This is the accessible text file for GAO report number GAO-08-183T 
entitled 'Geostationary Operational Environmental Satellites: Further 
Actions Needed to Effectively Manage Risks' which was released on 
October 23, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on Energy and the Environment, House Committee 
on Science and Technology: 

United States Government Accountability Office: 

GAO: 

For Release on Delivery Expected at 2:00 p.m. EDT: 

Tuesday, October 23, 2007: 

Geostationary Operational Environmental Satellites: 

Further Actions Needed to Effectively Manage Risks: 

Statement of David A. Powner, Director: 

Information Technology Management Issues: 

GOES-R: 

GAO-08-183T: 

GAO Highlights: 

Highlights of GAO-08-183T, a testimony before the Subcommittee on 
Energy and Environment, House Committee on Science and Technology. 

Why GAO Did This Study: 

The National Oceanic and Atmospheric Administration (NOAA), with the 
aid of the National Aeronautics and Space Administration (NASA), plans 
to procure the next generation of geostationary operational 
environmental satellites, called the Geostationary Operational 
Environmental Satellites-R series (GOES-R). This new series is 
considered critical to the United States’ ability to maintain the 
continuity of data required for weather forecasting through the year 
2028. 

GAO was asked to summarize its report being released today on the GOES-
R series. This report (1) assesses the status and revised plans for the 
GOES-R procurement and (2) evaluates whether NOAA is adequately 
mitigating key technical and programmatic risks facing the program. To 
conduct this review, GAO analyzed contractor and program data and 
interviewed officials from NOAA and NASA. 

What GAO Found: 

NOAA has made progress in planning its GOES-R procurement—which is 
estimated to cost $7 billion and scheduled to have the first satellite 
ready for launch in 2014—but cost and schedules are likely to grow. 
Specifically, the agency completed preliminary design studies of GOES-R 
and recently decided to separate the space and ground elements of the 
program into two separate development contracts. However, this change 
in strategy has delayed a planned September 2007 decision to proceed 
with the acquisition. Further, independent estimates are higher than 
the program’s current cost estimate and convey a low level of 
confidence in the program’s schedule. Independent studies show that the 
estimated program could cost about $2 billion more, and the first 
satellite launch could be delayed by 2 years. As NOAA works to 
reconcile the independent estimate with its own program office 
estimate, costs are likely to grow and schedules are likely to be 
delayed. 

To address cost, schedule, and technical risks, the GOES-R program has 
established a risk management program and has taken steps to mitigate 
selected risks. For example, as of July 2007, the program office 
identified the lack of an integrated master schedule to be its highest 
priority risk and established plans to bring this risk to closure. 
However, more remains to be done to fully address risks. Specifically, 
the program has multiple risk watchlists that are not always consistent 
and key risks are missing from the watchlists, including risks 
associated with unfilled executive positions, limitations in NOAA’s 
insight into NASA’s deliverables, and insufficient funds for unexpected 
costs—called management reserves (see table for more details). As a 
result, the GOES-R program is at risk that problems will not be 
identified or mitigated in a timely manner and could lead to program 
cost overruns and schedule delays 

What GAO Recommends: 

In its report, GAO is making recommendations to the Secretary of 
Commerce to improve GOES-R risk management. The Secretary agreed with 
the recommendations to use a program level risk list and to add 
selected risks to its list, but disagreed that NOAA has insufficient 
insight into NASA’s contracts. However, NOAA has not demonstrated that 
it has validated NASA’s contractor performance and GAO remains 
concerned that NOAA lacks the capability to oversee this key aspect of 
the program. 

Table: Description of Key Risks Missing from GOES-R Risk Lists: 

Key Risks: Unfilled GOES-R executive leadership positions; Description: 
Two senior program positions—the system program director and deputy 
system program director—are currently filled by NASA and NOAA personnel 
in an acting capacity until they can be permanently filled by NOAA. The 
agency reported that it plans to fill the deputy system program 
director role in the near future, but noted that it could take more 
than 6 months to fill the system program director role. 

Key Risks: Limitations in NOAA’s insight into NASA’s deliverables; 
Description: The established NOAA/NASA interagency agreements do not 
contain provisions that enable NOAA to ensure that monthly contractor 
data and reports, submitted by NASA, are reliable and that they 
accurately depict contractor performance. 

Key Risks: Insufficient management reserve (for unexpected costs) held 
by the program and a critical instrument contractor; Description: As of 
May 2007, the contractor for a critical instrument—the Advanced 
Baseline Imager—had less than 1 percent of funding in reserve to cover 
unexpected costs associated with the 40 percent of work left to be 
completed. In addition, as a result of addressing issues on the 
Advanced Baseline Imager in March 2007, the reserve funding for the 
overall GOES-R program dropped below 25 percent—a level that NOAA 
reported it intended to establish as a lesson learned from other 
satellite acquisitions. As of July 2007, the reserve level was at about 
15 percent. 

Source: GAO analysis. 

[End of table] 

To view the full product, including the scope and methodology, click on 
[hyperlink, http://www.GAO-08-183T]. For more information, contact 
David A. Powner at (202) 512-9286 or pownerd@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

We appreciate the opportunity to participate in today's hearing on the 
planned Geostationary Operational Environmental Satellites-R series 
(GOES-R) program. The GOES-R series is to replace the current series of 
satellites, which will likely begin to reach the end of their useful 
lives in approximately 2014. This new series is expected to mark the 
first major technological advance in GOES instrumentation since 1994. 
It is also considered critical to the United States' ability to 
maintain the continuity of data required for weather forecasting 
through the year 2028. 

