 

controversy of having two sets of census results as occurred during the 

1990 Census. Thus, as shown in table 1, the objectives of I.C.M. were 

to (1) measure census coverage, (2) generate, using statistical 

sampling and estimation methods, the detailed data required for 

apportionment, congressional redistricting, and federal program 

purposes, and (3) produce a one-number census.



The Bureau’s plans for I.C.M. emerged in response to the unsatisfactory 

results of the 1990 Census. Although the 1990 headcount was, at that 

time, the most costly in U.S. history, it produced data that were less 

accurate than those from the 1980 Census. The disappointing outcome was 

due in large part to the Bureau’s efforts to count housing units that 

did not mail back their census questionnaires. The operation, known as 

nonresponse follow-up, where enumerators visited and collected 

information from each nonresponding housing unit, proved to be costly 

and error-prone when a higher-than-expected workload and a shortage of 

enumerators caused the operation to fall behind schedule. The final 

stages of nonresponse follow-up were particularly problematic. Indeed, 

while enumerators finished 90 percent of the follow-up workload within 

8 weeks (2 weeks behind schedule), it took another 6 weeks to resolve 

the remaining 10 percent. Moreover, in trying to complete the last 

portion of nonresponse follow-up cases, the Bureau accepted less 

complete responses and information from nonhousehold members such as 

neighbors, which may have reduced the quality of the data.



In the years following the 1990 Census, Congress, the Bureau, several 

organizations, and GAO, concluded that fundamental design changes were 

needed to reduce census costs and improve the quality of the data. In 

response, the Bureau reengineered a number of operations for the 2000 

Census.



For example, to save time and reduce its nonresponse follow-up 

workload, the Bureau planned to enumerate a sample of the last 

remaining portion of nonresponse follow-up cases instead of visiting 

every nonresponding household as it had done in previous censuses. To 

adjust for enumeration errors, the Bureau developed I.C.M., which was 

intended to reconcile the original census figures with data obtained 

from a separate, independent count of a sample of 750,000 housing units 

using a statistical process called Dual System Estimation. The Bureau 

believed that this approach offered the best combination of reduced 

costs, improved accuracy expected at various geographic levels, and 

operational feasibility.



However, concerned about the legality of the Bureau’s planned use of 

sampling and estimation, members of Congress challenged the Bureau’s 

use of I.C.M. in court. In January 1999, the Supreme Court ruled that 

the Census Act[Footnote 4] prohibited the use of statistical sampling 

to generate population data for reapportioning the House of 

Representatives.[Footnote 5]



A.C.E. Did Not Meet Bureau Objectives:



Following the Supreme Court ruling, the Bureau planned to produce 

apportionment numbers using traditional census-taking methods, and 

provide statistically adjusted numbers for nonapportionment uses of the 

data such as congressional redistricting and allocating federal funds. 

The Bureau initiated the A.C.E. program, which was designed to take a 

national sample of approximately 300,000 housing units to evaluate 

coverage errors among different population groups and statistically 

correct for them. Thus, as shown in table 1, the Bureau’s objectives 

for A.C.E. were to (1) measure how many people were missed in the 

census and how many were erroneously included and (2) produce the 

detailed data required in time for redistricting and federal program 

purposes.



However, while the Bureau generally conducted A.C.E. in accordance with 

its plans,[Footnote 6] the Bureau later determined that the A.C.E. 

results did not provide a reliable measure of census accuracy and could 

not be used to adjust the nonapportionment census data.



The first decision against A.C.E. occurred in March 2001, when the 

Acting Director of the Census Bureau recommended to the Secretary of 

Commerce that the unadjusted census data be used for redistricting 

purposes. He cited as a primary reason an apparent inconsistency 

between the population growth over the prior decade, as implied by 

A.C.E. results, and demographic analysis, which estimated the 

population using birth, death, and other administrative records. The 

inconsistency raised the possibility of an unidentified error in either 

the A.C.E. or census numbers. He reported that the inconsistency could 

not be resolved prior to April 1, 2001, the legally mandated deadline 

for releasing redistricting data.[Footnote 7]



The second decision against A.C.E. came in October 2001 when, based on 

a large body of additional research, ESCAP decided against adjusting 

census data for allocating federal aid and other purposes, because 

A.C.E. failed to identify a significant number of people erroneously 

included in the census, and other remaining uncertainties. According to 

Bureau officials, it might be possible to use adjusted data to produce 

intercensal population estimates for federal programs that require this 

information; however, the Bureau would need to revise the A.C.E. 

results before any use of the data could be considered.



