This is the accessible text file for GAO report number GAO-13-690T 
entitled 'F-35 Joint Strike Fighter: Restructuring Has Improved the 
Program, but Affordability Challenges and Other Risks Remain' which 
was released on June 19, 2013. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

[On December 2, 2013, this testimony document was revised to correct 
the page numbering. The content was not revised] 

United States Government Accountability Office: 
GAO: 

Testimony: 

Before the Subcommittee on Defense, Committee on Appropriations, U.S. 
Senate: 

For Release on Delivery 
Expected at 10:00 a.m. EDT: 
Wednesday, June 19, 2013: 

F-35 Joint Strike Fighter: 

Restructuring Has Improved the Program, but Affordability Challenges 
and Other Risks Remain: 

Statement of Michael J. Sullivan, Director: 
Acquisition and Sourcing Management: 

GAO-13-690T: 

GAO Highlights: 

Highlights of GAO-13-690T, a testimony before the Subcommittee on 
Defense, Committee on Appropriations, U.S. Senate. 

Why GAO Did This Study: 

Fighter, is DOD’s most costly and ambitious aircraft acquisition. The 
program is developing and fielding three aircraft variants for the Air 
Force, Navy, Marine Corps, and eight international partners. The F-35 
is critical to long-term recapitalization plans as it is intended to 
replace hundreds of existing aircraft. This will require a long-term 
sustained funding commitment. Total U.S. investment is nearing $400 
billion to develop and procure 2,457 aircraft through 2037. Fifty-two 
aircraft have been delivered through 2012. The F-35 program has been 
extensively restructured over the last 3 years to address prior cost, 
schedule, and performance problems. DOD approved a new acquisition 
program baseline in March 2012. 

This testimony is largely based on GAO’s recently released report, 
[hyperlink, http://www.gao.gov/products/GAO-13-309]. This testimony 
discusses (1) progress the F-35 program made in 2012, and (2) major 
risks that program faces going forward. GAO’s work included analyses 
of a wide range of program documents and interviews with defense and 
contractor officials. 

What GAO Found: 

The new F-35 acquisition baseline reflects positive restructuring 
actions taken by the Department of Defense (DOD) since 2010, including 
more time and funding for development and deferred procurement of more 
than 400 aircraft to future years. Overall, the program progressed on 
several fronts during 2012 to further improve the current outlook. The 
program achieved 7 of 10 key management objectives and made 
substantial progress on one other. Objectives on aircraft deliveries 
and a corrective management plan were not met. The F-35 development 
test program substantially met expectations with some revisions to 
flight test plans and made considerable progress addressing key 
technical risks. Software management practices and some output 
measures improved, although deliveries to test continued to lag behind 
plans. Manufacturing and supply processes also improved—indicators 
such as factory throughput, labor efficiency, and quality measures 
were positive. While initial F-35 production overran target costs and 
delivered aircraft late, the latest data shows labor hours decreasing 
and deliveries accelerating. 

Going forward, the F-35 program still faces considerable challenges 
and risks. Ensuring that the F-35 is affordable and can be bought in 
the quantities and time required by the warfighter will be a paramount 
concern to the Congress, DOD, and international partners. With more 
austere budgets looming, F-35 acquisition funding requirements average 
$12.6 billion annually through 2037 (see below). Once fielded, the 
projected costs of sustaining the F-35 fleet have been deemed 
unaffordable by DOD officials; efforts to reduce these costs are 
underway. Software integration and test will be challenging as many 
complex tasks remain to enable full warfighting capability. The 
program is also incurring substantial costs for rework–currently 
projected at $1.7 billion over 10 years of production–to fix problems 
discovered during testing. With about two-thirds of development 
testing still to go, additional changes to design and manufacturing 
are likely. As a result, the program continues to incur financial risk 
from its plan to procure 289 aircraft for $57.8 billion before 
completing development flight testing. 

Figure: F-35 Joint Strike Fighter Acquisition Funding Requirements: 

[Refer to PDF for image: vertical bar graph] 

The year dollars: 

Average: $12.6 billion. 

Fiscal year 2013: $9.1 billion. 

Fiscal year 2014: $89.0 billion. 

Fiscal year 2015: $9.9 billion. 

Fiscal year 2016: $11.6 billion. 

Fiscal year 2017: $12.4 billion. 

Fiscal year 2018: $14.1 billion. 

Fiscal year 2019: $13.3 billion. 

Fiscal year 2020: $14.0 billion. 

Fiscal year 2021: $16.1 billion. 

Fiscal year 2022: $15.8 billion. 

Fiscal year 2023: $15.8 billion. 

Fiscal year 2024: $16.1 billion. 

Fiscal year 2025: $16.4 billion. 

Fiscal year 2026: $16.6 billion. 

Fiscal year 2027: $16.2 billion. 

Fiscal year 2028: $14.2 billion. 

Fiscal year 2029: $11.4 billion. 

Fiscal year 2030: $10.5 billion. 

Fiscal year 2031: $10.8 billion. 

Fiscal year 2032: $10.7 billion. 

Fiscal year 2033: $10.8 billion. 

Fiscal year 2034: $10.9 billion. 

Fiscal year 2035: $11.1 billion. 

Fiscal year 2036: $10.7 billion. 

Fiscal year 2037: $8.6 billion. 

Source: GAO analysis of DOD data. 

[End of figure] 

What GAO Recommends: 

GAO’s prior reviews of the F-35 made numerous recommendations to help 
reduce risk and improve outcomes. DOD has implemented those 
recommendations to varying degrees. 

View [hyperlink, http://www.gao.gov/products/GAO-13-690T]. For more 
information, contact Michael J. Sullivan at (202) 512-4841 or 
sullivanm@gao.gov. 

[End of section] 

GAO:
United States Government Accountability Office: 
441 G St. N.W. 
Washington, DC 20548: 

Chairman Durbin, Ranking Member Cochran, and Members of the 
Subcommittee: 

Thank you for the opportunity to discuss our work on the F-35 
Lightning II, also known as the Joint Strike Fighter (JSF). At a cost 
approaching $400 billion, the F-35 is the Department of Defense's 
(DOD) most costly and ambitious acquisition program. The program is 
developing and fielding three aircraft variants for the Air Force, 
Navy, and Marine Corps and eight international partners. The F-35 is 
the linchpin of U.S. and partner plans to replace existing fighters 
and support future combat operations. In a time of austere federal 
budgets, DOD continues to project significant long-term sustained 
funding requirements for the F-35 while, at the same time, pursuing 
several other expensive systems. Over the past 3 years, DOD has 
extensively restructured the F-35 program to address poor cost, 
schedule, and performance outcomes. Most recently, in March 2012, DOD 
established a new, more realistic, F-35 acquisition program baseline 
that reflects increased costs, longer schedule times, and deferred 
procurement of 410 aircraft to the future. Appendix I tracks program 
baseline changes since the start of system development in 2001. 

We have reported annually on F-35 issues since 2005.[Footnote 1] My 
testimony today is largely based on the results of our latest review, 
[Footnote 2] and addresses (1) the progress the F-35 program made in 
2012 and (2) the major risks that the program faces going forward. To 
conduct our work, we reviewed program status reports and briefings, 
management objectives, test plans and results, and internal DOD 
analyses with a focus on accomplishments in calendar year 2012 
compared to original plans for that year. We obtained manufacturing 
data and cumulative outputs from the start of production in 2007 
through the end of 2012, and discussed development and production 
issues and results to date, future expansion plans, and improvement 
efforts with DOD, F-35 program, and contractor officials. We toured 
the aircraft manufacturing plant, obtained production and supply 
performance indicators, identified cumulative and projected 
engineering changes, and discussed factory improvements and management 
controls with members of the contractor's work force and DOD plant 
representatives. We evaluated DOD's restructuring actions and impacts 
on the program, tracked cost and schedule changes from program start 
to the March 2012 baseline, and determined factors driving the 
changes. We obtained current projections of acquisition funding needs 
through 2037 and estimated life cycle sustainment funding 
requirements. We conducted this work in accordance with generally 
accepted government auditing standards. 

F-35 Program Performance Improved in 2012: 

The F-35 program made progress in 2012 on several fronts. The program 
met or substantially met most of its key management and development 
testing objectives for the year. We also found that the program made 
progress in addressing key technical risks, as well as improving 
software management, manufacturing, and supply processes. 

Most Management and Development Testing Objectives Were Achieved: 

The F-35 program met or substantially met most of its key management 
objectives established for calendar year 2012. The program office 
annually establishes major management objectives that it wants to 
achieve in the upcoming year. The F-35 program achieved 7 of its 10 
primary objectives in 2012. Those included, among other things, the 
completion of development testing on early increments of software, the 
beginning of lab testing for both variations of the helmet mounted 
display, the beginning of pilot training for two aircraft variants, 
and the completion of negotiations on the restructured development 
contract. Although the program did not complete its software block 3 
[Footnote 3] critical design review as planned in 2012, it did 
successfully complete its block 3 preliminary design review in 
November 2012 and the critical design review in late January 2013. The 
program did not meet its objectives to (1) deliver 40 production 
aircraft in 2012 and (2) receive approval from the Defense Contract 
Management Agency of the contractor's plan for correcting deficiencies 
in its system for tracking and reporting cost and schedule progress. 
[Footnote 4] 

The F-35 development flight test program also substantially met 2012 
expectations with some revisions to original plans. The program 
exceeded its planned number of flights by 18 percent, although it fell 
short of its plan in terms of test points[Footnote 5] flown by about 3 
percent, suggesting that the flights flown were not as productive as 
expected. Test officials had to make several adjustments to plans 
during the year due to operating and performance limitations with 
aircraft and late releases of software to test. As a result, none of 
the three variants completed all of their planned 2012 baseline 
points, but the test team was able to add and complete some test 
points that had been planned for future years. Testing accomplished on 
each of the aircraft variants in 2012 included: 

* Conventional takeoff and landing variant (F-35A)--accomplished high 
angle of attack testing, initial weapons separation, engine air start, 
expansion of the airspeed and altitude envelopes, and evaluated flying 
qualities with internal and external weapons.[Footnote 6] 

* Short takeoff and vertical landing variant (F-35B)--accomplished the 
first weapons release, engine air start tests, fuel dump operations, 
flight envelope expansion with weapons loaded, radar signature 
testing, and tested re-design air inlet doors for vertical lift 
operations. 

* Carrier suitable variant (F-35C)--conducted speed and altitude range 
verification and flights with external weapons, prepared for simulated 
carrier landings, and conducted shore-based tests of a redesigned 
arresting hook. 

Progress Made in Addressing Key Technical Risks: 

In 2012, the F-35 program also made considerable progress in 
addressing four areas of technical risk that if left unaddressed could 
substantially degrade the F-35's capabilities and mission 
effectiveness. However, additional work remains to fully address those 
risks. These risk areas and the actions taken in 2012 are discussed 
below: 

1. Helmet mounted display (HMD)--DOD continued to address technical 
issues with the HMD system. The original helmet mounted display, 
integral to mission systems, encountered significant technical 
deficiencies and did not meet warfighter requirements. The program is 
pursuing a dual path by developing a second, less capable helmet while 
working to fix the first helmet design. In 2012, DOD began dedicated 
ground and flight testing to address these issues. Both variations of 
the helmet mounted display are being evaluated and program and 
contractor officials told us that they have increased confidence that 
the helmet deficiencies will be fixed. DOD may make a decision in 2013 
as to which helmet to procure. 

2. Autonomic Logistics Information System (ALIS)--ALIS is an important 
tool to predict and diagnose aircraft maintenance and supply issues. 
ALIS systems with limited capability are in use at training and 
testing locations. More capable versions of ALIS are being developed 
and program and contractor officials believe that the program is on 
track to fix previously identified shortcomings and field the fully 
capable system in 2015. Limited progress was made in 2012 on 
developing a smaller, transportable version needed to support unit 
level deployments to operating locations. 

3. Arresting hook system--The carrier variant arresting hook system 
was redesigned after the original hook was found to be deficient, 
which prevented active carrier trials. The program accomplished risk 
reduction testing of a redesigned hook point to inform this new 
design. The preliminary design review was conducted in August 2012 and 
the critical design review in February 2013. Flight testing of the 
redesigned system is slated for late 2013. 

4. Structural durability--Over time, testing has discovered bulkhead 
and rib cracks on the aircraft. Structural and durability testing to 
verify that all three variants can achieve their expected life and 
identify life-limited parts was completed in 2012. The program is 
testing some redesigned structures and planning other modifications. 
Officials plan to retrofit and test a production aircraft already 
built and make changes to the production line for subsequent aircraft. 
Current projections show the aircraft and modifications remain within 
weight targets. 

Software Management and Output Improved: 

In 2012, the F-35 aircraft contractor and program office took steps to 
improve the program's software management and output. The program 
began the process of establishing a second system integration 
laboratory, adding substantial testing and development capacity. The 
program also began prioritizing and focusing its resources on 
incremental software development as opposed to the much riskier 
concurrent development approach. In addition, the program began 
implementing improvement initiatives recommended by an independent 
software review, and evaluated the possible deferral of some of the 
aircraft's capabilities to later blocks or moving them outside of the 
current F-35 program altogether. At the same time, program data 
regarding software output showed improvement. For example, program 
officials reported that the time it took to fix software defects 
decreased from180 days to 55 days, and the time it took to build and 
release software for testing decreased from 187 hours to 30 hours. 

Manufacturing Process Metrics Improved: 

Key manufacturing metrics and discussions with defense and contracting 
officials indicate that F-35 manufacturing and supply processes 
improved during 2012. While initial F-35 production overran target 
costs and delivered aircraft late, the latest data through the end of 
2012 shows labor hours decreasing and deliveries accelerating. The 
aircraft contractor's work force has gained important experience and 
processes have matured as more aircraft are built. We found that the 
labor hours needed to complete aircraft at the prime contractor's 
plant decreased, labor efficiency since the first production aircraft 
improved, time to manufacture aircraft in the final assembly area 
declined, factory throughput increased, and the amount of traveled 
work declined. In addition, program data showed that the reliability 
and predictability of the manufacturing processes increased while at 
the same time aircraft delivery rates improved considerably. Figure 1 
illustrates the improvement in production aircraft delivery time 
frames by comparing actual delivery dates against the dates specified 
in the contracts. 

Figure 1: F-35 Production Aircraft Deliveries Compared to Contract 
Dates: 

[Refer to PDF for image: multiple line graph] 

[Refer to PDF for image: multiple line graph] 

Aircraft: AF-06; 
Original contractual delivery month: January 2010; 
Actual delivery month: June 2011. 

Aircraft: AF-07; 
Original contractual delivery month: February 2010; 
Actual delivery month: May 2011. 

Aircraft: AF-08; 
Original contractual delivery month: April 2010; 
Actual delivery month: July 2011. 

Aircraft: AF-09; 
Original contractual delivery month: May 2010; 
Actual delivery month: 

Aircraft: AF-10; 
Original contractual delivery month: June 2010; 
Actual delivery month: August 2011. 

Aircraft: AF-11; 
Original contractual delivery month: July 2010; 
Actual delivery month: August 2011. 

Aircraft: AF-12; 
Original contractual delivery month: August 2010; 
Actual delivery month: September 2011. 

Aircraft: AF-13; 
Original contractual delivery month: September 2010; 
Actual delivery month: October 2011. 

Aircraft: BF-06; 
Original contractual delivery month: September 2010; 
Actual delivery month: January 2012. 

Aircraft: BF-07; 
Original contractual delivery month: October 2010; 
Actual delivery month: January 2012. 

Aircraft: BF-08; 
Original contractual delivery month: November 2010; 
Actual delivery month: January 2012. 

Aircraft: BF-09; 
Original contractual delivery month: December 2010; 
Actual delivery month: May 2012. 

Aircraft: BF-10; 
Original contractual delivery month: January 2011; 
Actual delivery month: May 2012. 

Aircraft: BF-11; 
Original contractual delivery month: January 2011; 
Actual delivery month: May 2012. 

Aircraft: BF-12; 
Original contractual delivery month: April 2011; 
Actual delivery month: June 2012. 

Aircraft: AF-14; 
Original contractual delivery month: May 2011; 
Actual delivery month: June 2012. 

Aircraft: BF-13; 
Original contractual delivery month: May 2011; 
Actual delivery month: July 2012. 

Aircraft: AF-15; 
Original contractual delivery month: July 2011; 
Actual delivery month: June 2012. 

Aircraft: BF-14; 
Original contractual delivery month: July 2011; 
Actual delivery month: July 2012. 

Aircraft: AF-16; 
Original contractual delivery month: August 2011; 
Actual delivery month: July 2012. 

Aircraft: BK-01; 
Original contractual delivery month: August 2011; 
Actual delivery month: July 2012. 

Aircraft: AF-17; 
Original contractual delivery month: August 2011; 
Actual delivery month: November 2012. 

Aircraft: AF-18; 
Original contractual delivery month: September 2011; 
Actual delivery month: November 2012. 

Aircraft: BK-02; 
Original contractual delivery month: September 2011; 
Actual delivery month: August 2012. 

Aircraft: AF-19; 
Original contractual delivery month: September 2011; 
Actual delivery month: November 2012. 

Aircraft: BF-15; 
Original contractual delivery month: October 2011; 
Actual delivery month: August 2012. 

Aircraft: AF-20; 
Original contractual delivery month: October 2011; 
Actual delivery month: November 2012. 

Aircraft: BF-16; 
Original contractual delivery month: November 2011; 
Actual delivery month: August 2012. 

Aircraft: BF-17; 
Original contractual delivery month: January 2012; 
Actual delivery month: August 2012. 

Aircraft: BF-18; 
Original contractual delivery month: January 2012; 
Actual delivery month: September 2012. 

Aircraft: BF-19; 
Original contractual delivery month: July 2012; 
Actual delivery month: October 2012. 

Aircraft: BF-20; 
Original contractual delivery month: July 2012; 
Actual delivery month: October 2012. 

Aircraft: AF-21; 
Original contractual delivery month: July 2012; 
Actual delivery month: November 2012. 

Aircraft: CF-05; 
Original contractual delivery month: August 2012; 
Actual delivery month: November 2012. 

Aircraft: AF-22; 
Original contractual delivery month: August 2012; 
Actual delivery month: November 2012. 

Aircraft: BF-21; 
Original contractual delivery month: August 2012; 
Actual delivery month: November 2012. 

Aircraft: AF-23; 
Original contractual delivery month: September 2012; 
Actual delivery month: November 2012. 

Aircraft: AF-24; 
Original contractual delivery month: September 2012; 
Actual delivery month: November 2012. 

Aircraft: BF-22; 
Original contractual delivery month: September 2012; 
Actual delivery month: November 2012. 

Source: GAO analysis of DOD data. 

Note: The numbered aircraft are in order of delivery. 
AF= U.S. Air Force F-35A, 
BF = U.S. Marine Corps F-35B, 
CF = U.S. Department of the Navy F-35C; and, 
BK = United Kingdom F-35B. 

[End of figure] 

F-35 Program Still Faces Risks: 

Ensuring that the F-35 is affordable and can be bought in the 
quantities and time frames required by the warfighter will be of 
paramount concern to the Congress, U.S. military and international 
partners. As we recently reported, the acquisition funding 
requirements for the United States alone are currently expected to 
average $12.6 billion per year through 2037, and the projected costs 
of operating and sustaining the F-35 fleet, once fielded, have been 
deemed unaffordable by DOD officials. In addition, the program faces 
challenges with software development and continues to incur 
substantial costs for rework to fix deficiencies discovered during 
testing. As testing continues additional changes to design and 
manufacturing processes will likely be required, while production 
rates continue to increase. 

Long-Term Affordability Remains a Concern: 

We recently concluded that while the March 2012 acquisition program 
baseline places the F-35 program on firmer footing, the aircraft are 
expected to cost more and deliveries to warfighters will take longer 
than previously projected. The new baseline projects the need for a 
total of $316 billion in development and procurement funding from 2013 
through 2037, or an average of $12.6 billion annually over that period 
(see figure 2). Maintaining this level of sustained funding will be 
difficult in a period of declining or flat defense budgets and 
competition with other "big ticket items" such as the KC-46 tanker and 
a new bomber program. In addition, the funding projections assume the 
financial benefits of the international partners purchasing at least 
697 aircraft. If fewer aircraft are procured in total or in smaller 
annual quantities--by the international partners or the United States--
unit costs will likely rise according to analysis done by the Office 
of the Secretary of Defense (OSD) Cost Assessment and Program 
Evaluation (CAPE) office. 

Figure 2: F-35 Program Budgeted Development and Procurement Funding 
Requirements, Fiscal Years 2013-2037: 

[Refer to PDF for image: stacked vertical bar graph] 

Then year dollars: 

Fiscal year average: $12.6 billion. 

Fiscal year: 2013; 
Air Force research, development, test, and evaluation: $1.2 billion; 
Air Force procurement: $3.7 billion; 
Navy research, development, test, and evaluation: $1.5 billion; 
Navy procurement: $2.7 billion. 

Fiscal year: 2014; 
Air Force research, development, test, and evaluation: $1.0 billion; 
Air Force procurement: $3.7 billion; 
Navy research, development, test, and evaluation: $1.3 billion; 
Navy procurement: $3.0 billion. 

Fiscal year: 2015; 
Air Force research, development, test, and evaluation: $0.6 billion; 
Air Force procurement: $5.1 billion; 
Navy research, development, test, and evaluation: $1.0 billion; 
Navy procurement: $3.2 billion. 

Fiscal year: 2016; 
Air Force research, development, test, and evaluation: $0.4 billion; 
Air Force procurement: $6.5 billion; 
Navy research, development, test, and evaluation: $0.7 billion; 
Navy procurement: $4.0 billion. 

Fiscal year: 2017; 
Air Force research, development, test, and evaluation: $0.2 billion; 
Air Force procurement: $6.5 billion; 
Navy research, development, test, and evaluation: $0.5 billion; 
Navy procurement: $5.3 billion. 

Fiscal year: 2018; 
Air Force research, development, test, and evaluation: $0.08 billion; 
Air Force procurement: $6.6 billion; 
Navy research, development, test, and evaluation: $0.8 billion; 
Navy procurement: $7.3 billion. 

Fiscal year: 2019; 
Air Force procurement: $6.3 billion; 
Navy procurement: $7.0 billion. 

Fiscal year: 2020; 
Air Force procurement: $6.8 billion; 
Navy procurement: $7.1 billion. 

Fiscal year: 2021; 
Air Force procurement: $8.6 billion; 
Navy procurement: $7.5 billion. 

Fiscal year: 2022; 
Air Force procurement: $8.8 billion; 
Navy procurement: $7.0 billion. 

Fiscal year: 2023; 
Air Force procurement: $8.8 billion; 
Navy procurement: $7.0 billion. 

Fiscal year: 2024; 
Air Force procurement: $9.1 billion; 
Navy procurement: $7.1 billion. 

Fiscal year: 2025; 
Air Force procurement: $9.1 billion; 
Navy procurement: $7.3 billion. 

Fiscal year: 2026; 
Air Force procurement: $9.4 billion; 
Navy procurement: $7.3 billion. 

Fiscal year: 2027; 
Air Force procurement: $9.6 billion; 
Navy procurement: $6.7 billion. 

Fiscal year: 2028; 
Air Force procurement: $9.7 billion; 
Navy procurement: $4.5 billion. 

Fiscal year: 2029; 
Air Force procurement: $10.1 billion; 
Navy procurement: $1.4 billion. 

Fiscal year: 2030; 
Air Force procurement: $10.5 billion. 

Fiscal year: 2031; 
Air Force procurement: $10.8 billion. 

Fiscal year: 2032; 
Air Force procurement: $10.7 billion. 

Fiscal year: 2033; 
Air Force procurement: $10.8 billion. 

Fiscal year: 2034; 
Air Force procurement: $10.9 billion. 

Fiscal year: 2035; 
Air Force procurement: $11.1 billion. 

Fiscal year: 2036; 
Air Force procurement: $10.7 billion. 

Fiscal year: 2037; 
Air Force procurement: $8.6 billion. 

Source: GAO analysis of DOD data. 

Note: Development and procurement of the Marine Corps variant is 
included in the Department of the Navy budget accounts. 

[End of figure] 

In addition to the costs for acquiring aircraft, we found that 
significant concerns and questions persist regarding the cost to 
operate and sustain the F-35 fleet over the coming decades. The 
current sustainment cost projection by CAPE for all U.S. aircraft, 
based on an estimated 30-year service life, exceeds $1 trillion. Using 
current program assumptions of aircraft inventory and flight hours, 
CAPE recently estimated annual operating and support costs of $18.2 
billion for all F-35 variants compared to $11.1 billion spent on 
legacy aircraft in 2010. DOD officials have declared that operating 
and support costs of this magnitude are unaffordable and the 
department is actively engaged in evaluating opportunities to reduce 
those costs, such as basing and infrastructure reductions, competitive 
sourcing, and reliability improvements. 

Because of F-35 delays and uncertainties, the military services have 
made investments to extend the service lives of legacy F-16 and F-18 
aircraft at a cost of $5 billion (in 2013 dollars). The Navy is also 
buying new F/A-18E/F Super Hornets at a cost of $3.1 billion (in then-
year dollars) to bridge the gap in F-35 deliveries and mitigate 
projected shortfalls in fighter aircraft force requirements. As a 
result, the services will incur additional future sustainment costs to 
support these new and extended-life aircraft, and will have a 
difficult time establishing and implementing retirement schedules for 
existing fleets. 

Software Development Challenges Remain: 

Our report found that over time, F-35 software requirements have grown 
in size and complexity and the contractor has taken more time and 
effort than expected to write computer code, integrate it on aircraft 
and subsystems, conduct lab and flight tests to verify it works, and 
to correct defects found in testing. Although recent management 
actions to refocus software development activities and implement 
improvement initiatives appeared to be yielding benefits, software 
continued to be a very challenging and high-risk undertaking, 
especially for mission systems.[Footnote 7] While most of the 
aircraft's software code has been developed, a substantial amount of 
integration and test work remain before the program can demonstrate 
full warfighting capability. About 12 percent of mission systems 
capabilities have now been validated, up from 4 percent about a year 
ago. However, progress on mission systems was limited in 2012 by 
contractor delays in software delivery, limited capability in the 
software when delivered, and the need to fix problems and retest 
multiple software versions. Further development and integration of the 
most complex elements--sensor fusion and helmet mounted display--lie 
ahead. 

F-35 software capabilities are being developed, tested and delivered 
in three major blocks and two increments--initial and final--within 
each block. The testing and delivery status of the three blocks is 
described below: 

* Block 1.0, providing initial training capability, was largely 
completed in 2012, although some final development and testing will 
continue. Also, the capability delivered did not fully meet expected 
requirements relating to the helmet, ALIS, and instrument landing 
capabilities. 

* Block 2.0, providing initial warfighting capabilities and limited 
weapons, fell behind due to integration challenges and the 
reallocation of resources to fix block 1.0 defects. The initial 
increment, block 2A, delivered late and was incomplete. Full release 
of the final increment, block 2B, has been delayed until November 2013 
and will not be complete until late 2015. 

* Block 3.0 providing full warfighting capability, to include sensor 
fusion and additional weapons, is the capability required by the Navy 
and Air Force for declaring their respective initial operational 
capability dates. Thus far, the program has made little progress on 
block 3.0 software. The program intends initial block 3.0 to enter 
flight test in 2013. This is rated as one of the program's highest 
risks because of its complexity. 

Design Changes and Rework Continue to Add Cost and Risk: 

Although our recent review found that F-35 manufacturing, cost, and 
schedule metrics have shown improvement, the aircraft contractor 
continues to make major design and tooling changes and alter 
manufacturing processes while development testing continues. 
Engineering design changes from discoveries in manufacturing and 
testing are declining in number, but are still substantial and higher 
than expected from a program this far along in production. Further, 
the critical work to test and verify aircraft design and operational 
performance is far from complete. Cumulatively, since the start of 
developmental flight testing, the program has accomplished 34 percent 
of its planned flights and test points. For development testing as a 
whole, the program verified 11.3 percent of the development contract 
specifications through November 2012. As indicated in table 1, DOD 
continues to incur financial risk from its plan to procure 289 
aircraft for $57.8 billion before completing development flight 
testing. 

Table 1: F-35 Procurement Investments and Flight Test Progress: 

Cumulative procurement (then year dollars): 
2007: $0.8 billion; 
2008: $3.5 billion; 
2009: $7.1 billion; 
2010: $14.3 billion; 
2011: $21.3 billion; 
2012: $27.6 billion; 
2013: $33.8 billion; 
2014: $40.1 billion; 
2015: $47.9 billion; 
2016: $57.8 billion; 
2017: $69.0 billion. 

Cumulative aircraft procured: 
2007: 2; 
2008: 14; 
2009: 28; 
2010: 58; 
2011: 90; 
2012: 121; 
2013: 150; 
2014: 179; 
2015: 223; 
2016: 289; 
2017: 365. 

Percent total flight test points completed: 
2007: 0; 
2008: less than 1%; 
2009: less than 1%; 
2010: 2%; 
2011: 9%; 
2012: 22%; 
2013: 34%; 
2014: 54%; 
2015: 74%; 
2016: 91%; 
2017: 100%. 

Source: GAO analysis of DOD data. 

Notes: Years listed denote fiscal years. Flight test data reflects the 
percentage of total flight test points completed in time to inform the 
next year's procurement decision. For example above, the F-35 program 
accomplished about 22 percent of total planned flight test points 
through the end of calendar year 2011 that could help inform the 
fiscal year 2012 procurement decision. The program intends to complete 
developmental flight test points in 2016 and would be in a position to 
fully support the 2017 procurement buy. 

[End of table] 

This highly concurrent approach to procurement and testing increases 
the risk that the government will incur substantial costs to retrofit 
(rework) already produced aircraft to fix deficiencies discovered in 
testing. In fact, the F-35 program office projects rework costs of 
about $900 million to fix the aircraft procured on the first four 
annual procurement contracts. Substantial rework costs are also 
forecasted to continue through the 10th annual contract (fiscal year 
2016 procurement), but at decreasing amounts annually and on each 
aircraft. The program office projects about $827 million more to 
rework aircraft procured under the next 6 annual contracts. 

DOD Actions On GAO Recommendations Have Varied, but F-35 Restructuring 
Was A Positive Step: 

We have reported on F-35 issues for over a decade and have found that 
the magnitude and persistence of the program's cost and schedule 
problems can be largely traced to (1) decisions at key junctures made 
without adequate product knowledge; and (2) a highly concurrent 
acquisition strategy that significantly overlapped development, 
testing, and manufacturing activities.[Footnote 8] Over that time, our 
reports included numerous recommendations aimed at reducing risk in 
these areas and improving the chances for successful outcomes. 
[Footnote 9] 

DOD has implemented our recommendations to varying degrees. For 
example, in 2001 we recommended that DOD delay the start of system 
development until the F-35's critical technologies were fully mature. 
DOD disagreed with that recommendation and chose to begin the program 
with limited knowledge about critical technologies. Several years 
later, we recommended that DOD delay the production decision until 
flight testing had shown that the F-35 would perform as expected, and 
although DOD partially concurred with our recommendation, it chose to 
initiate production before sufficient flight testing had been done. 
Citing concerns about the overlap--or concurrency--among development, 
testing, and production, we have recommended that DOD limit annual 
production quantities until F-35 flying qualities could be 
demonstrated. Although DOD disagreed with our recommendation at the 
time, it has since restructured the F-35 program and, among other 
things, deferred the production of hundreds of aircraft into the 
future, thus addressing the intent of our recommendation and reducing 
program risk. Appendix II lists these and other key recommendations we 
have made over time, and identifies the actions DOD has taken in 
response. 

In conclusion, while the recent restructuring of the F-35 program 
placed it on a firmer footing, tremendous challenges still remain. The 
program must fully validate the F-35's design and operational 
performance against warfighter requirements, while at the same time 
make the system affordable so that the United States and partners can 
acquire new capabilities in the quantity needed and can then sustain 
the force over its life cycle. Ensuring overall affordability will be 
a challenge as more austere budgets are looming. 

Chairman Durbin, Ranking Member Cochran and members of the 
subcommittee, this completes my prepared statement. I would be pleased 
to respond to any questions you may have. 

GAO Contact and Acknowledgments: 

For further information on this statement, please contact Michael 
Sullivan at (202) 512-4841 or sullivanm@gao.gov. Contact points for 
our Office of Congressional Relations and Public Affairs may be found 
on the last page of this statement. Individuals making key 
contributions to this statement are Bruce Fairbairn, Travis Masters, 
Marvin Bonner, W. Kendal Roberts, Megan Porter, Erin Stockdale, and 
Abby Volk. 

[End of section] 

Appendix I: Changes in Reported F-35 Program Quantity, Cost, and 
Deliveries, 2001-2012: 

Expected quantities: 

Development quantities; 
October 2001 (system development start): 14; 
December 2003 (approved baseline): 14; 
March 2007 (approved baseline): 15; 
June 2010 (Nunn-McCurdy): 14; 
March 2012 (approved baseline): 14. 

Procurement quantities (U.S. only); 
October 2001 (system development start): 2,852; 
December 2003 (approved baseline): 2,443; 
March 2007 (approved baseline): 2,443; 
June 2010 (Nunn-McCurdy): 2,443; 
March 2012 (approved baseline): 2,443. 

Total quantities; 
October 2001 (system development start): 2,866; 
December 2003 (approved baseline): 2,457; 
March 2007 (approved baseline): 2,458; 
June 2010 (Nunn-McCurdy): 2,457; 
March 2012 (approved baseline): 2,457. 

Cost estimates (then-year dollars in billions): 

Development; 
October 2001 (system development start): $34.4 billion; 
December 2003 (approved baseline): $44.8 billion; 
March 2007 (approved baseline): $44.8 billion; 
June 2010 (Nunn-McCurdy): $51.8 billion; 
March 2012 (approved baseline): $55.2 billion. 

Procurement; 
October 2001 (system development start): $196.6 billion; 
December 2003 (approved baseline): $199.8 billion; 
March 2007 (approved baseline): $231.7 billion; 
June 2010 (Nunn-McCurdy): $325.1 billion; 
March 2012 (approved baseline): $335.7 billion. 

Military construction; 
October 2001 (system development start): $2.0 billion; 
December 2003 (approved baseline): 0.2 billion; 
March 2007 (approved baseline): $2.0 billion; 
June 2010 (Nunn-McCurdy): $5.6 billion; 
March 2012 (approved baseline): $4.8 billion. 

Total program acquisition; 
October 2001 (system development start): $233.0 billion; 
December 2003 (approved baseline): $244.8 billion; 
March 2007 (approved baseline): $278.5 billion; 
June 2010 (Nunn-McCurdy): $382.5 billion; 
March 2012 (approved baseline): $395.7 billion. 

Unit cost estimates (then-year dollars in millions): 

Program acquisition; 
October 2001 (system development start): $81 million; 
December 2003 (approved baseline): $100 million; 
March 2007 (approved baseline): $113 million; 
June 2010 (Nunn-McCurdy): $156 million; 
March 2012 (approved baseline): $161 million. 

Average procurement; 
October 2001 (system development start): $69 million; 
December 2003 (approved baseline): $82 million; 
March 2007 (approved baseline): $95 million; 
June 2010 (Nunn-McCurdy): $133 million; 
March 2012 (approved baseline): $137 million. 

Estimated delivery and production dates: 

First production aircraft delivery; 
October 2001 (system development start): 2008; 
December 2003 (approved baseline): 2009; 
March 2007 (approved baseline): 2010; 
June 2010 (Nunn-McCurdy): 2010; 
March 2012 (approved baseline): 2011. 

Initial operational capability; 
October 2001 (system development start): 2010-2012; 
December 2003 (approved baseline): 2012-2013; 
March 2007 (approved baseline): 2012-2015; 
June 2010 (Nunn-McCurdy): TBD; 
March 2012 (approved baseline): TBD. 

Full-rate production; 
October 2001 (system development start): 2012; 
December 2003 (approved baseline): 2013; 
March 2007 (approved baseline): 2013; 
June 2010 (Nunn-McCurdy): 2016; 
March 2012 (approved baseline): 2019. 

Source: GAO analysis of DOD data. 

Note: TBD means to be determined. 

[End of table] 

[End of section] 

Appendix II: Prior GAO Reports and DOD Responses: 

GAO report: 2001; GAO-02-39; 
Estimated development costs: $34.4 Billion; 
Development length: 10 years; 
Aircraft unit cost: $69 Million; 
Key program event: Start of system development and demonstration 
approved; 
Primary GAO message: Critical technologies needed for key aircraft 
performance elements not mature. Program should delay start of system 
development until critical technologies mature to acceptable levels; 
DOD response and actions: DOD did not delay start of system 
development and demonstration stating technologies were at acceptable 
maturity levels and will manage risks in development. 

GAO report: 2005; GAO-05-271; 
Estimated development costs: $44.8 Billion; 
Development length: 12 years; 
Aircraft unit cost: $82 Million; 
Key program event: The program undergoes re-plan to address higher 
than expected design weight, which added $7 billion and 18 months to 
development schedule; 
Primary GAO message: We recommended that the program reduce risks and 
establish executable business case that is knowledge-based with an 
evolutionary acquisition strategy; 
DOD response and actions: DOD partially concurred but did not adjust 
strategy, believing that its approach is balanced between cost, 
schedule and technical risk. 

GAO report: 2006; GAO-06-356; 
Estimated development costs: $45.7 Billion; 
Development length: 12 years; 
Aircraft unit cost: $86 Million; 
Key program event: Program sets in motion plan to enter production in 
2007 shortly after first flight of the non-production representative 
aircraft; 
Primary GAO message: The program planned to enter production with less 
than 1 percent of testing complete. We recommended program delay 
investing in production until flight testing shows that JSF performs 
as expected; 
DOD response and actions: DOD partially concurred but did not delay 
start of production because it believed the risk level was appropriate. 

GAO report: 2007; GAO-07-360; 
Estimated development costs: $44.5 Billion; 
Development length: 12 years; 
Aircraft unit cost: $104 Million; 
Key program event: Congress reduced funding for first two low-rate 
production buys thereby slowing the ramp up of production; 
Primary GAO message: Progress was being made but concerns remained 
about undue overlap in testing and production. We recommended limits 
to annual production quantities to 24 a year until flying quantities 
are demonstrated; 
DOD response and actions: DOD non-concurred and felt that the program 
had an acceptable level of concurrency and an appropriate acquisition 
strategy. 

GAO report: 2008; GAO-08-388; 
Estimated development costs: $44.2 Billion; 
Development length: 12 years; 
Aircraft unit cost: $104 Million; 
Key program event: DOD implemented a Mid-Course Risk Reduction Plan to 
replenish management reserves from about $400 million to about $1 
billion by reducing test resources; 
Primary GAO message: We believed new plan increased risks and DOD 
should revise it to address testing, management reserves, and 
manufacturing concerns. We determined that the cost estimate was not 
reliable and that a new cost estimate and schedule risk assessment is 
needed; 
DOD response and actions: DOD did not revise risk plan or restore 
testing resources, stating that it will monitor the new plan and 
adjust it if necessary. Consistent with a report recommendation, a new 
cost estimate was eventually prepared, but DOD refused to do a risk 
and uncertainty analysis. 

GAO report: 2009; GAO-09-303; 
Estimated development costs: $44.4 Billion; 
Development length: 13 years; 
Aircraft unit cost: $104 Million; 
Key program event: The program increased the cost estimate and adds a 
year to development but accelerated the production ramp up. Primary 
GAO message: Independent DOD cost estimate (JET I) projects even 
higher costs and further delays; 
Moving forward with an accelerated procurement plan and use of cost 
reimbursement contracts is very risky. We recommended the program 
report on the risks and mitigation strategy for this approach; 
DOD response and actions: DOD agreed to report its contracting 
strategy and plans to Congress and conduct a schedule risk analysis. 
The program completed the first schedule risk assessment with plans to 
update semi-annually. The Department announced a major restructuring 
reducing procurement and moving to fixed-price contracts. 

GAO report: 2010; GAO-10-382; 
Estimated development costs: $49.3 Billion; 
Development length: 15 years; 
Aircraft unit cost: $112 Million; 
Key program event: The program was restructured to reflect findings of 
recent independent cost team (JET II) and independent manufacturing 
review team. As a result, development funds increased, test aircraft 
were added, the schedule was extended, and the early production rate 
decreased; 
Primary GAO message: Costs and schedule delays inhibit the program's 
ability to meet needs on time. We recommended the program complete a 
full comprehensive cost estimate and assess warfighter and IOC 
requirements. We suggest that Congress require DOD to tie annual 
procurement requests to demonstrated progress; 
DOD response and actions: DOD continued restructuring, increasing test 
resources and lowering the production rate. Independent review teams 
evaluated aircraft and engine manufacturing processes. Cost increases 
later resulted in a Nunn-McCurdy breach. Military services are 
currently reviewing capability requirements as we recommended. 

GAO report: 2011; GAO-11-325; 
Estimated development costs: $51.8 Billion; 
Development length: 16 years; 
Aircraft unit cost: $133 Million; 
Key program event: Restructuring continued with additional development 
cost increases; schedule growth; further reduction in near-term 
procurement quantities; and decreased the rate of increase for future 
production. The Secretary of Defense placed the STOVL variant on a 2 
year probation; decoupled STOVL from the other variants; and reduced 
STOVL production plans for fiscal years 2011 to 2013; 
Primary GAO message: The restructuring actions are positive and if 
implemented properly, should lead to more achievable and predictable 
outcomes. Concurrency of development, test, and production is 
substantial and provides risk to the program. We recommended the 
program maintain funding levels as budgeted; establish criteria for 
STOVL probation; and conduct an independent review of software 
development, integration, and test processes; 
DOD response and actions: DOD concurred with all three of the 
recommendations. DOD lifted STOVL probation, citing improved 
performance. Subsequently, DOD further reduced procurement quantities, 
decreasing funding requirements through 2016. The initial independent 
software assessment began in and ongoing reviews are planned through 
2012. 

GAO report: 2012; GAO-12-437; 
Estimated development costs: $55.2 Billion; 
Development length: 18 years; 
Aircraft unit cost: $137 Million; 
Key program event: The program established a new acquisition program 
baseline and approved the continuation of system development, 
increasing costs for development and procurements and extending the 
period of planned procurements by 2 years; 
Primary GAO message: Extensive restructuring places the program on a 
more achievable course. Most of the program's instability continues to 
be concurrency of development, test, and production. We recommend the 
Cost Assessment Program Evaluation office conduct an analysis on the 
impact of lower annual funding levels; JSF program office conducts an 
assessment of the supply chain and transportation network; 
DOD response and actions: DOD partially concurred with conducting an 
analysis on the impact of lower annual funding levels and concurred 
with assessing the supply chain and transportation network. 

Source: DOD data and GAO analysis in prior reports cited above. 

[End of table] 

[End of section] 

Related GAO Products: 

F-35 Joint Strike Fighter: Current Outlook Is Improved, but Long-Term 
Affordability Is a Major Concern. [hyperlink, 
http://www.gao.gov/products/GAO-13-309]. Washington, D.C.: March 11, 
2013. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-13-294SP]. Washington, 
D.C.: March 28, 2013. 

Joint Strike Fighter: DOD Actions Needed to Further Enhance 
Restructuring and Address Affordability Risks. [hyperlink, 
http://www.gao.gov/products/GAO-12-437]. Washington, D.C.: June 14, 
2012. 

Joint Strike Fighter: Restructuring Added Resources and Reduced Risk, 
but Concurrency Is Still a Major Concern. [hyperlink, 
http://www.gao.gov/products/GAO-12-525T]. Washington, D.C.: March 20, 
2012. 

Joint Strike Fighter: Implications of Program Restructuring and Other 
Recent Developments on Key Aspects of DOD's Prior Alternate Engine 
Analyses. [hyperlink, http://www.gao.gov/products/GAO-11-903R]. 
Washington, D.C.: September 14, 2011. 

Joint Strike Fighter: Restructuring Places Program on Firmer Footing, 
but Progress Still Lags. [hyperlink, 
http://www.gao.gov/products/GAO-11-325]. Washington, D.C.: April 7, 
2011. 

Joint Strike Fighter: Additional Costs and Delays Risk Not Meeting 
Warfighter Requirements on Time. [hyperlink, 
http://www.gao.gov/products/GAO-10-382]. Washington, D.C.: March 19, 
2010. 

Joint Strike Fighter: Accelerating Procurement before Completing 
Development Increases the Government's Financial Risk. [hyperlink, 
http://www.gao.gov/products/GAO-09-303]. Washington D.C.: March 12, 
2009. 

Joint Strike Fighter: Recent Decisions by DOD Add to Program Risks. 
[hyperlink, http://www.gao.gov/products/GAO-08-388]. Washington, D.C.: 
March 11, 2008. 

Joint Strike Fighter: Progress Made and Challenges Remain. [hyperlink, 
http://www.gao.gov/products/GAO-07-360]. Washington, D.C.: March 15, 
2007. 

Joint Strike Fighter: DOD Plans to Enter Production before Testing 
Demonstrates Acceptable Performance. [hyperlink, 
http://www.gao.gov/products/GAO-06-356]. Washington, D.C.: March 15, 
2006. 

Tactical Aircraft: Opportunity to Reduce Risks in the Joint Strike 
Fighter Program with Different Acquisition Strategy. [hyperlink, 
http://www.gao.gov/products/GAO-05-271]. Washington, D.C.: March 15, 
2005. 

[End of section] 

Footnotes: 

[1] See related GAO products at the end of this statement. 

[2] GAO: F-35 Joint Strike Fighter: Current Outlook Is Improved, but 
Long-Term Affordability Is a Major Concern, [hyperlink, 
http://www.gao.gov/products/GAO-13-309] (Washington, D.C.: Mar. 11, 
2013). 

[3] Software capabilities are developed, tested, and delivered in 
three major blocks. Block 3 is to provide the F-35 its full 
warfighting capability. 

[4] This specifically refers to the contractor's Earned Value 
Management System, which has been found to be deficient. Earned value 
management is a disciplined process for tracking, controlling, and 
reporting contract costs and schedule. DOD requires its use by major 
defense suppliers to facilitate good insight and oversight of the 
expenditure of government dollars. 

[5] Flight test points are specific, quantifiable objectives in flight 
plans that are needed to verify aircraft design and performance. 

[6] Due primarily to operating restrictions and deficiencies in the 
air refueling system, the F-35A did not accomplish as many flights as 
planned and fell short of planned test points by about 15 percent. 

[7] Mission systems are critical enablers of F-35's combat 
effectiveness, employing next generation sensors with fused 
information from on-board and off-board systems (i.e., electronic 
warfare, communication navigation identification, electro-optical 
target system, electro-optical distributed aperture system, radar, and 
data links). 

[8] We have an extensive body of work looking at knowledge-based best 
practices in successful private and public acquisitions of new 
technology. Defense policy and the Weapon Systems Acquisition Reform 
Act of 2009 incorporate elements of the knowledge-based approach. For 
an overview of the best practices criteria and methodologies, and how 
current defense programs including the F-35 fared, see GAO, Defense 
Acquisitions: Assessments of Selected Weapon Programs, [hyperlink, 
http://www.gao.gov/products/GAO-12-400SP] (Washington, D.C.: Mar. 29, 
2012). 

[9] See related GAO products for a list of previous F-35 reports. 

[End of section] 

GAO’s Mission: 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the 
performance and accountability of the federal government for the 
American people. GAO examines the use of public funds; evaluates 
federal programs and policies; and provides analyses, recommendations, 
and other assistance to help Congress make informed oversight, policy, 
and funding decisions. GAO’s commitment to good government is 
reflected in its core values of accountability, integrity, and 
reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO’s website [hyperlink, http://www.gao.gov]. Each 
weekday afternoon, GAO posts on its website newly released reports, 
testimony, and correspondence. To have GAO e-mail you a list of newly 
posted products, go to [hyperlink, http://www.gao.gov] and select 
“E-mail Updates.” 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of 
production and distribution and depends on the number of pages in the 
publication and whether the publication is printed in color or black 
and white. Pricing and ordering information is posted on GAO’s 
website, [hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or 
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card, 
MasterCard, Visa, check, or money order. Call for additional 
information. 

Connect with GAO: 

Connect with GAO on facebook, flickr, twitter, and YouTube.
Subscribe to our RSS Feeds or E mail Updates. Listen to our Podcasts.
Visit GAO on the web at [hyperlink, http://www.gao.gov]. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 
Website: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]; 
E-mail: fraudnet@gao.gov; 
Automated answering system: (800) 424-5454 or (202) 512-7470. 

Congressional Relations: 

Katherine Siggerud, Managing Director, siggerudk@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, DC 20548. 

Public Affairs: 
Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, DC 20548. 

[End of document]