As requested, our testimony summarizes the report we issued today on 
the GOES-R program. Specifically, we (1) assessed the status and 
revised plans for the GOES-R procurement and (2) evaluated whether the 
National Oceanic and Atmospheric Administration (NOAA) is adequately 
mitigating key technical and programmatic risks facing the GOES-R 
program.[Footnote 1] In preparing for this testimony, we relied on our 
work supporting the accompanying report. That report contains a 
detailed overview of our scope and methodology. All of the work on 
which this testimony is based was performed in accordance with 
generally accepted government auditing standards. 

Results in Brief: 

NOAA has made progress on its GOES-R procurement--which is estimated to 
cost $7 billion and scheduled to have the first satellite ready for 
launch in 2014--but costs and schedules are likely to grow. 
Specifically, NOAA completed preliminary design studies of its GOES-R 
acquisition and planned to make a decision to proceed to development 
and production in September 2007. In addition, the agency recently 
decided to separate the space and ground elements of the program into 
two separate contracts to be managed by the National Aeronautics and 
Space Administration (NASA) and NOAA, respectively. However, this 
change in the GOES-R acquisition strategy has delayed the decision to 
proceed with the acquisition. Further, independent estimates are higher 
than the program's current cost estimate and convey a low level of 
confidence in the program's schedule. Independent studies show that the 
estimated program could cost about $2 billion more, and the first 
satellite launch could be delayed by 2 years. As NOAA works to 
reconcile the independent estimate with its own program office 
estimate, costs are likely to grow and schedules are likely to be 
delayed. However, NOAA officials stated that while their reconciliation 
process is still ongoing, the revised cost estimate will likely be $1 
billion more than the current $7 billion and the first satellite launch 
will likely be delayed 1 year from 2014, rather than 2 years. 

To address cost, schedule, and technical risks, the GOES-R program has 
established a risk management program and has taken steps to identify 
and mitigate selected risks. For example, as of July 2007, the program 
office identified the lack of an integrated master schedule as its 
highest priority risk. It also identified other risks including 
technical challenges affecting the development of a critical instrument 
and the development of requirements between the space and ground 
segments. The program has also established plans for bringing these 
risks to closure. However, more remains to be done to fully address 
risks. Specifically, the program has multiple risk watchlists that are 
not always consistent. Further, key risks are missing from the risks 
lists, including risks associated with unfilled executive positions, 
limitations in NOAA's insight into NASA's deliverables, and 
insufficient funds for unexpected costs (called management reserve). As 
a result, the program is at risk that problems will not be identified 
or mitigated in a timely manner and could lead to program cost overruns 
and schedule delays. 

To improve NOAA's ability to effectively manage the GOES-R procurement, 
in our report being released today, we are making recommendations to 
ensure that the GOES-R program office manages, mitigates, and reports 
on risks using a more comprehensive program-level risk list. In written 
comments, the Secretary of Commerce agreed with our recommendations to 
use a program level risk list and to add selected risks to its list, 
but disagreed that NOAA has insufficient insight into NASA's contracts. 
The Secretary cited an unparalleled transparency between the two 
agencies. However, NOAA has not demonstrated that it has validated 
NASA's contractor performance and we remain concerned that NOAA lacks 
the capability to oversee this important aspect of the program. Given 
the past problems NOAA had in obtaining insight into NASA's contracts 
and the importance of this interagency relationship to the success of 
the GOES-R program, we believe that this issue should be managed and 
monitored as a risk. 

Background: 

Since the 1960s, geostationary and polar-orbiting environmental 
satellites have been used by the United States to provide 
meteorological data for weather observation, research, and forecasting. 
NOAA's National Environmental Satellite Data and Information Service 
(NESDIS) is responsible for managing the civilian geostationary and 
polar-orbiting satellite systems as two separate programs, called GOES 
and the Polar Operational Environmental Satellites, respectively. 

Unlike polar-orbiting satellites, which constantly circle the earth in 
a relatively low polar orbit, geostationary satellites can maintain a 
constant view of the earth from a high orbit of about 22,300 miles in 
space. NOAA operates GOES as a two-satellite system that is primarily 
focused on the United States. These satellites are uniquely positioned 
to provide timely environmental data to meteorologists and their 
audiences on the earth's atmosphere, its surface, cloud cover, and the 
space environment. They also observe the development of hazardous 
weather, such as hurricanes and severe thunderstorms, and track their 
movement and intensity to reduce or avoid major losses of property and 
life. Furthermore, the satellites' ability to provide broad, 
continuously updated coverage of atmospheric conditions over land and 
oceans is important to NOAA's weather forecasting operations. 

To provide continuous satellite coverage, NOAA acquires several 
geostationary satellites at a time as part of a series and launches new 
satellites every few years (see table 1). 

Table 1: Summary of the Procurement History of GOES: 

Series name: Original GOES[C]; 
Procurement duration[A]: 1970-1987; 
Satellites[B]: 1, 2, 3, 4, 5, 6, 7. 

Series name: GOES I-M; 
Procurement duration[A]: 1985-2001; 
Satellites[B]: 8, 9, 10, 11, 12. 

Series name: GOES-N; 
Procurement duration[A]: 1998-2011; 
Satellites[B]: 13, O, P, Q[D]. 

Series name: GOES-R; 
Procurement duration[A]: 2007-2016; 
Satellites[B]: R, S. 

Source: GAO analysis of NOAA data. 

[A] Duration includes time from contract award to final satellite 
launch. 

