This is the accessible text file for GAO report number GAO-06-827T 
entitled 'Capitol Visitor Center: Update on Status of Project's 
Schedule and Cost as of June 28, 2006' which was released on June 28, 
2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on the Legislative Branch, Committee on 
Appropriations, U.S. Senate: 

United States Government Accountability Office: 

GAO: 

For Release on Delivery Expected at 10:30 a.m. EDT: 

Wednesday, June 28, 2006: 

Capitol Visitor Center: 

Update on Status of Project's Schedule and Cost As of June 28, 2006: 

Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical 
Infrastructure Issues: 

GAO-06-827T: 

Mr. Chairman and Members of the Subcommittee: 

We are pleased to be here today to assist the Subcommittee in 
monitoring progress on the Capitol Visitor Center (CVC) project. Our 
remarks will focus on the Architect of the Capitol's (AOC) progress in 
achieving selected project milestones and in managing the project 
schedule since the Subcommittee's May 24, 2006, hearing on the 
project.[Footnote 1] As part of this discussion, we will address a 
number of key challenges and risks that continue to face the project, 
as well as actions AOC has taken or plans to take to address these 
risks. In addition, we will discuss the status of the project's costs 
and funding. 

Our remarks today are based on our review of schedules and financial 
reports for the CVC project and related records maintained by AOC and 
its construction management contractor, Gilbane Building Company; our 
observations on the progress of work at the CVC construction site; and 
our discussions with the CVC team (AOC and its major CVC contractors), 
AOC's Chief Fire Marshal, and representatives from the U.S. Capitol 
Police. We also reviewed AOC's construction management contractor's 
periodic schedule assessments and daily reports on the progress of 
interior wall and floor stonework. 

In summary: 

Since the Subcommittee's May 24 CVC hearing, AOC has extended the 
project's scheduled completion and opening dates. The CVC team has 
continued to move the project's construction forward, but primarily 
because of significant problems associated with the CVC's fire 
protection system, gift shops, and utility tunnel, AOC has extended the 
scheduled completion dates for the base CVC project and the House and 
Senate expansion spaces by approximately 2-1/2 months, from February 
23, 2007, to May 7, 2007, for the CVC, and from May 25, 2007, to August 
8, 2007, for the expansion spaces. Furthermore, to allow time for 
possible additional delays and preparation for operations, AOC is now 
proposing to open the CVC in July 2007 with a temporary certificate of 
occupancy and the expansion spaces in August 2007, at which point a 
final certificate of occupancy will be issued for the CVC. Previously, 
AOC was planning to open the CVC in April 2007 and the expansion spaces 
in May 2007. We are reassessing the project schedule, as we stated at 
the Subcommittee's last CVC hearing, and expect to finish our 
reassessment by mid-September. Pending our reassessment, AOC's new July 
and August 2007 time frames appear to be reasonable tentative targets 
for opening the CVC and House and Senate expansion spaces. However, we 
are not as confident as we would like to be about whether the CVC team 
will be able to meet the challenges, risks, and uncertainties that 
continue to face the project, given the difficulties the team has 
historically had in meeting its targets and milestones. Thus, we expect 
to have greater confidence in the target opening dates after we 
complete our schedule reassessment. 

* During the past month, work on the project has progressed in a number 
of areas. For example, the CVC team has finished restoring and has 
opened the portion of East Capitol Street that runs above the CVC's 
utility tunnel and has finished installing the veneer plaster portion 
of the ceiling in the great hall and piping for the sprinkler system 
throughout the CVC. In addition, critical interior wall and floor stone 
installation has continued, together with other interior and exterior 
construction work, and the sequence 2 contractor has continued work on 
its area-by-area plans to prevent trade stacking[Footnote 2] during 
finish work. About 96 percent of the interior wall stone for the CVC 
itself (excluding the atrium areas, the East Front, and the tunnels) is 
now installed. 

* Delays associated with the CVC's fire protection system, gift shops, 
and utility tunnel primarily led the CVC team to add about 50 workdays 
to the project schedule. During the last 5 weeks; the sequence 2 
contractor also fell short of its installation target for interior wall 
stone; the pace of floor stone installation remained far below the 
targeted pace; and several other base project and expansion space 
activities--including East Front work--fell further behind schedule. 
Indicators of construction progress that we have been tracking for the 
Subcommittee also support AOC's extensions of the proposed completion 
and opening dates. For example, the sequence 2 contractor met only 2 of 
the 14 milestones we have been tracking for this hearing, and this 
contractor's monthly billings indicate that construction work is more 
likely to be completed closer to AOC's new target dates than its 
previous ones. 

* AOC's new schedule provides additional time to complete work, and we 
believe, on the basis of the information available to us at this time, 
that AOC's July and August 2007 proposed opening dates tentatively 
appear reasonable; however, we have not yet finished reassessing AOC's 
schedule to better determine whether this additional time will be 
sufficient in view of the challenges, risks, and uncertainties that the 
project continues to face. For example, the CVC fire protection system 
has not yet been fully approved; critical building systems still have 
to be commissioned and tested; and certain design or work scope 
elements are still incomplete or are being clarified, refined, or 
changed, even though the project's overall design is essentially 
complete. In addition, the delays in completing the utility tunnel have 
created an additional risk: if the sequence 2 contractor has difficulty 
achieving and maintaining required temperature and humidity levels, the 
project's ceiling and finish work could be further delayed. More 
information should be available on this and other schedule-related 
issues by the time we finish reassessing the project schedule in mid- 
September, following the completion of AOC's reassessment, which is 
expected by July 31. 

