This is the accessible text file for GAO report number GAO-03-987T 
entitled 'Polar-Orbiting Environmental Satellites: Project Risks Could 
Affect Weather Data Needed by Civilian and Military Users' which was 
released on July 15, 2003.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Testimony:

Before the Subcommittee on Environment, Technology, and Standards, 
Committee on Science, House of Representatives:

United States General Accounting Office:

GAO:

For Release on Delivery Expected at 2 p.m. EDT:

Tuesday, July 15, 2003:

Polar-Orbiting Environmental Satellites:

Project Risks Could Affect Weather Data Needed by Civilian and Military 
Users:

Statement of David A. Powner, Acting Director, Information Technology 
Management Issues:

GAO-03-987T:

GAO Highlights:

Highlights of GAO-03-987T, a testimony before the Subcommittee on 
Environment, Technology, and Standards, Committee on Science, House of 
Representatives 

Why GAO Did This Study:

Polar-orbiting environmental satellites provide data and imagery that 
are used by weather forecasters, climatologists, and the military to 
map and monitor changes in weather, climate, the ocean, and the 
environment. The current polar satellite program is a complex 
infrastructure that includes two satellite systems, supporting ground 
stations, and four central data processing centers. In the future, the 
National Polar-orbiting Operational Environmental Satellite System 
(NPOESS) is to merge the two current satellite systems into a single 
state-of-the-art environment monitoring satellite system. This new $7 
billion satellite system is considered critical to the United States’ 
ability to maintain the continuity of data required for weather 
forecasting and global climate monitoring through the year 2018. In 
its testimony GAO was asked, among other topics, to discuss risks to 
the success of the NPOESS deployment. 

What GAO Found:

The NPOESS program faces key programmatic and technical risks that may 
affect the successful and timely deployment of the system. The 
original plan for NPOESS was that it would be available to serve as a 
backup to the March 2008 launch of the final satellite in one of the 
two current satellite programs—the Polar-orbiting Operational 
Environmental Satellite (POES) system. However, changing funding 
streams and revised schedules have delayed the expected launch date of 
the first NPOESS satellite by 21 months. Thus, the first NPOESS 
satellite will not be ready in time to back up the final POES 
satellite, resulting in a potential gap in satellite coverage should 
that satellite fail. Specifically, if the final POES launch fails and 
if existing satellites are unable to continue operations beyond their 
expected lifespans, the continuity of weather data needed for weather 
forecasts and climate monitoring will be put at risk. Moreover, 
concerns with the development of key NPOESS components, including 
critical sensors and the data processing system, may cause additional 
delays in the satellite launch date.

The program office is working to address the changes in funding levels 
and schedule, and to make plans for addressing specific risks. 
Further, it is working to develop a new cost and schedule baseline for 
the NPOESS program by August 2003. 

www.gao.gov/cgi-bin/getrpt?GAO-03-987T.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact David Powner at (202) 
512-9286 or pownerd@gao.gov.

[End of section]

Mr. Chairman and Members of the Subcommittee:

We appreciate the opportunity to join in today's hearing to discuss our 
work on the planned National Polar-orbiting Operational Environmental 
Satellite System (NPOESS). At your request, we will provide an overview 
of our nation's current polar-orbiting environmental satellite program 
and the planned NPOESS program. We will also discuss key risks to the 
successful and timely deployment of NPOESS.

In brief, today's polar-orbiting environmental satellite program is a 
complex infrastructure encompassing two satellite systems, supporting 
ground stations, and four central data processing centers that provide 
general weather information and specialized environmental products to a 
variety of users, including weather forecasters, military strategists, 
and the public. NPOESS is planned to merge the two satellite systems 
into a single state-of-the-art environment monitoring satellite system. 
This new satellite system, currently estimated to cost about $7 
billion, is considered critical to the United States' ability to 
maintain the continuity of data required for weather forecasting and 
global climate monitoring through the year 2018.

However, the NPOESS program faces key programmatic and technical risks 
that may affect the successful and timely deployment of the system. 
Specifically, changing funding streams and revised schedules have 
delayed the expected launch date of the first NPOESS satellite by 21 
months. Thus, the first NPOESS satellite will not be ready in time to 
back up the final POES satellite, resulting in a potential gap in 
satellite coverage should that satellite fail. Specifically, if the 
final POES launch fails and if existing satellites are unable to 
continue operations beyond their expected lifespans, the continuity of 
weather data needed for weather forecasts and climate monitoring will 
be put at risk. In addition, concerns with the development of key 
NPOESS components, including critical sensors and the data processing 
system, could cause additional delays in the satellite launch date.

The program office is working to address the changes in funding levels 
and schedule, and to make plans for addressing specific risks. Further, 
it is working to develop a new cost and schedule baseline for the 
NPOESS program by August 2003.

This statement builds on work we have done on environmental satellite 
programs over the last several years.[Footnote 1] An overview of the 
approach we used to perform this work--our objectives, scope, and 
methodology--is provided in appendix I.

Existing Polar Satellite Infrastructure:

Since the 1960s, the United States has operated two separate 
operational polar-orbiting meteorological satellite systems. These 
systems are known as the Polar-orbiting Operational Environmental 
Satellites (POES), managed by the National Oceanic and Atmospheric 
Administration's (NOAA) National Environmental Satellite, Data, and 
Information Service (NESDIS), and the Defense Meteorological Satellite 
Program (DMSP), managed by the Department of Defense (DOD). These 
satellites obtain environmental data that are processed to provide 
graphical weather images and specialized weather products, and that are 
the predominant input to numerical weather prediction models--all used 
by weather forecasters, the military, and the public. Polar satellites 
also provide data used to monitor environmental phenomena, such as 
ozone depletion and drought conditions, as well as data sets that are 
used by researchers for a variety of studies, such as climate 
monitoring.

Unlike geostationary satellites, which maintain a fixed position above 
the earth, polar-orbiting satellites constantly circle the earth in an 
almost north-south orbit, providing global coverage of conditions that 
affect the weather and climate. Each satellite makes about 14 orbits a 
day. As the earth rotates beneath it, each satellite views the entire 
earth's surface twice a day. Today, there are two operational POES 
satellites and two operational DMSP satellites that are positioned so 
that they can observe the earth in early morning, mid-morning, and 
early afternoon polar orbits. Together, they ensure that for any region 
of the earth, the data provided to users are generally no more than 6 
hours old. Figure 1 illustrates the current operational polar satellite 
configuration. Besides the four operational satellites, there are five 
older satellites in orbit that still collect some data and are 
available to provide some limited backup to the operational satellites 
should they degrade or fail. In the future, both NOAA and DOD plan to 
continue to launch additional POES and DMSP satellites every few years, 
with final launches scheduled for 2008 and 2010, respectively.

Figure 1: Configuration of Operational Polar Satellites:

[See PDF for image]

[End of figure]

Each of the polar satellites carries a suite of sensors designed to 
detect environmental data either reflected or emitted from the earth, 
the atmosphere, and space. The satellites store these data and then 
transmit the data to NOAA and Air Force ground stations when the 
satellites pass overhead. The ground stations then relay the data via 
communications satellites to the appropriate meteorological centers for 
processing.

Under a shared processing agreement among the four processing centers-
-NESDIS,[Footnote 2] the Air Force Weather Agency, Navy's Fleet 
Numerical Meteorology and Oceanography Center, and the Naval 
Oceanographic Office--different centers are responsible for producing 
and distributing different environmental data sets, specialized weather 
and oceanographic products, and weather prediction model outputs via a 
shared network. Each of the four processing centers is also responsible 
for distributing the data to its respective users. For the DOD centers, 
the users include regional meteorology and oceanography centers as well 
as meteorology and oceanography staff on military bases. NESDIS 
forwards the data to NOAA's National Weather Service for distribution 
and use by forecasters. The processing centers also use the Internet to 
distribute data to the general public. NESDIS is responsible for the 
long-term archiving of data and derived products from POES and DMSP.

In addition to the infrastructure supporting satellite data processing 
noted above, properly equipped field terminals that are within a direct 
line of sight of the satellites can receive real-time data directly 
from the polar-orbiting satellites. There are an estimated 150 such 
field terminals operated by the U.S. government, many by DOD. Field 
terminals can be taken into areas with little or no data communications 
infrastructure--such as on a battlefield or ship--and enable the 
receipt of weather data directly from the polar-orbiting satellites. 
These terminals have their own software and processing capability to 
decode and display a subset of the satellite data to the user. Figure 2 
depicts a generic data relay pattern from the polar-orbiting satellites 
to the data processing centers and field terminals.

Figure 2: Generic Data Relay Pattern for the Polar Meteorological 
Satellite System:

[See PDF for image]

[End of figure]

Polar Satellite Data, Products, and Uses:

Polar satellites gather a broad range of data that are transformed into 
a variety of products for many different uses. When first received, 
satellite data are considered raw data.[Footnote 3] To make them 
usable, the processing centers format the data so that they are time-
sequenced and include earth location and calibration information. After 
formatting, these data are called raw data records. The centers further 
process these raw data records into data sets, called sensor data 
records and temperature data records. These data records are then used 
to derive weather products called environmental data records (EDR). 
EDRs range from atmospheric products detailing cloud coverage, 
temperature, humidity, and ozone distribution; to land surface products 
showing snow cover, vegetation, and land use; to ocean products 
depicting sea surface temperatures, sea ice, and wave height; to 
characterizations of the space environment. Combinations of these data 
records (raw, sensor, temperature, and environmental data records) are 
also used to derive more sophisticated products, including outputs from 
numerical weather models and assessments of climate trends. Figure 3 is 
a simplified depiction of the various stages of data processing.

Figure 3: Satellite Data Processing Steps:

[See PDF for image]

[End of figure]

EDRs can be either images or quantitative data products. Image EDRs 
provide graphical depictions of the weather and are used to observe 
meteorological and oceanographic phenomena to track operationally 
significant events (such as tropical storms, volcanic ash,[Footnote 4] 
and icebergs), and to provide quality assurance for weather prediction 
models.

The following figures demonstrate polar-orbiting satellite images. 
Figure 4 is an image from a DMSP satellite showing an infrared picture 
taken over the west Atlantic Ocean. Figure 5 is a POES image of 
Hurricane Floyd, which struck the southern Atlantic coastline in 1999. 
Figure 6 is a polar-satellite image used to detect volcanic ash clouds, 
in particular the ash cloud resulting from the eruption of Mount Etna 
in 2001. Figure 7 shows the location of icebergs near Antarctica in 
February 2002.

Figure 4: DMSP Image of the West Atlantic Ocean:

[See PDF for image]

Source: Navy Fleet Numerical Meteorology and Oceanography Center.

[End of figure]

Figure 5: POES Image of Hurricane Floyd in 1999:

[See PDF for image]

Source: NOAA.

[End of figure]

Figure 6: POES Image of Volcanic Ash Cloud from Mt. Etna, Sicily, in 
2001:

[See PDF for image]

Source: NOAA.

[End of figure]

Figure 7: DMSP Image of Icebergs Near Antarctica:

[See PDF for image]

Source: Naval/National Ice Center.

[End of figure]

Quantitative EDRs are specialized weather products that can be used to 
assess the environment and climate or to derive other products. These 
EDRs can also be depicted graphically. Figures 8 and 9 are graphic 
depictions of quantitative data on sea surface temperature and ozone 
measurements, respectively. An example of a product that was derived 
from EDRs is provided in figure 10. This product shows how long a 
person could survive in the ocean--information used in military as well 
as search and rescue operations--and was based on sea surface 
temperature EDRs from polar-orbiting satellites.

Figure 8: Analysis of Sea Surface Temperatures from POES Satellite 
Data:

[See PDF for image]

Source: NOAA/NESDIS.

[End of figure]

Figure 9: Analysis of Ozone Concentration from POES Satellite Data:

[See PDF for image]

Source: NESDIS.

[End of figure]

Figure 10: Analysis of Water Survivability off the Atlantic Seaboard, 
January 2002:

[See PDF for image]

Source: Naval Oceanographic Office.

Note: Contour lines with blocked numbers depict survival time, in 
hours, without a survival suit..

[End of figure]

Another use of quantitative satellite data is in numerical weather 
prediction models. Based predominantly on observations from polar-
orbiting satellites and supplemented by data from other sources such as 
geostationary satellites, radar, weather balloons, and surface 
observing systems, numerical weather prediction models are used in 
producing hourly, daily, weekly, and monthly forecasts of atmospheric, 
land, and ocean conditions. These models require quantitative satellite 
data to update their analysis of weather and to produce new forecasts. 
Table 1 provides examples of models run by the processing centers. 
Figure 11 depicts the output of one common model.

Table 1: Common Numerical Weather Prediction Models Used by Processing 
Centers:

Model: Global Forecast System; Purpose: Global weather forecasts; 
Processing center: NESDIS/NCEP.

Model: Eta Model; Purpose: Regional weather forecasts; Processing 
center: NESDIS/NCEP.

Model: Mesoscale Model 5; Purpose: Regional forecasts; Processing 
center: Air Force Weather Agency.

Model: Advect Cloud Model; Purpose: Global cloud forecast and analysis; 
Processing center: Air Force Weather Agency.

Model: Navy Operational Global Atmospheric Prediction System; Purpose: 
Global weather forecasts; Processing center: Navy Fleet Numerical 
Meteorology and Oceanography Center.

Model: Coupled Oceanographic and Atmospheric Mesoscale Prediction 
System; Purpose: Regional weather forecasts; Processing center: Navy 
Fleet Numerical Meteorology and Oceanography Center.

Model: Wave Model; Purpose: Regional oceanographic forecasts; 
Processing center: Naval Oceanographic Office.

Source: NOAA and DOD.

[End of table]

Figure 11: Model Output Depicting a 6-Hour Precipitation Forecast:

[See PDF for image]

Source: NOAA/NCEP.

[End of figure]

All this information--satellite data, imagery, derived products, and 
model output--is used in mapping and monitoring changes in weather, 
climate, the ocean, and the environment. These data and products are 
provided to weather forecasters for use in issuing weather forecasts 
and warnings to the public and to support our nation's aviation, 
agriculture, and maritime communities. Also, weather data and products 
are used by climatologists and meteorologists to monitor the 
environment. Within the military, these data and products allow 
military planners and tactical users to focus on anticipating and 
exploiting atmospheric and space environmental conditions. For example, 
Air Force Weather Agency officials told us that accurate wind and 
temperature forecasts are critical to any decision to launch an 
aircraft that will need mid-flight refueling. In addition to these 
operational uses of satellite data, there is also a substantial need 
for polar satellite data for research. According to experts in climate 
research, the research community requires long-term, consistent sets of 
satellite data collected sequentially, usually at fixed intervals of 
time, in order to study many critical climate processes. Examples of 
research topics include long-term trends in temperature, precipitation, 
and snow cover.

The National Polar-orbiting Operational Environmental Satellite 
System:

Given the expectation that merging the POES and DMSP programs would 
reduce duplication and result in sizable cost savings, a May 1994 
Presidential Decision Directive required NOAA and DOD to converge the 
two satellite programs into a single satellite program capable of 
satisfying both civilian and military requirements. The converged 
program is called the National Polar-orbiting Operational Environmental 
Satellite System (NPOESS), and it is considered critical to the United 
States' ability to maintain the continuity of data required for weather 
forecasting and global climate monitoring. To manage this program, DOD, 
NOAA, and the National Aeronautics and Space Administration (NASA) have 
formed a tri-agency Integrated Program Office, located within NOAA.

Within the program office, each agency has the lead on certain 
activities. NOAA has overall responsibility for the converged system, 
as well as satellite operations; DOD has the lead on the acquisition; 
and NASA has primary responsibility for facilitating the development 
and incorporation of new technologies into the converged system. NOAA 
and DOD share the costs of funding NPOESS, while NASA funds specific 
technology projects and studies.

NPOESS Overview:

NPOESS is a major system acquisition estimated to cost almost $7 
billion over the 24-year period from the inception of the program in 
1995 through 2018.[Footnote 5] The program is to provide satellite 
development, satellite launch and operation, and integrated data 
processing. These deliverables are grouped into four main categories: 
(1) the launch segment, which includes the launch vehicle and 
supporting equipment, (2) the space segment, which includes the 
satellites and sensors, (3) the interface data processing segment, 
which includes the data processing system to be located at the four 
processing centers, and (4) the command, control, and communications 
segment, which includes the equipment and services needed to track and 
control satellites.

Program acquisition plans call for the procurement and launch of six 
NPOESS satellites over the life of the program and the integration of 
14 instruments, comprising 12 environmental sensors and 2 subsystems. 
Together, the sensors are to receive and transmit data on atmospheric, 
cloud cover, environmental, climate, oceanographic, and solar-
geophysical observations. The subsystems are to support 
nonenvironmental search and rescue efforts and environmental data 
collection activities. According to the Integrated Program Office, 8 of 
the 14 planned NPOESS instruments involve new technology development, 
whereas 6 others are based on existing technologies. The planned 
instruments and the state of technology on each are listed in table 2.

Table 2: Expected NPOESS Instruments:

Instrument name: Advanced technology microwave sounder; Description: 
This sensor is to measure microwave energy released and scattered by 
the atmosphere, and is to be used with infrared sounding data from 
NPOESS' cross-track infrared sounder to produce daily global 
atmospheric temperature, humidity, and pressure profiles; State of 
technology: New.

Instrument name: Aerosol polarimetry sensor; Description: This sensor 
is to retrieve specific aerosol (liquid droplets or solid particles 
suspended in the atmosphere, such as sea spray, smog, and smoke) and 
cloud measurements; State of technology: New.

Instrument name: Conical microwave imager/sounder; Description: This 
sensor is to collect microwave images and data needed to measure rain 
rate, ocean surface wind speed and direction, amount of water in the 
clouds, and soil moisture, as well as temperature and humidity at 
different atmospheric levels; State of technology: New.

Instrument name: Cross-track infrared sounder; Description: This sensor 
is to collect measurements of the earth's radiation to determine the 
vertical distribution of temperature, moisture, and pressure in the 
atmosphere; State of technology: New.

Instrument name: Data collection system; Description: This system 
collects environmental data from platforms around the world and 
delivers them to users worldwide; State of technology: Existing.

Instrument name: Earth radiation budget sensor; Description: This 
sensor measures solar short-wave radiation and long-wave radiation 
released by the earth back into space on a worldwide scale to enhance 
long-term climate studies; State of technology: Existing.

Instrument name: Global Positioning System occultation sensor; 
Description: This sensor is to measure the refraction of radio wave 
signals from the Global Positioning System and Russia's Global 
Navigation Satellite System to characterize the ionosphere; State of 
technology: New.

Instrument name: Ozone mapper/profiler suite; Description: This sensor 
is to collect data needed to measure the amount and distribution of 
ozone in the earth's atmosphere; State of technology: New.

Instrument name: Radar altimeter; Description: This sensor measures 
variances in sea surface height/topography and ocean surface roughness, 
which are used to determine sea surface height, significant wave 
height, and ocean surface wind speed and to provide critical inputs to 
ocean forecasting and climate prediction models; State of technology: 
Existing.

Instrument name: Search and rescue satellite aided tracking system; 
Description: This system detects and locates aviators, mariners, and 
land-based users in distress; State of technology: Existing.

Instrument name: Space environmental sensor suite; Description: This 
suite of sensors is to collect data to identify, reduce, and predict 
the effects of space weather on technological systems, including 
satellites and radio links; State of technology: New.

Instrument name: Survivability sensor; Description: This sensor 
monitors for attacks on the satellite and notifies other instruments in 
case of an attack; State of technology: Existing.

Instrument name: Total solar irradiance sensor; Description: This 
sensor monitors and captures total and spectral solar irradiance data; 
State of technology: Existing.

Instrument name: Visible/infrared imager radiometer suite; 
Description: This sensor is to collect images and radiometric data used 
to provide information on the earth's clouds, atmosphere, ocean, and 
land surfaces; State of technology: New.

Source: Integrated Program Office.

[End of table]

Unlike the current polar satellite program, in which the four centers 
use different approaches to process raw data into the environmental 
data records that they are responsible for, the NPOESS integrated data 
processing systemæto be located at the four centers--is expected to 
provide a standard system to produce these data sets and products. The 
four processing centers will continue to use these data sets to produce 
other derived products, as well as for input to their numerical 
prediction models.

NPOESS is planned to produce 55 EDRs, including atmospheric vertical 
temperature profile, sea surface temperature, cloud base height, ocean 
wave characteristics, and ozone profile. Some of these EDRs are 
comparable to existing products, whereas others are new. The user 
community designated six of these data products--supported by four 
sensors[Footnote 6]--as key EDRs, and noted that failure to provide 
them would cause the system to be reevaluated or the program to be 
terminated.

Acquisition Strategy:

The NPOESS acquisition program consists of three key phases: the 
concept and technology development phase, which lasted from roughly 
1995 to early 1997; the program definition and risk reduction phase, 
which began in early 1997 and ended in August 2002; and the engineering 
and manufacturing development and production phase, which began in 
August 2002 and is expected to continue through the life of the 
program. The concept and technology development phase began with the 
decision to converge the POES and DMSP satellites and included early 
planning for the NPOESS acquisition. This phase included the successful 
convergence of the command and control of existing DMSP and POES 
satellites at NOAA's satellite operations center.

The program definition and risk reduction phase involved both system-
level and sensor-level initiatives. At the system level, the program 
office awarded contracts to two competing prime contractors to prepare 
for NPOESS system performance responsibility. These contractors 
developed unique approaches to meeting requirements, designing system 
architectures, and developing initiatives to reduce sensor development 
and integration risks. These contractors competed for the development 
and production contract. At the sensor level, the program office 
awarded contracts to develop five sensors.[Footnote 7] This phase ended 
when the development and production contract was awarded. At that 
point, the winning contractor was expected to assume overall 
responsibility for managing continued sensor development.

The final phase, engineering and manufacturing development and 
production, began when the development and production contract was 
awarded to TRW in August 2002. At that time, TRW assumed system 
performance responsibility for the overall program. This responsibility 
includes all aspects of design, development, integration, assembly, 
test and evaluation, operations, and on-orbit support. Shortly after 
the contract was awarded, Northrop Grumman Space Technology purchased 
TRW and became the prime contractor on the NPOESS project.

Risk Reduction Activities Are Underway:

In May 1997, the Integrated Program Office assessed the technical, 
schedule, and cost risks of key elements of the NPOESS program, 
including (1) overall system integration, (2) the launch segment, (3) 
the space segment, (4) the interface data processing segment, and (5) 
the command, control, and communications segment. As a result of this 
assessment, the program office determined that three elements had high 
risk components: the interface data processing segment, the space 
segment, and the overall system integration. Specifically, the 
interface data processing segment and overall system integration were 
assessed as high risk in all three areas (technical, cost, and 
schedule), whereas the space segment was assessed to be high risk in 
the technical and cost areas, and moderate risk in the schedule area. 
The launch segment and the command, control, and communications segment 
were determined to present low or moderate risks. The program office 
expected to reduce its high risk components to low and moderate risks 
by the time the development and production contract was awarded, and to 
have all risk levels reduced to low before the first launch. Table 3 
displays the results of the 1997 risk assessment as well as the program 
office's estimated risk levels by August 2002 and by first launch.

Table 3: Actual Risk Levels in 1997, at Contract Award in August 
2002, and Projected Risk Level by First Launch:

[See PDF for image]

[End of table]

In order to meet its goals of reducing program risks, the program 
office developed and implemented multiple risk reduction initiatives. 
One risk reduction initiative specifically targeted the space segment 
risks by initiating the development of key sensor technologies in 
advance of the satellite system itself. Because environmental sensors 
have historically taken 8 years to develop, the program office began 
developing six of the eight sensors with more advanced technologies 
early. In the late 1990s, the program office awarded contracts for the 
development, analysis, simulation, and prototype fabrication of five of 
these sensors.[Footnote 8] In addition, NASA awarded a contract for the 
early development of one other sensor.[Footnote 9] Responsibility for 
delivering these sensors was transferred from the program office to the 
prime contractor when the NPOESS contract was awarded in August 
2002.[Footnote 10]

Another major risk reduction initiative expected to address risks in 
three of the four segments with identified risks is called the NPOESS 
Preparatory Project (NPP).[Footnote 11] NPP is a planned demonstration 
satellite to be launched in 2006, several years before the first NPOESS 
satellite launch in 2009. It is scheduled to host three of the four 
critical NPOESS sensors (the visible/infrared imager radiometer suite, 
the cross-track infrared sounder, and the advanced technology microwave 
sounder), as well as two other noncritical sensors. Further, NPP will 
provide the program office and the processing centers an early 
opportunity to work with the sensors, ground control, and data 
processing systems. Specifically, this satellite is expected to 
demonstrate about half of the NPOESS EDRs and about 93 percent of its 
data processing load.

Since our statement last year,[Footnote 12] the Integrated Program 
Office has made further progress on NPOESS. Specifically, it awarded 
the contract for the overall program and is monitoring and managing 
contract deliverables, including products that will be tested on NPP. 
The program office is also continuing to work on various other risk 
reduction activities, including learning from experiences with sensors 
on existing platforms, including NASA research satellites, the WINDSAT/
Coriolis weather satellite, and the NPOESS airborne sounding testbed.

NPOESS Faces Key Programmatic and Technical Risks:

While the program office has made progress both on the acquisition and 
risk reduction activities, the NPOESS program faces key programmatic 
and technical risks that may affect the successful and timely 
deployment of the system. Specifically, changing funding streams and 
revised schedules have delayed the expected launch date of the first 
NPOESS satellite, and concerns with the development of key sensors and 
the data processing system may cause additional delays in the satellite 
launch date. These planned and potential schedule delays could affect 
the continuity of weather data. Addressing these risks may result in 
increased costs for the overall program. In attempting to address these 
risks, the program office is working to develop a new cost and schedule 
baseline for the NPOESS program, which it hopes to complete by August 
2003.

NPOESS Funding and Schedule Are Changing:

When the NPOESS development contract was awarded, program office 
officials identified an anticipated schedule and funding stream for the 
program. The schedule for launching the satellites was driven by a 
requirement that the satellites be available to back up the final POES 
and DMSP satellites should anything go wrong during these satellites' 
planned launches. In general, program officials anticipate that roughly 
1 out of every 10 satellites will fail either during launch or during 
early operations after launch.

Key program milestones included (1) launching NPP by May 2006 in order 
to allow time to learn from that risk reduction effort, (2) having the 
first NPOESS satellite available to back up the final POES satellite 
launch in March 2008, and (3) having the second NPOESS satellite 
available to back up the final DMSP satellite launch in October 2009. 
If the NPOESS satellites were not needed to back up the final 
predecessor satellites, their anticipated launch dates would have been 
April 2009 and June 2011, respectively.

However, a DOD program official reported that between 2001 and 2002, 
the agency experienced delays in launching a DMSP satellite, causing 
delays in the expected launch dates of another DMSP satellite. In late 
2002, DOD shifted the expected launch date for the final DMSP satellite 
from 2009 to 2010. As a result, DOD reduced funding for NPOESS by about 
$65 million between fiscal years 2004 and 2007. According to NPOESS 
program officials, because NOAA is required to provide no more funding 
than DOD does, this change triggered a corresponding reduction in 
funding by NOAA for those years. As a result of the reduced funding, 
program office officials were forced to make difficult decisions about 
what to focus on first. The program office decided to keep NPP as close 
to its original schedule as possible because of its importance to the 
eventual NPOESS development, and to shift some of the NPOESS 
deliverables to later years. This shift will affect the NPOESS 
deployment schedule. Table 4 compares the program office's current 
estimates for key milestones, given current funding levels.

Table 3: Comparison of Key Milestones Related to the NPOESS Program:

Milestone: NPP launch; As of August 2002 contract award: May 2006; As 
of July 2003: October 2006.

Milestone: Final POES launch; As of August 2002 contract award: March 
2008; As of July 2003: March 2008.

Milestone: First NPOESS satellite available for launch; As of August 
2002 contract award: March 2008; As of July 2003: December 2009.

Milestone: First NPOESS satellite planned for launch; As of August 2002 
contract award: April 2009; As of July 2003: November 2009[A].

Milestone: Final DMSP launch; As of August 2002 contract award: October 
2009; As of July 2003: May 2010.

Milestone: Second NPOESS satellite available for launch; As of August 
2002 contract award: October 2009; As of July 2003: April 2011.

Milestone: Second NPOESS satellite planned for launch; As of August 
2002 contract award: June 2011; As of July 2003: June 2011.

Source: Integrated Program Office, DOD, and GAO.

[A] A program official reported that if the first NPOESS satellite is 
not needed to back up the final POES launch in March 2008, the 
contractor will prepare the satellite to be launched in a different 
orbit with a different suite of sensors. These factors will allow the 
launch to take place earlier than if the satellite were to be used as a 
backup to the final POES launch.

[End of table]

As a result of the changes in funding between 2003 and 2007, project 
office officials estimate that the first NPOESS satellite will be 
available for launch 21 months after it is needed to back up the final 
POES satellite. This means that should the final POES launch fail in 
March 2008, there would be no backup satellite ready for launch. Unless 
the existing operational satellite is able to continue operations 
beyond its expected lifespan, there could be a gap in satellite 
coverage. Figure 12 depicts the schedule delay.

Figure 12: Timeline of Delay in Launch Availability:

[See PDF for image]

[End of figure]

We have reported on concerns about gaps in satellite coverage in the 
past. In the early 1990s, the development of the second generation of 
NOAA's geostationary satellites experienced severe technical problems, 
cost overruns, and schedule delays, resulting in a 5-year schedule slip 
in the launch of the first satellite; this schedule slip left NOAA in 
danger of temporarily losing geostationary satellite data coverage--
although no gap in coverage actually occurred.[Footnote 13] In 2000, we 
reported that geostationary satellite data coverage was again at risk 
because of a delay in a satellite launch due to a problem with the 
engine of its launch vehicle.[Footnote 14] At that time, existing 
satellites were able to maintain coverage until the new satellite was 
launched over a year later--although one satellite had exceeded its 
expected lifespan and was using several backup systems in cases where 
primary systems had failed. DOD experienced the loss of DMSP satellite 
coverage in the 1970s, which led to increased recognition of the 
importance of polar-orbiting satellites and of the impact of the loss 
of satellite data.

Key Sensor Development Efforts Are Experiencing Cost Increases, 
Schedule Delays, and Performance Shortfalls:

In addition to the schedule issues facing the NPOESS program, concerns 
have arisen regarding key components. Although the program office 
reduced some of the risks inherent in developing new technologies by 
initiating the development of these sensors early, individual sensor 
development efforts have experienced cost increases, schedule delays, 
and performance shortfalls. The cost estimates for all four critical 
sensors (the ones that are to support the most critical NPOESS EDRs) 
have increased, due in part to including items that were not included 
in the original estimates, and in part to addressing technical 
issues.[Footnote 15] These increases range from approximately $60 
million to $200 million. Further, while all the sensors are still 
expected to be completed within schedule, many have slipped to the end 
of their schedule buffers--meaning that no additional time is available 
should other problems arise. Details on the status and changes in cost 
and schedule of four critical sensors are provided in table 5. The 
timely development of three of these sensors (the visible/infrared 
imager radiometer suite, the cross-track infrared sounder, and the 
advanced technology microwave sounder) is especially critical, because 
these sensors are to be demonstrated on the NPP satellite, currently 
scheduled for launch in October 2006.

Table 4: Comparison of Costs and Schedules of Four Critical SensorsA:

Critical sensors: Advanced technology microwave sounder[B]; 
Comparison of cost estimates (millions of dollars): Original: $78.6; 
Comparison of cost estimates (millions of dollars): Current: $137.8; 
Comparison of cost estimates (millions of dollars): Change: $59.2; 
Comparison of schedule estimates: Critical design review: Contract 
award: Dec 2001; Comparison of schedule estimates: Critical design 
review: Current date: May 2002; Comparison of schedule estimates: 
Critical design review: Change: 5 months; Comparison of schedule 
estimates: First unit delivery: Contract award: Oct 2004; Comparison of 
schedule estimates: First unit delivery: Current: Dec 2004; Comparison 
of schedule estimates: First unit delivery: Change: 2 months.

Critical sensors: Cross-track infrared sounder; Comparison of cost 
estimates (millions of dollars): Original: $74.1; Comparison of cost 
estimates (millions of dollars): Current:  $275.3; Comparison of cost 
estimates (millions of dollars): Change:  $201.2; Comparison of 
schedule estimates: Critical design review: Contract award: Jan 2003; 
Comparison of schedule estimates: Critical design review: Current date: 
Aug 2003; Comparison of schedule estimates: Critical design review: 
Change: 7 months; Comparison of schedule estimates: First unit 
delivery: Contract award: Feb 2005; Comparison of schedule estimates: 
First unit delivery: Current: Oct 2005; Comparison of schedule 
estimates: First unit delivery: Change: 8 months.

Critical sensors: Visible/infrared imager radiometer suite; Comparison 
of cost estimates (millions of dollars): Original: $297.6; Comparison 
of cost estimates (millions of dollars): Current: $426.75; Comparison 
of cost estimates (millions of dollars): Change:  $129.15; Comparison 
of schedule estimates: Critical design review: Contract award: Mar 
2002; Comparison of schedule estimates: Critical design review: Current 
date: Mar 2002; Comparison of schedule estimates: Critical design 
review: Change: 0 months; Comparison of schedule estimates: First unit 
delivery: Contract award: Dec 2004; Comparison of schedule estimates: 
First unit delivery: Current: Nov 2005; Comparison of schedule 
estimates: First unit delivery: Change: 11 months.

Critical sensors: Conical microwave imager/sounder; Comparison of cost 
estimates (millions of dollars): Original: $298.0; Comparison of cost 
estimates (millions of dollars): Current:  $384.5; Comparison of cost 
estimates (millions of dollars): Change:  $86.5; Comparison of schedule 
estimates: Critical design review: Contract award: Apr 2004; Comparison 
of schedule estimates: Critical design review: Current date: Nov 2005; 
Comparison of schedule estimates: Critical design review: Change: 19 
months; Comparison of schedule estimates: First unit delivery: Contract 
award: Apr 2006; Comparison of schedule estimates: First unit delivery: 
Current: Apr 2008; Comparison of schedule estimates: First unit 
delivery: Change: 24 months.

Source: Integrated Program Office and NASA data.

[A] Program officials noted that the recent estimates include items 
such as system integration and testing that were not included in the 
original estimates.

[B] NASA is incurring all costs for the development of the advanced 
technology microwave sounder instrument, which is to fly on NPP. The 
program office expects to fund the other advanced technology microwave 
sounder instruments at a cost of $206.6 million.

[End of table]

Critical sensors are also falling short of achieving the required 
levels of performance. As part of a review in early 2003, the program 
officials determined that all four critical sensors were at medium to 
high risk of shortfalls in performance. Program officials recently 
reported that since the time of that review, the concerns that led to 
those risk designations have been addressed, which contributed to the 
schedule delays and cost increases noted above. We have not evaluated 
the closure of these risk items. However, program officials acknowledge 
that there are still performance issues on two critical sensors which 
they are working to address. Specifically, officials reported that they 
are working to fix a problem with radio frequency interference on the 
conical microwave imager/sounder. Also, the program office is working 
with NASA to fix problems with electrostatic discharge procedures and 
misalignment of key components on the advanced technology microwave 
sounder. Further, the program office will likely continue to identify 
additional performance issues as the sensors are developed and tested. 
Officials anticipate that there could be cost increases and schedule 
delays associated with addressing performance issues.

Program officials reported that these and other sensor problems are not 
unexpected; previous experience with such problems was what motivated 
them to begin developing the sensors early. However, officials 
acknowledge that continued problems could affect the sensors' delivery 
dates and potentially delay the NPP launch. Any delay in that launch 
date could affect the overall NPOESS program because the success of the 
program depends on learning lessons in data processing and system 
integration from the NPP satellite.

Level of Effort and Time Needed to Develop the Interface Data 
Processing System for NPP and NPOESS Is Not Known:

The interface data processing system is a ground-based system that is 
to process the sensors' data so that they are usable by the data 
processing centers and the broader community of environmental data 
users. The development of this system is critical for both NPP and 
NPOESS. When used with NPP, the data processing system is expected to 
produce 26 of the 55 EDRs that NPOESS will provide, processing 
approximately 93 percent of the planned volume of NPOESS data. Further, 
the central processing centers will be able to work with these EDRs to 
begin developing their own specialized products with NPP data. These 
activities will allow system users to work through any problems well in 
advance of when the NPOESS data are needed. We reported last year that 
the volumes of data that NPOESS will provide present immense challenges 
to the centers' infrastructures and to their scientific capability to 
use these additional data effectively in weather products and 
models.[Footnote 16] We also noted that the centers need time to 
incorporate these new data into their products and models. Using the 
data processing system in conjunction with NPP will allow them to begin 
to do so.

While the data processing segment is currently on schedule, program 
officials acknowledge the potential for future schedule delays. 
Specifically, an initial version of the data processing system is on 
track to be delivered at the end of July, and a later version is being 
planned. However, the data processing system faces potential risks that 
could affect the availability of NPP and in turn NPOESS. Specifically, 
program officials reported that there is a risk that the roughly 32 
months allocated for developing the remaining software and delivering, 
installing, and verifying the system at two central processing centers 
will not be sufficient. A significant portion of the data processing 
system software involves converting scientific algorithms for 
operational use, but program officials noted that there is still 
uncertainty in how much time and effort it will take to complete this 
conversion. Any significant delays could cause the potential coverage 
gap between the launches of the final POES and first NPOESS satellites 
to grow even larger.

NPOESS Program Office Is Working to Address Risks:

Program officials are working to address the changes in funding levels 
and schedule, and to make plans for addressing specific sensor and data 
processing system risks. They acknowledge that delays in the program 
and efforts to address risks on key components could increase the 
overall cost of the program, which could result on the loss of some or 
all of the promised cost savings from converging the two separate 
satellite systems. However, estimates on these cost increases are still 
being determined. The program office is working to develop a new cost 
and schedule baseline based on the fiscal year 2004 President's budget 
for the NPOESS program. Officials noted that this rebaselining effort 
will involve a major contract renegotiation. Program officials reported 
that they hope to complete the new program baseline by August 2003.

In summary, today's polar-orbiting weather satellite program is 
essential to a variety of civilian and military operations, ranging 
from weather warnings and forecasts to specialized weather products. 
NPOESS is expected to merge today's two separate satellite systems into 
a single state-of-the-art weather and environmental monitoring 
satellite system to support all military and civilian users, as well as 
the public. This new satellite system is considered critical to the 
United States' ability to maintain the continuity of data required for 
weather forecasting and global climate monitoring through the year 
2018, and the first satellite was expected to be ready to act as a 
backup should the launch of the final satellites in the predecessor 
POES and DMSP programs fail.

The NPOESS program office has made progress over the last years in 
trying to reduce project risks by developing critical sensors early and 
by planning the NPOESS Preparatory Project to demonstrate key sensors 
and the data processing system well before the first NPOESS launch. 
However, the NPOESS program faces key programmatic and technical risks 
that may affect the successful and timely deployment of the system. 
Specifically, changing funding streams and revised schedules have 
delayed the expected launch date of the first NPOESS satellite, and 
concerns with the development of key sensors and the data processing 
system may cause additional delays in the satellite launch date. These 
factors could affect the continuity of weather data needed for weather 
forecasts and climate monitoring.

This concludes my statement. I would be pleased to respond to any 
questions that you or other members of the Subcommittee may have at 
this time.

Contact and Acknowledgements:

If you have any questions regarding this testimony, please contact 
David Powner at (202) 512-9286 or by E-mail at pownerd@gao.gov. 
Individuals making key contributions to this testimony include Barbara 
Collier, John Dale, Ramnik Dhaliwal, Colleen Phillips, and Cynthia 
Scott.

[End of section]

Appendix I: Objectives, Scope, and Methodology:

Our objectives were to provide an overview of our nation's current 
polar-orbiting weather satellite program and the planned National 
Polar-orbiting Operational Environmental Satellite System (NPOESS) 
program and to identify key risks to the successful and timely 
deployment of NPOESS.

To provide an overview of the nation's current and future polar-
orbiting weather satellite system programs, we relied on prior GAO 
reviews of the satellite programs of the National Oceanic and 
Atmospheric Administration (NOAA) and the Department of Defense (DOD). 
We reviewed documents from NOAA, DOD, and the National Aeronautics and 
Space Administration (NASA) that describe the purpose and origin of the 
polar satellite program and the status of the NPOESS program. We also 
interviewed Integrated Program Office and NASA officials to determine 
the program's background, status, and plans.

To identify key risks to the successful and timely deployment of 
NPOESS, we assessed the NPOESS acquisition status and program risk 
reduction efforts to understand how the program office plans to manage 
the acquisition and mitigate the risks to successful NPOESS 
implementation. We reviewed descriptions of the NPOESS sensors and 
interviewed officials at the Integrated Program Office, NASA, and DOD 
to determine the status of key sensors, program segments, and risk 
reduction activities. We also reviewed documents and interviewed 
program office officials on plans to address NPOESS challenges.

NOAA, DOD, and NASA officials generally agreed with the facts as 
presented in this statement and provided some technical corrections, 
which we have incorporated. We performed our work at the NPOESS 
Integrated Program Office, NASA headquarters, and DOD offices, all 
located in the Washington, D.C., metropolitan area. Our work was 
performed between April and July 2003 in accordance with generally 
accepted government auditing standards.

FOOTNOTES

[1] U.S. General Accounting Office, Polar-orbiting Environmental 
Satellites: Status, Plans, and Future Data Management Challenges, 
GAO-02-684T (Washington, D.C.: July 24, 2002); National Oceanic and 
Atmospheric Administration: National Weather Service Modernization and 
Weather Satellite Program, GAO/T-AIMD-00-86 (Washington, D.C.: Mar. 29, 
2000); and Weather Satellites: Planning for the Geostationary Satellite 
Program Needs More Attention, GAO-AIMD-97-37 (Washington, D.C.: Mar. 
13, 1997).

[2] Within NOAA, NESDIS processes the satellite data, and the National 
Centers for Environmental Prediction (NCEP), a component of NOAA's 
National Weather Service, runs the models. For simplicity, we refer to 
the combined NESDIS/NCEP processing center as the NESDIS processing 
center. 

[3] NOAA uses different nomenclature for its data processing stages: 
raw data are known as level 0 data; raw data records are known as level 
1a data; sensor data records and temperature data records are known as 
level 1b data; and environmental data records are known as level 2 
data.

[4] Volcanic ash presents a hazard to aviation because of its potential 
to damage engines.

[5] The fiscal year 2004 President's budget identified the $6.96 
billion estimate in base year dollars.

[6] The four sensors supporting key EDRs are (1) the advanced 
technology microwave sounder, (2)the conical microwave imager/sounder, 
(3) the cross-track infrared sounder, and (4) the visible/infrared 
imager radiometer suite.

[7] The five sensors include (1) the conical microwave imager/sounder, 
(2) the cross-track infrared sounder, (3) the Global Positioning System 
occultation sensor, (4) the ozone mapper/profiler suite, and (5) the 
visible/infrared imager radiometer suite.

[8] The five program office-initiated sensors include (1) the conical 
microwave imager/sounder, (2) the cross-track infrared sounder, 
(3) the Global Positioning System occultation sensor, (4) the ozone 
mapper/profiler suite, and (5) the visible/infrared imager radiometer 
suite.

[9] NASA contracted for the advanced technology microwave sounder 
sensor.

[10] In the case of the advanced technology microwave sounder sensor, 
NASA is responsible for developing the initial sensor while the NPOESS 
prime contractor is responsible for subsequent production of these 
sensors. 

[11] NPP will not address risks in the launch segment.

[12] GAO-02-684T.

[13] GAO/AIMD-97-37.

[14] GAO/T-AIMD-00-86.

[15] Program officials noted that the more recent cost estimates 
include items that were not included in the original estimates, such as 
system engineering, integration, and testing; overhead costs; on-orbit 
support; and additional units of one of the sensors, as well as costs 
to address technical issues.

[16] GAO-02-684T.