This is the accessible text file for GAO report number GAO-02-201 
entitled 'Defense Acquisitions: Steps to Improve the Crusader 
Program's Investment Decisions' which was released on February 25, 
2002. 

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the 
printed version. The portable document format (PDF) file is an exact 
electronic replica of the printed version. We welcome your feedback. 
Please E-mail your comments regarding the contents or accessibility 
features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States General Accounting Office: 
GAO: 

Report to Congressional Committees: 

February 2002:  

Defense Acquisitions: 

Steps to Improve the Crusader Program's Investment Decisions: 

GAO-02-201: 

Letter: 

Results in Brief: 

Background: 

Critical Technologies Need Additional Maturity to Better Assure Low-
risk Product Development: 

Lighter-weight Crusader May Not Significantly Improve Strategic 
Deployability: 

Apparent Overlap of Crusader and Future Combat Systems Programs 
Creates Uncertainties: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Scope and Methodology: 

Appendixes: 

Appendix I: Technology Readiness Levels and Their Descriptions: 

Appendix II: Comments from the Department of Defense: 

Appendix III: GAO Contacts and Staff Acknowledgments: 

Table: 

Table 1: Results of the Joint Crusader TRL Assessment: 

Figures: 

Figure 1: Crusader Howitzer: 

Figure 2: Crusader Tracked Resupply Vehicle: 

Figure 3: Crusader Wheeled Resupply Vehicle: 

[End of section] 

United States General Accounting Office: 
Washington, D.C. 20548: 

February 25, 2002: 

Congressional Committees: 

To address future threats, the Army has identified a requirement for 
an artillery system that has greater firepower, range, and mobility 
than its current self-propelled howitzer—-the Paladin. Operation 
Desert Storm demonstrated that current howitzers were unable to keep 
up with our tanks and fighting vehicles. In 1994, the Army began to 
develop the Crusader, an advanced artillery system consisting of a 
self-propelled 155-millimeter howitzer and a resupply vehicle. The 
Army's total acquisition cost in the Crusader program is projected to 
be about $11 billion. In 2000, the Army changed its requirements and 
restructured the Crusader program to make the system lighter and more 
deployable. This change was in response to the Army's planned 
transformation to a future force, which will also be lighter and more 
deployable. The Army expects to use the Crusader until it is 
eventually replaced by the main component of the future force, known 
as the Future Combat Systems. 

In April 2003, Department of Defense (DOD) will decide whether the
Crusader program should enter its system development and 
demonstration—-or product development—-stage, which will require the 
commitment of major resources to develop and design the Crusader 
system and to demonstrate its integration, interoperability, and 
utility. The opportunity to take actions that can put the program in a 
better position to succeed and, thus, minimize future cost and 
schedule increases is now, before the start of product development. As 
the Army approaches that decision point, we examined three major 
aspects of the program: (1) the progress in developing Crusader's 
technology and software, (2) the Crusader's requirement for improved 
deployability, and (3) the Army's timetables for developing the 
Crusader and the Future Combat Systems. 

Results in Brief:  

The Crusader program has made considerable progress in developing key
technologies and reducing its size and weight. However, with a 2003 
decision date for committing to product development, more progress and 
knowledge will be needed to minimize risks of cost overruns, schedule 
delays, and performance shortfalls. 

* Based on current Army plans, the Crusader program will likely enter 
product development with the majority of its critical technologies 
less mature than best practices recommend. Most of the Crusader's 
critical technologies have been demonstrated in a relevant environment 
but not the more demanding operational environment. Achieving the 
higher level of technology maturity prior to beginning product 
development reduces the risk of costly schedule delays. Crusader 
technologies that have not reached the desired level of maturity for 
product development include the suspension, track, transmission, and 
prognostics.[Footnote 1] The Army made significant improvements to the 
management of the Crusader's software development process in response 
to software design problems experienced in 1998. The Army's continued 
attention to software development is essential given the large amount 
that remains to be completed. 

* Although the Army is redesigning the Crusader to reduce individual 
vehicle weight from about 60 tons to about 40 tons so that two 
vehicles can be deployed on a C-17 aircraft, the deployability 
advantage gained does not appear significant. An Army analysis 
conducted at our request shows that the reduction in the Crusader 
system's weight would only decrease the number of C-17 flights needed 
to transport two complete systems and support equipment from five 
flights to four flights. Moreover, the Army plans to move Crusaders by 
aircraft only under extraordinary conditions and in limited numbers. 
Also, as currently designed, the weight of two howitzers is projected 
to be very close to the C-17's weight limit and their projected size 
would make them a very tight fit in the aircraft, if they fit at all. 
The Army may need to make cost, schedule, and performance trade-offs 
to meet and maintain that weight. While, in general, a lighter system 
offers a number of other benefits, knowing the magnitude of the 
deployability advantage gained by reducing weight would enable the 
Army to make better trade-off decisions. 

* An apparent overlap exists between the Crusader's and the Future
Combat Systems' capabilities and schedules. The Army expects the
Future Combat Systems to eventually meet the same artillery missions 
as the Crusader and eventually replace it. The current schedules for 
initial fielding of the Future Combat Systems and the Crusader system 
occur in the same year, 2008. The extent of this apparent overlap 
depends more on the Future Combat Systems than the Crusader, because 
less is known about the Future Combat Systems' technologies. More will 
be understood about these technologies and, thus, the Future Combat 
Systems' schedule, when the Army formally assesses their maturity in 
early 2003. Current plans call for committing to the Crusader's 
product development in the same year the Future Combat Systems' 
technologies are assessed. 

We are recommending that the Army further mature the Crusader's 
technologies before committing to product development; assess the 
benefits of its weight reduction relative to its strategic 
deployability; and assess the projected capabilities and fielding 
schedules for Future Combat Systems as part of the Crusader's 
milestone decision for beginning product development. 

In commenting on our report, DOD did not agree with our recommendation 
on maturing critical Crusader technologies and partially agreed with 
our recommendations on Crusader's deployability requirement and the
Crusader's apparent overlap with the Future Combat Systems. In not 
agreeing, DOD noted that the Crusader program is using modeling and 
simulation to determine the Crusader's readiness to enter product 
development and stated that changing its acquisition strategy to 
further mature critical technologies would add significantly to the 
development time and expense without significantly reducing risk or 
improving performance. We agree that modeling and simulation are 
useful management tools, but believe that demonstrating critical 
technologies in an operational environment before the start of product 
development has been shown to lower program risks of significant cost 
overruns, schedule delays, and performance shortfalls. In partially 
agreeing with our recommendation to conduct an analysis of the 
Crusader's deployability requirement, DOD said that the current 
requirement is not considered a key performance parameter and, as a 
result, the Army is allowed to make tradeoffs between the requirement 
and system cost and performance. DOD further stated that the Army 
plans to review the Crusader's requirements prior to the 2003 
milestone B decision as required by regulations. We believe that an 
analysis to determine the importance of deploying two Crusader 
howitzers on a C-17 aircraft should be conducted as soon as possible 
to provide the Army greater flexibility and knowledge in considering 
its ongoing trade-off decisions needed to meet weight requirements. In 
partially agreeing with our recommendation to determine the potential 
capabilities and schedule of the initial version of the Future
Combat Systems before making the decision to begin Crusader product 
development, DOD said that the Crusader's capabilities are intended to 
complement rather than be redundant to the capabilities of the Future 
Combat Systems. We continue to believe that DOD cannot determine 
whether the two systems will be complementary or redundant without 
knowledge of the initial Future Combat Systems capabilities and 
fielding schedule. DOD does not yet have this knowledge. We also 
continue to believe that this knowledge needs to be considered as part 
of the decision to allow the Crusader program to enter product 
development. 