The Bureau’s Experience in Implementing

Coverage Measurement Programs 

Highlights Important Lessons Learned:



Although I.C.M. and A.C.E. did not meet their formal objectives, they 

did produce a body of important lessons learned. As the Bureau’s 

current approach for the 2010 Census includes coverage measurement to 

assess the accuracy of the census (but not necessarily to adjust the 

numbers themselves), it will be important for the Bureau to consider 

these lessons as its planning efforts continue. The lessons include (1) 

developing a coverage measurement methodology that is both technically 

and operationally feasible, (2) determining the level of geography at 

which coverage measurement is intended, (3) keeping stakeholders, 

particularly Congress, informed of the Bureau’s plans, and (4) 

adequately testing the eventual coverage measurement program.



1. A.C.E. demonstrated operational, but not technical feasibility. 

According to Bureau officials, an important result of the A.C.E. 

program was that it demonstrated, from an operational perspective only, 

the feasibility of conducting a large independent field check on the 

quality of the census. The Bureau canvassed the entire A.C.E. sample 

area to develop an address list, collected census response data for 

persons living in the sample areas on census day, and conducted an 

operation to try and match A.C.E. respondents to census respondents, 

all independent of the regular census operations and within required 

time frames.



Our separate reviews of two of these operations--interviewing 

respondents and matching A.C.E. and census data--while raising 

questions about the impact on final A.C.E. results due to apparently 

small operational deviations, also concluded that the Bureau 

implemented those two operations largely as planned.[Footnote 8]



Nevertheless, while the Bureau demonstrated that it could execute 

A.C.E. field operations using available resources within required time 

frames, as the Bureau has noted, feasibility also consists of a 

technical component--that is, whether the A.C.E. methodology would 

improve the accuracy of the census. Although the Bureau clearly stated 

in its justification for A.C.E. that the effort would make the census 

more accurate, as noted earlier, because of unresolved data 

discrepancies, its experience in 2000 proved otherwise. Moreover, 

according to the Bureau, because the A.C.E. was designed to correct a 

census with a net coverage error similar to that observed in previous 

censuses, the Bureau commented that applying the methodology to the 

historically low levels of net error observed in the 2000 Census 

represented a unique and unanticipated challenge for A.C.E. Thus, it 

will be important for the Bureau to refine its coverage measurement 

methodology to ensure that it is technically feasible.



2. The level of geography at which the Bureau can successfully measure 

coverage is unclear. Since the October 2001 decision to not rely on 

adjusted census data for nonapportionment and nonredistricting 

purposes, Bureau officials have told us that they now doubt whether 

census data can reliably be improved down to the level of geography for 

which A.C.E. was intended to improve the accuracy--the census tract 

level (neighborhoods that typically contain around 1,700 housing units 

and 4,000 people). The Bureau’s current position differs from that 

taken in 2000, when it reported to Congress that it expected accuracy 

at the tract level to be improved, on average, by A.C.E. statistically 

adjusting numbers at an even lower level of geography--the census block 

level.[Footnote 9] Uncertainty in the level of geography at which 

accuracy is to be measured or improved can affect the overall design of 

coverage measurement, as well as its technical feasibility. Therefore, 

it will be important for the Bureau to determine the level of geography 

at which it intends to measure accuracy as it decides the role and 

design of future coverage measurement programs.



3. Keeping stakeholders informed is essential. Throughout the 1990s, 

Congress and other stakeholders, including GAO, expressed concerns 

about the Bureau’s planned use of sampling and statistical estimation 

procedures to adjust the census. A key cause of this skepticism was the 

Bureau’s failure to provide sufficiently detailed data on the effects 

that I.C.M. would have at different levels of geographic detail. 

Information was also lacking on the various design alternatives being 

considered, their likely implications, and the basis for certain 

decisions. As a result, it was difficult for Congress and other 

stakeholders to support the Bureau’s coverage measurement initiatives.



For example, on September 24, 1996, the House Committee on Government 

Reform and Oversight issued a report that criticized the Bureau’s 

initiatives for sampling and statistical estimation. Among other 

things, the Committee found that the Bureau had not clarified issues of 

accuracy, particularly for small geographic areas, raised by the 

sampling initiative. Congress’s perspective on the process was later 

reflected in its enactment of legislation in 1997 that included 

provisions requiring the Department of Commerce to provide Congress 

with comprehensive information on its planned use of statistical 

estimation within 30 days.[Footnote 10]



4. Adequate testing of coverage measurement methodologies is critical. 

Although the Bureau conducted a dress rehearsal for the census in three 

locations across the country that was intended to demonstrate the 

overall design of the census, the 1998 operation did not reveal the 

problems that the Bureau encountered in dealing with the discrepancies 

between the 2000 A.C.E. results and its benchmarks. According to Bureau 

officials, this was partly because the sites were not representative of 

the nation at large. Additionally, as a result of a compromise between 

Congress and the administration to simultaneously prepare for a 

nonsampling census, the I.C.M. was tested at only two of the three 

dress rehearsal sites--an urban area and an Indian reservation--but was 

not tested in a rural location as was originally planned. An earlier 

test in 1995 was also not comprehensive in that it did not test a 

sampling operation designed to help determine whether nonresponse 

follow-up of the magnitude projected by the Bureau’s current plan could 

be completed in time for the I.C.M to be done on schedule.



I.C.M./A.C.E. Contractor Costs Are Not Complete:



From fiscal year 1996 through fiscal year 2001, the Bureau obligated 

about $207 million for I.C.M./A.C.E. activities.[Footnote 11] As shown 

in table 2, of that 

$207 million, we identified about $22.3 million (11 percent) in 

obligated amounts for contracts involving more than 170 vendors. These 

contracts were primarily for technical advisory and assistant services, 

computer systems support, and training.



Table 2: Census 2000 I.C.M./A.C.E. Contractor Costs for Fiscal Years 

1996 through 2001 (Dollars in thousands):



Project description: A.C.E. coverage management; FY96:  0; FY97: 0 ; 

FY98: 0; FY99: 0; FY00: $1,458; FY01: 0; Total: $1,458.



Project description: A.C.E. operations; FY96: 0; FY97: 0; FY98: 0; 

FY99: 0; FY00: 249; FY01: ($2); Total: 247.



Project description: I.C.M. collection; FY96: 0; FY97: 0; FY98: $201; 

FY99: $41; FY00: 6,272; FY01: 467; Total: 6,981.



Project description: Framework 3 total; FY96: 0 ; FY97: 0; FY98: 201; 

FY99: 41; FY00: 7,979; FY01: 465; Total: 8,686.



Project description: I.C.M. procedures and training; FY96: 0; FY97: 

$249; FY98: 594; FY99: 1,065; FY00: 1,766; FY01: 814; Total: 4,488.



Project description: I.C.M. processing; FY96: 0; FY97: 0; FY98: 0; 

FY99: 2,412; FY00: 287; FY01: 574; Total: 3,273.



Project description: Framework 5 total; FY96: 0; FY97: 249; FY98: 594; 

FY99: 3,477; FY00: 2,053; FY01: 1,388; Total: 7,761.



Project description: I.C.M. dress rehearsal; FY96: 0; FY97: 0; FY98: 

502; FY99: 20; FY00: 0; FY01: (10); Total: 512.



Project description: I.C.M. special test; FY96: $182; FY97: 628; FY98: 

0; FY99: 0; FY00: 0; FY01: 0; Total: 810.



Project description: I.C.M. coverage measurement; FY96: 0; FY97: 409; 

FY98: 1,257; FY99: 1,991; FY00: (130); FY01: 999; Total: 4,526.



Project description: Framework 6 total; FY96: 182; FY97: 1,037; FY98: 

1,759; FY99: 2,011; FY00: (130); FY01: 989; Total: 5,848.



Project description: Total; FY96: $182; FY97: $1,286; FY98: $2,554; 

FY99: $5,529; FY00: $9,902; FY01: $2,842; Total: $22,295.



Source: GAO.



Note: This table reflects GAO’s analysis of U.S. Census Bureau 

financial management reports.



[End of table]



Although the Bureau tracked some costs of contracts for the I.C.M./

A.C.E. programs, we found that the $22.3 million did not represent the 

complete contractor costs of the programs because of the following 

three factors.



* First, the Bureau only tracked the contractor costs associated with 

conducting the I.C.M./A.C.E. programs, which covers the period from 

fiscal year 1997 through 2003. Although life cycle costs for the 2000 

Census cover a 13-year period from fiscal years 1991 through 2003, 

senior Bureau officials said that the I.C.M./A.C.E. program was not 

viable for implementation until fiscal year 1997. Therefore, the Bureau 

considered contractor costs from earlier years as part of its general 

research and development programs, and the Bureau did not assign unique 

project codes to identify I.C.M./A.C.E. programs and related costs in 

its financial management system.



* Second, although $182,000 of fiscal year 1996 obligated contractor 

costs were identifiable in the Bureau’s financial management system as 

an I.C.M. special test, the Bureau did not consider these costs as part 

of the I.C.M./A.C.E. programs. Instead, these costs were considered 

general research and development. However, because the Bureau 

separately identified these costs as I.C.M. program contractor costs, 

we have included the $182,000 as part of the I.C.M./A.C.E. program 

contractor costs in this report.



* Finally, we were unable to identify the I.C.M./A.C.E. portions of 

costs that were part of other programs. For example, in late fiscal 

year 2000 and after, the Bureau did not separate A.C.E. evaluations 

from its other 2000 Census evaluations in its financial management 

systems. Bureau officials stated that the contracts for evaluations 

included overall 2000 Census and A.C.E. evaluations, and did not have a 

separate code identifying A.C.E. costs.



Tracking Future Coverage Measurement Costs:



During the 2000 Census, the Bureau, its auditors, and GAO, found 

extensive weaknesses in the Bureau’s financial management system, the 

components of which include hardware, software, and associated 

personnel. The weaknesses included difficulties in providing reliable 

and timely financial information to manage current government 

operations and preparing financial statements and other reports. 

Together, they affected the completeness, accuracy, and timeliness of 

data needed for informed management decisions and effective oversight. 

In light of these weaknesses, the Bureau’s ability to track future 

costs of coverage measurement activities will largely depend on three 

factors.



* First, a sound financial management system is critical. As discussed 

in our December 2001 report, the Bureau’s core financial management 

system, CAMS, had persistent internal control weaknesses in fiscal year 

2000.[Footnote 12] In its latest financial report, the Bureau indicated 

that these weaknesses have continued through fiscal year 2001.[Footnote 

13] The Bureau expects to issue its fiscal year 2002 financial report 

shortly.



* Second, it would be important to set up project codes to capture 

coverage measurement activities as early in the planning process as 

possible. The Bureau did not set up a specific project code to identify 

I.C.M. program costs until 1996 because, according to Bureau officials, 

the I.C.M. program was not viable until 1997 and all costs up to this 

point were considered general research.



* Finally, it would be important for Bureau personnel to correctly 

charge the project codes established for the coverage measurement 

program activities. During the 2000 Census, for example, while the 

Bureau established a project code and a budget for the remote Alaska 

enumeration, the project costs were erroneously charged to and 

commingled with a project code for enumerating special populations. As 

a result, the actual costs for remote Alaska enumeration were reported 

by the Bureau’s financial management system as zero and are unknown, 

while enumerating special population costs are overstated.



