This is the accessible text file for GAO report number GAO-06-991T 
entitled 'Tactical Aircraft: Questions Concerning the F-22A's Business 
Case' which was released on July 25, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony before the Subcommittee on Tactical Air and Land Forces, 
Committee on Armed Services, House of Representatives: 

United States Government Accountability Office: 

GAO: 

For Release on Delivery Expected at 9:30 a.m. EST: 

Tuesday, July 25, 2006: 

Tactical Aircraft: 

Questions Concerning the F-22A's Business Case: 

Statement of David M. Walker, Comptroller General of the United States: 

GAO-06-991T: 

GAO Highlights: 

Highlights of GAO-06-991T, a testimony before the Subcommittee on 
Tactical Air and Land Forces, Committee on Armed Services, House of 
Representatives 

Why GAO Did This Study: 

The F-22A—the Air Force’s next generation air superiority fighter 
aircraft—incorporates a low observable (stealth) and highly 
maneuverable airframe, advanced integrated avionics, and a new engine 
capable of sustained supersonic flight without the use of afterburners. 
The F-22A acquisition history is a case study in increased cost and 
schedule inefficiency. Since the program’s inception in 1986, the Air 
Force has added new requirements, more than doubled the length of the 
acquisition schedule, cut purchase quantities by more than 75 percent, 
and increased total acquisition unit costs by more than 100 percent. 

The F-22A program’s significant cost and schedule growth is 
illustrative of a number of systemic problems in the Department of 
Defense’s (DOD) major weapon system acquisitions. Currently, DOD is 
proposing to buy the remaining 60 F-22As under a 3-year contract. At 
the request of this subcommittee, GAO was asked for its views on DOD’s 
latest plan to restructure the program and on the Air Force’s request 
for authority to enter into a multiyear contract to implement this 
restructuring. 

What GAO Found: 

Under DOD’s latest restructuring of the F-22A program, as reflected in 
the fiscal year 2007 President’s budget, the program will spread the 
production of the remaining 60 aircraft over 3 lots extending the 
period of production by 2 years. The Air Force states that this is to 
avoid a gap in the production capabilities of the industrial base 
sector responsible for the latest generation of tactical fighter 
aircraft. Stretching out the production period will result in lower 
annual production rates and increased costs to the program of $1.7 
billion when compared to the costs the program would have incurred 
under the fiscal year 2006 President’s Budget proposal to buy the then-
remaining quantity of 56 F-22As in two annual lots. The restructured F-
22A program’s increased costs to complete the production will reduce 
the Department’s options in fulfilling other important national 
security priorities. 

Having made the decision to extend the program, the Air Force, in an 
attempt to reduce some of the costs of the restructured program, is 
proposing that Congress authorize its use of a multiyear contract to 
buy the remaining aircraft. The Air Force has concluded that it has met 
the six statutory criteria required for entering into a multiyear 
contract. GAO offers several points for congressional consideration. 
The Air Force estimates savings of approximately $225 million, 2.7 
percent of remaining procurement cost for 56 aircraft—a significantly 
lower estimated savings percentage than past multiyear procurement 
program estimates, which averaged 13 percent. The Air Force wants to 
buy 4 additional aircraft at a cost of $674 million to save an 
additional $10 million, but has not yet funded this plan. Finally, the 
statute requires that production rates and quantities remain 
substantially unchanged during the contract period as downward 
adjustments could impact contract prices and savings. F-22A quantities 
have fluctuated recently and further downward adjustments after signing 
a multiyear contract could result in cancellation costs as high as $201 
million currently not funded. 

Figure: Changes in F-22A Procurement Quantities and Effect on Unit 
Costs: 

[See PDF for Image] 

Source: U.S. Air Force (data); GAO (presentation). 

[End of Figure] 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-991T]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Michael J. Sullivan at 
(202) 512-4841 or sullivanm@gao.gov. 

[End of Section] 

Mr. Chairman and Members of the Subcommittee: 

I am pleased to be here today to discuss the Department of Defense's 
(DOD) proposal to buy sixty F-22As under a multiyear contract. As you 
know, GAO has recommended that the Air Force prepare a new business 
case for the F-22A program to justify the substantial changes planned 
in the mission roles and the quantities to be acquired--a 
recommendation that has yet to be implemented. Additionally, we share 
the Congress's concerns over DOD's wherewithal to acquire the F-22A and 
other key assets in light of current and expected resource constraints. 
Over the past several years, it has become increasingly clear that DOD 
must reassess what is affordable and separate its many wants from its 
real needs. DOD must make tough acquisition choices in order for the 
country to begin to address the large and growing fiscal imbalance it 
faces. 