Background:  

The Army plans to invest about $11 billion developing and procuring 
the Crusader, an automated, next generation field artillery system. To 
date, the program has spent about $1.7 billion in development costs. 
It plans to procure 482 Crusader systems—each system consisting of a 
self-propelled 155-millimeter howitzer and a resupply vehicle. The 
Army is developing 2 different resupply vehicles-1 with tracks and 1 
with wheels—and plans to procure 241 of each type. The purpose of the 
Crusader system is to overcome threats from enemy artillery and 
reconnaissance or surveillance systems as well as have the mobility 
needed to keep up with Army tanks and fighting vehicles. Figure 1 
shows the planned Crusader howitzer, figure 2 the planned tracked 
resupply vehicle, and figure 3 the planned wheeled resupply vehicle. 

Figure 1: Crusader Howitzer: 

[Refer to PDF for image: photograph] 

Source: United Defense Limited Partnership. 

[End of figure] 

Figure 2: Crusader Tracked Resupply Vehicle: 

[Refer to PDF for image: photograph] 

Source: United Defense Limited Partnership. 

[End of figure] 

Figure 3: Crusader Wheeled Resupply Vehicle: 

[Refer to PDF for image: photograph] 

Source: United Defense Limited Partnership. 

[End of figure] 

The Army restructured the Crusader program in January 2000 to align
Crusader's design with the Army's transformation to a lighter force. The
Army's transformation will affect all aspects of Army organization, 
training, doctrine, leadership, and strategic plans as well as the 
types of equipment and technology the Army acquires. The Army expects 
the transformation to be at least a 30-year process and has not 
estimated its full cost. The centerpiece of the lighter, more 
deployable future force is the Future Combat Systems. The Future 
Combat Systems concept is a system of ground and air, manned and 
unmanned weapon systems, each under 20 tons that is planned to replace 
most, if not all, of the Army's ground combat systems without a loss 
in lethality and survivability. Artillery systems are among those to 
be replaced. 

The Army expects the Crusader system to fill the existing gap in 
artillery capabilities until it is replaced by the Future Combat 
Systems. In keeping with the transformation philosophy of lightweight 
vehicles and ease of deployability, the Army is redesigning Crusader 
to make it lighter and more deployable, with the goal of reducing the 
weight of the self-propelled howitzer and tracked resupply vehicle 
from about 60 tons to about 40 tons each. Program officials said that 
a lighter system would enhance operational flexibility in employing 
Crusader in support of any operation. 

The Crusader is currently in the program definition and risk reduction 
phase of its development program. In April 2003, the program is 
scheduled for a milestone B review to determine whether it is ready to 
enter its system development and demonstration phase. Milestone B is 
the point at which DOD decides whether to commit major resources to 
develop and design the system and to demonstrate its integration, 
interoperability, and utility. The milestone marks the start of the 
program's product development. The Army plans to deliver the first 
full Crusader prototype system in October 2004, followed by a low-rate 
initial production decision in February 2006, and initial system 
fielding in April 2008. 

Critical Technologies Need Additional Maturity to Better Assure Low-
risk Product Development:  

Based on current Army plans, the Army will begin the Crusader's 
product development in April 2003 but before maturing critical 
Crusader technologies to a level considered low risk relative to best 
practices. These risks relate less to whether these technologies can 
be matured, but more to how much time and cost it will take to mature 
them. If, after starting product development, the Crusader 
technologies do not mature on schedule and instead cause delays, the 
Army may spend more and take longer to develop, produce, and field the 
Crusader system. Crusader performance goals may also be at risk. On 
the other hand, the Army has made improvements to the management of 
the Crusader software development process. 

Assessing Technology Readiness Provides Opportunities to Improve 
Outcomes: 

The maturity of a program's technologies at the start of product 
development is a good predictor of that program's future performance. 
Our past reviews of programs incorporating technologies into new 
products and weapon systems showed that they were more likely to meet 
product objectives when the technologies were matured before product 
development started. For example, the Ford Motor Company's practice of 
demonstrating new technologies in driving conditions before they are 
included in a new product is essential to ensuring that the new 
product can be developed on time and within budget. Similarly, we have 
found that the early demonstration of propulsion and water-planing 
technologies, essential to the performance of the Marine Corps' 
Advance Amphibious Assault Vehicle, has been instrumental to that 
program's staying within 15 percent of cost and schedule estimates. 

Conversely, cost, schedule, and performance problems were more likely to
occur when programs started with technologies at lower readiness 
levels.[Footnote 2] For example, the enabling technologies for the 
Army's Brilliant Anti-Armor Submunition program were very immature at 
the start of the program, and their delays became major contributors 
to the program's subsequent 88-percent cost growth and 62-percent 
schedule slippage. Separating technology development from product 
development into two distinct program phases is a best practice of 
both successful commercial and defense programs. This entails 
demonstrating all critical technologies at the component or subsystem 
level in an operational environment during technology development, 
prior to committing major funding to product development. Under this 
practice, the critical technologies would be demonstrated in component 
or subsystem prototypes that are nearly the right size, weight, and 
configuration needed for the intended product. Such demonstrations 
need not require a full system prototype of a Crusader vehicle, but 
can be done using surrogate vehicles. 

Technology readiness levels (TRL) are a good way to gauge the maturity 
of technologies. TRLs were pioneered by the National Aeronautics and 
Space Administration to determine the readiness of technologies to be 
incorporated into products such as weapon systems. Readiness levels 
are measured along a scale of one to nine, starting with paper studies 
of the basic concept, proceeding with laboratory demonstrations, and 
ending with a technology that has proven itself on the intended 
product. TRLs are based on actual demonstrations of how well specific 
technologies perform in the intended application. For example, a 
technology that has been demonstrated in an operational environment 
using subsystem prototype hardware (such as a complete cannon system) 
that is at or near the final system design would be rated as a TRL 7. 
The individual TRL descriptions can be found in appendix I. 

DOD has agreed that technology readiness assessments are important and 
necessary in assisting officials who decide when and where to insert 
new technologies into weapon system programs. In January 2001, DOD 
issued a new acquisition instruction that redefined the phases in the 
defense acquisition cycle and emphasized the role of technology 
development in the acquisition process.[Footnote 3] Under the 
instruction, programs use the concept and technology development 
phase, which precedes the system development and demonstration phase, 
for developing components and subsystems that must be demonstrated 
before integration into the system. The first portion of system 
development and demonstration phase is dedicated to integrating the 
components and subsystems into the system. The instruction states that 
DOD prefers that technology be demonstrated in an operational 
environment but must be demonstrated in a relevant environment to be 
considered mature enough for product development in the system 
development and demonstration phase. According to the TRL 
descriptions, technology demonstrated in an operational environment is
TRL 7 and technology demonstrated in a relevant environment is TRL 6. 

Maturing technology from a TRL 6 to a TRL 7 represents a major step up 
in maturity. A technology at the TRL 6 maturity level needs only to be 
demonstrated as a subsystem prototype or model in a laboratory or 
simulated operational environment. A technology at the TRL 7 maturity 
level must be demonstrated as a subsystem prototype at or near the 
size of the required subsystem outside the laboratory in an actual 
operational environment. For example, operating a prototype engine on 
a laboratory test stand that simulates the effects of the vehicle's 
weight on the engine would be a TRL 6 level demonstration while 
operating an engine in a surrogate vehicle or actual prototype that 
weighed 50 tons, on roads and cross country, would be a TRL 7 
demonstration. 

In June 2001, DOD issued a new acquisition regulation.[Footnote 4] It 
stated that technology maturity is a principal element of program risk 
and directed technology readiness assessments for critical 
technologies sufficiently prior to selected milestone decision points-—
including milestone B--to provide useful technology maturity 
information to the acquisition review process. Although the new 
regulation recognizes that TRLs enable consistent, uniform discussions 
of technical maturity across different types of technologies and 
provides the definitions of TRLs used in this report, it permits the 
use of TRLs or "some equivalent assessment" when performing a 
technology readiness assessment. 

Technology Maturation Will Continue into Product Development: 

In June 2001, Crusader program office engineers and we assessed the 
maturity of 16 critical Crusader technologies using TRLs.[Footnotes 5, 
6] This joint assessment determined that 10 of the 16 critical 
Crusader technologies were below TRL 7. Since the Crusader program is 
not scheduled to commit to product development until April 2003, the 
Army still has time to mature the 10 critical technologies to a TRL 7 
level—-demonstrate them in a component or subsystem prototype in an 
operational environment. However, the Army's Crusader plans will 
result in 10 of the critical Crusader technologies remaining below TRL 
7 at the milestone B decision and in technology development continuing 
into the product development phase. As a result, the Crusader program 
would not reach the low levels of risk that best practices show is 
needed for meeting product development cost and schedule commitments. 
Table 1 shows the results of our joint technology readiness assessment. 

Table 1: Results of the Joint Crusader TRL Assessment[A]: 

Key system element: System management; 
Critical Crusader Technology: 1. Digitization (real time situational 
awareness); 
Assessment: June 2001: 5; 
Assessment: April 2003: 6. 

Critical Crusader Technology: 2. System prognostics; 
Assessment: June 2001: 5; 
Assessment: April 2003: 5. 

Critical Crusader Technology: 3. System diagnostics (including fault 
detection); 
Assessment: June 2001: 5; 
Assessment: April 2003: 6. 

Key system element: Armament; 
 
Critical Crusader Technology: 4. Cannon subsystem (including the tube, 
cooling system, laser ignition, Modular Artillery Charge System);
Assessment: June 2001: 7; 
Assessment: April 2003: 7. 
 
Critical Crusader Technology: 5. Inductive fuzing; 
Assessment: June 2001: 6; 
Assessment: April 2003: 6. 

Critical Crusader Technology: 6. Automated loading; 
Assessment: June 2001: 7; 
Assessment: April 2003: 7. 

Critical Crusader Technology: 7. Projectile tracking system ;
Assessment: June 2001: 7; 
Assessment: April 2003: 7. 

Key system element: Resupply and ammunition handling; 

Critical Crusader Technology: 8. Automated inventory management 
(includes recognition); 
Assessment: June 2001: 6; 
Assessment: April 2003: 6. 

Critical Crusader Technology: 9. Vehicle docking and transfer of 
projectiles, propellant, fuel and data; 
Assessment: June 2001: 6; 
Assessment: April 2003: 6. 
 
Key system element: Mobility; 

Critical Crusader Technology: 10. Common engine (with the Abrams tank 
program); 
Assessment: June 2001: 7; 
Assessment: April 2003: 7. 

Critical Crusader Technology: 11. Transmission; 
Assessment: June 2001: 5; 
Assessment: April 2003: 6. 

Critical Crusader Technology: 12. Next generation suspension; 
Assessment: June 2001: 7; 
Assessment: April 2003: 7. 

Critical Crusader Technology: 13. Track; 
Assessment: June 2001: 5; 
Assessment: April 2003: 5. 

Critical Crusader Technology: 14. Drive by wire; 
Assessment: June 2001: 6; 
Assessment: April 2003: 6. 

Key system element: Survivability; 

Critical Crusader Technology: 15. Integrated composite armor; 
Assessment: June 2001: 7; 
Assessment: April 2003: 7. 

Critical Crusader Technology: 16. Detection avoidance; 
Assessment: June 2001: 6; 
Assessment: April 2003: 6. 

[A] The table represents a joint assessment of TRLs by GAO and the 
Crusader program office. The TRLs reflect the level of maturity of 
critical technologies at the time of the assessment in June 2001 and 
their expected level of maturity at the time of the Crusader milestone 
B decision in April 2003. 

[End of table] 

As shown in table 1, if technology develops as planned, eight critical 
technologies will be at a TRL 6 level of maturity and two will be at a 
TRL 5 level of maturity at milestone B. While some technologies may 
embody some risk in meeting requirements, for the most part, the risk 
in the Crusader technologies involves the amount of time and effort 
needed to reach maturity. The planned technology maturity levels for 
the Crusader program at milestone B increase the probability that 
technical problems, if they occur, will need to be resolved in the 
higher cost environment of system development and demonstration. 
Confining delays in maturing technology to a time prior to the start 
of product development—in an environment where small teams of 
technologists work in laboratories and are dedicated to perfecting the 
technology—is critical to saving time and money. Conversely, if delays 
occur in product development when a large engineering force is in 
place to design and manufacture the product, delays would be much more 
costly. In fact, industry experts estimate that a delay during product 
development costs several times more than a similar delay that occurs 
before product development. 

Under the current Crusader acquisition plans, the critical 
technologies would be demonstrated in two steps after milestone B. 
Program officials are planning to demonstrate mobility component 
technologies first and then the remaining critical technologies. They 
recognize a risk in integrating the Crusader's mobility components-—
track, suspension, engine, and transmission—-and plan to produce a 
mobility test rig to demonstrate that integration and to start 
accumulating reliability data on the mobility components. The mobility 
test rig would have the additional advantage of demonstrating the 
maturity of those technologies in an operational environment. The 
contractor is scheduled to deliver the mobility test rig in December 
2003. The test rig would later be rebuilt as a Crusader prototype. 

The remaining critical technologies would not be demonstrated until 
after the contractor delivers the Crusader prototypes. The first 
Crusader system prototype is scheduled for delivery in October 2004 
and is to enter testing the same month. Other prototypes would enter 
testing as they are delivered. The Army plans to award contracts for 
low-rate initial production long-lead items in March 2005—less than a 
fourth of the way through the prototype-testing schedule. This leaves 
little time in the Crusader's projected system development and 
demonstration schedule for solving unanticipated problems before the 
Army awards contracts for long-lead production items. 

The Army's approach to readying the Crusader for milestone B is to 
demonstrate progress toward achieving five of the system's 
requirements, two of which are key performance parameters[Footnote 7]-—
the cannon rate of fire and the ability to resupply the self-propelled 
howitzer. For example, a Crusader key performance parameter is that 
the Crusader cannon be able to fire 10 to 12 rounds per minute; 
however, the program only needs to demonstrate the ability to fire 6 
rounds per minute before milestone B. The demonstrations, called exit 
criteria, were approved by both the Army and DOD. Among the 
demonstrations required by the exit criteria, only the cannon system 
is expected to be demonstrated in an operational environment; the 
other critical technologies are expected to be demonstrated in a 
laboratory environment. 

Moreover, like many other DOD programs, the Crusader program is using 
risk management plans and engineering judgment, without the benefit of 
TRLs, to assess technological maturity and mitigate program risk. Risk 
management plans and engineering judgment are necessary to manage risk 
in any major development effort like the Crusader. However, we have 
found in our reviews that without an underpinning, such as TRLs, that 
allows transparency into program decisions, significant technical 
unknowns may be judged acceptable risks because a plan exists for 
resolving them. For example, we recently reported that while DOD 
judged the technical risks facing the Joint Strike Fighter as 
acceptable for starting product development, an analysis of TRLs 
showed that eight critical technologies were below TRL 7, with six 
technologies at TRL 4 or 5. When problems are encountered in resolving 
these unknowns, programs often fail to meet promised outcomes, as 
noted above with the Brilliant Anti-Armor Submunition program. 

Army Has Improved the Crusader's Software Development Management: 

The Army has made improvements to its management of the software 
development process. Program officials stated that they would continue 
to aggressively manage the software development program to achieve and 
sustain the software process improvements. 

The automated Crusader system will be a software intensive program, 
projected to use about 1.9 million lines of code. Unlike any previous 
ground vehicle, all of the major functions of the Crusader are 
automated, including aiming, loading, and firing the cannon; managing 
inventory (projectiles and propellant); and resupplying the howitzer 
with ammunition and fuel. The crew compartment consists of a digital 
command center, with flat panel displays and re-configurable crew 
stations that give the crew real-time situation awareness, targeting 
information, integrated electronic technical manuals, decision aids, 
and diagnostic information. 

In 1998, the program began to experience software problems before 
meeting the software's preliminary design milestone. In June 1999, the
 Army decided that there were incomplete areas of the preliminary 
design and that the software team was not resolving design issues in a 
timely manner. Additionally, the software engineering team lacked 
disciplined quality assurance and configuration management practices, 
which led to some of the problems. 

In response, the program office tasked a software action team to 
identify problems and recommend improvements. The team drafted a 
recovery plan and recommended a number of process improvements for the 
prime contractor to implement. Program officials used the Software 
Development Capability Maturity Model to define and determine the 
software development process maturity.[Footnote 8] The Software 
Engineering Institute, part of Carnegie Mellon University, developed 
the model to measure and rank an organization's software development 
and acquisition process. The contractor agreed to mature its software 
engineering processes to a level where the standard processes for 
software development, such as project and risk management, are 
documented and enforced across the organization. According to the 
Software Engineering Institute, increasing the maturity level of an 
organization's software engineering process puts the organization in 
better position to successfully develop software. 

As a result of these efforts, the Army and its prime contractor have 
made improvements to their management of the Crusader software 
engineering process. Improved areas include requirements generation 
and validation, quality assurance, configuration management, risk 
management, schedule and cost estimation, project tracking and 
control, and peer reviews of software engineering products such as 
design documents, code, and test plans. In addition, outside experts 
assisted in software analysis and design. Others were brought in to 
independently assess the software recovery plan. The contractor 
implemented a number of changes in the software design process, 
including the establishment of a common set of software development 
and management tools shared by all software teams and improved 
software testing. The program office has also revised the
Crusader contract to provide the contractor monetary incentives to 
produce high-quality software on schedule. Software teams are also 
tracking progress and reporting it to management on a weekly or 
biweekly basis and have greatly improved their processes for 
estimating the size and schedule of the software. As a result of these 
improvements, the contractor has made more timely deliveries of 
software. 

Army officials will need to continue their aggressive management 
approach because significant amounts of software remain to be 
developed before the Crusader is fully operational. Program officials 
stated that they would continue to manage the program to achieve and 
sustain the software process improvements. 

Lighter-weight Crusader May Not Significantly Improve Strategic 
Deployability: 

The Army has made considerable progress over the past 2 years in 
redesigning the Crusader to substantially reduce its size and weight. 
In general, a lighter system offers a number of advantages, such as 
lower fuel consumption and easier transportation by truck and rail. 
However, it is uncertain that the requirement to deploy two Crusader 
howitzers on a C-17 aircraft provides a significant improvement in 
strategic deployability. Efforts to meet the deployability requirement 
will be a challenge and may require costly design changes and/or 
performance tradeoffs. 

According to an Army official, in October 1999, the Chief of Staff of 
the Army directed that the Crusader system become lighter and more 
deployable to better fit in with the Army's transformation to lighter 
forces. The Army subsequently revised the Crusader's Operational 
Requirements Documents to reflect new deployability requirements. 
Specifically, the documents state that: 

* the Crusader vehicles must not exceed 42 tons at curb weight and 50 
tons at combat weight;[Footnote 9] 

* any combination of two Crusader vehicles, at curb weight, must be 
air transportable on both a C-5 and a C-17 aircraft;[Footnote 10] and; 

* both the C-5 and C-17 aircraft must be able to transport a single 
Crusader vehicle at combat weight. 

Crusader's Reduced Size and Weight May Not Provide a Significant 
Improvement in Deployability: 

The main reason for the decision in January 2000 to restructure the 
program and redesign the Crusader weapon system was to reduce the 
system's weight and to improve its strategic deployability by air. 
However, the Army expects to rarely airlift the Crusader system-—only 
during extreme emergencies-—and that, in those circumstances, it would 
be likely that only small numbers of Crusader systems would be 
airlifted. Sealift would be the primary means of moving the Crusader 
system over long distances. In February 1999, the Army reported to 
Congress that the fielding of a lighter-weight Crusader would provide 
little in improved strategic deployability over a heavier version. 
[Footnote 11] In May 2000, the DOD's Office of Program Analysis and 
Evaluation questioned the need to improve the Crusader's 
deployability, stating that it is unclear whether airlifting a small 
force of the heavier Crusaders, when needed, would be a severe burden 
on airlift. 

A limited Army analysis comparing the deployability by air of small 
numbers of the original heavier Crusader with that of the lighter-
weight Crusader showed that the lighter-weight Crusader system might 
not significantly improve the system's strategic deployability. For 
example, this analysis showed that the lighter-weight Crusader system 
would reduce the number of sorties required to carry two Crusader 
systems and support equipment by 20 percent—one aircraft sortie—over 
the system's original, heavier design. The study showed that it would 
take four C-17 sorties to airlift two of the lighter-weight Crusader 
systems and support equipment while it would take five sorties to 
airlift two of the original heavier systems and support equipment. In 
addition, the heavier Crusader howitzers and both resupply vehicles 
would arrive loaded for combat while the lighter Crusader howitzers 
and only one resupply vehicle would arrive loaded for combat. The 
other resupply vehicle would have to be manually loaded upon arrival. 

The recent analysis was done with inputs from various Army officials 
but has not been officially reviewed by the Air Force. Prior to our 
request, the Army had not formally analyzed the improvements in 
strategic deployability offered by a 40-ton Crusader over the earlier 
60-ton Crusader. 

Army Faces Risks in Meeting Crusader's Deployability Requirement: 

Meeting the requirement for carrying two Crusader howitzers on a C-17 
aircraft will be challenging. According to the Air Force, the C-17 
aircraft is a more versatile aircraft and smaller than the C-5 
aircraft. The C-5 is normally used for strategic deployments—into and 
out of the combat theater—while the C-17 aircraft can be used for both 
strategic deployments and tactical missions within a combat theater. 
According to Army and Air Force officials responsible for aircraft 
loading plans, the only possible way to load two Crusader howitzers on 
a C-17 aircraft would be back to back. However, they have concerns 
about this loading method. First, it will be a very tight fit with one 
howitzer's cannon barrel expected to be 20 inches from the forward 
bulkhead (on the edge of a crew safety zone) and the other howitzer's 
barrel expected to be within 3 inches of the stowed aft loading ramp. 
Second, according to an Air Force official, the 59 inches separating 
the two howitzers may not be enough room to properly restrain the 
vehicles with heavy chains. 

In October 2001, the Army performed a preliminary computer analysis of 
loading two Crusader howitzers on a C-17. It indicated that, if the 
vehicles dimensions remain the same through redesign, development, 
testing, production, and fielding, the two howitzers may fit. This 
analysis also showed that the loading plan would be a very tight fit 
and does not address the issue of restraining the howitzers during 
flight. Air Force officials have not reviewed this analysis. Army and 
Air Force officials told us that it is unlikely they will know if the 
Crusader can actually be loaded and carried until two lighter-weight 
prototypes are produced and tested in a C-17 aircraft. 

Army officials told us that, if carrying two Crusaders on a C-17 
aircraft is not feasible, they will still accept the Crusader system 
because it is a much more capable system than the current self-
propelled howitzer system, the Paladin. Program officials also told us 
that reducing the system's weight is desirable because it reduced the 
logistics needed to support the system and improves, among other 
things, ground transportability and mobility. 

Cost and/or Performance Trade-offs May Be Needed to Meet Weight 
Requirement: 

According to the DOD and the Army, achieving the Crusader's reduced 
weight requirement and meeting the 42-ton limit will be a difficult 
challenge and will require aggressive weight management to mitigate 
the risks involved with system weight. As of November 2001, the 
Crusader howitzer is projected to weigh 41.2 tons, which is close to 
the upper limit of the 42-ton curb weight requirement. This 
projection, however, is based on computer modeling that is still 
evolving. The projected weight could change considerably as specific 
components are fabricated and tested. Program office officials told us 
that, at this point in time, they have an 80-percent confidence level 
in the model's weight projection. 

The Army has already made significant changes to the Crusader system 
design to reduce the curb weights of the system's vehicles. The curb 
weight of the howitzer is expected to go from 60 tons to a projected 
weight of below 42 tons. To achieve this weight reduction, the program 
office is redesigning the Crusader system by reducing the size and 
payload of the Crusader vehicles, substituting lighter weight 
materials for some components, and developing, with the Abrams tank 
program, a lighter weight engine. Additionally, the team plans to 
remove the heavy armor for top attack and road wheel protection and 
make it into kits that can be applied when needed in combat 
situations. To help reduce the overall weight of the Crusader system, 
the team decided to use a Palletized Load System truck carrying a 
newly designed resupply module as a second type of Crusader resupply 
vehicle-—a wheeled resupply vehicle. 

Although the Army has not made vehicle weight a key performance 
parameter for the Crusader program, it has instituted an aggressive 
weight management program designed to mitigate the risks associated 
with maintaining the 42-ton per vehicle weight limit. As part of the 
weight management program, the Army may have to consider the trade-
offs between the system's weight and the program's cost, schedule, and 
performance requirements in order to achieve the required curb and 
combat weights. The program is also in the position of not being 
allowed any weight growth during development, production, fielding, 
and service. Before the Crusader redesign, the program had a 17-
percent weight growth expectation for the Crusader vehicles. According 
to an Army official, if a new capability is added to the Crusader that 
increases its weight, the Army will have to find a way to reduce the 
weight of the Crusader by an equivalent amount. 

Apparent Overlap of Crusader and Future Combat Systems Programs 
Creates Uncertainties: 

The Army's current schedule to begin fielding the Crusader system and 
its replacement, the Future Combat Systems, in the same fiscal year-- 
2008-—represents a potential risk of investing in duplicative systems 
to fulfill the same missions. However, at this time it is uncertain 
that the initial versions of the Future Combat Systems will have the 
capabilities to meet the Crusader's missions. 

The Future Combat Systems are expected to be revolutionary, 
lightweight weapon systems-20 tons or less—that involve manned and 
unmanned, ground and air systems, all of which would be digitally 
networked together. All the vehicles in the system are being designed 
for transport on a C-130 or similar aircraft-—which are smaller 
aircraft than the C-17. Future Combat Systems vehicles may include 
command and control systems, reconnaissance systems, direct- and 
indirect-fire guns, rockets, and antitank missiles. 

The Future Combat Systems program is in an earlier stage of 
development than the Crusader—it is still in its initial 2-year 
concept design. Although the Future Combat Systems is a complex system 
of systems and the Army is still developing system concepts and 
technologies, the Army expects that the Future Combat Systems can be 
developed and produced in much shorter time frames than other weapons 
programs. Under the current Army schedule, the initial versions of the 
Future Combat Systems might enter the system development and 
demonstration phase as early as fiscal year 2003 and the first combat 
unit is scheduled to be equipped in 2008. Once fully fielded, the 
Future Combat Systems are intended to replace all of the Army's heavy 
weapon systems including the Crusader. Current Army plans show the 
Crusader to be in the force until 2032 or later. 
 
Because all the technologies needed for the Future Combat Systems may 
not be mature enough to be put into systems, the Army is planning to 
develop the initial version of the Future Combat Systems with less 
than its full capabilities and then upgrade it in a number of steps, 
called blocks, as the required technologies mature. The Army has not 
defined the capabilities that it can develop in the initial version of 
the Future Combat Systems, which it hopes will enter product 
development in 2003. As early as February 2002, the Army plans to 
award a contract to define these initial capabilities based on 
technologies that are mature enough to enter system development and 
demonstration in 2003. 

Eventually, the Army expects the Future Combat Systems to meet, using 
advanced technologies, the same artillery missions as the Crusader and 
eventually replace the Crusader system. While the final weapon 
technologies have not been selected for the Future Combat Systems, 
technologies that could provide the systems with capabilities to 
perform artillery missions similar to or greater than the Crusader 
include a multi-role armament system. This possible system could 
feature a 105-mm cannon that may have a non-line-of-sight capability 
out to a range of about 50 kilometers. Also, the Army is considering 
an advanced missile system that could be comprised of small-
containerized missiles, known as NetFires, which are projected to have 
a range of 50 to 100 kilometers. A high-level Army official told us 
that he believes, based on recent technical briefings, that the 
initial version of the Future Combat Systems will not have the 
capabilities to meet the same artillery missions as the Crusader. 

Conclusions: 

Moving into product development without demonstrating critical 
technologies in an operational environment increases the risk of cost 
overruns, schedule delays, and performance shortfalls. As currently 
planned, the majority of the critical Crusader technologies will have 
been demonstrated in a relevant environment but not the important 
operational environment. If the Crusader program follows the approach 
of moving into product development with less mature technologies, the 
program will need to continue to develop and demonstrate those 
technologies while concentrating on integrating subsystems into the 
system, testing at the subsystem and system levels, and preparing for 
production. As a result, technical problems, if they occur, will need 
to be resolved in the higher cost environment of system development 
and demonstration. On the other hand, demonstrating the critical 
technologies in an operational environment before entering system 
development and demonstration could necessitate more time and money 
than currently planned before the milestone B decision, but such 
investments would be relatively small compared to solving technical 
problems after the decision. 

The Army restructured the Crusader program to improve the system's 
strategic deployability by reducing the system's weight. The lighter-
weight system, however, may not provide a significant improvement to 
strategic deployability. At this time, the Army is making design trade-
offs to meet its weight requirement and it is not clear whether the 
Army can maintain its lighter weight goals throughout the development, 
production, and fielding of the Crusader system. Given the 
uncertainty, the Army risks making unnecessary cost, schedule, and 
performance trade-offs to meet deployability requirements that may not 
be clearly justified. 