[B] Satellites in a series are identified by letters of the alphabet 
when they are on the ground and by numbers once they are in orbit. 

[C] The procurement of these satellites consisted of four separate 
contracts for (1) two early prototype satellites and GOES-1, (2) GOES- 
2 and -3, (3) GOES-4 through -6, and (4) GOES-G (failed on launch) and 
GOES-7. 

[D] NOAA decided not to exercise the option for this satellite. 

[End of table] 

Three satellites--GOES-11, GOES-12, and GOES-13--are currently in 
orbit. Both GOES-11 and GOES-12 are operational satellites, while GOES- 
13 is in an on-orbit storage mode. It is a backup for the other two 
satellites should they experience any degradation in service. The 
others in the series, GOES-O and GOES-P, are planned for launch over 
the next few years. NOAA is also planning the next generation of 
satellites, known as the GOES-R series, which are planned for launch 
beginning in 2014. 

GOES-R Program--An Overview: 

NOAA plans for the GOES-R program to improve on the technology of prior 
series, in terms of both system and instrument improvements, to fulfill 
more demanding user requirements and to provide more rapid information 
updates. Table 2 highlights key system-related improvements GOES-R is 
expected to make to the geostationary satellite program. 

Table 2: Summary of Key GOES-R System Improvements: 

Key feature: Total number of products; 
GOES-N (current): 41; 
GOES-R: ~68-120. 

Key feature: Downlink rate of raw data collected by instruments (from 
satellite to ground stations); 
GOES-N (current): 2.6 Mbps; 
GOES-R: 70 Mbps. 

Key feature: Broadcast rate of processed GOES data (from satellite to 
users); 
GOES-N (current): 2.1 Mbps; 
GOES-R: 40 Mbps. 

Key feature: Raw data storage (the length of time that raw data will be 
stored at ground stations); 
GOES-N (current): 0 days; 
GOES-R: 3 days. 

Source: GAO analysis of NOAA data. 

[End of table] 

In addition to the system improvements, the instruments on the GOES-R 
series are expected to significantly increase the clarity and precision 
of the observed environmental data. NOAA originally planned to acquire 
six different types of instruments. Furthermore, two of these 
instruments--the Advanced Baseline Imager and the Hyperspectral 
Environmental Suite--were considered to be the most critical because 
they would provide data for key weather products. Table 3 summarizes 
the originally planned instruments and their expected capabilities. 

Table 3: Originally Planned GOES-R Series Instruments, as of August 
2006: 

Planned instrument: Advanced Baseline Imager (ABI); 
Description: Expected to provide variable area imagery and radiometric 
information of the earth's surface, atmosphere, and cloud cover. Key 
features include: 
* monitoring and tracking severe weather; 
* providing images of clouds to support forecasts, and: 
* providing higher resolution, faster coverage, and broader coverage 
simultaneously. 

Planned instrument: Hyperspectral Environmental Suite (HES)[A]; 
Description: Expected to provide information about the earth's surface 
to aid in the prediction of weather and climate monitoring. Key 
features include: 
* providing atmospheric moisture and temperature profiles to support 
forecasts and climate monitoring; 
* monitoring coastal regions for ecosystem health, water quality, 
coastal erosion, and harmful algal blooms, and: 
* providing higher resolution and faster coverage. 

Planned instrument: Geostationary Lightning Mapper (GLM); 
Description: Expected to continuously monitor lightning activity over 
the United States and provide a more complete dataset than previously 
possible. Key features include: 
* detecting lightning strikes as an indicator of severe storms and: 
* providing a new capability to GOES that only previously existed on 
polar satellites. 

Planned instrument: Magnetometer; 
Description: Expected to provide information on the general level of 
geomagnetic activity, monitor current systems in space, and permit 
detection of magnetopause crossings, sudden storm commencements, and 
substorms. 

Planned instrument: Space Environmental In-Situ Suite (SEISS); 
Description: Expected to provide information on space weather to aid in 
the prediction of particle precipitation, which causes disturbance and 
disruption of radio communications and navigation systems. Key features 
include: 
* measuring magnetic fields and charged particles; 
* providing improved heavy ion detection, adding low energy electrons 
and protons, and: 
* enabling early warnings for satellite and power grid operation, 
telecom services, astronauts, and airlines. 

Planned instrument: Solar Imaging Suite (SIS)[B]; Description: Expected 
to provide coverage of the entire dynamic range of solar X-ray 
features, from coronal holes to X-class flares, as well as estimate the 
measure of temperature and emissions. Key features include: 
* providing images of the sun and measuring solar output to monitor 
solar storms and: 
* providing improved imager capability. 

Source: GAO analysis of NOAA data. 

[A] HES was cancelled in September 2006. 

[B] SIS development work was divided into two separate acquisitions, 
the Solar Ultra Violet Imager and the Extreme Ultraviolet and X-Ray 
Irradiance Suite. 

[End of table] 

More recently, however, NOAA reduced the scope of the GOES-R program 
because of expectations of higher costs. In May 2006, the program 
office projected that total costs, which were originally estimated to 
be $6.2 billion, could reach $11.4 billion. We reported that this led 
NOAA to reduce the scope and technical complexity of the baseline 
program.[Footnote 2] Specifically, in September 2006, NOAA reduced the 
minimum number of satellites from four to two, cancelled plans for 
developing the Hyperspectral Environmental Suite, and estimated the 
revised program would cost $7 billion. Table 4 provides a summary of 
the timeline and scope of these key changes. 

Table 4: Key Changes to the GOES-R Program: 

Number of satellites; 
Baseline program, as of August 2006: 4; 
Program with reduced scope, as of September 2006: 2. 

Planned instruments; 
Baseline program, as of August 2006: 2 critical instruments and 4 
noncritical instruments or instrument suites: 
Critical instruments: 
* Advanced Baseline Imager; 
* Hyperspectral Environmental Suite; 
Noncritical instruments/suites: 
* Geostationary Lightning Mapper; 
* Magnetometer; 
* Space Environmental In-Situ Suite; 
* Solar Imaging Suite; 
Program with reduced scope, as of September 2006: 1 critical instrument 
and 4 noncritical instruments or instrument suites: 
Critical instrument: 
Advanced Baseline Imager; 
Noncritical instruments/suites: 
* Geostationary Lightning Mapper; 
* Magnetometer; 
* Space Environmental In-Situ Suite; 
* Two components of the former Solar Imaging Suite (the Solar Ultra 
Violet Imager and Extreme Ultraviolet and X-Ray Irradiance Suite). 

Life-cycle cost estimate (in then year dollars); 
Baseline program, as of August 2006: $6.2-11.4 billion; 
Program with reduced scope, as of September 2006: $7 billion. 

End of operations and maintenance; 
Baseline program, as of August 2006: 2028; 
Program with reduced scope, as of September 2006: 2028[A]. 

Source: GAO analysis of NOAA data. 

[A] All satellites are expected to have a 15-year lifespan (5 years in 
on-orbit storage plus 10 years in operation). 

[End of table] 

GOES-R Program Office Structure: 

NOAA is solely responsible for GOES-R program funding and overall 
mission success. However, since it relies on NASA's acquisition 
experience and technical expertise to help ensure the success of its 
programs, NOAA implemented an integrated program management structure 
with NASA for the GOES-R program. Within the program office, there are 
two project offices that manage key components of the GOES-R system. 
These are called the flight and operations project offices. The flight 
project office oversees the spacecraft, instruments, and launch 
services. The operations project office oversees the ground elements 
and on-orbit operations of the satellites. The project manager for the 
flight project office and the deputy project manager for operations 
project office are designated to be filled with NASA personnel. 
Additionally, NOAA has located the program office at NASA's Goddard 
Space Flight Center. 

Planned GOES-R Acquisition Strategy: 

NOAA's acquisition strategy was to award contracts for the preliminary 
design of the GOES-R system to several vendors who would subsequently 
compete for the contract to be the single prime contractor responsible 
for overall system development and production. As such, in October 
2005, NOAA awarded contracts for the preliminary design of the overall 
GOES-R system to three vendors.[Footnote 3] 

In addition, to reduce the risks associated with developing technically 
advanced instruments, NASA awarded contracts for the preliminary 
designs for five of the originally planned instruments. NASA expected 
to subsequently award development contracts for these instruments and 
to eventually turn them over to the prime contractor responsible for 
the overall GOES-R program. 

GOES-R Preliminary Design Studies Are Completed, but Key Program 
Changes Have Been Made and Cost and Schedule Estimates Are Likely to 
Grow: 

NOAA has completed preliminary design studies of its GOES-R 
procurement. In addition, the agency recently decided to separate the 
space and ground elements of the program into two separate contracts to 
be managed by NASA and NOAA, respectively. However, this change has 
delayed a key decision to proceed with the acquisition, which was 
planned for September 2007. Further, independent estimates are higher 
than the program's current $7 billion cost estimate and convey a low 
level of confidence in the program's schedule for launching the first 
satellite by 2014. As NOAA works to reconcile the independent estimate 
with its own program office estimate, costs are likely to grow and 
schedules are likely to be delayed. 

Progress Has Been Made on GOES-R Procurement Activities: 

NOAA and NASA have made progress on GOES-R. The program office has 
completed preliminary design studies of the overall GOES-R system and 
has initiated development work on most of the planned instruments. 
Specifically, the NOAA-issued contracts for the preliminary design of 
the overall GOES-R system to three vendors have ended, and the designs 
have been completed. 

In addition, after completing preliminary designs on five of the 
originally planned instruments, NASA awarded development contracts for 
three of them.[Footnote 4] Further, the most critical of these 
instruments--the Advanced Baseline Imager--has completed a major 
development milestone. In February 2007, it passed a critical design 
review gate and NASA approved the contractor to begin production of a 
prototype model. 

NOAA Revised its Acquisition Strategy: 

NOAA recently made a number of key changes in how it plans to acquire 
the GOES-R system. Originally, NOAA planned to award and manage a 
single prime contract for the acquisition and operation of the 
integrated system. However, an independent review team assessed the 
program and found that this approach was risky.[Footnote 5] It 
recommended that NOAA split the acquisition effort into two separate 
contracts for the space and ground segments and have NASA manage the 
space segment. The independent review team concluded that there was 
less risk in continuing with this approach than there would be if NOAA 
took on a new and expanded role. 

In March 2007, Commerce approved NOAA's decision to implement these 
recommendations. The agency revised its acquisition strategy to include 
two separate contracts--the space segment and the ground segment. The 
two contracts are expected to be awarded in May 2008 and August 2008, 
respectively. The space segment is to be managed by a NASA-led flight 
project office. As such, NASA is to be responsible for awarding and 
managing the space segment contract, delivering the flight-ready 
instruments to the space segment contractor for integration onto the 
satellites, and overseeing the systems engineering and integration. 
NOAA is to be responsible for the ground segment contract, which is to 
be managed by the NOAA-led operations project office. 

The revised acquisition strategy has delayed NOAA's plans to complete a 
key decision milestone on whether to proceed with GOES-R development 
and production in September 2007. Once this decision is made, the final 
requests for proposals on the system segments are to be released. The 
agency could not provide a timeframe for when this key decision 
milestone would take place. 

GOES-R Cost Estimates Are Likely to Grow and Schedule Estimates Are 
Likely to Slip: 

NOAA's current estimate that the life cycle cost of the GOES-R program 
would be $7 billion is likely to grow, and its estimate that the first 
satellite would be launched in December 2014 is likely to slip. 
Consistent with best practices in cost estimating, in May 2007, NOAA 
had two different cost estimates completed for the current GOES-R 
program--one by its program office and one by an independent cost 
estimating firm. The program office estimated with 80 percent 
confidence that the program would cost $6.9 billion. The independent 
estimating firm estimated with 80 percent confidence that the program 
would cost $9.3 billion. 

A comparison of the two cost models shows that the independent 
estimator has about a 20 percent level of confidence that the program 
can be completed for $6.9 billion. Further, the independent estimator 
concluded that the program office estimate significantly understated 
the risk of cost overruns. Other major differences between the two 
estimates are contained in government costs and in the space and ground 
segments. In commenting on a draft of the accompanying report, NOAA 
officials noted that one of the differences between the estimates is 
the inflation rate. The independent estimator assumed a higher 
inflation rate than the rate that NOAA and NASA typically use. NOAA 
officials noted that if the independent estimate was adjusted to NOAA's 
inflation rate, the program's cost estimate--with 80 percent 
confidence--would be $8.7 billion. However, we believe that the value 
of an independent estimate is that it does not necessarily use the same 
assumptions as the program office. By offering alternative assumptions, 
the independent estimate provides valuable information for government 
officials to consider when revising program cost estimates. 

Program officials are reconciling the two different cost estimates and 
plan to establish a new program cost estimate to be released in 
conjunction with the President's fiscal year 2009 budget in February 
2008. Program officials were unable to provide us information on the 
reconciled estimate until it is released. Nonetheless, the revised cost 
estimate will likely be $1 billion more than the current $7 billion. 

Regarding schedule, NOAA's current plan to launch the first GOES-R 
series satellite in December 2014 could be delayed. This schedule was 
driven by a requirement that the satellites be available to back up the 
last remaining GOES satellites (GOES-O and GOES-P) should anything go 
wrong during the planned launches of these satellites (see table 5). 
However, as part of its cost estimate, the independent estimator 
performed a schedule risk analysis. The independent estimator 
determined that there was less than a 50 percent chance that the first 
satellite would be ready for launch by December 2014 and that a later 
date would be more realistic. The estimator determined that it had 50 
percent confidence that the first satellite would launch by October 
2015 and 80 percent confidence that the satellite would launch by March 
2017. A delay of this magnitude could affect the continuity of GOES 
data should the agency experience problems with the predecessor 
satellites. 

Table 5: GOES-R Program Launch Schedule, as of July 2007: 

Milestone: GOES-O launch[A]; 
Planned date: April 2008. 

Milestone: GOES-P launch[A]; 
Planned date: April 2009. 

Milestone: GOES-R satellite available for launch; 
Planned date: Dec. 2014. 

Milestone: GOES-S satellite available for launch; 
Planned date: April 2016. 

Source: NOAA. 

[A] GOES-O and GOES-P are not part of the GOES-R series program. Their 
launch dates are provided because of their relevance to the GOES-R 
series satellite schedules. 

[End of table] 

NOAA is Taking Steps to Address Key Risks, but More Remains to Be Done: 

To address cost, schedule, and technical risks, the GOES-R program 
established a risk management program and has taken steps to identify 
and mitigate selected risks. However, more remains to be done to fully 
address a comprehensive set of risks. Specifically, the program has 
multiple risk watchlists and they are not always consistent. Further, 
key risks are missing from the risks lists, including risks associated 
with unfilled executive positions, limitations in NOAA's insight into 
NASA's deliverables, and insufficient funding for unexpected costs 
(called management reserve) on a critical sensor. As a result, the GOES-
R program is at increased risk that problems will not be identified or 
mitigated in a timely manner and that they could lead to program cost 
overruns and schedule delays. 

GOES-R Has a Risk Management Program and Is Taking Measures to Address 
Selected Risks: 

The GOES-R program office established a risk management program and is 
tracking and mitigating selected risks. Risk management is a leading 
management practice that is widely recognized as a key component of a 
sound system development approach. An effective risk management 
approach typically includes identifying, prioritizing, and mitigating 
risks, and escalating key risks to the attention of senior management. 

In accordance with leading management practices, the GOES-R program 
identifies risks, assigns a severity rating to risks, tracks these 
risks in a database, plans response strategies for each risk in the 
database, and reviews and evaluates these risks during monthly program 
risk management board meetings. Programwide and project-specific risks 
are managed by different offices. The program office identifies and 
tracks programwide risks--those that affect the overall GOES-R program. 
NASA's flight project office and NOAA's operations project office 
manage risks affecting their respective aspects of the 
program.[Footnote 6] Further, the program office briefs senior 
executives on top program and project risks on a monthly basis. 

GOES-R Program Office Identified and Is Working to Mitigate Programwide 
Risks: 

As of July 2007, the program office identified three program risks 
affecting the overall GOES-R program. These risks include the 
development of the integrated master schedule, the ability to secure 
authorization to use a key frequency band to meet the space-to-ground 
communication data link requirements for the GOES-R system, and the 
final approval of the GOES-R mission requirements from the NOAA Deputy 
Undersecretary. 

NOAA is working to mitigate and close program risks that it is 
tracking. For example, the program office recently closed the risk 
associated with GOES-R requirements because it had sufficiently defined 
and obtained approval of these requirements. As another example, the 
program office considers the lack of an integrated master schedule to 
be its highest priority risk. Program officials reported that 
completion of the integrated master schedule is driven by the 
completion of the intermediate schedules for the ground segment and the 
space-to-ground interdependencies. Key program staff members, including 
a resident scheduler, meet on a weekly basis to resolve outstanding 
design issues and hone these schedules. Program officials reported that 
the intermediate schedules are near completion and that they plan to 
have the integrated master schedule completed in Fall 2007. They expect 
to remove this issue from the risk watchlist at that time. 

NASA Identified Flight Segment Risks and Is Working to Mitigate Them: 

As of July 2007, the NASA flight project office identified four risks 
affecting instrument development, all of which are classified as medium 
risk. The top three risks pertain to the advanced imaging instrument, 
ABI--including issues on timely and quality subcontractor delivery of a 
critical part, stray light negatively impacting the performance of the 
optical system, and meeting specified performance requirements on image 
navigation and registration. The fourth priority risk pertains to the 
improvement of subcontractor quality assurance on a key sensor for the 
Space Environmental In-Situ Suite. 

NASA is working to mitigate the flight segment risks that it is 
tracking. For example, the ABI contractor, among other things, plans to 
complete a key simulation review before the end of the year (called the 
structural thermal optical performance analysis) to evaluate whether 
the instrument can meet its expected performance parameters for image 
navigation and registration. NASA also recently conducted a vendor 
facility assessment of the Space Environmental In-Situ Suite 
subcontractor to determine whether adequate quality assurance 
improvements had been made to be compliant with contract requirements. 
These actions are expected to help mitigate the risk. 

NOAA Identified Risks in its Operations Segment and Is Working to 
Mitigate Them: 

As of July 2007, the NOAA operations project office identified five 
risks impacting the management and development of the ground system and 
operations, including one that is identified as a medium risk. These 
risks include, among other things, inadequate definition of flight and 
operations project interdependencies, algorithm development 
responsibilities, and the adequate definition of coordination 
requirements between the space and ground segments to ensure that the 
two requests for proposals are consistent. 

NOAA is working to mitigate the ground system and operations risks that 
it is tracking. For example, for the highest priority risk regarding 
schedule interdependencies, key staff from both the flight and 
operations projects meet weekly in order to identify and synchronize 
project schedules. The project office expects to close this risk in 
Fall 2007. 

Multiple Watchlists Are Not Consistent, Making it Difficult to 
Prioritize and Manage Risks: 

While GOES-R has implemented a risk management process, its multiple 
risk watchlists are not consistent in areas where there are 
interdependencies between the lists, which makes it difficult to 
effectively prioritize and manage risks at the appropriate 
organizational levels. Sound risk management practices call for having 
a consistent prioritization approach and for significant problems to be 
elevated from the component level to the program level. This is because 
an issue affecting a critical component could have severe programmatic 
implications and should be identified, tracked, and overseen at the 
program level. In addition, program executives should be briefed 
regularly on the status of key risks. 

However, on the GOES-R program, the risks identified on the multiple 
risk lists are inconsistent in areas where there are interdependencies 
between the lists. These interdependencies include situations where a 
risk is raised by one project office and affects the other project 
office, but is not identified by the other project office or elevated 
to the program level risk list. They also include situations where a 
risk identified by a project office has programwide implications, but 
is not elevated to the program level risk list. For example, the 
operations project office identified schedule interdependencies between 
the flight and operations project offices as a medium criticality risk, 
but neither the flight project office nor the program identified this 
risk even though it is relevant to both. As another example, the 
operations project office identified the ground procurement schedule as 
a major issue in its briefing to senior management, but this risk was 
not identified on its own or on the programwide risk lists. 

In addition, while the three offices brief senior management about 
their key risks on a monthly basis, selected risks may not be 
accurately depicted in these briefings because of the inconsistencies 
among the risk watchlists. For example, both the flight and operations 
project offices identified technical development issues as minor to 
moderate risk areas, but the program office did not identify this item 
as a risk and, when it briefed senior management, it noted that 
technical development was in good shape. Figure 1 depicts examples of 
inconsistencies among risk lists and briefings to senior management. 

The lack of consistency in managing risks in areas where there are 
interdependencies makes it difficult to ensure that all identified 
risks are appropriately prioritized and managed. This situation hampers 
the program office's ability to identify and mitigate risks early on 
and to anticipate and manage the impact of risks on other areas of the 
program. 

Figure 1: Examples of Inconsistencies among GOES-R Risk Watchlists, as 
of July 2007: 

[See PDF for image] 

GAO analysis of NASA and NOAA data. 

[End of figure] 

Important GOES-R Management Risks Are Missing from the Program 
Watchlist: 

To be effective, a risk management program should have a comprehensive 
list of risks. However, several key risks that impact the GOES-R 
procurement and merit agency attention are not identified in the 
program's risk lists. These risks include (1) key leadership positions 
that need to be filled, (2) NOAA's limited insight into NASA's 
deliverables, and (3) insufficient management reserves (held by the 
program and a key instrument contractor). At the conclusion of our 
review for the accompanying report, program officials stated that they 
are aware of these issues and are working to monitor them or address 
them, as warranted. Nevertheless, until these and other programwide 
risks are identified and addressed as part of a comprehensive risk 
management program, there is increased likelihood that issues will be 
overlooked that could affect the acquisition of the GOES-R system. 

Key GOES-R Leadership Positions Need to be Filled: 

The two senior GOES-R program positions--the system program director 
and deputy system program director--are currently filled by NASA and 
NOAA personnel in an acting capacity until they can be permanently 
filled by NOAA. In addition, the acting system program director is not 
able to work full time in this role because she is also on a special 
assignment as the NESDIS Deputy Assistant Administrator for Systems. 
NOAA reported that it plans to fill the deputy system program director 
role in the near future, but noted that it could take more than 6 
months to fill the system program director role. Given the approach of 
the development phase of the GOES-R acquisition and the competing 
priorities of the acting system program director, it is especially 
important that these key leadership positions be filled quickly. At the 
conclusion of our review, agency officials stated that they are aware 
of this issue and are working to fill the positions, but they did not 
believe the issue warranted inclusion on the program level risk watch 
list. However, without the senior level attention inherent in a sound 
risk management program, it is not clear that NOAA is sufficiently 
focused on the importance of establishing knowledgeable and committed 
program executives, or in moving quickly to fill these critical 
positions. 

NOAA's Insight into NASA's Program Elements Is Limited: 

NOAA's March 2007 decision to adopt an acquisition management approach 
similar to prior GOES procurements could make the agency vulnerable to 
repeating some of the problems experienced in the past. In particular, 
our work on the GOES I-M series found that NOAA did not have the 
ability to make quick decisions on problems because portions of the 
procurement were managed by NASA.[Footnote 7] In fact, NOAA officials 
originally intended to depart from this approach as a lesson they 
learned from the GOES I-M acquisition, because it limited the agency's 
insight and management involvement in the procurement of major elements 
of the system. 

The established NOAA/NASA interagency agreements require NASA to submit 
monthly contractor cost performance reports to NOAA and to alert NOAA 
should cost and schedule performance drop below certain thresholds. 
NASA is currently submitting the required reports and has alerted NOAA 
on major cost and schedule changes. However, these interagency 
agreements do not contain provisions that enable NOAA to ensure that 
the data and reports are reliable and that they accurately depict 
contractor performance. To do so would entail NOAA having the ability 
and means to question and validate data, such as by having direct 
access to the contractor. 

NASA and NOAA officials reported that the two agencies are working 
together with an unparalleled level of transparency and noted that NOAA 
program staff have access to contractor data and can bring any 
questions with the data to the relevant NASA staff. However, they 
acknowledged that this process is not documented and were not able to 
demonstrate that NOAA staff had questioned contract data and that NASA 
had facilitated obtaining answers to the questions. By not identifying 
and mitigating this risk on its program risk list, NOAA increases the 
likelihood that the GOES-R program will repeat the management and 
contractor shortfalls that plagued past GOES procurements. 

Recent Changes on a Key Instrument Have Reduced Program Management 
Reserve Funds and Limited Contractor Reserve Funds Leave GOES-R 
Vulnerable to Future Cost Increases: 

A recent modification to the critical ABI instrument contract increased 
its cost, thereby reducing the amount of management reserve funds held 
by the program office for unexpected expenses. In September 2006, we 
reported that ABI was experiencing technical challenges, that were 
resulting in cost and schedule overruns. Since then, the contractor 
continued missing cost and schedule targets--a trend that continued 
until February 2007. At that time, NASA modified the contract to 
implement a revised baseline cost and schedule. The added cost of this 
modification was funded using management reserve funds held by the GOES-
R program office.[Footnote 8] As a result, the amount of reserve held 
by the program office dropped below 25 percent--a level that NOAA 
reported it intended to establish as a lesson learned from other 
satellite acquisitions. As of July 2007, the program's reserve level 
was at about 15 percent. Program officials stated that their revised 
goal is to maintain between 10 and 15 percent in reserve at the program 
level. While maintaining a 10 to 15 percent management reserve is on 
par with other major satellite acquisitions, the depletion of 
management reserves this early in the GOES-R acquisition raises 
concerns that there will be insufficient reserves during the 
challenging development, integration, and testing phases to come. 

In addition, the contractor for the ABI instrument has a very low level 
of reserve funding for unexpected costs, which means that any 
unexpected problems will likely lead to cost growth on the overall GOES-
R program. As of May 2007, the contractor was holding less than 1 
percent of funding in reserve to cover unexpected costs associated with 
the 40 percent of work left to be completed. As such, there is a risk 
that the new baseline could fail due to inadequate reserves to finish 
the program. This would likely have a diminishing effect on the reserve 
held by the GOES-R flight project and the program office to cover the 
costs of a second revised baseline plan. Our prior work on system 
acquisitions has shown inadequate reserves to be an indicator of poor 
management performance that could lead to cost overruns.[Footnote 9] 
Considering that GOES-R has not yet entered the development and 
production phases, it will be critical for NOAA's senior executive 
management to aggressively manage this risk. By not identifying, 
mitigating, and tracking this risk in a programwide risk list, the GOES-
R program runs an increased risk that unanticipated issues on the ABI 
instrument will lead to programwide cost overruns and schedule delays. 

Implementation of GAO Recommendations Should Improve NOAA's Ability to 
Effectively Manage the GOES-R Procurement: 

To improve NOAA's ability to effectively manage the procurement of the 
GOES-R system, we recommended in our accompanying report[Footnote 10] 
that the Secretary of Commerce direct the Undersecretary of Commerce 
for Oceans and Atmosphere to take the following two actions: 

* Ensure that the GOES-R program office manages, mitigates, and reports 
on risks using a program-level risk list that is reconciled with and 
includes risks from its flight and operations project offices that 
could impact the overall program. 

* Include the following risks on the programwide risk list, develop 
plans to mitigate them, and report to senior executives on progress in 
mitigating them: 

- unfilled or temporary GOES-R program leadership positions, 

- insufficient program insight on NASA contract performance, and: 

- insufficient management reserve on the critical Advanced Baseline 
Imager instrument and at the GOES-R program level. 

In written comments, Commerce agreed with our recommendations to use a 
program level risk list and to add selected risks to its list. The 
department reported that NOAA has established a consolidated 
programwide risk list that is to be used to evaluate risks during 
monthly internal and external reviews. Further, NOAA acknowledges the 
risks associated with having unfilled leadership positions and 
insufficient management reserves and is working to mitigate these 
risks. However, the department disagreed with our recommendation to 
manage and mitigate the risk that NOAA has insufficient insight into 
NASA's contracts. The department cited an unparalleled level of 
transparency between the two agencies and listed multiple regular 
meetings that the two agencies hold to ensure close coordination. While 
an improved working relationship between the two agencies is critical, 
NOAA has not provided any evidence that it has been able to effectively 
question and validate data on NASA's contractor performance. Given the 
past problems that NOAA has experienced in obtaining insight into 
NASA's contracts and the importance of this interagency relationship to 
the success of the GOES-R program, we believe that this issue should be 
managed and monitored as a risk. 

NOAA also requested that we acknowledge its effort to reconcile its 
program estimate with the independent estimate and reflect a 20 percent 
possibility that the program could cost $1 billion more than the 
current estimate of $7 billion, rather than $2 billion more. We 
acknowledge this in our report; however, the reconciliation effort is 
not complete and NOAA did not provide us with a reconciled estimate. 

In summary, although NOAA has made progress in the GOES-R procurement, 
changes in the GOES-R acquisition strategy could lead to cost overruns 
and schedule delays if not managed effectively. Over the last year, 
NOAA has completed preliminary design studies of its GOES-R system and 
decided to separate the space and ground elements of the program into 
two contracts and have NASA oversee the system integration effort. 
Current program plans call for a two-satellite program--estimated to 
cost about $7 billion--with launch of the first satellite in December 
2014. However, independent studies show that the program's cost could 
increase by about $2 billion and that the first launch could be delayed 
by at least 2 years. 

NOAA has taken steps to identify and address key risks but more could 
be done to effectively manage risks from a programwide perspective. In 
particular, the program has multiple risk watchlists that are not 
consistent in areas where there are interdependencies and key risks 
have not been elevated for programwide attention. Also, several risks 
that warrant NOAA's attention have not been placed on any watchlist. 
Specifically, the top two leadership positions are only temporarily 
filled; NOAA does not have the ability and means to obtain insight into 
NASA contracts in order to validate contractor performance data; and 
insufficient management reserves to handle unexpected problems on a 
critical instrument and at the program level are likely to affect 
overall program costs when any unexpected problems arise. Until NOAA 
manages and addresses a comprehensive set of program risks, the 
agency's ability to effectively manage the GOES-R acquisition will be 
significantly weakened and could lead to substantial program overruns 
and delays. 

Mr. Chairman, this concludes my statement. I would be happy to answer 
any questions that you or members of the subcommittee may have at this 
time. 

If you have any questions on matters discussed in this testimony, 
please contact me at (202) 512-9286 or by e-mail at pownerd@gao.gov. 
Other key contributors to this testimony include Carol Cha, Neil 
Doherty, Nancy Glover, Colleen Phillips (Assistant Director), and 
Teresa Smith. 

[End of section] 

Footnotes: 

[1] GAO, Geostationary Operational Environmental Satellites: Progress 
Has Been Made, but Improvements Are Needed to Effectively Manage Risks, 
GAO-08-18 (Washington, D.C.: Oct. 23, 2007). 

[2] GAO, Geostationary Operational Environmental Satellites: Additional 
Action Needed to Incorporate Lessons Learned from Other Satellite 
Programs, GAO-06-1129T (Washington, D.C.: Sept. 29, 2006) and 
Geostationary Operational Environmental Satellites: Steps Remain in 
Incorporating Lessons Learned from Other Satellite Programs, GAO-06-993 
(Washington, D.C.: Sept. 6, 2006). 

[3] These were called Program Definition and Risk Reduction contracts. 

[4] NASA has not yet issued a development contract for the 
Geostationary Lightning Mapper. This contract is expected to be awarded 
at the end of October 2007. 

[5] This independent review team, comprised of former senior industry 
and government space acquisition experts, was hired by NOAA to assess 
the adequacy of the GOES-R program's management approach, acquisition 
strategy, and resource availability, among other things. 

[6] NASA's GOES-R flight project office is responsible for the 
spacecraft, instruments, and launch services. NOAA's GOES-R operations 
project office is responsible for the ground elements and on-orbit 
operations of the satellites. 

[7] GAO-06-993. 

[8] This reserve is intended to cover expected costs above those 
projected by the contractor and unexpected costs in solving problems 
during a system development program. 

[9] GAO-06-993. 

[10] GAO-08-18.

GAO's Mission: 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, DC 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, DC 20548: 

Public Affairs: 

Susan Becker, Acting Manager, BeckerS@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, DC 20548: