Reports & Testimonies

  • GAO’s recommendations database contains report recommendations that still need to be addressed.

    GAO’s recommendations help congressional and agency leaders prepare for appropriations and oversight activities, as well as help improve government operations. Recommendations remain open until they are designated as Closed-implemented or Closed-not implemented. You can explore open recommendations by searching or browsing.

    GAO's priority recommendations are those that we believe warrant priority attention. We sent letters to the heads of key departments and agencies, urging them to continue focusing on these issues. These recommendations are labeled as such. You can find priority recommendations by searching or browsing our open recommendations below, or through our mobile app.

  • Browse Open Recommendations

    Explore priority recommendations by subject terms or browse by federal agency

    Search Open Recommendations

    Search for a specific priority recommendation by word or phrase



  • Governing on the go?

    Our Priorities for Policy Makers app makes it easier for leaders to search our recommendations on the go.

    See the November 10th Press Release


  • Have a Question about a Recommendation?

    • For questions about a specific recommendation, contact the person or office listed with the recommendation.
    • For general information about recommendations, contact GAO's Audit Policy and Quality Assurance office at (202) 512-6100 or apqa@gao.gov.
  • « Back to Results List Sort by   

    Results:

    Subject Term: Bombs

    2 publications with a total of 5 open recommendations
    Director: Pendleton, John H
    Phone: 202) 512-3489

    2 open recommendations
    Recommendation: To assist DOD and DOE in synchronizing plans for modernizing the nuclear weapons enterprise and for assessing the feasibility of the interoperable warhead concept, and to ensure that DOD and NNSA are able to consider the possibilities of potentially designing and developing an interoperable warhead as directed by the Nuclear Weapons Council during the W78/88-1 life-extension program, the Secretary of Defense should direct the Secretary of the Navy to identify the long-term resources needed to implement the W78/88-1 life-extension program once the warhead feasibility study is completed, should the Nuclear Weapons Council approve of an interoperable warhead design.

    Agency: Department of Defense
    Status: Open

    Comments: DOD concurred with the recommendation. In September 2014, agency officials stated that the Nuclear Weapons Council formally delayed the W78/88-1 Life Extension Program first production unit 5 years to Fiscal Year 2030. As a result, officials stated that the warhead feasibility study has been delayed. The recommendation remains open. As of September 2017, the status of this recommendation has not changed.
    Recommendation: To assist DOD and DOE in synchronizing plans for modernizing the nuclear weapons enterprise and for assessing the feasibility of the interoperable warhead concept, and to ensure that the services are able to support the consideration of interoperable warhead concepts during future life-extension programs, the Secretary of Defense should issue or revise existing guidance to require the services to align their programs and resources before beginning concept or feasibility studies jointly with another service.

    Agency: Department of Defense
    Status: Open

    Comments: DOD concurred with the recommendation. In December 2015, DOD and DOE published the revised Guideline for the Phase 6.X Process and is in the process of updating the DOD implementing instructions. In August 2016, DOD officials told us that the updated instruction will include a provision to require the services to align their programs and resources before beginning concept or feasibility studies jointly with another service. Officials expect the revised instruction to be finalized and published in mid-2017. As of September 2017, the updated DOD manual (DODM 5030.55) is undergoing final coordination within the department. This recommendation remains open pending the approval and issuance of the revised instruction.
    Director: Trimble, David
    Phone: (202) 512-3000

    3 open recommendations
    Recommendation: To improve the management of the stockpile life extension program, the Administrator of NNSA should direct the Deputy Administrator for Defense Programs to develop a realistic schedule for the W76 warhead and future life extension programs that allows NNSA to (1) address technical challenges while meeting all military requirements and (2) build in time for unexpected technical challenges that may delay the program.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: In past and ongoing work, GAO has identified areas where NNSA's modernization plans may not align with planned funding requests over the Future Years Nuclear Security Plan (FYNSP) and post-FYNSP periods. Based on the FY 2014 Stockpile Stewardship and Management Plan (SSMP), (GAO-14-45) NNSA plans to work on five LEPs or major alterations through 2038. The FY 2014 SSMP states that the LEP workload represents a resource and production throughput challenge that requires improvements in LEP planning and execution. GAO's analysis indicates there is limited contingency time built into the LEP schedules, all of which are technically ambitious. Any delays in schedules could lead to an increase in program costs or a reduction in the number built for any of the LEPs, both of which have occurred in prior and ongoing LEPs. While NNSA has acknowledged issues and identified some steps to improve the LEP process, this recommendation will remain open and unimplemented until NNSA demonstrates successful LEP and refurbishment execution. We recently reconfirmed this finding in GAO-17-341 where we found the following: In some cases, NNSA's fiscal year 2017 nuclear security budget materials do not align with the agency's modernization plans, both within the 5-year Future-Years Nuclear Security Program (FYNSP)for fiscal years 2017 through 2021 and beyond, raising concerns about the affordability of NNSA's planned portfolio of modernization programs.
    Recommendation: To improve the management of the stockpile life extension program, the Administrator of NNSA should direct the Deputy Administrator for Defense Programs to ensure that the program managers responsible for overseeing the construction of new facilities directly related to future life extension programs coordinate with the program managers of such future programs to avoid the types of delays and problems faced with the construction and operation of the Fogbank manufacturing facility for the W76 program.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: A number of Stockpile Stewardship and Management Plans (SSMP) states that the life extension program (LEP) workload represents a resource and production throughput challenge that requires improvements in LEP planning and execution. The officials elaborated that the main area that will be strained is pit production. The alternate plutonium strategy needs to be resourced fully to support the W78/88-1 LEP. Additionally, the officials said that the UPF transition needs to go as planned or there will be challenges in completing all of the planned LEPs. As such, this recommendation will remain open.
    Recommendation: To improve the management of the stockpile life extension program, the Administrator of NNSA should direct the Deputy Administrator for Defense Programs to ensure that program managers for the construction of new facilities for future life extensions base their schedule for the construction and start-up of a facility on the life extension program managers' needs identified in their risk mitigation strategies.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: NNSA has generally improved its management of construction projects, to include requirements setting, Analysis of Alternatives, independent cost estimates, etc. However, it is too soon to tell if these positive developments will help-or hinder-LEPs that are underway or are being conducted. Key uranium activities, to include construction and operating funds will not be complete until 2025; key plutonium activities are underway as well, but will not be complete until the late 2020s. As a result, this recommendation will need to remain open.