Reports & Testimonies

  • GAO’s recommendations database contains report recommendations that still need to be addressed.

    GAO’s recommendations help congressional and agency leaders prepare for appropriations and oversight activities, as well as help improve government operations. Recommendations remain open until they are designated as Closed-implemented or Closed-not implemented. You can explore open recommendations by searching or browsing.

    GAO's priority recommendations are those that we believe warrant priority attention. We sent letters to the heads of key departments and agencies, urging them to continue focusing on these issues. These recommendations are labeled as such. You can find priority recommendations by searching or browsing our open recommendations below, or through our mobile app.

  • Browse Open Recommendations

    Explore priority recommendations by subject terms or browse by federal agency

    Search Open Recommendations

    Search for a specific priority recommendation by word or phrase



  • Governing on the go?

    Our Priorities for Policy Makers app makes it easier for leaders to search our recommendations on the go.

    See the November 10th Press Release


  • Have a Question about a Recommendation?

    • For questions about a specific recommendation, contact the person or office listed with the recommendation.
    • For general information about recommendations, contact GAO's Audit Policy and Quality Assurance office at (202) 512-6100 or apqa@gao.gov.
  • « Back to Results List Sort by   

    Results:

    Subject Term: "Contract management"

    6 publications with a total of 18 open recommendations including 1 priority recommendation
    Director: Timothy J. DiNapoli
    Phone: (202) 512-4841

    7 open recommendations
    Recommendation: To enhance management attention to closing out contracts, the Secretary of Defense should develop a means for department-wide oversight into components' progress in meeting their goals on closing contracts and the status of contracts eligible for closeout. (Recommendation 1)

    Agency: Department of Defense
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To enhance management attention to closing out contracts, the Secretary of Health and Human Services should develop a means for department-wide oversight into components' progress in meeting their goals on closing contracts and the status of contracts eligible for closeout. (Recommendation 2)

    Agency: Department of Health and Human Services
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To enhance management attention to closing out contracts, the Secretary of Homeland Security should develop a means, either at the agency or the component level, to track where the contracts are in the closeout process, and establish goals and performance measures for closing contracts. (Recommendation 3)

    Agency: Department of Homeland Security
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To enhance management attention to closing out contracts, the Attorney General should direct the Senior Procurement Executive to ensure the development of a means to track data on the number and type of contracts eligible for closeout and where the contracts are in the closeout process, as well as a means to assess--at the agency or component level--progress by establishing goals and performance measures for closing contracts. (Recommendation 4)

    Agency: Department of Justice
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To enhance management attention to closing out contracts, the Secretary of State should develop a means at the agency level to track data on the entirety of the number and type of contracts eligible for closeout, where the contracts are in the closeout process, and establish goals and performance measures for closing contracts. (Recommendation 5)

    Agency: Department of State
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To manage its incurred cost inventory, the Director, DCAA should assess and implement options for reducing the length of time to begin incurred cost audit work and establish related performance measures. (Recommendation 6)

    Agency: Department of Defense: Defense Contract Audit Agency
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To manage its incurred cost inventory, the Director, DCAA should comprehensively assess the use and effect of multi-year audits on both DCAA and contractors and establish related performance measures. (Recommendation 7)

    Agency: Department of Defense: Defense Contract Audit Agency
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Director: Dave Wise
    Phone: (202) 512-5731

    3 open recommendations
    including 1 priority recommendation
    Recommendation: To improve VA's management of medical-facility construction projects and its accountability and to allow for more informed decision making by Congress and VA, the Secretary of Veterans Affairs should establish a mechanism to monitor the extent that major facilities projects are following guidelines on change orders' time frames and design changes.

    Agency: Department of Veterans Affairs
    Status: Open
    Priority recommendation

    Comments: GAO reviewed VA's 60 day letter and identified that VA did not address the part of GAO?s recommendation that is intended to help VA ensure that information on the reasons for change orders is collected to better inform managers whether guidelines regarding changes are being followed on construction projects. Consequently, in May 2017, GAO requested that VA provide documentation indicating that its current system collects the necessary information on change order processing timeframes for managers to ensure compliance with processing time guidelines. GAO will continue to monitor and update the status of this recommendation.
    Recommendation: To improve VA's management of medical-facility construction projects and its accountability and to allow for more informed decision making by Congress and VA, the Secretary of Veterans Affairs should develop an activation cost estimate for the Denver project that is reliable and conforms with best practices as described in the GAO Cost Estimating and Assessment Guide.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In its 60-day letter to Congress, VA said that it had analyzed its Activation Cost Budget Model (ACBM), which VA uses to estimate activation costs for new medical facilities, and its activation funding process, to improve cost forecasting and management of the activations process. VA said that it has modified ACBM to better support funding estimates and began using it in February 2017. GAO will continue to monitor and update the status of this recommendation.
    Recommendation: To improve VA's management of medical-facility construction projects and its accountability and to allow for more informed decision making by Congress and VA, the Secretary of Veterans Affairs should clarify Office of Construction and Facilities Management (CFM) policies to require that: (1) all projects have an integrated master schedule to ensure that the integrated master schedules include and link all construction and activation activities, and (2) the policies on integrated master schedule for projects managed by CFM and USACE are consistent.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In its 60-day letter to Congress, VA said that it is clarifying its policy and standard operation procedure on developing and maintaining an integrated master schedule. VA will also develop a standard operation procedure specifically for projects that the U.S. Army Corps of Engineers (USACE) is managing for VA. GAO will continue to monitor and update the status of this recommendation.
    Director: Anne-Marie Fennell
    Phone: (202) 512-3841

    3 open recommendations
    Recommendation: To help improve oversight of the concessions program, the Secretary of the Interior should direct the Director of the National Park Service to review the financial reporting process and make any necessary adjustments to help ensure timely and accurate reporting of data on annual financial reports.

    Agency: Department of the Interior: National Park Service
    Status: Open

    Comments: In its May 25, 2017 update letter, the Department of the Interior stated that the National Park Service will (1) review the current financial reporting process and take steps to improve the timeliness of concessioners' annual financial reports as outlined in their contracts, and (2) develop internal controls to ensure that concessioner data is accurate. The agency anticipates having these actions implemented by March 31, 2018.
    Recommendation: To help improve oversight of the concessions program, the Secretary of the Interior should direct the Director of the National Park Service to finalize guidance on maintenance and capital improvements and make it publicly available to concessioners.

    Agency: Department of the Interior: National Park Service
    Status: Open

    Comments: In its May 25, 2017 update letter, the Department of the Interior stated that the National Park Service will finalize the existing draft guidance on maintenance and capital improvements to clarify the funding sources available to concessioners for particular repairs and maintenance needs. The agency added that the finalized guidance will be made publicly available. The agency anticipates having this guidance finalized by November 30, 2017.
    Recommendation: To help improve oversight of the concessions program, the Secretary of the Interior should direct the Director of the National Park Service to develop performance goals with targets and timeframes in its commercial services strategic plan.

    Agency: Department of the Interior: National Park Service
    Status: Open

    Comments: In its May 25, 2017 update letter, the Department of the Interior stated that the National Park Service will review the commercial services program strategic plan and develop meaningful and measurable performance goals with timeframes. The agency anticipates having this implemented by June 30, 2018.
    Director: Michele Mackin
    Phone: (202) 512-4841

    1 open recommendations
    Recommendation: To ensure consistent implementation and documentation of actions relating to interagency agreements, the Secretary of Veterans Affairs should ensure that planned training on interagency agreements reaches the full range of program and contracting officials, particularly those who only occasionally award interagency agreements.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: VA concurred with this recommendation, and developed training based on the revised policy on interagency agreements issued in October 2016. GAO requested information in June 2017 on how VA will ensure this training reaches the full range of program and contracting officials, but as of September 2017 we have not yet received these details.
    Director: Lori Rectanus
    Phone: (202) 512-2834

    1 open recommendations
    Recommendation: To better understand attributable costs for individual Parcel Select NSAs, the Postmaster General should direct the appropriate staff to identify and implement cost-effective methods, such as using a sample, to collect and study information on the costs of delivering Parcel Select packages of varying characteristics in order to develop contract-specific attributable cost estimates.

    Agency: United States Postal Service
    Status: Open

    Comments: USPS developed analysis in response to this recommendation by using a proxy for package dimension rather than a sample of customer-specific dimension data, as GAO recommended. The assumptions used in the methodology by USPS result in only minor cost differences regardless of the dimension or weight of packages shipped under individual Parcel Select NSAs. As of June 13, 2017, this recommendation remains open pending additional discussions with USPS about its methodology and results.
    Director: J. Alfredo Gómez
    Phone: (202) 512-3841

    3 open recommendations
    Recommendation: To develop an estimate of the scope of work remaining to address uranium contamination on or near the Navajo reservation, Congress should consider requiring that the Environmental Protection Agency take the lead and work with the other federal agencies to develop an overall estimate of the remaining scope of the work, time frames, and costs.

    Agency: Congress
    Status: Open

    Comments: As of December 2016, we are not aware of any legislation being enacted to address this matter for congressional consideration.
    Recommendation: In light of the problems BIA has encountered in managing the cleanup at the Tuba City Dump site, the Secretary of the Interior should direct the Assistant Secretary for Indian Affairs to employ best practices in creating the schedule and cost estimates for the remedial action cleanup phase.

    Agency: Department of the Interior
    Status: Open

    Comments: As of December 2016, GAO is awaiting action by the agency to implement this recommendation.
    Recommendation: In light of the problems BIA has encountered in managing the cleanup at the Tuba City Dump site, the Secretary of the Interior should direct the Assistant Secretary for Indian Affairs to identify and examine any lessons learned from managing the remedial investigation and feasibility study contract and consider these lessons as part of the acquisition planning process for the remedial action contract.

    Agency: Department of the Interior
    Status: Open

    Comments: As of December 2016, GAO is awaiting action by the agency to implement this recommendation.