Before the schedule changed this month, we were estimating that the 
total cost to complete the entire CVC project would be about $556 
million without an allowance for risks and uncertainties and $584 
million with such an allowance--an amount that we continue to believe 
should be sufficient. To date, about $530 million has been provided for 
CVC construction. The $26 million in remaining funds needed is 
consistent with our last estimate of the amount of additional funds AOC 
would need to complete the entire CVC project. In addition, as we have 
previously indicated, AOC preliminarily expects to need about $950,000 
in fiscal year 2007 AOC general administration appropriations to pay 
for the contractual support needed to complete acceptance testing of 
the facility's fire protection system in time to meet the project 
schedule. AOC plans to determine if it can reduce the amount needed for 
this contractual support; we will keep the Subcommittee apprised of 
this situation. Furthermore, AOC is likely to incur additional costs 
because of the problems associated with the CVC's fire protection 
system, gift shops, utility tunnel, and other issues. In light of these 
problems, we do not know whether the $556 million estimate, which does 
not include an allowance for risks and uncertainties, will cover the 
costs to complete the project, but we currently believe that our $584 
million estimate, which does include such an allowance, should be 
sufficient. We plan to reassess our cost-to-complete estimate this 
summer and provide our results to the Subcommittee by mid-September. 

AOC Has Extended the Project's Proposed Completion and Opening Dates: 

AOC has extended the CVC project's proposed completion and opening 
dates because, although the CVC team has continued to make progress in 
a number of areas since the Subcommittee's last CVC hearing, 
significant delays have also occurred, especially in work on the CVC's 
fire protection system, gift shops, and utility tunnel. Indicators of 
progress that we have been monitoring for the Subcommittee support 
AOC's extension of the proposed dates, and remaining challenges, risks, 
and uncertainties could further affect the project's progress. AOC's 
proposed time frames tentatively appear reasonable, but further 
reassessment of the project schedule is needed to gain greater 
confidence in the revised dates. 

AOC Has Postponed the Proposed Completion and Opening Dates about 2-1/ 
2 Months: 

According to the May 2006 project schedule, the base CVC project will 
be completed in May 2007 and the House and Senate expansion spaces will 
be completed in August 2007, about 2-1/2 months later than indicated in 
the April 2006 schedule. Moreover, according to the May schedule, the 
base project will be opened in July 2007 and the expansion spaces will 
be opened in August 2007--time frames that AOC believes will 
accommodate possible additional delays and allow start-up time for 
operations. 

According to the May 2006 schedule, most of the physical construction 
work in the CVC, the East Front, and the expansion spaces will be 
completed by December 31, 2006; however, some work in the exhibit 
gallery, the gift shops, and the East Front extends into 2007--as far 
as March 2007 for the gift shops and certain East Front work. Neither 
the CVC nor the expansion spaces can be opened until the Chief Fire 
Marshal has completed acceptance testing for the fire protection and 
life safety systems, now scheduled for May 2007 for the CVC and August 
2007 for the expansion spaces. The Chief Fire Marshal plans to issue a 
temporary certificate of occupancy for the CVC's base building when he 
completes his testing of it and a final certificate after he completes 
his testing of the expansion spaces and limited retesting of the CVC's 
base building. AOC believes that it may be able to shorten some of the 
time scheduled for testing the fire protection system and that it may 
be able to open segments of the expansion spaces earlier than August 
2007. As we have discussed in previous CVC testimonies, AOC is 
continuing to explore this possibility. 

Although the CVC team has had difficulty meeting milestones and 
continues to face challenges, risks, and uncertainties, the July 2007 
opening time frame for the CVC would give the team 2 to 3 months 
(depending on the specific date in July) after the May 7, 2007, 
scheduled completion date to address additional delays and prepare for 
operations. Some time could also be available in August to address 
issues associated with the acceptance testing of the expansion spaces, 
which is scheduled to begin on May 8, 2007, after the initial 
acceptance testing of the CVC is completed. Thus, AOC's July and August 
2007 time frames for opening the CVC and expansion spaces tentatively 
appear reasonable at this time pending our reassessment of the project 
schedule, to be done over the next several weeks. 

Construction Work Is Progressing: 

According to information provided by AOC and its construction 
management contractor and our observations, work on the project has 
advanced, in terms of both the dollar value of the work in place and 
individual project elements. In dollar terms, AOC's construction 
management contractor reported that, as of May 31, the overall CVC 
project was about 82 percent complete and the sequence 2 work was about 
71 percent complete-up from about 81 percent and 70 percent, 
respectively, as of April 30. Progress on individual project elements 
includes the following: 

* Surface work above the CVC utility tunnel was largely completed, 
leading to the opening of East Capitol Street in June, and work on the 
House connector tunnel has continued. 

* Interior CVC work has made additional progress, according to AOC's 
construction management and sequence 2 contractors. For example, the 
sequence 2 contractor has finished installing veneer plaster ceilings 
in the great hall; structural steel framing for the glass floor in the 
exhibit gallery; piping for the heating, air conditioning, and 
ventilation system throughout the CVC and expansion spaces; and piping 
for the sprinkler system throughout the CVC. Furthermore, the CVC team, 
the U.S. Capitol Police, and AOC's Fire Marshal Division have also 
resolved issues associated with the CVC's security and fire protection 
systems that, if not resolved, could have impeded construction 
progress. 

* Wall stone installation has progressed substantially in the East 
Front plaza level, atriums, and auditorium and continued in other 
areas, such as the food service area. As of last week, the sequence 2 
contractor had installed about 96 percent of the interior wall stone in 
the CVC itself, excluding the atrium areas, the East Front, and the 
tunnels. 

* On the East Front exterior, AOC and its construction management 
contractor reported, new waterproofing was installed under the center 
steps, a skylight structure was erected and glass was installed in the 
openings north and south of the great hall, and materials and equipment 
were delivered for the penthouse mechanical work. 

* In the House and Senate expansion spaces, progress was made in 
installing drywall, roughing in electrical systems, and performing work 
in other trade areas. 

Further Delays Have Occurred as Risks Have Materialized: 

Since the Subcommittee's May 24 hearing, problems have occurred in a 
number of areas that we expressed concerns about during the 
Subcommittee's last three CVC hearings, These include problems 
associated with the base project's fire protection system and the House 
and Senate gift shops, which have had the largest impact on the 
schedule--resulting in AOC's extension of the date for the CVC to 
obtain a temporary certificate of occupancy from February 23, 2007, as 
shown in the April schedule, to May 7, 2007, as shown in the May 
schedule. Problems have also delayed work on the CVC utility tunnel and 
the expansion spaces. 

To resolve issues associated with the base project's fire alarm system 
and gift shops, the CVC team added a net of 51 workdays to the 
project's May schedule, reflecting (1) additional time for resolving 
issues raised by AOC's Fire Marshal Division about shop drawings for 
the base CVC building's fire alarm system, (2) additional time for 
programming the fire alarm system, and (3) a change in the schedule 
logic involving the time for starting the programming. AOC's Fire 
Marshal Division completed its review on June 1 and approved most 
elements of the base building's fire alarm system, but raised a number 
of problems and concerns. For example, it found that the firefighter 
telephone system and manual pull stations proposed by the subcontractor 
did not meet contract specifications. In addition, the CVC team learned 
that the sequence 2 fire alarm system subcontractor did not plan to 
start programming the fire alarm system until all relevant issues, 
including those raised by the Fire Marshal Division about the CVC's 
fire alarm shop drawings and proposed fire alarm system equipment, were 
resolved. Because the programming had previously been scheduled 
concurrently with other activities, the team added time to the schedule 
for the programming. Work on the gift shops has been delayed because 
the estimated costs and bid price for their fit-out greatly exceeded 
the budget for this work. AOC planned to request approval from the 
House and Senate Committees on Appropriations to reprogram funds from 
CVC operations to construction to cover the shortfall and plans to move 
forward with the gift shops in segments by executing contract 
modifications based on the available funding until its reprogramming 
request is approved. However, AOC said that this reprogramming request 
did not include any contingency funding for the gift shops and 
therefore it anticipates having to request another reprogramming of 
funds for such contingency funding. The CVC team and the Fire Marshal 
Division established and have implemented an expedited process for 
resolving the identified problems and concerns, and according to the 
team and AOC's Chief Fire Marshal, the issues raised by the Fire 
Marshal Division about the CVC's fire alarm shop drawings and proposed 
fire alarm system equipment are being worked through for resolution and 
resubmission to the Fire Marshal Division. However, it is not yet clear 
how much time will be needed to address other fire protection system 
issues; the Fire Marshal Division has not yet completed its reviews of 
shop drawings for other components of the system because the design of 
the CVC's base building fire alarm system had to be approved first; and 
the gift shop design and funding issues have not been fully resolved. 
We plan to include these areas in our reassessment this summer. 

Delays associated with the CVC utility tunnel led the CVC team to 
extend the date for it to become operational from June 29, 2006, as 
shown in the April 2006 schedule, to August 4, 2006, as shown in the 
May 2006 schedule. These delays occurred because preliminary work on an 
old tunnel took longer than expected. The old tunnel, which contains 
piping from the Capitol Power Plant that is connected to piping in the 
CVC utility tunnel, was inaccessible before temporary shoring work was 
completed. According to AOC, this temporary shoring work was completed 
on June 16, and last week the CVC team began asbestos cleanup in the 
old tunnel, in the area where piping from the new tunnel is connected 
to piping in the old tunnel. After this cleanup is done, the CVC team 
is to continue work in the old tunnel necessary to enable steam and 
chilled water to flow from the Capitol Power Plant to the CVC. Given 
the history of problems associated with the utility tunnel, it is not 
clear at this time whether it will be operational on schedule, and 
additional delays could further adversely affect the project, as we 
will discuss later in our testimony. Several other base project 
activities--which we will discuss shortly--have also been delayed, but 
these delays have had a smaller impact. 

Delays in commissioning the air handling units and in installing 
ceiling tile in the expansion spaces during the past month will affect 
the project schedule, and some work has been resequenced, but the 
resequencing will not affect the schedule, according to the sequence 2 
contractor. The air handling units are necessary for testing the fire 
protection system in both the CVC and the expansion spaces, and the 
ceiling tile must be installed in the expansion spaces for that 
testing. According to the fit-out subcontractor, the ceiling tile work 
was delayed because the subcontractor doing the work had to wait for 
direction on audio-visual rough-in work. The sequence 2 contractor 
resequenced the installation of circular staircases in the House and 
Senate atrium areas because extensive concrete chipping in one atrium, 
which was required to correct out-of-tolerance sequence 1 work, and 
scaffolding set up in the atriums to install wall stone precluded the 
sequence 2 fit-out subcontractor from gaining access to work areas in 
both atriums. 

In addition to the construction-related adjustments to the schedule for 
the expansion spaces, the 51-workday delay in the CVC schedule produced 
a corresponding 51-workday delay in the schedule for the expansion 
spaces, extending their opening from May 25, 2007, as shown in the 
April schedule, to August 8, 2007, as shown in the May schedule. This 
extension will occur because, as we have discussed in our previous CVC 
testimonies, AOC plans to have most of the acceptance testing of the 
CVC's fire protection system completed before the acceptance testing of 
the expansion spaces begins.[Footnote 3] AOC believes that this 
sequential approach to the acceptance testing will allow the CVC to 
open with a temporary certificate of occupancy somewhat earlier than if 
the acceptance testing were performed concurrently. AOC is still 
considering opening the expansion spaces in sections, which means that 
some sections could possibly open earlier than August 8, 2007. 

Indicators of Construction Progress Support Extension of Project 
Schedule: 

Besides the delays that have already occurred, several indicators of 
construction progress that we have been tracking for the Subcommittee 
suggest that the revised completion and opening dates in AOC's May 2006 
schedule are more realistic than the previously scheduled dates. An 
update on these indicators follows: 

Sequence 2 contractor continues to miss milestones. Starting with the 
Subcommittee's June 2005 CVC hearing, at the Subcommittee's request, we 
and AOC have been selecting and tracking sequence 2 milestones to help 
the Subcommittee monitor construction progress. These milestones 
include activities that were either on the project's critical path or 
that we and AOC believe are critical to the project's timely 
completion. As figure 1 shows, the sequence 2 contractor has generally 
missed these milestones. For today's hearing, 14 of these milestones 
were due to be completed, according to the project's January 2006 
schedule. One was completed ahead of schedule, one was completed on 
schedule; and none of the remaining 12 had been completed as of June 
26. (See app. I.) AOC's sequence 2 contractor attributed the slippages 
to a number of factors, including the need to do remedial or 
preparatory work in the East Front and auditorium and the need to 
resolve outstanding issues and resequence work for a number of reasons, 
such as to prevent damage or to move materials stored in an area that 
was otherwise ready for the next stage of work. 

Figure 1: Sequence 2 Contractor's Progress in Meeting Selected 
Milestones as of CVC Hearing Dates: 

[See PDF for image] 

Source: Sequence 2 contractor, AOC and its construction management 
contractor, and GAO. 

[End of figure] 

In total, AOC's construction management contractor reported delays in 
17 of 23 critical and near-critical paths that AOC's construction 
management contractor identified as important to meeting the base 
project's overall completion date.[Footnote 4] According to AOC's 
construction management contractor, delays besides those in the fire 
protection system, gift shops, and utility tunnel have occurred in 
other activity paths since the Subcommittee's last CVC hearing. These 
other delays occurred in, but were not limited to, the East Front, the 
orientation theaters, the exhibit gallery, certain elevator 
installations, the upper level assembly room, and the House connector 
and Library of Congress tunnels. According to the CVC team, these other 
delays were attributable to design changes, water leaks, deficient 
sequence 1 work, changes in the sequence of work activities by the 
sequence 2 contractor, and inaccessible work areas. Even more important 
than the individual delays themselves, however, is their likely impact 
on the CVC team's ability to complete construction work on schedule. So 
many activities have fallen behind schedule that relatively short 
additional delays could push the CVC's overall completion date further 
back. The number of critical and near-critical paths increased from 21 
in the project's April schedule to 23 in the May schedule. 

Value of completed work is consistent with revised schedule. Another 
indicator of construction progress that we and AOC's construction 
management contractor have been tracking is the value of the completed 
construction work billed to the government each month. Both we and the 
construction management contractor believe that the sequence 2 
contractor's monthly billings, including the bills for March, April, 
and May 2006, indicate that AOC is more likely to finish closer to its 
currently scheduled completion dates than its previously scheduled 
completion dates. While this indicator has some limitations (for 
example, billings lag behind construction), it is generally regarded in 
the construction industry as a useful measure of how likely a project 
is to be completed on time. Figure 2 compares the sequence 2 
contractor's billings since May 2003 with the billings needed to 
complete construction work on schedule and indicates that the sequence 
2 contractor is unlikely to finish the project until the late spring or 
summer of 2007 unless the value of completed work increases 
significantly. We believe that a significant increase will be 
difficult, given the limited number of areas that will be ready for 
finish work at any given time. 

Figure 2: Total Billings by the Sequence 2 Contractor for the Entire 
CVC Project Compared with the Billings Needed to Finish Construction 
Work on Schedule: 

[See PDF for image] 

Source: AOC's construction management contractor. 

Notes: 

The early and late lines on this figure reflect the cumulative billings 
that would be required to complete the project through contract 
modification number 102 ($224.8 million total contact value) by the 
early and late finish dates shown in the sequence 2 contractor's 
schedule based on the September 2006 contractual completion date. 

The actual line reflects the sequence 2 contractor's actual monthly 
billings. 

Although bills are typically submitted for payment after work is 
completed, it is often likely that construction work will be completed 
on schedule when the actual billing line falls between the early and 
late lines in the figure. With respect to the CVC, the actual billing 
line has been trending below, and in March 2006 went below, the late 
finish line, where it remained in April and May 2006. Even with the lag 
in billings, this trend indicates that the amount of work being 
completed each month is not sufficient to finish the project on the 
project's previous schedule. 

[End of figure] 

Interior stone installation is taking longer than expected. Overall, 
about 80 percent of the CVC's interior wall stone has been installed 
(includes the CVC, East Front, atrium areas, and tunnels), according to 
AOC's construction management contractor, and the sequence 2 contractor 
installed 4,795 pieces of interior wall stone during the last 5 weeks, 
about 30 percent short of its 6,959-piece production target. During the 
same period, the sequence 2 contractor installed about 2,825 square 
feet of floor stone, or about 20 percent of the 15,070 square feet 
specified in a preliminary floor stone installation plan that the 
contractor provided to AOC shortly after the February 15 CVC hearing. 
In addition, 4 of the 14 schedule milestones that we and AOC have been 
tracking for the Subcommittee for today's hearing are related to 
interior wall stone installation, and the sequence 2 contractor met 1 
of these 4 milestones. 

According to the CVC team, the sequence 2 contractor has missed its 
stone installation targets for a variety of reasons, including the need 
to correct problematic sequence 1 work or properly prepare certain 
spaces for the installation of wall or floor stone, a change in wall 
stone design, late deliveries of floor stone for the exhibit gallery, 
and delays in some spaces in finishing certain work, such as ceiling 
work, that usually precedes floor stone installation. The sequence 2 
contractor did not meet the milestones for wall stone installation that 
we are tracking for the Subcommittee because certain remedial work was 
necessary and several of its masons were doing noncritical wall stone 
installation in other areas. The masons were doing this noncritical 
work while remedial or preparatory work was being performed in the East 
Front and atrium areas so that wall stone installation could start or 
continue in those areas, according to AOC's construction management 
contractor. In addition, AOC's construction management contractor 
reported that wall stone for remaining work in the upper level of the 
orientation lobby, which had been awaiting delivery because of a change 
in the type of stone to be used, has been delivered. 

The sequence 2 contractor has not yet finished installing floor stone 
in the exhibit gallery, largely because it ran out of floor stone for 
that area during certain periods in April and May. According to the 
sequence 2 contractor, the supplier of floor stone for the exhibit 
gallery is a small company that was not able to fabricate the floor 
stone as quickly as needed. AOC's construction management contractor 
said that the sequence 2 contractor has now received all of the exhibit 
gallery floor stone. The sequence 2 contractor does not expect previous 
installation delays to adversely affect the overall completion of the 
exhibit gallery. 

To finish installing floor stone in other areas of the CVC, the 
sequence 2 contractor said that it (1) plans to move many of the masons 
installing wall stone to floor stone installation soon and (2) has 
drafted a new set of targets for floor stone installation, which the 
CVC team has been reviewing. We plan to review the contractor's revised 
targets when they are provided to us and will track the contractor's 
performance against its revised targets for the Subcommittee's 
subsequent CVC hearings. Finally, according to AOC's construction 
management contractor, over 60 percent of the CVC's interior floor 
stone has been fabricated, and the sequence 2 contractor does not 
anticipate future problems with floor stone supply. 

Figures 3 and 4 show the sequence 2 contractor's progress in installing 
interior wall and floor stone since January 23 and February 13, 2006, 
respectively. 

Figure 3: Progress of CVC Interior Wall Stone Installation Compared 
with Targets Set by the Sequence 2 Contractor: 

[See PDF for image] 

Source: AOC's construction management contractor. 

[End of figure] 

Figure 4: Progress of CVC Interior Floor Stone Installation Compared 
with Preliminary Targets Set by the Sequence 2 Contractor: 

[See PDF for image] 

Source: AOC's construction management contractor. 

[End of figure] 

Project Schedule Remains Vulnerable to Challenges, Risks, and 
Uncertainties: 

As we have indicated during the Subcommittee's previous CVC hearings, 
we believe that the CVC team continues to face challenges, risks, and 
uncertainties in completing the project. At this time, the 2 to 3 
months that AOC has added to the proposed opening dates for the CVC and 
the expansion spaces seem sufficient to address these challenges, 
risks, and uncertainties. Nevertheless, given the project's history of 
delays--including those that have occurred since the Subcommittee's 
last hearing--together with information previously provided to us by 
CVC team managers and members about the lack of sufficient time in the 
schedule for certain activities, we are not as confident as we would 
like to be about whether the CVC team will be able to address all of 
the challenges, risks, and uncertainties and finish all construction 
activities by the currently scheduled dates. Accordingly, we plan to 
reassess the project schedule this summer and report our results to the 
Subcommittee by mid-September 2006. A brief update follows on the 
challenges, risks, and uncertainties the CVC team continues to face and 
the team's plans for addressing them: 

* Trade stacking could delay completion. As we discussed during the 
Subcommittee's previous CVC hearings, trade stacking could hold up 
finish work, such as drywall or ceiling installation, electrical and 
plumbing work, plastering, or floor stone installation. This work could 
be stacked because of delays in wall stone installation. Trade stacking 
could also increase the risk of accidents and injuries. Hence, it 
remains important, as we said at previous CVC hearings, for the CVC 
team to closely monitor construction to identify potential trade 
stacking and promptly take steps to address it. The CVC team has also 
identified trade stacking as a high risk, and in its May progress 
report, AOC's construction management contractor expressed concern 
about having enough workers to do ceiling work because much of the wall 
stone work is to be finished at the same time, making several areas 
available for ceiling work at the same time. The sequence 2 contractor 
has developed plans that show when various subcontractors will be 
working in each area of the CVC except the East Front, which the 
sequence 2 contractor does not expect to be ready for finish work for 
several weeks. According to the sequence 2 contractor, it intends to 
continue meeting regularly with its subcontractors to review and update 
the area plans and to have the area plan for the East Front done before 
finish work begins there. In mid-June, the sequence 2 contractor 
reported that its area-by-area plans had prevented trade stacking to 
date. Although we and AOC agree that these area-by-area plans are 
important and should be helpful in reducing the risk of trade stacking, 
we are still concerned about the potential for future trade stacking 
because of the delays that have already occurred and future delays that 
could occur. 

* Complex building systems remain a significant risk. The CVC will 
house complex building systems, including systems for heating, 
ventilation, and air conditioning; fire protection; and security. These 
systems not only have to perform well individually, but their operation 
also has to be integrated. If the CVC team encounters any significant 
problems with their functioning, either separately or together, during 
commissioning or acceptance testing, the project could be seriously 
delayed. During the Subcommittee's March 15 CVC hearing, we noted that 
the sequence 2 contractor planned to submit the shop drawings for the 
CVC's fire protection system for review by March 17. However, the 
contractor did not submit the drawings for the base project until the 
end of April, in part because more time was needed to incorporate 
changes, AOC's construction management contractor said. The shop 
drawings for the CVC's base building fire alarm system were given to 
AOC's Chief Fire Marshal on May 1, and he and his staff completed their 
review on June 1. As we previously mentioned, AOC's Fire Marshal 
Division approved most of the system and is now resolving the open 
issues with the CVC team. Some additional construction work may be 
required to address some of the Fire Marshal Division's comments, but 
AOC does not expect this work to further delay the project's 
completion. The Fire Marshal Division finished reviewing the shop 
drawings for the expansion space fire alarm system by June 26. The Fire 
Marshal Division has not been able to finish reviewing the shop 
drawings it has received for components of the fire protection system 
outside the base project because the CVC's base building fire alarm 
system had to be reviewed first. In addition, the Division did not yet 
have complete information on when it would receive additional shop 
drawings. Delays could arise if it takes longer than expected for the 
team to get approved shop drawings or if the proposed system does not 
meet the project's design specifications or the fire protection code's 
requirements.[Footnote 5] In addition, the Chief Fire Marshal noted 
that delays could occur if the CVC team does not adequately pretest the 
system and correct any problems found during the pretesting. On March 
23, AOC's commissioning contractor submitted its plan for testing the 
performance of the CVC's smoke control system, which is a critical 
component of the CVC's fire protection system and must work properly 
before the CVC can be opened to the public. This plan had not yet been 
submitted to or approved by the Fire Marshal Division. In addition, as 
we have previously noted, the Chief Fire Marshal's timely completion of 
the fire protection system's acceptance testing depends on his ability 
to obtain sufficient funding for a contractor to help perform the 
tests. 

* Building design and work scope continue to evolve. The CVC has 
undergone a number of design and work scope changes. Since the 
Subcommittee's May 24 CVC hearing, AOC's architectural contractor has 
issued three design changes or clarifications. As of June 22, 2006, 
this contractor reported, another 14 were in process. In addition, 
since the project began, AOC has executed more than 80 sequence 2 
contract modifications for work that was not anticipated.[Footnote 6] 
Some of these changes, such as changes in the exhibit gallery and in 
the East Front, have resulted in delays. Furthermore, shop drawings for 
a number of project elements, such as certain components of the 
facility's fire protection system discussed above, and the design for 
the House and Senate gift shops have not yet been fully approved and 
are subject to change. Further design or scope changes in various 
project elements are also likely, given the project's experience to 
date. Project design and scope changes are typically reflected in the 
development of potential change orders (PCO), many of which result in 
contract modifications. Figure 5 shows the PCOs submitted for 
consideration for sequences 1 and 2 since September 2003. Although PCOs 
are not always approved, they are often regarded as a reasonably good 
indicator of likely future design or scope changes that can affect a 
project's cost and schedule. Even more important, the adverse impact of 
scope and design changes on a project schedule is likely to increase as 
the project moves toward completion. For example, changes in the design 
of the gift shops are likely to affect the project schedule more 
adversely now than if the changes had been made several months ago. 

Figure 5: Cumulative Number of Potential Change Orders Submitted for 
CVC Sequences 1 and 2 between September 2003 and April 2006: 

[See PDF for image] 

Source: AOC's construction management contractor. 

[End of figure] 

As the figure indicates, new PCOs for sequence 1 were submitted until 
shortly before, and even for several months after, November 2004, when 
AOC determined that the sequence 1 contract work was substantially 
complete. Similarly, PCOs for sequence 2 are still being submitted, and 
we have seen no indication that their submission is likely to stop 
soon. It therefore appears likely to us that some of the design or 
scope changes indicated in PCOs could lead to contract modifications 
that will affect the project schedule. AOC agrees that it is important 
to minimize the impact of proposed design and scope changes. 

Three additional issues associated with the CVC's new utility tunnel 
have resulted, or are likely to result, in additional work or 
slippages. First, AOC recently said that it plans to add an exit to the 
new CVC utility tunnel to enhance worker safety. However, the 
construction work to add this exit may not start until after the CVC is 
open, according to AOC. Second, AOC recently identified complications 
that are affecting work on the new CVC utility tunnel. Specifically, 
AOC found that potential asbestos and other safety-related problems in 
an older tunnel that intersects the new utility tunnel will have to be 
addressed before other work needed for the new utility tunnel's 
operation can proceed in the older tunnel. This additional safety- 
related work has contributed to the delay in the utility tunnel's 
completion discussed earlier in our testimony; had not been completed 
as of June 26; and could lead to additional delays in getting the 
utility tunnel operational. (AOC expects this work to be done by July 
1, 2006.) Third, the delay in starting up the utility tunnel's 
operations has necessitated the use of temporary humidity control 
equipment for the orientation theaters to avoid damage to finish work 
and ceiling tile. In addition, further utility tunnel delays could 
require additional equipment in other areas, subject certain work to 
risk of damage, or delay finish or ceiling work in areas not suitable 
for the use of temporary humidity and temperature control equipment. 
For example, the CVC team installed ceiling tile in portions of the 
great hall to take advantage of the scaffolding in place, even though 
neither the temperature nor the humidity were controlled in that area. 
According to the CVC team, the installed tile could be damaged if the 
temperature or humidity is not within the specified levels. 

* Opening the CVC and expansion spaces at different times is likely to 
result in a temporary cap on CVC occupancy and could increase costs. 
AOC's current plan to open the CVC in July 2007 before the expansion 
spaces are scheduled for completion is likely to result in a temporary 
cap on CVC visitor occupancy and may necessitate the construction of 
temporary emergency exits for fire and life safety protection.[Footnote 
7] AOC is proposing this sequential approach because it believes that 
conducting acceptance testing for the fire protection system for the 
CVC and the expansion spaces concurrently would delay opening the CVC 
to the public. AOC's proposed July 2007 opening date for the CVC 
depends on the timely completion of work not only on the base project 
but also on the expansion spaces, since certain expansion space work 
must be completed before the CVC's opening. Because work on both the 
base project and the expansion spaces has been delayed during the last 
3 months, we believe that it will be especially important to monitor 
the progress of construction to determine what additional work (and 
funding) may be needed to meet AOC's planned date for opening the CVC, 
including what temporary work may be required in the expansion spaces 
for the opening to occur before the expansion space work is completed. 

* Risks from insufficient stone deliveries remain, but may be 
diminishing. According to AOC's construction management contractor, the 
sequence 2 contractor has, since the week of May 22, received four 
truckloads of interior wall stone from the wall stone fabricator. The 
sequence 2 subcontractor installing the interior wall stone recently 
asked its supplier to hold fabricated wall stone at its facility 
pending a request for delivery because of a shortage of storage space 
on the CVC site. As of June16, the supplier had two truckloads on hold, 
according to AOC's construction management contractor. The sequence 2 
contractor said that it does not foresee any further delays in the CVC 
work due to a lack of wall stone. Moreover, although none of the wall 
stone for the House and Senate expansion spaces was on site yet, the 
subcontractor responsible for this work is not anticipating delivery 
problems at this time. AOC's construction management contractor 
reported that no floor stone was installed in the exhibit gallery 
during the week of April 10 or between May 9 and May17 because the 
installers ran out of floor stone for that area. According to AOC's 
construction management contractor, the remaining exhibit gallery floor 
stone has now been delivered, and the installation has been continuing. 
The CVC team does not expect delays in floor stone shipments to affect 
the pace of future floor stone installation. 

Finally, as we have said in previous discussions with AOC, its 
construction management contractor, and the Subcommittee, it will be 
important for AOC to have adequate analysis and documentation of the 
reasons and responsibilities for delays.[Footnote 8] On April 11, 2006, 
AOC executed a contract modification authorizing its construction 
management contractor to have one of its managers who has not been 
involved in the CVC project assess the adequacy of this type of 
information. The manager submitted his report to AOC in early June. He 
reported generally positive findings but also identified desired 
improvements. He made several recommendations to AOC, which AOC has 
generally agreed with and plans to implement consistent with the 
availability of resources. As we have previously stated, we believe it 
is important for AOC to complete its analysis of delays expeditiously 
given the current September 15, 2006, sequence 2 contract completion 
date and the impact this analysis is likely to have on delay-related 
costs. 

Estimated Project Cost and Funding: 

As we testified during the Subcommittee's last three CVC hearings, we 
have estimated that the total cost to complete the entire CVC project 
would be about $556 million without an allowance for risks and 
uncertainties and could be as much as about $584 million with such an 
allowance. To date, about $530 million has been provided for CVC 
construction. This amount includes about $3.6 million that was made 
available for either CVC construction or operations and has been 
approved for CVC construction by the House and Senate Committees on 
Appropriations.[Footnote 9] To obtain the additional funding that it 
expected to need to complete the project's construction, AOC, in 
December 2005, requested $20.6 million as part of its budget request 
for fiscal year 2007. This request was based, in part, on discussions 
with us and took into account our November 16, 2005, estimate of the 
cost to complete the project's construction without an allowance for 
risks and uncertainties and funding from existing appropriations. Our 
subsequent work--completed in preparation for the Subcommittee's 
February 15 and March 15 CVC hearings--indicated that AOC would need 
about $5 million more, or about $25.6 million in total additional CVC 
construction funds, to complete construction without an allowance for 
risks and uncertainties. This would bring AOC's total request for 
fiscal year 2007 CVC construction funds to $25.6 million. In addition, 
AOC has indicated that it plans to use about $950,000 of the fiscal 
year 2007 general administration appropriations it has requested to 
provide contractual support for its Fire Marshal Division. 

As we stated in our last three CVC testimonies, AOC believes that it 
may be able to reduce the amount of funds it will need in fiscal year 
2007 to provide contractual support for testing the CVC's fire 
protection system and is exploring ways to do so. We plan to monitor 
this situation and report to the Subcommittee as soon as AOC has a 
firmer estimate. In addition, events occurring since the Subcommittee's 
May 24 CVC hearing have raised questions about the sufficiency of the 
$556 million cost-to-complete estimate, given that it does not provide 
an allowance for risks and uncertainties. For example, AOC's extension 
of the project schedule by more than 2 months is likely to result in 
increased costs; AOC recently learned that a redesign of the gift shop 
fit-out did not reduce the cost estimate or bid price to the budgeted 
amount; and the cost estimates for wayfinding signage have exceeded the 
budgeted amount. Nevertheless, at this time, we have no specific 
indication that the total cost to complete the project will exceed our 
$584 million estimate, which does include an allowance for risks and 
uncertainties. We plan to reassess our cost-to-complete estimate this 
summer and will keep the Subcommittee apprised of our results. 

Mr. Chairman, this completes our prepared statement. We would be 
pleased to answer any questions that you or Members of the Subcommittee 
may have. 

Contacts and Acknowledgments: 

For further information about this testimony, please contact Bernard 
Ungar at (202) 512-4232 or Terrell Dorn at (202) 512-6923. Other key 
contributors to this testimony include Shirley Abel, John Craig, Maria 
Edelstein, Elizabeth Eisenstadt, Jeanette Franzel, Jackie Hamilton, 
Bradley James, Joshua Ormond, and Scott Riback. 

[End of section] 

Appendix I: Capitol Visitor Center Critical Construction Milestones, 
May 25, 2006-June 28, 2006: 

Activity: Projection Screens; 
Location: Orientation Theaters;  
Scheduled completion: 5/30/06; 
Actual completion: 4/22/06. 

Activity: Floor Stone; 
Location: East Front Basement; 
Scheduled completion: 5/30/06; 
Actual completion: [Empty]. 

Activity: Ceiling Fabric; 
Location: Congressional Auditorium; 
Scheduled completion: 6/06/06; 
Actual completion: [Empty]. 

Activity: Wall Stone Area 2; 
Location: East Front Principal; 
Scheduled completion: 6/06/06; 
Actual completion: [Empty]. 

Activity: Wood Doors and Frames; 
Location: Food Service; 
Scheduled completion: 6/13/06; 
Actual completion: [Empty]. 

Activity: Plaster Walls; 
Location: Orientation Lobby; 
Scheduled completion: 6/15/06; 
Actual completion: [Empty]. 

Activity: Wall Stone Area 6; 
Location: Congressional Auditorium; 
Scheduled completion: 6/15/06; 
Actual completion: [Empty]. 

Activity: Finish Paint; 
Location: West Lobby Assembly; 
Scheduled completion: 6/20/06; 
Actual completion: [Empty]. 

Activity: Finish Paint; 
Location: East Front Basement; 
Scheduled completion: 6/20/06; 
Actual completion: [Empty]. 

Activity: Wall Stone Area 2; 
Location: Atria North Lower Level; 
Scheduled completion: 6/20/06; 
Actual completion: 6/20/06. 

Activity: Flooring; 
Location: East Front Basement; 
Scheduled completion: 6/23/06; 
Actual completion: [Empty]. 

Activity: Stone Stairs; 
Location: East Front Principal; 
Scheduled completion: 6/27/06; 
Actual completion: [Empty]. 

Activity: Ceiling Stone; 
Location: East Front Principal; 
Scheduled completion: 6/27/06; 
Actual completion: [Empty]. 

Activity: Wall Stone Area 1; 
Location: East Front Gallery; 
Scheduled completion: 6/27/06; 
Actual completion: [Empty]. 

Source: AOC's January 2006 CVC sequence 2 construction schedule for the 
scheduled completion dates and AOC and its construction management 
contractor for the actual completion dates as of June 26. 

[End of table] 

FOOTNOTES 

[1] GAO, Capitol Visitor Center: Update on Status of Project's Schedule 
and Cost as of May 24, 2006, GA0-06-803T (Washington, D.C.: May 24, 
2006). 

[2] Trade stacking can occur when workers from different trades, such 
as stone masons, electricians, plumbers, or plasterers, have to work in 
the same area at the same time to meet a schedule, sometimes making it 
difficult to ensure sufficient space and resources for concurrent work. 

[3] AOC is planning to have the smoke control system in the CVC and 
expansion spaces tested at about the same time because certain parts of 
the smoke control system in the expansion spaces must operate before 
the CVC can open. 

[4] Construction projects typically have one critical path, which is 
the sequence of activities having the longest duration through the 
schedule. There is no slack time associated with these activities, 
meaning that a delay in a critical path activity will delay the entire 
project unless a way is found to reduce the time required for other 
activities along the critical path. Some projects have multiple 
critical paths simultaneously; in practice, the CVC had what 
essentially amounted to two concurrent critical paths in May--(1) 
acceptance testing of the fire protection system and (2) fit-out of the 
gift shops. (AOC's construction management contractor reported the fit- 
out of the gift shops as a near-critical activity because of a change 
in schedule logic it had made, but because this delay would otherwise 
have had the same impact on the project's completion as the acceptance 
testing delay, we regard it as a second critical path.) Generally, the 
more critical and near-critical activities a project has, the greater 
is the risk of late completion because there are more opportunities for 
slight delays that can adversely affect the project's completion. 

[5] According to the sequence 2 subcontractor that is fitting out the 
House and Senate expansion spaces, the delays in getting approved shop 
drawings for the fire protection system have already postponed ceiling 
close-ins in the expansion spaces, and AOC believes that further such 
delays, along with possible requests for design changes, pose the 
greatest risks to the completion schedule for the expansion spaces. 

[6] These data exclude sequence 2 contract modifications for work that 
was planned but not included in the sequence 2 base contract. Examples 
include the fit-out of the House and Senate expansion spaces, the 
construction of the utility tunnel, and the purchase and installation 
of food service equipment. 

[7] According to AOC, the CVC's occupancy at any one time would be 
temporarily limited to 3,500, compared with about 4,200, the normal 
anticipated occupancy level, until acceptance testing of the fire 
protection system for the expansion spaces has been completed. Although 
AOC anticipates the need for some temporary work, it does not believe 
that the associated costs will be substantial. 

[8] See for example: GAO, Capitol Visitor Center: Effective Schedule 
Management and Updated Cost Information Are Important, GAO-05-811T 
(Washington, D.C.: June 14, 2005). 

[9] Public Law 108-447, enacted on December 8, 2004, provided that up 
to $10.6 million could be transferred from AOC's Capitol Building 
appropriation account for the use of the CVC project. The use of the 
amount transferred is subject to the approval of the House and Senate 
Committees on Appropriations. In June 2005, AOC received approval to 
use about $2.8 million (including about $1.6 million for CVC 
construction) of this $10.6 million, leaving a balance of about $7.7 
million that could be used in the future after a rescission amounting 
to $84,800. AOC recently received approval to use about an additional 
$2 million of these funds for CVC construction, including, for example, 
the fabrication and installation of wayfinding signage and the fit-out 
of the gift shops, and about $2.3 million for CVC operations. Thus, 
about $3.4 million of the $10.6 million remains available for approval 
for use for CVC construction or operations. 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: