From the U.S. Government Accountability Office, www.gao.gov Transcript for: F-35 JOINT STRIKE FIGHTER: Actions Needed to Address Late Deliveries Description: DOD's F-35 has unique capabilities that make it crucial to U.S. national security. DOD awarded billions to 2 defense contractors to build the aircraft and its engine. In 2024, aircraft deliveries were late by an average of 238 days. To encourage timely delivery, among other things, DOD paid the contractors hundreds of millions in incentives over the last several years. Nonetheless, delivery time frames continued to worsen--but DOD continued to pay incentives. DOD plans to increase production until 2032, despite contractors' inability to keep up with current engine and aircraft deliveries. Our recommendations address these issues, and others. Related GAO Works: GAO-25-107632, F-35 Joint Strike Fighter: Actions Needed to Address Late Deliveries Released: September 2025 [ START ] [ Text On-Screen: ] The F-35 plays a crucial role in U.S. national security. DOD is upgrading the F-35's software and hardware. These upgrades are $6 billion over budget and at least five years behind schedule. Although deliveries were late, contractors still received incentive fees. As the F-35 program continues, there are opportunities for improvement. The program could benefit from adopting GAO's leading practices for product development. find out more @ GAO.gov image credits: DVIDS [ END ] For more info, check out our report GAO-25-107632 at: GAO.gov