

Over the years, GAO has developed a substantial body of law and standard procedures for considering bid protests. This is the sixth edition of Bid Protests at GAO: A Descriptive Guide, prepared by the Office of the General Counsel to aid those interested in GAO's bid protest process. We issued the first edition of this booklet in 1975 to facilitate greater public familiarity with the bid protest process at GAO and we have revised it over the years to reflect changes in our bid protest procedures. This edition incorporates changes made to our Bid Protest Regulations, effective August 8, 1996, to implement the Federal Acquisition Reform Act of 1996 and the Information Technology Management Reform Act of 1996, as included in the National Defense Authorization Act for Fiscal Year 1996.
We have improved this edition of the booklet by providing additional and updated practice tips to assist parties participating in a bid protest at GAO. We also have updated the appendixes which contain a revised sample protective order and revised sample applications for access to material under a protective order.
Robert P. Murphy
General Counsel
Contents, Previous, Next
This booklet is an informal, practical guide to the bid protest process at GAO; however, it is not the law. The legal rules governing this process are set forth in GAO's Bid Protest Regulations. Since 1985, GAO has had detailed regulations to inform protesters of the rules concerning where and how to file a protest, what to expect in the way of subsequent actions, and the time frames established for completion of those actions. These regulations were promulgated to implement the Competition in Contracting Act of 1984 and were revised to implement the requirement in the Information Technology Management Reform Act of 1996, as included in the National Defense Authorization Act for Fiscal Year 1996, that GAO issue bid protest decisions within 100 calendar days for any new protest filed with GAO on or after August 8, 1996. (In these regulations, all "days" are calendar days.) The revised regulations will appear in Title 4 of the Code of Federal Regulations (C.F.R.), Part 21, and are reproduced in this booklet for ease of reference.
GAO changes its regulations from time to time because of changes in applicable statutes, a binding court decision, or when experience dictates that a modification is appropriate. These changes are published in the Federal Register, and then incorporated into the Code of Federal Regulations, which is published annually and reflects the revisions or additions to the regulations that were published in the Federal Register during the preceding year. Because the regulations are published in the Federal Register, protesters and other parties are deemed to have "constructive knowledge" of them, meaning that they are expected to comply with the regulations, even if they have never actually read the regulations.
In deciding bid protests, GAO considers whether federal agencies have complied with statutes and regulations controlling government procurements. The main statutes controlling federal procurements are the Armed Services Procurement Act of 1947 and the Federal Property and Administrative Services Act of 1949, as amended, particularly by the Competition in Contracting Act of 1984, the Federal Acquisition Streamlining Act of 1994, and the Federal Acquisition Reform Act of 1996 and the Information Technology Management Reform Act of 1996, as included in the National Defense Authorization Act for Fiscal Year 1996. These statutes are found in the United States Code, titles 10 and 41, respectively, and are implemented by the Federal Acquisition Regulation (FAR) and individual agency regulations. GAO's Bid Protest Regulations govern GAO's handling of protests and impose certain requirements on contracting agencies, protesters, and others who participate in the bid protest process at GAO.
During the course of a GAO protest, as appropriate, GAO may schedule status or other informal types of conferences to resolve procedural matters and to obtain information material to the disposition of the protest. GAO also may find that a hearing is necessary to resolve factual and legal issues raised in the protest. If it decides to hold a hearing, GAO will usually conduct a pre-hearing conference to decide the issues that will be considered at the hearing, to identify the witnesses who will testify at the hearing, and to settle procedural questions. After the hearing, all parties will be allowed to submit written comments on the hearing.
After the record is complete, GAO will consider the facts and legal issues raised and will issue a decision, a copy of which will be sent to all parties participating in the protest. GAO may sustain the protest (that is, find that the agency violated a procurement statute or regulation and that the violation prejudiced the protester), in which case GAO will recommend appropriate corrective action. Alternatively, GAO may deny the protest or may dismiss the protest without reviewing the matter. GAO will issue its decision not later than 100 days from the date the protest was filed. The exact date on which GAO issues the decision depends on the urgency of the procurement, the complexity of the factual and legal issues raised in the protest, and GAO's work load.
Although many parties retain an attorney in order to benefit from the attorney's familiarity with GAO's bid protest process and with procurement statutes and regulations, an attorney is not required for purposes of filing a protest. However, where the record includes another company's proprietary information or the agency's source-selection-sensitive information, only attorneys (and then only if the attorneys are admitted under a protective order, as discussed below) will be allowed to see that information.
There are some matters that cannot be protested to GAO. The most common grounds for dismissal of a protest in whole or in part are set forth in 4 C.F.R. § 21.5.
GAO does not require formal briefs or other technical forms of pleadings. However, at a minimum, a protest shall:
(1) Include the name, address, and telephone and facsimile (fax) numbers of the protester (or its representative, if any);
(2) Be signed by the protester or its representative;
(3) Identify the contracting agency and the solicitation and/or contract number;
(4) Set forth a detailed statement of the legal and factual grounds of protest, including copies of relevant documents;
(5) Set forth all information establishing that the protester is an interested party for the purpose of filing a protest;
(6) Set forth all information establishing the timeliness of the protest;
(7) Specifically request a ruling by the Comptroller General of the United States; and
(8) State the form of relief requested. 4 C.F.R. § 21.1(c).
In addition, a protest may include a request for a protective order, specific documents relevant to the protest, and a hearing. 4 C.F.R. § 21.1(d). In this regard, protesters must explain the relevancy of requested documents to their protest grounds and the reason a hearing is necessary to resolve the protest. Id.
The protest document must be clearly labeled if it contains information which the protester believes is proprietary, confidential, or otherwise not releasable to the public. In those cases, within 1 day after the filing of the unredacted protest with GAO, the protester must provide to GAO and the contracting agency a redacted version of the protest which omits such information. 4 C.F.R. § 21.1(g).
A party may request that GAO decide a protest using an express option schedule or other flexible alternative procedures, including establishing an accelerated schedule and/or issuing a summary decision. 4 C.F.R. § 21.10(a), (e).
Protests alleging improprieties in a solicitation must be filed prior to bid opening or the time set for receipt of initial proposals if the improprieties were apparent prior to that time. 4 C.F.R. § 21.2(a)(1). A solicitation defect that was not apparent before that time must be protested not later than 10 days after the defect became apparent. In negotiated procurements, if an alleged impropriety did not exist in the initial solicitation but was later incorporated into the solicitation by an amendment, a protest based on that impropriety must be filed before the next closing time established for submitting proposals. Id.
In all other cases, protests must be filed not later than 10 days after the protester knew or should have known the basis of protest (whichever is earlier), with the exception of protests challenging a procurement conducted on the basis of competitive proposals under which a debriefing is "requested and, when requested, is required" (that is, a statutorily required debriefing). In these cases, with respect to any protest basis which was known or should have been known before the statutorily required debriefing, the protester must not file its initial protest before the debriefing date offered to the protester, but must file its initial protest not later than 10 days after the date on which the debriefing was held. 4 C.F.R. § 21.2(a)(2).
The purpose of the exception to the timeliness rules for negotiated procurements is to encourage vendors to seek, and contracting agencies to give, early and meaningful debriefings prior to the vendor deciding whether or not to file a protest. Thus, in procurements conducted on the basis of competitive proposals in which a statutorily required debriefing is held, that is, where a debriefing is requested and, when requested, is required, a protester will always have up to 10 days after the debriefing to file its initial protest.
Special timeliness rules govern protests initially filed with the contracting agency. In those cases, the protest to GAO must be filed not later than 10 days after the protester learned of "initial adverse agency action." 4 C.F.R. § 21.2(a)(3). Deciding when adverse agency action occurs is straightforward when the protester receives oral or written notice that the agency is denying the agency-level protest. Protesters should keep in mind, however, that GAO views any action that makes clear that the agency is denying the agency-level protest as adverse agency action. Examples of adverse agency action include the agency's proceeding with bid opening or the receipt of proposals, the rejection of a bid or proposal, or the award of a contract despite the agency-level protest. Firms which have filed an agency-level protest and are considering filing a subsequent protest with GAO should be alert to any possible agency action that could be viewed as indicating that the agency is denying the agency-level protest.
Agency-level protests must be filed in accordance with GAO's timeliness rules at 4 C.F.R. § 21.2(a)(1) and (a)(2), unless the agency imposes a more stringent time for filing, in which case the agency's time for filing will control. Thus, even if a firm files a protest with GAO within 10 days of initial adverse agency action, GAO will consider the protest untimely if the agency-level protest was not timely filed under GAO's timeliness rules or under an agency's rules if those rules are stricter. 4 C.F.R. § 21.2(a)(3). For example, if a firm waits until after bid opening to file an agency-level protest of an apparent solicitation impropriety, even if the subsequent protest to GAO is filed within 10 days of the firm's learning that the agency has denied the agency-level protest, GAO will not consider a protest of that impropriety since the agency-level protest of the alleged impropriety was not filed prior to bid opening.
GAO may consider an untimely protest where exceptional circumstances beyond the protester's control caused the delay in filing the protest, or where the protest presents novel or significant issues of interest to the procurement community. 4 C.F.R. § 21.2(c). Protesters should be aware, however, that GAO will invoke these exceptions sparingly.
Finally, GAO recognizes that the North American Free Trade Agreement (NAFTA) contains a 10-working-day timeliness requirement which is inconsistent with GAO's timeliness rules. However, because of the flexibility of GAO's timeliness rules, GAO will afford a NAFTA protester all treaty rights for purposes of the timely filing of a protest.
Protests may be filed by hand delivery, mail, commercial carrier, or fax. 4 C.F.R. § 21.0(g). Protests filed by hand delivery or commercial carrier must be delivered to the window located in the G Street lobby in GAO's main building at the above-referenced address. Protesters filing their protests by fax should verify GAO's fax number prior to transmission. GAO's current official bid protest fax number is (202) 512-9749. Fax users should take into account the risk that GAO's receiving fax machine might be busy, particularly near the end of a business day. GAO will time/date stamp a fax transmission as of the time that the last page is received, which may affect the timeliness of the entire submission. Additional recorded information concerning the filing of protests at GAO may be obtained by calling GAO's Procurement Law Control Group at (202) 512-5282.
A copy of the protest, including all attachments, must be filed with the individual or location identified for that purpose in a solicitation, or with the contracting officer, within 1 day after the protest is filed with GAO. 4 C.F.R. § 21.1(e).
The acknowledgment notice includes important information. First, it provides the file number by which GAO identifies the protest. That number consists of a letter followed by six digits (e.g., B-123456). Second, the notice contains the date on which the contracting agency's response to the protest, the agency report, is due. The notice warns that GAO will assume that the protester receives the report on that date and may dismiss the protest if the protester's written comments in response to the report are not received by GAO within 10 days of that date. Third, the notice contains the date by which a written decision will be issued by GAO.
Finally, the acknowledgment notice identifies the GAO attorney or the GAO contact person handling the protest and that individual's telephone number. That individual is the GAO employee who should generally be contacted with any procedural questions about the protest. Inquiries about the status of the case may be directed to GAO's bid protest status line at (202) 512-5436. This telephone number and the previously referenced official fax number also appear on the notice.
As a general rule, GAO will dismiss a protest that fails to set forth a detailed statement of the legal and factual grounds of protest or that fails to clearly state legally sufficient grounds of protest. 4 C.F.R. § 21.5(f), citing 4 C.F.R. § 21.1(c)(4) and 4 C.F.R. § 21.1(f), respectively.
Once the protest is received, the contracting agency and/or an intervenor may request that GAO summarily dismiss the protest or some of its grounds. 4 C.F.R. § 21.3(b). Where summary dismissal may be appropriate, the request for dismissal should be made as soon as practicable after the protest is filed. Id. The request should be in writing and sent to all parties. Unless it is clear that dismissal is appropriate, GAO will generally permit the protester to file a written response to the dismissal request. GAO will promptly address the dismissal request. If GAO grants the request, either in whole or in part, GAO will not require the agency to prepare a report in response to the protest or in response to those grounds of protest which were dismissed.
Only individuals who apply to GAO, and whose applications are approved by GAO, will be permitted access to protected information. Those individuals must be attorneys or consultants retained by attorneys; the attorneys may be outside counsel or in-house counsel. The applicants need to show that they are not involved in competitive decisionmaking for any company that could gain a competitive advantage from access to protected information and that there will be no significant risk of inadvertent disclosure of such information. 4 C.F.R. § 21.4(c). GAO has issued a number of decisions which address matters related to the admission of applicants under a protective order. Individuals permitted access to protected information are not allowed to disclose that information to others. This means, for example, that a protester's attorney permitted access to protected information under a protective order is prohibited from revealing such information to the client. GAO may impose sanctions on any individual who violates the terms of a protective order. 4 C.F.R. § 21.4(d).
Because the information released under a protective order is not GAO's, but rather the contracting agency's or one of the private parties, GAO relies on these parties to carefully review applications for access to material under a protective order (and to call to GAO's attention any possible violation of a protective order). If no party objects to an individual's application, GAO will generally admit the applicant under the protective order. It is important that any objections to an individual's application be promptly raised. By the end of the second day after receiving the application, the objecting party must advise GAO and the other parties that there is an objection to the applicant's admission. 4 C.F.R. § 21.4(c). The GAO attorney will generally permit the objecting party to submit the specific objection, in writing, the next day. GAO will promptly address any objections. Even after the period for filing an objection has passed, GAO may withhold its ruling on an application (or may revoke an admission) if information comes to light which indicates that the applicant does not meet the criteria for admission.
A sample protective order and sample applications for access to material under a protective order for outside counsel, in-house counsel, and consultants retained by counsel are reproduced in the appendixes to this booklet. These sample documents, which are provided in this booklet for informational purposes only, have recently been revised. More specifically, under paragraph 1 of the protective order, a protective order issued for an initial protest is now automatically extended by the terms of the order to cover all proceedings associated with the initial protest, including supplemental/amended protests, requests for reconsideration, and claims for costs. Under paragraph 7 of the protective order, GAO expressly authorizes a party admitted under a protective order to retain a single copy of a protected decision or letter issued by GAO, subject indefinitely to the terms of the order (except those terms regarding the return or destruction of protected material). Finally, in paragraph 7 of the application for access to material under a protective order for both outside counsel and in-house counsel, GAO requires applicants to disclose those instances within the last 5 years (as opposed to in perpetuity) when they have been denied admission to a protective order, or had admission revoked, or been found to have violated a protective order issued by GAO or by an administrative or judicial tribunal. (No substantive revisions were made to the application for access to material under a protective order for consultant.) The sample documents also reflect minor language revisions and are subject to further change.
Any violation of the terms of a protective order may result in the imposition of such sanctions as GAO deems appropriate, including but not limited to referral of the violation to appropriate bar associations or other disciplinary bodies, and restricting the individual's practice before GAO. 4 C.F.R. § 21.4(d).
GAO encourages agencies to voluntarily release to the parties documents which are relevant to the protest prior to the filing of the agency report. Documents provided to the parties prior to the filing of the agency report or documents which are otherwise made available to the parties, for example, by allowing the parties to review documents on site at the agency prior to the filing of the report, need not be produced in the copy of the report provided to the parties. 4 C.F.R. § 21.3(c).
In addition, so that GAO may resolve any document disputes prior to the filing of the agency report, GAO requires that at least 5 days prior to the filing of the report, in cases in which the protester has requested in its protest or shortly thereafter specific documents material to the disposition of the protest, that the agency prepare a list of those documents, or portions of documents, which it has previously released or intends to produce in its report, and of the documents which it intends to withhold and the reasons for the proposed withholding. Id. The list must be provided to all parties and to GAO. Objections to the scope of the agency's proposed disclosure or nondisclosure of documents must be filed with GAO and all other parties within 2 days of receiving the list. Id.
The agency may omit documents, or portions of documents, from the copy of the report provided to the parties if the omitted information is protected and a party receiving the report is not represented by counsel admitted under a protective order. 4 C.F.R. § 21.3(e). Where the protester is proceeding without counsel admitted under a protective order and documents are withheld, it is important that the agency provide the protester with information sufficient to clearly inform the protester of the agency's position, so that the protester may comment intelligently on the report.
Occasionally, the agency may be aware of the existence of relevant documents that only the protester possesses. In appropriate cases, the agency may request that the protester produce those documents. 4 C.F.R. § 21.3(d). If GAO agrees that the documents are relevant, it may ask the protester to provide a copy of the documents to GAO and the other parties, subject to the terms of any protective order.
If the contracting agency produces withheld documents at the direction of GAO after the report has been submitted, comments will be due within the original 10-day comment filing period, unless GAO extends this period. 4 C.F.R. § 21.3(h).
Failure of the protester to file comments, to request in writing that the case be decided on the existing written record, or to request an extension of time within the 10-day period will result in dismissal of the protest. 4 C.F.R. § 21.3(i).
Because hearings increase the costs and burdens of protests, GAO holds hearings only when necessary. A request for a hearing should explain why a hearing is necessary to resolve the protest, and point out, for example, factual and legal questions that GAO must consider in order to decide the protest. 4 C.F.R. § 21.1(d)(3), 21.7(a). GAO has issued a number of decisions which discuss reasons for holding hearings. While the regulations do not establish a deadline for requesting a hearing, such a request should be submitted as early as possible in the protest process in order to avoid unnecessary delays and disruptions. Parties should also be aware that GAO may identify shortly after a protest is filed whether the case is one in which a hearing appears likely to be appropriate. On the other hand, the appropriateness of a hearing often is not clear until after the contracting agency has filed its report and, in many cases, is not clear until after the protester has submitted its comments on the report. GAO may decide at these later times that a hearing is necessary to resolve the protest.
In cases where GAO decides to hold a hearing, it will generally conduct a pre-hearing conference with all parties. 4 C.F.R. § 21.7(b). The purpose of that conference is to review the scope of the hearing, to identify the appropriate witnesses and their availability, to establish the date and location of the hearing, and to discuss other logistical matters. In cases where GAO determines that only some of the protest issues require a hearing, it will generally limit the hearing to those issues. The GAO attorney handling the protest will conduct both the pre-hearing conference and the hearing. The format of hearings varies from formal (direct- and cross-examination of witnesses conducted by counsel for the parties) to informal (a discussion of the issues by counsel and others). For this reason, the pre-hearing conference is usually the best opportunity to clarify how the GAO attorney expects to conduct the hearing, as well as to raise any other questions about the hearing.
A GAO hearing is, in principle, open to the public. In practice, however, protest hearings often involve protected information. As a result, most hearings are closed except to agency personnel and those individuals admitted under the protective order. 4 C.F.R. § 21.7(d).
At least 1 day prior to the hearing, parties must advise GAO of those individuals expected to attend the hearing so that these individuals may gain access to the GAO building where the hearing room is located.
The GAO hearing room is equipped with video cameras and microphones which automatically record the proceedings. That system produces a video transcript, a copy of which is provided to the parties at no charge at the conclusion of the hearing. In addition, parties may wish to have a court reporter attend the hearing to prepare a written transcript. A request to that effect should be presented before the day of the hearing to the GAO attorney handling the protest. Such a request will usually be granted as long as all parties have access to a written transcript.
If a hearing is held, all parties, including the agency, will be permitted to file written comments on the hearing. 4 C.F.R. § 21.7(g). Those comments are due 5 days after the hearing ends, unless GAO sets a different date. Id. If GAO decides to hold a hearing before the receipt of comments on the agency report, GAO may direct the private parties not to submit separate comments on the report, but to consolidate their views on the report with their comments on the hearing. Id.
Under the express option schedule, the agency report is due within 20 days after the contracting agency receives notice from GAO that the express option will be used. 4 C.F.R. § 21.10(d)(1). Comments on the report generally are due within 5 days after receipt of the report. 4 C.F.R. § 21.10(d)(2). If a hearing is needed, GAO generally will not request separate comments on the agency report; rather, GAO will require that consolidated comments on the report and hearing be filed within 5 days after the hearing ends, unless GAO sets a different date. 4 C.F.R. § 21.10(d)(3). Under the express option schedule, GAO's decision will be issued not later than 65 days after the protest is filed. 4 C.F.R. § 21.9(b), 21.10(b). GAO may decide at any time that the express option schedule is no longer appropriate, and may set a different schedule for the protest, which will not exceed the time frame (100 days) for deciding a non-express option case.
If the protest is sustained, GAO will recommend that the protester be reimbursed for the costs of filing and pursuing the protest, including attorneys' fees and consultant and expert witness fees. Occasionally, where there is no other relief available, GAO will recommend that the protester also be reimbursed for the costs of preparing its bid or proposal. 4 C.F.R. § 21.8(d).
Where GAO has recommended reimbursement of costs, the protester must submit a detailed claim for costs, certifying the time expended and costs incurred in pursuing the protest, directly to the contracting agency within 60 days after receipt of GAO's recommendation that the agency pay these costs. 4 C.F.R. § 21.8(f)(1). A claim must be supported by adequate documentation. GAO expects the protester and the agency to determine the exact amount to be paid. If the protester and the agency cannot agree, GAO may, upon request of the protester, decide the matter. 4 C.F.R. § 21.8(f)(2). Protesters should keep in mind that, except in very limited circumstances, the costs for attorneys' fees may not exceed $150 per hour. GAO never recommends that agencies pay lost profits or other common-law damages.
When GAO recommends corrective action, the Competition in Contracting Act of 1984 requires the agencies affected to report to the Comptroller General whenever they have not fully implemented the recommendation within 60 days. The Comptroller General, in turn, annually reports to the Congress each instance where recommendations were not fully implemented.
GAO also will not review a protest where the issues involved have already been decided on the merits by a court. Id.
GAO must receive the request for reconsideration within 10 days after the basis of reconsideration is known or should have been known, whichever is earlier. 4 C.F.R. § 21.14(b). The request must identify the alleged factual and/or legal errors in the decision. 4 C.F.R. § 21.14(a). GAO will not consider a request which merely repeats the party's views already expressed in the protest; a request which simply expresses disagreement with the decision; or a request which provides information or raises an argument that could have been, but was not, provided or raised during the protest.
Contents, Previous, Next
(b) Intervenor means an awardee if the award has been made or, if no award has been made, all bidders or offerors who appear to have a substantial prospect of receiving an award if the protest is denied.
(c) Federal agency means any executive department or independent establishment in the executive branch, including any wholly owned government corporation, and any establishment in the legislative or judicial branch, except the Senate, the House of Representatives, and the Architect of the Capitol and any activities under his direction.
(d) Contracting agency means a Federal agency which has awarded or proposes to award a contract under a protested procurement.
(e) Days are calendar days. In computing any period of time described in Subchapter V, Chapter 35 of Title 31, United States Code, including those described in this part, the day from which the period begins to run is not counted, and when the last day of the period is a Saturday, Sunday, or Federal holiday, the period extends to the next day that is not a Saturday, Sunday, or Federal holiday. Similarly, when the General Accounting Office (GAO), or another Federal agency where a submission is due, is closed for all or part of the last day, the period extends to the next day on which the agency is open.
(f) Adverse agency action is any action or inaction by a contracting agency which is prejudicial to the position taken in a protest filed with the agency, including a decision on the merits of a protest; the opening of bids or receipt of proposals, the award of a contract, or the rejection of a bid despite a pending protest; or contracting agency acquiescence in continued and substantial contract performance.
(g) A document is filed on a particular day when it is received by GAO by 5:30 p.m., eastern time, on that day. A document may be filed by hand delivery, mail, or commercial carrier; parties wishing to file a document by facsimile transmission or other electronic means must ensure that the necessary equipment is operational at GAO's Procurement Law Control Group.
(b) Protests must be in writing and addressed as follows: General Counsel, General Accounting Office, 441 G Street, NW., Washington, DC 20548, Attention: Procurement Law Control Group.
(c) A protest filed with GAO shall:
(1) Include the name, address, and telephone and facsimile numbers of the protester,
(2) Be signed by the protester or its representative,
(3) Identify the contracting agency and the solicitation and/or contract number,
(4) Set forth a detailed statement of the legal and factual grounds of protest including copies of relevant documents,
(5) Set forth all information establishing that the protester is an interested party for the purpose of filing a protest,
(6) Set forth all information establishing the timeliness of the protest,
(7) Specifically request a ruling by the Comptroller General of the United States, and
(8) State the form of relief requested.
(d) In addition, a protest filed with GAO may:
(1) Request a protective order,
(2) Request specific documents, explaining the relevancy of the documents to the protest grounds, and
(3) Request a hearing, explaining the reasons that a hearing is needed to resolve the protest.
(e) The protester shall furnish a complete copy of the protest, including all attachments, to the individual or location designated by the contracting agency in the solicitation for receipt of protests, or if there is no designation, to the contracting officer. The designated individual or location (or, if applicable, the contracting officer) must receive a complete copy of the protest and all attachments not later than 1 day after the protest is filed with GAO. The protest document must indicate that a complete copy of the protest and all attachments are being furnished within 1 day to the appropriate individual or location.
(f) No formal briefs or other technical forms of pleading or motion are required. Protest submissions should be concise and logically arranged, and should clearly state legally sufficient grounds of protest. Protests of different procurements should be separately filed.
(g) Unless precluded by law, GAO will not withhold material submitted by a protester from any party outside the government. If the protester believes that the protest contains information which should be withheld, a statement advising of this fact must be on the front page of the submission. This information must be identified wherever it appears, and the protester must file a redacted copy of the protest which omits the information with GAO and the agency within 1 day after the filing of its protest with GAO.
(h) Parties who intend to file documents containing classified information should notify GAO in advance to obtain advice regarding procedures for filing and handling the information.
(i) A protest may be dismissed for failure to comply with any of the requirements of this section, except for the items in paragraph (d) of this section. In addition, a protest shall not be dismissed for failure to comply with paragraph (e) of this section where the contracting officer has actual knowledge of the basis of protest, or the agency, in the preparation of its report, was not prejudiced by the protester's noncompliance.
(2) Protests other than those covered by paragraph (a)(1) of this section shall be filed not later than 10 days after the basis of protest is known or should have been known (whichever is earlier), with the exception of protests challenging a procurement conducted on the basis of competitive proposals under which a debriefing is requested and, when requested, is required. In such cases, with respect to any protest basis which is known or should have been known either before or as a result of the debriefing, the initial protest shall not be filed before the debriefing date offered to the protester, but shall be filed not later than 10 days after the date on which the debriefing is held.
(3) If a timely agency-level protest was previously filed, any subsequent protest to GAO filed within 10 days of actual or constructive knowledge of initial adverse agency action will be considered, provided the agency-level protest was filed in accordance with paragraphs (a)(1) and (a)(2) of this section, unless the contracting agency imposes a more stringent time for filing, in which case the agency's time for filing will control. In cases where an alleged impropriety in a solicitation is timely protested to a contracting agency, any subsequent protest to GAO will be considered timely if filed within the 10-day period provided by this paragraph, even if filed after bid opening or the closing time for receipt of proposals.
(b) Protests untimely on their face may be dismissed. A protester shall include in its protest all information establishing the timeliness of the protest; a protester will not be permitted to introduce for the first time in a request for reconsideration information necessary to establish that the protest was timely.
(c) GAO, for good cause shown, or where it determines that a protest raises issues significant to the procurement system, may consider an untimely protest.
(b) A contracting agency or intervenor which believes that the protest or specific protest allegations should be dismissed before submission of an agency report should file a request for dismissal as soon as practicable.
(c) The contracting agency shall file a report on the protest with GAO within 30 days after the telephone notice of the protest from GAO. The report provided to the parties need not contain documents which the agency has previously furnished or otherwise made available to the parties in response to the protest. At least 5 days prior to the filing of the report, in cases in which the protester has filed a request for specific documents, the agency shall provide to all parties and GAO a list of those documents, or portions of documents, which the agency has released to the protester or intends to produce in its report, and of the documents which the agency intends to withhold from the protester and the reasons for the proposed withholding. Any objection to the scope of the agency's proposed disclosure or nondisclosure of documents must be filed with GAO and the other parties within 2 days of receipt of this list.
(d) The report shall include the contracting officer's statement of the relevant facts, including a best estimate of the contract value, a memorandum of law, and a list and a copy of all relevant documents, or portions of documents, not previously produced, including, as appropriate: the protest; the bid or proposal submitted by the protester; the bid or proposal of the firm which is being considered for award, or whose bid or proposal is being protested; all evaluation documents; the solicitation, including the specifications; the abstract of bids or offers; and any other relevant documents. In appropriate cases, the contracting agency may request that the protester produce relevant documents, or portions of documents, that are not in the agency's possession.
(e) Subject to any protective order issued in the protest pursuant to § 21.4, the contracting agency shall simultaneously furnish a copy of the report to the protester and any intervenors. The copy of the report filed with GAO shall list the parties who have been furnished copies of the report. Where a protester does not have counsel admitted to a protective order and documents are withheld from the protester in accordance with this part, the agency shall provide documents adequate to inform the protester of the basis of the agency's position.
(f) The contracting agency may request an extension of time for the submission of the list of documents to be provided by the agency pursuant to § 21.3(c) or for the submission of the agency report. Extensions will be granted on a case-by-case basis.
(g) The protester may request additional documents after receipt of the agency report when their existence or relevance first becomes evident. Except when authorized by GAO, any request for additional documents must be filed with GAO and the contracting agency not later than 2 days after their existence or relevance is known or should have been known, whichever is earlier. The contracting agency shall provide the requested documents, or portions of documents, and a list to GAO and the other parties within 2 days or explain why it is not required to produce the documents.
(h) Upon the request of a party, GAO will decide whether the contracting agency must provide any withheld documents, or portions of documents, and whether this should be done under a protective order. When withheld documents are provided, the protester's comments on the agency report shall be filed within the original comment filing period unless GAO determines that an extension is appropriate.
(i) Comments on the agency report shall be filed with GAO within 10 days after receipt of the report, with a copy provided to the contracting agency and other participating parties. The protest shall be dismissed unless the protester files comments or a written statement requesting that the case be decided on the existing record, or requests an extension of time within the 10-day period. Unless otherwise advised by the protester, GAO will assume the protester received the agency report by the due date specified in the acknowledgment of protest furnished by GAO. Upon a showing that the specific circumstances of a protest require a period longer than 10 days for the submission of comments, GAO will set a new date for the submission of comments. Extensions will be granted on a case-by-case basis.
(j) GAO may request or permit the submission of additional statements by the parties and by other parties not participating in the protest as may be necessary for the fair resolution of the protest. The agency and other parties shall not submit any additional statements unless the statements are specifically requested by GAO or submitted after permission has been granted by GAO.
(b) If no protective order has been issued, the agency may withhold from the parties those portions of its report which would ordinarily be subject to a protective order. GAO will review in camera all information not released to the parties.
(c) After a protective order has been issued, counsel or consultants retained by counsel appearing on behalf of a party may apply for admission under the order by submitting an application to GAO, with copies furnished simultaneously to all parties. The application shall establish that the applicant is not involved in competitive decision-making for any firm that could gain a competitive advantage from access to the protected information and that there will be no significant risk of inadvertent disclosure of protected information. Objections to an applicant's admission shall be raised within 2 days after receipt of the application, although GAO may consider objections raised after that time.
(d) Any violation of the terms of a protective order may result in the imposition of such sanctions as GAO deems appropriate, including referral to appropriate bar associations or other disciplinary bodies and restricting the individual's practice before GAO.
(a) Contract administration. The administration of an existing contract is within the discretion of the contracting agency. Disputes between a contractor and the agency are resolved pursuant to the disputes clause of the contract and the Contract Disputes Act of 1978. 41 U.S.C. 601-613.
(b) Small Business Administration issues.
(1) Small
business size standards and standard industrial
classification. Challenges of established size standards or
the size status of particular firms, and challenges of the
selected standard industrial classification may be reviewed
solely by the Small Business Administration. 15 U.S.C.
637(b)(6).
(2) Small Business Certificate of Competency Program. Any referral made to the Small Business Administration pursuant to sec. 8(b)(7) of the Small Business Act, or any issuance of, or refusal to issue, a certificate of competency under that section will not be reviewed by GAO absent a showing of possible bad faith on the part of government officials or a failure to consider vital information bearing on the firm's responsibility. 15 U.S.C. 637(b)(7).
(3) Procurements under sec. 8(a) of the Small Business Act. Under that section, since contracts are entered into with the Small Business Administration at the contracting officer's discretion and on such terms as are agreed upon by the procuring agency and the Small Business Administration, the decision to place or not to place a procurement under the 8(a) program is not subject to review absent a showing of possible bad faith on the part of government officials or that regulations may have been violated. 15 U.S.C. 637(a).
(c) Affirmative determination of responsibility by the contracting officer. Because the determination that a bidder or offeror is capable of performing a contract is based in large measure on subjective judgments which generally are not readily susceptible of reasoned review, an affirmative determination of responsibility will not be reviewed absent a showing of possible bad faith on the part of government officials or that definitive responsibility criteria in the solicitation were not met.
(d) Procurement integrity. For any Federal procurement, GAO
will not review an alleged violation of subsections (a),
(b), (c), or (d) of sec. 27 of the Office of Federal
Procurement Policy Act,
41 U.S.C. 423, as amended by
sec. 4304 of the National Defense Authorization Act for
Fiscal Year 1996,
Pub. L. 104-106, 110 Stat. 186,
February 10, 1996, where the protester failed to report the
information it believed constituted evidence of the offense
to the Federal agency responsible for the procurement
within 14 days after the protester first discovered the
possible violation. The provision in paragraph (d) of
§ 21.5 will apply not later than January 1, 1997.
(e) Protests not filed either in GAO or the contracting agency within the time limits set forth in § 21.2.
(f) Protests which lack a detailed statement of the legal and factual grounds of protest as required by § 21.1(c)(4), or which fail to clearly state legally sufficient grounds of protest as required by § 21.1(f).
(g) Procurements by agencies other than Federal agencies as
defined by sec. 3 of the Federal Property and
Administrative Services Act of 1949, 40 U.S.C. 472.
Protests of procurements or proposed procurements by
agencies such as the U.S. Postal Service, the Federal
Deposit Insurance Corporation, and nonappropriated fund
activities are beyond GAO's bid protest jurisdiction as
established in
31 U.S.C. 3551-3556.
(h) Subcontract protests. GAO will not consider a protest of the award or proposed award of a subcontract except where the agency awarding the prime contract has requested in writing that subcontract protests be decided pursuant to § 21.13.
(b) Prior to the hearing, GAO may hold a pre-hearing conference to discuss and resolve matters such as the procedures to be followed, the issues to be considered, and the witnesses who will testify.
(c) Hearings generally will be conducted as soon as practicable after receipt by the parties of the agency report and relevant documents. Although hearings ordinarily will be conducted at GAO in Washington, DC, hearings may, at the discretion of GAO, be conducted at other locations, or by telephone.
(d) All parties participating in the protest shall be invited to attend the hearing. Others may be permitted to attend as observers and may participate as allowed by GAO's hearing official. In order to prevent the improper disclosure of protected information at the hearing, GAO's hearing official may restrict attendance during all or part of the proceeding.
(e) Hearings shall normally be recorded and/or transcribed. If a recording and/or transcript is made, any party may obtain copies at its own expense.
(f) If a witness whose attendance has been requested by GAO fails to attend the hearing or fails to answer a relevant question, GAO may draw an inference unfavorable to the party for whom the witness would have testified.
(g) If a hearing is held, no separate comments on the agency report should be submitted unless specifically requested by GAO. Each party shall file with GAO, within 5 days after the hearing was held or as specified by GAO, a single document expressing any comments on both the hearing and agency report, with copies furnished to the other parties. By the due date, if the protester has not filed comments or a written statement requesting that the case be decided on the existing record, GAO shall dismiss the protest.
(h) In post-hearing comments, the parties should reference all testimony and admissions in the hearing record that they consider relevant, providing specific citations to the testimony and admissions referenced.
(1) Refrain from exercising options under the contract;
(2) Terminate the contract;
(3) Recompete the contract;
(4) Issue a new solicitation;
(5) Award a contract consistent with statute and regulation; or
(6) Such other recommendation(s) as GAO determines necessary to promote compliance.
(b) In determining the appropriate recommendation(s), GAO shall, except as specified in paragraph (c) of this section, consider all circumstances surrounding the procurement or proposed procurement including the seriousness of the procurement deficiency, the degree of prejudice to other parties or to the integrity of the competitive procurement system, the good faith of the parties, the extent of performance, the cost to the government, the urgency of the procurement, and the impact of the recommendation(s) on the contracting agency's mission.
(c) If the head of the procuring activity determines that performance of the contract notwithstanding a pending protest is in the government's best interest, GAO shall make its recommendation(s) under paragraph (a) of this section without regard to any cost or disruption from terminating, recompeting, or reawarding the contract.
(d) If GAO determines that a solicitation, proposed award, or award does not comply with statute or regulation, it may recommend that the contracting agency pay the protester the costs of:
(1) Filing and pursuing the protest, including attorneys' fees and consultant and expert witness fees; and
(2) Bid and proposal preparation.
(e) If the contracting agency decides to take corrective action in response to a protest, GAO may recommend that the agency pay the protester the costs of filing and pursuing the protest, including attorneys' fees and consultant and expert witness fees. The protester shall file any request that GAO recommend that costs be paid within 15 days after being advised that the contracting agency has decided to take corrective action. The protester shall furnish a copy of its request to the contracting agency, which may file a response within 15 days after receipt of the request, with a copy furnished to the protester.
(f)(1) If GAO recommends that the contracting agency pay the protester the costs of filing and pursuing the protest and/or of bid or proposal preparation, the protester and the agency shall attempt to reach agreement on the amount of costs. The protester shall file its claim for costs, detailing and certifying the time expended and costs incurred, with the contracting agency within 60 days after receipt of GAO's recommendation that the agency pay the protester its costs. Failure to file the claim within that time may result in forfeiture of the protester's right to recover its costs.
(2) The contracting agency shall issue a decision on the claim for costs as soon as practicable after the claim is filed. If the protester and the contracting agency cannot reach agreement within a reasonable time, GAO may, upon request of the protester, recommend the amount of costs the agency should pay in accordance with 31 U.S.C. 3554(c). In such cases, GAO may also recommend that the contracting agency pay the protester the costs of pursuing the claim for costs before GAO.
(3) The contracting agency shall notify GAO within 60 days after GAO recommends the amount of costs the agency should pay the protester of the action taken by the agency in response to the recommendation.
(b) In protests where GAO uses the express option procedures in § 21.10, GAO shall issue a decision on a protest within 65 days after it is filed.
(c) GAO, to the maximum extent practicable, shall resolve a timely supplemental protest adding one or more new grounds to an existing protest, or a timely amended protest, within the time limit established in paragraph (a) of this section for decision on the initial protest. If a supplemental or an amended protest cannot be resolved within that time limit, GAO may resolve the supplemental or amended protest using the express option procedures in § 21.10.
(b) The express option will be adopted at the discretion of GAO and only in those cases suitable for resolution within 65 days.
(c) Requests for the express option shall be in writing and received in GAO not later than 5 days after the protest or supplemental/amended protest is filed. GAO will promptly notify the parties whether the case will be handled using the express option.
(d) When the express option is used, the following schedule applies instead of those deadlines in § 21.3 and § 21.7:
(1) The contracting agency shall file a complete report with GAO and the parties within 20 days after it receives notice from GAO that the express option will be used.
(2) Comments on the agency report shall be filed with GAO and the other parties within 5 days after receipt of the report.
(3) If a hearing is held, no separate comments on the agency report under paragraph (d)(2) of this section should be submitted unless specifically requested by GAO. Consolidated comments on the agency report and hearing shall be filed within 5 days after the hearing was held or as specified by GAO.
(4) Where circumstances demonstrate that a case is no longer suitable for resolution using the express option, GAO shall establish a new schedule for submissions by the parties.
(e) GAO may use flexible alternative procedures to promptly and fairly resolve a protest, including establishing an accelerated schedule and/or issuing a summary decision.
(f) GAO may conduct status and other conferences by telephone or in person with all parties participating in a protest to promote the expeditious development and resolution of the protest.
(b) GAO will dismiss any protest where the matter involved is the subject of litigation before a court of competent jurisdiction, or where the matter involved has been decided on the merits by a court of competent jurisdiction. GAO may, at the request of a court, issue an advisory opinion on a bid protest issue that is before the court. In these cases, unless a different schedule is established, the times provided in this part for filing the agency report (§ 21.3(c)), filing comments on the report (§ 21.3(i)), holding a hearing and filing comments (§ 21.7), and issuing a decision (§ 21.9) shall apply.
(b) Decisions are available from GAO by electronic means.
(b) The provisions of this part shall apply to nonstatutory protests except for the provision of § 21.8(d) pertaining to recommendations for the payment of costs. The provision for the withholding of award and the suspension of contract performance, 31 U.S.C. 3553(c) and (d), also does not apply to nonstatutory protests.
(b) A request for reconsideration of a bid protest decision shall be filed, with copies to the parties who participated in the protest, not later than 10 days after the basis for reconsideration is known or should have been known, whichever is earlier.
(c) GAO will summarily dismiss any request for reconsideration that fails to state a valid basis for reconsideration or is untimely. The filing of a request for reconsideration does not require the withholding of award and the suspension of contract performance under 31 U.S.C. 3553(c) and (d).
Contents, Previous, Next
(See image in printed edition.)Appendix I
(See image in printed edition.)
(See image in printed edition.)
(See image in printed edition.)
Contents, Previous, Next
(See image in printed edition.)Appendix II
(See image in printed edition.)
(See image in printed edition.)
(See image in printed edition.)
(See image in printed edition.)
(See image in printed edition.)
(See image in printed edition.)
(See image in printed edition.)