Conclusions:



The Bureau’s 2000 Census coverage measurement programs did not achieve 

their primary objectives of measuring the accuracy of the census and 

adjusting the results because of legal challenges, technical hurdles, 

and questionable data. However, beyond these formal objectives, there 

emerged several important lessons learned that Bureau managers should 

consider because current plans for the 2010 Census include coverage 

measurement. At the same time, it will also be important for the Bureau 

to be capable of fully tracking the money it spends on coverage 

measurement and other census activities so that Congress and other 

stakeholders can hold the Bureau accountable for achieving intended 

results.



Although the Bureau has never used the results of its coverage 

measurement programs to adjust census numbers, we believe that an 

evaluation of the accuracy and completeness of the census is critical 

given the many uses of census data, the importance of identifying the 

magnitude and characteristics of any under-and overcounts, and the cost 

of the census overall. Less clear is whether the results of the 

coverage measurement should be used to adjust the census. Any Bureau 

decisions on this matter should involve close consultation with 

Congress and other stakeholders, and be based on detailed data and a 

convincing demonstration of the feasibility of the Bureau’s proposed 

approach. Whatever the decision, it is imperative that it be made soon 

so that the Bureau can design appropriate procedures and concentrate on 

the business of counting the nation’s population. The longer the 2010 

planning process proceeds without a firm decision on the role of 

coverage measurement, the greater the risk of wasted resources and 

disappointing results.



Recommendations for Executive Action:



To help ensure that any future coverage measurement efforts achieve 

their intended objectives and costs can be properly tracked, we 

recommend that the Secretary of Commerce direct the Bureau to:



* in conjunction with Congress and other stakeholders, come to a 

decision soon on whether and how coverage measurement will be used in 

the 2010 Census;



* consider incorporating lessons learned from its coverage measurement 

experience during the 2000 Census, such as (1) demonstrating both the 

operational and technical feasibility of its coverage measurement 

methods, (2) determining the level of geography at which coverage can 

be reliably measured, (3) keeping Congress and other stakeholders 

informed of its plans, and (4) adequately testing coverage measurement 

prior to full implementation; and:



* ensure that the Bureau’s financial management systems can capture and 

report program activities early in the decennial process and ensure 

that project costs are monitored for accuracy and completeness.



Agency Comments and Our Evaluation:



The Secretary of Commerce forwarded written comments from the Census 

Bureau on a draft of this report, which are reprinted in appendix I. 

The Bureau agreed with our recommendations highlighting the steps that 

should be followed in the development of a coverage measurement 

methodology for the 2010 Census and acknowledged their importance. 

However, the Bureau maintained that it followed most of these steps for 

the 2000 Census including (1) keeping stakeholders, particularly 

Congress, informed of the Bureau’s plans, (2) determining the level of 

geography at which coverage measurement is intended, and (3) adequately 

testing coverage measurement methodologies. The Bureau also maintained 

that throughout the 1990s, it had an open and transparent process for 

implementing the coverage measurement program, including the levels of 

geography to which its results would be applied.



We disagree. As we stated in our report, the Bureau’s failure to 

provide important information was a key cause of congressional 

skepticism over the Bureau’s coverage measurement plans. In fact, 

Congress was so concerned about the lack of comprehensive information 

on the Bureau’s proposed approach that in July 1997, it passed a law 

that included provisions requiring the Department of Commerce to 

provide detailed data on the Bureau’s planned use of statistical 

estimation within 30 days.[Footnote 14] We revised the report to 

include this, and provide other examples to further support our 

position that the Bureau’s I.C.M. and A.C.E. planning and development 

processes were less than fully open and transparent.



The Bureau also commented that each major component of the I.C.M./

A.C.E. program underwent “rigorous” testing in the middle of the decade 

as well as during the dress rehearsal for the 2000 Census held in 1998. 

We believe this overstates what actually occurred. As we noted in the 

report, the dress rehearsal failed to detect the problems that A.C.E. 

encountered during the 2000 Census because the sites were not 

representative of the nation. Additionally, because of an agreement 

between Congress and the administration to simultaneously prepare for a 

census that did not include sampling, the I.C.M. was only tested at two 

of the three dress rehearsal sites--an urban area and an Indian 

reservation--but was not tested in a rural location as was originally 

planned. We made this and other revisions to strengthen our point.



Because the A.C.E. was designed to correct a census with a net coverage 

error similar to that observed in previous censuses, the Bureau 

commented that applying the methodology to the historically low levels 

of net error observed in the 2000 Census represented a unique and 

unexpected challenge for A.C.E. We revised the report to reflect this 

additional context.



The Bureau took exception to the way we presented our conclusions 

concerning its ability to properly classify certain costs associated 

with the development of the Bureau’s coverage measurement programs. The 

Bureau noted that it decided not to separately track coverage 

measurement development costs in 1994, because there was no internal or 

external request for a separate cost accounting of the program.



Our report does not make interpretive conclusions or qualitative 

judgments about which coverage measurement program costs the Bureau 

decided to track. Instead, the report (1) points out that we could not 

identify all of the contractor costs associated with the I.C.M./A.C.E. 

programs because of the three factors described in the report, and (2) 

underscores the importance of a sound financial management system for 

tracking, planning, and development costs for the 2010 Census.



We are sending copies of this report to other interested congressional 

committees, the Secretary of Commerce, and the Director of the U.S. 

Census Bureau. Copies will be made available to others upon request. 

This report will also be available at no charge on GAO’s home page at 

http://www.gao.gov.



Please contact Patricia A. Dalton on (202) 512-6806 or by E-mail at 

daltonp@gao.gov if you have any questions. Other key contributors to 

this report were Robert Goldenkoff, Roger Stoltz, Carolyn Samuels, 

Cindy Brown-Barnes, Ty Mitchell, and Linda Brigham.



Sincerely yours,



Patricia A. Dalton

Director, Strategic Issues:

Signed by Patricia A. Dalton:



McCoy Williams

Director

Financial Management and Assurance:

Signed by McCoy Williams:



[End of section]



Appendixes:



Appendix I: Comments from the Department of Commerce:



THE SECRETARY OF COMMERCE Washington D.C. 20230:



JAN 7 2003:



Ms. Patricia A Dalton Director:



Strategic Issues:



United States General Accounting Office Washington, DC 20548:



Dear Ms. Dalton:



The Department of Commerce appreciates the opportunity to comment on 

the General Accounting Office (GAO) draft document entitled 2000 

Census: Coverage Measurement Programs’ Results, Costs and Lessons 

Learned (GAO-03-287)_ The Department’s comments on this report are 

enclosed.



Sincerely,

Donald L. Evans:

Signed by Donald L. Evans:



Enclosure:



Comments from the U.S. Department of Commerce U.S. Census Bureau:



U.S. General Accounting Office draft report entitled 2000 Census: 

Coverage Measurement Programs’ Results, Costs, and Lessons Learned:



Comments on the Teat of the Report:



In its analysis of the coverage measurement program implemented by the 

U.S. Census Bureau during Census 2000, the General Accounting Office 

{GAO) reaches conclusions that undcrscore the importance of finalizing 

the census design early in the decade, continuing to refine coverage 

measurement methodology based on lessons learned from Census 2000, and 

thoroughly testing coverage measurement operations prior to 

implementing them in 2010. We take exception with the way in which 

these conclusions are presented Moreover, the GAO asserts that the 

Census Bureau did not maintain a financial accounting system that could 

properly classify certain costs attributable to the development of the 

integrated Coverage Measurement (ICM)/Accuracy and Coverage Evaluation 

(A.C.E.) programs. We fundamentally disagree with this assertion, as we 

stressed in our response to the GAO’s earlier discussion of this issue 

(see GAO-03-41).



The GAO states that the Census Bureau did not adequately account for 

the costs of the ICM/A.C.E. program. This conclusion was correct only 

at the beginning of the Census 2000 cycle. At the beginning of each 

census, we identify the specific activities for which we think costs 

should be separately tracked. The decision not to separately track 

coverage measurement development costs was made in 1994, when there was 

no internal or extetnal request for a separate cost accounting of this 

program. The GAO’s suggestion after Census 2000 that we should have 

separately tracked coverage measurement activities early in the census 

cycle is far different from the implication that we had no system in 

place for tracking those costs. The Census Bureau plans to track 

coverage measurement expenditures earlier in the 2010 census cycle and, 

in fact, will be happy to begin tracking costs in whatever additional 

categories the GAO identifies.



(2) The GAO also identifies a series of “lessons learned” from Census 

2000 that include the following:



“keeping stakeholders, particularly Congress, informed of the Bureau’s 

plans” “determining the level of geography at which coverage 

measurement is intended” “adequately testing coverage measurement 

methodologies’*:



It is worth underscoring that each of these steps was taken during 

Census 2000. Throughout the census, and in the years leading up to it, 

the Census Bureau was unwavering in its maintenance of an open and 

transparent process for implementing the coverage measurement program, 

including the levels of geography to which its remits:



See the one-page overview ar the beginning of the report and the 

“Results in Brief” section of the text.



would be applied, in the face of unprecedented scrutiny from census 

stakeholders. Moreover, each major component of the ICM/A.C.E. program 

underwent rigorous testing in the middle of the decade and in the dress 

rehearsal conducted in 1998.



Finally, while shortcomings in the data from the A.C.E. prevented their 

use for improving the counts from Census 2000, as originally intended, 

the A.C.E. itself was designed to correct a census with a net coverage 

error based on the level of error observed in previous decennial 

censuses. Applying the dual system estimation methodology central to 

the A.C.E. to improve upon a level of net coverage error at the 

historically low levels observed in Census 2000 represented a unique 

and unexpected challenge for this program. This new circumstance will 

be taken into consideration as coverage measurement methodologies are 

developed for the 2010 census.



In short, the GAO has identified important steps that should be 

followed in the development of a coverage measurement methodology for 

the 2010 census. It is important to stress, however, that most of these 

steps were followed in Census 2000, as well.



[End of Section]



Related GAO Products:



2000 Census: Complete Costs of Coverage Evaluation Programs Are Not 

Available. GAO-03-41. Washington, D.C.: October 31, 2002.



2000 Census: Lessons Learned for Planning a More Cost-Effective 2010 

Census. GAO-03-40. Washington, D.C.: October 31, 2002.



2000 Census: Refinements to Full Count Review Program Could Improve 

Future Data Quality. GAO-02-562. Washington, D.C.: July 3, 2002.



2000 Census: Coverage Evaluation Matching Implemented as Planned, but 

Census Bureau Should Evaluate Lessons Learned. GAO-02-297. Washington, 

D.C.: March 14, 2002.



2000 Census: Best Practices and Lessons Learned for More Cost-Effective 

Nonresponse Follow-up. GAO-02-196. Washington, D.C.: February 11, 2002.



2000 Census: Coverage Evaluation Interviewing Overcame Challenges, but 

Further Research Needed. GAO-02-26. Washington, D.C.: 

December 31, 2001.



2000 Census: Analysis of Fiscal Year 2000 Budget and Internal Control 

Weaknesses at the U.S. Census Bureau. GAO-02-30. Washington, D.C.: 

December 28, 2001.



2000 Census: Significant Increase in Cost Per Housing Unit Compared to 

1990 Census. GAO-02-31. Washington, D.C.: December 11, 2001.



2000 Census: Better Productivity Data Needed for Future Planning and 

Budgeting. GAO-02-4. Washington, D.C.: October 4, 2001.



2000 Census: Review of Partnership Program Highlights Best Practices 

for Future Operations. GAO-01-579. Washington, D.C.: August 20, 2001.



Decennial Censuses: Historical Data on Enumerator Productivity Are 

Limited. GAO-01-208R. Washington, D.C.: January 5, 2001.



2000 Census: Information on Short-and Long-Form Response Rates. GAO/

GGD-00-127R. Washington, D.C.: June 7, 2000.



FOOTNOTES



[1] At the time of our report, obligated costs after fiscal year 2001 

were not final.



[2] U.S. General Accounting Office, 2000 Census: Complete Costs of 

Coverage Evaluation Programs Are Not Available, GAO-03-41 (Washington, 

D.C.: Oct. 31, 2002).



[3] Department of Commerce v. United States House of Representatives, 

525 U.S. 316 (1999).



[4] 13 U.S.C. 195.



[5] Department of Commerce v. United States House of Representatives 

525, U.S. 316 (1999).



[6] See, for example, U.S. General Accounting Office, 2000 Census: 

Coverage Evaluation Interviewing Overcame Challenges, but Further 

Research Needed, GAO-02-26 (Washington, D.C.: Dec. 31, 2001), and 2000 

Census: Coverage Evaluation Matching Implemented as Planned, but Census 

Bureau Should Evaluate Lessons Learned, GAO-02-297 (Washington, D.C.: 

Mar. 14, 2002).



[7] March 1, 2001, Memorandum to Secretary Donald Evans from Acting 

Director William Barron, Jr. (ESCAP I decision memo.)



[8] See GAO-02-26 and GAO-02-297.



[9] U.S. Census Bureau, “Report to Congress--The Plan for Census 2000,” 

44-46 and Accuracy and Coverage Evaluation--Statement on the 

Feasibility of Using Statistical Methods to Improve the Accuracy of the 

Census 2000 (June 2000), 19, fn. 19.



[10] Pub. L. 105-18, Title VIII, June 12, 1997.



[11] At the time of our report, obligated costs after fiscal year 2001 

were not final.



[12] U.S. General Accounting Office, 2000 Census: Analysis of Fiscal 

Year 2000 Budget and Internal Control Weaknesses at the U.S. Census 

Bureau, GAO-02-30 (Washington, D.C.: Dec. 28, 2001).



[13] U.S. Census Bureau, 2001 Financial Report (Suitland, Md.: May 

2002).



[14] Pub. L. 105-18, Title VIII, June 12, 1997.



GAO’s Mission:



The General Accounting Office, the investigative arm of Congress, 

exists to support Congress in meeting its constitutional 

responsibilities and to help improve the performance and accountability 

of the federal government for the American people. GAO examines the use 

of public funds; evaluates federal programs and policies; and provides 

analyses, recommendations, and other assistance to help Congress make 

informed oversight, policy, and funding decisions. GAO’s commitment to 

good government is reflected in its core values of accountability, 

integrity, and reliability.



Obtaining Copies of GAO Reports and Testimony:



The fastest and easiest way to obtain copies of GAO documents at no 

cost is through the Internet. GAO’s Web site ( www.gao.gov ) contains 

abstracts and full-text files of current reports and testimony and an 

expanding archive of older products. The Web site features a search 

engine to help you locate documents using key words and phrases. You 

can print these documents in their entirety, including charts and other 

graphics.



Each day, GAO issues a list of newly released reports, testimony, and 

correspondence. GAO posts this list, known as “Today’s Reports,” on its 

Web site daily. The list contains links to the full-text document 

files. To have GAO e-mail this list to you every afternoon, go to 

www.gao.gov and select “Subscribe to daily E-mail alert for newly 

released products” under the GAO Reports heading.



Order by Mail or Phone:



The first copy of each printed report is free. Additional copies are $2 

each. A check or money order should be made out to the Superintendent 

of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 

more copies mailed to a single address are discounted 25 percent. 

Orders should be sent to:



U.S. General Accounting Office



441 G Street NW,



Room LM Washington,



D.C. 20548:



To order by Phone: 	



	Voice: (202) 512-6000:



	TDD: (202) 512-2537:



	Fax: (202) 512-6061:



To Report Fraud, Waste, and Abuse in Federal Programs:



Contact:



Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov



Automated answering system: (800) 424-5454 or (202) 512-7470:



Public Affairs:



Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.



General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.



20548: