This is the accessible text file for GAO report number GAO-10-478T 
entitled 'Joint Strike Fighter: Significant Challenges and Decision 
Ahead' which was released on March 24, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittees on Air and Land Forces and Seapower and 
Expeditionary Forces, Committee on Armed Services, House of 
Representatives: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 2:00 p.m. EDT:
Wednesday, March 24, 2010: 

Joint Strike Fighter: 

Significant Challenges and Decision Ahead: 

Statement of Michael Sullivan, Director: 
Acquisition and Sourcing Management: 

GAO-10-478T: 

GAO Highlights: 

Highlights of GAO-10-478T, a testimony before the Subcommittees on Air 
and Land Forces and Seapower and Expeditionary Forces, Committee on 
Armed Services, U.S. House of Representatives. 

Why GAO Did This Study: 

The F-35 Lightning II, also known as the Joint Strike Fighter (JSF), 
is the Department of Defense’s (DOD) most costly and ambitious 
aircraft acquisition, seeking to simultaneously develop and field 
three aircraft variants for the Air Force, Navy, Marine Corps, and 
eight international partners. The JSF is critical for recapitalizing 
tactical air forces and will require a long-term commitment to very 
large annual funding outlays. The current estimated investment is $323 
billion to develop and procure 2,457 aircraft. 

This statement draws substantively from GAO’s March 19, 2010 report 
(GAO-10-382). That report discusses JSF costs and schedules, 
warfighter requirements, manufacturing performance, procurement rates, 
and development testing plans. This statement also provides an updated 
analysis of relative costs and benefits from a second (or alternate) 
engine program. 

In previous years, we recommended, among other things, that DOD 
rethink plans to cut test resources, improve reliability of cost 
estimates, and reduce the number of aircraft procured before testing 
demonstrates their performance capabilities. In our March 2010 report, 
we recommended that DOD (1) make a new, comprehensive assessment of 
the program’s costs and schedule and (2) reassess warfighter 
requirements. DOD concurred with both recommendations. 

What GAO Found: 

The JSF program continues to struggle with increased costs and slowed 
progress—negative outcomes that were foreseeable as events have 
unfolded over several years. Total estimated acquisition costs have 
increased $46 billion and development extended 2 ˝ more years, 
compared to the approved program baseline approved in 2007. Aircraft 
unit costs will likely exceed the thresholds established by the 
statutory provision referred to as Nunn McCurdy and may require DOD to 
recertify the need for the JSF to Congress. The program is at risk for 
not delivering aircraft quantities and capabilities on time. Dates for 
achieving initial operational capabilities may have to be extended or 
some requirements deferred to future upgrades. DOD leadership is 
taking some positive steps that should reduce risk and provide more 
realistic cost and schedule estimates. Officials increased time and 
funding for system development, added four aircraft to the flight test 
program, and reduced near-term procurement quantities. If effectively 
implemented, these actions should improve future program outcomes. 
Currently, however, manufacturing JSF test aircraft continues to take 
more time, money, and effort than budgeted, hampering the development 
flight test program. Slowed by late aircraft deliveries and low 
productivity, the flight test program only completed 10 percent of the 
sorties planned during 2009. Although restructuring actions should 
help, there is still substantial overlap of development, test, and 
production activities while DOD continues to invest in large 
quantities of production aircraft before variant designs are proven 
and performance verified. Under the current plan, DOD may procure as 
many as 307 aircraft at a total estimated cost of $58.2 billion before 
development flight testing is completed. 

Our updated analysis on engine costs shows that, without competition, 
an estimated $62.5 billion will be needed over the remainder of the 
F135 primary engine effort to cover costs for completing system 
development, procuring 2,443 engines, production support, and 
sustainment. Additional investment of between $4.5 billion to $5.7 
billion may be required should the department continue competition. 
Under certain assumptions, the additional costs of continuing the F136 
alternate engine program could be recouped if competition were to 
generate approximately 10.1 to 12.6 percent savings over the life of 
the program. Air Force data on the first 4 years of competition for 
engines on the F-16 aircraft projected they would recoup at least that 
much. Actual savings will ultimately depend on factors such as the 
number of aircraft actually purchased, the ratio of engines awarded to 
each contractor, and when the competition begins. Competition may also 
provide non-quantifiable benefits with respect to better contractor 
responsiveness, technical innovation and improved operational 
readiness. 

View [hyperlink, http://www.gao.gov/products/GAO-10-478T] or key 
components. For more information, contact Michael J. Sullivan at (202) 
512-4841or sullivanm@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

I am very pleased to be here today to discuss the F-35 Joint Strike 
Fighter (JSF) program. The JSF is the Department of Defense's (DOD) 
most costly and, arguably, its most complex and ambitious acquisition, 
seeking to simultaneously develop, produce, and field three aircraft 
variants for the Air Force, Navy, Marine Corps, and eight 
international partners. The JSF is critical to our nation's plans for 
recapitalizing the tactical air forces and will require a long-term 
commitment to very large annual funding outlays. The total expected 
U.S. investment is now more than $323 billion to develop and procure 
2,457 aircraft. 

GAO has issued annual reports on the JSF for the last 6 years. Our 
most recent report was issued last week and discussed relatively poor 
program cost and schedule outcomes and specific concerns about flight 
testing, manufacturing, and technical challenges as the program moves 
forward.[Footnote 1] A recurring theme in our work has been concern 
about what we believe is undue concurrency of development, test, and 
production activities and the heightened risks it poses to achieving 
good cost, schedule, and performance outcomes. We have also raised 
concerns about the department continuing to buy large quantities of 
low rate production aircraft on cost reimbursement contracts far in 
advance of flight and ground testing to verify the design and 
operational performance. We are pleased that defense leadership has 
lately agreed with our concerns and those of other defense offices and 
task forces. The acquisition decision memorandum, dated February 24, 
2010, directs numerous critical actions that we believe will, if 
effectively implemented, significantly improve program outcomes and 
provide more realistic projections of costs and schedule. 

Today, I will discuss (1) JSF current cost and schedule estimates and 
the significant challenges ahead as DOD substantially restructures the 
acquisition program; and (2) our updated analysis of potential costs 
and savings from pursuing a competitive engine program. This statement 
draws primarily from our March 2010 report, updated to the extent 
possible with new budget data and a recently revised procurement 
profile directed by the Secretary of Defense. To conduct this work, we 
tracked and compared current cost and schedule estimates with those of 
prior years, identified changes, and determined causes. We obtained 
program status reports, manufacturing data, and test planning 
documents. We conducted our own analyses of the information. We 
discussed results to date and future plans with DOD, JSF, and aircraft 
and engine contractor officials. We obtained information on the recent 
restructuring, including critical inputs from three independent 
defense teams established to review program execution, manufacturing 
capacity, and engine performance. For the engine cost analysis, we 
employed our methodology, first reported in 2007, updated with current 
cost and program data.[Footnote 2] A more detailed description of our 
methodology and assumptions can be found in Appendix I. We conducted 
this performance audit from May 2009 to March 2010 in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings 
and conclusions based on our audit objectives. We believe that the 
evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

Significant Challenges Remain as DOD Restructures Program: 

Continuing cost increases and schedule delays culminated in the 
extensive restructuring of the JSF program recently announced. 
Restructuring is not complete and further cost growth and schedule 
extensions are likely. Manufacturing test aircraft continues to take 
more time, money, and effort than budgeted, contributing to 
substantial flight testing delays and raising questions about the 
ability to ramp up production as rapidly and steeply as planned. There 
is still substantial overlap of development, test, and production 
activities while DOD continues to push ahead and invest in large 
quantities of production aircraft before variant designs are proven 
and system performance verified. 

Cost Increases and Schedule Delays Increase Risk of Not Meeting 
Warfighter Requirements on Time: 

The JSF program continues to struggle with increased costs and slowed 
progress--negative outcomes that were foreseeable as events have 
unfolded over several years. Total estimated acquisition costs have 
increased $46 billion and development extended 2˝ years, compared to 
the program baseline approved in 2007. DOD is now taking some positive 
steps that, if effectively implemented, should improve future outcomes 
and provide more realistic cost and schedule estimates. Officials 
increased time and funding for system development, added four aircraft 
to the flight test program, and reduced near-term procurement 
quantities by 122 aircraft. However, there is still substantial risk 
that the program will not deliver the expected number of aircraft and 
required capabilities on time. Dates for achieving initial operational 
capabilities may have to be extended or some requirements deferred to 
future upgrades. Also, aircraft unit costs will likely exceed the 
thresholds established by the statutory provision commonly referred to 
as Nunn-McCurdy[Footnote 3] and require the department to certify the 
need for the JSF to Congress. Program setbacks in costs, deliveries, 
and performance directly impact modernization plans and retirement 
schedules of the legacy aircraft the JSF is slated to replace. 

Table 1 summarizes changes in program cost, quantities, and schedules 
at key stages of acquisition. The 2004 replan estimates reflect a 
quantity reduction and a major restructuring of the program after 
integration efforts and design review identified significant weight 
problems. The 2007 data is the current approved acquisition baseline 
and the 2011 budget request reflects cost increases stemming from a 
major reassessment of the program by a joint team comprised of the 
Office of the Secretary of Defense (OSD), Air Force, and Navy 
representatives. 

Table 1: Changes in Reported JSF Program Costs, Quantities, and 
Deliveries: 

Expected quantities: Development quantities; 
October 2001 (system development start): 14; 
December 2003 (2004 Replan): 14; 
March 2007: (Approved Baseline): 15; 
Fiscal Year 2011 Budget Request: 14. 

Expected quantities: Procurement quantities (U.S. only); 
October 2001 (system development start): 2,852; 
December 2003 (2004 Replan): 2,443; 
March 2007: (Approved Baseline): 2,443; 
Fiscal Year 2011 Budget Request: 2,443. 

Total quantities; 
October 2001 (system development start): 2,866; 
December 2003 (2004 Replan): 2,457; 
March 2007: (Approved Baseline): 2,458; 
Fiscal Year 2011 Budget Request: 2,457. 

Cost estimates (then-year dollars in billions): Development; 
October 2001 (system development start): $34.4 billion; 
December 2003 (2004 Replan): $44.8 billion; 
March 2007: (Approved Baseline): $44.8 billion; 
Fiscal Year 2011 Budget Request: $49.3 billion. 

Cost estimates (then-year dollars in billions): Procurement; 
October 2001 (system development start): $196.6 billion; 
December 2003 (2004 Replan): $199.8 billion; 
March 2007: (Approved Baseline): $231.7 billion; 
Fiscal Year 2011 Budget Request: $273.3 billion. 

Total program Acquisition(see note); 
October 2001 (system development start): $231.0 billion; 
December 2003 (2004 Replan): $244.6 billion; 
March 2007: (Approved Baseline): $276.5 billion; 
Fiscal Year 2011 Budget Request: $322.6 billion. 

Unit cost estimates (then-year dollars in millions): Program 
acquisition; 
October 2001 (system development start): $81 million; 
December 2003 (2004 Replan): $100 million; 
March 2007: (Approved Baseline): $113 million; 
Fiscal Year 2011 Budget Request: $131 million. 

Unit cost estimates (then-year dollars in millions): Average 
procurement; 
October 2001 (system development start): $69 million; 
December 2003 (2004 Replan): $82 million; 
March 2007: (Approved Baseline): $95 million; 
Fiscal Year 2011 Budget Request: $112 million. 

Estimated delivery dates: First operational aircraft delivery; 
October 2001 (system development start): 2008; 
December 2003 (2004 Replan): 2009; 
March 2007: (Approved Baseline): 2010; 
Fiscal Year 2011 Budget Request: 2010. 

Estimated delivery dates: Initial operational capability; 
October 2001 (system development start): 2010-2012; 
December 2003 (2004 Replan): 2012-2013; 
March 2007: (Approved Baseline): 2012-2015; 
Fiscal Year 2011 Budget Request: 2012-2015. 

Source: GAO analysis of DOD data. 

Note: Military construction costs, typically part of total program 
acquisition costs, are not included in this table. Construction cost 
estimates for the JSF program are incomplete and have been 
inconsistently portrayed at various stages. 

[End of table] 

Table 2 shows the extension of major milestone dates for completing 
key acquisition activities. The February 2010 restructure reflects the 
direction ordered by the Secretary in an acquisition decision 
memorandum issued on February 24 and revised on March 3. Completing 
system development and approving full-rate production is now expected 
in April 2016, about 2 ˝ years later than planned in the acquisition 
program baseline approved in 2007. 

Table 2: Changes in Major Milestones: 

Major milestones: Development testing complete; 
Program of record December 2007: October 2012; 
Program of record December 2008: October 2013; 
Restructure February 2010: March 2015. 

Major milestones: Initial operational test and evaluation complete; 
Program of record December 2007: October 2013; 
Program of record December 2008: October 2014; 
Restructure February 2010: January 2016. 

Major milestones: System development and demonstration phase complete; 
Program of record December 2007: October 2013; 
Program of record December 2008: October 2014; 
Restructure February 2010: April 2016. 

Major milestones: Full-rate production decision; 
Program of record December 2007: October 2013; 
Program of record December 2008: October 2014; 
Restructure February 2010: April 2016. 

Source: GAO analysis of DOD data. 

[End of table] 

Manufacturing and Engineering Challenges Continue to Slow Aircraft 
Deliveries and Put the Production Schedule at Risk: 

Manufacturing JSF test aircraft continues to take more time, money, 
and effort than budgeted. By December 2009, only 4 of 13 test aircraft 
had been delivered and total labor hours to build the aircraft had 
increased more than 50 percent above earlier estimates. Late 
deliveries hamper the development flight test program and affect work 
on production aircraft, even as plans proceed to significantly ramp up 
annual procurement rates. Some improvement is noted, but continuing 
manufacturing inefficiencies, parts problems, and engineering 
technical changes indicate that design and production processes may 
lack the maturity needed to efficiently produce aircraft at planned 
rates. An independent manufacturing review team determined that the 
planned production ramp rate was unachievable absent significant 
improvements. While the restructuring has reduced near-term 
procurement, annual aircraft quantities are still substantial. In 
addition, the program is procuring a substantial number of low rate 
initial production (LRIP) aircraft using cost-reimbursement contracts, 
a contract type that places most of the cost risk on the government. 
Continued use of cost reimbursement contracts beyond initial LRIP 
quantities indicate that uncertainties in contract performance exist 
that do not permit costs to be estimated with sufficient accuracy for 
the contractor to assume the risk under a fixed price contract. Figure 
1 compares labor hour estimates for test aircraft in 2007 and the 
revised manufacturing plan in 2009. 

Figure 1: JSF Labor Hours for Manufacturing Test Aircraft: 

[Refer to PDF for image: multiple line graph] 

Aircraft: BF-1; 
2007 budget, labor hours: 342,647; 
2009 estimated actual hours: 341,296. 

Aircraft: BF-2; 
2007 budget, labor hours: 233,319; 
2009 estimated actual hours: 331,238. 

Aircraft: BF-3; 
2007 budget, labor hours: 179,892; 
2009 estimated actual hours: 292,318. 

Aircraft: BF-4; 
2007 budget, labor hours: 155,420; 
2009 estimated actual hours: 296,165. 

Aircraft: AF-1; 
2007 budget, labor hours: 187,781; 
2009 estimated actual hours: 288,772. 

Aircraft: AF-2; 
2007 budget, labor hours: 145,607; 
2009 estimated actual hours: 259,655. 

Aircraft: AF-3; 
2007 budget, labor hours: 130,955; 
2009 estimated actual hours: 264,973. 

Aircraft: CF-1; 
2007 budget, labor hours: 239,351; 
2009 estimated actual hours: 274,391. 

Aircraft: CF-2; 
2007 budget, labor hours: 125,602; 
2009 estimated actual hours: 228,672. 

Aircraft: CF-3v
2007 budget, labor hours: 118,153; 
2009 estimated actual hours: 200,933. 

Aircraft: BF-5; 
2007 budget, labor hours: 102,505; 
2009 estimated actual hours: 203,701. 

Aircraft: AF-4; 
2007 budget, labor hours: 91,218; 
2009 estimated actual hours: 178,723. 

Source: GAO analysis of DOD data. 

BF= Short take-off and vertical landing aircraft for the Marine Corps. 

AF= Conventional take-off and landing aircraft for the Air Force. 

CF= Carrier variant for the Navy. 

Source: GAO analysis of DOD data. 

[End of figure] 

Little Progress in Development Testing While Program Continues to Face 
Technical Challenges: 

Although DOD's restructuring actions should help, there is still 
substantial overlap of development, test, and production activities 
while DOD continues to push ahead and invest in large quantities of 
production aircraft before variant designs are proven and system 
performance verified. Given the extended development time and reduced 
near-term procurement, DOD still intends to procure up to 307 aircraft 
at an estimated cost of $58.2 billion before completing development 
flight testing by the beginning of fiscal year 2015 (see figure 2). At 
the same time, progress on flight testing is behind schedule--slowed 
by late aircraft deliveries and low productivity, the flight test 
program completed only 10 percent of the sorties planned during 2009. 
Other technical challenges include (1) relying on an extensive but 
largely unproven and unaccredited network of ground test laboratories 
and simulation models to evaluate system performance; (2) developing 
and integrating very large and complex software requirements; and (3) 
maturing several critical technologies essential to meet operational 
performance and logistical support requirements. Collectively, testing 
and technical challenges will likely add more costs and time to 
development, slowing delivery of capabilities to warfighters and 
hampering start up of pilot and maintainer training and initial 
operational testing. 

Figure 2: JSF Procurement Investments and Progress of Flight Testing: 

[Refer to PDF for image: illustrated table] 

Cumulative procurement: 
2007: $0.9 billion; 
2008: $3.6 billion; 
2009: $7.1 billion; 
2010: $14.4 billion; 
2011: $23.6 billion; 
2012: $33.2 billion; 
2013: $45.2 billion; 
2014: $58.2 billion; 
2015: $72.4 billion. 

Cumulative aircraft procured: 
2007: 2; 
2008: 14; 
2009: 28; 
2010: 58; 
2011: 101; 
2012: 146; 
2013: 217; 
2014: 307; 
2015: 420. 

Development flight testing schedule: 2007 through 2015; ongoing. 

Source: GAO analysis of DOD data. 

Note: U.S. investments only. 

[End of table] 

Updated Analysis Shows that Competition Savings Still Has Potential to 
Outweigh Costs Depending on Acquisition Approach: 

The JSF program began with an acquisition strategy that called for a 
competitive engine development effort. In the fiscal year 2007 budget 
submission, DOD stopped requesting funding for the alternate engine 
(F136). At that time, DOD determined that the risks of a single point 
failure in a sole source environment were very low and did not justify 
the extra costs to maintain a second source. Each year since then, 
Congress has subsequently recommended funding for alternate engine 
development. We have previously testified on our assessment that, 
based on past defense competitions (including a fighter engine 
competition started in the 1980s between these same manufacturers) and 
making certain assumptions about relative quantities purchased from 
each, competition could reasonably be expected to yield enough savings 
across the JSF life cycle to offset the remaining investments required 
to sustain a second source.[Footnote 4] Prior studies also indicate a 
number of nonfinancial benefits from competition, including better 
performance, increased reliability, and improved contractor 
responsiveness. 

As noted in our prior testimonies, the acquisition strategy for the 
JSF engine must weigh expected costs against potential rewards—both 
quantifiable and non quantifiable. As a result, we have updated our 
prior studies conducted in 2007, and later updated in 2008, to assess 
whether changes in the JSF program have impacted the costs and 
benefits of the sole-source and competitive scenarios for acquisition 
and sustainment of the JSF engine. We updated our analysis to include 
(1) new estimates for Research, Development, Test, and Evaluation 
(RDT&E) and additional sunk costs, (2) a slower production ramp as a 
result of the recent program restructure, (3) increased engine unit 
recurring costs, and (4) updated production support costs. Based on 
schedule delays with the program, we moved the starting point of the 
procurement competition to fiscal year 2015, a 3-year slip from our 
past analysis. This adjustment aligns with the completion of the JSF 
development flight test program and would start the competition with 
the last low-rate initial production aircraft buy. We were not 
provided information that allowed us to update operations and support 
costs. 

Our updated analysis, based largely on data provided by the JSF 
program office, found that, without competition, an estimated $62.5 
billion will be needed over the remainder of the F135 primary 
(current) engine to cover costs for completing system development, 
procuring 2,443 engines, production support, and sustainment. An 
additional investment of between $4.5 billion to $5.7 billion 
(depending on the competitive scenario) may be required should the 
department continue competition. Depending on assumptions, the 
additional costs of the alternate engine investment could be recouped 
if competition were to generate approximately 10.1 to 12.6 percent 
savings over the life of the program. Air Force data on the first 4 
years of competition for engines on the F-16 aircraft projected they 
would recoup at least that much. Actual savings will ultimately depend 
on factors such as the number of aircraft actually purchased, the 
ratio of engines awarded to each contractor, and when the competition 
begins. Competition may also provide non-quantifiable benefits with 
respect to better contractor responsiveness, technical innovation and 
improved operational readiness. Recent engine cost concerns and past 
test failures are other factors that should be considered in deciding 
whether to continue the engine competition. 

Costs of Sole Source Approach: 

Our updated analysis estimates the remaining costs for the Pratt & 
Whitney F135 engine is estimated to be $62.5 billion over the life of 
the program. This includes cost estimates for the completion of system 
development, procurement of engines, production support, and 
sustainment. Table 3 shows the costs remaining to acquire and support 
the Pratt & Whitney F135 engine on a sole-source basis in our updated 
analysis. 

Table 3: Costs to Complete Pratt & Whitney F135 Engine Program (Fiscal 
year 2002 dollars in billions): 

Cost element: System development and demonstration costs; 
Cost: $0.5 billion. 

Cost element: Total engine recurring flyaway costs; 
Cost: $24.7 billion. 

Cost element: Production support costs (including initial spares, 
training, manpower, and depot standup); 
Cost: $5.7 billion. 

Cost element: Sustainment costs of fielded aircraft; 
Cost: $31.6 billion. 

Cost element: Total; 
Cost: $62.5 billion. 

Source: JSF program office or other DOD data; GAO analysis. 

Note: Based on 2,443 installed engines and spares. 

[End of table] 

In addition to development of the F135 engine design, Pratt & Whitney 
also has responsibility for the common components that will be 
designed and developed to go on all JSF aircraft, regardless of which 
contractor provides the engine core. This responsibility supports the 
JSF program level requirement that the engine be interchangeable--
either engine can be used in any aircraft variant. In the event that 
Pratt &Whitney is made the sole-source engine provider, future 
configuration changes to the aircraft and common components could be 
optimized for the F135 engine. 

Additional Costs of Competition: 

Our updated analysis estimated the additional costs under two 
competitive scenarios; one in which contractors are each awarded 50 
percent of the total engine purchases (50/50 split) and one in which 
there is an annual 70/30 percent award split of total engine purchases 
to either contractor, beginning in fiscal year 2015. Without 
consideration of potential savings, the additional costs of 
competition total about $5.7 billion under the first scenario and 
about $4.5 billion under the second scenario. Table 4 shows the 
additional cost associated with competition under these two scenarios. 

Table 4: Additional Costs for Competition in JSF Engine Program 
(Fiscal year 2002 dollars in billions): 

Additional costs: System development and demonstration costs; 
50/50 Aircraft award split: $1.3 billion; 
70/30 Aircraft award split: $1.3 billion. 

Additional costs: Total engine recurring flyaway costs; 
50/50 Aircraft award split: $4.3 billion; 
70/30 Aircraft award split: $3.1 billion. 

Additional costs: Production support costs (including initial spares, 
training, manpower, and depot standup); 
50/50 Aircraft award split: $0.1 billion; 
70/30 Aircraft award split: $0.1 billion. 

Additional costs: Sustainment costs of fielded aircraft[A]; 
50/50 Aircraft award split: N/A; 
70/30 Aircraft award split: N/A. 

Additional costs: Total; 
50/50 Aircraft award split: $5.7 billion; 
70/30 Aircraft award split: $4.5 billion. 

Source: JSF program office or other DOD data; GAO analysis. 

Notes: Based on 2,443 installed engines and spares. 

[A] No additional sustainment costs were considered because the number 
of aircraft and cost per flight hour would be the same under either 
scenario. 

[End of table] 

The disparity in costs between the two competitive scenarios reflects 
the loss of learning resulting from lower production volume that is 
accounted for in the projected recurring flyaway costs used to 
construct each estimate. The other costs include approximately $1.3 
billion for remaining F136 development and $140 million in additional 
standup costs, which would be the same under either competitive 
scenario. 

Level of Savings Needed to Recoup Additional Costs Varies Based on 
Assumptions: 

Competition may incentivize the contractors to achieve more aggressive 
production learning curves, produce more reliable engines that are 
less costly to maintain, and invest additional corporate money in 
technological improvements to remain competitive. However, it is 
important to consider that many of the additional investments 
associated with competition are often made earlier in the program's 
life cycle, while much of the expected savings do not accrue for 
decades. As such, we include a net present value calculation (time 
value of money) in the analysis that, once applied, provides for a 
better estimate of program rate of return. Our analysis indicates that 
recoupment of those initial investment costs would occur at somewhere 
between 10.1 and 12.6 percent, depending on the number of engines 
awarded to each contractor. A competitive scenario, where one 
contractor receives 70 percent of the annual procurement and the other 
receives 30 percent, reaches the breakeven point at 10.1 percent 
savings. A competitive scenario where both contractors receive 50 
percent of the procurement reaches this point at 12.6 percent savings. 

The government's ability to recoup the additional investments required 
to support competition depends largely on (1) the number of aircraft 
procured,[Footnote 5] (2) the ratio that each contractor wins out of 
that total, and (3) the savings rate that competitive pressures drive. 
Another key variable is when the competition actually begins. In our 
analysis described above, we assume competition begins with the fiscal 
year 2015 buy which would be after system development flight test 
program is currently scheduled to be completed and would be the last 
low rate initial production order. However, we ran an alternative 
scenario where competition did not begin until 2017, or 2 years later. 
Such a delay would increase the level of savings needed to recoup the 
additional investments. This was primarily due to the fact that 
savings from the competition began later in the life cycle and fewer 
engines from the total 2,443 procurement would be available for 
competition. Recoupment under the assumption that competition begins 
in 2017 would occur at 11.3 to 14.1 percent savings depending on the 
scenario whether competitive buys was a 70/30 or 50/50 split between 
contractors, this is compared to 10.1 to 12.6 percent if the 
competition begins in 2015. 

Prior experience indicates that it is reasonable that competition of 
the JSF engine program could yield savings of at least that much. 
While we did not do an in-depth analysis of the competition, the 
"Great Engine War", may provide a good example of the potential 
savings achievable. The competition was between Pratt & Whitney and 
General Electric to supply military engines for the F-16 and other 
fighter aircraft programs. At that time, all engines for the F-14 and 
F-15 aircraft were being produced on a sole-source basis by Pratt & 
Whitney, which was criticized for increased procurement and 
maintenance costs, along with a general lack of responsiveness to 
government concerns about those programs. Beginning in 1983, the Air 
Force initiated a competition that resulted in significant cost 
savings in the program. For example, in the first 4 years of the 
competition, when comparing actual costs to the program's baseline 
estimate, results included: 

* Nearly 30 percent cumulative savings for acquisition costs, 

* Roughly 16 percent cumulative savings for operations and support 
costs, and: 

* Total savings of about 21 percent in overall life cycle costs. 

It is difficult to estimate the costs that would have been incurred if 
there never were a competition. However, prior to the competition, 
there was an upward trend in the expected unit costs of the F-16 
primary engine. When the alternate engine was introduced as a 
competitor, the upward trend stopped. 

Multiple Studies and Analyses Show Additional Benefits from 
Competition: 

Competition for the JSF engines may provide benefits that do not 
result in immediate financial savings, but could result in reduced 
costs or other positive outcomes over time. Our prior work, along with 
studies by DOD and others, indicated there are a number of 
nonfinancial benefits that may result from competition, including 
better performance, increased reliability, and improved contractor 
responsiveness. DOD and others have performed studies and have 
widespread concurrence as to these other benefits, including better 
engine performance, increased reliability, and improved contractor 
responsiveness. In fact, in 1998 and 2002, DOD program management 
advisory groups assessed the JSF alternate engine program and found 
the potential for significant benefits in these and other areas. While 
the benefits highlighted may be more difficult to quantify, they were 
strongly considered in an earlier recommendation to continue the 
alternate engine program. These studies concluded that the program 
would: 

* Maintain the industrial base for fighter engine technology, 

* Enhance readiness, 

* Instill contractor incentives for better performance, 

* Ensure an operational alternative if the current engine developed 
problems, and: 

* Enhance international participation. 

In the OSD Cost Analysis Improvement Group's (now Cost Assessment and 
Program Evaluation) 2007 Joint Strike Fighter Alternate Engine 
Acquisition and Independent Cost Analyses Report, it also concluded 
that there are nonfinancial benefits to competition. 

Another potential benefit of having an alternate engine program cited 
by the program management advisory group studies is the hedge against 
a catastrophic risk that a single point, systemic failure in the 
engine design could substantially affect the fighter aircraft fleet. 
Though current data indicate that it is unlikely that engine problems 
would lead to fleet wide groundings in modern aircraft, having two 
engine sources for the single-engine JSF further reduces this risk as 
it is less likely that such a problem would occur to both engine types 
at the same time. Because the JSF is expected to be the primary 
fighter aircraft in the U.S. inventory, and Pratt & Whitney will also 
be the sole-source provider of F119 engines for the F-22A aircraft, 
DOD is faced with the potential scenario where most of the fleet could 
be dependent on similar engine cores, produced by the same contractor 
in a sole-source environment. 

JSF Engine Costs and Flight Test Progress Have Not Met Expectations: 

Both the F135 and F136 have experienced cost growth and delays. The 
F135 primary engine development effort--a separate contract from the 
airframe development effort--is now estimated to cost about $7.3 
billion, about a 50 percent increase over the original contract award. 
This includes an $800 million contract cost overrun in 2008. Engine 
development cost increases primarily resulted from higher costs for 
labor and materials, supplier problems, and the rework needed to 
correct deficiencies with an engine blade during redesign. Engine 
redesigns and test problems caused slips in engine deliveries, 
according to program officials. Officials note that these late engine 
deliveries have not yet critically affected the delivery of test 
aircraft because airframe production lagged even further behind. 
However, the prime contractor has been forced to perform out-of-
station engine installations and other workarounds as a result of 
engine issues. As of January 2010, 17 of 18 F135 development flight 
test engines have been delivered, seven of which have flown. However, 
release date for short take-off and vertical landing variant has 
slipped about 21 months from 2007 plans until third quarter 2010. 

Engine procurement unit costs are higher than earlier budget 
estimates. For example, the most recent negotiated unit cost for the 
conventional take-off and landing variant is now $17.7 million--42 
percent higher than the original budget estimate of $12.5 million. 
Similarly, the unit cost for the short take-off and vertical landing 
(STOVL) engine (including lift fan and related parts) rose from $27.6 
million, to $33.4 million, a 21 percent increase. JSF program 
officials cite several reasons for the higher than budgeted unit 
costs, including configuration changes and quantity reductions. Based 
on recent data provided by the program office, the average unit costs 
projected through the end of procurement has increased by 45 to 55 
percent since 2006, depending on the variant. 

As planned, the F136 second engine development is about 3 years behind 
F135 engine development. While the time lag and funding instability 
make precise assessments more difficult, the second engine contractor 
is also facing cost and schedule challenges. Through fiscal year 2010, 
the government has invested about $2.9 billion in developing the 
second engine and DOD cost analysts estimate that about $1.6 billion 
more would be needed to complete F136 development in 2016. F136 
contractor officials told us that funding stability, engine 
affordability, and testing issues are key concerns for the program to 
go forward. According to the F136 contractor, it believes system 
development could be completed by 2014 and requires less than $1 
billion, not including other government costs. While the F136 engine 
has not yet been flown, it has experienced some delays. For example, 
its initial release for flight testing for the short take-off and 
vertical landing variant has slipped by about 21 months (about same 
length as the F135 delay) to late 2011. 

Concluding Remarks: 

The JSF is DOD's largest and most complex acquisition program and the 
linchpin of the United States and its allies' long-term plans to 
modernize tactical air forces. It will require exceptional levels of 
funding for a sustained period through 2035, competing against other 
defense and nondefense priorities for the federal discretionary 
dollar. The Department has recently taken some positive steps that, if 
effectively implemented, should improve outcomes and provide more 
realistic, executable program. However, the program will still be 
challenged to meet cost and schedule targets. To date, the Department 
does not have a full, comprehensive cost estimate for completing the 
program. Credible costs and schedules estimates are critical because 
they allow DOD management to make sound trade-off decisions against 
competing demands and allow Congress to perform oversight and hold DOD 
accountable. Because the JSF is expected to eventually make up most of 
the tactical aircraft fleet, the services should have a high degree of 
confidence in their ability to meet their initial operational 
capability requirements and to acquire JSFs in quantity so that DOD 
can plan its overall tactical aircraft force structure strategy. 
However, the Department has not yet defined reasonable expectations 
for achieving initial operational capabilities for each of the 
services given the recent restructuring. While the Department has 
lowered cost risk by reducing near term procurement quantities, there 
is still substantial overlap of development, test, and production 
activities now stretching into 2016. Constant program changes and 
turbulence have made it difficult to accurately and confidently 
measure program progress in maturing the aircraft system. Tying annual 
investments more directly to demonstrated progress in developing, 
testing, and manufacturing aircraft may be a prudent fiscal measure 
for ensuring government funds are invested wisely. 

In previous years, we recommended, among others, that DOD rethink 
plans to cut test resources, improve cost estimates, and reduce the 
number of aircraft procured before testing demonstrates their 
performance capabilities. In light of these circumstances, we 
recommended in our March 2010 JSF report that DOD (1) make a new, 
comprehensive and independent assessment of the costs and schedule to 
complete the program, including military construction, JSF-related 
expenses in other budgets, and life cycle costs; and (2) reassess 
warfighter requirements and, if necessary, defer some capabilities to 
future increments. GAO may also have a matter for congressional 
consideration to address some of the issues raised in this testimony. 

Decisions made on whether to continue the alternate engine program 
will likely have long term implications for the JSF program, 
industrial base, and fleet readiness. Expected costs must be weighed 
against potential benefits, both quantifiable and unquantifiable. Last 
year, Congress enacted legislation to help improve weapons acquisition 
outcomes. The legislation, referred to as the Weapon Systems 
Acquisition Reform Act of 2009, included a provision requiring DOD to 
ensure that the acquisition strategy for each major defense 
acquisition program includes measures to ensure competition, or the 
option of competition, throughout the life of the program. The long-
term impact on the industrial base is likely to be high given the size 
of the JSF program, international participation, and the expected 
supplier base. Depending on the assumptions made, a competitive 
environment could yield enough financial savings over the life of the 
program to offset the immediate cost of investing in competition. 
Specifically, key assumptions include the number of aircraft 
purchased, the ratio of engines each contractor wins, and savings 
competitive pressures drive. The timing of when a competition occurs 
will also have a direct bearing on the amount of savings that is 
needed to recoup the additional costs of competition. Competition 
could also provide many intangible benefits that do not result in 
immediate financial savings but could result in reduced costs or other 
positive outcomes over time. It is important that DOD and Congress 
reach an agreement on the best path forward. 

Mr. Chairman, this completes my prepared statement. I would be pleased 
to respond to any questions you or other Members of the Committee may 
have. 

For further information on this statement, please contact Michael 
Sullivan at (202) 512-4841 or sullivanm@gao.gov. Contact points for 
our Office of Congressional Relations and Public Affairs may be found 
on the last page of this statement. Individuals making key 
contributions to this statement are Bruce Fairbairn, Matt Lea, Kris 
Keener, Ridge Bowman, Charlie Shivers, Charles Perdue, and Greg 
Campbell. 

[End of section] 

Footnotes: 

[1] GAO, Joint Strike Fighter: Additional Costs and Delays Risk Not 
Meeting Warfighter Requirements on Time, [hyperlink, 
http://www.gao.gov/products/GAO-10-382] (Washington, D.C.: Mar. 19, 
2010). 

[2] For a detailed discussion on our analytical approach and 
methodology, 
see our original testimony GAO, Defense Acquisitions: Analysis of Costs 
for the Joint Strike Fighter Engine Program, GAO-07-656T (Washington, 
D.C.: March 22, 2007). 

[3] 10 U.S.C. § 2433 establishes the requirement for DOD to prepare 
unit cost reports on major defense acquisition programs or designated 
major defense subprograms. If a program exceeds cost growth thresholds 
specified in the law, this is known as a Nunn-McCurdy breach. DOD is 
required to report breaches to Congress and, in certain circumstances, 
DOD must reassess the program and submit a certification to Congress 
in order to continue the program, in accordance with 10 U.S.C. § 2433a. 

[4] GAO, Joint Strike Fighter: Strong Risk Management Essential as 
Program Enters Most Challenging Phase, [hyperlink, 
http://www.gao.gov/products/GAO-09-711T] (Washington, D.C.: May, 20, 
2009) is our most recent testimony on engine issues. 

[5] In conducting our cost analysis of the alternate engine program, 
we presented the cost of only 2,443 U.S. aircraft currently expected 
for production. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: