This is the accessible text file for GAO report number GAO-02-124 
entitled 'Missile Defense: Review of Results and Limitations of an 
Early National Missile Defense Flight Test' which was released on 
February 28, 2002. 

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the 
printed version. The portable document format (PDF) file is an exact 
electronic replica of the printed version. We welcome your feedback. 
Please E-mail your comments regarding the contents or accessibility 
features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States General Accounting Office: 
GAO: 

Report to the Honorable Edward J. Markey, House of Representatives: 

February 2002:  

Missile Defense: 

Review of Results and Limitations of an Early National Missile Defense 
Flight Test: 

GAO-02-124: 

Contents: 

Letter Disclosure of Key Results and Limitations: 

Project Office Reliance on Various Sources for Contractor Oversight: 

Distinguishable Differences in Objects Deployed in Space Decoy 
Reduction in Later Tests: 

Evaluation of TRW's Discrimination Software: 

Agency Comments and Our Evaluation: 

Appendix I: Disclosure of Flight Test's Key Results and Limitations: 

The Test: 

Reported Key Results and Limitations: 

Effect of Cooling Failure on Sensor's Performance: 

Appendix II: Project Office Reliance on Various Sources for Contractor 
Oversight: 

Appendix III: Reduced Test Complexity: 

Decoys in Early Intercept Tests: 

Opinions on Decoys: 

Appendix IV: Phase One Engineering Team's Evaluation of TRW's Software: 

Phase One Engineering Team's Methodology: 

The Phase One Engineering Team's Key Results: 

Limitations of the Team's Evaluation: 

Appendix V: Boeing Integrated Flight Test 1A Requirements and Actual 
Performance as Reported by Boeing and TRW: 

Appendix VI: Scope and Methodology: 

Appendix VII: Comments from the Department of Defense: 

Appendix VIII: Major Contributors: 

Acquisition and Sourcing Management: 

Applied Research and Methods: 

General Counsel: 

Tables: 

Table 1: What and When Key Results and Limitations Were Included in 
Contractors' Written Reports: 

Table 2: Planned and Actual Targets for Initial Flight Tests: 

Table 3: Integrated Flight Test 1A Requirements Established by Boeing 
and Actual Performance: 

[End of section] 

United States General Accounting Office: 
Washington, DC 20548: 

February 28, 2002: 

The Honorable Edward J. Markey: 
House of Representatives: 

For a number of years, the Department of Defense has been researching 
and developing defenses against ballistic missile attacks on the 
United States, its deployed forces, friends, and allies. In 1990, the 
Department awarded research and development contracts to three 
contractors to develop and test exoatmospheric kill vehicles.[Footnote 
1] The Department planned to use the best of the three vehicles in a 
follow-on missile defense program. One of the contractors, Rockwell 
International, subcontracted a portion of its kill vehicle design work 
to TRW. TRW was tasked with developing software that could operate on 
a computer onboard the kill vehicle. The software was to analyze data 
collected in flight by the kill vehicle's sensor (which collects real-
time information about threat objects), enabling the kill vehicle to 
distinguish an enemy warhead from accompanying decoys.[Footnote 2] 

The three contractors proceeded with development of the kill vehicle 
designs and built and tested key subsystems (such as the sensor) until 
1994. In 1994, the Department of Defense eliminated Martin Marietta 
from the competition. Both Rockwell—-portions of which in December 
1996 became Boeing North American-—and Hughes-—now Raytheon—-continued 
designing and testing their kill vehicles. In 1997 and 1998, the 
National Missile Defense Joint Program Office[Footnote 3] conducted 
tests, in space, of the sensors being developed by the contractors for 
their competing kill vehicles. Boeing's sensor was tested in June 1997 
(Integrated Flight Test 1A) and Raytheon's sensor was tested in 
January 1998 (Integrated Flight Test 2). Program officials said these 
tests were not meant to demonstrate that the sensor met performance 
requirements, nor were they intended to be the basis for any contract 
award decisions. Rather, they were early research and development 
tests that the program office considered experiments to primarily 
reduce risk in future flight tests. Specifically, the tests were 
designed to determine if the sensor could operate in space; to examine 
the extent to which the sensor could detect small differences in 
infrared emissions; to determine if the sensor was accurately 
calibrated; and to collect target signature[Footnote 4] data for post-
mission discrimination analysis. 

After the two sensor tests, the program office planned another 19 
flight tests from 1999 through 2005 in which the kill vehicle would 
attempt to intercept a mock warhead. Initially, Boeing's kill vehicle 
was scheduled for testing in Integrated Flight Test 3 and Raytheon's 
in Integrated Flight Test 4. However, Boeing became the Lead System 
Integrator for the National Missile Defense Program in April 1998 and, 
before the third flight test was conducted, selected Raytheon as the 
primary kill vehicle developer.[Footnote 5] 

Meanwhile, in September 1995, TRW had hired a senior staff engineer,
Dr. Nira Schwartz, to work on various projects, including the 
company's effort to develop the exoatmospheric kill vehicle's 
discrimination software. The engineer helped evaluate some facets of a 
technology known as the Extended Kalman Filter Feature Extractor, 
[Footnote 6] which TRW planned to add as an enhancement to its 
discrimination software. The engineer reported to TRW in February 1996 
that tests revealed that the Filter could not extract the key 
characteristics, or features, from various target objects that an 
enemy missile might deploy and demanded that the company inform 
Rockwell and the Department of Defense. TRW fired the engineer in 
March 1996. In April 1996, the engineer filed a lawsuit under the 
False Claims Act[Footnote 7] alleging that TRW[Footnote 8] falsely 
reported or hid information to make the National Missile Defense Joint 
Program Office believe that the Extended Kalman Filter Feature 
Extractor met the Department's technical requirements. The engineer 
has amended the lawsuit several times, including adding allegations 
that TRW misled the Department of Defense about the ability of its 
discrimination software to distinguish a warhead from decoys and that 
TRW's test reports on Integrated Flight Test 1A falsely represented 
the discrimination software's performance. 

The False Claims Act allows a person to bring a lawsuit on behalf of the
U.S. government if he or she has knowledge that a person or company 
has made a false or fraudulent claim against the government. If the 
suit is successful, the person bringing the lawsuit may share in any 
money recovered. The Department of Justice reviews all lawsuits filed 
under the act before deciding whether to join them. If it does, it 
becomes primarily responsible for prosecuting the case. 

To determine whether it should join the engineer's lawsuit against TRW,
Justice asked the Defense Criminal Investigative Service, a unit 
within the Department of Defense Inspector General's office,[Footnote 
9] to examine the allegations. The engineer cooperated with the 
Investigative Service for more than 2 years. During the course of the 
Department of Defense's investigation into the allegations of 
contractor fraud, two groups examined the former employee's specific 
allegations regarding the performance of TRW's basic discrimination 
software and performed limited evaluations of the Extended Kalman 
Filter Feature Extractor. The first was Nichols Research Corporation, 
a contractor providing technical assistance to the Ground Based 
Interceptor Project Management Office for its oversight of the 
exoatmospheric kill vehicle contracts. (This office within the 
National Missile Defense Joint Program Office is responsible for the 
exoatmospheric kill vehicle contracts.) Because an investigator for the
Defense Criminal Investigative Service was concerned about the ability 
of Nichols to provide a truly objective assessment, the National Missile
Defense Joint Program Office asked an existing advisory group, known 
as the Phase One Engineering Team,[Footnote 10] to undertake another 
review of the specific allegations of fraud with respect to the 
software. This group is comprised of scientists from Federally Funded 
Research and Development Centers who were selected for the review team 
because of their knowledge of the National Missile Defense system. In 
addition, both Nichols and the Phase One Engineering Team assessed the 
feasibility of using the Extended Kalman Filter Feature Extractor to 
extract additional features from target objects that an enemy missile 
might deploy.[Footnote 11] 

The Department of Justice and the Defense Criminal Investigative 
Service investigated the engineer's allegations until March 1999. At 
that time, the Department of Justice decided not to intervene in the 
lawsuit. The engineer has continued to pursue her lawsuit without 
Justice's intervention. 

When a Massachusetts Institute of Technology professor, Dr. Theodore
Postol, learned of the engineer's claims, he conducted his own 
analysis of Integrated Flight Test 1A. In May 2000, the professor 
wrote to the White House alleging that Boeing North American and TRW 
misrepresented the results of the test. 

The professor claimed that his analysis of Integrated Flight Test 1A 
showed that the system can be defeated by the simplest of decoys and 
that the National Missile Defense Joint Program Office and its 
contractors attempted to hide this fact by tampering with the flight 
test data and altering their analysis of the sensor's discrimination 
capabilities. The professor also alleged that objects deployed as part 
of Integrated Flight Test 1A displayed no distinguishable differences 
that Boeing's infrared  sensor could use to identify the mock warhead 
from decoys and that the program office hid the sensor's weaknesses by 
reducing the number of decoys planned for future tests. Further, the 
professor claimed that the Phase One Engineering Team's analysis was 
faulty. 

 At your request, we reviewed the professor's allegations. 
Specifically, as discussed with your office, we addressed the 
following questions: 
 
1. Did Boeing and TRW disclose the key results and limitations of the 
flight test to the National Missile Defense Joint Program Office? 

2. How did the Ground Based Interceptor Project Management Office 
oversee Boeing's and TRW's technical performance? 

3. Did the flight test show whether each object deployed in space by 
an attacking missile exhibits distinguishable features? 

4. Why did the National Missile Defense Joint Program Office reduce 
the complexity of later flight tests? 

5. What were the methodology, findings, and limitations of the 
evaluation conducted by the Phase One Engineering Team of TRW's 
discrimination software? 

You also asked us to determine whether the Department of Defense 
misused the security classification process to stifle public 
discussion of possible problems with the National Missile Defense 
system. We addressed this question in a separate report, dated June 
12, 2001.[Footnote 12] 

Disclosure of Key Results and Limitations: 

Boeing and TRW disclosed the key results and limitations of Integrated 
Flight Test 1A in written reports released between August 13, 1997, 
and April 1, 1998. The contractors explained in a report issued 60 
days after the June 1997 test that the test achieved its primary 
objectives, but that some sensor abnormalities were noted.[Footnote 
13] For example, while the report explained that the sensor detected 
the deployed targets and collected some usable target signals, the 
report also stated that some sensor components did not operate as 
desired and the sensor often detected targets where there were none. 
In December 1997, the contractors documented other test anomalies. 
According to briefing charts prepared for a December meeting, the 
Boeing sensor tested in Integrated Flight Test 1A had a low 
probability of detection; the sensor's software was not always 
confident that it had correctly identified some target objects; the 
software significantly increased the rank of one target object toward 
the end of the flight; and in-flight calibration of the sensor was 
inconsistent. Additionally, on April 1, 1998, the contractors 
submitted an addendum to an earlier report that noted two more 
problems. In this addendum, the contractors disclosed that their claim 
that TRW's software successfully distinguished a mock warhead from 
decoys during a post-flight analysis was based on tests of the 
software using about one-third of the target signals collected during 
Integrated Flight Test 1A. The contractors also noted that TRW reduced 
the software's reference data{Footnote 14] so that it would correspond 
to the collected target signals being analyzed. Project office and 
Nichols Research officials said that in late August 1997, the 
contractors orally communicated to them all problems and limitations 
that were subsequently described in the December 1997 briefing and the 
April 1998 addendum. However, neither project officials nor 
contractors could provide us with documentation of these 
communications. 

Although the contractors reported the test's key results and 
limitations, they described the results using some terms that were not 
defined. For example, one written report characterized the test as a 
"success" and the sensor's performance as "excellent." We found that 
the information in the contractors' reports, in total, enabled 
officials in the Ground Based Interceptor Project Management Office 
and Nichols Research to understand the key results and limitations of 
the test. However, because such terms are qualitative and subjective 
rather than quantitative and objective, their use increased the 
likelihood that test results would be interpreted in different ways 
and might even be misunderstood. As part of our ongoing review of 
missile defense testing, we are examining the need for improvements in 
test reporting. 

Appendix I provides details on the test and the information disclosed. 

Project Office Reliance on Various Sources for Contractor Oversight: 

The Ground Based Interceptor Project Management Office relied on an on-
site engineer and Nichols Research Corporation to provide insight into 
Boeing's work. The project office also relied on Boeing to oversee the 
performance of its subcontractor, TRW. Oversight was limited by the 
ongoing competition between Boeing and another contractor competing 
for the exoatmospheric kill vehicle contract because the Ground Based 
Interceptor Project Management Office and its support contractors had 
to be careful not to affect competition by assisting one contractor 
more than another. Project officials said that they relied more on 
"insight" into the contractors' work rather than oversight of that 
work. Nichols gained program insight by attending technical meetings, 
assessing test reports, and sometimes evaluating technologies proposed 
by Boeing and TRW. 

For more information on how the project office exercised oversight 
over its contractors' technical performance, see appendix II. 
 
Distinguishable Differences in Objects Deployed in Space: 

Boeing and TRW reported that post-flight testing and analysis of data 
collected during Integrated Flight Test 1A showed that deployed target 
objects displayed distinguishable features when observed by an 
infrared sensor. The contractors reported the test also showed that 
Boeing's exoatmospheric kill vehicle sensor could collect target 
signals from which TRW's software could extract distinguishable 
features and that the software could identify the mock warhead from 
other objects by comparing the extracted features to the features that 
it had been told to expect each object to display. However, there has 
been no independent verification of these claims. 

We talked with Dr. Mike Munn, who was, during the 1980s, the Chief 
Scientist for missile defense programs at Lockheed Missiles and Space 
Company. He agreed that a warhead and decoys deployed in the 
exoatmosphere likely display distinguishable differences in the 
infrared spectrum. However, the differences may not be fully 
understood or there may not presently be methods to predict the 
differences. Dr. Munn added that the key was in the ability to make 
both accurate and precise measurements and also to predict signatures 
accurately. He emphasized that robust discrimination depends on the 
ability to predict signatures and then to match in-space measurements 
with those predictions. The Phase One Engineering Team and Nichols 
Research Corporation have noted that TRW's software used prior 
knowledge of warhead and decoy differences, to the maximum extent 
available, to discriminate one object from the other and cautioned 
such knowledge may not always be available in the real world. 

Decoy Reduction in Later Tests: 

National Missile Defense program officials said that after 
considerable debate among themselves and contractors, the program 
manager reduced the number of decoys planned for intercept flight 
tests in response to a recommendation by an independent panel, known 
as the Welch Panel.[Footnote 15] The panel, established to reduce risk 
in ballistic missile defense flight test programs, viewed a successful 
hit-to-kill engagement as a difficult task that should not be further 
complicated in early tests by the addition of decoys. After 
contemplating the advice of the Welch panel and considering the 
opinions of program officials and contractors who disagreed over the 
number and complexity of decoys that should be deployed in future 
tests, the program manager decided that early tests should include 
only one decoy, a large balloon. 

See appendix III for more information on the reduction of decoys in 
later tests. 

Evaluation of TRW's Discrimination Software: 

The Phase One Engineering Team was tasked by the National Missile 
Defense Joint Program Office to assess the performance of TRW's 
software and to complete the assessment within 2 months using 
available data. The team's methodology included determining if TRW's 
software was based on sound mathematical, engineering, and scientific 
principles and testing the software's critical modules using data from 
Integrated Flight Test 1A. 

The team reported that although the software had weaknesses, it was 
well designed and worked properly, with only some changes needed to 
increase the robustness of the discrimination function. Further, the 
team reported that the results of its test of the software using 
Integrated Flight Test 1A data produced essentially the same results 
as those reported by TRW. Based on its analysis, team members 
predicted that the software would perform successfully in a future 
intercept test if target objects deployed as expected. 

Because the Phase One Engineering Team did not process the raw data 
from Integrated Flight Test 1A or develop its own reference data, the 
team cannot be said to have definitively proved or disproved TRW's 
claim that its software successfully discriminated the mock warhead 
from decoys using data collected from Integrated Flight Test 1A. A 
team member told us its use of Boeing- and TRW-provided data was 
appropriate because the former TRW employee had not alleged that the 
contractors tampered with the raw test data or used inappropriate 
reference data. 

 Appendix IV provides additional details on the Phase One Engineering 
Team evaluation. 
 
Agency Comments and Our Evaluation: 

In commenting on a draft of this report, the Department of Defense 
concurred with our findings. It also suggested technical changes, 
which we incorporated as appropriate. The Department's comments are 
reprinted in appendix VII. 

We conducted our review from August 2000 through February 2002 in 
accordance with generally accepted government auditing standards. 
Appendix VI provides details on our scope and methodology. The 
National Missile Defense Joint Program Office's process for releasing 
documents significantly slowed our work. For example, the program 
office took approximately 4 months to release key documents such as 
the Phase One Engineering Team's response to the professor's 
allegations. We requested these and other documents on September 14, 
2000, and received them on January 9, 2001. 

As arranged with your staff, unless you publicly announce its contents 
earlier, we plan no further distribution of this report until 30 days 
from its issue date. At that time, we plan to provide copies of this 
report to the Chairmen and Ranking Minority Members of the Senate 
Committee on Armed Services; the Senate Committee on Appropriations, 
Subcommittee on Defense; the House Committee on Armed Services; and 
the House Committee on Appropriations, Subcommittee on Defense; and 
the Secretary of Defense; and the Director, Missile Defense Agency. We 
will make copies available to others upon request. 

If you or your staff have any questions concerning this report, please 
contact Bob Levin, Director, Acquisition and Sourcing Management, on 
(202) 512-4841; Jack Brock, Managing Director, on (202) 512-4841; or
Keith Rhodes, Chief Technologist, on (202) 512-6412. Major 
contributors to this report are listed in appendix VIII. 

Sincerely yours, 

Signed by: 

Jack L. Brock, Jr.
Managing Director: 
Acquisition and Sourcing Management: 

Signed by: 

Keith Rhodes: 
Chief Technologist: 
Applied Research and Methods: 

[End of section] 

Appendix I: Disclosure of Flight Test's Key Results and Limitations: 

Boeing and TRW disclosed the key results and limitations of an early 
sensor flight test, known as Integrated Flight Test 1A, to the Ground 
Based Interceptor Project Management Office. The contractors included 
some key results and limitations in written reports submitted soon 
after the June 1997 test, but others were not included in written 
reports until December 1997 or April 1998. However, according to 
project office and Nichols officials, all problems and limitations 
included in the written reports were communicated orally to the 
project management office in late August 1997. The deputy project 
office manager said his office did not report these verbal 
communications to others within the Program Office or the Department 
of Defense because the project office was the office within the 
Department responsible for the Boeing contract. 

One problem that was included in initial reports to program officials 
was a malfunctioning cooling mechanism that did not lower the sensor's 
temperature to the desired level. Boeing characterized the mechanism's 
performance as somewhat below expectations but functioning well enough 
for the sensor's operation. We hired experts to determine the extent 
to which the problem could affect the sensor's performance. The 
experts found that the cooling problem degraded the sensor's 
performance in a number of ways, but would not likely result in 
extreme performance degradation. The experts studied only how 
increased noise[Footnote 16] affected the sensor's performance 
regarding comparative strengths of the target signals and the noise 
(signal to noise ratio). The experts did not evaluate discrimination 
performance, which is dependent on the measurement accuracy of the 
collected infrared signals. The experts' findings are discussed in 
more detail later in this appendix. 

The Test: 

Integrated Flight Test 1A, conducted in June 1997, was a test of the 
Boeing sensor—a highly sensitive, compact, infrared device, consisting 
of an array of silicon detectors, that is normally mounted on the 
exoatmospheric kill vehicle. However, in this test, a surrogate launch 
vehicle carried the sensor above the earth's atmosphere to view a 
cluster of target objects that included a mock warhead and various 
decoys. When the sensor detected the target cluster, its silicon 
detectors began to make precise measurements of the infrared radiation 
emitted by the target objects. Over the tens of seconds that the 
target objects were within its field of view, the sensor continuously 
converted the infrared radiation into an electrical current, or 
signal, proportional to the amount of energy collected by the 
detectors. The sensor then digitized the signal (converted the signals 
into numerical values), completed a preliminary part of the planned 
signal processing, and formatted the signal so that it could be 
transmitted via a data link to a recorder on the ground. After the 
test, Boeing processed the signals further[Footnote 17] and formatted 
them so that TRW could input the signals into its discrimination 
software to assess its capability to distinguish the mock warhead from 
decoys. In post-flight ground testing, the software analyzed the 
processed data and identified the key characteristics, or features, of 
each signal. The software then compared the features it extracted to 
the expected features of various types of target objects. Based on 
this comparison, the software ranked each item according to its 
likelihood of being the mock warhead. TRW reported that the highest-
ranked object was the mock warhead. 

The primary objective of Integrated Flight Test 1A was to reduce risk 
in future flight tests. Specifically, the test was designed to 
determine if the sensor could operate in space; to examine the extent 
to which the sensor could detect small differences in infrared 
emissions; to determine if the sensor was accurately calibrated; and 
to collect target signature3[Footnote 18] data for post-mission 
discrimination analysis. In addition, Boeing established quantitative 
requirements for the test.[Footnote 19] For example, the sensor was 
expected to acquire the target objects at a specified distance. 
According to a Nichols' engineer, Boeing established these 
requirements to ensure that its exoatmospheric kill vehicle, when 
fully developed, could destroy a warhead with the single shot 
precision (expressed as a probability) required by the Ground Based 
Interceptor Project Management Office. The engineer said that in 
Integrated Flight Test IA, Boeing planned to measure its sensor's 
performance against these lower-level requirements so that
Boeing engineers could determine which sensor elements, including the 
software, required further refinement. However, the engineer told us 
that because of the various sensor problems, of which the contractor 
and project office were aware, Boeing determined before the test that 
it would not use most of these requirements to judge the sensor's 
performance. (Although Boeing did not judge the performance of its 
sensor against the requirements as it originally planned, Boeing did, 
in some cases, report the sensor's performance in terms of these 
requirements. For a summary of selected test requirements and the 
sensor's performance as reported by Boeing and TRW in their August 22, 
1997, report, see appendix V.) 

Reported Key Results and Limitations:  

Table 1 provides details on the key results and limitations of 
Integrated Flight Test 1A that contractors disclosed in various 
written reports and briefing charts. 

Table 1: What and When Key Results and Limitations Were Included in 
Contractors' Written Reports: 

August 13, 1997, Report: 
* Detected deployed targets; 
* Target signals collected; 
* Discrimination software distinguished mock warhead from decoys. 

August 22, 1997, Report: 
* Detected deployed targets; 
* Target signals collected; 
* Discrimination software distinguished mock warhead from decoys; 
* Excellent performance of sensor payload; 
* Power supply caused noisy target signals; 
* Sensor did not cool to desired temperature; 
* High false alarm rate; 
* Slow turn-around of launch vehicle caused data loss. 

December 11, 1997, Briefing: 
* High false alarm rate; 
* Sensor did not cool to desired temperature; 
* Software confidence factor remained small for two target objects; 
* Sensor had a lower than expected probability of detection; 
* In-flight calibration of sensor was inconsistent. 

April 1, 1998, Report: 
* Failure of gap-filling modules[A]; 
* Target signals collected during selected portion of the flight 
timeline used in assessment of discrimination software; 
* Selected reference data used in assessment of discrimination 
software. 
Software significantly increased rank of one target object toward
the end of the flight. 

[A] TRW designed a gap-filling module for its discrimination software 
to replace missing or noisy portions of collected and simulated target 
signals. 

[End of table] 

Although the contractors disclosed the key results and limitations of 
the flight test in written reports and in discussions, the written 
reports described the results using some terms that were not defined. 
For example, in their August 22, 1997, report, Boeing and TRW 
described Integrated Flight Test 1A as a "success" and the performance 
of the Boeing sensor as "excellent." We asked the contractors to 
explain their use of these terms. We asked Boeing, for example, why it 
characterized its sensor's performance as "excellent" when the 
sensor's silicon detector array did not cool to the desired 
temperature, the sensor's power supply created excess noise, and the 
sensor detected numerous false targets. Boeing said that even though 
the silicon detector array operated at temperatures 20 to 30 percent 
higher than desired, the sensor produced useful data Officials said 
they knew of no other sensor that would be capable of producing any 
useful data under those conditions. Boeing officials went on to say 
that the sensor continuously produced usable, and, much of the time, 
excellent data in "real-time" during flight. In addition, officials 
said the sensor component responsible for suppressing background noise 
in the silicon detector array performed perfectly in space and the 
silicon detectors collected data in more than one wave band. Boeing 
concluded that the sensor's performance allowed the test to meet all 
mission objectives. 

Based on our review of the reports and discussions with officials in 
the Ground Based Interceptor Project Management Office and Nichols 
Research, we found that the contractors' reports, in total, contained 
information for those officials to understand the key results and 
limitations of the test. However, because terms such as "success" and 
"excellent" are qualitative and subjective rather than quantitative 
and objective, we believe their use increases the likelihood that test 
results would be interpreted in different ways and could even be 
misunderstood. As part of our ongoing review of missile defense 
testing, we are examining the need for improvements in test reporting. 

The August 13 Report: 

This report, sometimes referred to as the 45-day report, was a series 
of briefing charts. In it, contractors reported that Integrated Flight 
Test 1A achieved its principal objectives of reducing risks for 
subsequent flight tests, demonstrating the performance of the 
exoatmospheric kill vehicle's sensor, and collecting target signature 
data. In addition, the report stated that TRW's software successfully 
distinguished a mock warhead from accompanying decoys.[Footnote 20] 

The August 22 Report: 

The August 22 report, known as the 60-day report, was a lengthy 
document that disclosed much more than the August 13 report. As 
discussed in more detail below, the report explained that some sensor 
abnormalities were observed during the test, that some signals 
collected from the target objects were degraded, that the launch 
vehicle carrying the sensor into space adversely affected the sensor's 
ability to collect target signals, and that the sensor sometimes 
detected targets where there were none. These problems were all noted 
in the body of the report, but the report summary stated that review 
and analysis subsequent to the test confirmed the "excellent" 
performance and nominal operation of all sensor subsystems. 

Some Sensor Abnormalities Were Observed During the Test: 

Boeing disclosed in the report that sensor abnormalities were observed 
during the test and that the sensor experienced a higher than expected 
false alarm rate. These abnormalities were (1) a cooling mechanism 
that did not bring the sensor's silicon detectors to the intended 
operating temperature, (2) a power supply unit[Footnote 21] that 
created excess noise, and (3) software that did not function as 
designed because of the slow turnaround of the surrogate launch 
vehicle. 

In the report's summary, Boeing characterized the cooling mechanism's 
performance as somewhat below expectations but functioning well enough 
for the sensor's operation. In the body of the report, Boeing said 
that the fluctuations in temperature could lead to an apparent 
decrease in sensor performance. Additionally, Boeing engineers told us 
that the cooling mechanism's failure to bring the silicon detector 
array to the required temperature caused the detectors to be noisy. 
Because the discrimination software identifies objects as a warhead or 
a decoy by comparing the features of a target's signal with those it 
expects a warhead or decoy to display, a noisy signal may confuse the 
software. Boeing and TRW engineers said that they and program office 
officials were aware that there was a problem with the sensor's 
cooling mechanism before the test was conducted. However, Boeing 
believed that the sensor would perform adequately at higher 
temperatures. According to contractor documents, the sensor did not 
perform as well as expected, and some target signals were degraded 
more than anticipated. Boeing disclosed in the report that sensor 
abnormalities were observed during the test and that the sensor 
experienced a higher than expected false alarm rate. These 
abnormalities were (1) a cooling mechanism that did not bring the 
sensor's silicon detectors to the intended operating temperature, (2) 
a power supply unit that created excess noise, and (3) software that 
did not function as designed because of the slow turnaround of the 
surrogate launch vehicle. 

In the report's summary, Boeing characterized the cooling mechanism's 
performance as somewhat below expectations but functioning well enough 
for the sensor's operation. In the body of the report, Boeing said 
that the fluctuations in temperature could lead to an apparent 
decrease in sensor performance. Additionally, Boeing engineers told us 
that the cooling mechanism's failure to bring the silicon detector 
array to the required temperature caused the detectors to be noisy. 
Because the discrimination software identifies objects as a warhead or 
a decoy by comparing the features of a target's signal with those it 
expects a warhead or decoy to display, a noisy signal may confuse the 
software. Boeing and TRW engineers said that they and program office 
officials were aware that there was a problem with the sensor's 
cooling mechanism before the test was conducted. However, Boeing 
believed that the sensor would perform adequately at higher 
temperatures. According to contractor documents, the sensor did not 
perform as well as expected, and some target signals were degraded 
more than anticipated. 

Power Supply Creates Noise: 

The report also referred to a problem with the sensor's power supply 
unit and its effect on target signals. An expert we hired to evaluate 
the sensor's performance at higher than expected temperatures found 
that the power supply, rather than the temperature, was the primary 
cause of excess noise early in the sensor's flight. Boeing engineers 
told us that they were aware that the power supply was noisy before 
the test, but, as shown by the test, it was worse than expected. 

Payload Launch Vehicle Affected Software's Ability to Remove 
Background Noise: 

The report explained that, as expected before the flight, the slow 
turnaround of the massive launch vehicle on which the sensor was 
mounted in Integrated Flight Test 1A caused the loss of some target 
signals. Engineers explained to us that the sensor would eventually be 
mounted on the lighter, more agile exoatmospheric kill vehicle, which 
would move back and forth to detect objects that did not initially 
appear in the sensor's field of view. The engineers said that Boeing 
designed software that takes into account the kill vehicle's normal 
motion to remove the background noise, but the software's 
effectiveness depended on the fast movement of the kill vehicle. 
Boeing engineers told us that, because of the slow turnaround of the 
launch vehicle used in the test, the target signals detected during 
the turnaround were particularly noisy and the software sometimes 
removed not only the noise but the entire signal as well. 

Sensor Sometimes Detected False Targets: 

The report mentioned that the sensor experienced more false alarms 
than expected. A false alarm is a detection of a target that is not 
there. According to the experts we hired, during Integrated Flight 
Test 1A, the Boeing sensor often mistakenly identified noise produced 
by the power supply as signals from actual target objects. In a fully 
automated discrimination software program, a high false alarm rate 
could overwhelm the tracking software. Because the post-flight 
processing tools were not fully developed at the time of the August 13 
and August 22, 1997, reports, Boeing did not rely upon a fully 
automated tracking system when it processed the Integrated Flight Test 
1A data. Instead, a Boeing engineer manually tracked the target 
objects. The contractors realized, and reported to the Ground Based 
Interceptor Project Management Office, that numerous false alarms 
could cause problems in future flight tests, and they identified 
software changes to reduce their occurrence. 

December 11 Briefing: 

On December 11, 1997, Boeing and TRW briefed officials from the Ground 
Based Interceptor Project Management Office and one of its support 
contractors on various anomalies observed during Integrated Flight 
Test 1A. The contractors' briefing charts explained the effect the 
anomalies could have on Integrated Flight Test 3, the first planned 
intercept test for the Boeing exoatmospheric kill vehicle, identified 
potential causes of the anomalies, and summarized the solutions to 
mitigate their effect. While some of the anomalies included in the 
December 11 briefing charts were referred to in the August 13 and 
August 22 reports, others were being reported in writing for the first 
time. 

The anomalies referenced in the briefing charts included the sensor's 
high false alarm rate, the silicon detector array's higher-than-
expected temperature, the software's low confidence factor that it had 
correctly identified two target objects correctly, the sensor's lower 
than expected probability of detection, and the software's elevation 
in rank of one target object toward the end of the test. In addition, 
the charts showed that an in-flight attempt to calibrate the sensor 
was inconsistent. According to the charts, actions to prevent similar 
anomalies from occurring or impacting Integrated Flight Test 3 had in 
most cases already been implemented or were under way. 

Contractors Report Further on False Alarms: 

The contractors again recognized that a large number of false alarms 
occurred during Integrated Flight Test 1A. According to the briefing 
charts, false alarms occurred during the slow turnarounds of the 
surrogate launch vehicle. Additionally, the contractors hypothesized 
that some false alarms resulted from space-ionizing events. By 
December 11, engineers had identified solutions to reduce the number 
of false alarms in future tests. 

Briefing Charts Include Observations on Higher Detector Array 
Temperature: 

As they had in the August 22, 1997, report, the contractors recognized 
that the silicon detector array did not cool properly during 
Integrated Flight Test 1A. The contractors reported that higher 
silicon detector array temperatures could cause noisy signals that 
would adversely impact the detector array's ability to estimate the 
infrared intensity of observed objects. Efforts to eliminate the 
impact of the higher temperatures, should they occur in future tests, 
were on-going at the time of the briefing. 

Some Software Confidence Factors Lower Than Expected: 

Contractors observed that the confidence factor produced by the 
software was small for two target objects. The software equation that 
makes a determination as to how confident the software should be to 
identify a target object correctly, did not work properly for the 
large balloon or multiple-service launch vehicle. Corrections to the 
equation had been made by the time of the briefing. 

Sensor's Probability of Detection Is Lower Than Expected: 

The charts state that the Integrated Flight Test 1A sensor had a lower 
than anticipated probability of detection and a high false alarm rate. 
Because a part of the tracking, fusion, and discrimination software 
was designed for a sensor with a high probability of detection and a 
low false alarm rate, the software did not function optimally and 
needed revision. Changes to prevent this from happening in future 
flight tests were under way. 

Software Increases the Rank of One Object Near Test's End: 

The briefing charts showed that TRW's software significantly increased 
the rank of one target object just before target objects began to 
leave the sensor's field of view. Although a later Integrated Flight 
Test 1A report stated the mock warhead was consistently ranked as the 
most likely target, the charts show that if in Integrated Flight Test 
3 the same object's rank began to increase, the software could select 
the object as the intercept target. In the briefing charts, the 
contractors reported that TRW made a software change in the model that 
is used to generate reference data. When reference data was generated 
with the software change, the importance of the mock warhead was 
increased, and it was selected as the target. Tests of the software 
change were in progress as of December 11. 

In-Flight Calibration Was Inconsistent: 

The Boeing sensor measures the infrared emissions of target objects by
converting the collected signals into intensity with the help of 
calibration data obtained from the sensor prior to flight. However, 
the sensor was not calibrated at the higher temperature range that was 
experienced during Integrated Flight Test 1A. To remedy the problem, 
the sensor viewed a star with known infrared emissions. The 
measurement of the star's intensity was to have helped fill the gaps 
in calibration data that was essential to making accurate measurements 
of the target object signals. Boeing disclosed that the corrections 
based on the star calibration were inconsistent and did not improve 
the match of calculated and measured target signatures. Boeing 
subsequently told us that the star calibration corrections were 
effective for one of the wavelength bands, but not for another, and 
that the inconsistency referred to in the briefing charts was in how 
these bands behaved at temperatures above the intended operating 
range. Efforts to find and implement solutions were in progress. 

April 1, 1998, Report: 

On April 1, 1998, Boeing submitted a revised addendum to replace an 
addendum that had accompanied the August 22, 1997, report. This 
revised addendum was prepared in response to comments and questions 
submitted by officials from the Ground Based Interceptor Project 
Management Office, Nichols Research Corporation, and the Defense 
Criminal Investigative Service concerning the August 22 report. In 
this addendum, the contractors referred in writing to three problems 
and limitations that had not been addressed in earlier written test 
reports or the December 11 briefing. Contractors noted that a gap-
filling module, which was designed to replace noisy or missing 
signals, did not operate as designed. They also disclosed that TRW's 
analysis of its discrimination software used target signals collected 
during a selected portion of the flight timeline and used a portion of 
the Integrated Flight Test 1A reference data that corresponded to this 
same timeline. 

Gap-Filling Software Module Did Not Perform As Designed: 

The April 1 addendum reported that a gap-filling module that was 
designed to replace portions of noisy or missing target signals with 
expected signal values did not operate as designed. TRW officials told 
us that the module's replacement values were too conservative and 
resulted in a poor match between collected signals and the signals the 
software expected the target objects to display. 

Assessment Uses Selected Target Signals: 

The April 1, 1998, addendum also disclosed that the August 13 and 
August 22 reports, in which TRW conveyed that its software 
successfully distinguished the mock warhead from decoys, were based on 
tests of the software using about one-third of the target signals 
collected during Integrated Flight Test 1A. We talked to TRW officials 
who told us that Boeing provided several data sets to TRW, including 
the full data set. The officials said that Boeing provided target 
signals from the entire timeline to a TRW office that was developing a 
prototype version of the exoatmospheric kill vehicle's tracking, 
fusion, and discrimination software,[Footnote 22] which was not yet 
operational. However, TRW representatives said that the test bed 
version of the software that TRW was using so that it could submit its 
analysis within 60 days of Integrated Flight Test 1A could not process 
the full data set. The officials said that shortly before the
August 22 report was issued, the prototype version of the tracking, 
fusion, and discrimination software became functional and engineers 
were able to use the software to assess the expanded set of target 
signals. According to the officials, this assessment also resulted in 
the software's selecting the mock warhead as the most likely target. 
In our review of the August 22 report, we found no analysis of the 
expanded set of target signals. The April 1, 1998, report, did include 
an analysis of a few additional seconds of data collected near the end 
of Integrated Flight Test 1A, but did not include an analysis of 
target signals collected at the beginning of the flight. 

Most of the signals that were excluded from TRW's discrimination 
analysis were collected during the early part of the flight, when the 
sensor's temperature was fluctuating. TRW told us that their software 
was designed to drop a target object's track if the tracking portion 
of the software received no data updates for a defined period. This 
design feature was meant to reduce false tracks that the software 
might establish if the sensor detected targets where there were none. 
In Integrated Flight Test 1A, the fluctuation of the sensor's 
temperature caused the loss of target signals. TRW engineers said that 
Boeing recognized that this interruption would cause TRW's software to 
stop tracking all target objects and restart the discrimination 
process. Therefore, Boeing focused its efforts on processing those 
target signals that were collected after the sensor's temperature 
stabilized and signals were collected continuously.[Footnote 23] 

Some signals collected during the last seconds of the sensor's flight 
were also excluded. The former TRW employee alleged that these latter 
signals were excluded because during this time a decoy was selected as 
the target. The Phase One Engineering Team cited one explanation for 
the exclusion of the signals. The team said that TRW stopped using 
data when objects began leaving the sensor's field of view. Our review 
did not confirm this explanation. We reviewed the target intensities 
derived from the infrared frames covering that period and found that 
several seconds of data were excluded before objects began to leave 
the field of view. Boeing officials gave us another explanation. They 
said that target signals collected during the last few seconds of the 
flight were streaking, or blurring, because the sensor was viewing the 
target objects as it flew by them. Boeing told us that streaking would 
not occur in an intercept flight because the kill vehicle would have 
continued to approach the target objects. We could not confirm that 
the test of TRW's discrimination software, as explained in the
 August 22, 1997, report, included all target signals that did not 
streak. We noted that the April 1, 1998, addendum shows that TRW 
analyzed several more seconds of target signals than is shown in the 
August 22, 1997, report. It was in these additional seconds that the 
software began to increase the rank of one decoy as it assessed which 
target object was most likely the mock warhead. However, the April 1, 
1998, addendum also shows that even though the decoy's rank increased 
the software continued to rank the mock warhead as the most likely 
target. But, because not all of the Integrated Flight Test 1A timeline 
was presented in the April 1 addendum, we could not determine whether 
any portion of the excluded timeline might have been useful data and 
if there were additional seconds of useful data whether a target 
object other than the mock warhead might have been ranked as the most 
likely target. 
 