The Army has not ruled out the possibility that it will field the 
Future Combat Systems with the ability to meet the same artillery 
mission as the Crusader in the same year the Crusader is fielded. 
However, the extent of this apparent overlap will not be clear until 
the potential capabilities and schedule of the initial version of the 
Future Combat Systems are determined. Therefore, it is important that 
the Army ensure that the projected capabilities and schedule for the 
initial Future Combat Systems are considered in the Crusader milestone 
decision. 

Recommendations for Executive Action: 

To reduce the risk of schedule delays and increased costs in the 
product development phase of the Crusader program, we recommend that 
the secretary of defense direct the secretary of the army to dedicate 
the resources necessary to ensure that the critical Crusader 
technologies are demonstrated, at the component and subsystem level, 
in an operational environment before the program commits to product 
development at milestone B. 

To confirm the value and usefulness of the Crusader program's 
deployability requirement, we recommend that the secretary of defense 
direct the secretary of the army to conduct an analysis, before the 
decision to enter product development, to determine how important it 
is to deploy two Crusaders howitzers on a single C-17 aircraft. If it 
is important to the Army, we recommend that the secretary of defense 
direct the secretary of the army to establish, as a key performance 
parameter, the maximum per vehicle weight that would allow the C-17 
aircraft to carry two Crusader howitzers. If the analysis determines 
that the redesigned Crusader does not significantly improve the 
system's military utility, we recommend that the secretary of defense 
direct the secretary of the army to reduce the priority placed on 
attaining the 42-ton weight limit. 

Finally, to ensure the Army does not invest in two weapon systems that 
will meet the same artillery missions at the same time, we recommend 
that the secretary of defense direct the secretary of the army to 
determine, based on available data, the potential capabilities and 
schedule of the initial version of the Future Combat Systems and the 
implication of those capabilities and schedule on the Crusader's 
utility to the Army before making the decision on beginning the 
Crusader's system development and demonstration—-currently scheduled 
for April 2003. 

Agency Comments: 

In written comments on a draft of this report, the director of 
strategic and tactical systems, within the Office of the Under 
Secretary of Defense for and Our Evaluation Acquisition, Technology, 
and Logistics, said that DOD did not agree with our recommendation 
that the Crusader technologies be demonstrated in an operational 
environment before the program commits to product development. DOD 
said that the Crusader program was a simulation-based acquisition 
program and, as such, evaluates system, component, and subsystem 
performance and technology readiness using modeling and simulation 
validated with test stands, integration laboratories, and subsystem 
prototypes. DOD questioned our definition of critical Crusader 
technologies and said that the track, for example, was selected by us 
as a critical technology and assessed as a TRL 5 despite the Army's 
many years of expertise in track development. DOD also said that the 
Crusader is currently demonstrating performance equal to or in excess 
of threshold requirements for the final system. Finally, DOD said that 
changing the Crusader's acquisition strategy to accommodate building 
system level prototypes required to demonstrate TRL 7 for all critical 
technologies would add significantly to the development time and 
expense without significantly reducing risk or improving performance. 
The full text of DOD's comments is included in appendix II. 

We agree that modeling and simulation is a key and accepted practice 
in any modern development program. However, we have found that 
programs need to demonstrate a high level of technology maturity 
before committing to product development. As shown by our past 
reviews, the best practice standard is that technology must be 
demonstrated, at the component or subsystem level, in an operational 
environment to be considered mature enough for entering product 
development. We believe that a program should use this best practice 
to assure success in meeting its cost and schedule goals. 

The determination of the critical Crusader technologies was a joint 
effort between the Crusader program office and us. We defined critical 
Crusader technologies as those required to meet the Crusader's key 
performance parameters and developed the initial critical technology 
list. Crusader program office engineers reviewed the initial list, 
suggested revisions, and agreed that the revised critical technologies 
list was complete and appropriate. Also, our analysts and program 
office engineers jointly arrived at the appropriate TRL for each 
critical technology. In addition, DOD's statement that track should 
not be a critical Crusader technology or should have been assessed at 
a higher TRL because of the Army's many years of expertise in track 
development underscores the value of the TRL methodology. Track was 
included as a critical Crusader technology because the Crusader cannot 
meet its mobility key performance parameter without track. The track 
was assessed at TRL 5 because the Crusader program was developing a 
new lighter-weight track. The Army plans to demonstrate it in an 
operational environment after milestone B. TRLs measure whether 
sufficient knowledge has been accumulated with respect to each 
application of a technology, not the development difficulty of the 
technology or whether the technology has been previously used in 
another application. The issue is not whether a technology like the 
newly developed track will ever work, but how much time and effort 
will be needed to demonstrate its maturity in this application. The 
Crusader system development and demonstration phase does not have much 
time between prototype testing and procurement of long-lead items for 
production to adjust for any delays or problems in prototype testing 
caused by technology problems. Such delays or problems could either 
delay the long-lead item procurement or reduce the amount of 
information available when committing to the procurement. 

DOD's assessment that the Crusader system is currently demonstrating 
performance equal to or in excess of threshold requirements for the 
final system is based mainly on modeling, simulations, and laboratory 
tests because the program has not produced the final system. As 
mentioned above, best practice calls for critical technologies to be 
demonstrated in an operational environment not in models, simulations, 
or laboratory environments before entering product development. 

DOD stated that building the full system prototype required to 
demonstrate TRL 7 would add significant time and expense to the 
program. However, demonstrating at TRL 7 does not require a full 
system prototype but only a prototype of the component or subsystem 
that contains a new technology. The demonstration can be accomplished 
by putting the new component or subsystem, such as an engine, on a 
surrogate vehicle; that is, a vehicle that already exists. The 
report's point is that using full system prototypes to demonstrate the 
maturity of critical technologies during the product development 
phase, as planned in the Crusader program, is potentially more costly 
than using component or subsystem prototypes to do so during the 
technology development phase. Problems that occur during required 
demonstrations may cause program delays in either phase, but as noted 
in the report, the delay is more expensive during the product 
development phase. 

DOD stated that it partially agreed with our recommendation to conduct 
an analysis to determine the importance of the deployability 
requirement and said that the current requirement is not considered a 
key performance parameter and, as a result, the Army is allowed to 
make trade-offs between the requirement and system cost and 
performance. DOD further stated that the Army plans to review the 
Crusader's requirements prior to the 2003 milestone B decision as 
required by regulations. We believe that an analysis to determine the 
importance of deploying two Crusader howitzers on a C-17 aircraft 
should be conducted as soon as possible to provide the Army greater 
flexibility and knowledge in considering its ongoing trade-off 
decisions needed to meet weight requirements. 

DOD stated that it partially agreed with our recommendation to 
determine the potential capabilities and schedule of the initial 
version of the Future Combat Systems before making the decision to 
begin Crusader product development and stated that the Crusader's 
capabilities are intended to complement rather than compete with or be 
redundant to the capabilities of the Future Combat Systems. We 
continue to believe that DOD cannot determine whether the two systems 
will be complementary or redundant without knowledge of the initial 
Future Combat Systems capabilities and fielding schedule. DOD does not 
have this knowledge. We continue to believe that this knowledge needs 
to be considered as part of the decision to allow the Crusader program 
to enter product development. We have rewritten the recommendation to 
clarify its intent. 

Scope and Methodology: 

To determine the readiness of the Crusader program to enter the system 
development and demonstration phase, we assessed, along with engineers 
from the Crusader Project Office, the current maturity of the critical 
Crusader technologies using the technology readiness level tool. We 
identified the Crusader technologies we believed were critical to 
meeting the Crusader system key performance parameters. Program 
engineers reviewed our list, suggested revisions, and agreed that the 
revised critical technologies list was complete and appropriate. After 
considering the program's plans for maturing the critical technologies 
before milestone B, we jointly determined the probable TRL levels of 
each of the critical technologies at the milestone. This determination 
assumed that the program office would successfully execute its 
existing plans for demonstrating some of the technologies before the 
milestone. 

To assess the status of the Crusader software development, we used 
project management criteria derived from Software Engineering 
Institute's Software Development Capability Maturity Model. We visited 
the Crusader prime contractor, met with Army and contractor officials, 
observed software development and test facilities, and examined 
project information. We also obtained and reviewed project 
documentation from the prime contractor and the Army program office. 

To assess the Crusader program's ability to meet the Crusader reduced 
weight requirements and improve the Crusader system's strategic 
deployability, we analyzed the Army's plans and requirements for 
reducing the weight of the Crusader and requested that the Army 
perform an analysis of the improvement in strategic deployability that 
the reduced weight Crusader system would provide compared to the 
original weight Crusader system. For this analysis, at our request, 
the Army determined the number of Crusader systems to be deployed, the 
other equipment and supplies that were required to be deployed with 
the Crusader systems, and the range of the aircraft used for the 
deployment. We reviewed the results of the Army's Crusader deployment 
analysis. 

To determine whether the Army is developing the Crusader and the Future
Combat Systems to be fielded at the same time and to meet the same 
artillery missions, we analyzed and compared the Crusader and Future
Combat Systems schedules and reviewed the Crusader system operational 
requirements documents. The Future Combat Systems do not have 
operational requirements documents at this stage of development. Also, 
we discussed with appropriate officials in the Army's Objective Force 
Task Force, the Army's artillery school, and the Crusader and the 
Future Combat Systems programs (1) the probability that the two 
programs would meet their individual schedules and (2) the potential 
technologies that might be used in the Future Combat Systems to 
provide it with artillery capabilities. 

In performing our work, we obtained documents and interviewed 
officials involved in the Crusader and the Future Combat Systems 
programs in the Office of the Deputy Chief of Staff for Operations, 
Washington, D.C.; U.S. Army Training and Doctrine Command, Fort 
Monroe, Virginia; U.S. Army Field Artillery School and Center, Fort 
Sill, Oklahoma; the Defense Advanced Research Projects Agency, 
Arlington, Virginia; the Military Traffic Management Command, Newport 
News, Virginia; the U.S. Air Force, Air Mobility Command, St. Louis, 
Missouri; the U.S. Air Force Aeronautical Systems Command, Dayton, 
Ohio; the Crusader Project Office, Picatinny Arsenal, New Jersey; and 
the prime contractor's Minneapolis, Minnesota, facility. 

We conducted our review between March 2001 and October 2001 in 
accordance with generally accepted government auditing standards.
We also are sending copies of this report to the appropriate 
congressional committees; the director, Office of Management and 
Budget; and the secretaries of defense and the army. We will also 
provide copies to others upon request. 

If you or your staff have any questions concerning this report, please 
contact me at (202) 512-4841 or William R. Graveline at (256) 650-
1414. Key contributors are listed in appendix III. 

Signed by: 

James F. Wiggins: 
Director: 
Acquisition and Sourcing Management: 

List of Committees: 

The Honorable Carl Levin: 
Chairman: 
The Honorable John W. Warner: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Daniel K. Inouye: 
Chairman: 
The Honorable Ted Stevens: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Bob Stump: 
Chairman: 
The Honorable Ike Skelton: 
Ranking Minority Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable Jerry Lewis: 
Chairman: 
The Honorable John P. Murtha: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

[End of section] 

Appendix I: Technology Readiness Levels and Their Descriptions: 

Technology readiness level: 1. Basic principles observed and reported. 
Description: Lowest level of technology readiness. Scientific research 
begins to be translated into technology's basic properties. 

Technology readiness level: 2. Technology concept and/or application 
formulated. 
Description: Invention begins. Once basic principles are observed, 
practical applications can be invented. The application is speculative 
and there is no proof or detailed analysis to support the assumptions. 
Examples are still limited to paper studies. 

Technology readiness level: 3. Analytical and experimental critical 
functions and/or characteristic proof of concept. 
Description: Active research and development is initiated. This 
includes analytical studies and laboratory studies to physically 
validate analytical predictions of separate elements of the 
technology. Examples include components that are not yet integrated or 
representative. 

Technology readiness level: 4. Component and/or breadboard validation 
in laboratory environment. 
Description: Basic technological components are integrated to 
establish that the pieces will work together. This is relatively "low 
fidelity' compared to the eventual system. Examples include 
integration of "ad hoc" hardware in a laboratory. 

Technology readiness level: 5. Component and/or breadboard validation 
in relevant environment. 
Description: Fidelity of breadboard technology increases 
significantly. The basic technological components are integrated with 
reasonably realistic supporting elements so that the technology can be 
tested in a simulated environment. Examples include "high fidelity' 
laboratory integration of components. 

Technology readiness level: 6. System/subsystem model or prototype 
demonstration in a relevant environment. 
Description: Representative model or prototype system, which is well 
beyond the breadboard tested for level 5, is tested in a relevant 
environment. Represents a major step up in technology's demonstrated 
readiness. Examples include testing a prototype in a high fidelity 
laboratory environment or in a simulated operational environment. 

Technology readiness level: 7. System prototype demonstration in an 
operational environment. 
Description: Prototype near or at planned operational system. 
Represents a major step up from level 6, requiring the demonstration 
of an actual system prototype in an operational environment. Examples 
include testing the prototype in a test bed aircraft. 

Technology readiness level: 8. Actual system completed and qualified 
through test and demonstration. 
Description: Technology has been proven to work in its final form and 
under expected conditions. In almost all cases, this level represents 
the end of true system development. Examples include developmental 
test and evaluation of the system in its intended weapon system to 
determine if it meets design specifications. 

Technology readiness level: 9. Actual system proven through successful 
mission operations. 
Description: Actual application of technology in its final form and 
under mission conditions, such as those encountered in operational 
test and evaluation. Examples include using the system under 
operational mission conditions. 

Source: Appendix 6 of DOD Regulation 5000.2R, "Mandatory Procedures 
for Major Defense Acquisition Programs (MDAPS) and Major Automated 
Information System (MAIS) Acquisition Programs," June 10, 2001. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
Acquisition, Technology And Logistics:
3000 Defense Pentagon: 
Washington, DC 20301-3000: 

January 28, 2002: 

Mr. James Wiggins: 
Director: 
Acquisition and Sourcing Management: 
U.S. General Accounting Office: 
Washington, D.C. 20548: 

Dear Mr. Wiggins: 

This is the Department of Defense (DoD) response to the GAO draft 
report, "Defense Acquisitions: Crusader Program Faces Technical and 
Other Risks," dated December 14, 2001 (GAO Code 120027/GAO-02-201). 
The DoD nonconcurs with recommendation 1 and partially concurs with 
recommendations 2 and 3. Our specific responses to the GAO's 
recommendations are attached. 

The DoD appreciates the opportunity to comment on the draft report. 

Signed by: 

[Illegible] for George R. Schneiter: 
Director: 
Strategic and Tactical Systems: 

Attachment: As Stated: 

[End of letter] 

GAO Draft Report Dated December 14, 2001: 
(GAO Code 120027) GAO-02-201: 

"Defense Acquisitions: Crusader Program Faces Technical And Other 
Risks" 

Department Of Army Comments To The GAO Recommendations: 

Recommendation 1: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Army to dedicate the resources necessary 
to ensure that the critical Crusader technologies are demonstrated in 
an operational environment before the program commits to product 
development at Milestone B. (p. 14/GAO Draft Report) 

DOD Response: Nonconcur. Crusader is fully resourced in accordance 
with its approved Acquisition Program Baseline and Acquisition 
Strategy Report. The GAO recommends that Crusader demonstrate 
Technology Readiness Level Seven (TRL 7) prior to Milestone B. 
Crusader is a Simulation-Based Acquisition program as defined in
DoD Instruction 5000.1, DoD Regulation 5000.2, and DoD 5000.2-R. As 
such, Crusader evaluates system, subsystem, and component performance 
and technology readiness using modeling and simulation validated with 
test stands, integration laboratories, and subsystem prototypes, 
avoiding the time and expense of major system prototypes, at this 
stage in development. This is an accepted practice within both the 
government and industry. Crusader's approved Acquisition Strategy 
Report employs a single iteration of system prototypes following 
Milestone B. Validation of the modeling and simulation used in 
developing Crusader shows excellent correlation with the actual 
performance of Crusader's subsystems and components. The modeling used 
for Crusader has shown sufficient fidelity to identify potential 
physical interface problems as close as one thousandth of an inch. 
Additionally, the DoD questions the GAO's definition of critical
Crusader technologies. Track, for example, was selected as a critical 
technology and given a TRL 5 rating despite many years of experience 
in track development. Currently, Crusader is on schedule, within 
budget, and exceeding performance exit criteria for Milestone B. In 
fact, Crusader is currently demonstrating performance equal to or in 
excess of threshold requirements for the final system. Changing the 
Acquisition Strategy for Crusader to accommodate building the system-
level prototypes required to demonstrate TRL 7 for all critical 
technologies prior to Milestone B would add significantly to the 
development time and expense without significantly reducing risk or 
improving performance. 

Recommendation 2: The GAO recommended that the Secretary of Defense 
direct the Secretary of the Army to, before the decision to enter 
product development, conduct an analysis to determine how important it 
is to deploy two Crusaders on a single C-17 aircraft. (p. 14/Draft 
Report) 

a. If it is important to the Army, GAO recommends that the Secretary 
of Defense direct the Secretary of the Army to establish, as a key 
performance parameter, the maximum per-vehicle weight that would allow 
the C-17 aircraft to carry two Crusader self-propelled howitzers. 

b. If the analysis determines that the redesigned Crusader does not 
significantly improve the system's military utility, the GAO 
recommends that the Secretary of Defense direct the Secretary of the 
Army to reduce the priority placed on attaining the 42-ton weight 
limit. 

DOD Response: Partially concur. Continued analysis of weight and 
transportability will continue throughout Crusader's development. An 
Analysis of Alternatives and review of system requirements by the Army 
Requirements Oversight Committee (AROC) and Joint Requirements 
Oversight Council (JROC) will be conducted prior to Milestone B, as 
required by Army and DoD policy and regulation, to validate current 
systems performance parameters, including Key Performance Parameters. 
The current Key Performance Parameters were established in a similar 
fashion prior to Crusader's Milestone I decision. Maximum system 
weight, while a very important requirement, is not a Key Performance 
Parameter. This allows the cost of increasing, reducing, or
maintaining system weight to be balanced with total system performance 
(Cost as an Independent Variable, CAIV). In fact, the current key 
performance requirements for system mobility and maximum range are 
sensitive to changes in system weight, among other factors. The DoD 
believes that the current treatment of system weight is appropriate. 

Recommendation 3: The GAO recommended that the Secretary of Defense make
the Crusader's product development decision only after he determines 
that the Army will not field Future Combat Systems with the ability to 
meet the same artillery mission as the Crusader in nearly the same 
time frame as the Crusader. (p. 14/Draft Report) 

DOD Response: Partially concur. Crusader's capabilities are intended 
to complement rather than compete with or be redundant to the 
capabilities of the Future Combat Systems that are expected to exist 
on the battlefield during Crusader's service life. The fire support 
variants of the Future Combat Systems and the Crusader each respond to 
unique requirements. 

[End of section] 

Appendix III: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

James F. Wiggins, (202) 512-4841: 
William R. Graveline, (256) 650-1414: 

Staff Acknowledgments: 

In addition to those named above, the following individuals made
significant contributions to this report: Robert L. Ackley; Nabajyoti  
Barkakati; Paul L. Francis; Lawrence D. Gaston, Jr.; Matthew B. Lea;
Gary L. Middleton; Madhav S. Panwar; Robert J. Stolba; and John P. 
Swain. 
 
[End of section] 

Footnotes: 

[1] Prognostics is a system to forecast potential failures in 
subsystems, allowing the maintainers to correct them before they fail. 

[2] Best Practices: Successful Application to Weapon Acquisitions 
Requires Changes in DOD's Environment [hyperlink, 
http://www.gao.gov/products/GAO/NSIAD-98-56], Feb. 24, 1998, and Best 
Practices: Better Management of Technology Development Can Improve 
Weapon System Outcomes [hyperlink, 
http://www.gao.gov/products/GAO/NSIAD-99-162], July 30, 1999. 

[3] DOD Instruction 5000.2 "Operation of the Defense Acquisition 
System," Jan. 4, 2001. 

[4] DOD Regulation 5000.2R "Mandatory Procedures for Major Defense 
Acquisition Programs (MDAPS) and Major Automated Information System 
(MAIS) Acquisition Programs," June 10, 2001. 

[5] We identified critical technologies as those needed to meet 
Crusader's key performance parameters. 

[6] GAO has performed or is performing similar TRL assessments of the 
Airborne Laser, Comanche, Joint Strike Fighter, and Space-Based 
Infrared Satellite. 

[7] A key performance parameter is a capability or characteristic that 
DOD believes is central to a system's performance. 

[8] Software Development Capability Maturity Model' is a service mark 
of Carnegie Mellon University and is registered in the U.S. Patent and 
Trademark Office. 

[9] The curb weight is the vehicle weight without a full load of fuel, 
with no ammunition or extra armor. The combat weight is the vehicle's 
weight fully loaded with fuel, ammunition, and armor kits. The reason 
for the curb weight limit is to allow any combination of the two 
Crusader vehicles to be flown in a C-5 aircraft to a desired range of 
3,200 nautical miles and on a C-17 with no specific range requirement. 

[10] The 42-ton upper-limit on the Crusader weight is needed to 
accommodate the requirement for the C-17 to carry two Crusader 
vehicles. The C-17's maximum payload is about 85 tons. At that weight, 
the range of the C-17 would be about 2,200 nautical miles. 

[11] Crusader, Advanced Field Artillery System, A Report to 
Congressional Defense Committees; U.S. Army; February 1999. 

[End of section] 

GAO’s Mission: 

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analysis, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO’s commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO’s Web site [hyperlink, 
http://www.gao.gov] contains abstracts and fulltext files of current 
reports and testimony and an expanding archive of older products. The 
Web site features a search engine to help you locate documents using 
key words and phrases. You can print these documents in their entirety, 
including charts and other graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as “Today’s Reports,” on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
[hyperlink, http://www.gao.gov] and select “Subscribe to daily E-mail 
alert for newly released products” under the GAO Reports heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. General Accounting Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, NelliganJ@gao.gov: 
(202) 512-4800: 
U.S. General Accounting Office: 
441 G Street NW, Room 7149:
Washington, D.C. 20548: