Reports & Testimonies

  • GAO’s recommendations database contains report recommendations that still need to be addressed.

    GAO’s recommendations help congressional and agency leaders prepare for appropriations and oversight activities, as well as help improve government operations. Recommendations remain open until they are designated as Closed-implemented or Closed-not implemented. You can explore open recommendations by searching or browsing.

    GAO's priority recommendations are those that we believe warrant priority attention. We sent letters to the heads of key departments and agencies, urging them to continue focusing on these issues. These recommendations are labeled as such. You can find priority recommendations by searching or browsing our open recommendations below, or through our mobile app.

  • Browse Open Recommendations

    Explore priority recommendations by subject terms or browse by federal agency

    Search Open Recommendations

    Search for a specific priority recommendation by word or phrase



  • Governing on the go?

    Our Priorities for Policy Makers app makes it easier for leaders to search our recommendations on the go.

    See the November 10th Press Release


  • Have a Question about a Recommendation?

    • For questions about a specific recommendation, contact the person or office listed with the recommendation.
    • For general information about recommendations, contact GAO's Audit Policy and Quality Assurance office at (202) 512-6100 or apqa@gao.gov.
  • « Back to Results List Sort by   

    Results:

    Subject Term: "Nuclear weapons testing"

    4 publications with a total of 6 open recommendations
    Director: David C. Trimble
    Phone: (202) 512-3841

    1 open recommendations
    Recommendation: To help NNSA put forth more credible modernization plans, the NNSA Administrator should include an assessment of the affordability of NNSA's portfolio of modernization programs in future versions of the Stockpile Stewardship and Management Plan--for example, by presenting options NNSA could consider to bring its estimates of modernization funding needs into alignment with potential future budgets, such as potentially deferring the start of or canceling specific modernization programs.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Director: David Trimble
    Phone: (202) 512-3841

    1 open recommendations
    Recommendation: To help ensure that NNSA can better inform long-term planning and management decision making as well as to ensure that the Enhanced Surveillance Program complements NNSA's other efforts to assess the nuclear weapons stockpile, the NNSA Administrator should develop a long-term strategy for the Enhanced Surveillance Program that incorporates outcome-oriented strategic goals, addresses management challenges and identifies resources needed to achieve these goals, and develops and uses performance measures to track progress in achieving these goals.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: Fiscal year 2018 budget submission data indicates some new activities but not yet mention a strategy change.
    Director: Aloise, Eugene E
    Phone: (202)512-6870

    1 open recommendations
    Recommendation: To allow Congress to better oversee management of the nuclear security enterprise and to improve NNSA's management information with respect to the base capabilities necessary to ensure nuclear weapons are safe, secure, and reliable, the Administrator of NNSA should, once the Stockpile Services work breakdown structure reflects a product or capability basis, use this work breakdown structure to develop product/capability cost estimates that adequately justify the congressional budget request for Stockpile Services.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: In process: NNSA has significantly improved its work breakdown structure for Stockpile Services. The work breakdown structure now reflects a product or capability basis to a much greater extent than it did previously. NNSA is continuing to work to develop cost estimates for these products and capabilities to adequately justify the congressional budget request for Stockpile Services. In 2014, the Senate Appropriations Committee's Energy and Water Development Subcommittee suggested changes to NNSA's budget structure to align it more closely with products and capabilities beginning with fiscal year 2016 appropriations. GAO will continue to monitor whether NNSA develops cost estimates for Stockpile Services products and capabilities that inform future years' budget requests and justifications.
    Director: Trimble, David
    Phone: (202) 512-3000

    3 open recommendations
    Recommendation: To improve the management of the stockpile life extension program, the Administrator of NNSA should direct the Deputy Administrator for Defense Programs to develop a realistic schedule for the W76 warhead and future life extension programs that allows NNSA to (1) address technical challenges while meeting all military requirements and (2) build in time for unexpected technical challenges that may delay the program.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: In past and ongoing work, GAO has identified areas where NNSA's modernization plans may not align with planned funding requests over the Future Years Nuclear Security Plan (FYNSP) and post-FYNSP periods. Based on the FY 2014 Stockpile Stewardship and Management Plan (SSMP), (GAO-14-45) NNSA plans to work on five LEPs or major alterations through 2038. The FY 2014 SSMP states that the LEP workload represents a resource and production throughput challenge that requires improvements in LEP planning and execution. GAO's analysis indicates there is limited contingency time built into the LEP schedules, all of which are technically ambitious. Any delays in schedules could lead to an increase in program costs or a reduction in the number built for any of the LEPs, both of which have occurred in prior and ongoing LEPs. While NNSA has acknowledged issues and identified some steps to improve the LEP process, this recommendation will remain open and unimplemented until NNSA demonstrates successful LEP and refurbishment execution. We recently reconfirmed this finding in GAO-17-341 where we found the following: In some cases, NNSA's fiscal year 2017 nuclear security budget materials do not align with the agency's modernization plans, both within the 5-year Future-Years Nuclear Security Program (FYNSP)for fiscal years 2017 through 2021 and beyond, raising concerns about the affordability of NNSA's planned portfolio of modernization programs.
    Recommendation: To improve the management of the stockpile life extension program, the Administrator of NNSA should direct the Deputy Administrator for Defense Programs to ensure that the program managers responsible for overseeing the construction of new facilities directly related to future life extension programs coordinate with the program managers of such future programs to avoid the types of delays and problems faced with the construction and operation of the Fogbank manufacturing facility for the W76 program.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: A number of Stockpile Stewardship and Management Plans (SSMP) states that the life extension program (LEP) workload represents a resource and production throughput challenge that requires improvements in LEP planning and execution. The officials elaborated that the main area that will be strained is pit production. The alternate plutonium strategy needs to be resourced fully to support the W78/88-1 LEP. Additionally, the officials said that the UPF transition needs to go as planned or there will be challenges in completing all of the planned LEPs. As such, this recommendation will remain open.
    Recommendation: To improve the management of the stockpile life extension program, the Administrator of NNSA should direct the Deputy Administrator for Defense Programs to ensure that program managers for the construction of new facilities for future life extensions base their schedule for the construction and start-up of a facility on the life extension program managers' needs identified in their risk mitigation strategies.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: NNSA has generally improved its management of construction projects, to include requirements setting, Analysis of Alternatives, independent cost estimates, etc. However, it is too soon to tell if these positive developments will help-or hinder-LEPs that are underway or are being conducted. Key uranium activities, to include construction and operating funds will not be complete until 2025; key plutonium activities are underway as well, but will not be complete until the late 2020s. As a result, this recommendation will need to remain open.