This is the accessible text file for GAO report number GAO-09-648T 
entitled 'Space Acquisitions: Government and Industry Partners Face 
Substantial Challenges in Developing New DOD Space Systems' which was 
released on April 30, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on Strategic Forces, Committee on Armed 
Services, House of Representatives: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 1:00 p.m. EDT:
Thursday, April 30, 2009: 

Space Acquisitions: 

Government and Industry Partners Face Substantial Challenges in 
Developing New DOD Space Systems: 

Statement of Cristina Chaplain, Director: 
Acquisition and Sourcing Management: 

GAO-09-648T: 

GAO Highlights: 

Highlights of GAO-09-648T, a testimony before the Subcommittee on 
Strategic Forces, Committee on Armed Services, House of 
Representatives. 

Why GAO Did This Study: 

Despite a growing investment in space, the majority of large-scale 
acquisition programs in the Department of Defense’s (DOD) space 
portfolio have experienced problems during the past two decades that 
have driven up cost and schedules and increased technical risks. The 
cost resulting from acquisition problems along with the ambitious 
nature of space programs have resulted in cancellations of programs 
that were expected to require investments of tens of billions of 
dollars. Along with the cost increases, many programs are experiencing 
significant schedule delays—as much as 7 years—resulting in potential 
capability gaps in areas such as positioning, navigation, and timing; 
missile warning; and weather monitoring. 

This testimony focuses on: 

* the condition of space acquisitions, 

* causal factors, 

* observations on the space industrial base, and; 

* recommendations for better positioning programs and industry for 
success. 

In preparing this testimony, GAO relied on its body of work in space 
and other programs, including previously issued GAO reports on 
assessments of individual space programs, common problems affecting 
space system acquisitions, and DOD’s acquisition policies. 

What GAO Found: 

Estimated costs for major space acquisition programs have increased by 
about $10.9 billion from initial estimates for fiscal years 2008 
through 2013. As seen in the figure below, in several cases, DOD has 
had to cut back on quantity and capability in the face of escalating 
costs. 

Figure: Total Cost Differences from Program Start to Most Recent 
Estimates: 

[Refer to PDF for image: vertical bar graph] 

Fiscal year 2009 dollars in millions. 

Program and start date: SBIRS, 1996; 
Initial estimate: $4,427; 
Most recent estimate: $12,210 (one fewer satellite and deferred 
requirement). 

Program and start date: GPS II, 2000; 
Initial estimate: $6,005; 
Most recent estimate: $7,154. 

Program and start date: WGS, 2000; 
Initial estimate: $1,152; 
Most recent estimate: $2,073 (two additional satellites). 

Program and start date: AEHF, 2001; 
Initial estimate: $6,153; 
Most recent estimate: $10,304 (one fewer satellite). 

Program and start date: NPOESS, 2002; 
Initial estimate: $6,455; 
Most recent estimate: $10,913 (fewer key sensors and two fewer 
satellites). 

Program and start date: MUOS, 2004; 
Initial estimate: $6,492; 
Most recent estimate: $6,411. 

Program and start date: GPS IIIA, 2008; 
Initial estimate: $3,807; 
Most recent estimate: $3,807. 

Source: GAO analysis of DOD data. 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning 
System, WGS = Wideband Global SATCOM, AEHF = Advanced Extremely High 
Frequency, NPOESS = National Polar-orbiting Operational Environmental 
Satellite System, and MUOS = Mobile User Objective System. 

[End of figure] 

Several causes behind the cost growth and related problems consistently 
stand out. First, DOD starts more weapon programs than it can afford, 
creating a competition for funding that encourages, among other things, 
low cost estimating and optimistic scheduling. Second, DOD has tended 
to start its space programs before it has the assurance that the 
capabilities it is pursuing can be achieved within available resources. 

GAO and others have identified a number of pressures associated with 
the contractors that develop space systems for the government that have 
hampered the acquisition process, including ambitious requirements, the 
impact of industry consolidation, and shortages of technical expertise 
in the workforce. Although DOD has taken a number of actions to address 
the problems on which GAO has reported, additional leadership and 
support are still needed to ensure that reforms that DOD has begun will 
take hold. 

View [hyperlink, http://www.gao.gov/products/GAO-09-648T] or key 
components. For more information, contact Cristina Chaplain at (202) 
512-4841 or chaplainc@gao.gov. 

[End of section] 

Madam Chairman and Members of the Subcommittee: 

I am pleased to be here today to discuss the Department of Defense's 
(DOD) space acquisitions and the space industrial base. The topic of 
today's hearing is critically important. Despite a growing investment 
in space, the majority of large-scale acquisition programs in DOD's 
space portfolio have experienced problems during the past two decades 
that have driven up cost and schedules and increased technical risks. 
The cost resulting from acquisition problems along with the ambitious 
nature of space programs have resulted in cancellations of programs 
that were expected to require investments of tens of billions of 
dollars, including the recently proposed cancellation of the 
Transformational Satellite Communications System (TSAT). Moreover, 
along with the cost increases, many programs are experiencing 
significant schedule delays--as much as 7 years--resulting in potential 
capability gaps in areas such as positioning, navigation, and timing; 
missile warning; and weather monitoring. 

My testimony today will focus on the condition of space acquisitions, 
causal factors, observations on the space industrial base, and 
recommendations for better positioning programs and industry for 
success. Many of these have been echoed by the Allard Commission, 
[Footnote 1] which studied space issues in response to a requirement in 
the John Warner National Defense Authorization Act for Fiscal Year 
2007, and by a study by the House Permanent Select Committee on 
Intelligence (HPSCI),[Footnote 2] among other groups. The two studies 
also highlighted concerns about diffuse leadership for military and 
intelligence space efforts, declining numbers of space engineering and 
technical professionals, and weaknesses in the space industrial base. 
Members of the Allard Commission were unanimous in their conviction 
that without significant improvements in the leadership and management 
of national security space programs, U.S. space preeminence will erode 
"to the extent that space ceases to provide a competitive national 
security advantage." The HPSCI reached very similar conclusions, adding 
that "a once robust partnership between the U.S. government and the 
American space industry has been weakened by years of demanding space 
programs, the exponential complexity of technology, and an inattention 
to acquisition discipline." 

Space Acquisition Problems Persist: 

Figure 1 compares original cost estimates and current cost estimates 
for the broader portfolio of major space acquisitions for fiscal years 
2008 through 2013. The wider the gap between original and current 
estimates, the fewer dollars DOD has available to invest in new 
programs. As shown in the figure, estimated costs for the major space 
acquisition programs have increased by about $10.9 billion from initial 
estimates for fiscal years 2008 through 2013. The declining investment 
in the later years is the result of the Evolved Expendable Launch 
Vehicle (EELV) program no longer being considered a major acquisition 
program and the cancellation and proposed cancellation of two 
development efforts which would have significantly increased DOD's 
major space acquisition investment. 

Figure 1: Comparison between Original Cost Estimates and Current Cost 
Estimates for Selected Major Space Acquisition Programs for Fiscal 
Years 2008 through 2013 (Fiscal year 2009 dollars in millions): 

[Refer to PDF for image: multiple line graph] 

Fiscal year: 2008; 
Original cost estimate: $2,832.97; 
Current cost estimate: $4,089.27. 

Fiscal year: 2009; 
Original cost estimate: $2,617.25; 
Current cost estimate: $4,782.13. 

Fiscal year: 2010; 
Original cost estimate: $1,888.13; 
Current cost estimate: $5,069.85. 

Fiscal year: 2011; 
Original cost estimate: $1,728.98; 
Current cost estimate: $3,514.5. 

Fiscal year: 2012; 
Original cost estimate: $1,499.27; 
Current cost estimate: $2,847.83. 

Fiscal year: 2013; 
Original cost estimate: $831.67; 
Current cost estimate: $2,074.85. 

Source: GAO analysis of DOD data. 

Note: The acquisition programs include Advanced Extremely High 
Frequency, Global Broadcast Service, Global Positioning System II, 
Global Positioning System IIIA, Mobile User Objective System, National 
Polar-orbiting Operational Environmental Satellite System, Space Based 
Infrared System, and Wideband Global SATCOM. 

[End of figure] 

Figures 2 and 3 reflect differences in total life-cycle costs and unit 
costs for satellites from the time the programs officially began to 
their most recent cost estimate. As figure 3 notes, in several cases, 
DOD has had to cut back on quantity and capability in the face of 
escalating costs. For example, two satellites and four instruments were 
deleted from National Polar-orbiting Operational Environmental 
Satellite System (NPOESS) and four sensors are expected to have fewer 
capabilities. This will reduce some planned capabilities for NPOESS as 
well as planned coverage. 

Figure 2: Differences in Total Life-Cycle Program Costs from Program 
Start and Most Recent Estimates (Fiscal year 2009 dollars in millions): 

[Refer to PDF for image: vertical bar graph] 

Program and start date: SBIRS, 1996; 
Initial estimate: $4,427; 
Most recent estimate: $12,210 (one fewer satellite and deferred 
requirement). 

Program and start date: GPS II, 2000; 
Initial estimate: $6,005; 
Most recent estimate: $7,154. 

Program and start date: WGS, 2000; 
Initial estimate: $1,152; 
Most recent estimate: $2,073 (two additional satellites). 

Program and start date: AEHF, 2001; 
Initial estimate: $6,153; 
Most recent estimate: $10,304 (one fewer satellite). 

Program and start date: NPOESS, 2002; 
Initial estimate: $6,455; 
Most recent estimate: $10,913 (fewer key sensors and two fewer 
satellites). 

Program and start date: MUOS, 2004; 
Initial estimate: $6,492; 
Most recent estimate: $6,411. 

Program and start date: GPS IIIA, 2008; 
Initial estimate: $3,807; 
Most recent estimate: $3,807. 

Source: GAO analysis of DOD data. 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning 
System, WGS = Wideband Global SATCOM, AEHF = Advanced Extremely High 
Frequency, NPOESS = National Polar-orbiting Operational Environmental 
Satellite System, and MUOS = Mobile User Objective System. 

[End of figure] 

Figure 3: Differences in Unit Costs from Program Start to Most Recent 
Estimates (Fiscal year 2009 dollars in millions): 

[Refer to PDF for image: vertical bar graph] 

Program and start date:	SBIRS, 1996; 
Initial unit cost: $885; 
Most recent unit cost: $3,052. 

Program and start date:	GPS, II 2000; 
Initial unit cost: $182; 
Most recent unit cost: $217. 

Program and start date:	WGS, 2000; 
Initial unit cost: $384; 
Most recent unit cost: $415. 

Program and start date:	AEHF, 2001; 
Initial unit cost: $1,231; 
Most recent unit cost: $2,576. 

Program and start date:	NPOESS, 2002; 
Initial unit cost: $1,076; 
Most recent unit cost: $2,728. 

Program and start date:	MUOS, 2004; 
Initial unit cost: $1,082; 
Most recent unit cost: $1,069. 

Program and start date:	GPS IIIA, 2008; 
Initial unit cost: $476; 
Most recent unit cost: $476. 

Source: GAO analysis of DOD data. 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning 
System, WGS = Wideband Global SATCOM, AEHF = Advanced Extremely High 
Frequency, NPOESS = National Polar-orbiting Operational Environmental 
Satellite System, and MUOS = Mobile User Objective System. 

[End of figure] 

Figure 4 highlights the additional estimated months needed to complete 
programs. These additional months represent time not anticipated at the 
programs' start dates. Generally, the further schedules slip, the more 
DOD is at risk of not sustaining current capabilities. For this reason, 
DOD began a follow-on system effort, known as the Third Generation 
Infrared Satellite to run in parallel with the Space Based Infrared 
System (SBIRS) program. 

Figure 4: Differences in Total Number of Months to Initial Operational 
Capability (IOC) from Program Start and Most Recent Estimates: 

[Refer to PDF for image: vertical bar graph] 

Program and start date:	SBIRS, 1996; 
Initial estimate: 86 months; 
Most recent estimate: System IOC no longer defined, but program is 
roughly 7 years behind its original delivery of the first satellite. 

Program and start date:	GPS II, 2000; 
Not applicable because of program not estimating an IOC date, but 
program is almost 3 years behind its original schedule for launch of 
the first Block IIF satellite. 

Program and start date:	WGS, 2000; 
Initial estimate: 49 months; 
Most recent estimate: 98 months. 

Program and start date:	AEHF, 2001; 
Initial estimate: 82 months; 
Most recent estimate: 141 months. 

Program and start date:	NPOESS, 2002; 
Initial estimate: 107 months; 
Most recent estimate: 128 months. 

Program and start date:	MUOS, 2004; 
Initial estimate: 66 months; 
Most recent estimate: 77 months. 

Program and start date:	GPS IIIA, 2008; 
Not applicable because of the program not estimating an IOC date. 

Source: GAO analysis of DOD data. 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning 
System, WGS = Wideband Global SATCOM, AEHF = Advanced Extremely High 
Frequency, NPOESS = National Polar-orbiting Operational Environmental 
Satellite System, and MUOS = Mobile User Objective System. 

[End of figure] 

This fiscal year, DOD launched the second Wideband Global SATCOM (WGS) 
satellite. WGS had previously been experiencing technical and other 
problems, including improperly installed fasteners and data 
transmission errors. When DOD finally resolved these issues, it 
significantly advanced capability available to warfighters. 
Additionally, the EELV program had its 23rd consecutive successful 
operational launch earlier this month. However, other major space 
programs have had setbacks. For example: 

* In September 2008, the Air Force reported a Nunn-McCurdy unit cost 
breach of the critical cost growth threshold[Footnote 3] for the 
Advanced Extremely High Frequency (AEHF) satellite because of cost 
growth brought on by technical issues, schedule delays, and increased 
costs for the procurement of a fourth AEHF satellite. The launch of the 
first satellite has slipped further by almost 2 years from November 
2008 to as late as September 2010. Further, the program office 
estimates that the fourth AEHF satellite could cost more than twice the 
third satellite because some components that are no longer manufactured 
will have to be replaced and production will have to be restarted after 
a 4-year gap. Because of these delays, initial operational capability 
has slipped 3 years--from 2010 to 2013. 

* The Mobile User Objective System (MUOS) communications satellite 
estimates an 11-month delay--from March 2010 to February 2011--in the 
delivery of on-orbit capability from the first satellite. Further, 
contractor costs for the space segment have increased about 48 percent 
because of the additional labor required to address issues related to 
satellite design complexity, satellite weight, and satellite component 
test anomalies and associated rework. Despite the contractor cost 
increases, the program has been able to remain within its baseline 
program cost estimate. 

* The Global Positioning System (GPS) IIF satellite is now expected to 
be delayed almost 3 years from its original date to November 2009. 
Also, the cost of GPS IIF is now expected to be about $1.6 billion-- 
about $870 million over the original cost estimate of $729 million. 
(This approximately 119 percent cost increase is not that noticeable in 
figures 2 and 3 because the GPS II modernization program includes the 
development and procurement of 33 satellites, only 12 of which are IIF 
satellites.) The Air Force has had difficulty in the past building GPS 
satellites within cost and schedule goals because of significant 
technical problems, which still threaten its delivery schedule and 
because of challenges it faced with a different contractor for the IIF 
program, which did not possess the same expertise as the previous GPS 
contractor. Further, while the Air Force is structuring the new GPS 
IIIA program to prevent mistakes made on the IIF program, the Air Force 
is aiming to deploy the GPS IIIA satellites 3 years faster than the IIF 
satellites. We believe the IIIA schedule is optimistic given the 
program's late start, past trends in space acquisitions, and challenges 
facing the new contractor. 

* Total program cost for the SBIRS program is estimated around $12.2 
billion, an increase of $7.5 billion over the original program cost, 
which included 5 geosynchronous earth orbit (GEO) satellites. The first 
GEO satellite has been delayed roughly 7 years in part because of poor 
oversight, technical complexities, and rework. Although the program 
office set December 2009 as the new launch goal for the satellite, a 
recent assessment by the Defense Contract Management Agency anticipates 
an August 2010 launch date, adding an additional 8 months to the 
previous launch estimate. Subsequent GEO satellites have also slipped 
as a result of the flight software design issues. 

* The NPOESS program has experienced problems with replenishing its 
aging constellation of satellites and was restructured in July 2007 in 
response to a Nunn-McCurdy unit cost breach of the critical cost growth 
threshold. The program was originally estimated to cost about $6.5 
billion for six satellites from 1995 through 2018. The restructured 
program called for reducing the number of satellites from six to four 
and included an overall increase in program costs, delays in satellite 
launches, and deletions or replacements of satellite sensors. Although 
the number of satellites has been reduced, total costs have increased 
by almost 108 percent since program start. Specifically, the current 
estimated life cycle cost of the restructured program is now about 
$13.5 billion for four satellites through 2026. This amount is higher 
than what is reflected in figure 2 as it represents the most recent GAO 
estimate as opposed to the DOD estimates used in the figure. We 
reported last year that poor workmanship and testing delays caused an 8-
month slip in the delivery of a complex imaging sensor. This late 
delivery caused a delay in the expected launch date of a demonstration 
satellite, moving it from late September 2009 to early January 2011. 

This year it is also becoming more apparent that space acquisition 
problems are leading to potential gaps in the delivery of critical 
capabilities. For example, DOD faces a potential gap in protected 
military communications caused by delays in the AEHF program and the 
proposed cancellation of the TSAT program, which itself posed risks in 
schedule delays because of TSAT's complexity and funding cuts designed 
to ensure technology objectives were achievable. DOD faces a potential 
gap in ultra high frequency (UHF) communications capability caused by 
the unexpected failures of two satellites already in orbit and the 
delays resulting from the MUOS program. DOD also faces potential gaps 
or decreases in positioning, navigation and timing capabilities because 
of late delivery of the GPS IIF satellites and the late start of the 
GPS IIIA program. There are also concerns about potential gaps in 
missile warning and weather monitoring capabilities because of delays 
in SBIRS and NPOESS. 

Addressing gaps in any one of these areas is not a simple matter. While 
there may be opportunities to build less complex "gap filler" 
satellites, for example, these still require time and money that may 
not be readily available because of commitments to the longer-term 
programs. There may also be opportunities to continue production of 
"older" generation satellites, but such efforts also require time and 
money that may not be readily available and may face other challenges 
such as restarting production lines and addressing issues related to 
obsolete parts and materials. Further, satellites on orbit can be made 
to last longer by turning power off at certain points in time, but this 
may also present unacceptable tradeoffs in capability. 

Underlying Reasons for Cost and Schedule Growth: 

Our past work has identified a number of causes behind the cost growth 
and related problems, but several consistently stand out. First, on a 
broad scale, DOD starts more weapon programs than it can afford, 
creating a competition for funding that encourages low cost estimating, 
optimistic scheduling, overpromising, suppressing bad news, and, for 
space programs, forsaking the opportunity to identify and assess 
potentially more executable alternatives. Programs focus on advocacy at 
the expense of realism and sound management. Invariably, with too many 
programs in its portfolio, DOD is forced to continually shift funds to 
and from programs--particularly as programs experience problems that 
require additional time and money to address. Such shifts, in turn, 
have had costly, reverberating effects. 

Second, DOD has tended to start its space programs too early, that is, 
before it has the assurance that the capabilities it is pursuing can be 
achieved within available resources and time constraints. This tendency 
is caused largely by the funding process, since acquisition programs 
attract more dollars than efforts concentrating solely on proving 
technologies. Nevertheless, when DOD chooses to extend technology 
invention into acquisition, programs experience technical problems that 
require large amounts of time and money to fix. Moreover, when this 
approach is followed, cost estimators are not well positioned to 
develop accurate cost estimates because there are too many unknowns. 
Put more simply, there is no way to accurately estimate how long it 
would take to design, develop, and build a satellite system when 
critical technologies planned for that system are still in relatively 
early stages of discovery and invention. 

While our work has consistently found that maturing technologies before 
program start is a critical enabler of success, it is important to keep 
in mind that this is not the only solution. Both the TSAT and the Space 
Radar development efforts, for example, were seeking to mature critical 
technologies before program start, but they faced other risks related 
to the systems' complexity, affordability, and other development 
challenges. Ultimately, Space Radar was canceled and DOD has proposed 
the cancellation of TSAT. Last year, we cited the MUOS program's 
attempts to mature critical technologies before program start as a best 
practice, but the program has since encountered technical problems 
related to design issues and test anomalies. 

Third, programs have historically attempted to satisfy all requirements 
in a single step, regardless of the design challenge or the maturity of 
the technologies necessary to achieve the full capability. DOD has 
preferred to make fewer but heavier, larger, and more complex 
satellites that perform a multitude of missions rather than larger 
constellations of smaller, less complex satellites that gradually 
increase in sophistication. This has stretched technology challenges 
beyond current capabilities in some cases and vastly increased the 
complexities related to software. Programs also seek to maximize 
capability because it is expensive to launch satellites. A launch using 
a medium-or intermediate-lift evolved expendable launch vehicle, for 
example, would cost roughly $65 million. 

Fourth, several of today's high-risk space programs began in the late 
1990s, when DOD structured contracts in a way that reduced government 
oversight and shifted key decision-making responsibility onto 
contractors. This approach--known as Total System Performance 
Responsibility, or TSPR--was intended to facilitate acquisition reform 
and enable DOD to streamline its acquisition process and leverage 
innovation and management expertise from the private sector. 
Specifically, TSPR gave a contractor total responsibility for the 
integration of an entire weapon system and for meeting DOD's 
requirements. However, because this reform made the contractor 
responsible for day-to-day program management, DOD did not require 
formal deliverable documents--such as earned value management reports-
-to assess the status and performance of the contractor. The resulting 
erosion of DOD's capability to lead and manage the space acquisition 
process magnified problems related to requirements creep and poor 
contractor performance. Further, the reduction in government oversight 
and involvement led to major reductions in various government 
capabilities, including cost-estimating and systems-engineering staff. 
The loss of cost-estimating and systems-engineering staff in turn led 
to a lack of technical data needed to develop sound cost estimates. 

Observations on the Space Industrial Base: 

We have not performed a comprehensive review of the space industrial 
base, but our prior work has identified a number of pressures 
associated with contractors that develop space systems for the 
government that have hampered the acquisition process. Many of these 
have been echoed in other studies conducted by DOD and congressionally 
chartered commissions. 

We and others have reported that industry--including both prime 
contractors and subcontractors--has been consolidated to a point where 
there may be only one company that can develop a needed capability or a 
specific component for a satellite system[Footnote 4]. In the view of 
DOD and industry officials we have interviewed, this condition has 
enabled contractors to hold some programs hostage and has made it 
difficult to inject competition into space programs. We also have 
identified cases where space programs experienced unanticipated 
problems resulting from consolidations in the supplier base. For 
example, contractors took cost-cutting measures that reduced the 
quality of parts. In the case of GPS IIF, contractors lost key 
technical personnel as they consolidated development and manufacturing 
facilities, causing inefficiencies in the program. 

In addition, space contractors are facing workforce pressures similar 
to those experienced by the government, that is, there is not enough 
technical expertise to develop highly complex space systems. A number 
of studies have found that both industry and the U.S. government face 
substantial shortages of scientists and engineers and that recruitment 
of new personnel is difficult because the space industry is one of many 
sectors competing for the limited number of trained scientists and 
engineers. Security clearance requirements make competing for talented 
personnel even more difficult for military and intelligence space 
programs as opposed to civil space programs. 

In a 2006 review of space cost estimating, we also found that the 
government has made erroneous assumptions about the space industrial 
base when it started the programs that are experiencing the most 
challenges today.[Footnote 5] In a review for this subcommittee, for 
instance, we found that the original contracting concept for the EELV 
program was for the Air Force to piggyback on the anticipated launch 
demand of the commercial sector. Furthermore, the Air Force assumed 
that it would benefit financially from competition among commercial 
vendors. However, the commercial demand never materialized, and the 
government decided to bear the cost burden of maintaining the 
industrial base in order to maintain launch capability, and assumed 
savings from competition were never realized. 

Actions Needed to Address Space and Weapon Acquisition Problems: 

Over the past decade, we have identified best practices that DOD space 
programs can benefit from. DOD has taken a number of actions to address 
the problems on which we have reported. These include initiatives at 
the department level that will affect its major weapons programs, as 
well as changes in course within specific Air Force programs. Although 
these actions are a step in the right direction, additional leadership 
and support are still needed to ensure that reforms that DOD has begun 
will take hold. 

Our work--which is largely based on best practices in the commercial 
sector--has recommended numerous actions that can be taken to address 
the problems we identified. Generally, we have recommended that DOD 
separate technology discovery from acquisition, follow an incremental 
path toward meeting user needs, match resources and requirements at 
program start, and use quantifiable data and demonstrable knowledge to 
make decisions to move to next phases. We have also identified 
practices related to cost estimating, program manager tenure, quality 
assurance, technology transition, and an array of other aspects of 
acquisition program management that space programs could benefit from. 
Table 1 highlights these practices. 

Table 1: Actions Needed to Address Space and Weapon Acquisition 
Problems: 

Before undertaking new programs: 

* Prioritize investments so that projects can be fully funded and it is 
clear where projects stand in relation to the overall portfolio. 

* Follow an evolutionary path toward meeting mission needs rather than 
attempting to satisfy all needs in a single step. 

* Match requirements to resources-- that is, time, money, technology, 
and people--before undertaking a new development effort. 

* Research and define requirements before programs are started and 
limit changes after they are started. 

* Ensure that cost estimates are complete, accurate, and updated 
regularly. 

* Commit to fully fund projects before they begin. 

* Ensure that critical technologies are proven to work as intended 
before programs are started. 

* Assign more ambitious technology development efforts to research 
departments until they are ready to be added to future generations 
(increments) of a product. 

* Use systems engineering to close gaps between resources and 
requirements before launching the development process. 

During program development: 

* Use quantifiable data and demonstrable knowledge to make go/no-go 
decisions, covering critical facets of the program such as cost, 
schedule, technology readiness, design readiness, production readiness, 
and relationships with suppliers. 

* Do not allow development to proceed until certain thresholds are met--
for example, a high proportion of engineering drawings completed or 
production processes under statistical control. 

* Empower program managers to make decisions on the direction of the 
program and to resolve problems and implement solutions. 

* Hold program managers accountable for their choices. 

* Require program managers to stay with a project to its end. 

* Hold suppliers accountable to deliver high-quality parts for their 
products through such activities as regular supplier audits and 
performance evaluations of quality and delivery, among other things. 

* Encourage program managers to share bad news, and encourage 
collaboration and communication. 

Source: GAO. 

[End of table] 

Several of these practices could also benefit the space industrial 
base. For instance, applying an evolutionary approach to development 
would likely provide a steadier pipeline of government orders and thus 
enable suppliers to maintain their expertise and production lines. More 
realistic cost estimating and full funding would reduce funding 
instability, which could reduce fits and starts that create planning 
difficulties for suppliers. Longer tenure and more authority for 
program managers would provide more continuity in relationships between 
the government and its suppliers. 

DOD is attempting to implement some of these practices for its major 
weapon programs. For example, as part of its strategy for enhancing the 
roles of program managers in major weapon system acquisitions, the 
department has established a policy that requires formal agreements 
among program managers, their acquisition executives, and the user 
community that set forth common program goals. These agreements are 
intended to be binding and to detail the progress a program is expected 
to make during the year and the resources the program will be provided 
to reach these goals. DOD is also requiring program managers to sign 
tenure agreements so that their tenure will correspond to the next 
major milestone review closest to 4 years. Over the past few years, DOD 
has also been testing portfolio management approaches in selected 
capability areas--command and control, net-centric operations, 
battlespace awareness, and logistics--to facilitate more strategic 
choices for resource allocation across programs. 

Within the space community, cost estimators from industry and agencies 
involved in space have been working together to improve the accuracy 
and quality of their estimates. In addition, on specific programs, 
actions have been taken to prevent mistakes made in the past. For 
example, on the GPS IIIA program, the Air Force is using an incremental 
development approach, where it will gradually meet the needs of its 
users; using military standards for satellite quality; conducting 
multiple design reviews; exercising more government oversight and 
interaction with the contractor and spending more time at the 
contractor's site; and using an improved risk management process. On 
the SBIRS program, the Air Force acted to strengthen relationships 
between the government and the SBIRS contractor team, and to implement 
more effective software development practices as it sought to address 
problems related to the systems flight software system. 
Correspondingly, DOD's Office of the Under Secretary of Defense for 
Acquisition, Technology, and Logistics is asking space programs passing 
through milestone reviews to take specific measures to better hold 
contractors accountable through award and incentive fees, to require 
independent technology readiness assessments at particular points in 
the acquisition process, and to hold requirements stable. 

Furthermore, the Air Force, U.S. Strategic Command, and other key 
organizations have made progress in implementing the Operationally 
Responsive Space (ORS) initiative. This initiative encompasses several 
separate endeavors with a goal to provide short-term tactical 
capabilities as well as identifying and implementing long-term 
technology and design solutions to reduce the cost and time of 
developing and delivering simpler satellites in greater numbers. ORS 
provides DOD with an opportunity to work outside the typical 
acquisition channels to more quickly and less expensively deliver these 
capabilities. In 2008, we found that DOD has made progress in putting a 
program management structure in place for ORS as well as executing ORS- 
related research and development efforts, which include development of 
low-cost small satellites, common design techniques, and common 
interfaces. 

Legislation introduced in recent years has also focused on improving 
space and weapon acquisitions. In February, the Senate Committee on 
Armed Services introduced an acquisition reform bill which contains 
provisions that could significantly improve DOD's management of space 
programs. For instance, the bill focuses on increasing emphasis on 
systems engineering and developmental testing, instituting earlier 
preliminary design reviews, and strengthening independent cost 
estimates and technology readiness assessments. Taken together, these 
measures could instill more discipline in the front end of the 
acquisition process when it is critical for programs to gain knowledge. 
The bill also requires greater involvement by the combatant commands in 
determining requirements and requiring greater consultation among the 
requirements, budget, and acquisition processes. In addition, several 
of the bill's sections, as currently drafted, would require in law what 
DOD policy already calls for, but it is not being implemented 
consistently in weapon programs. Last week, the House Committee on 
Armed Services announced it would be introducing a bill to similarly 
reform DOD's system for acquiring weapons by providing for, among other 
things, oversight early in product development and for appointment of 
independent officials to review acquisition programs. However, we did 
not have time to assess the bill for this statement. 

The actions that the Air Force and Office of the Secretary of Defense 
have been taking to address acquisition problems are good steps. But, 
there are still more, significant changes to processes, policies, and 
support needed to ensure reforms can take hold. In particular, several 
studies have recently concluded that there is a need to strengthen 
leadership for military and intelligence space efforts. The Allard 
Commission reported that responsibilities for military space and 
intelligence programs are scattered across the staffs of the DOD and 
the Intelligence Community and that it appears that "no one is in 
charge" of national security space. The HPSCI expressed similar 
concerns in its report, focusing specifically on difficulties in 
bringing together decisions that would involve both the Director of 
National Intelligence and the Secretary of Defense. Prior studies, 
including those conducted by the Defense Science Board and the 
Commission to Assess United States National Security Space Management 
and Organization (Space Commission)[Footnote 6] have identified similar 
problems, both for space as a whole and for specific programs. While 
these studies have made recommendations for strengthening leadership 
for space acquisitions, no major changes to the leadership structure 
have been made in recent years. In fact, an "executive agent" position 
within the Air Force that was designated in 2001 in response to a Space 
Commission recommendation to provide leadership has not been filled 
since the last executive resigned in 2007. 

In addition, more actions may be needed to address shortages of 
personnel in program offices for major space programs. We recently 
reported that personnel shortages at the EELV program office have 
occurred particularly in highly specialized areas, such as avionics and 
launch vehicle groups. Program officials stated that 7 of 12 positions 
in the engineering branch for the Atlas group were vacant. These 
engineers work on issues such as reviewing components responsible for 
navigation and control of the rocket. Moreover, only half the 
government jobs in some key areas were projected to be filled. These 
and other shortages in the EELV program office heightened concerns 
about DOD's ability to use a cost-reimbursement contract acquisition 
strategy for EELV since that strategy required greater government 
attention to the contractor's technical, cost, and schedule performance 
information. In previous reviews, we cited personnel shortages at 
program offices for TSAT as well as for cost estimators across space. 
While increased reliance on contractor employees has helped to address 
workforce shortages, it could ultimately create gaps in areas of 
expertise that could limit the government's ability to conduct 
oversight. 

Further, while actions are being undertaken to make more realistic cost 
estimates, programs are still producing schedule estimates that are 
optimistic and promising that they will not miss their schedule goals. 
The GPS IIIA program, for example, began 9 months later than originally 
anticipated because of funding delays, but the delivery date remained 
the same. The schedule is 3 years shorter than the one achieved so far 
on GPS IIF. We recognize that the GPS IIIA program has built a more 
solid foundation for success than the IIF, which offers the best course 
to deliver on time, but setting an ambitious schedule goal should not 
be the Air Force's only measure for mitigating potential capability 
gaps. Last year, we also reported that the SBIRS program's revised 
schedule estimates for addressing software problems appeared too 
optimistic. For example, software experts, independent reviewers, as 
well as the government officials we interviewed agreed that the 
schedule was aggressive, and the Defense Contract Management Agency has 
repeatedly highlighted the schedule as high risk. 

Concluding Remarks: 

In conclusion, senior leaders managing DOD's space portfolio are 
working in a challenging environment. There are pressures to deliver 
new, transformational capabilities, but problematic older satellite 
programs continue to cost more than expected, constrain investment 
dollars, pose risks of capability caps, and thus require more time and 
attention from senior leaders than well-performing efforts. Moreover, 
military space is at a critical juncture. While there are concerns 
about the United States losing its competitive edge in the development 
of space technology, there are critical capabilities that are at risk 
of falling behind their current level of service. To best mitigate 
these circumstances and put future programs on a better path, DOD needs 
to focus foremost on sustaining current capabilities and preparing for 
potential gaps. In addition, there is still a looming question of how 
military and intelligence space activities should be organized and led. 
From an acquisition perspective, what is important is that the right 
decisions are made on individual programs, the right capability is in 
place to manage them, and there is someone to hold accountable when 
programs go off track. 

Madam Chairman, this concludes my prepared statement. I would be happy 
to answer any questions you or members of the subcommittee may have at 
this time. 

Contacts and Acknowledgments: 

For further information about this statement, please contact Cristina 
Chaplain at (202) 512-4841 or chaplainc@gao.gov. Contact points for our 
Offices of Congressional Relations and Pubic Affairs may be found on 
the last page of this statement. Individuals who made key contributions 
to this statement include Art Gallegos, Assistant Director; Greg 
Campbell; Maria Durant; Arturo Holguin; Laura Holliday; Rich Horiuchi; 
Sylvia Schatz; and Peter Zwanzig. 

[End of section] 

Appendix I: Scope and Methodology: 

In preparing this testimony, we relied on our body of work in space 
programs, including previously issued GAO reports on assessments of 
individual space programs, common problems affecting space system 
acquisitions, and the Department of Defense's (DOD) acquisition 
policies. We relied on our best practices studies, which comment on the 
persistent problems affecting space acquisitions, the actions DOD has 
been taking to address these problems, and what remains to be done. We 
also relied on work performed in support of our 2009 annual weapons 
system assessment. The individual reviews were conducted in accordance 
with generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the evidence 
obtained provides a reasonable basis for our findings and conclusions 
based on our audit objectives. 

[End of section] 

Footnotes: 

[1] Institute for Defense Analyses, Leadership, Management, and 
Organization for National Security Space: Report to Congress of the 
Independent Assessment Panel on the Organization and Management of 
National Security Space (Alexandria, VA.: July 2008). 

[2] House Permanent Select Committee on Intelligence, Report on 
Challenges and Recommendations for United States Overhead Architecture 
(Washington, D.C.: October 2008). 

[3] The Nunn-McCurdy provision (10 U.S.C. § 2433) currently requires 
DOD to take specific actions when a major defense acquisition program's 
growth exceeds certain cost thresholds. Some of the key provisions of 
the law require, for example, that for major defense acquisition 
programs, (1) Congress must be notified when a program has an increase 
of at least 15 percent in program acquisition unit cost above the unit 
cost in the current baseline estimate and (2) the Secretary of Defense 
must certify the program to Congress when the program has unit cost 
increases of at least 25 percent of the current baseline estimate or at 
least 50 percent of the original baseline estimate. 10 U.S.C. § 
2433(a)(4)(5);(d)(3);(e)(4). The current law also includes cost growth 
thresholds from the program's original baseline estimate. 10 U.S.C. § 
2433(a)(4)(5). 

[4] GAO, Defense Acquisitions: Incentives and Pressures That Drive 
Problems Affecting Satellite and Related Acquisitions. [hyperlink, 
http://www.gao.gov/products/GAO-05-570R] (Washington, D.C.: June 23, 
2005). 

[5] GAO, Space Acquisitions: DOD Needs to Take More Action to Address 
Unrealistic Initial Cost Estimates of Space Systems. [hyperlink, 
http://www.gao.gov/products/GAO-07-96] (Washington, D.C.: Nov. 17, 
2006). 

[6] Department of Defense. Report of the Commission to Assess United 
States National Security Space Management and Organization (Washington, 
D.C.: Jan. 11, 2001). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: