This is the accessible text file for GAO report number GAO-09-462T 
entitled 'Coast Guard: Observations on Changes to Management and 
Oversight of the Deepwater Program' which was released on March 24, 
2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on Coast Guard and Maritime Transportation, 
Committee on Transportation and Infrastructure, House of 
Representatives: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 10:00 a.m. EDT:
Tuesday, March 24, 2009: 

Coast Guard: 

Observations on Changes to Management and Oversight of the Deepwater 
Program: 

Statement of John P. Hutton, Director:
Acquisition and Sourcing Management: 

GAO-09-462T: 

GAO Highlights: 

Highlights of GAO-09-462T, a testimony before the Subcommittee on Coast 
Guard and Maritime Transportation, Committee on Transportation and 
Infrastructure, House of Representatives. 

Why GAO Did This Study: 

GAO has a large body of work examining government agencies’ approaches 
to managing their large acquisition projects. GAO has noted that 
without sufficient knowledge about system requirements, technology, and 
design maturity, programs are subject to cost overruns, schedule 
delays, and performance that does not meet expectations. 

The Deepwater Program, intended to replace or modernize 15 major 
classes of Coast Guard assets, accounts for almost 60 percent of the 
Coast Guard’s fiscal year 2009 appropriation for acquisition, 
construction and improvements. GAO has reported over the years on this 
program, which has experienced serious performance and management 
problems such as cost breaches, schedule slips, and assets designed and 
delivered with significant defects. 

To carry out the Deepwater acquisition, the Coast Guard contracted with 
Integrated Coast Guard Systems (ICGS) as a systems integrator. In April 
2007, the Commandant acknowledged that the Coast Guard had relied too 
heavily on contractors to do the work of government and announced that 
the Coast Guard was taking over the lead role in systems integration 
from ICGS. 

This testimony reflects our most recent issued work on Deepwater, 
specifically our June 2008 report, Coast Guard: Change in Course 
Improves Deepwater Management and Oversight, but Outcome Still 
Uncertain, GAO-08-745. 

What GAO Found: 

Over the past two years, the Coast Guard has reoriented its acquisition 
function to position itself to execute systems integration and program 
management responsibilities formerly carried out by ICGS. The 
acquisition directorate has been consolidated to oversee all Coast 
Guard acquisitions, including the Deepwater Program, and Coast Guard 
project managers have been vested with management and oversight 
responsibilities formerly held by ICGS. Another key change has been to 
manage the procurement of Deepwater assets on a more disciplined, asset-
by-asset approach rather than as an overall system of systems, where 
visibility into requirements and capabilities was limited. For example, 
cost and schedule information is now captured at the individual asset 
level, resulting in the ability to track and report breaches for 
assets. Further, to manage Deepwater acquisitions at the asset level, 
the Coast Guard has begun to follow a disciplined project management 
process that requires documentation and approval of program activities 
at key points in a program’s life cycle. 

These process changes, coupled with strong leadership to help ensure 
the processes are followed in practice, have helped to improve 
Deepwater management and oversight. However, the Coast Guard still 
faces many hurdles going forward and the acquisition outcome remains 
uncertain. 

* The consequences of not following a disciplined acquisition approach 
for Deepwater acquisitions and of relying on the contractor to define 
Coast Guard requirements are clear now that assets, such as the 
National Security Cutter, have been paid for and delivered without the 
Coast Guard’s having determined whether the assets’ planned 
capabilities would meet mission needs. 

* While the asset-based approach is beneficial, certain cross-cutting 
aspects of Deepwater—such as command, control, communications, 
computers, intelligence, surveillance, and reconnaissance (C4ISR) and 
the overall numbers of each asset needed to meet requirements—still 
require a system-level approach. The Coast Guard is not fully 
positioned to manage these aspects. 

* One of the reasons the Coast Guard originally contracted with ICGS as 
the systems integrator was the recognition that the Coast Guard lacked 
the experience and depth in workforce to manage the acquisition itself. 
The Coast Guard has faced challenges in building an adequate government 
acquisition workforce and, like many other federal agencies, is relying 
on support contractors—some in key positions such as cost estimating 
and contract support. GAO has pointed out the potential concerns of 
reliance on contractors who closely support inherently governmental 
functions. 

View [hyperlink, http://www.gao.gov/products/GAO-09-462T] or key 
components. For more information, contact John P. Hutton at (202) 512-
4841 orhuttonj@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

I appreciate the opportunity to be here today to discuss Coast Guard 
acquisitions, specifically its Deepwater Program, the largest 
acquisition in the Coast Guard's history. GAO has a significant body of 
work examining government agencies' approaches to managing their large 
acquisition projects, including Department of Defense weapon systems, 
Department of Homeland Security (DHS) major investments, and large, 
high-risk information technology investments across the government. We 
have pointed to the need for more discipline and accountability in the 
acquisition process to help ensure that programs are not initiated 
until sufficient knowledge exists about system requirements, 
technology, and design maturity. Without this knowledge, programs are 
subject to cost overruns, schedule delays, and performance 
deficiencies. The Deepwater Program represents the largest portion of 
the Coast Guard's appropriation for acquisition, construction, and 
improvements--almost 60 percent in fiscal year 2009.[Footnote 1] 
Unfortunately, Deepwater has experienced serious performance and 
management problems such as cost breaches, schedule slips, and assets 
designed and delivered with significant defects. 

The Deepwater Program is intended to replace or modernize 15 major 
classes of Coast Guard assets--five each of vessels and aircraft, and 
five other projects, including command, control, communications, 
computers, intelligence, surveillance, and reconnaissance (C4ISR) 
systems. To carry out this acquisition, the Coast Guard awarded a 
contract in June 2002 to Integrated Coast Guard Systems (ICGS), a joint 
venture formed by Lockheed Martin Corporation and Northrop Grumman Ship 
Systems, as a systems integrator. In April 2007, the Coast Guard 
Commandant acknowledged that the Coast Guard had relied too heavily on 
contractors to do the work of government and that government and 
industry had failed to control costs. He announced several major 
changes to the acquisition approach to Deepwater, the key one being 
that the Coast Guard was taking over the lead role in systems 
integration from ICGS, with future work on individual assets 
potentially bid competitively outside of the existing contract. 

My statement today will focus on the progress the Coast Guard has made 
in improving its acquisition approach to the Deepwater Program and the 
challenges it continues to face. We have ongoing work on Deepwater 
acquisitions issues--specifically, the Coast Guard's acquisition 
workforce, the cost of the Deepwater Program, and challenges associated 
with C4ISR and other "system-of-systems" aspects--for the House and 
Senate appropriations committees and expect to issue a report later 
this summer. We also have ongoing work for the same committees 
examining the potential operational gaps the Coast Guard may encounter 
based on delays in delivery of the National Security Cutter (NSC) and 
its accompanying package of small boats and unmanned aircraft systems; 
the Coast Guard's mitigation strategies for addressing these potential 
gaps; and how the Coast Guard plans to handle maintenance of the NSC 
while still operating and maintaining its legacy high endurance 
cutters. That report is also expected to be issued this summer. 

This statement is based on our issued work on the Coast Guard's 
Deepwater Program, specifically the information in our June 2008 
report, Coast Guard: Change in Course Improves Deepwater Management and 
Oversight, but Outcome Still Uncertain.[Footnote 2] That work was 
conducted in accordance with generally acceptable government audit 
standards. Those standards require that we plan and perform the audit 
to obtain sufficient, appropriate evidence to provide a reasonable 
basis for our findings and conclusions based on our audit objectives. 
We believe that the evidence obtained provides a reasonable basis for 
our findings and conclusions based on our audit objectives. 

Background: 

The Coast Guard is a multimission, maritime military service within 
DHS. The Coast Guard's responsibilities fall into two general 
categories--those related to homeland security missions, such as port 
security and vessel escorts, and those related to non-homeland security 
missions, such as search and rescue and polar ice operations. To carry 
out these responsibilities, the Coast Guard operates a number of 
vessels and aircraft and, through its Deepwater Program, is currently 
modernizing or replacing those assets. At the start of Deepwater in the 
late 1990s, the Coast Guard chose to use a system of systems 
acquisition strategy that was intended to replace the assets with a 
single, integrated package of aircraft, vessels, and communications 
systems. As the systems integrator, ICGS was responsible for designing, 
constructing, deploying, supporting, and integrating the assets. The 
decision to use a systems integrator for the Deepwater Program was 
driven in part because of the Coast Guard's lack of expertise in 
managing and executing an acquisition of this magnitude. Under this 
approach, the Coast Guard provided the contractor with broad, overall 
performance specifications--such as the ability to interdict illegal 
immigrants--and ICGS determined the specifications for the Deepwater 
assets. According to Coast Guard officials, the ICGS proposal was 
submitted and priced as a package; that is, the Coast Guard bought the 
entire solution and could not reject any individual component. 

Deepwater assets are in various stages of the acquisition process. 
Some, such as the NSC and Maritime Patrol Aircraft, are in production. 
Others, such as the Fast Response Cutter, are in design, and still 
others, such as the Offshore Patrol Cutter, are in the early stages of 
requirements definition. 

Coast Guard Has Made Improvements but Faces Continued Challenges in 
Managing Deepwater Acquisitions: 

Since the Commandant's April 2007 announcement that the Coast Guard was 
taking over the lead role in systems integration from ICGS, the Coast 
Guard has undertaken several initiatives that have increased 
accountability for Deepwater outcomes within the Coast Guard and to 
DHS. The Coast Guard's Blueprint for Acquisition Reform sets forth a 
number of objectives and specific tasks with the intent of improving 
acquisition processes and results. Its overarching goal is to enhance 
the Coast Guard's mission execution through improved contracting and 
acquisition approaches. One key effort in this regard was the July 2007 
consolidation of the Coast Guard's acquisition responsibilities-- 
including the Deepwater Program--into a single acquisition directorate. 
Previously, Deepwater assets were managed independently of other Coast 
Guard acquisitions within an insulated structure. The Coast Guard has 
also vested its government project managers with management and 
oversight responsibilities formerly held by ICGS. 

The Coast Guard is also now managing Deepwater under an asset-based 
approach, rather than as an overall system-of-systems as initially 
envisioned. This approach has resulted in increased government control 
and visibility. For example, cost and schedule information is now 
captured at the individual asset level, resulting in the ability to 
track and report cost breaches for assets.[Footnote 3] Under the prior 
structure, a cost breach was to be tracked at the overall Deepwater 
Program level, and the threshold was so high that a breach would have 
been triggered only by a catastrophic event. 

To manage Deepwater acquisitions at the asset level, the Coast Guard 
has begun to follow a disciplined project management process using the 
framework set forth in its Major Systems Acquisition Manual. This 
process requires documentation and approval of program activities at 
key points in a program's life cycle. The process begins with 
identification of deficiencies in Coast Guard capabilities and then 
proceeds through a series of structured phases and decision points to 
identify requirements for performance, develop and select candidate 
systems that meet those requirements, demonstrate the feasibility of 
selected systems, and produce a functional capability. Previously, the 
Coast Guard authorized the Deepwater Program to deviate from the 
structured acquisition process, stating that the requirements of the 
process were not appropriate for the Deepwater system-of-systems 
approach. Instead, Deepwater Program reviews were required on a 
schedule-driven--as opposed to the current event-driven--basis. 

Further, leadership at DHS is now formally involved in reviewing and 
approving key acquisition decisions for Deepwater assets. We reported 
in June 2008 that DHS approval of Deepwater acquisition decisions as 
part of its investment review process was not required, as the 
department had deferred decisions on specific assets to the Coast Guard 
in 2003. We recommended that the Secretary of DHS direct the Under 
Secretary for Management to rescind the delegation of Deepwater 
acquisition decision authority. In September 2008, the Under Secretary 
took this step, so that Deepwater acquisitions are now subject to the 
department's investment review process, which calls for executive 
decision making at key points in an investment's life cycle. 

We also reported this past fall, however, that DHS had not effectively 
implemented or adhered to this investment review process; consequently, 
the department had not provided the oversight needed to identify and 
address cost, schedule, and performance problems in its major 
investments.[Footnote 4] Without the appropriate reviews, DHS loses the 
opportunity to identify and address cost, schedule, and performance 
problems and, thereby, minimize program risk. We reported that 14 of 
the department's investments that lacked appropriate review experienced 
cost growth, schedule delays, and underperformance--some of which were 
substantial. Other programs within DHS have also experienced cost 
growth and schedule delays. For example, we reported in July 2008 that 
the Coast Guard's Rescue 21 system was projected to experience cost 
increases of 184 percent and schedule delays of 5 years after 
rebaselining.[Footnote 5] DHS issued a new interim management directive 
on November 7, 2008, that addresses many of our findings and 
recommendations on the department's major investments. If implemented 
as intended, the more disciplined acquisition and investment review 
process outlined in the directive will help ensure that the 
department's largest acquisitions, including Deepwater, are effectively 
overseen and managed. 

Consequences of Prior Deepwater Acquisition Approach May Be Costly: 

While the decision to follow the Major Systems Acquisition Manual 
process for Deepwater assets is promising, the consequences of not 
following this acquisition approach in the past--when the contractor 
managed the overall acquisition--are now apparent for assets already in 
production, such as the NSC, and are likely to pose continued problems, 
such as increased costs. Because ICGS had determined the overall 
Deepwater solution, the Coast Guard had not ensured traceability from 
identification of mission needs to performance specifications for the 
Deepwater assets. In some cases it is already known that the ICGS 
solution does not meet Coast Guard needs, for example: 

* The Coast Guard accepted the ICGS-proposed performance specifications 
for the long-range interceptor, a small boat intended to be launched 
from larger cutters such as the NSC, with no assurance that the boat it 
was buying was what was needed to accomplish its missions. Ultimately, 
after a number of design changes and a cost increase from $744,621 to 
almost $3 million, the Coast Guard began to define for itself the 
capabilities it needed and has decided not to buy any more of the ICGS 
boats. 

* ICGS had initially proposed a fleet of 58 fast response cutters, 
subsequently termed the Fast Response Cutter-A (FRC-A), which were to 
be constructed of composite materials (as opposed to steel, for 
example). However, the Coast Guard suspended design work on the FRC-A 
in February 2006 to assess and mitigate technical risks. Ultimately, 
because of high risk and uncertain cost savings, the Coast Guard 
decided not to pursue the acquisition, a decision based largely on a 
third-party analysis that found the composite technology was unlikely 
to meet the Coast Guard's desired 35-year service life. After 
obligating $35 million to ICGS for the FRC-A, the Coast Guard pursued a 
competitively awarded fast response cutter based on a modified 
commercially available patrol boat. That contract was awarded in 
September 2008. 

System-Level Aspects Pose Additional Challenges under Revised 
Acquisition Approach: 

Although the shift to individual acquisitions is intended to provide 
the Coast Guard with more visibility and control, key aspects still 
require a system-level approach. These aspects include an integrated 
C4ISR system--needed to provide critical information to field 
commanders and facilitate interoperability with the Department of 
Defense and DHS--and decisions on production quantities of each 
Deepwater asset the Coast Guard requires to achieve its missions. The 
Coast Guard is not fully positioned to manage these aspects under its 
new acquisition approach but is engaged in efforts to do so. 

C4ISR is a key aspect of the Coast Guard's ability to meet its 
missions. How the Coast Guard structures C4ISR is fundamental to the 
success of the Deepwater Program because C4ISR encompasses the 
connections among surface, aircraft, and shore-based assets and the 
means by which information is communicated through them. C4ISR is 
intended to provide operationally relevant information to Coast Guard 
field commanders to allow the efficient and effective execution of 
their missions. However, an acquisition strategy for C4ISR is still in 
development. Officials stated that the Coast Guard is revisiting the 
C4ISR incremental acquisition approach proposed by ICGS and analyzing 
that approach's requirements and architecture. In the meantime, the 
Coast Guard is continuing to acquire C4ISR through ICGS. 

As the Coast Guard transitions from the ICGS-based system-of-systems 
acquisition strategy to an asset-based approach, it will need to 
maintain a strategic outlook to determine how many of the various 
Deepwater assets to procure to meet Coast Guard needs. When deciding 
how many of a specific vessel or aircraft to procure, it is important 
to consider not only the capabilities of that asset, but how it can 
complement or duplicate the capabilities of the other assets with which 
it is intended to operate. To that end, the Coast Guard is modeling the 
planned capabilities of Deepwater assets, as well as the capabilities 
and operations of existing assets, against the requirements for Coast 
Guard missions. The intent of this modeling is to test each planned 
asset to ensure that its capabilities fill stated deficiencies in the 
Coast Guard's force structure and to inform how many of a particular 
asset are needed. However, the analysis based on the modeling is not 
expected to be completed until the summer of 2009. In the meantime, 
Coast Guard continues to plan for asset acquisitions in numbers very 
similar to those determined by ICGS, such as 8 NSCs. 

Challenges in Building an Acquisition Workforce: 

Like many federal agencies that acquire major systems, the Coast Guard 
faces challenges in recruiting and retaining a sufficient government 
acquisition workforce. In fact, one of the reasons the Coast Guard 
originally contracted with ICGS as a systems integrator was the 
recognition that the Coast Guard lacked the experience and depth in its 
workforce to manage the acquisition itself. 

The Coast Guard's 2008 acquisition human capital strategic plan sets 
forth a number of workforce challenges that pose the greatest threats 
to acquisition success, including a shortage of civilian acquisition 
staff, its military personnel rotation policy, and the lack of an 
acquisition career path for its military personnel. The Coast Guard has 
taken a number of steps to hire more acquisition professionals, 
including the increased use of recruitment incentives and relocation 
bonuses, utilizing direct hire authority, and rehiring government 
annuitants. The Coast Guard also recognizes the impact of military 
personnel rotation on its ability to retain people in key positions. 
Its policy of 3-year rotations of military personnel among units, 
including to and from the acquisition directorate, limits continuity in 
key project roles and can have a serious impact on acquisition 
expertise. While the Coast Guard concedes that it does not have the 
personnel required to form a dedicated acquisition career field for 
military personnel, such as that found in the Navy, it is seeking to 
improve the base of acquisition knowledge throughout the Coast Guard by 
exposing more officers to acquisition as they follow their regular 
rotations. 

In the meantime, the lack of a sufficient government acquisition 
workforce means that the Coast Guard is relying on contractors to 
supplement government staff, often in key positions such as cost 
estimators, contract specialists, and program management support. While 
support contractors can provide a variety of essential services, when 
they are performing certain activities that closely support inherently 
governmental functions their use must be carefully overseen to ensure 
that they do not perform inherently governmental roles. Conflicts of 
interest, improper use of personal services contracts, and increased 
costs are also potential concerns of reliance on contractors.[Footnote 
6] 

Concluding Observations: 

In response to significant problems in achieving its intended outcomes 
under the Deepwater Program, the Coast Guard leadership has made a 
major change in course in its management and oversight by re-organizing 
its acquisition directorate, moving away from the use of a contractor 
as the systems integrator, and putting in place a structured, more 
disciplined acquisition approach for Deepwater assets. While the 
initiatives the Coast Guard has underway have begun to have a positive 
impact, the extent and duration of this impact depend on positive 
decisions that continue to increase and improve government management 
and oversight. 

Mr. Chairman, this concludes my prepared statement. I will be pleased 
to answer any questions you or members of the subcommittee may have at 
this time. 

GAO Contact: 

For further information about this testimony, please contact John P. 
Hutton, Director, at 202-512-4841 or huttonj@gao.gov. Contact points 
for our Offices of Congressional Relations and Public Affairs may be 
found on the last page of this testimony. 

[End of section] 

Footnotes: 

[1] The Coast Guard's fiscal year 2009 appropriation includes an 
additional $300 million for acquisition, construction, and improvements 
for necessary expenses related to the consequences of 2008 natural 
disasters and flooding. In addition, the American Recovery and 
Reinvestment Act of 2009, signed into law on February 17, 2009, 
authorized $98 million for the Coast Guard to spend on, among other 
things, "priority procurements due to materials and labor cost 
increases." The Coast Guard is required to submit an expenditure plan 
to Congress within 45 days after enactment. 

[2] GAO, Coast Guard: Change in Course Improves Deepwater Management 
and Oversight, but Outcome Still Uncertain, [hyperlink, 
http://www.gao.gov/products/GAO-08-745] (Washington, D.C.: June 24, 
2008). 

[3] DHS requires cost breaches of 8 percent or higher to be reported to 
the department. 

[4] GAO, Department of Homeland Security: Billions Invested in Major 
Programs Lack Appropriate Oversight, [hyperlink, 
http://www.gao.gov/products/GAO-09-29] (Washington, D.C.: Nov. 18, 
2008). 

[5] See GAO, Information Technology: Agencies Need to Establish 
Comprehensive Policies to Address Changes to Projects' Cost, Schedule, 
and Performance Goals, [hyperlink, http://www.gao.gov/products/GAO-08-
925] (Washington, D.C.: July 31, 2008). Rescue 21 is a command, 
control, and communication system that improves mission execution in 
coastal zones to help the Coast Guard meet its search and rescue 
program goals. It is intended to result in improved response to 
distress calls and better coordination and interoperability with other 
government agencies and first responders. 

[6] The issue of support contractors in acquisition is not unique to 
the Coast Guard. In our March 2008 report on the acquisition of major 
weapons systems in the Department of Defense, we found that it too 
relies heavily on contractors to perform roles in program management, 
cost estimation, and engineering and technical functions. GAO, Defense 
Acquisitions: Assessments of Major Weapons Programs, [hyperlink, 
http://www.gao.gov/products/GAO-08-467SP] (Washington, D.C.: Mar. 31, 
2008). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: