This is the accessible text file for GAO report number GAO-14-447 
entitled 'Littoral Combat Ship: Deployment of USS Freedom Revealed 
Risks in Implementing Operational Concepts and Uncertain Costs' which 
was released on July 8, 2014. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 
GAO: 

Report to Congressional Committees: 

July 2014: 

Littoral Combat Ship: 

Deployment of USS Freedom Revealed Risks in Implementing Operational 
Concepts and Uncertain Costs: 

GAO-14-447: 

GAO Highlights: 

Highlights of GAO-14-447, a report to congressional committees. 

Why GAO Did This Study: 

The LCS was intended to be a low-cost surface combatant that uses 
innovative operational concepts, such as minimal crew size, to lower 
operations and support costs. In 2013, the Navy deployed USS Freedom, 
one of two LCS variants, to Singapore to “prove its concept,” 
demonstrate operational capabilities, and collect data on the ship's 
manning, training, maintenance, and logistics needs. 

The House report accompanying the National Defense Authorization Act 
for Fiscal Year 2014 mandated that GAO analyze the Navy's sustainment 
plans for its LCS program—including lessons from the USS Freedom 
deployment. This report addressed (1) the benefits and limitations of 
the operational data that have been collected on LCS ships; (2) the 
extent to which the Navy has evaluated risk in its operational support 
and sustainment concepts for LCS; and (3) how LCS life-cycle cost 
estimates compare with those for other surface-ship classes. GAO 
analyzed documents from the 2013 deployment, and LCS and surface-ship 
life-cycle costs, and interviewed program officials and USS Freedom 
crews. 

What GAO Found: 

The USS Freedom deployment provided beneficial data on operational 
support and sustainment concepts for the Littoral Combat Ship (LCS), 
but these data have limitations, and the Navy still lacks key data on 
LCS ships and concepts. The USS Freedom deployed for 10 months with a 
surface-warfare mission package, and the Navy collected data on items 
such as systems reliability and crew sleep hours. However, several 
factors limited the operational lessons learned. For example, 
mechanical problems prevented the ship from spending as much time at 
sea as planned. Further, the Navy continues to lack operational data 
for key operational and warfighting concepts, such as deployment with 
the other mission packages—mine countermeasures and antisubmarine 
warfare—and data on the other LCS variant which, under current plans, 
will comprise half the ship class. 

Although the Navy is adjusting some operational support and 
sustainment concepts, it has not yet addressed risks that remain in 
executing key concepts. 

* Manning: The crew experienced high workload and fell short of the 
Navy's sleep standards despite adding personnel for the deployment. 

* Training: Gaps remain in fully training LCS sailors prior to 
deployment. 

* Maintenance: The Navy is adjusting maintenance requirements and has 
not yet determined the optimal mix of contractor and crew workload to 
perform preventative maintenance. 

* Logistics: The Navy is reallocating duties among crew and shore 
support, but the infrastructure needed to support both variants is 
incomplete. 

Without fully analyzing risks in key concepts, the LCS may have 
operational limitations, deficits in personnel and materiel readiness, 
and higher costs. 

The Navy has produced life-cycle cost estimates for the LCS seaframes 
and mission modules. Although those estimates contain uncertainty and 
there are inherent difficulties in comparing the life-cycle costs of 
ships with differing capabilities and missions, the best available 
Navy data indicate that the annual per ship costs for LCS are nearing 
or may exceed those of other surface ships, including those with 
greater size and larger crews, such as frigates. 

Figure: Annualized Life-Cycle Cost Estimates of LCS and Navy Surface 
Ships: 

[Refer to PDF for image: illustrated vertical bar graph with 6 
photographs] 

Millions of 2014 dollars: 

Navy Surface Ship: PC-1 Patrol Coastal Ships; 
Annualized Life-Cycle Cost Estimate: $8 million. 

Navy Surface Ship: MCM-1 Mine Countermeasures Ships; 
Annualized Life-Cycle Cost Estimate: $24 million. 

Navy Surface Ship: FFG-7 Frigates; 
Annualized Life-Cycle Cost Estimate: $54 million. 

Navy Surface Ship: DDG-51 Destroyers (Flight IIA); 
Annualized Life-Cycle Cost Estimate: $88 million. 

Navy Surface Ship: CG-46 Cruisers (Upgraded); 
Annualized Life-Cycle Cost Estimate: $126 million. 

Navy Surface Ship: Littoral Combat Ships (LCS)
Annualized Life-Cycle Cost Estimate: $79 million: 
* Seaframes: $64 million; 
* Mission modules: $15 million. 

Source: GAO analysis of Navy information (data); Department of Defense 
(photos). GAO-14-447. 

[End of figure] 

What GAO Recommends: 

GAO is emphasizing its prior recommendations that, before buying more 
LCS ships, the Navy (1) conduct and consider the results of a risk 
assessment and (2) collect additional data and update cost estimates. 
The Department of Defense expressed concerns that its life-cycle cost 
data are not comparable across ship types. GAO believes the analysis 
provides a reasonable comparison using the best available data from 
the Navy, as discussed in the report. 

View GAO-14-447. For more information, contact John Pendleton at (202) 
512-3489 or pendletonj@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

USS Freedom Deployment Provided Some Data on LCS Operations, but the 
Navy Still Lacks Key Operational Data on LCS Ships and Concepts: 

The Navy Has Not Yet Fully Addressed Risks to Its Operational Support 
and Sustainment Concepts That Were Identified by the USS Freedom 
Deployment: 

Available LCS Cost Data Are Limited, but Annual Per-Ship Costs May Be 
Approaching Those of Other Multimission Surface Ships with Larger 
Crews: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Littoral Combat Ship Plan of Action and Milestones, as of 
March 2014: 

Appendix III: Remaining Risks in Implementing Littoral Combat Ship 
Operational Support and Sustainment Concepts: 

Appendix IV: Overview of Navy Surface Ships Used in Life-Cycle Cost 
Comparison: 

Appendix V: Comments from the Department of Defense: 

Appendix VI: GAO Contact and Staff Acknowledgments: 

Related GAO Products: 

Tables: 

Table 1: USS Freedom Underway Time in 7th Fleet Area of Responsibility: 

Table 2: Key Littoral Combat Ship (LCS) Systems and Concepts 
Demonstrated during USS Freedom Deployment to Singapore and Those That 
Require Future Overseas Deployments for Demonstration: 

Table 3: Summary of Risks to Littoral Combat Ship (LCS) Operational 
Support and Sustainment Concepts and Navy Actions to Address 
Observations from USS Freedom Deployment: 

Table 4: Summary of USS Freedom Crew Discussion Groups: 

Table 5: Status of Littoral Combat Ship (LCS) Plan of Action and 
Milestones Action Items as of March 2014: 

Figures: 

Figure 1: USS Freedom in Singapore: 

Figure 2: USS Freedom Deployment Operational Area and Selected Events: 

Figure 3: USS Freedom Operational Activities in 7th Fleet Area of 
Responsibility: 

Figure 4: Independence Variant Littoral Combat Ship (LCS): 

Figure 5: Life-Cycle Cost Estimates of Littoral Combat Ship (LCS) and 
Various Navy Surface Ships in Constant Fiscal Year 2014 Dollars: 

Figure 6: Extent of Overlap in Billets between Littoral Combat Ship 
(LCS) Core Crew and Mission-Module Crews: 

Figure 7: USS Freedom Sailor Conducting Engine Maintenance during 
Singapore Deployment: 

Abbreviations: 

DOD: Department of Defense: 

LCS: Littoral Combat Ship: 

LCS Squadron: LCS Class Squadron: 

NAVMAC: Navy Manpower Analysis Center: 

[End of section] 

United States Government Accountability Office: 
GAO:
441 G St. N.W. 
Washington, DC 20548: 

July 8, 2014: 

Congressional Committees: 

For over 10 years, the Navy has been refining the concept of 
operations for its newest class of surface warship--the Littoral 
Combat Ship (LCS). The LCS was intended to be a comparatively low-cost 
surface-combatant ship that could operate in the shallow waters close 
to shore, known as the littorals. Its design concept consists of two 
distinct parts--the ship itself (seaframe) and the interchangeable 
mission modules it is expected to carry and deploy (i.e., surface 
warfare, mine countermeasures, and antisubmarine warfare). In early 
2013, the Navy deployed its first LCS--USS Freedom--to Singapore to 
"prove its concept," demonstrate operational capabilities, and collect 
cost and other data on the ship's manning, training, maintenance, and 
logistics needs in the actual overseas environment in which it is 
expected to operate. The Navy recognizes that the LCS program faces 
distinct challenges as it continues to assess a number of operational 
support and sustainment concepts--such as reliance on shore support 
and the use of flyaway maintenance teams (i.e., contractors flown to 
the ship to conduct maintenance)--to determine whether they can be 
used together to minimize crew size and lower operations and support 
costs over the long term. As we previously reported, the Navy's 
acquisition approach to the LCS program involves a significant degree 
of concurrency; that is, the Navy is buying the ships while key 
concepts and performance are still being tested.[Footnote 1] The Navy 
is procuring two seaframe variants of different hull types from two 
different contractors.[Footnote 2] To date, the Navy has committed to 
procuring 24 seaframes, 12 of each variant, and plans to contract for 
up to 8 additional seaframes--while still testing the operational 
concepts it will use to employ the vessels.[Footnote 3] 

In prior reports, we identified numerous challenges related to the 
acquisition of LCS seaframes and mission modules and the 
implementation of their unique operational concepts. In February 2010, 
we reported several potential risks in implementing the new 
operational concepts for the LCS.[Footnote 4] In September 2013, we 
issued a For Official Use Only report and found deficiencies in the 
Navy's LCS life-cycle cost estimates, noting that uncertainty exists 
in these estimates because they were developed without actual 
operational and cost data. We recommended that the Navy conduct and 
consider the results of a risk assessment to identify operational 
limitations if the Navy's approach to personnel, training, and 
maintenance cannot be implemented as envisioned and that the Navy 
collect additional operational data and update its cost estimates 
before contracting for additional ships. The Navy partially concurred 
with the risk recommendation and concurred with the operational data 
and updated cost estimates recommendation, but has not yet completed 
implementation of these recommendations. 

In its report accompanying HR 1960, a bill for the National Defense 
Authorization Act for Fiscal Year 2014, the House Armed Services 
Committee mandated that GAO review and analyze the Navy's operational 
support and sustainment[Footnote 5] plans for its LCS program. 
[Footnote 6] For this report, we addressed (1) the benefits and 
limitations of the operational data that have been collected on LCS 
ships; (2) the extent to which the Navy has evaluated risk in its 
operational support and sustainment concepts for the LCS in the areas 
of manning, training, maintenance, and logistics; and (3) how LCS life-
cycle cost estimates compare with those for other surface-ship classes. 

To address the benefits and limitations of the operational data that 
have been collected on LCS ships, we analyzed and compared USS 
Freedom's planned deployment schedule with its actual executed 
schedule. We reviewed documentation related to USS Freedom's 
operational activities while it was deployed, including execution 
orders, concepts of operations, and exercise briefings. We also 
interviewed forward-deployed crew members in Singapore and Navy 
officials responsible for the ship's operational employment at 7th 
Fleet in Japan to discuss the successes and challenges of the 
deployment, including any limitations. Further, we analyzed the 
operational activities of USS Independence and interviewed Navy 
officials to determine what operational data have been collected on 
the Independence variant. Finally, we reviewed and analyzed the LCS 
wholeness and warfighting concepts of operations to identify any 
additional LCS operational and warfighting concepts that still need to 
be demonstrated in an operational environment. 

To assess the extent to which the Navy has evaluated risk in its 
operational support and sustainment concepts for the LCS in the areas 
of manning, training, maintenance, and logistics, we reviewed relevant 
data-collection and analysis plans and mid-point and final reports on 
the Freedom 2013 deployment to Singapore from the Commander Naval 
Surface Forces Pacific, 7th Fleet, and the Center for Naval Analyses. 
We also interviewed officials from organizations responsible for 
collecting and analyzing data from this deployment. We reviewed the 
LCS wholeness concept of operations, the life-cycle sustainment plans 
for the LCS, and various other Navy documents associated with LCS 
manning, training, maintenance, and logistics, and interviewed USS 
Freedom crews who participated in the 2013 deployment to obtain their 
perspectives on the implementation of these concepts. 

To assess how LCS life-cycle cost estimates compare with those for 
other surface-ship classes, we modified a framework used in a similar 
comparison published by the Congressional Budget Office in 2010. 
[Footnote 7] To do this, we reviewed cost estimates in the current LCS 
Seaframe Program Life Cycle Cost Estimate (2011) and the LCS Mission 
Module Program Life Cycle Cost Estimate (2013). Although the Navy to 
date has not updated these life-cycle cost estimates to reflect 
changes in the program, the Navy adjusted the estimates for inflation 
to fiscal year 2014 dollars. Using these data, we calculated an annual 
per ship life-cycle cost estimate for the combined LCS seaframes and 
mission modules to account for differences in the number of ships and 
mission modules and their respective expected service lives. We also 
obtained life-cycle cost data in fiscal year 2014 dollars from the 
Navy for five surface ships, patrol coastal ships, mine 
countermeasures ships, frigates, destroyers, and cruisers, and used 
these data to calculate an annual per ship life-cycle cost estimate 
for each of these five surface ships. We then compared these data with 
the data we calculated for the LCS seaframes and mission modules. We 
analyzed and assessed these data and found them to be sufficiently 
reliable for the purposes of reporting the estimated life-cycle costs 
of these surface ships. We selected the non-LCS surface ships used for 
our comparison because cost data were readily available and they all 
conduct at least one mission that the LCS is also expected to perform. 
A more detailed-description of our scope and methodology is presented 
in appendix I. 

We conducted this performance audit from September 2013 to July 2014 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Background: 

The LCS was intended to be a comparatively low-cost surface combatant 
that could address the challenges of operating U.S. military forces in 
the shallow waters close to shore, known as the littorals. The ship is 
designed for three principal missions: surface warfare, mine 
countermeasures, and antisubmarine warfare--to address threats posed 
by small surface boats, mines, and submarines, respectively. Its 
design concept consists of two distinct parts--the ship itself 
(seaframe) and the interchangeable mission modules it is expected to 
carry and deploy. These mission modules consist of containers carrying 
various unmanned systems, sensors, and weapons that provide different 
combat capabilities for the ship's three principal missions. These 
mission modules are intended to give the Navy the flexibility to 
change equipment to meet different mission needs while forward 
deployed. The mission modules, when combined with the mission-module 
crew and an aviation detachment--consisting of an MH-60 helicopter and 
its flight and support crew, as well as vertical takeoff unmanned 
aerial vehicles--make up a mission package. The LCS is designed to 
embark with only one mission package at a time. 

The Navy envisioned the LCS as a ship that could operate with a much 
smaller crew size than other surface combatants, with preventative 
maintenance duties performed primarily by contractors. This concept 
would in turn lead to lower operations and support costs, which 
traditionally account for about 70 percent of the total cost over a 
ship's lifetime. The Navy planned the LCS to have a core crew of 40 
sailors and mission-module crews of 15 to 20 sailors--far fewer than 
the crew of approximately 170 sailors for a frigate and approximately 
250 sailors for a destroyer. To meet its operational, maintenance, 
support, and administrative needs with these reduced manning levels, 
the Navy is developing a new maintenance and support concept.[Footnote 
8] Unlike other ships, the LCS would have no onboard administrative 
personnel and a limited ability to conduct maintenance at sea; 
instead, it would rely heavily on shore-based support, including 
flyaway maintenance teams made up of contractors flown in to conduct 
scheduled maintenance. The Navy also opted to use a rotational crewing 
concept, whereby three crews rotate between two ships, one of which is 
forward deployed. The Navy has used a different form of rotational 
crewing on ballistic missile submarines for years but has not used it 
widely on surface combatants.[Footnote 9] 

As of July 2014, the Navy has accepted delivery of four LCS seaframes-
-two of each variant--and has already contracted for 20 more seaframes 
(10 of each variant). The Navy plans to award contracts for up to 
eight additional seaframes.[Footnote 10] Twelve seaframes are 
currently in production, and at the same time the Navy is in the 
process of incrementally developing and procuring the three mission 
packages. 

Several Navy organizations and commands have responsibilities for 
managing the LCS program, overseeing training, and maintaining 
readiness of LCS ships: 

* The Program Executive Office Littoral Combat Ship provides a single 
program executive who is responsible for acquiring and maintaining the 
littoral mission capabilities of the LCS class--from procurement to 
fleet employment and sustainment. 

* The LCS Class Squadron (LCS Squadron) oversees LCS seaframes, 
mission modules, and their crews for numerous functional area 
requirements including, among others, administrative, personnel, 
operational, maintenance, logistics, training, and facilities. 

* The LCS Council--established by the Chief of Naval Operations in 
August 2012 to ensure the successful introduction of the LCS into the 
fleet--created an LCS Plan of Action and Milestones to address program 
challenges and continues to use this tool to monitor progress across 
the program.[Footnote 11] Our September 2013 report contains a 
description of how the council tracks progress through the LCS Plan of 
Action and Milestones, and a status update on the LCS Plan of Action 
and Milestones can be found in appendix II. 

USS Freedom Deployment Provided Some Data on LCS Operations, but the 
Navy Still Lacks Key Operational Data on LCS Ships and Concepts: 

The USS Freedom's deployment to Singapore was an opportunity for the 
Navy to learn lessons about the feasibility and sustainability of 
unique LCS operational support and sustainment concepts in an 
operational environment. The Navy was able to collect data during the 
deployment on items such as systems usage and reliability and crew 
sleep hours. However, several factors, such as mechanical failures 
during the deployment, limited the operational lessons learned and the 
extent to which they are projectable across the LCS class. 
Additionally, the Navy continues to lack overseas deployment data for 
the Independence variant ships and for additional operational and 
warfighting concepts--such as overseas mission-package swaps and 
deployment with the mine countermeasures and antisubmarine-warfare 
mission packages. 

Deployment to Singapore Intended to Examine Operational Concepts: 

In March 2013, the Navy deployed its first LCS--USS Freedom--to 
Singapore with an increment 2 surface-warfare mission package for the 
first-ever overseas-based operational deployment of an LCS.[Footnote 
12] Navy officials saw the deployment as an opportunity to examine the 
feasibility of LCS manning, training, maintenance, and logistics 
concepts in an operational environment including, among other things, 
using a minimally sized crew, swapping out one crew with another while 
forward deployed, and maintaining the ship primarily with private 
contractors. Although the Navy concept of operations envisioned 40 
sailors in the LCS core crew, the core crew was increased to 50 for 
the Singapore deployment as a pilot program to address crew fatigue 
and workload concerns that the Navy was already aware of before the 
deployment. USS Freedom deployed for 10 months and conducted one crew 
swap midway through the deployment, operating in 7th Fleet's area of 
responsibility and using Singapore as a logistics and maintenance hub 
(see figure 1).[Footnote 13] 

Figure 1: USS Freedom in Singapore: 

[Refer to PDF for image: photograph] 

Source: Department of Defense (DOD). GAO-14-447. 

[End of figure] 

USS Freedom Deployment Provided Some Useful Data on Operational 
Support and Sustainment Concepts, but Several Factors Limited the 
Lessons Learned: 

During its 10-month deployment to the 7th Fleet area of 
responsibility, USS Freedom participated in joint exercises with 
regional partners, maritime security operations, and disaster-relief 
efforts in the Philippines following Typhoon Haiyan. Figure 2 provides 
an overview of the operational area for the USS Freedom deployment and 
shows the sites of selected events. 

Figure 2: USS Freedom Deployment Operational Area and Selected Events: 

[Refer to PDF for image: map of deployment area] 

Cooperation Afloat Readiness and Training Malaysia; 
Southeast Asia Cooperation and Training; 
Typhoon Assistance; 
Cooperation Afloat Readiness and Training Singapore. 

Source: GAO analysis of Navy information (data); Map Resources (map). 
GAO-14-447. 

[End of figure] 

The ship and crew implemented some of the LCS-specific operational 
support and sustainment concepts, including a crew swap that took 
place in August 2013 as well as the use of contractor teams for 
scheduled maintenance periods in Singapore.[Footnote 14] Additionally, 
several commands and organizations responsible for analyzing lessons 
learned from the deployment--including the Commander Naval Surface 
Forces Pacific, the Naval Warfare Development Command, and the Center 
for Naval Analyses--collected data during the USS Freedom deployment 
on equipment reliability rates and crew-reported sleep statistics, 
among other things. For example, the Freedom crew provided daily 
reports on the amount of time they spent sleeping, training, and 
completing preventative and corrective maintenance. After USS Freedom 
returned to San Diego, nearly every LCS stakeholder--including the 
operational commander of the ship in Singapore (Commander, Destroyer 
Squadron Seven) and each of the USS Freedom crews--produced lessons-
learned summaries. According to Navy officials, they were able to 
learn some operational lessons from the 10-month deployment. For 
example: 

* The Freedom deployment demonstrated the LCS's ability to participate 
in theater security-cooperation activities, such as joint exercises 
with regional navies, and helped carry out the Navy's forward-presence 
mission in Southeast Asia--thereby freeing larger multimission 
warships to carry out other high-priority Navy duties. 

* Navy officials are implementing a condition-based maintenance system 
on the LCS, whereby sensors provided some useful data on system usage 
and reliability.[Footnote 15] For example, medium-pressure air 
compressors had seen high casualty rates on USS Freedom prior to the 
deployment. However, Navy officials reported that USS Freedom did not 
experience significant failures of these compressors during the 
Singapore deployment because they were constantly monitored by sensors 
and were replaced before they could fail. 

Navy officials reported that data and lessons learned collected during 
the USS Freedom deployment will be used to develop and refine the 
concept of operations for the USS Fort Worth (Freedom variant) 
deployment and the LCS wholeness concept of operations. USS Fort Worth 
(LCS 3) is scheduled to deploy to Singapore in late 2014, and the next 
revision of the wholeness concept of operations is scheduled for 
completion in November 2014. 

Although the Navy collected some useful data from the deployment, 
mechanical issues reduced time at sea with 55 total mission days lost, 
limiting the operational lessons learned. The operational effect of 
these lost mission days was that the ship had to cut short its 
participation in two joint exercises and did not complete at least two 
of its planned presence operations.[Footnote 16] Our analysis of USS 
Freedom's actual executed schedule showed that these mechanical 
failures contributed to limiting the ship's underway time to 35 
percent of its deployment in the 7th Fleet area of responsibility (see 
table 1). Underway time includes all time the ship operated outside of 
port in the 7th Fleet area of responsibility including time spent 
transiting to and from Singapore. 

Table 1: USS Freedom Underway Time in 7th Fleet Area of Responsibility: 

Activity: Underway; 
Number of days: 53; 
Percentage of time: [Empty]. 

Activity: In transit under way to/from Singapore; 
Number of days: 40; 
Percentage of time: [Empty]. 

Activity: Total underway days; 
Number of days: 93; 
Percentage of time: 35%. 

Activity: In port in Singapore; 
Number of days: 155; 
Percentage of time: [Empty]. 

Activity: Other port time; 
Number of days: 17; 
Percentage of time: [Empty]. 

Activity: Total time in port; 
Number of days: 172; 
Percentage of time: 65%. 

Activity: Total days in 7th Fleet, including transit; 
Number of days: 265; 
Percentage of time: 100%. 

Source: GAO analysis of Navy data. GAO-14-447. 

Note: Underway percentage is calculated using USS Freedom executed 
schedule and includes all time the ship operated outside of port in 
the 7th Fleet area of responsibility (i.e., under way), including 
transit to and from Singapore. 

[End of table] 

The 7th Fleet concept of operations for the USS Freedom deployment 
stated that the ship should spend more time outside of Singapore 
(i.e., greater than 50 percent) than in port in Singapore. However, 
during its 10-month deployment, USS Freedom spent 58 percent of its 
time in port in Singapore (see figure 3). According to 7th Fleet 
officials, other ships deployed to the 7th Fleet area of 
responsibility typically spend about 20 percent of their time in port. 
LCS program officials explained that the unique LCS maintenance 
concept--USS Freedom returned to port every 25 days to undergo a 5-day 
preventative maintenance availability and every 120 days for more-
intensive 2-week intermediate maintenance--resulted in a rigid 
deployment schedule with more port time than other deployed Navy 
ships. However, Navy officials acknowledged that the mechanical issues 
on this deployment extended the ship's time in port. LCS program 
officials told us that while equipment problems limited operational 
lessons learned, the Navy gained experience conducting emergent 
repairs overseas and putting stress on the LCS maintenance concept. 

Figure 3: USS Freedom Operational Activities in 7th Fleet Area of 
Responsibility: 

[Refer to PDF for image: pie-chart] 

265 total days in 7th Fleet area of responsibility: 
In port in Singapore: 58%; 
In transit to/from Singapore[A]: 18%; 
7th Fleet exercises: 9%; 
7th Fleet operations: 8%; 
Crew workups/sea trials: 7%. 

Source: GAO analysis of Navy data. GAO-14-447. 

[A] In-transit time includes stops in Guam, Philippines, Brunei, and 
some taskings from 7th Fleet (e.g., tracking vessels of interest). 

[End of figure] 

Additionally, some Freedom systems, such as several water-jet 
components and the satellite communication system, are unique to that 
hull, and their performance data cannot be generalized even to other 
Freedom variant ships. USS Freedom is different in several respects 
from later (follow-on) ships of its own variant, since some major 
equipment has been changed. As a result, learning about these systems' 
performance during deployment cannot be directly applied to predict 
how the replacement systems might perform on other ships of the 
Freedom variant. According to the Navy, improving these systems should 
mean that future deployments of other ships from the Freedom variant 
will not incur the same number of equipment problems as USS Freedom 
did. However, as the Department of Defense's Director of Operational 
Test and Evaluation noted, no formal operational testing has been 
conducted to verify and quantify the effect of these changes, so 
further deployments or additional underway time, or both, will be 
necessary before the effects of these improvements on ship 
availability can be determined.[Footnote 17] 

The Navy Continues to Lack Operational Data on the Other LCS Variant: 

The Navy continues to lack operational data, specifically overseas 
deployment data, on the other LCS variant--the Independence variant--
which, under current plans, is expected to comprise half of the LCS 
ship class (see figure 4). 

Figure 4: Independence Variant Littoral Combat Ship (LCS): 

[Refer to PDF for image: photograph] 

Source: Department of Defense (DOD). GAO-14-447. 

[End of figure] 

In September 2013, we reported that the Navy had not scheduled an 
overseas operational deployment for an Independence variant LCS and 
therefore would not have comparable actual data and lessons learned 
for this variant. We recommended that the Navy collect actual 
operational data on this variant and the Navy concurred, stating that 
it would identify the actions and milestones needed to collect 
additional actual operational data on the Independence variant. 
However, the Department of Defense's Director of Operational Test and 
Evaluation noted in January 2014 that the core combat capabilities of 
the Independence variant seaframe remain largely untested and that 
equipment reliability problems have degraded the operational 
availability of USS Independence (LCS 2).[Footnote 18] 

While the Navy deployed a Freedom variant LCS to Singapore for nearly 
all of 2013, our analysis found that, over the same period, USS 
Independence spent about 8 months, or 65 percent, of 2013 in port or 
dry dock maintenance periods, limiting any operational data that the 
Navy could obtain when operating the ship out of its homeport in 
California. In addition, according to Navy officials, from October 
2012 to December 2013, USS Independence spent only 44 days under 
way.[Footnote 19] Navy officials told us that an Independence variant 
LCS needs to deploy to Singapore to determine whether the LCS 
operational support and sustainment concepts will be feasible and 
effective in supporting this variant, since not only does it have 
different systems than the Freedom variant that require different 
logistical support, but Singapore presents unique environmental 
conditions such as high humidity and warm ocean temperatures. At the 
time of our review, the Navy stated that it has notional plans to 
deploy an Independence variant LCS sometime before 2017. Navy 
officials also noted that an extended test period is planned in 2014 
for the mine countermeasures mission package for USS Independence. 
This testing will take place in the Gulf of Mexico near Florida, and 
the ship will use Pensacola to exercise the maintenance concept 
outside of homeport. 

Additional LCS Concepts Need Operational Demonstration: 

LCS operational and warfighting concepts that require demonstration in 
an operational environment include overseas mission-package swaps, 
deployments of the mine countermeasures and antisubmarine warfare 
mission packages, and tests of warfighting concepts in exercises 
related to operational plans, among others.[Footnote 20] According to 
the 7th Fleet USS Freedom deployment concept of operations, the 
Freedom deployment was intended to support validation of warfighting 
and wholeness concepts. However, the deployment largely focused on 
sustainment concepts, and key warfighting concepts were not 
demonstrated. Table 2 shows the key LCS systems and concepts 
demonstrated during the USS Freedom deployment to Singapore and those 
that require future deployments to demonstrate their feasibility. 

Table 2: Key Littoral Combat Ship (LCS) Systems and Concepts 
Demonstrated during USS Freedom Deployment to Singapore and Those That 
Require Future Overseas Deployments for Demonstration: 

Mission package: 

System/concept: Surface warfare[C]; 
Planned for and demonstrated during deployment: [Check]; 
Not yet demonstrated during a deployment: [Empty]. 

System/concept: Mine countermeasures; 
Planned for and demonstrated during deployment: [Empty]; 
Not yet demonstrated during a deployment: [Check]. 

System/concept: Antisubmarine warfare; 
Planned for and demonstrated during deployment: [Empty]; 
Not yet demonstrated during a deployment: [Check]. 

Wholeness concepts[A]: 

System/concept: Shore-based maintenance concept in Singapore; 
Planned for and demonstrated during deployment: [Check]; 
Not yet demonstrated during a deployment: [Empty]. 

System/concept: Overseas crew swap; 
Planned for and demonstrated during deployment: [Check]; 
Not yet demonstrated during a deployment: [Empty]. 

System/concept: Core crew size of 50; 
Planned for and demonstrated during deployment: [Check]; 
Not yet demonstrated during a deployment: [Empty]. 

System/concept: LCS rotational crewing strategy[D]; 
Planned for and demonstrated during deployment: [Empty]; 
Not yet demonstrated during a deployment: [Check]. 

System/concept: 16-month deployment; 
Planned for and demonstrated during deployment: [Empty]; 
Not yet demonstrated during a deployment: [Check]. 

System/concept: Shore-based maintenance concept outside of Singapore; 
Planned for and demonstrated during deployment: [Empty]; 
Not yet demonstrated during a deployment: [Check]. 

Warfighting concepts[B]: 

System/concept: Theater security cooperation; 
Planned for and demonstrated during deployment: [Check]; 
Not yet demonstrated during a deployment: [Empty]. 

System/concept: Exercise related to operational plans; 
Planned for and demonstrated during deployment: [Empty]; 
Not yet demonstrated during a deployment: [Check]. 

System/concept: Overseas mission-package swap; 
Planned for and demonstrated during deployment: [Empty]; 
Not yet demonstrated during a deployment: [Check]. 

Source: GAO analysis of Department of Defense (DOD) data. GAO-14-447. 

[A] Concepts found in U.S. Fleet Forces Command, LCS Platform 
Wholeness Concept of Operations Revision D (Jan. 9, 2013). 

[B] Concepts found in classified warfighting concept of operations. 

[C] USS Freedom deployed with an increment 2 surface-warfare mission 
package. Four total increments are planned for this mission package. 

[D] The LCS rotational crewing strategy consists of three crews 
rotating between two ships, one of which is forward deployed. 

[End of table] 

To date, none of the mission packages have been completely developed, 
tested, and deployed.[Footnote 21] There are nine different capability 
increments within the three mission packages. USS Freedom deployed 
with an increment 2 surface-warfare mission package. There are two 
other mission packages for the LCS--mine countermeasures and 
antisubmarine warfare--neither of which has yet deployed. The three 
mission packages each require different crews and equipment and 
operate differently from one another, and the manning for each package 
differs in skill sets. This can alter the extent to which the mission 
package crew will be able to support the seaframe crew; to determine 
this, each mission package will need to be deployed. Navy officials 
said that the USS Fort Worth deployment beginning in late 2014 will 
address some, but not all, of these gaps. For example, Fort Worth will 
utilize the rotational crewing strategy, deploy for 16 months, and 
implement the shore-based maintenance concept outside of Singapore. 
However, Fort Worth will not swap mission packages while deployed. 
Navy officials also noted that additional war gaming is required to 
refine the operational use of the LCS seaframe and mission packages. 
The Navy held an operational war game in March 2014 to try to 
understand how well the LCS would support the Navy's needs and 
operational plans in various phases of operations in a Pacific theater 
crisis, but it has not yet released any formal reporting on the 
results of this effort. 

In September 2013, we recommended that the Navy collect actual 
operational data on the Independence variant prior to contracting for 
additional LCS ships in 2016. Our work shows that the Navy still lacks 
key operational data needed to refine its concepts and develop more-
reliable cost estimates. We believe our 2013 recommendation is still 
valid. 

The Navy Has Not Yet Fully Addressed Risks to Its Operational Support 
and Sustainment Concepts That Were Identified by the USS Freedom 
Deployment: 

Although the Navy is adjusting some operational support and 
sustainment concepts based on data collected and lessons learned 
during the USS Freedom deployment, it has not yet addressed some risks 
that remain in executing and sustaining key manning, training, 
maintenance, and logistics concepts. Federal standards for internal 
controls state that decision makers should comprehensively identify 
risks associated with achieving program objectives, analyze them to 
determine their potential effect, and decide how to manage the risk 
and identify what actions should be taken.[Footnote 22] This is an 
ongoing process, since operating conditions continually change. In 
2010, we reported that the Navy faced several risks in implementing 
new LCS concepts for manning, training, and maintenance necessitated 
by the small crew size, and recommended that the Navy conduct and 
consider the results of a risk assessment to identify operational 
limitations if the Navy's approach to manning, training, and 
maintenance cannot be implemented as envisioned; develop possible 
alternatives to these concepts; and make policy and process changes to 
reduce risks to the LCS program.[Footnote 23] At the time of this 
review, the Navy had not fully addressed our prior recommendation, 
although Navy officials told us that they have undertaken a number of 
activities to manage risks in the LCS program. For example, the LCS 
program office convenes a risk-management board on a regular basis to 
identify potential program risks. As the program attempts to manage 
and mitigate these risks, the maiden deployment of USS Freedom 
identified additional issues with the manning, training, maintenance, 
and logistics concepts that have not been fully addressed by the Navy. 
Key observations from the deployment, the actions the Navy has taken 
to address them, and the outstanding risks that still remain in 
further implementing LCS operational support and sustainment concepts 
are summarized below in table 3. 

Table 3: Summary of Risks to Littoral Combat Ship (LCS) Operational 
Support and Sustainment Concepts and Navy Actions to Address 
Observations from USS Freedom Deployment: 

Concept area: Manning; 
Observations from Freedom deployment: 
Freedom crews averaged about 6 hours of sleep per day compared to the 
Navy standard of 8 hours; 
Core crews augmented by mission-module crew and contractor ship 
riders, which is not part of the manning concept; 
Navy actions to address these observations: 
Navy is conducting a manpower study to validate the size and 
composition of Freedom core crew and surface-warfare mission-module 
crew; expected completion in 2015; 
Remaining risks: 
Navy has not yet conducted further manpower studies to validate 
Independence variant core crew and other two mission-module crews; 
Manpower studies do not account for the issue of core crews relying on 
mission-module crew and contractor ship riders to assist with their 
core crew functions. 

Concept area: Training; 
Observations from Freedom deployment: 
Not all core crew members were fully trained prior to deployment; 
Sailors were training while deployed, which is not part of the LCS 
concept of operations; 
Sailors widely reported the inadequacy of the training they received; 
Navy actions to address these observations: 
Navy is training late-addition ensigns and "plus-up" personnel to 
minimize training while deployed; 
Navy is developing simulator-based training to replace current vendor 
training; 
Navy is making some improvements to existing training based on crew 
feedback; 
Remaining risks: 
Training time during deployment not accounted for in LCS work day; 
While new training is being developed, sailors will still require 
training while under way; 
Gaps in training may exist until 2019, when the LCS training 
curriculum is expected to be fully implemented. 

Concept area: Maintenance; 
Observations from Freedom deployment: 
Freedom had a limited range due to its rigid maintenance schedule; 
Lack of continuity in contractor personnel conducting maintenance was 
an issue; 
Crew said that some maintenance would be performed more efficiently by 
contractors while some should be executed by crew; 
Navy actions to address these observations: 
Future deployments will have a longer, more-flexible interval for 
scheduling maintenance; 
Navy is continuously reviewing maintenance requirements and the mix of 
contractor-and sailor-executed workload; 
Navy is implementing a pilot condition-based maintenance program to 
increase maintenance efficiency; 
Remaining risks: 
Navy is still working to manage the scope of who is executing the work 
and establishing baseline tools to ensure accountability; 
Navy may utilize its maintenance contractors and LCS crews 
inefficiently until it determines the most-appropriate timing and 
number of planned LCS maintenance checks and the optimal mix of 
contractor-and crew-performed maintenance. 

Concept area: Logistics; 
Observations from Freedom deployment: 
Distance support reporting process not followed, resulting in 
duplication of effort among the crew and shore support personnel; 
Several limitations of LCS support infrastructure such as poor pier-
side Internet connectivity; 
Navy actions to address these observations: 
Navy is revising instructions for the LCS Squadron's Forward Liaison 
Element; 
Some reporting that was originally to be completed by shore support 
will be conducted by the crew; 
Navy is exploring options with the host-nation government to improve 
pier-side support; 
Remaining risks: 
The logistics infrastructure needed to support four LCSs in Singapore 
and at other planned forward operating stations has not been completed; 
LCS crews may be burdened with additional reporting requirements not 
factored into their workday; 
Additional lessons may be learned on supporting Independence variant 
ships when deployed. 

Source: GAO analysis of Navy and Center for Naval Analyses data. GAO-
14-447. 

[End of table] 

Our work shows that the Navy has not fully identified, analyzed, and 
mitigated the risks associated with LCS concepts. Having such a risk 
assessment would enable decision makers to identify and assess the 
operational effects if these concepts cannot be implemented as 
envisioned; alternatives to mitigate these risks; and information to 
link the effectiveness of these new operational concepts with 
decisions on program investment. If the operational concepts for 
manning, training, maintenance, and logistics cannot be implemented as 
desired, the Navy may face operational limitations, may have to 
reengineer its operational concept, or may have to make significant 
design changes to the ship after committing to building most of the 
class. The 2013 deployment of USS Freedom to Singapore highlighted 
that these risks remain. Therefore, we continue to believe that our 
2010 recommendation is valid. 

For additional details and information on our observations from the 
deployment, actions the Navy has taken to address them, and the 
outstanding risks that still remain in further implementing LCS 
concepts in the areas of manning, training, maintenance, and 
logistics, see appendix III. 

Available LCS Cost Data Are Limited, but Annual Per-Ship Costs May Be 
Approaching Those of Other Multimission Surface Ships with Larger 
Crews: 

Although the Navy's life-cycle cost estimates for the LCS seaframe and 
mission modules contain uncertainty, they indicate that the annualized 
per ship costs for the LCS may be approaching those of other 
multimission surface ships with larger crews. The Navy planned to use 
data collected during USS Freedom's deployment, particularly data on 
maintenance costs, to update and improve the life-cycle cost estimates 
for the LCS seaframe. The Navy collected cost data during USS 
Freedom's deployment to Singapore; however, Navy officials explained 
that much of the data may be of limited usefulness for projection 
across the LCS ship class. We reported in September 2013 that a lack 
of operational data had prevented the Navy from developing life-cycle 
cost estimates for the LCS seaframe above a relatively low confidence 
level. Although the Navy's LCS cost estimates contain uncertainty, 
especially in regard to operations and support costs, and there are 
inherent difficulties associated with comparing the life-cycle costs 
of various surface ships with differing capabilities and mission sets, 
we found that the per ship per year cost estimates for the LCS program 
are nearing or may exceed the costs of other surface ships, including 
multimission ships with greater size and more crew members, such as 
guided-missile frigates and destroyers. 

Usefulness of USS Freedom Deployment for Updating LCS Cost Estimates 
May Be Limited: 

During the course of our prior review, Navy officials explained that 
they planned to update and improve life-cycle cost estimates for the 
LCS seaframe, in part by using data collected during USS Freedom's 
deployment to Singapore. The deployment provided additional data 
associated with actual operations and support costs specific to USS 
Freedom, including maintenance and emergent repair costs. However, 
according to Navy officials, much of these data may be of limited 
usefulness for projection across the LCS ship class. In early 2014, 
Navy officials said that they were evaluating the deployment data but 
that first-time deployments on any ship class include costs related to 
issues that are not representative of the entire ship class and will 
therefore limit their ability to update the LCS life-cycle cost 
estimate for the seaframes. Two such factors are described below: 

* Certain problematic engineering systems that required emergent 
repairs and increased the overall deployment cost figures have been or 
will be replaced on future LCSs. 

* The fuel capacity and efficiency of USS Freedom will differ from 
other Freedom and Independence variant ships. 

In September 2013, we recommended that the Navy identify actions and 
milestones to collect additional actual operational data on the 
Independence variant and to update operations and support cost 
estimates for both variants.[Footnote 24] Navy officials said that an 
updated life-cycle cost estimate for the LCS seaframe would likely be 
available in the fall of 2014. However, based on the Navy's LCS 
deployment schedule, this update will likely not include additional 
overseas deployment-related cost data for either LCS variant; USS Fort 
Worth will not deploy until late 2014, and the Navy has only notional 
plans to deploy an Independence variant LCS sometime before 2017. 
[Footnote 25] Navy officials explained that the Navy will not have a 
life-cycle cost based on actual deployment data for the LCS until it 
is operating multiple LCSs from a forward location such as Singapore 
in accordance with employment and operational concepts. 

LCS Life-Cycle Cost Estimates Contain Uncertainty: 

The Navy estimated in 2011 that operations and support costs for the 
LCS seaframes would be about $50 billion over the life of the ship 
class. In 2013, it estimated that operations and support costs for the 
mission modules would be about $18 billion. Both of these estimates 
were calculated in fiscal year 2010 dollars.[Footnote 26] However, as 
we reported in September 2013, the seaframe estimate is at the 10 
percent confidence level, meaning that there is 90 percent chance that 
costs will be higher than this estimate.[Footnote 27] We reported that 
those estimates were at a low level of confidence due to overall lack 
of operational data on both LCS seaframes and operating concepts that 
are unique among the surface fleet. In lieu of actual LCS data, the 
Navy used operations and support data from other surface ships, such 
as frigates, and modified them to approximate LCS characteristics 
(referred to by the Navy as modified analogous data) to build the LCS 
cost estimate. For example, maintenance cost estimates were calculated 
by modifying analogous data from frigates and destroyers, among other 
ships, even though the maintenance concepts for these ships differ 
from those for the LCS.[Footnote 28] Moreover, since the time when the 
Navy developed the seaframe estimate in 2011, it has made several 
programmatic changes to LCS concepts that will increase the overall 
cost to operate and sustain the ship class.[Footnote 29] For example: 

* The number of shore personnel to support the ship has more than 
tripled--from 271 to 862--since the estimate was developed in 2011, as 
support requirements have become better understood. 

* The Navy has increased the total number of core crew members onboard 
each ship from 40 to 50 in order to better address workload and watch-
standing requirements.[Footnote 30] 

As the Navy continues to better understand the work requirements 
associated with the ship class, the required numbers of shore support 
and ship crew have risen. Navy officials explained that such changes 
are necessary for the success of the program and acknowledged that 
those changes would increase the overall costs of the LCS and should 
be included in future LCS life-cycle cost estimates. 

LCS Costs May Be Approaching Those of Other Surface Ships with Larger 
Crews: 

From the outset of the program, the Navy has described the LCS as a 
low-cost alternative to other ships in the surface fleet, yet the 
available data indicate that the per year, per ship life-cycle costs 
are nearing or may exceed those of other surface ships, including 
multimission ships with greater size and larger crews. The LCS 
consists of two distinct parts--the ship itself (seaframe) and the 
interchangeable mission modules it is expected to carry and deploy. 
These mission modules consist of various unmanned systems, sensors, 
and weapons that provide different combat capabilities for the ship's 
three principal missions. Many LCS cost estimates only refer to the 
acquisition cost of individual seaframes rather than the total life-
cycle cost of the seaframe and mission modules. The operations and 
support costs for the LCS seaframe that are included in the life-cycle 
cost estimates are significant--due in part to unique LCS operational 
concepts--while the LCS mission modules that provide each ship with 
operational capability account for a significant component of the 
costs for the ship class. As we noted above, the cost estimates for 
both the seaframe and the mission modules contain uncertainty; 
however, we believe that when combined they provide the best available 
estimate to date of the overall life-cycle costs for the LCS program. 
Moreover, because the Navy has acknowledged it has made several 
programmatic changes to LCS concepts that will increase the overall 
costs to operate and sustain the ship class, it is likely that the per 
ship, per year life-cycle costs for the program will be higher than 
this current estimate.[Footnote 31] 

We analyzed the Navy's life-cycle cost estimates for LCS seaframes 
(2011) and mission modules (2013), which the Navy adjusted for 
inflation to fiscal year 2014 dollars, and used updated Navy life-
cycle cost estimates provided in April 2014 by Naval Sea Systems 
Command for patrol coastal ships, mine countermeasures ships, 
frigates, destroyers, and cruisers.[Footnote 32] These ships were 
selected for comparison because they have been in the surface fleet 
for decades and historical cost data are readily available, and they 
all conduct at least one mission that the LCS is also expected to 
perform. We calculated the life-cycle costs on a per ship annualized 
basis to account for differences in the number of ships and expected 
service life of each class. As shown in figure 5, we found that per 
ship life-cycle costs per year for the LCS program are nearing or may 
exceed those for other surface ships, including guided-missile 
frigates and multimission destroyers. 

We are providing a descriptive comparison of annual life-cycle costs 
per ship using available data and are not assessing the relative 
benefits and capabilities of these various ship classes. Navy 
officials point out that the below estimates may not include the full 
costs of developing, modernizing, and sustaining software and combat 
systems installed on the surface ships we use for comparative purposes 
(e.g., Aegis ballistic missile defense system used on cruisers and 
destroyers). Additionally, officials stated that the acquisition costs 
presented are not to be interpreted as replacement costs since a 
replacement value for the specific ship would have to take into 
account changes in productivity, design specifications, and 
legislative and contracting environments. Despite the inherent 
difficulties associated with comparing the life-cycle costs of various 
surface ships with differing capabilities and mission sets, and at 
different points in their respective service lives, we believe this 
analysis is useful because it provides a framework for comparing the 
life-cycle cost estimates of various surface ships on a per ship, per 
year basis, thereby accounting for variations in expected service life 
and the number of ships. For an overview of the surface ships used in 
figure 5, including their missions and crew sizes, see appendix IV. We 
used the Navy's expected ship service lives of record, although the 
Navy has made decisions to retire vessels before they've reached their 
expected service lives in some instances and has extended the service 
lives of other vessels, such as destroyers.[Footnote 33] For LCS 
seaframes, the Navy used a 25-year expected service life to calculate 
life-cycle costs, which is an average of the 20-year service-life 
threshold and 30-year service-life objective outlined in key 
performance parameters. 

Figure 5: Life-Cycle Cost Estimates of Littoral Combat Ship (LCS) and 
Various Navy Surface Ships in Constant Fiscal Year 2014 Dollars: 

[Refer to PDF for image: illustrated table with 7 photographs] 

Navy surface ships estimates (based on actual data): 

PC-1 Patrol Coastal Ships: 
Number of ships/modules: 13 ships; 
Life-cycle costs per ship/module: $243 million; 
* Research and development: 0[C]; 
* Procurement: $33 million; 
* Operations and support: $210 million; 
* Other[D]: 0; 
Expected service life: 30 years; 
Average life-cycle cost per year[E]: $8 million. 

MCM-1 Mine Countermeasures Ships; 
Number of ships/modules: 14 ships; 
Life-cycle costs per ship/module: $717 million; 
* Research and development: $3 million; 
* Procurement: $282 million; 
* Operations and support: $432 million; 
* Other[D]: 0; 
Expected service life: 30 years; 
Average life-cycle cost per year[E]: $24 million. 

FFG-7 Frigates; 
Number of ships/modules: 51 ships; 
Life-cycle costs per ship/module: $1.607 billion; 
* Research and development: $2 million; 
* Procurement: $579 million; 
* Operations and support: $1,026 billion; 
* Other[D]: 0; 
Expected service life: 30 years; 
Average life-cycle cost per year[E]: $54 million. 

DDG-51 Destroyers (Flight IIA]: 
Number of ships/modules: 34 ships; 
Life-cycle costs per ship/module: $3.508 billion; 
* Research and development: $91 million; 
* Procurement: $1.501 billion; 
* Operations and support: $1.916 billion; 
* Other[D]: 0; 
Expected service life: 40 years; 
Average life-cycle cost per year[E]: $88 million. 

CG-47 Cruisers (Upgraded); 
Number of ships/modules: 22 ships; 
Life-cycle costs per ship/module: $4.410 billion; 
* Research and development: $9 million; 
* Procurement: $1.964 billion; 
* Operations and support: $2.436 billion; 
* Other[D]: 0; 
Expected service life: 35 years; 
Average life-cycle cost per year[E]: $126 million. 

Littoral Combat Ships (LCS) estimates: 

LCS seaframes[A]: 
Number of ships/modules: 55 ships; 
Life-cycle costs per ship/module: $1.592 billion; 
* Research and development: $66 million; 
* Procurement: $506 million; 
* Operations and support: $1.013 billion; 
* Other[D]: $7 million; 
Expected service life: 25 years; 
Average life-cycle cost per year[E]: $64 million. 

LCS mission modules[B]: 
Number of ships/modules: 64 modules; 
Life-cycle costs per ship/module: $449 million; 
* Research and development: $37 million; 
* Procurement: $61 million; 
* Operations and support: $292 million; 
* Other[D]: $59 million; 
Expected service life: 30 years; 
Average life-cycle cost per year[E]: $15 million. 

Littoral Combat Ships (LCS) estimates, total : $79 million. 

Source: GAO analysis of Navy information (data); Department of Defense 
(DOD) (photos). GAO-14-447. 

Notes: Numbers may not add due to rounding. Life-cycle cost estimates 
for patrol coastal ships, mine countermeasures ships, frigates, 
destroyers, and cruisers were calculated by Naval Sea Systems Command 
in April 2014 in fiscal year 2014 constant dollars. For these ship 
classes, research and development costs are derived from class 
Selected Acquisition Reports. Procurement costs are derived from the 
Naval Sea Systems Command Historical Cost of Ships database. Multiyear 
historical averages for operations and support costs are derived from 
the Navy Visibility and Management of Operating and Support Costs 
database. As of April 2014, the Navy reduced its planned number of 
LCSs to 32 from an original requirement of 55 ships. The Navy created 
its Program Life Cycle Cost Estimate in 2011 based on the original 
requirement of 55 ships and has not updated this document to reflect 
the Navy's plan for 32 LCSs. We did not independently validate the 
underlying data for the Navy's estimates. 

[A] LCS seaframe life-cycle cost estimates are based on the purchase 
of 55 seaframes. The seaframe cost estimates are calculated in fiscal 
year 2010 constant dollars, and Naval Sea Systems Command adjusted 
them for inflation to fiscal year 2014 constant dollars using the 
appropriate Navy inflation factors in April 2014 for the purposes of 
this table. The seaframe estimate is at the 10 percent confidence 
level meaning there is a 90 percent chance that the costs will be 
higher than this estimate. 

[B] LCS mission-module life-cycle cost estimates are based on the 
purchase of 64 mission modules. The mission-module cost estimates are 
calculated in fiscal year 2010 constant dollars, and Naval Sea Systems 
Command adjusted them for inflation to fiscal year 2014 constant 
dollars using the appropriate Navy inflation factors in April 2014 for 
the purposes of this table. The mission-module estimate is at the 50 
percent confidence level. 

[C] The patrol costal class acquisition strategy was a 
nondevelopmental item. The United States bought the design 
specification from Vosper-Thornycraft, with Bollinger Shipyards 
(Lockport, Louisiana) designated as the U.S. Licensee. Therefore, 
there is no research and development cost for the patrol coastal class. 

[D] Other includes costs of disposal and, for LCS mission modules, the 
costs of technology replacement and upgrades. Naval Sea Systems 
Command noted that end-of-service-life disposition is variable; ships 
in some classes are sold to other countries; current market conditions 
support disposal on a "sales basis," yielding revenue for the United 
States. Therefore, no disposal costs are shown for the other surface 
ship classes. 

[E] We calculated the life-cycle costs on a per ship annualized basis 
to account for different ship numbers and expected ship service lives. 

[End of figure] 

Although the LCS has been identified by the Navy as a low-cost 
alternative to other surface ship classes, the available data indicate 
that the costs of the LCS may exceed or closely align with the costs 
of other multimission surface ships with larger crews. Without 
comprehensive life-cycle cost estimates, the Navy may be hindered in 
its ability to evaluate the merits of investing in LCS ships compared 
with other alternatives, conduct long-term budgetary planning, or 
determine the level of resources required to implement the program in 
accordance with the LCS concept of operations. 

In 2013, we recommended that the Navy collect actual operational data 
on the Independence variant and update operations and support cost 
estimates for both variants prior to contracting for additional LCS 
ships in 2016. Our work shows that the Navy still lacks operational 
data and that life-cycle cost estimates are still not comprehensive. 
We continue to believe that the Navy should have greater clarity on 
the performance of its operational concepts and greater confidence in 
its cost estimates before it enters into contracts for additional LCS 
ships. 

Agency Comments and Our Evaluation: 

In written comments on a draft of this report, the Department of 
Defense (DOD) noted it is concerned with the conclusions drawn from 
the analysis of life-cycle cost data across ship classes. DOD added 
that due to known gaps in existing ship class cost data, the available 
data do not allow for an accurate comparison of the life cycle costs 
among LCS and other existing surface ship classes. DOD's comments are 
summarized below and reprinted in their entirety in appendix V. DOD 
also provided technical comments, which we have incorporated as 
appropriate. 

In its comments, DOD noted differences in the scope of cost data 
across the ship classes and differences in life-cycle phases among the 
ship classes included in our life-cycle cost analysis. For example, 
DOD commented that there are gaps in the Navy's record keeping for 
operations and support costs, so that some potential costs may not be 
captured in the estimates the Navy provided us, such as system 
modernization, software maintenance, and program startup, which could 
understate the costs of the other surface ships. However, these data 
are the most comprehensive operations and support cost data that the 
Navy could provide us. As we noted in the report, the Navy also has 
used these data from other surface ship classes to build its LCS life-
cycle cost estimates. Moreover, we discussed in the report the known 
limitations to comparing the life-cycle costs of these ship classes, 
including that the estimates may not include the full costs of 
developing, modernizing, and sustaining software and combat systems 
installed on the ships, as well as past acquisition costs not aligning 
with what current production costs would be, and the ships being at 
different points in their service lives. Despite the known 
limitations, we believe our analysis uses the best available data to 
provide a reasonable comparison of the life-cycle costs across the 
ship classes. Consequently, we have made no revisions to the report, 
as suggested by DOD. 

Finally, DOD provided us with additional information to clarify that 
the Navy's mission-module program life-cycle cost estimate is at the 
50 percent confidence level. We verified this information and updated 
the report to include this confidence level. 

We are sending copies of this report to the appropriate congressional 
committees, the Secretary of Defense, and the Secretary of the Navy. 
In addition, the report is available at no charge on the GAO website 
at [hyperlink, http://www.gao.gov]. If you or your staff have any 
questions about this report, please contact me at (202) 512-3489 or at 
pendletonj@gao.gov. Contact points for our Offices of Congressional 
Relations and Public Affairs may be found on the last page of this 
report. Key contributors to this report are listed in appendix VI. 

Signed by: 

John H. Pendleton: 
Director: 
Defense Capabilities and Management: 

List of Committees: 

The Honorable Carl Levin: 
Chairman: 
The Honorable James Inhofe: 
Ranking Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Richard Durbin: 
Chairman: 
The Honorable Thad Cochran: 
Ranking Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Howard P. "Buck" McKeon: 
Chairman: 
The Honorable Adam Smith: 
Ranking Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable Rodney Frelinghuysen: 
Chairman: 
The Honorable Pete Visclosky: 
Ranking Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

[End of section] 

Appendix I: Scope and Methodology: 

To address the benefits and limitations of the operational data that 
have been collected on Littoral Combat Ships (LCS), we analyzed and 
compared the planned USS Freedom deployment schedule with the actual 
executed schedule. We reviewed documentation related to operational 
activities while deployed including execution orders, concepts of 
operations such as the 7th Fleet USS Freedom deployment concept of 
operations, and exercise briefings. We also analyzed operational data 
from the deployment, including readiness data and equipment casualty 
reports. We interviewed forward-deployed crew members in Singapore as 
well as Navy officials responsible for the ship's operational 
employment at 7th Fleet in Japan to discuss the successes and 
challenges of the deployment, including any limitations. Further, we 
analyzed the operational activities of USS Independence and 
interviewed Navy officials to determine what operational data has been 
collected on Independence variant ships. Finally, we reviewed and 
analyzed the LCS wholeness and warfighting concepts of operations to 
determine any additional LCS operational and warfighting concepts that 
still require demonstration.[Footnote 34] 

To assess the extent to which the Navy has evaluated risk in its 
operational support and sustainment concepts for the LCS in the areas 
of manning, training, maintenance, and logistics, we reviewed relevant 
data-collection and analysis plans and mid-point and final reports on 
the Freedom deployment to Singapore in 2013 from Commander Naval 
Surface Forces Pacific, 7th Fleet, and the Center for Naval Analyses, 
and we interviewed officials from organizations responsible for 
collecting and analyzing data from this deployment. We reviewed the 
LCS wholeness concept of operations, the life-cycle sustainment plans 
for the LCS, LCS manpower estimate report, LCS training plans, and 
various other Navy documents associated with LCS manning, training, 
maintenance, and logistics, and interviewed USS Freedom crews who 
participated in the 2013 deployment, to obtain their perspectives on 
the implementation of these concepts. We also reviewed the extent to 
which the Navy has analyzed the costs and benefits associated with the 
use of contractor flyaway maintenance teams. Finally, we discussed 
with LCS program office officials and other LCS stakeholders any 
actions that were being taken to analyze potential risks or mitigate 
them for future LCS deployments. 

To assess how LCS life-cycle cost estimates compare with those for 
other surface-ship classes, we modified a framework used in an earlier 
and similar comparison conducted by the Congressional Budget 
Office.[Footnote 35] To do this, we reviewed cost estimates in the 
current LCS Seaframe Program Life Cycle Cost Estimate (2011) and the 
LCS Mission Module Program Life Cycle Cost Estimate (2013), both 
prepared by the cost-estimating division of the Naval Sea Systems 
Command, and determined that these are the latest estimates available 
from the Navy. Although the Navy to date has not updated these life-
cycle cost estimates (which were estimated using fiscal year 2010 
dollars) to reflect changes in the program or the number of ships to 
be purchased, the Navy adjusted the estimates for inflation to fiscal 
year 2014 dollars. Using these data, we calculated an annual per ship 
life-cycle cost estimate for the combined LCS seaframes and mission 
modules to account for differences in the number of ships and mission 
modules and their respective expected service lives. We also obtained 
life-cycle cost data in fiscal year 2014 dollars from the Navy for 
five surface ships (patrol coastal ships, mine countermeasures ships, 
frigates, destroyers, and cruisers) and used these data to calculate 
an annual per-ship life-cycle cost estimate for each of these five 
surface ships so as to account for differences in the number of ships 
and their expected service lives. We then compared these data with the 
annual per ship life-cycle cost data we calculated for the LCS 
seaframes and mission modules. We analyzed and assessed these data and 
found them to be sufficiently reliable for the purposes of reporting 
the estimated life-cycle costs of these surface ships. The five non-
LCS surface ships we used for our comparison were selected because 
historical cost data were readily available and they all conduct at 
least one mission that the LCS is also expected to perform. Further, 
we interviewed Navy LCS program officials and cost estimating 
officials to determine the extent to which data from the USS Freedom 
deployment in 2013 may be used to refine future life-cycle cost 
estimates. 

We interviewed officials, and where appropriate obtained 
documentation, at the following locations: 

Department of the Navy: 

* Office of the Chief of Naval Operations: 

* Naval Sea Systems Command: 
- Program Executive Office Littoral Combat Ship, Fleet Introduction 
Office: 
- Cost-Estimating Division: 
- Program Executive Office, Ships: 

* U.S. Fleet Forces Command: 

* Naval Warfare Development Command: 

* Navy Manpower Analysis Center: 

* Southwest Regional Maintenance Center: 

* LCS Class Squadron: 
- Operations: 
- Training: 

* Commander, Naval Surface Force, U.S. Pacific Fleet: 

* Commander, Naval Air Force, U.S. Pacific Fleet: 

* Naval Supply Systems Command: 

* U.S. 7th Fleet: 
- Operations: 
- Logistics: 
- Warfare requirements: 
- Training and exercises: 

* U.S. Pacific Fleet: 

* Commander, Logistics Force Western Pacific: 
- Maintenance: 
- Logistics: 

* Commander, Destroyer Squadron Seven: 

* Navy Region Center, Singapore: 

* LCS Class Squadron Forward Liaison Element: 

Other Organizations: 

* Congressional Budget Office: 

* Center for Naval Analyses: 

We conducted group discussions with USS Freedom blue and gold crew 
officer and enlisted personnel who participated in the 2013 Singapore 
deployment. The discussions involved small-group meetings designed to 
gain more in-depth information about specific issues that cannot 
easily be obtained from single or serial interviews. Our design 
included multiple groups with varying characteristics but some 
homogeneity--such as rank and responsibility--within groups. For 
example, with few exceptions we met with officers separately from 
enlisted personnel and we met separately with personnel from each 
major ship department such as engineering, combat systems, and 
operations. Most groups involved three to five participants. 
Participants were selected based on their availability by USS Freedom 
commanding and executive officers in Singapore and the LCS Class 
Squadron in San Diego to ensure we had at least three members from 
each major ship function. Discussions were held in a semistructured 
manner using a broad list of discussion topics to encourage 
participants to share their thoughts and experiences related to the 
crew-swap experience, crew integration, maintenance, systems 
reliability, training, logistics support, quality of life, and overall 
satisfaction with the LCS experience. We assured participants that we 
would not link their names to their responses. 

To gain a broad perspective of crew experience during the USS Freedom 
deployment, we conducted 17 small-group sessions with USS Freedom 
officers and enlisted personnel across all ship departments. Table 4 
provides a summary of the composition of the group discussions held by 
GAO analysts in Singapore (during deployment) and in San Diego 
(postdeployment). All discussions were held aboard USS Freedom. 

Table 4: Summary of USS Freedom Crew Discussion Groups: 

USS Freedom department: Operations; 
Blue crew: During deployment; Postdeployment; 
Gold crew: Postdeployment. 

USS Freedom department: Engineering; 
Blue crew: During deployment; Postdeployment; 
Gold crew: Postdeployment. 

USS Freedom department: Combat systems; 
Blue crew: During deployment; Postdeployment; 
Gold crew: Postdeployment. 

USS Freedom department: Supply; 
Blue crew: Postdeployment; 
Gold crew: Postdeployment. 

USS Freedom department: Surface-warfare mission module; 
Blue crew: During deployment; Postdeployment; 
Gold crew: Postdeployment. 

USS Freedom department: Department heads; 
Blue crew: Postdeployment; 
Gold crew: [Empty]. 

USS Freedom department: Junior officers; 
Blue crew: Postdeployment; 
Gold crew: [Empty]. 

USS Freedom department: Commanding officer and executive officer; 
Blue crew: During deployment; Postdeployment; 
Gold crew: Postdeployment. 

Source: GAO. GAO-14-447. 

Note: For two discussion groups, we combined Freedom blue and gold 
crew supply department and mission-module personnel, respectively, for 
logistical purposes. 

[End of table] 

Our group discussions were not designed to (1) demonstrate the extent 
of a problem or to generalize results to the entire USS Freedom crew 
population or to other LCS variants, (2) develop a consensus to arrive 
at an agreed-upon plan or make decisions about what actions to take, 
or (3) provide statistically representative samples or reliable 
quantitative estimates. Instead, they were intended to generate in-
depth information about the discussion group participants' attitudes 
and reasons for their attitudes toward specific topics and to offer 
insights into the range of concerns and support for an issue. The 
generalizability of the information produced by our discussion groups 
is limited for several reasons. First, the information represents the 
responses of USS Freedom officers and enlisted personnel from the 17 
groups described above. Second, while the composition of the groups 
was designed to assure a distribution of Navy officers, enlisted 
personnel, seniority, and ship departments, the group participants 
were not probabilistically sampled. Third, participants were asked 
questions about their specific experiences on the Singapore 
deployment. The experiences of other USS Freedom personnel who did not 
participate in our group discussions may have varied. Because of these 
limitations, we did not rely entirely on group discussions, but rather 
used several different methodologies to corroborate and support our 
conclusions. 

We conducted this performance audit from September 2013 to July 2014 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: Littoral Combat Ship Plan of Action and Milestones, as of 
March 2014: 

In 2012, the Chief of Naval Operations received the results of four 
internal studies he requested to assess, among other things, the 
Littoral Combat Ship (LCS) across aspects of manning, training, and 
maintenance to assist in preparing the USS Freedom for deployment in 
March 2013. Two of the four studies were independent Navy studies--one 
conducted by the Board of Inspection and Survey (the Navy's ship-
inspection entity) and one conducted by the office of the Chief of 
Naval Operations. These two studies identified concerns with, among 
other things, LCS manning, training, and maintenance, and recommended 
steps to improve aspects of the program. The other two studies were 
two war game reports, which identified findings and made 
recommendations on LCS operations and sustainment. All four of these 
reports identified numerous operational support and sustainment 
issues, such as insufficient manning of ships leading to crew fatigue, 
inadequate training of crews, incomplete maintenance plans, and 
insufficient shore support, and culminated in about 170 
recommendations for improvement. 

The LCS Council developed a Plan of Action and Milestones document as 
directed by the Chief of Naval Operations to address the findings and 
recommendations from the four internal Navy reports. The Plan of 
Action and Milestones is organized around lines of operation (e.g., 
fleet introduction and sustainability, platform and capabilities 
evolution, and developing and aligning concept of operations and other 
documentation) and has over 1,000 action items and milestones--many 
directly addressing operational support and sustainment issues. Each 
of the lines of operation has subordinate action items, with a 
stakeholder assigned responsibility for each action item, and both a 
start date and expected finish date for the tasking. Table 5 below 
provides an update on the number of discrete (nonrecurring) subtasks 
that the Navy has completed as of March 2014. 

Table 5: Status of Littoral Combat Ship (LCS) Plan of Action and 
Milestones Action Items as of March 2014: 

Line of operation: Fleet introduction and sustainment; 
Lead stakeholder: Commander, Naval Surface Force, U.S. Pacific Fleet; 
Number of nonrecurring action items: 261; 
Scheduled completion dates for all action items: 9/2018; 
Nonrecurring action items completed by March 25, 2014: 171; 
Percentage of nonrecurring action items completed as of March 25, 
2014: 66%; 
Number of nonrecurring action items overdue: 9. 

Line of operation: Platform and capabilities evolution; 
Lead stakeholder: Office of the Chief of Naval Operations, Surface 
Warfare Directorate; 
Number of nonrecurring action items: 168; 
Scheduled completion dates for all action items: 9/2018; 
Nonrecurring action items completed by March 25, 2014: 91; 
Percentage of nonrecurring action items completed as of March 25, 
2014: 54%; 
Number of nonrecurring action items overdue: 5. 

Line of operation: Concept of operations, doctrine, and policy; 
Lead stakeholder: U.S. Fleet Forces Command; 
Number of nonrecurring action items: 70; 
Scheduled completion dates for all action items: 11/2017; 
Nonrecurring action items completed by March 25, 2014: 34; 
Percentage of nonrecurring action items completed as of March 25, 
2014: 49%; 
Number of nonrecurring action items overdue: 0. 

Source: GAO analysis of Department of Defense (DOD) data. GAO-14-447. 

[End of table] 

[End of section] 

Appendix III: Remaining Risks in Implementing Littoral Combat Ship 
Operational Support and Sustainment Concepts: 

The Navy is adjusting some operational support and sustainment 
concepts based on data collected and lessons learned during the USS 
Freedom deployment, but it has not yet addressed some risks that 
remain in executing and sustaining key manning, training, maintenance, 
and logistics concepts. 

Manning Risks and Navy Actions to Address Them: 

The Littoral Combat Ship (LCS) manning concept calls for a relatively 
small crew to operate the ship. The minimal crew size drives many of 
the other LCS concepts, since LCS sailors are expected to spend most 
of their time operating the ship rather than performing training, 
maintenance, or administrative functions. The last revision of the LCS 
wholeness concept of operations, approved in January 2013, called for 
a core crew size of 40 and mission-module crews of 15 to 19 sailors. 
[Footnote 36] The maximum number of core crew members allowed by LCS 
key performance parameters is 50.[Footnote 37] To add berthing spaces 
for additional crew members beyond 50, the ships would require 
significant design changes. A number of internal Navy reports issued 
in 2012 raised concerns about the adequacy of a 40-member core crew 
size, with crew fatigue and overwork as potential negative effects of 
this manning concept.[Footnote 38] In response to these concerns, the 
Navy added 10 sailors to the USS Freedom core crew deploying to 
Singapore as part of a pilot program. Navy leadership determined early 
in the deployment that these additional crew members were helpful in 
performing maintenance and watch-standing duties, and decided to 
permanently increase LCS core crews to 50 sailors. The Navy also added 
three ensigns to the Freedom crews prior to deployment, and intends on 
continuing and expanding this program to attach four ensigns to each 
LCS crew.[Footnote 39] In addition to the core and mission-module 
crews, contractors were also onboard during the course of the 
deployment to assist with equipment troubleshooting and repair. 

Despite the addition of 10 sailors to the core crew and contractor 
support, data collected from the Freedom's deployment show that 
sailors' sleep hours did not increase compared to the sleep hours 
reported in studies that examined LCS with 40-member crews; this 
suggests that the Navy has not fully addressed crew fatigue issues by 
increasing crew size.[Footnote 40] Specifically, the Center for Naval 
Analyses found that Freedom crews averaged about 6 hours of sleep per 
day compared to the Navy standard of 8 hours; some key departments, 
such as engineering and operations, averaged even fewer. While Navy 
officials told us that sailors do not realistically expect 8 hours of 
sleep while they are under way and may choose to have more down time 
rather than sleep, the LCS must adhere to Navy manpower standards, 
including those for crewmember fatigue levels and workload hours found 
in Navy standard workweeks. These standards are set to minimize 
potential adverse effects on morale, retention, and safety.[Footnote 
41] Crew members told us that their sleep hours decreased 
significantly during major equipment casualties, particularly those 
affecting the ship's diesel generators and other engineering systems. 
Navy officials said that follow-on ships have been outfitted with 
different systems that are supposed to be more reliable than those on 
Freedom, which should decrease the amount of corrective maintenance 
required, and thereby decrease crew fatigue on future deployments. 
However, as previously discussed, these systems have not been fully 
tested or operated on the LCS, and their reliability has yet to be 
proven by actual experience. 

Additionally, we found that core crews depended heavily on sailors 
from the surface warfare mission-module crew to perform watch 
standing, training drills, and engineering maintenance over the course 
of the deployment. This is a departure from what was envisioned in the 
concept of operations, and creates a situation that may not be 
sustainable under a different pace of operations or with a different 
mission module deployed. Officers and enlisted sailors from both core 
and mission-module crews told us that mission-module sailors were 
heavily leveraged to help complete core crew functions and that the 
crews were fully integrated. The crews added that the surface warfare 
mission module is uniquely qualified to help with core crew functions, 
since these sailors' billet structure--their mix of skills and 
expertise--completely aligns with that of the core crew. For example, 
there are engineers in the surface-warfare mission-module crew to 
operate and maintain the motors on the module's rigid-hull inflatable 
boats. Since these boats are not part of the antisubmarine warfare 
mission modules, there are no engineers in those crews. Sailors from 
the core crews' engineering department told us they depended on the 
qualified mission-module engineers to assist them and were at a loss 
as to how the engineering department would function effectively if 
deployed with the other mission modules. Figure 6 shows the extent of 
overlap between the core crew billets and the three mission-module 
crew billets. 

Figure 6: Extent of Overlap in Billets between Littoral Combat Ship 
(LCS) Core Crew and Mission-Module Crews: 

[Refer to PDF for image: illustration of overlapping spheres] 

Core crew Size: 50[A]: 

Surface warfare mission-module crew: 
Size: 19; 
Overlap: 19. 

Mine countermeasures mission-module crew: 
Size: 20; 
Overlap: 3.5. 

Antisubmarine warfare mission-module crew: 
Size: 15: 
Overlap: 1. 

Source: GAO analysis of Navy data. GAO-14-447. 

[A] The Navy has increased the core crew from 40 to 50, but it is 
still determining the billet structure for the 10 additional sailors. 

[End of figure] 

Core crews also relied heavily on support from the maintenance 
contractors embarked during the course of the deployment.[Footnote 42] 
Program officials and crew members cited these contractors' expertise 
with engineering systems and said they were of great assistance, 
essentially becoming additional highly experienced engineers always on 
watch in the engineering space. Engineering department crew members 
told us that the ship would not have gotten under way if not for these 
contractors. Program officials do not yet know whether contractors 
will always be embarked during future LCS deployments, but they said 
that the Navy utilizes contractors on other surface combatants when 
they are deployed and underway. Navy officials noted that USS Fort 
Worth, deploying in late 2014, will have two contractor personnel 
onboard. 

The Navy Manpower Analysis Center (NAVMAC) is in the ongoing process 
of analyzing the workload of USS Freedom's core and surface-warfare 
mission-module crews.[Footnote 43] The Navy expects the analysis to be 
complete by February 2015, and it will establish the manning 
requirement for Freedom variant core crews and surface-warfare mission-
module crews. NAVMAC's analysis produces a Ship Manpower Document, 
which establishes the required number and composition of personnel on 
the ship. The ship manpower document is developed by analyzing the 
ship's required operational capabilities, projected operational 
environment, and concept of operations as a starting point and 
building an independent assessment of the required number and 
composition of the crews, based on Navy standards and observations of 
operations. However, the NAVMAC analysis uses as its baseline LCS 
program concepts that delineate work between independent and 
separately operating core and mission-module crews, so it does not 
account for the significant leveraging of mission-module crew or for 
embarked contractors to perform core crew functions. Additionally, the 
analysis may not fully account for some additional work that crews are 
performing that is not included in the concept of operations, like 
training while under way. NAVMAC officials said that they collaborate 
with program offices and type commanders early in a ship's acquisition 
phases so that initial crew projections and manning concepts are 
feasible and realistic, but they said that they expect some changes to 
the LCS manning structure based on their initial observations. 

Manpower requirements for the other variant and mission modules have 
not yet been validated. A similar study to determine the requirements 
for Independence variant crews is scheduled to begin in 2016. Since 
the mine countermeasures and antisubmarine warfare mission modules are 
still being developed, validation of their crews has not been 
scheduled. Without validating the optimal crew size and billet 
structure for all LCS crews and without accounting for the full scope 
and distribution of work performed by sailors across all ship 
departments, the Navy risks that crew fatigue will exceed Navy 
standards and could negatively affect crew members' performance as 
well as morale, retention, safety, and ultimately the operational 
readiness of the ship class. 

Training Risks and Navy Actions to Address Them: 

The LCS training concept calls for sailors to report to a core or 
mission-module crew qualified to stand watch and carry out their other 
duties. Most LCS training is conducted off the ship in a classroom or 
simulator setting as operational demands do not allow sufficient time 
for training during operational periods. Crews are expected to be 
fully trained (qualified and certified) prior to deployment, and there 
is no training department embedded within the crew and no training 
required while under way.[Footnote 44] 

During discussions with Freedom crews, we found that not all sailors 
had completed training prior to deploying to Singapore. The 10 sailors 
added to the crew as part of the "plus-up" pilot program were 
identified in the months leading up to the March 2013 deployment date 
and did not undergo LCS-specific training or complete their 
qualifications prior to deploying. Some of these 10 additional crew 
members were junior sailors and told us they had limited sailing 
experience but were ultimately able to earn their qualifications over 
the course of the deployment. More-experienced core crew members who 
completed LCS training were in part responsible for instructing and 
training these additional 10 sailors, a collateral duty not accounted 
for within the standard LCS workday or envisioned in the LCS concept 
of operations. The Navy is in the process of reviewing and defining 
training needed for the 10 additional sailors, but since the training 
pipeline for LCS service can take about 2 years to complete, the Navy 
risks repeating this situation on upcoming deployments.[Footnote 45] 

While the Navy is reviewing training for the late-addition ensigns and 
the 10 "plus-up" sailors, it considers the training process to have 
been validated by the Freedom deployment, since no major training 
omissions or deficiencies were identified. However, we found that in 
addition to the 10 "plus-up" sailors not receiving all training prior 
to deployment, sailors from the original 40-person crews were training 
over the course of the deployment as well. The Center for Naval 
Analyses found that more than half of the qualification and instructed 
training that occurred during the deployment was for the original core 
crews, not the crew plus-ups. The Center for Naval Analyses added that 
sailors will train no matter what--at times out of necessity but also 
to maintain proficiency and in support of career development and well-
being--and that time must be made available for training during 
deployments. The Center for Naval Analyses calculated the average 
amount of training conducted by all crew members over the course of 
the deployment to be about an hour a day. However, this hour is 
unaccounted for in the Navy's expected LCS workday and detracts from 
the time a sailor could otherwise be resting or performing other 
collateral duties. The most common reasons for performing training, 
drills, and underway instruction while deployed were to cover training 
that was not provided prior to the deployment or to maintain 
proficiency. LCS program officials explained that much of this 
training was planned to be conducted during the deployment, and that 
underway training will likely continue until the new curriculum is 
fully implemented over the next several years. However, requiring LCS 
sailors to train while deployed was not envisioned in the LCS 
wholeness concept of operations, and it can exacerbate crew fatigue 
levels and negatively affect performance, morale, retention, safety, 
and the operational readiness of the ship. 

In addition to sailors not being fully trained prior to deployment, we 
heard concerns about the quality of the training the sailors received. 
The Navy is aware of this and is investing heavily in virtual reality-
based training simulations and a curriculum to prepare sailors for LCS 
service as envisioned in the concept of operations. Specifically, the 
Navy has budgeted for construction of another LCS training facility in 
Mayport, Florida, and awarded several contracts valued up to $300 
million to develop training simulations. While the final LCS training 
infrastructure is being developed, the program is training sailors 
through a combination of classroom instruction, vendor training 
(whereby contractors or original-equipment manufacturers train sailors 
on how to operate certain equipment), shore-based trainers, and very 
limited on-hull "school ship periods" to complete the qualification 
and certification process. Enlisted sailors from both core crews 
across ship departments expressed general dissatisfaction with the LCS 
training they received prior to the deployment. Some cited the 
obsolescence of vendor training and the limited utility of the 3-week 
LCS Academy in preparing them to serve on the LCS, and others stated 
that insufficient training left them ill-prepared to deal with 
contingencies on the deployment. Freedom officers said that it will 
take time for training to adapt to the needs of LCS sailors, but that 
it would make sense to cut the training that is not proving useful to 
LCS sailors in the short term until a more-tailored curriculum is 
developed. Navy training officials told us that they are aware of some 
of the quality issues with the current training and are attempting to 
make reasonable improvements that are cost-effective, but they pointed 
out that this interim training will be phased out over the next 
several years. While the program seeks to have useful and applicable 
training available for sailors progressing through the training 
pipeline now, the officials added that it would not be prudent to make 
major investments to overhaul temporary training. 

Navy officials told us that they are in the process of reviewing a 
revised LCS training plan that should be released in 2014. The 
training plan will lay out the schedule and process for replacing 
current training with the new simulations being developed. While this 
plan was not released early enough for inclusion in our review, 
earlier versions of LCS training plans did not include measures of 
effectiveness or training effectiveness-evaluation plans. In light of 
crew feedback on the inadequacy of current training, and unless the 
Navy acts on this feedback and builds effectiveness measures into its 
new training plan, it risks making significant investments to develop 
training that will not meet LCS sailors' training needs. Additionally, 
the Navy risks deploying LCS crews that are not properly qualified and 
certified, which in turn could negatively affect the crews' ability to 
operate and maintain the ship and perform warfighting duties as 
expected. 

Maintenance Risks and Navy Actions to Address Them: 

Because of the relatively small size of LCS crews, the maintenance 
concept calls for contractors to perform most preventative maintenance 
during regularly scheduled in-port periods. During the Singapore 
deployment, USS Freedom executed this concept, returning to port every 
25 days to undergo a 5-day preventative maintenance availability and 
every 120 days for a more-intensive 2-week intermediate maintenance 
availability. Flyaway maintenance teams of about 30 contractors were 
flown to Singapore for the 5-day maintenance periods, and about 60-70 
contractors for the 2-week periods. Because of the regular returns to 
Singapore for maintenance availabilities, the USS Freedom had a 
somewhat limited range in theater, and Navy officials noted that this 
rigid maintenance periodicity limited operational flexibility. Navy 
officials explained that this was a deliberate decision and that 
future deployments will have a longer, more-flexible interval for 
scheduling in-port maintenance. During the maintenance availabilities, 
there were some maintenance checks that could not be completed because 
the needed parts, tools, or equipment were not prepositioned by the 
contractor in time. The Navy attributes some of these issues to 
changing the maintenance schedule without enough lead time for the 
contractor to adequately respond. The Navy notes that contractor 
execution rates improved over the course of the deployment, and the 
Navy has established an improved maintenance scheduling process that 
should help prevent this problem on future deployments. 

Although contractors reportedly improved their positioning of materiel 
in time for the scheduled maintenance periods, Navy officials and 
Freedom crews said that lack of continuity in contractor personnel is 
an issue. They said that it is not unusual to see different 
contractors sent every month to perform scheduled maintenance. This 
presents a problem, since there is a learning curve associated with 
new maintainers coming onboard to execute their assigned maintenance 
checks. Freedom sailors told us that the burden of teaching new 
contractors how to complete their checks often falls on them, as does 
the task of repairing any equipment broken in the course of an 
inexperienced or unqualified contractor trying to maintain it. While 
Navy officials said that quality-assurance provisions will be included 
in the maintenance contracts expected to be awarded later in 2014, 
officials acknowledged that these provisions may not address this 
problem. 

Although contractors perform much of the preventative maintenance on 
LCS, the crews are still responsible for performing limited checks 
between scheduled maintenance periods. Sailors are largely responsible 
for performing more-frequent daily or weekly maintenance checks, and 
contractors for those that are required monthly or quarterly. During 
the deployment, the Center for Naval Analyses reported that Freedom 
sailors performed both scheduled and corrective maintenance actions 
each day (see figure 7). 

Figure 7: USS Freedom Sailor Conducting Engine Maintenance during 
Singapore Deployment: 

[Refer to PDF for image: photograph] 

USS Freedom crewmember performs maintenance on diesel engine. 

Source: Department of Defense (DOD). GAO-14-447. 

[End of figure] 

However, crew members told us that unexpected levels of maintenance 
activities impacted crew fatigue levels. Navy officials stated this 
maintenance effort reflects the materiel reliability issues that they 
say have been remedied for follow-on LCS ships. Yet crew members told 
us of several instances where some of their preventative maintenance 
responsibilities would be better suited to contractors and other 
examples of how some routine maintenance activities could be shifted 
from contractors to crew. For example, members of the combat systems 
department crew reported that approximately 90 percent of combat 
systems spaces are sensitive and therefore require the presence of LCS 
crew members in the workspace while contractors complete maintenance 
on department systems. Crew members must essentially "shadow" 
contractors as they perform such basic tasks as changing batteries and 
cleaning filters. Each maintenance activity has a tag that specifies 
the amount of time it should take to perform the check, and crew 
members voiced frustration over having to watch contractors take the 
full amount of time to perform the check even if they could have 
performed it in a fraction of the time specified on the tag. 

A major action item in the LCS Plan of Action and Milestones calls for 
developing an integrated and coordinated plan for the planning, 
executing, tracking, reporting, and quality assurance of planned 
maintenance between the ship's force, shore sailors, the LCS Squadron, 
and contractors on both variants. However, this broad action item, as 
well as another action item calling for the continuous review of 
maintenance requirements, extends out to December 2015 for completion. 
Program officials said that the current process for refining 
maintenance requirements--where changes in the frequency or 
responsibility for maintenance actions is reviewed and approved by the 
Navy's in-service engineering agents or through maintenance 
effectiveness reviews--is adequate, but added that the program is 
still working to develop a tool that would allow better management and 
coordination of maintenance activities.[Footnote 46] For example, 
greater visibility into the full scope of planned maintenance work 
performed by both crew and contractor personnel would allow program 
managers greater foresight into how and when certain parts should be 
repaired or replaced. 

The Navy is implementing a pilot condition-based maintenance program, 
whereby sensors installed on ship systems collect usage and 
reliability data, with the intention of conducting maintenance based 
on the condition of the equipment rather than according to a 
predetermined schedule. As more data are collected on equipment 
failure rates by condition-based maintenance sensors and as knowledge 
of LCS systems grows, the Navy intends for some maintenance 
requirements to be eventually phased out without increasing the risk 
of failure or sacrificing reliability. For example, there are a number 
of shut-off valves on the Freedom variant with a scheduled maintenance 
requirement to check them every month. These could be continuously 
monitored by sensors rather than being checked by a contractor or crew 
member on a monthly basis. The LCS program office has plans to expand 
the condition-based maintenance program on other LCS ships; for 
example, USS Fort Worth is being fitted with additional sensors in 
preparation for its late 2014 deployment. 

The maintenance concept for LCS may be changed in the future. The LCS 
program office requested that a business-case analysis be conducted to 
develop a sustainment strategy that will provide the most cost-
effective solution for providing LCS maintenance outside the 
continental United States. The analysis, completed in April 2013, 
compared five alternatives to the current contractor-based maintenance 
approach and recommended shifting responsibility from contractors to 
shore-based Navy personnel to achieve cost savings and other 
improvements. The Navy is exploring options to enact this 
recommendation under different scenarios and plans to do so as more 
LCSs are deployed to more forward operating stations. For example, the 
Navy plans to use reservists to conduct some LCS maintenance in lieu 
of contractors and intends to shift more maintenance responsibility to 
shore-based Navy personnel. However, program officials said that they 
may be somewhat limited in carrying out the recommendation by 
statutory maintenance requirements that govern how maintenance is 
performed abroad for ships, such as the LCS, that are homeported in 
the United States.[Footnote 47] The Navy is planning to award 5-year 
maintenance contracts later this year, and officials said there will 
be enough flexibility built into the contracts to allow 
experimentation with different maintenance alternatives. 

Logistics Risks and Navy Actions to Address Them: 

Shore-based support networks perform LCS logistics functions such as 
administrative tasks, emergent repairs, and management of ship support 
needs. Primary support is provided by the LCS Squadron in San Diego. 
For the USS Freedom deployment, several entities based in Singapore 
provided additional support, including the LCS Squadron Forward 
Liaison Element--12 LCS Squadron personnel sent to Singapore for the 
course of the deployment to provide local support and coordination on 
maintenance activities and ship reporting--and the Commander, 
Logistics Group, Western Pacific--7th Fleet's principal logistics 
group stationed in Singapore, which was responsible for emergent 
maintenance on USS Freedom.[Footnote 48] Navy officials noted several 
command and control-related challenges associated with this distance 
support concept during the Freedom deployment. For example, the ship's 
crew did not follow established distance support processes to address 
emergent maintenance needs, resulting in significant opportunity costs 
and duplication of effort. The LCS Squadron is revising its written 
instructions to resolve this issue for future deployments. However, 
some of the reporting duties that were supposed to be performed by 
shore support teams under original distance support concepts--such as 
reporting of equipment casualties--have now become crew 
responsibilities. Officials said the time difference between San Diego 
and Singapore was creating a lag in reporting and response times and 
cited this as a reason for shifting some reporting duties back to the 
crew. As mentioned earlier, adding additional responsibilities to an 
LCS sailor's already-full workday may exacerbate crew fatigue and may 
require reallocation of workloads or other revisions to the LCS 
concept of operations. 

We found several additional limitations of the LCS support 
infrastructure over the course of the deployment. For example, the 
Navy noted that existing Internet resources ashore were insufficient 
for managing maintenance, and the Navy continues to explore options 
with the host nation for improving connectivity. Another issue still 
being resolved is finding adequate providers for facilities 
maintenance and ship cleaning, as the services contracted for 
Freedom's deployment were not up to sailors' expectations. The Navy 
would also prefer to have LCS hulls cleaned while deployed and is in 
the process of determining a cost-effective way to execute this task 
in compliance with statutory maintenance requirements.[Footnote 49] 
Finally, USS Freedom required nearly three times as many underway 
refuelings as were scheduled.[Footnote 50] Navy logisticians in 
Singapore scheduled seven at-sea refuelings for the deployment but 18 
were eventually required. LCS program officials say that this was a 
scheduling error rather than an indication of higher-than-expected 
fuel burn rates. As the Navy gains more operational experience in an 
overseas environment, it expects to learn additional lessons about 
more-accurately scheduling LCS refuelings. 

Additionally, Navy officials acknowledged that the logistics footprint 
needed to support four LCSs in Singapore by 2017 must be defined and 
expanded over the next several years. The Navy is in the process of 
determining the final logistics requirements to support additional 
ships at Singapore and other forward operating stations; these efforts 
are scheduled to be completed by April 2014.[Footnote 51] Currently, 
there is only a temporary tension-fabric structure in Singapore to 
house spare parts, tools, and working space for maintenance 
contractors, but this temporary structure does not have adequate space 
to house support elements for four LCS of both variants, according to 
Navy officials. Permanent support facilities have not been built in 
Singapore or other potential forward operating stations, and the lack 
of operational data on the Independence variant limits the Navy's 
ability to accurately plan for logistics support when both variants 
deploy. Without a clear understanding of the logistics needs of both 
variants, the Navy risks being underprepared to support both while 
forward deployed. 

[End of section] 

Appendix IV: Overview of Navy Surface Ships Used in Life-Cycle Cost 
Comparison: 

Cruisers (CG): 
Large guided-missile combat vessel with multiple target response 
capability; 
Length: 567 feet; 
Displacement: 9,754 metric tons; 
Speed: 30 plus knots; 
Armament: Mark 41 vertical launching system Standard Missile; Vertical 
Launch Anti-Submarine Rocket Missile; Tomahawk Cruise Missile; six 
Mark-46 torpedoes (from two triple mounts); two Mark 45 5-inch/54 
caliber lightweight guns; two Phalanx close-in-weapons systems; two 
helicopters; 
Crew: 29 officers, 297 enlisted. 

Destroyers (DDG): 
Large guided-missile combat vessel with multiple mission offensive and 
defensive capabilities; 
Length: Flight IIA: 509 feet; 
Displacement: 9,648 metric tons; 
Speed: 30 plus knots; 
Armament: Standard Missile; Vertical Launch Anti-Submarine Rocket 
missiles; Tomahawk Cruise Missile; six Mark-46 torpedoes (from two 
triple mounts); Close In Weapon System, 5” Mark 45 Gun, Evolved Sea 
Sparrow Missile; two helicopters; 
Crew: 24 officers, 279 enlisted. 

Frigates (FFG): 
Fulfill a protection of shipping mission as anti-submarine warfare 
combatants for amphibious expeditionary forces, underway replenishment 
groups, and merchant convoys; 
Length: 445 feet; 
Displacement: 4,165-4,369 metric tons; 
Speed: 29 plus knots; 
Armament: Six Mark-46 torpedoes (from two triple mounts); one 76 mm (3-
inch)/62 caliber Mark 75 rapid fire gun; one Phalanx close-in-weapons 
system; one or two helicopters; 
Crew: 17 officers, 198 enlisted. 

Mine Countermeasures Ships (MCM): 
Mine sweepers/hunter-killers capable of finding, classifying and 
destroying moored and bottom mines; 
Length: 224 feet; 
Displacement: 1,333 metric tons; 
Speed: 14 knots; 
Armament: Mine neutralization system; four .50 caliber machine guns; 
Crew: 9 officers, 83 enlisted. 

Patrol Coastal Ships (PC): 
Perform coastal patrol and interdiction surveillance, including 
maritime homeland security; 
Length: 179 feet; 
Displacement: 387 metric tons; 
Speed: 35 knots; 
Armament: Two Mark 38 25mm machine guns; four .50 caliber machine 
guns; two Mark 19 40mm automatic grenade launchers; two M-60 machine 
guns; 
Crew: 4 officers, 25 enlisted. 

Littoral Combat Ship (Freedom Variant): 
Designed to defeat asymmetric antiaccess threats such as mines, quiet 
diesel submarines, and fast surface craft; 
Length: 387 feet; 
Displacement: 3,400 metric tons; 
Speed: 40 plus knots; 
Armament: See Littoral Combat Ship mission modules; 
Crew: 50 plus mission package crew. 

Littoral Combat Ship (Independence Variant): 
Designed to defeat asymmetric anti-access threats such as mines, quiet 
diesel submarines and fast surface craft; 
Length: 418 feet; 
Displacement: 3,100 metric tons; 
Speed: 40 plus knots; 
Armament: See Littoral Combat Ship mission modules; 
Crew: 50 plus mission package crew. 

Littoral Combat Ship Mission Modules: 
Each mission module, when combined with the mission-module crew and an 
aviation detachment, provides warfighting capabilities for one of the 
three focused mission areas; 
Surface warfare: Maritime security and destruction of small-boat 
threats; 
Mine countermeasures: Detection and neutralization of mine threats; 
Antisubmarine warfare: Detect, classify, localize, and destroy enemy 
submarines; 
Crew: 15-20. 

Source: Department of Defense (DOD). GAO-14-447. 

[End of section] 

Appendix V: Comments from the Department of Defense: 

Note: The Department of Defense provided comments and a security 
review on a draft of this report. DOD deemed certain technical 
information to be sensitive but unclassified, which GAO omitted from 
the report to allow for public release. 

The Assistant Secretary of Defense: 
Acquisition: 
3015 Defense Pentagon: 
Washington, DC 20301-3015: 

June 5, 2014: 

Mr. John Pendleton: 
Director: 
Defense Capabilities and Management: 
U.S. Government Accountability Office: 
441 G Street NW: 
Washington, DC 20548: 

Dear Mr. Pendleton: 

This is the Department of Defense (DoD) response to the GAO Draft 
Report, GAO-14-447SU, "Littoral Combat Ship: Deployment of USS Freedom 
Revealed Risks in Implementing Operational Concepts and Uncertain 
Costs," dated April 17, 2014 (GAO Code 351865). The Department 
acknowledges receipt of the draft report. 

The Department is concerned with the conclusions drawn from the 
analysis of life cycle cost data across ship classes contained in the 
draft report in statements such as the following on page 23 of the 
draft report: 

"... we found that the per-ship life-cycle cost per-year for the LCS 
program are nearing or may exceed those for other surface ships, 
including guided missile frigates and multimission destroyers." 

The Department recommends that you modify your conclusions by saying 
that the available data does not allow for an accurate comparison of 
the life cycle costs among LCS and other existing surface ship classes 
due to known gaps in existing ship class cost data. The data gaps 
detailed below should also be identified clearly in the final report 
and associated with Figure 5 at page 25 and on the Highlights page at 
the beginning of the draft report. 

Differences in the scope of cost data across the ship classes: 

The cost of combat system development, software maintenance, and ship 
modernization is not fully included in the legacy platform (i.e., non-
LCS) historical costs. For example, Aegis combat system development,
procurement, modernization baseline upgrade, sustainment and training 
costs should be applied to the DDG 51 and CG 47 costs. The Navy funds 
DDG 51 and CG 47 ship and combat system midlife modernization efforts 
separately from the ongoing operation and sustainment of those 
ship classes. These efforts are not fully captured in the Visibility 
and Management of Operating and Support Cost (V AMOSC) database so 
gaps exist in reported costs for areas such as system modernization 
and software maintenance. Further, Navy systems that are purchased 
through Participating Acquisition Resource Managers would not 
necessarily be included in a legacy ship's historical costs, whereas 
the LCS data includes all of those costs. 

Differences in life cycle phases among the ship classes: 

The costs from FFG 7 and CG 47 Classes only include the later stages 
in their service lives. This reflects the savings achieved through 
system maturity and experience in sustainment, procurement, and 
operations that have not yet been experienced by the LCS program. 
Likewise, many of the first of class costs for the DDG 51 program 
would have been captured in Flight I actuals and thus are not included 
in the Flight IIA costs, as they are in LCS. Additionally, many of the 
costs associated with DDG 51 program startup to establish land-based 
development, integration, and test sites; shore support; training 
simulators; indirect support; and military construction are not 
captured by Flight IIA costs, but program startup is included as part 
of the LCS costs. Disposal costs are not captured consistently across 
the platforms (seaframe and mission modules includes disposal; other 
surface ships do not) causing LCS costs to be skewed higher. 

Confidence Level of the Cost Estimate of the LCS Mission Modules: 

The draft report states that the Navy did not have a confidence level 
for its formal Program Life Cycle Cost Estimate although the Navy's 
submission indicated it used a 50% confidence level. 

The Department appreciates the opportunity to comment on the draft 
report. For further questions concerning this report, please contact 
Mr. James MacStravic, Deputy Assistant Secretary of Defense, Tactical 
Warfare Systems, 703-697-9387. 

Sincerely, 

Signed by: 

Katrina McFarland: 

[End of section] 

Appendix VI: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

John H. Pendleton, (202) 512-3489 or pendletonj@gao.gov: 

Staff Acknowledgments: 

In addition to the contact named above, Suzanne Wren, Assistant 
Director; Steven Banovac; Kristine Hassinger; Joanne Landesman; Carol 
Petersen; Michael Silver; Amie Steele; Sabrina Streagle; Grant Sutton; 
and Chris Watson made key contributions to this report. 

[End of section] 

Related GAO Products: 

Navy Shipbuilding: Significant Investments in the Littoral Combat Ship 
Continue Amid Substantial Unknowns about Capabilities, Use, and Cost. 
[hyperlink, http://www.gao.gov/products/GAO-13-738T]. Washington, 
D.C.: July 25, 2013. 

Navy Shipbuilding: Significant Investments in the Littoral Combat Ship 
Continue Amid Substantial Unknowns about Capabilities, Use, and Cost. 
[hyperlink, http://www.gao.gov/products/GAO-13-530]. Washington, D.C.: 
July 22, 2013. 

Defense Acquisitions: Realizing Savings under Different Littoral 
Combat Ship Acquisition Strategies Depends on Successful Management of 
Risks. [hyperlink, http://www.gao.gov/products/GAO-11-277T]. 
Washington, D.C.: December 14, 2010. 

Navy's Proposed Dual Award Acquisition Strategy for the Littoral 
Combat Ship Program. [hyperlink, 
http://www.gao.gov/products/GAO-11-249R]. Washington, D.C.: December 
8, 2010. 

Defense Acquisitions: Navy's Ability to Overcome Challenges Facing the 
Littoral Combat Ship Will Determine Eventual Capabilities. [hyperlink, 
http://www.gao.gov/products/GAO-10-523]. Washington, D.C.: August 31, 
2010. 

Littoral Combat Ship: Actions Needed to Improve Operating Cost 
Estimates and Mitigate Risks in Implementing New Concepts. [hyperlink, 
http://www.gao.gov/products/GAO-10-257]. Washington, D.C.: February 2, 
2010. 

Defense Acquisitions: Realistic Business Cases Needed to Execute Navy 
Shipbuilding Programs. [hyperlink, 
http://www.gao.gov/products/GAO-07-943T]. Washington, D.C.: July 24, 
2007. 

Defense Acquisitions: Plans Need to Allow Enough Time to Demonstrate 
Capability of First Littoral Combat Ships. [hyperlink, 
http://www.gao.gov/products/GAO-05-255]. Washington, D.C.: March 1, 
2005. 

[End of section] 

Footnotes: 

[1] GAO, Navy Shipbuilding: Significant Investments in the Littoral 
Combat Ship Continue Amid Substantial Unknowns about Capabilities, 
Use, and Cost, [hyperlink, http://www.gao.gov/products/GAO-13-530] 
(Washington, D.C.: July 22, 2013). 

[2] This report refers to LCS 1 and the other odd-numbered seaframes 
as the Freedom variant, and LCS 2 and the other even-numbered 
seaframes as the Independence variant. 

[3] The Navy had planned to contract for up to 28 additional 
seaframes, but on February 24, 2014, the Secretary of Defense 
announced that as part of its fiscal year 2015 budget proposal the 
Navy would contract for no more than 32 LCS--instead of the 52 ships 
previously planned--until the Navy evaluates potential courses of 
action, including the current LCS program and provides a report to the 
Secretary of Defense, which is due by July 31, 2014. The Navy has not 
specified which variants it will procure in the future. 

[4] See GAO, Littoral Combat Ship: Actions Needed to Improve Operating 
Cost Estimates and Mitigate Risks in Implementing New Concepts, 
[hyperlink, http://www.gao.gov/products/GAO-10-257] (Washington, D.C.: 
Feb. 2, 2010). 

[5] For the purposes of this review, operational support and 
sustainment for LCS includes manning, training, maintenance, and 
logistics--both onboard and shore-based support. 

[6] H.R. Rep. No. 113-102, at 115-116 (2013). We provided a 
preliminary briefing on February 26, 2014. 

[7] In 2010, the Congressional Budget Office completed a preliminary 
study of LCS life-cycle costs and compared them to the costs of other 
ship classes in the surface fleet. This analysis included Navy data on 
operations and support costs for mine countermeasures ships, frigates, 
destroyers, and cruisers and other life-cycle costs components, and 
compared those costs to projections for each LCS seaframe variant--
excluding mission modules. We modified the Congressional Budget 
Office's analytic framework to conduct further analysis using 
additional and updated data for the LCS, its mission modules, and 
other surface-ship classes. See Congressional Budget Office, Life-
Cycle Costs of Selected Navy Ships (Apr. 28, 2010). 

[8] Details related to unique LCS operational support and sustainment 
concepts are found in the U.S. Fleet Forces Command, LCS Platform 
Wholeness Concept of Operations Revision D (Jan. 9, 2013), the Navy's 
high-level document summarizing manning, training, equipping, and 
sustaining concepts for LCS seaframes and mission packages. 

[9] GAO, Force Structure: Ship Rotational Crewing Initiatives Would 
Benefit from Top-Level Leadership, Navy-wide Guidance, Comprehensive 
Analysis, and Improved Lessons-Learned Sharing, [hyperlink, 
http://www.gao.gov/products/GAO-08-418] (Washington: D.C.: May 29, 
2008). The Navy uses rotational crewing on mine countermeasures ships 
and patrol coastal ships. 

[10] The Navy had planned to contract for up to 28 additional 
seaframes, but on February 24, 2014, the Secretary of Defense 
announced that as part of its fiscal year 2015 budget proposal the 
Navy would contract for no more than 32 LCS--instead of the 52 ships 
previously planned--(a further reduction from the original 55-ship 
plan), until the Navy evaluates potential courses of action, including 
the current LCS program and provides a report to the Secretary of 
Defense, which is due by July 31, 2014. 

[11] In March 2013, the Chief of Naval Operations expanded the duties 
of the council to include responsibilities for the Joint High Speed 
Vessel and added a Rear Admiral, Commander of the Military Sealift 
Command, to the renamed Littoral Combat Ship and Joint High Speed 
Vessel Council. See U.S. Navy, Littoral Combat Ship and Joint High 
Speed Vessel Council Charter (March 2013). 

[12] There are three mission packages (surface warfare, mine 
countermeasures, antisubmarine warfare), and nine different capability 
increments within these three packages. All carry different crews and 
equipment and operate differently from one another. Increment 2 of the 
surface-warfare mission package does not include the surface-to-
surface missile that is planned for increments 3 and 4. 

[13] U.S. Navy 7th Fleet, a Navy component command, had operational 
control of USS Freedom across the 7th Fleet area of responsibility 
which covers more than 48 million square miles and spans from west of 
Hawaii to the western coast of India. 

[14] The USS Freedom blue and gold crews executed a crew turnover in 
August 2013 in the port of Sembawang in Singapore. 

[15] Condition-based maintenance is the process of scheduling 
maintenance based on actual need through analysis of data from the 
seaframe's equipment. The data is obtained in real time or near-real 
time from sensors embedded in seaframe components or systems, and then 
monitored and analyzed ashore. 

[16] Specific equipment failures resulting in lost mission days are 
sensitive information. There is disagreement within the Navy on how 
many mission days were lost due to mechanical failures. The LCS fleet 
introduction program office provided us with documentation showing 
that 55 days were lost; other Navy offices stated that 28 days were 
lost, but they did not provide documentation for how this number was 
determined. 

[17] Director, Operational Test and Evaluation, Fiscal Year 2013 
Annual Report (January 2014). 

[18] Director, Operational Test and Evaluation, Fiscal Year 2013 
Annual Report. 

[19] During this period, USS Independence underwent major safety-
related modifications that required lengthy time either in port or in 
dry dock. LCS program officials said that in 2011, the USS 
Independence spent 5 months under way completing mine countermeasures 
mission package testing, but they acknowledged that recent operational 
data are limited. They added that since the ships have been delivered, 
USS Freedom has spent 29 percent of its time under way, while USS 
Independence has spent 26 percent of its time under way. 

[20] Operational plans refer to any plan for the conduct of military 
operations prepared in response to actual and potential contingencies. 

[21] The Navy is pursuing an evolutionary acquisition strategy for the 
mission packages. This means that it plans to deliver improving levels 
of capability over multiple increments (four for surface warfare, four 
for mine countermeasures, and one for antisubmarine warfare). The 
Navy's threshold performance requirements as currently defined in LCS 
requirements documentation will be met only when the final increment 
of each package is completed, and not by each individual increment. 
See [hyperlink, http://www.gao.gov/products/GAO-13-530]. 

[22] GAO, Standards for Internal Control in the Federal Government, 
[hyperlink, http://www.gao.gov/products/GAO/AIMD-00-21.3.1] 
(Washington, D.C.: November 1999). 

[23] [hyperlink, http://www.gao.gov/products/GAO-10-257]. 

[24] We recently reported that more-comprehensive and more-complete 
cost data can help the Department of Defense improve the cost-
effectiveness of sustaining weapons systems. GAO, 2014 Annual Report: 
Additional Opportunities to Reduce Fragmentation, Overlap, and 
Duplication and Achieve Other Financial Benefits, [hyperlink, 
http://www.gao.gov/products/GAO-14-343SP] (Washington, D.C.: Apr. 8, 
2014). 

[25] According to the Navy, the exact deployment date of the 
Independence variant is classified, but it is notionally planned to 
deploy before 2017. Navy officials said that an extended mine 
countermeasures mission-package test period is planned for the USS 
Independence in 2014 in the Gulf of Mexico near Florida, which will 
likely allow the Navy to update some cost data associated with that 
variant. 

[26] See LCS Seaframe Program Life Cycle Cost Estimate (2011) and the 
LCS Mission Module Program Life Cycle Cost Estimate (2013). A Program 
Life Cycle Cost Estimate document provides a detailed explanation of 
the program's cost components including research, development, test, 
and evaluation cost, along with operations and support costs, such as 
maintenance and system improvement, among others. Aircraft accompany 
LCS and commonly accompany other Navy surface vessels, but their 
operations and sustainment are funded through the Naval Air Systems 
Command rather than being included in the ships' operations and 
support costs. 

[27] The confidence level is an output of the statistical risk 
analysis of the parameters and assumptions used to build the point 
estimate. Cost-estimating experts agree that a confidence level of 
between 55 percent and 65 percent is desired to set a program's 
budget, recognizing that the tendency is for costs to overrun in a 
program's early phases. 

[28] The LCS Seaframe Program Life Cycle Cost Estimate (2011) provided 
estimates for all levels of maintenance--organizational, intermediate, 
and depot--for both variants. 

[29] Operations and support costs traditionally account for about 70 
percent of the total cost over a system's lifetime. 

[30] The Navy increased the core crew size from 40 to 50 for USS 
Freedom's deployment to Singapore, and this number is now the class 
standard across both variants. Additionally, Freedom deployed with 
three ensigns as part of a pilot program seeking to increase the 
junior officer ranks within the LCS community, and officials said the 
Navy intends on continuing and expanding this program to attach four 
ensigns to each LCS crew. 

[31] While the Navy told us that material selection changes may 
increase the reliability of select systems and therefore decrease 
short-term emergent repair costs, the effects of these changes on long-
term operations and support costs is unknown. 

[32] In 2010, the Congressional Budget Office completed a similar and 
preliminary study of LCS life-cycle costs and compared them to the 
costs of other ship classes in the surface fleet. This analysis 
provided us with a framework by which to conduct further analysis 
using additional and updated data for the LCS, its mission modules, 
and other surface ship classes. For additional information see 
Congressional Budget Office, Life-Cycle Costs of Selected Navy Ships. 

[33] See GAO, Military Capabilities: Navy Should Reevaluate Its Plan 
to Decommission the USS Port Royal, [hyperlink, 
http://www.gao.gov/products/GAO-14-336] (Washington, D.C.: Apr. 8, 
2014). 

[34] U.S. Fleet Forces Command, LCS Platform Wholeness Concept of 
Operations Revision D (Jan. 9, 2013) and classified warfighting 
concept of operations. 

[35] In 2010, the Congressional Budget Office completed a preliminary 
study of LCS life-cycle costs and compared them to the costs of other 
ship classes in the surface fleet. This analysis included Navy data on 
operations and support costs for mine countermeasures ships, frigates, 
destroyers, and cruisers and other life-cycle costs components, and 
compared those costs to projections for each LCS seaframe variant--
excluding mission modules. The analysis provided an early glimpse into 
the seaframe costs of the LCS program and provides a useful framework 
by which to conduct further analysis using additional and updated data 
for the LCS, its mission modules, and other surface-ship classes. See 
Congressional Budget Office, Life-Cycle Costs of Selected Navy Ships 
(Apr. 28, 2010). 

[36] The core crew operates the LCS seaframe, with sailors organized 
into four departments: combat systems, engineering, operations, and 
supply, overseen by the ship's commanding and executive officers. A 
separate crew operates the mission module deployed with the seaframe, 
in addition to the aviation detachment crew responsible for the MH-60 
helicopter and vertical takeoff unmanned aerial vehicles that are part 
of each LCS mission package. 

[37] Key performance parameters are system characteristics that are 
considered critical or essential to the development of an effective 
military capability. Failure of a system to meet a validated key 
performance parameter threshold brings the military utility of the 
associated systems into question, and may result in a reevaluation of 
the program or modification to production increments. The Navy 
established these LCS manning parameters in 2003. 

[38] Two of the studies were independent Navy studies--one conducted 
by the Board of Inspection and Survey (the Navy's ship-inspection 
entity) and one conducted by the office of the Chief of Naval 
Operations. These two studies identified concerns with, among other 
things, LCS manning, training, and maintenance, and recommended steps 
to improve aspects of the program. Two other studies were war game 
reports, which identified findings and made recommendations on LCS 
operations and sustainment. All four of these reports identified 
numerous operational support and sustainment issues, such as 
insufficient manning of ships leading to crew fatigue, inadequate 
training of crews, incomplete maintenance plans, and insufficient 
shore support, and culminated in about 170 recommendations for 
improvement. In September 2013, we issued a For Official Use Only 
report that assessed the extent to which the Navy addressed these 
recommendations. 

[39] Ensign is the junior commissioned officer rank in the United 
States Navy. Navy officials explained that the ensign program will be 
helpful in building an officer corps for this relatively new ship 
class. 

[40] The Center for Naval Analyses compared both crews' sleep hours 
during the deployment against those collected during a 2010 sleep 
study and Rough Water Trials conducted in 2011. 

[41] Office of the Chief of Naval Operations Instruction 1000.16K 
Change Transmittal 1, Navy Total Force Manpower Policies Procedures, 
Encl. 1, App. C., paras. 1.b. and 4.a. (Oct. 4, 2011). 

[42] As many as six contractors were aboard USS Freedom during its 
transit from San Diego to Singapore with a minimum of two contractors 
onboard at any given time. 

[43] NAVMAC leads the manpower requirements-determination process, 
which identifies multiyear manpower requirements to support the 
budgeting process. 

[44] Train-to-qualify is the process of training an individual in an 
off-ship environment in the knowledge, skills, and abilities required 
to competently perform tasks associated with a designated ship-board 
watch station or position. Train-to-certify is the advanced training 
for a team once qualification has been achieved by individuals. It is 
achieved through demonstrated proficiency in operating equipment and 
completing scenarios as a team, and also relies heavily on shore-based 
training. 

[45] In February 2010, we reported that the Navy faced risks in its 
ability to identify and assign LCS personnel given the time needed to 
achieve the extensive training required. See GAO, Littoral Combat 
Ship: Actions Needed to Improve Operating Cost Estimates and Mitigate 
Risks in Implementing New Concepts, [hyperlink, 
http://www.gao.gov/products/GAO-10-257] (Washington, D.C.: Feb. 2, 
2010). 

[46] Maintenance requirements are established and managed by the 
Navy's in-service engineering agents who must approve shifts in the 
responsibility of a maintenance check from a contractor to a crew 
member or vice versa. Maintenance checks are permitted to be conducted 
more frequently than what the requirement calls for, but in-service 
engineering agent approval is needed to extend the periodicity of a 
check (e.g., changing a required check from being performed monthly to 
quarterly). 

[47] Section 7310 of title 10 U.S.C. states that a naval vessel 
homeported in the United States or Guam may not be overhauled, 
repaired, or maintained in a shipyard outside the United States or 
Guam, other than in the case of voyage repairs. 

[48] Commander, Logistics Group Western Pacific, principal logistics 
agent for the 7th Fleet, located in Singapore, is responsible for 
emergent maintenance and replenishments for ships throughout 7th Fleet 
including USS Freedom during its deployment. Emergent maintenance is 
unplanned need-based maintenance, for example, repairs required by an 
equipment casualty or malfunction. Emergent maintenance is defined in 
Office of the Chief of Naval Operations Inst. 4700.7L, Encl. 8, para. 
9 (May 25, 2010). 

[49] Section 7310 of title 10 U.S.C. states that a naval vessel 
homeported in the United States or Guam may not be overhauled, 
repaired, or maintained in a shipyard outside the United States or 
Guam, other than in the case of voyage repairs. 

[50] USS Freedom has the least fuel capacity of existing LCS ships. 
Navy officials noted that Independence variant ships have at least 50 
percent more fuel capacity and additional fuel capacity has been added 
to follow-on Freedom variant ships. 

[51] See LCS Plan of Action and Milestones. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the 
performance and accountability of the federal government for the 
American people. GAO examines the use of public funds; evaluates 
federal programs and policies; and provides analyses, recommendations, 
and other assistance to help Congress make informed oversight, policy, 
and funding decisions. GAO's commitment to good government is 
reflected in its core values of accountability, integrity, and 
reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's website [hyperlink, http://www.gao.gov]. Each 
weekday afternoon, GAO posts on its website newly released reports, 
testimony, and correspondence. To have GAO e-mail you a list of newly 
posted products, go to [hyperlink, http://www.gao.gov] and select 
"E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO's actual cost of 
production and distribution and depends on the number of pages in the 
publication and whether the publication is printed in color or black 
and white. Pricing and ordering information is posted on GAO's 
website, [hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or 
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card, 
MasterCard, Visa, check, or money order. Call for additional 
information. 

Connect with GAO: 

Connect with GAO on facebook, flickr, twitter, and YouTube.
Subscribe to our RSS Feeds or E mail Updates. Listen to our Podcasts.
Visit GAO on the web at [hyperlink, http://www.gao.gov]. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 
Website: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]; 
E-mail: fraudnet@gao.gov; 
Automated answering system: (800) 424-5454 or (202) 512-7470. 

Congressional Relations: 

Katherine Siggerud, Managing Director, siggerudk@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, DC 20548. 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, DC 20548. 

[End of document]