Corresponding Portions of Reference Data Excluded: 

The April 1 addendum also documented that portions of the reference 
data developed for Integrated Flight Test 1A were also excluded from 
the discrimination analysis. Nichols and project office officials told 
us the software identifies the various target objects by comparing the 
target signals collected from each object at a given point in their 
flight to the target signals it expects each object to display at that 
same point in the flight. Therefore, when target signals collected 
during a portion of the flight timeline are excluded, reference data 
developed for the same portion of the timeline must be excluded. 

Information Provided Verbally to Project Office: 

Officials in the National Missile Defense Joint Program Office's 
Ground Based Interceptor Project Management Office and Nichols 
Research told us that soon after Integrated Flight Test 1A the 
contractors orally disclosed all of the problems and limitations cited 
in the December 11, 1997, briefing and the April 1, 1998, addendum. 
Contractors made these disclosures to project office and Nichols 
Research officials during meetings that were held to review Integrated 
Flight Test 1A results sometime in late August 1997. The project 
office and contractors could not, however, provide us with 
documentation of these disclosures. 

The current Ground Based Interceptor Project Management Office deputy 
manager said that the problems that contractors discussed with his 
office were not specifically communicated to others within the 
Department of Defense because his office was the office within the 
Department responsible for the Boeing contract. The project office's 
assessment was that these problems did not compromise the reported 
success of the mission, were similar in nature to problems normally 
found in initial developmental tests, and could be easily corrected. 

Effect of Cooling Failure on Sensor's Performance: 

Because we questioned whether Boeing's sensor could collect any usable 
target signals if the silicon detector array was not cooled to the 
desired temperature, we hired sensor experts at Utah State 
University's Space Dynamics Laboratory to determine the extent to 
which the sub-optimal cooling degraded the sensor's performance. These 
experts concluded that the higher temperature of the silicon detectors 
degraded the sensor's performance in a number of ways, but did not 
result in extreme degradation. For example, the experts said the 
higher temperature reduced by approximately 7 percent the distance at 
which the sensor could detect targets. The experts also said that the 
rapid temperature fluctuation at the beginning and at the end of data 
acquisition contributed to the number of times that the sensor 
detected a false target. However, the experts said the major cause of 
the false alarms was the power supply noise that contaminated the 
electrical signals generated by the sensor in response to the infrared 
energy. When the sensor signals were processed after Integrated Flight 
Test 1A, the noise appeared as objects, but they were actually false 
alarms. 

Additionally, the experts said that the precision with which the 
sensor could estimate the infrared energy emanating from an object 
based on the electrical signal produced by the energy was especially 
degraded in one of the sensor's two infrared wave bands. In their 
report, the experts said that the Massachusetts Institute of 
Technology's Lincoln Laboratory analyzed the precision with which the 
Boeing sensor could measure infrared radiation and found large errors 
in measurement accuracy. The Utah State experts said that their 
determination that the sensor's measurement capability was degraded in 
one infrared wave band might partially explain the errors found by 
Lincoln Laboratory. 

Although Boeing's sensor did not cool to the desired temperature during
Integrated Flight Test 1A, the experts found that an obstruction in 
gas flow rather than the sensor's design was at fault. These experts 
said the sensor's cooling mechanism was properly designed and Boeing's 
sensor design was sound. 

[End of section] 

Appendix II: Project Office Reliance on Various Sources for Contractor 
Oversight" 

The Ground Based Interceptor Project Management Office used several 
sources to monitor the contractors' technical performance, but 
oversight activities were limited by the ongoing exoatmospheric kill 
vehicle contract competition between Boeing and Raytheon. 
Specifically, the project office relied on an engineer and a System 
Engineering and Technical Analysis contractor, Nichols Research 
Corporation, to provide insight into Boeing's work. The project office 
also relied on Boeing to oversee TRW's performance. 

The deputy manager of the Ground Based Interceptor Project Management
Office told us that competition between Boeing and Raytheon limited 
oversight to some extent. He said that because of the ongoing 
competition, the project office monitored the two contractors' 
progress but was careful not to affect the competition by assisting 
one contractor more than the other. The project office primarily 
ensured that the contractors abided by their contractual requirements. 

The project office deputy manager told us that his office relied on 
"insight" into the contractors' work rather than oversight of that work.
The project office gained insight by placing an engineer on-site at 
Boeing and tasking Nichols Research Corporation to attend technical 
meetings, assess test reports, and, in some cases, evaluate Boeing's 
and TRW's technologies. The on-site engineer was responsible for 
observing the performance of Boeing and TRW and relaying any problems 
back to the project office. He did not have authority to provide 
technical direction to the contractors. According to the Ground Based 
Interceptor Project Management Office deputy manager, Nichols 
essentially "looked over the shoulder" of Boeing and TRW. We observed 
evidence of Nichols' insight in memorandums that Nichols' engineers 
submitted to the project office suggesting questions that should be 
asked of the contractors, memorandums documenting engineer's comments 
on various contractor reports, and trip reports recorded by the 
engineers after various technical meetings. 

Boeing said its oversight of TRW's work complied with contract 
requirements. The contract between the Department of Defense and
Boeing required Boeing to declare that "to the best of its knowledge 
and belief, the technical data delivered is complete, accurate, and 
complies with all requirements of the contract." With regard to 
Integrated Flight Test 1A, Boeing officials said that they complied 
with this provision by selecting a qualified subcontractor, TRW, to 
develop the discrimination concepts, software, and system design in 
support of the flight tests, and by holding weekly team meetings with 
subcontractor and project office officials. Boeing officials stated 
that they were not required to verify the validity of their 
subcontractor's flight test analyses; rather, they were only required 
to verify that the analyses seemed reasonable. According to Boeing 
officials, both they and the project office shared the belief that
TRW possessed the necessary technical expertise in threat
phenomenology modeling, discrimination, and target tracking, and both 
relied on TRW's expertise. 

[End of section] 

Appendix III: Reduced Test Complexity: 

National Missile Defense Joint Program Office officials said that they 
reduced the number of decoys planned for intercept flight tests in 
response to a recommendation by an independent panel, known as the
 Welch Panel. The panel, established to reduce risk in ballistic 
missile defense flight test programs, viewed a successful hit-to-kill 
engagement as a difficult task that should not be further complicated 
in early tests by the addition of decoys. In contemplating the panel's 
advice, the program manager discussed various target options with 
other program officials and the contractors competing to develop and 
produce the system's exoatmospheric kill vehicle. The officials 
disagreed on the number of decoys that should be deployed in the first 
intercept flight tests. Some recommended using the same target set 
deployed in Integrated Flight Test 1A and 2, while others wanted to 
eliminate some decoys. After considering the differing viewpoints, the 
program manager decided to deploy only one decoy-—a large balloon-—in 
early intercept tests. 
 
Decoys in Early Intercept Tests: 

As flight tests began in 1997, the National Missile Defense Joint 
Program Office was planning two sensor tests—-Integrated Flight Test 
1A and 2-—and 19 intercept tests. The primary objective of the sensor 
flight tests was to reduce risk in future flight tests. Specifically 
the tests were designed to determine if the sensor could operate in 
space; to examine the extent to which the sensor could detect small 
differences in infrared emissions; to determine if the sensor was 
accurately calibrated; and to collect target signature[Footnote 24] 
data for post-mission discrimination analysis. 

Initially, the next two flight tests were to demonstrate the ability 
of the competing kill vehicles to intercept a mock warhead. Integrated 
Flight Test 3 was to test the Boeing kill vehicle and Integrated 
Flight Test 4 was to test the Raytheon kill vehicle. Table 1 shows the 
number of target objects deployed in the two sensor tests, the number 
of objects originally planned to be deployed in the first two 
intercept attempts, and the number of objects actually deployed in the 
intercept attempts. 

Table 2: Planned and Actual Targets for Initial Flight Tests: 

Target suite: Mock warhead[A]; 
Actual targets in integrated flight tests 1A and 2: 1; 
Initial plan for integrated flight tests 3 and 4: 1; 
Actual targets deployed for integrated flight tests 3 and 4: 1. 

Target suite: Medium rigid light replica[B]; 
Actual targets in integrated flight tests 1A and 2: 2; 
Initial plan for integrated flight tests 3 and 4: 2; 
Actual targets deployed for integrated flight tests 3 and 4: 0. 

Target suite: Small canisterized[C] light replica; 
Actual targets in integrated flight tests 1A and 2: 1; 
Initial plan for integrated flight tests 3 and 4: 1; 
Actual targets deployed for integrated flight tests 3 and 4: 0. 

Target suite: Canisterized small balloon; 
Actual targets in integrated flight tests 1A and 2: 2; 
Initial plan for integrated flight tests 3 and 4: 2; 
Actual targets deployed for integrated flight tests 3 and 4: 0. 

Target suite: Large balloon; 
Actual targets in integrated flight tests 1A and 2: 1; 
Initial plan for integrated flight tests 3 and 4: 1; 
Actual targets deployed for integrated flight tests 3 and 4: 1. 

Target suite: Medium balloon; 
Actual targets in integrated flight tests 1A and 2: 2; 
Initial plan for integrated flight tests 3 and 4: 2; 
Actual targets deployed for integrated flight tests 3 and 4: 0. 

Target suite: Total objects; 
Actual targets in integrated flight tests 1A and 2: 9; 
Initial plan for integrated flight tests 3 and 4: 9; 
Actual targets deployed for integrated flight tests 3 and 4: 2. 

[A] The mock warhead, also known as the medium reentry vehicle, is the 
test target. Not included in this table is the multi-service launch 
system, which carries the mock warhead and all of the decoys into 
space. The launch system will likely become an object in the field of 
view of the exoatmospheric kill vehicle, like the mock warhead and 
decoys, and must be discriminated. 

[B] This is a replica of the warhead. 

[C] Decoys can be stored in canisters and released in flight. 

Source: GAO generated from Department of Defense information. 

[End of table] 

By the time Integrated Flight Tests 3 and 4 were actually conducted, 
Boeing had become the National Missile Defense Lead System Integrator 
and had selected Raytheon's exoatmospheric kill vehicle for use in the 
National Missile Defense system. Boeing conducted Integrated Flight 
Test 3 (in October 1999) and Integrated Flight Test 4 (in January 
2000) with the Raytheon kill vehicle. However, both of these flight 
tests used only the mock warhead and one large balloon, rather than 
the nine objects originally planned. Integrated Flight Test 5 (flown 
in July 2000) also used only the mock warhead and one large balloon. 

Program officials told us that the National Missile Defense Program 
Manager decided to reduce the number of decoys used in Integrated 
Flight Tests 3, 4, and 5, based on the findings of an expert panel. 
This panel, known as the Welch Panel, reviewed the flight test 
programs of several Ballistic Missile Defense Organization programs, 
including the National Missile Defense program. The resulting report,
[Footnote 25] which was released shortly after Integrated Flight Test 
2, found that U.S. ballistic missile defense programs, including the 
National Missile Defense program, had not yet demonstrated that they 
could reliably intercept a ballistic missile warhead using the 
technology known as "hit-to-kill." Numerous failures had occurred for 
several of these programs and the Welch Panel concluded that the 
National Missile Defense program (as well as other programs using "hit-
to-kill" technology) needed to demonstrate that it could reliably 
intercept simple targets before it attempted to demonstrate that it 
could hit a target accompanied by decoys. The panel reported again 1 
month after Integrated Flight Test 3[Footnote 26] and came to the same 
conclusion. 

The Director of the Ballistic Missile Defense Organization testified 
[Footnote 27] at a congressional hearing that the Welch Panel 
advocated removing all decoys from the initial flight tests, but that 
the Ballistic Missile Defense Organization opted to include a limited 
discrimination requirement with the use of one decoy. Nevertheless, he 
said that the primary purpose of the tests was to demonstrate the 
system's "hit-to-kill" capability. 

Opinions on Decoys: 

Program officials said there was disagreement within the Joint Program 
Office and among the key contractors as to how many targets to use in 
the early intercept flight tests. Raytheon and one high-ranking 
program official wanted Integrated Flight Tests 3, 4, and 5 to include 
target objects identical to those deployed in the sensor flight tests. 
Boeing and other program officials wanted to deploy fewer target 
objects. After considering all options, the Joint Program Office 
decided to deploy a mock warhead and one decoy—-a large balloon. 

Raytheon officials told us that they discussed the number of objects 
to be deployed in Integrated Flight Tests 3, 4, and 5 with program 
officials and recommended using the same target set as deployed in 
Integrated Flight Tests 1A and 2. Raytheon believed that this approach 
would be less risky because it would not require revisions to be made 
to the kill vehicle's software. Raytheon and program officials told us 
that Raytheon was confident that it could successfully identify and 
intercept the mock warhead even with this larger target set. 

One high-ranking program official said that she objected to reducing 
the number of decoys used in Integrated Flight Test 3, because there 
was a need to more completely test the system. However, other program 
officials lobbied for a smaller target set. One program official said 
that his position was based on the Welch Panel's findings and on the 
fact that the program office was not concerned at that time about 
discrimination capability. He added that the National Missile Defense 
program was responding to the threat of "nations of concern," which 
could only develop simple targets, rather than major nuclear powers, 
which were more likely to be able to deploy decoys. 

The Boeing/TRW team also wanted to reduce the number of decoys used in 
the first intercept tests. In a December 1997 study, the companies 
recommended that Integrated Flight Test 3 be conducted with a total of 
four objects—-the mock warhead, the two small balloons, and the large 
balloon. (The multi-service launch system was not counted as one of 
the objects.) The study cited concerns about the inclusion of decoys 
that were not part of the initially expected threat and about the need 
to reduce risk. Boeing said that the risk increased significantly that 
the exoatmospheric kill vehicle would not intercept the mock warhead 
if the target objects did not deploy from the test missile as expected. 

According to Boeing/TRW, as the types and number of target objects 
increased, the potential risk that the target objects would be 
different in some way from what was expected also increased. 
Specifically, the December 1997 study noted that the medium balloons 
had been in inventory for some time and had not deployed as expected 
in other tests, including Integrated Flight Test 1A. In that test, one 
medium balloon only partially inflated and was not positioned within 
the target cluster as expected. The study also found that the medium 
rigid light replicas are the easiest to misdeploy and the small 
canisterized light replica moved differently than expected during 
Integrated Flight Test 1A. 

Appendix IV: Phase One Engineering Team's Evaluation of TRW's 
Software:  

In 1998, the National Missile Defense Joint Program Office asked the 
Phase One Engineering Team to conduct an assessment, using available 
data, of TRW's discrimination software even though Nichols Research 
Corporation had already concluded that it met the requirements 
established by Boeing.[Footnote 28] The program office asked for the 
second evaluation because the Defense Criminal Investigative Service 
lead investigator was concerned about the ability of Nichols to 
provide a truly objective evaluation. 

The Phase One Engineering Team developed a methodology to (1) 
determine if TRW's software was consistent with scientific,
 mathematical, and engineering principles; (2) determine whether TRW 
accurately reported that its software successfully discriminated a 
mock warhead from decoys using data collected during Integrated Flight 
Test 1A; and (3) predict the performance of TRW's basic discrimination 
software against Integrated Flight Test 3 scenarios. The key results 
of the team's evaluation were that the software was well designed; the 
contractors accurately reported the results of Integrated Flight Test 
1A; and the software would likely perform successfully in Integrated 
Flight Test 3. The primary limitation was that the team used Boeing- 
and TRW-processed target data and TRW-developed reference data in 
determining the accuracy of TRW reports for Integrated Flight Test 1A. 
 
Phase One Engineering Team's Methodology: 

The team began its work by assuring itself that TRW's discrimination 
software was based on sound scientific, engineering, and mathematical 
principles and that those principles had been correctly implemented. 
It did this primarily by studying technical documents provided by the 
contractors and the program office. Next, the team began to look at 
the software's performance using Integrated Flight Test 1A data. The 
team studied TRW's August 13 and August 22, 1997, test reports to 
learn more about discrepancies that the Defense Criminal Investigative 
Service said it found in these reports. Team members also received 
briefings from the Defense Criminal Investigative Service, Boeing, 
TRW, and Nichols Research Corporation. 

Team members told us that they did not replicate TRW's software in 
total. Instead, the team emulated critical functions of TRW's 
discrimination software and tested those functions using data 
collected during Integrated Flight Test 1A. To test the ability of 
TRW's software to extract the features of each target object's signal, 
the team designed a software routine that mirrored TRW's feature-
extraction design. The team received Integrated Flight Test 1A target 
signals that had been processed by Boeing and then further processed 
by TRW. These signals represented about one-third of the collected 
signals. Team members input the TRW-supplied target signals into the 
team's feature-extraction software routine and extracted two features 
from each target signal. The team then compared the extracted features 
to TRW's reports on these same features and concluded that TRW's 
software-extraction process worked as reported by TRW. Next, the team 
acquired the results of 200 of the 1,000 simulations that TRW had run 
to determine the features that target objects deployed in Integrated
Flight Test 1A would likely display.[Footnote 29] Using these results, 
team members developed reference data that the software could compare 
to the features extracted from Integrated Flight Test 1A target 
signals. Finally, the team wrote software that ranked the different 
observed target objects in terms of the probability that each was the 
mock warhead. The results produced by the team's software were then 
compared to TRW's reported results. 

The team did not perform any additional analysis to predict the 
performance of the Boeing sensor and its software in Integrated Flight
Test 3. Instead, the team used the knowledge that it gained from its 
assessment of the software's performance using Integrated Flight Test 
1A data to estimate the software's performance in the third flight 
test. 

The Phase One Engineering Team's Key Results: 

In its report published on January 25, 1999, the Phase One Engineering 
Team reported that even though it noted some weaknesses, TRW's 
discrimination software was well designed and worked properly, with 
only some refinement or redesign needed to increase the robustness of 
the discrimination function. In addition, the team reported that its 
test of the software using data from Integrated Flight Test 1A 
produced essentially the same results as those reported by TRW. The 
team also predicted that the Boeing sensor and its software would 
perform well in Integrated Flight Test 3 if target objects deployed as 
expected. 

Weaknesses in TRW's Software: 

The team's assessment identified some software weaknesses. First, the
 team reported that TRW's use of a software module to replace missing 
or noisy target signals was not effective and could actually hurt 
rather than help the performance of the discrimination software. 
Second, the Phase One Engineering Team pointed out that while TRW 
proposed extracting several features from each target-object signal, 
only a few of the features could be used. 
 
The Phase One Engineering Team also reported that it found TRW's 
software to be fragile because the software was unlikely to operate 
effectively if the reference data—or expected target signals—did not 
closely match the signals that the sensor collected from deployed 
target objects. The team warned that the software's performance could 
degrade significantly if incorrect reference data were loaded into the 
software. Because developing good reference data is dependent upon 
having the correct information about target characteristics, sensor-to-
target geometry, and engagement timelines, unexpected targets might 
challenge the software. The team suggested that very good knowledge 
about all of these parameters might not always be available. 

Accuracy of Contractors' Integrated Flight Test 1A Reports: 

The Phase One Engineering Team reported that the results of its 
evaluation using Integrated Flight Test 1A data supported TRW's claim 
that in post-flight analysis its software accurately distinguished a 
mock warhead from decoys. The report stated that TRW explained why 
there were differences in the discrimination analysis included in the 
August 13, 1997, Integrated Flight Test 1A test report and that 
included in the August 22, 1997, report. According to the report, one 
difference was that TRW mislabeled a chart in the August 22 report. 
Another difference was that the August 22 discrimination analysis was 
based on target signals collected over a shorter period of time (see 
appendix I for more information regarding TRW's explanation of report 
differences). Team members said that they found TRW's explanations 
reasonable. 

Predicted Success in Integrated Flight Test 3: 

The Phase One Engineering Team predicted that if the targets deployed 
in Integrated Flight Test 3 performed as expected, TRW's 
discrimination software would successfully identify the warhead as the 
target. The team observed that the targets proposed for the flight 
test had been viewed by Boeing's sensor in Integrated Flight Test 1A 
and that target-object features collected by the sensor would be 
extremely useful in constructing reference data for the third flight 
test. The team concluded that given this prior knowledge, TRW's 
discrimination software would successfully select the correct target 
even in the most stressing Integrated Flight Test 3 scenario being 
considered, if all target objects deployed as expected. However, the 
team expressed concern about the software's capabilities if objects 
deployed differently, as had happened in previous flight tests. 

Limitations of the Team's Evaluation: 

The Phase One Engineering Team's conclusion that TRW's software 
successfully discriminated is based on the assumption that Boeing's 
and TRW's input data were accurate. The team did not process the raw 
data collected by the sensor's silicon detector array during 
Integrated Flight Test 1A or develop their own reference data by 
running hundreds of simulations. Instead, the team used target 
signature data extracted by Boeing and TRW and developed reference 
data from a portion of the simulations that TRW ran for its own post-
flight analysis. Because it did not process the raw data from 
Integrated Flight Test 1A or develop its own reference data, the team 
cannot be said to have definitively proved or disproved TRW's claim 
that its software successfully discriminated the mock warhead from 
decoys using data collected from Integrated Flight Test 1A. A team 
member told us its use of Boeing- and TRW-provided data was 
appropriate because the former TRW employee had not alleged that the 
contractors tampered with the raw test data or used inappropriate 
reference data. 

[End of section] 

Appendix V: Boeing Integrated Flight Test 1A Requirements and Actual 
Performance as Reported by Boeing and TRW:  

The table below includes selected requirements that Boeing established 
before the flight test to evaluate sensor performance and the actual 
sensor performance characteristics that Boeing and TRW discussed in 
the August 22 report.  

Table 3: Integrated Flight-Test 1A Requirements Established by Boeing 
and Actual Performance: 

Capability Tested[A]: Acquisition range[B]; 
Requirement: The sensor subsystem shall acquire the target objects at 
a specified distance; 
Integrated Flight Test 1A performance reported by Boeing/TRW: The 
performance exceeded the requirement[C]; 

Capability Tested[A]: Probability of detection; 
Requirement: The sensor shall detect target objects with a specified 
precision, which is expressed as a probability; 
Integrated Flight Test 1A performance reported by Boeing/TRW: The 
performance satisfied the requirement. 

Capability Tested[A]: False alarm rate; 
Requirement: False alarms shall not exceed a specified level; 
Integrated Flight Test 1A performance reported by Boeing/TRW: The 
performance did not satisfy the requirement. The false alarm rate 
exceeded Boeing's requirement by more than 200 to 1 because of 
problems with the power supply and the higher than expected 
temperature of the sensor. 

Capability Tested[A]: Infrared radiation measurement precision; 
Requirement: The sensor subsystem shall demonstrate a specified 
measurement precision at a specified range; 
Integrated Flight Test 1A performance reported by Boeing/TRW: The 
contractor met the requirement in one infrared measurement band, but 
not in another. 

Capability Tested[A]: Angular Measurement Precision (AMP); 
Requirement: Given specified conditions, the sensor subsystem shall 
determine the angular position of the targets with a specified angular 
measurement precision; 
Integrated Flight Test 1A performance reported by Boeing/TRW: The 
performance was better than the requirement. 

Capability Tested[A]: Closely spaced objects resolution; 
Requirement: Resolution of closely spaced objects shall be satisfied 
at a specified range; 
Integrated Flight Test 1A performance reported by Boeing/TRW: The 
closely spaced objects requirement could not be validated because the 
targets did not deploy with the required separation. 

Capability Tested[A]: Silicon detector array cool-down time; 
Requirement: The time to cool the silicon detector array to less than 
a desired temperature shall be less than or equal to a specified 
length of time; 
Integrated Flight Test 1A performance reported by Boeing/TRW: The 
performance did not satisfy the requirement because the desired 
temperature was not reached. Nevertheless, the silicon detector 
operated as designed at the higher temperatures. 

Capability Tested[A]: Hold time[D]; 
Requirement: With a certain probability, the silicon detector array's 
temperature shall be held below a desired temperature for a specified 
minimum length of time; 
Integrated Flight Test 1A performance reported by Boeing/TRW: Even 
though the detector array's temperature did not reach the desired 
temperature, the array was cooled to an acceptable operating 
temperature and held at that temperature for longer than required. 

[A] The requirements displayed in the table were established by the 
contractor and were not imposed by the government. Additionally, 
because of various sensor problems recognized prior to the test, 
Boeing waived most of the requirements. Boeing established these 
requirements to ensure that its exoatmospheric kill vehicle, when 
fully developed, could destroy a warhead with the single shot 
precision (expressed as a probability) required by the Ground Based 
Interceptor Project Management Office. 

[B] Boeing's acquisition range specification required that the 
specified range, detection probability, and false alarm rate be 
achieved simultaneously. Boeing's Chief Scientist said that because 
the range and target signals varied with time and the total 
observation time was sharply limited during Integrated Flight Test 1A, 
the probability of detection could not be accurately determined. As a 
result, the test was not a suitable means for assessing whether the 
sensor can attain the specified acquisition range. 

[C] The revised 60-day report states that the sensor did not detect 
the target until approximately two-thirds of the nominal acquisition 
range. Boeing engineers told us that while this statement appears to 
contradict the claim that the target was acquired at 107 percent of 
the specified range, it does not. Boeing engineers said that the 
nominal acquisition range refers to the range at which a sensor that 
is performing as designed would acquire the target, which is a 
substantially greater range than the specified acquisition range. 
However, neither Boeing nor TRW could provide documentation of the 
nominal acquisition range so that we could verify that these 
statements are not contradictory. 

[D] In the main body of the August 22 report, the contractor discussed 
"hold time." However, it is not mentioned in the appendix to the 
August 22 report that lists the performance characteristics against 
which Boeing planned to evaluate its sensor's performance. Rather, the 
appendix refers to a "minimum target object viewing" time, which has 
the same requirement as the hold time. Boeing reported that its sensor 
collected target signals over approximately 54 seconds. 

[End of table] 

[End of section] 

Appendix VI: Scope and Methodology: 

We determined whether Boeing and TRW disclosed key results and 
limitations of Integrated Flight Test 1A to the National Missile Defense
Joint Program Office by examining test reports submitted to the 
program office on August 13, 1997, August 22, 1997, and April 1, 1998, 
and by examining the December 11, 1997, briefing charts. We also held 
discussions with and examined various reports and documents prepared 
by Boeing North American, Anaheim, California; TRW Inc., Redondo
Beach, California; the Raytheon Company, Tucson, Arizona; Nichols
Research Corporation, Huntsville, Alabama; the Phase One Engineering
Team, Washington, D.C.; the Massachusetts Institute of
Technology/Lincoln Laboratory, Lexington, Massachusetts; the National
Missile Defense Joint Program Office, Arlington, Virginia, and 
Huntsville, Alabama; the Office of the Director, Operational Test and 
Evaluation, Washington D.C.; the U.S. Army Space and Missile Defense 
Command, Huntsville, Alabama; the Defense Criminal Investigative 
Service, Mission Viejo, California, and Arlington, Virginia; and the 
Institute for Defense Analyses, Alexandria, Virginia. 

We held discussions with and examined documents prepared by Dr.
Theodore Postol, Massachusetts Institute of Technology, Cambridge,
Massachusetts; Dr. Nira Schwartz, Torrance, California; Mr. Roy 
Danchick, Santa Monica, California; and Dr. Michael Munn, Benson, 
Arizona. 

In addition, we hired the Utah State University Space Dynamics
Laboratory, Logan, Utah, to examine the performance of the Boeing 
sensor because we needed to determine the effect the higher operating 
temperature had on the sensor's performance. We did not replicate 
TRW's assessment of its software using target signals that the Boeing 
sensor collected during the test. This would have required us to make 
engineers and computers available to verify TRW's software, format raw 
target signals for input into the software, develop reference data, 
and run the data through the software. We did not have these resources 
available, and we, therefore, cannot attest to the accuracy of TRW's 
discrimination claims. 

We also examined the methodologies, findings, and limitations of the 
review conducted by the Phase One Engineering Team of TRW's 
discrimination software. To accomplish this task, we analyzed the Phase
One Engineering Team's "Independent Review of TRW EKV Discrimination 
Techniques" dated January 1999. In addition, we held discussions with 
Phase One Engineering Team members, officials from the National 
Missile Defense Joint Program Office, and contractor officials. 

We did not replicate the evaluations conducted by the Phase One
Engineering Team and cannot attest to the accuracy of their reports. 

We reviewed the decision by the National Missile Defense Joint Program
Office to reduce the complexity of later flight tests by comparing 
actual flight test information with information in prior plans and by 
discussing these differences with program and contractor officials. We 
held discussions with and examined documents prepared by the National
Missile Defense Joint Program Office, the Institute for Defense 
Analyses, Boeing North American, and the Raytheon Company. 

Our work was conducted from August 2000 through February 2002 
according to generally accepted government auditing standards. The 
length of time the National Missile Defense Joint Program Office 
required to release documents to us significantly slowed our review. 
For example, the Program Office required approximately 4 months to 
release key documents such as the Phase One Engineering Team's 
response to the professor's allegations. We requested these and other 
documents on September 14, 2000, and received them on January 9, 2001. 

[End of section] 

Appendix VII: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
Acquisition, Technology And Logistics: 
3000 Defense Pentagon: 
Washington, DC 20301-3000: 

December 20, 2001: 

Mr. Jack L. Brock: 
Managing Director, Acquisition and Sourcing Management: 
U.S. General Accounting Office: 
Washington, D.C. 20548: 
 
Dear Mr. Brock: 
 
This is the Department of Defense (DoD) response to the General 
Accounting Office (GAO) draft report to The Honorable Edward J. 
Markey, House of Representatives, GAO-02124, "Missile Defense: Review 
of Results and Limitations of an Early National Missile Defense Flight 
Test," dated November 2001 (GAO Code 707541). The Department 
appreciates the opportunity to comment on the draft report. 

The Department concurs with the comments contained in the draft report 
(GAO did not have any recommendations) and recommends minor changes to 
the draft which will downgrade the report classification from Secret 
to Unclassified. 

Sincerely, 

Signed by: 

George R. Schneiter: 
Director: 
Strategic and Tactical Systems: 

[End of section] 

Appendix VIII: Major Contributors: 

Acquisition and Sourcing Management:  

Bob Levin, Director: 
Barbara Haynes, Assistant Director: 
Cristina Chaplain, Assistant Director, Communications: 
David Hand, Analyst-in-charge:
Subrata Ghoshroy, Technical Advisor:
Stan Lipscomb, Senior Analyst:
Terry Wyatt, Senior Analyst:
William Petrick, Analyst: 

Applied Research and Methods: 

Nabajyoti Barkakati, Senior Level Technologist: 
Hai Tran, Senior Level Technologist: 

General Counsel: 

Stephanie May, Assistant General Counsel: 

[End of section] 

Footnote: 

[1] An exoatmospheric kill vehicle is the part of a defensive missile 
that is designed to hit and destroy an incoming enemy warhead above 
the earth's atmosphere. 

[2] In some instances, the system may also use ground radar data. 

[3] The National Missile Defense Joint Program Office reports to the 
Ballistic Missile Defense Organization within the Department of 
Defense. The National Missile Defense program is now known as the 
Ground-based Midcourse Missile Defense Program and the Ballistic 
Missile Defense Organization is now the Missile Defense Agency. 

[4] A target object's signature is the set of infrared signals emitted 
by the target. 

[5] The Department of Defense continued funding the Boeing kill 
vehicle at a reduced level as a backup to Raytheon's kill vehicle. In 
mid-2000, the Department terminated all funding for Boeing's kill 
vehicle, ending TRW's involvement in development of the kill vehicle's 
discrimination software. 

[6] The Kalman Filter is a mathematical model commonly used in real 
time data processing to estimate a variable of interest, such as an 
object's position or velocity. The Extended Kalman Filter Feature 
Extractor is used to extract features, which are used to perform 
discrimination. 

[7] 31 USC 3729-3733. 

[8] Rockwell, now Boeing North American, was later added to the 
lawsuit. 

[9] Department of Justice officials told us that they often use other 
agencies' investigative units to investigate contractor fraud cases. 

[10] The Phase One Engineering Team, according to its director, was 
established in 1988 by the Strategic Defense Initiative Organization-—
later known as the Ballistic Missile Defense Organization-—as an 
umbrella mechanism to obtain technical and engineering support from
Federally Funded Research and Development Centers. To ensure that the 
scientists who work on each review undertaken by the Phase One 
Engineering Team have the requisite expertise in the subjects they are 
asked to review, the membership on each review team varies with each 
assignment. The team assembled to review TRW's software included two 
individuals from the Massachusetts Institute of Technology's Lincoln 
Laboratory, two from Lawrence Livermore National Laboratory, and one 
from the Aerospace Corporation. 

[11] In October 1996, TRW removed the Extended Kalman Filter Feature 
Extractor from its discrimination software. According to company 
officials, the Filter required computer speed and memory resources 
that were not available in the kill vehicle's onboard processor. In 
addition, the officials said that the basic discrimination software 
would perform adequately even without the Filter. 

[12] DOD Officials Acted in Accordance With Executive Order for 
Addressing Security Classification Concerns [hyperlink, 
http://www.gao.gov/products/GAO-01-737R], June 12, 2001. 

[13] Appendix V includes selected requirements that Boeing established 
before the flight test to evaluate sensor performance and the actual 
sensor performance characteristics that Boeing and TRW discussed in 
the report. 

[14] Reference data are a collection of predicted characteristics, or 
features, that target objects are expected to display during flight. 
The software identifies the warhead from the decoys by comparing the 
features displayed by the different target objects to the reference 
data. 

[15] The Welch Panel was chaired by Larry Welch, President of the 
Institute for Defense Analyses, and included 15 other members, some of 
whom were retired flag officers and former Department of Defense 
officials. 

[16] Noise is undesirable electronic energy from sources other than 
the target objects. 

[17] The signal processing that Boeing completed after the test will 
be completed onboard the exoatmospheric kill vehicle in an operational 
system. 

[18] A target object's signature is the set of infrared signals 
emitted by the target. 

[19] These requirements were established by the contractor and were 
not imposed by the government. 

[20] Boeing and TRW reported that the original test objectives did not 
include a test of TRW's discrimination software. However, program 
officials decided immediately prior to the test that it offered an 
excellent opportunity to assess the software's capability even though 
post-processing tools needed to assess the software were not yet 
available and would need rapid development after Integrated Flight 
Test 1A. 

[21] The power supply unit is designed to power the sensor's 
electronic components. 

[22] The purpose of TRW's tracking, fusion, and discrimination 
software, which was being designed to operate on-board Boeing's 
exoatmospheric kill vehicle, was to record the positions of the target 
objects as they moved through space, fuse information about the 
objects collected by ground-based radar with data collected by the 
kill vehicle's infrared sensor, and discriminate the warhead from 
decoys. The software's tracking function was not operational when the 
project office asked the contractors to determine the software's 
ability to discriminate. As a result, Boeing hand-tracked the target 
objects so that TRW could use test bed discrimination software, which 
is almost identical to the discrimination portion of the operational 
version of the tracking, fusion, and discrimination software, to 
assess the discrimination capability. 

[23] When the Ground Based Interceptor Project Management Office asked 
Boeing to assess the discrimination capability of its sensor's 
software, TRW's prototype tracking, fusion, and discrimination 
software was not operational. To perform the requested assessment, TRW 
used test-bed discrimination software that was almost identical to the 
discrimination software that TRW engineers designed for the prototype 
tracking, fusion, and discrimination software. Because the test-bed 
software did not have the ability to track targets, Boeing performed 
the tracking function and provided the tracked signals to TRW. 

[24] A target object's signature is the set of infrared signals 
emitted by the target. 

[25] Report of the Panel on Reducing Risk in Ballistic Missile Defense 
Flight Test Programs, February 27, 1998. 

[26] National Missile Defense Review, November 1999. 

[27] Statement of Lieutenant General Ronald T. Kalish, USAF, Director, 
Ballistic Missile Defense Organization, Before the House Armed 
Services Committee, Subcommittee on Military Research & Development, 
June 14, 2001. 

[28] The Ground Based Interceptor Project Management Office identified 
the precision (expressed as a probability) with which the 
exoatmospheric kill vehicle is expected to destroy a warhead with a 
single shot. To ensure that the kill vehicle would meet this 
requirement, Boeing established lower-level requirements for each 
function that affects the kill vehicle's performance, including the 
discrimination function. Nichols compared the contractor-established 
software discrimination performance requirement to the software's 
performance in simulated scenarios. 

[29] The Phase One Engineering Team reported that TRW ran 1,000 
simulations to determine the reference data for Integrated flight Test 
1A, but the Team received the results of only 200 simulations. TRW 
engineers said this was most likely to save time. Also, the engineers 
said that the only effect of developing reference data from 200 
simulations rather than 1,000 simulations is that confidence in the 
reference data drops from 98 percent to approximately 96 percent. 

[End of section] 

GAO’s Mission: 

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analysis, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO’s commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO’s Web site [hyperlink, 
http://www.gao.gov] contains abstracts and fulltext files of current 
reports and testimony and an expanding archive of older products. The 
Web site features a search engine to help you locate documents using 
key words and phrases. You can print these documents in their entirety, 
including charts and other graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as “Today’s Reports,” on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
[hyperlink, http://www.gao.gov] and select “Subscribe to daily E-mail 
alert for newly released products” under the GAO Reports heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. General Accounting Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs Contact:
Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, NelliganJ@gao.gov: 
(202) 512-4800: 
U.S. General Accounting Office: 
441 G Street NW, Room 7149:
Washington, D.C. 20548: