This is the accessible text file for GAO report number GAO-04-1064T 
entitled 'Nuclear Regulatory Commission: Preliminary Observations on 
Efforts to Improve Security at Nuclear Power Plants' which was released 
on September 14, 2004.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Testimony:

Before the Subcommittee on National Security, Emerging Threats, and 
International Relations, Committee on Government Reform, House of 
Representatives:

United States Government Accountability Office:

GAO:

For Release on Delivery Expected at 10:00 a.m. EDT:

Tuesday, September 14, 2004:

Nuclear Regulatory Commission:

Preliminary Observations on Efforts to Improve Security at Nuclear 
Power Plants:

Statement of Jim Wells, Director: 
Natural Resources and Environment:

GAO-04-1064T:

GAO Highlights:

Highlights of GAO-04-1064T, testimony before the Subcommittee on 
National Security, Emerging Threats, and International Relations, 
Committee on Government Reform, House of Representatives: 

Why GAO Did This Study:

The events of September 11, 2001, and the subsequent discovery of 
commercial nuclear power plants on a list of possible terrorist 
targets have focused considerable attention on the plants’ 
capabilities to defend against a terrorist attack. The Nuclear 
Regulatory Commission (NRC), an independent agency established by the 
Energy Reorganization Act of 1974 to regulate the civilian use of 
nuclear materials, is responsible for regulating and overseeing 
security at commercial nuclear power plants. 

GAO was asked to review (1) NRC’s efforts since September 11, 2001, to 
improve security at nuclear power plants, including actions NRC has 
taken to implement some of GAO’s September 2003 recommendations to 
improve security oversight and (2) the extent to which NRC is in a 
position to assure itself and the public that the plants are protected 
against terrorist attacks. This testimony reflects the preliminary 
results of GAO’s review. GAO will issue a more comprehensive report in 
early 2005.

What GAO Found:

NRC responded quickly and decisively to the September 11, 2001, 
terrorist attacks with multiple steps to enhance security at commercial 
nuclear power plants. NRC immediately advised the plants to go to the 
highest level of security according to the system in place at the time 
and issued advisories and orders to the plants to make certain 
enhancements, such as installing more physical barriers and augmenting 
security forces, that could be completed quickly to shore up security. 
According to NRC officials, their inspections found that the plants 
complied with these advisories and orders. Later, in April 2003, NRC 
issued a new design basis threat (DBT), which establishes the maximum 
terrorist threat that a facility must defend against, and required the 
plants to develop and implement new security plans to address the new 
threat by October 2004. It is also improving its force-on-force 
exercises, as GAO recommended in its September 2003 report. These 
exercises are an important agency tool to ensure that the plants’ 
security plans are adequate to protect against the DBT. 

While its efforts to date have enhanced security, NRC is not yet in a 
position to provide an independent determination that each plant has 
taken reasonable and appropriate steps to protect against the new DBT. 
According to NRC officials, the facilities’ new security plans are on 
schedule to be implemented by October 2004. However, NRC’s review of 
the plans, which are not available to the general public for security 
reasons, has primarily been a paper review and is not detailed enough 
for NRC to determine if the plans would protect the facility against 
the threat presented in the DBT. For example, the plans GAO reviewed 
are largely based on a template and often do not include important 
site-specific information, such as where responding guards are 
stationed, how the responders would deploy to their defensive 
positions, and how long deployment would take. In addition, NRC 
officials are generally not visiting the facilities to obtain site-
specific information and assess the plans in terms of each facility’s 
layout. NRC is largely relying on force-on-force exercises it conducts 
to test the plans, but these exercises will not be conducted at all 
facilities for 3 years. NRC’s oversight of plants’ security could also 
be improved. However, NRC does not plan to make some improvements in 
its inspection program that GAO previously recommended and still 
believes are needed. For example, NRC is not following up to verify 
that all violations of security requirements have been corrected or 
taking steps to make “lessons learned” from inspections available to 
other NRC regional offices and nuclear power plants. Moreover, if NRC 
needs to revise its DBT further as the terrorist threat is better 
defined, it will need longer to make and test all the necessary 
enhancements. The Department of Energy, for example, is currently 
reviewing the DBT for its nuclear facilities. 

www.gao.gov/cgi-bin/getrpt?GAO-04-1064T.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Jim Wells, (202) 
512-3841, wellsj@gao.gov.

[End of section]

Mr. Chairman and Members of the Subcommittee:

We are pleased to be here today to discuss our ongoing review of the 
Nuclear Regulatory Commission's (NRC) efforts to improve security at 
the nation's 104 commercial nuclear power plants licensed to operate. 
These plants, which are located at 65 facilities in 31 states, provide 
about 20 percent of the nation's electricity.[Footnote 1] We are 
conducting this review at your request and expect to issue our final 
report early next year.

The events of September 11, 2001, and the subsequent discovery of 
commercial nuclear power plants on a list of possible terrorist targets 
have focused considerable attention on the plants' capabilities to 
defend against a terrorist attack. However, as you know, NRC is not 
alone in the challenges it faces to protect against terrorism. 
Recently, the 9/11 Commission's report highlighted the accomplishments 
and challenges that remain on many fronts in the nation's fight against 
terrorism. In recent testimony before this Committee, the Comptroller 
General applauded the efforts of the 9/11 Commission and discussed its 
recommendations to improve information sharing and analysis by the 
intelligence agencies.[Footnote 2] We have also testified several times 
before this Subcommittee on weaknesses in border security, federal 
action needed to address security challenges at the nation's chemical 
facilities, and the issues faced by the Department of Energy (DOE) in 
its efforts to secure its nuclear facilities.[Footnote 3]

To protect commercial nuclear power plants from a terrorist attack, NRC 
formulates a design basis threat (DBT), which establishes the maximum 
terrorist threat that a facility must prepare to defend against. The 
DBT characterizes the elements of a postulated attack, including the 
number of attackers, their training, and the weapons and tactics they 
are capable of using. Each facility must prepare a security plan 
describing its strategy for defending against the threat presented in 
the DBT. NRC is responsible for reviewing and approving these plans, 
inspecting the facilities to verify compliance with the plans and other 
NRC requirements, and conducting force-on-force exercises (mock 
terrorist attacks) at the facilities to ensure that the facilities' 
execution of their security plans could repel an attack. NRC considers 
the DBT and the security plans to be safeguards or sensitive 
information and does not make them available to the general public.

Our current review is the second on NRC's security program since the 
September 11 attacks. In our earlier report, issued in September 2003, 
we made a number of recommendations to NRC to improve its oversight of 
security at commercial nuclear power plants.[Footnote 4]

In my testimony today, I will (1) describe NRC's efforts since 
September 11, 2001, to improve security at nuclear power plants, 
including actions it has taken to implement some of our September 2003 
recommendations to improve security oversight and (2) discuss our 
preliminary views on the extent to which NRC is in a position to assure 
itself and the public that its efforts will protect the plants against 
terrorist attacks. To conduct this work, we reviewed the security 
advisories and orders NRC has issued to the facilities since September 
11, 2001. We also reviewed security documents, such as the DBT and 
individual facilities' draft security plans,[Footnote 5] and 
interviewed NRC security program officials. We did the work reflected 
in this statement from March 2004 through August 2004 in accordance 
with generally accepted government auditing standards.

In our final report, we will discuss the extent to which NRC is using a 
risk management approach to improve security at nuclear power plants. 
More specifically, we will report on NRC's efforts to (1) define the 
threat faced by nuclear power plants, (2) identify and characterize the 
vulnerabilities that would allow a threat to be realized, (3) assess 
the risks and determine priorities for protecting the plants, and (4) 
identify the countermeasures to reduce the risk of a successful 
terrorist attack.

In summary:

NRC responded quickly to the September 11, 2001, terrorist attacks with 
multiple steps to enhance security at commercial nuclear power plants. 
For example, NRC:

* immediately advised the plants to go to the highest level of security 
according to the system in place at the time;

* issued a series of advisories and orders to the plants to make 
certain security enhancements--such as installing additional physical 
barriers, augmenting security forces, increasing patrols, and further 
restricting plant access--that could be completed quickly to shore up 
security until a more comprehensive analysis of the terrorist threat 
and how to best protect the plants against that threat could be 
completed;

* issued a new DBT in April 2003 and required the plants to develop and 
implement--by October 2004--new security plans setting out how the 
plants will protect against the threat defined in the new DBT. NRC 
expects the plants will meet this deadline; and:

* improved its force-on-force exercises, which are an important agency 
tool to ensure that the plants are secure, by planning to conduct the 
exercises every 3 years instead of every 8 years and to make them more 
realistic, which we had recommended.

While we applaud these efforts, it will take several more years for NRC 
to make an independent determination that each plant has taken 
reasonable and appropriate steps to protect against the threat 
presented in the new DBT. The plants' development and implementation of 
security plans to comprehensively address the new DBT is a critical 
step in ensuring that individual plants can defend against terrorism. 
Although new security plans are to be approved and implemented by 
October 29, 2004, NRC will not have detailed knowledge about security 
at individual facilities to ensure that these plans provide this 
protection. NRC will not have this detailed knowledge, primarily for 
two reasons:

* First, NRC's review of the new security plans has been rushed and is 
largely a paper review. NRC is conducting its review of the plans over 
a 6-month period--as the plants are implementing the plans--and NRC 
reviewers are generally not visiting the plants to obtain details about 
the plans and view how the plans interface with the plants' physical 
layout. For example, the plans do not detail defensive positions at the 
site, how the defenders would deploy to respond to an attack, or how 
long the deployment would take. In addition, NRC is not requesting, and 
the facilities are generally not submitting for review, the documents 
and studies supporting the draft security plans.

* Second, it will take up to 3 years for NRC to test implementation of 
the new plans through force-on-force exercises at all facilities. 
Moreover, NRC is considering action that could potentially compromise 
the integrity of the exercises. The agency is planning to require the 
use of an adversary force trained in terrorist tactics, as we 
recommended in our September 2003 report. However, NRC is considering 
the use of a force provided by a company that the nuclear power 
industry selected; this company provides guards for about half the 
facilities to be tested. This relationship with the industry raises 
questions about the force's independence. Furthermore, NRC is not 
taking advantage of other opportunities to improve the effectiveness of 
the exercises and its oversight in general by implementing other 
recommendations from our September 2003 report. For example, NRC is not 
following up to verify that all violations it found in previous 
inspections have been corrected and is not taking steps to make 
"lessons-learned" from inspections available to other regional offices 
and nuclear power plants, as we had recommended.

In addition to these concerns, we note that NRC's DBT is similar to the 
DOE's DBT for its nuclear facilities. As you know, in April 2004, DOE 
officials told this Subcommittee that it would have to revisit its 
post-September 11 DBT. If NRC also decides to revisit and revise its 
DBT, NRC will need even longer to put all the necessary security 
enhancements in place and to test them. Funding the costs of the 
additional protection could also be an issue. NRC has already stated 
that the current DBT is the largest reasonable threat against which a 
regulated private guard force should be expected to defend under 
existing law. Also, certain potential vulnerabilities, such as airborne 
assaults, are currently being addressed outside of the DBT. Any changes 
in this approach to certain vulnerabilities could similarly place 
additional requirements on the plants.

Background:

NRC is an independent agency established by the Energy Reorganization 
Act of 1974 to regulate the civilian use of nuclear materials. NRC's 
Office of Nuclear Security and Incident Response, which was established 
in April 2002, is primarily responsible for regulating and overseeing 
security at commercial nuclear power plants. This office also develops 
overall agency policy and provides management direction for evaluating 
and assessing technical issues involving security at nuclear 
facilities. In addition, it coordinates with the Department of Homeland 
Security, the intelligence and law enforcement communities, DOE, and 
other agencies on security matters.

NRC begins regulating security at a commercial nuclear power plant when 
the plant is constructed. Before granting an operating license, NRC 
must approve a security plan for the plant. If more than one plant is 
located at a facility, the licensee prepares a physical security plan 
covering all the plants at the site. Since 1977, NRC has required 
facilities to have a security plan that is designed to protect against 
a DBT for radiological sabotage.[Footnote 6] The DBT characterizes the 
elements of a possible attack, including the number of attackers, their 
training, and the weapons and tactics they are capable of using. Since 
it was first issued in 1977, the DBT has been revised twice, each time 
to reflect increased terrorist threats. The first revision occurred in 
1993 in response to the first terrorist attack on the World Trade 
Center in New York City and to a vehicle intrusion at the Three Mile 
Island nuclear power plant in Pennsylvania.[Footnote 7] The second 
revision was issued on April 29, 2003, in response to the September 11, 
2001, terrorist attacks.

NRC oversees plant security through several activities, particularly 
security inspections and force-on-force exercises. In annual security 
inspections at all the plants, inspectors are to check that the plant's 
security programs meet NRC requirements for access authorization, 
access control, and response to contingency events. The inspectors also 
are to review changes to the plant's security plan and self-assessment 
of security. NRC suspended these inspections in September 2001 to focus 
its resources on the implementation of security enhancements from NRC's 
advisories and orders. NRC reinstated the inspection program in early 
2004.

NRC began conducting force-on-force exercises under its security 
inspection program in 1991. The agency suspended these exercises, which 
were referred to as Operational Safeguards Response Evaluation (OSRE) 
exercises, after the September 11, 2001, attacks because they 
considered it unsafe to perform mock attacks during a period of 
heightened security and because NRC and licenses security resources 
were focused on responding to the events of September 11, 2001. NRC has 
conducted some exercises during 2003 and 2004 to gain the information 
necessary to initiate a revised, permanent force-on-force exercise 
program sometime in the near future. Although NRC officials have not 
decided on an exact date, they anticipate that the exercises will 
resume very soon after the facilities have implemented their security 
plans, which is scheduled for the end of October 2004.

NRC Actions Since September 11, 2001, to Improve Security at Nuclear 
Power Plants:

Shortly after September 11, 2001, NRC began to respond to the 
heightened risk of terrorist attacks. Between September 11, 2001, and 
the end of March 2003, the agency issued over 60 advisories to 
licensees of nuclear power plants. These advisories recommended 
enhancements that could be made quickly to shore up security until a 
more comprehensive analysis of the terrorist threat and how best to 
protect the plants against the threat could be completed. NRC 
immediately advised the plants to go to the highest level of security 
according to the system in place at the time. It followed with 
advisories and orders designed to increase the size and improve the 
proficiency of plants' security forces, restrict access to plants, and 
increase and improve plants' defensive barriers. For example, on 
October 6, 2001, NRC issued a major advisory, recommending that the 
licensees take immediate action to increase the number of security 
guards and to be cautious about using temporary employees.

From October 2001 to January 2002, NRC conducted a three-phase security 
inspection, checking the facilities to see if they had implemented 
these advisories. In phase one, NRC inspectors used an NRC-prepared 
checklist to document the implementation status of NRC's October 6, 
2001 advisory. In phase two, security inspectors conducted a more in-
depth evaluation of the facilities' implementation of the advisories. 
During phase three, NRC's security inspectors reviewed each facility's 
security program to determine if it had complied with the additional 
measures recommended in the October 6, 2001, advisory. NRC concluded 
that all facilities were in compliance but that the facilities had not 
consistently interpreted the recommended measures.

NRC used the results from the three-phase inspection to develop a 
February 25, 2002, order requiring facilities to implement additional 
security measures by August 31, 2002.[Footnote 8] Many of these 
measures had been recommended in previous advisories. NRC then 
conducted security inspections to verify facilities' compliance with 
all aspects of the order. The inspections were completed in December 
2003, and NRC found that all nuclear power facilities were in 
compliance with the order.

NRC also acted on an item that had been a security concern for a number 
of years--the use of temporary clearances for temporary employees at 
the plants. Commercial nuclear power plants use hundreds of temporary 
employees for maintenance--most frequently during the period when the 
plant is shut down for refueling. In the past, NRC found instances in 
which personnel who failed to report criminal records had temporary 
clearances that allowed them unescorted access to vital areas.[Footnote 
9] In an October 6, 2001, advisory, NRC suggested that facilities limit 
temporary clearances for temporary workers. On February 25, 2002, NRC 
issued an order that limited the use and duration of temporary 
clearances, and on January 7, 2003, NRC issued an order to eliminate 
the use of temporary clearances altogether. NRC now requires a criminal 
history review and a background check investigation to be completed 
before allowing temporary workers to have unescorted access to the 
power plant.

NRC issued its revised DBT in April 2003 to reflect the post-September 
11 terrorist threat. In January 2003, NRC developed a draft DBT that it 
sent to federal, state, and local law enforcement agencies, federal 
intelligence and counterintelligence agencies, and the nuclear industry 
for review and comment. Between January and April of 2003, revisions 
were made, and the revised drafts were sent for additional comments. On 
April 29, 2003, NRC issued an order requiring the facilities to protect 
the power plants from a terrorist attack fitting within the parameters 
of the new DBT. The new DBT reflected the increased size of a potential 
terrorist force, the more sophisticated weaponry, and the different 
methods of deployment demonstrated by the September 11 terrorist 
attacks. NRC stated that this new DBT was the "largest reasonable 
threat against which a regulated private guard force should be expected 
to defend under existing law." Licensees were given 1 year to develop 
new security plans based on the new DBT.

At the same time, NRC issued two other orders that (1) limited work 
hours for security personnel (to 16 hours per 24-hour period, 26 hours 
per 48-hour period, and 72 hours per week) so that excessive hours 
would not impair security forces in performing their duties and (2) 
required enhanced training and qualifications for the plants' security 
forces. All told, according to the Nuclear Energy Institute,[Footnote 
10] by the end of 2004, the nuclear power industry will have invested 
about $1 billion in security enhancements since September 11, 2001.

During this period, NRC also developed and strengthened its relations 
with other federal agencies. It collaborated with the Federal Aviation 
Administration on protecting airspace over the plants and worked with 
the Department of Homeland Security, Federal Bureau of Investigation, 
and local law enforcement agencies to monitor and analyze security 
threats and to determine additional security measures needed to meet 
such threats.

NRC has also taken, or is taking, steps to implement our September 2003 
recommendations to improve its security inspections and force-on-force 
exercises. We had recommended that the NRC Commissioners ensure that 
the agency's security inspection program and force-on-force exercise 
program are restored promptly. NRC reinstated the security inspection 
program in February 2004.

NRC has not yet made force-on-force exercises a required activity, as 
we recommended, but it is taking steps in that direction. During 2003, 
NRC completed a "pilot" force-on-force program, which included 15 
exercises. This pilot program was designed to determine how future 
force-on-force exercises would be conducted. After completing the 15 
pilot exercises, NRC summarized the results in a "lessons learned" 
document. NRC is now conducting "transition" force-on-force exercises 
to help it formulate a new, permanent program. Participation in both 
the pilot and most of the transition exercises was voluntary for the 
facilities. Only some of the pilot exercises tested the full DBT, and 
none of the transitional exercises have or will test the full terrorist 
capabilities of the DBT. NRC officials said that they will not start 
conducting exercises using the new DBT until November 2004, after the 
facilities have implemented their new security plans.

NRC is also making the following additional improvements we recommended 
for these exercises:

* conducting the exercises more frequently at each site--every 3 years 
rather than the once every 8 years schedule of the past;

* using laser equipment in all force-on-force exercises to more 
accurately account for shots fired and to establish a more realistic 
setting;

* continuing the practice, begun in 2000, of prohibiting licensees from 
temporarily increasing the number of guards defending the plant and 
enhancing plant defenses for force-on-force exercises, or requiring 
that any temporary security enhancements be officially incorporated 
into the licensees' security plans; and:

* requiring the exercises to make use of the full terrorist 
capabilities stated in the DBT, including the use of an adversary force 
that has been trained in terrorist tactics.

NRC Cannot Yet Provide Assurances That Its Efforts Will Protect Nuclear 
Power Plants Against Terrorist Attacks as Outlined in the New DBT:

As the principal regulator of commercial nuclear power plants, NRC has 
an important responsibility to provide an independent determination 
that each plant is protected against the threat presented in the new 
DBT. While its efforts to date have no doubt enhanced security, NRC 
cannot yet provide this determination for three principal reasons. 
First, its review of the facilities' new security plans setting out how 
the facilities will respond to the threat presented in the new DBT is 
not detailed enough. Second, it will not test the effectiveness of all 
the plans and security at all plants with force-on-force exercises for 
3 years, and it does not plan to make some improvements in its security 
oversight that we believe are needed and have previously recommended. 
Third, NRC could potentially need to further revise its DBT as the 
terrorist threat is better defined, which could require changes in the 
security plans and additional security improvements.

NRC's Review of Security Plans Is Not Detailed Enough to Determine if 
They Effectively Address the New DBT:

NRC's strategy for reviewing the facilities' security plans generally 
allows for only a document review. While NRC staff originally estimated 
that it would take 2 years to review the plans, NRC now expects to take 
6 months--from April 29, 2004, through October 29, 2004--to review and 
approve the facilities' security plans. The facilities are also 
expected to have their plans implemented by that date.

To review the plans in 6 months, NRC assigned 20 NRC staff and 
contracted for 20 staff from DOE's Idaho National Engineering 
Laboratory to perform the reviews. The facilities' use of an industry-
developed template is also expected to help speed the review.[Footnote 
11] The template was intended to provide standard language for about 80 
percent of the plans' contents. However, the plans we reviewed relied 
almost entirely on the template language and provided little facility-
specific information.

Agency officials are generally not visiting the facilities to obtain 
site-specific information and assess the plans in terms of each 
facility's particular layout. Since completion of our work, NRC has 
decided to visit six or seven of the plants to verify information in 
the plan; however, it will not visit the vast majority of plants. In 
addition, the plans do not contain much detail. For example, the 12 
plans NRC provided for our review do not include information about 
where responding guards are stationed, where their defensive positions 
are located, how the responders would deploy to their defensive 
positions, and how long deployment would take.[Footnote 12] The plans 
state that "[p]hysical security measures and specific response 
protocols for the onsite security force are contained in facility 
implementing procedures." Also, in all the plans we reviewed, the 
defensive positions are described only as being established "where 
necessary." None of the plans we reviewed specified the type of weapons 
the security forces will carry; stating only that the forces will meet 
NRC's minimum requirements. According to staff from our Office of 
Special Investigations with experience in law enforcement and physical 
security, the security plans are, at best, general guidelines.

The plans often refer to other documents that detail how the 
requirements will be met and how the plans will be implemented. 
However, because of the 6-month review time frame, NRC officials do not 
plan to review these supporting documents as part of their approval 
process. According to NRC officials, the principal purpose of the plans 
is to commit the facilities to comply with all NRC security regulations 
and the template-based plans accomplish that purpose for about 80 to 90 
percent of the information.

NRC's Security Oversight Is Limited by Timing of Key Activities and 
Inaction on Some of Our Recommendations:

NRC will not determine the adequacy of the sites' procedures and 
programs for implementing their security plans and the sites' ability 
to actually implement the plan until it conducts inspections and force-
on-force exercises at the sites. Because NRC plans to annually inspect 
all sites and conduct force-on-force exercises on a 3-year cycle, it 
could be 2007 before NRC can say with assurance that all the sites can 
be protected from a terrorist attack as presented in the new DBT.

In addition to the limitations of the security inspections and the 
timing of the force-on-force exercises, NRC has not implemented some of 
the recommendations we made in our September 2003 report to improve its 
oversight. We recommended that the NRC Commissioners:

* require that NRC regional inspectors conduct follow-up visits to 
verify that corrective action has been taken when security violations, 
including non-cited violations,[Footnote 13] have been identified;

* ensure that NRC routinely collects, analyzes, and disseminates:

information on security problems, solutions, and lessons learned and 
shares this information with all NRC regions and licensees; and:

* enforce NRC's requirement that force-on-force exercise reports be 
issued within 30 to 45 days after the end of the exercise to ensure 
prompt correction of the problems noted.

Implementation of these recommendations is needed to correct some 
important program limitations. For example, during annual inspections, 
NRC inspectors often classified security problems as non-cited 
violations if the problem had not been identified frequently in the 
past or if the problem had no direct, immediate, adverse consequence at 
the time that it was identified. Instances of a security guard sleeping 
on duty and a security officer falsifying logs to show that he had 
checked vital areas and barriers when he was actually in another part 
of the plant, for example, were treated as non-cited violations. This 
classification tends to minimize the seriousness of the problem. Non-
cited violations do not require a written response from the licensee 
and do not require NRC inspectors to verify that the problem has been 
corrected. NRC used non-cited violations extensively for serious 
problems, thereby allowing the licensees to correct the problem on 
their own without NRC verification of the correction. Consequently, we 
believe NRC may not be fully aware of the quality of security at a 
site, and the lack of follow-up and verification reduces assurances 
that needed improvements have been made.

NRC also has not created a system to share the security problems, 
solutions, and lessons learned that it finds during security 
inspections with all the NRC regions and licensees. NRC did create a 
management review panel that is tracking the regions' findings during 
the security inspections and the dispositions of the findings. It is 
also keeping a database of all the findings and dispositions or 
solutions; however, the database is not accessible by the regions and 
licensees.

With respect to NRC's enforcement of its requirement for force-on-force 
exercise reports, NRC officials said they do plan to issue reports when 
the permanent force-on-force program is reinstated, but the reports 
will not be made public. During the pilot force-on-force exercises, NRC 
did not issue any reports, although it prepared a "lessons learned" 
document for the Commissioners. In addition, an NRC official stated 
that NRC will not issue reports on the new transitional force-on-force 
exercises, but will prepare another internal lessons learned document. 
We continue to believe that NRC needs to promptly issue reports on each 
exercise to ensure that any security problems are quickly corrected. 
These reports would also provide the documentation needed to assess 
trends and patterns among facilities as well as at particular 
facilities over time.

Finally, although NRC is taking action--as we recommended in our 
September 2003 report--to establish an adversary force trained in 
terrorist tactics, NRC is not establishing the force in a manner that 
provides confidence that the force will be independent and highly 
trained, and will endeavor to find weaknesses in the facilities' 
security. NRC delegated the task of establishing the adversary force to 
an organization--the Nuclear Energy Institute--that represents the 
licensees of nuclear power plants. The company the Institute selected 
currently provides security guards to about half of the nuclear power 
sites to be tested. The company's relationship with the industry raises 
questions about the force's independence. Of further concern, this 
company was recently involved in a controversy over similar tests. 
During a June 2003 DOE force-on-force exercise at a nuclear site in Oak 
Ridge, Tennessee, security guards working for this company received 
uncharacteristically high scores. A subsequent investigation by DOE's 
Office of the Inspector General indicated that the guards might have 
cheated on the test and perhaps on many other tests at Oak Ridge, 
dating back to the mid-1980s. It was alleged that the guards had 
studied plans for the simulated attacks before they were carried out, 
had disabled the laser sensors they wore during tests to determine when 
they were "shot" by mock enemies, arranged trucks and other obstacles 
to help foil simulated attacks, created special, nonstandard plans to 
help them perform better on tests, and put more guards on duty at the 
time of the tests than would normally have been present.

If NRC Needs to Revise Its DBT, Additional Security Enhancements Could 
Be Required:

In April 2004, DOE told this Subcommittee that it would have to review 
its post-September 11, 2001, DBT for its nuclear facilities to 
determine if it should be more stringent.[Footnote 14] If NRC decides, 
as it gains a better understanding of the terrorist threat, that it 
also needs to reconsider its DBT, it could take longer to put all 
necessary enhancements in place and test them with force-on-force 
exercises. Depending on the additional enhancements needed, funding of 
the costs of the additional protection and how quickly it could be put 
in place could also become an issue. NRC previously stated that its 
April 29, 2003, DBT is the largest reasonable threat against which a 
regulated private guard force should be expected to defend under 
current law.

Similarly, NRC is addressing certain potential vulnerabilities outside 
of the DBT. For example, the terrorists' use of aircraft on September 
11 raised questions about nuclear power plants' vulnerabilities to such 
attacks. According to NRC, although the design of many facilities 
considered the probability of accidental aircraft crashes that may pose 
undue risks to public health and safety, only a few facilities were 
specifically designed to withstand an accidental impact. Nonetheless, 
NRC believes that nuclear power facilities are among the most hardened 
industrial facilities in the United States. They are massive structures 
with thick exterior walls and interior barriers of reinforced concrete 
designed to withstand tornadoes (and projectiles propelled by 
tornadoes), hurricanes, fires, floods, and earthquakes. NRC also 
believes that the efforts to enhance security at airports and on 
airplanes and to identify potential terrorists and prevent potential 
attacks before they occur are an important part of reducing the threat 
of airborne attacks.

After the September 11 attacks, the Federal Aviation Administration, 
working with NRC, advised pilots to avoid the airspace above or in 
proximity to all nuclear power facilities and not to circle in their 
vicinity. NRC also undertook a major classified research and 
engineering effort, in conjunction with national laboratories, to 
evaluate the vulnerabilities and potential effects of a large 
commercial aircraft's hitting a nuclear power site. This effort 
includes consideration of additional preventive or mitigating measures 
to enhance the protection of public health and safety in the event of a 
deliberate aircraft crash into a nuclear power plant or spent (used) 
nuclear fuel storage facility. The results are classified and cannot be 
discussed in this open hearing. According to NRC officials, certain 
types of aircraft hitting facilities at certain locations pose some 
risks. The officials noted that, in these cases, the plants would have 
enough time to take advantage of certain safety features to 
substantially lessen the risks. NRC officials also believe that the 
plants would have sufficient time to implement emergency preparedness 
plans, if necessary.

Airborne assaults on plants remain a public concern. If further 
consideration of NRC's aircraft study results lead to changes in NRC's 
approach, the DBT may need to be revised further, again raising 
questions about the timing and cost of improvements.

In closing, the nation's commercial nuclear power plants are no doubt 
more secure against a terrorist attack now than they were on September 
11, 2001. NRC responded quickly and decisively to the attacks by 
requiring various enhancements to existing security at the plants. It 
will be some time, however, before NRC can provide the public with 
assurances that what has been done is enough. Some of these 
enhancements are still being put in place, and NRC cannot independently 
determine that the enhancements will adequately secure the facilities 
until they have been effectively tested with force-on-force exercises. 
While our assessment of NRC activities is still underway, we believe 
that it is important for NRC to act quickly and take a strong 
leadership role in establishing a worthy adversary team for these 
exercises, establish priorities for the facilities to be tested, 
carefully analyze the test results for shortcomings in facility 
security, and be willing to require additional security improvements as 
warranted.

Mr. Chairman, this testimony provides our preliminary views. We would 
be happy to respond to any questions that you or Members of the 
Subcommittee may have.

For further GAO Contact and Staff Acknowledgements:

For further information on this testimony, please contact Jim Wells at 
(202) 512-3841 or at Wellsj@gao.gov. Raymond H. Smith, Jr.; Kenneth E. 
Lightner, Jr.; Jill Ann Roth Edelson; Kevin L. Jackson; Carol 
Herrnstadt Shulman; and Barbara R. Timmerman made key contributions to 
this testimony. 

FOOTNOTES

[1] More than one nuclear power plant are located at some facilities.

[2] GAO, 9/11 Commission Report: Reorganization, Transformation, and 
Information Sharing, GAO-04-1033T (Washington, D.C.: Aug. 3, 2004).

[3] GAO, Border Security: Additional Actions Needed to Eliminate 
Weaknesses in the Visa Revocation Process, GAO-04-899T, (Washington, 
D.C.: July 13, 2004); GAO, Homeland Security: Federal Action Needed to 
Address Security Challenges at Chemical Facilities, GAO-04-482T 
(Washington, D.C.: February 23, 2004); GAO, Nuclear Security: DOE Must 
Address Significant Issues to Meet the Requirements of the New Design 
Basis Threat, GAO-04-701T (Washington, D.C.: April 27, 2004); and GAO, 
Nuclear Security: Several Issues Could Impede the Ability of DOE's 
Office of Energy, Science and Environment to Meet the May 2003 Design 
Basis Threat, GAO-04-894T (Washington, D.C.: June 22, 2004). 

[4] GAO, Nuclear Regulatory Commission: Oversight of Security at 
Commercial Nuclear Power Plants Needs to Be Strengthened, GAO-03-752, 
(Washington, D.C.: September 4, 2003).

[5] We reviewed 12 of the 65 facilities' draft security plans. 
According to NRC officials, the plans we reviewed were generally 
representative of all the plans.

[6] Radiological sabotage against a nuclear power plant is a deliberate 
act that could directly or indirectly endanger public health and safety 
by exposure to radiation.

[7] On February 7, 1993, an intruder drove onto the Three Mile Island 
power plant site, through a gate, and crashed through a roll-up door 
into the turbine area. The intruder challenged security barriers and 
disrupted operations for 4 hours before he was apprehended.

[8] NRC Order EA-02-026.

[9] The vital area, within the protected area, contains the plant's 
equipment, systems, devices, or material whose failure, destruction, or 
release could endanger the public health and safety by exposure to 
radiation. This area is protected by guard stations, reinforced gates, 
surveillance cameras, and locked doors.

[10] The institute represents licensees of commercial nuclear power 
plants.

[11] NRC provided input to the template's development.

[12] Staff from our Office of Special Investigations with experience in 
law enforcement and physical security assisted in reviewing these 
plans.

[13] A non-cited violation is a problem that had not been identified 
more than twice in the past year or had no immediate, direct 
consequences at the time it was identified.

[14] DOE's post-September 11, 2001, DBT, which is similar to NRC's in 
terms of the threat it outlines, was issued in May 2003. DOE has not 
yet completed its review of the DBT.