My statement today--which is based on our recent report on the F-22A 
program[Footnote 1]--will highlight our key concerns with moving 
forward with F-22A procurement, as DOD proposes. Our work was performed 
in accordance with generally accepted government auditing standards. 

Summary: 

Our review indicates that DOD's proposal to add 2 years to the 
production period of the remaining F-22A's and to procure the planes 
under a 3-year multiyear contract will cost about $1.7 billion more 
than called for to procure the last two annual lots as compared to the 
amount previously provided in the fiscal year 2006 budget. The primary 
reasons cited for this change to the program are industrial base health 
and the need to preserve the F-22A production line until production of 
the Joint Strike Fighter (JSF) begins. The Air Force has reported to 
Congress that the F-22A program meets the criteria set forth in section 
2306b of Title 10 of the U.S. Code for a multiyear contract. We have 
serious concerns regarding whether all of the criteria have been 
satisfied (i.e. substantial savings, sufficient funding, and stable 
quantities). 

First, the timing of the proposal--near the end of the F-22A's 
acquisition--reduces the ability of the program to achieve substantial 
savings. Savings are currently estimated to be about $225 million or 
2.7 percent of remaining procurement cost if 56 additional aircraft are 
purchased--a savings that, in terms of percentage of costs, is far 
below historic estimates of savings for other multiyear contracts. 
Second, the Air Force is proposing to buy 4 additional aircraft--60 in 
total--at an added cost of $674 million in order to save an additional 
$10 million under the multiyear contract; however, it has not funded 
the proposal. Finally, to satisfy other needs in DOD, F-22A quantities 
have been unstable over the last 2 years reducing quantities from 279 
aircraft to 179 in the fiscal year 2006 budget and increasing 
quantities to 183 aircraft in the fiscal year 2007 budget. If 
quantities continue to fluctuate downward it could result in additional 
costs. For example, according to the Air Force cancellation costs alone 
could be as much as $201 million--a sum currently unfunded in the 
multiyear proposal. This financial risk, when compared to the savings 
projected from a multiyear contract, raises additional questions about 
the proposal and limits flexibility for future decision making. 

Background: 

The F-22A program is illustrative of a number of systemic problems in 
DOD's acquisition system. First, the F-22A was approved in an 
environment with no clear agreement on enterprise-wide priorities and 
without due consideration of current and likely future threats and 
resource constraints. Second, the requirements and key program 
specifications were not fixed when the program began and have changed 
over its decades-long development. Third, key procurement decisions 
were made without adequate consideration of technology and other 
program risks, with costly consequences. And finally, in this program 
as in many others, DOD has paid out significant incentive and award 
fees to its contractors despite large cost overruns and schedule 
delays. 

The program has been a case study in cost increases and schedule 
inefficiency in major weapon system acquisitions. We have issued 
numerous reports over the years on the problems and issues associated 
with the F-22A development program. Beginning in 1986 the program was 
expected to complete development in 9 years for an estimated cost of 
$12.6 billion. After taking 19 years to complete development in 
December 2005, development costs were reported at $26.3 billion--109 
percent more than expected. The end result of these inefficiencies in 
the acquisition program has been a loss of buying power as the reduced 
quantity of aircraft will require a significantly higher unit cost than 
expected. Figure 1 shows the changes in procurement quantities over 
time and allocates both development and procurement costs to those 
changing procurement quantities to show the trend of average total 
acquisition unit costs and procurement unit costs. 

Figure 1: Changes to Quantities and Costs of F-22As as Program Has 
Evolved: 

[See PDF for image] 

Sources: U.S. Air Force (data); GAO (presentation). 

[End of figure] 

While the F-22A program has completed development and testing of its 
initially planned air-to-air capability, the Air Force now sees a need 
to develop more robust air-to-ground attack and intelligence-gathering 
capabilities. Therefore, it has started a multibillion dollar 
development program for these additional capabilities. These 
capabilities were not previously considered a primary role for the F- 
22A as it was intended to be primarily an air-to-air fighter to replace 
the F-15. From the outset the F-22A was built to counter expected large 
numbers of new advanced Soviet fighter aircraft but this threat never 
materialized. The expanded air-to-ground attack capability is intended 
to allow the F-22A to engage a greater variety of ground targets, such 
as surface-to-air missile systems, that have posed a significant threat 
to U.S. aircraft in recent years. 

DOD's Latest Restructuring Is More Expensive and Slows F-22A 
Deliveries: 

Amidst changes to expand F-22A missions and roles, the procurement 
quantities and acquisition strategy have also been in flux in recent 
years. In December 2004, the Office of the Secretary of Defense (OSD) 
reduced planned quantities to a total of 179 F-22A aircraft. At the 
same time, it decided to terminate the procurement program at the end 
of 2008 in order to free up about $10 billion for other priorities. 
Then, the fiscal year 2007 budget extended the procurement program 2 
years, to 2010. The department cited the health of the industrial base-
-the need for maintaining a fifth generation fighter[Footnote 2] 
production line--as its rationale for this added expense and delay. DOD 
also proposed buying four additional aircraft and using a 3-year 
multiyear contract to procure the remaining 60 F-22As to mitigate some 
of the costs of extending procurement for at least 2 years. 

To identify savings that might reduce the cost impact of the 
restructured acquisition strategy, the Air Force is proposing a 
multiyear contract to buy the remaining F-22A aircraft. The Air Force 
formulated an estimate for three annual contracts to compare to a 
single multiyear contract to buy 56 aircraft. While this comparison can 
provide a basis for determining potential savings, the Air Force had 
not previously planned to buy the remaining aircraft over 3 years. 
Instead, the fiscal year 2006 President's Budget included procurement 
costs to buy 56 F-22As in two annual lots--29 F-22As in 2007 and 27 F- 
22As in 2008. Therefore, even utilizing the multiyear contract 
authority, the restructuring will add $1.7 billion in cost to the 
procurement program and slow deliveries of the final aircraft when 
compared to the plan previously provided for in DOD's fiscal year 2006 
budget. The final 60 aircraft will each cost 10 percent more on average 
(unit procurement costs increase from $166 million per aircraft to $183 
million per aircraft) under the restructured plan, even taking into 
account expected savings from the multiyear procurement. 

Concerns Whether DOD Satisfies All Multiyear Procurement Criteria: 

The Air Force submitted its justification to the Congress on May 16, 
2006, to buy the remaining 56 to 60 F-22A aircraft over a 3-year period 
with a multiyear contract. To enter into a multiyear contract for the F-
22A, the Air Force must first obtain specific legislative authorization 
in both the annual DOD appropriations act and in an authorization act. 
If authorization is obtained from Congress, the Air Force must also 
meet the statutory criteria listed in 10 U.S.C. § 2306b(a) for entering 
into a multiyear contract. The justification package the Air Force 
submitted to Congress in support of its request for authority to enter 
into a multiyear contract for the F-22A concludes that the statutory 
criteria for multiyear procurement have been met and that such a 
multiyear contract would provide substantial cost savings or avoidance 
over three annual lot buys. In reviewing these criteria and the Air 
Force's position, we have serious concerns regarding whether all of the 
criteria have been satisfied (i.e. substantial savings, sufficient 
funding and stable quantities). Table 1 lists the six criteria and our 
observations (we did not assess two of the criteria). 

Table 1: Observations of F-22A Multiyear Contract Criteria: 

Multiyear criteria: Contract will result in substantial savings; 
GAO observations: Substantial savings are not defined in the statute, 
but the 2005 F-22A Independent Cost Estimate states that between 1982 
and 1989 estimates for multiyear savings for proposed weapon systems 
averaged 13 percent. The Air Force justification package shows only 2.7 
percent cost avoidance ($225 million) for 56 aircraft. 

Multiyear criteria: Reasonable expectation agency head will request 
funding at required level to avoid contract cancellation; 
GAO observations: The Air Force has indicated that its multiyear budget 
is currently under funded by $674 million and is seeking authorization 
to use incremental funding rather than fully funding each aircraft lot. 

Multiyear criteria: Minimum need expected to remain substantially 
unchanged during contract period in terms of production rates and total 
quantities; 
GAO observations: F-22A quantities have changed in the last 2 fiscal 
years to accommodate the need to fund other annual priorities. Given 
the potential for other priorities in the future--military presence 
overseas, global war on terrorism, and response to natural disasters--
there is a risk that F-22A quantities would need to be adjusted again. 
Quantity reductions could result in cancellation costs of as much as 
$201 million, an amount that is currently unfunded. 

Multiyear criteria: There is stable design, and technical risks are not 
excessive; 
GAO observations: The baseline F-22A aircraft design is stable (the 
proposed multiyear contract is for the baseline aircraft). While not 
the subject of the proposed multiyear contract because it is a separate 
effort, the design for adding new ground attack and ISR capabilities 
has not been demonstrated through development or operational testing 
and cannot be considered "stable" at this time. 

Multiyear criteria: Estimates of contract cost and cost avoidance are 
realistic; 
GAO observations: Not assessed. 

Multiyear criteria: Use of the multiyear contract will promote national 
security of the United States; 
GAO observations: Not assessed. 

Source: GAO Analysis and 10 U.S.C. 2306b. 

[End of table] 

Substantial Savings Criterion: 

To identify potential savings, the Air Force formulated an estimate for 
three annual contracts to compare to a single multiyear contract with 
buys of 56 and 60 aircraft. Section 2306b of Title 10 of the U.S. Code 
does not define what constitutes substantial savings, but the 2005 F- 
22A Independent Cost Estimate[Footnote 3] indicates that from 1982 to 
1989, DOD proposed at least 60 multiyear procurement programs for 
congressional approval, with estimated savings averaging 13 percent. 
The Air Force estimates F-22A multiyear procurement savings to be 2.7 
percent if 56 aircraft are procured, approximately $225 million. The 
justification package also shows that an additional $10 million could 
be saved by buying 60 aircraft as stated in the fiscal year 2007 
President's Budget, but it would require an additional $674 million not 
included in the fiscal year 2007 future year defense plan. 

Funds Have Not Been Budgeted: 

The proposed multiyear contract for 60 F-22As submitted with the fiscal 
year 2007 budget is under funded by about $674 million--funds the Air 
Force believes it will need in fiscal years 2008 through 2010 to 
complete these buys. Additionally, the Air Force has proposed using 
incremental funding to pay for the multiyear contract. Instead of fully 
funding the buy for each fiscal year, this proposal plans four funding 
increments--economic order quantity, advanced buy, subsystem, and final 
assembly. Incremental funding for multiyear procurement is neither 
permitted by the annual DOD appropriations act[Footnote 4] nor the 
multiyear authorizing statute, which requires that funds only be 
obligated under a multiyear contract "for procurement of a complete and 
usable end item."[Footnote 5] The Air Force is seeking an exception to 
these requirements in its request to Congress for statutory 
authorization for the multiyear contract. The congressional defense 
committees are aware of the concerns with incremental funding, and 
those committees that have completed a defense bill have provided full 
funding for the initial year of the proposed multiyear contract. 
However, the congressional authorization and appropriations processes 
are ongoing. 

Multiyear Contract Quantities Could Be Changed in the Future: 

OSD has restructured the F-22A acquisition program twice in the last 2 
years in order to allocate funds to other priorities. In December 2004, 
OSD reduced the program from 279 to 179 F-22As to save $10.5 billion. 
Then in December 2005, OSD changed the F-22A program again, adding $1 
billion to extend the production line for 2 years to ensure a fifth 
generation fighter aircraft production line would remain in operation 
in case the JSF experiences delays or problems. So far we have not seen 
detailed rationale concerning the impact to the health of the 
industrial base. OSD also added 4 aircraft at this time for a total of 
183 F-22As. We have also not seen the threat based justification for 
buying these additional aircraft at an estimated cost of $674 million. 
Given the potential for priorities to change again in the future to 
fund the military presence in Iraq and Afghanistan, fight terrorism 
around the globe, fund the response to natural disasters, or for other 
reasons, there is risk that F-22A quantities under the proposed 
multiyear contract would need to be adjusted again. According to the 
Air Force's multiyear proposal, if a reduction in quantity were to 
happen, it could result in cancellation costs of as much as $201 
million in fiscal year 2007, the first year of the multiyear contract. 
The current Air Force acquisition strategy does not fund these 
potential cancellation costs. Therefore, the Air Force would have to 
find funds from other sources to pay these costs in the event 
quantities are reduced. This is therefore a risk that must be weighed 
in approving a multiyear contract for the F-22A, particularly at this 
late stage of its procurement program as it could limit the flexibility 
of decision makers in the future. 

Other Factors Influence the Practicality of Using Multiyear Contracts 
at This Stage in the F-22A Program: 

Other circumstances argue against using a multiyear contract. Multiyear 
contracts are typically used earlier in an acquisition program when 
greater efficiencies in buying materials and subsystems can be achieved 
and thereby provide more substantial savings at both the prime 
contractor and subcontractor levels. In the case of the F-22A, the 
multiyear proposal comes at the end of production. At the same time, 
the F-22A program plans to reduce the annual buying rate, providing 
less opportunity to incur savings. Previously, the Air Force had 
planned to purchase 29 and 27 aircraft in fiscal years 2007 and 2008, 
respectively. The multiyear plan calls for 20 aircraft a year in 2008, 
2009, and 2010--7 to 9 aircraft fewer in each of the 2 years under the 
previous plan. Additionally, it appears the primary purpose for 
proposing a multiyear contract was to mitigate the additional cost of 
extending procurement for an additional 2 years; even with the proposed 
multiyear contract, procurement costs will be $1.7 billion higher than 
costs proposed under the previous program structure. 

The length of the proposed multiyear contract and the lower quantity of 
aircraft planned for multiyear are concerns identified in the May 2006 
Air Force business case analysis for F-22A multiyear procurement. For 
example, the business case analysis states that the average number of 
air vehicles procured under a multiyear contract was 308[Footnote 6]-- 
more than five times the number of aircraft the F-22A program is 
proposing to buy under its 3-year contract. The analysis also 
acknowledges that there is limited opportunity to obtain additional 
savings from the previously planned initiatives to improve the F-22A 
production efficiency as these savings were obtained earlier in the 
acquisition cycle. 

In conclusion, the Air Force's decision to extend production for 2 
years for industrial base purposes has increased the length and cost of 
the F-22A program. We are not sure what the Air Force's rationale was 
for extending production and how it specifically relates to maintaining 
the industrial base so as to warrant an increased cost of at least $1.7 
billion. At the same time, our nation's large and growing long-term 
fiscal imbalance requires the federal government--especially DOD--to 
begin making hard choices between its many wants and real needs. In 
this context, we continue to believe that the Congress needs to 
reevaluate a range of existing federal programs and polices, including 
the F-22A program, based on credible current and future threats, 
current and expected future national budget levels and priorities, and 
the warfighter's many true needs. As it stands, the restructured F-22A 
program's increased cost to complete the procurement program--$1.7 
billion--will eventually serve to reduce the Department's options in 
fulfilling other important national security priorities. This at a time 
when the difference between DOD's program wants and its expected 
resource levels is growing. 

FOOTNOTES 

[1] GAO, Tactical Aircraft: DOD Should Present a New F-22A Business 
Case before Making Further Investments, GAO-06-455R (Washington, D.C.: 
June 20, 2006). 

[2] F-22A and F-35 are considered fifth generation fighter aircraft as 
compared to the F-15, F-16, F/A-18, and F-117. The primary 
characteristics are Very Low Observable (VLO) stealth and information 
fusion capabilities that make fifth generation aircraft more survivable 
and lethal. 

[3] F/A-22 Independent Cost Estimate, Institute for Defense Analyses, 
August 2005. 

[4] Section 8008 of the fiscal years 2005 and 2006 Department of 
Defense Appropriations Acts (Public Laws 108-287 and 109-148, 
respectively) require full funding of units to be procured. 

[5] 10 U.S.C. § 2306b (i)(4)(A). This restriction was added by section 
820 of the Bob Stump National Defense Authorization Act for Fiscal Year 
2003 (Public Law 107-314). 

[6] The Institute for Defense Analysis analyzed the multiyear 
procurement programs for the F/18, C-17, C-130J/KC-130, and F-16. 
Institute for Defense Analysis, F-22A Multiyear Procurement Business 
Case Analysis (May 2006).

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: