Reports & Testimonies

  • GAO’s recommendations database contains report recommendations that still need to be addressed.

    GAO’s recommendations help congressional and agency leaders prepare for appropriations and oversight activities, as well as help improve government operations. Recommendations remain open until they are designated as Closed-implemented or Closed-not implemented. You can explore open recommendations by searching or browsing.

    GAO's priority recommendations are those that we believe warrant priority attention. We sent letters to the heads of key departments and agencies, urging them to continue focusing on these issues. These recommendations are labeled as such. You can find priority recommendations by searching or browsing our open recommendations below, or through our mobile app.

  • Browse Open Recommendations

    Explore priority recommendations by subject terms or browse by federal agency

    Search Open Recommendations

    Search for a specific priority recommendation by word or phrase



  • Governing on the go?

    Our Priorities for Policy Makers app makes it easier for leaders to search our recommendations on the go.

    See the November 10th Press Release


  • Have a Question about a Recommendation?

    • For questions about a specific recommendation, contact the person or office listed with the recommendation.
    • For general information about recommendations, contact GAO's Audit Policy and Quality Assurance office at (202) 512-6100 or apqa@gao.gov.
  • « Back to Results List Sort by   

    Results:

    Subject Term: "Contract administration"

    34 publications with a total of 116 open recommendations including 2 priority recommendations
    Director: Timothy J. DiNapoli
    Phone: (202) 512-4841

    7 open recommendations
    Recommendation: To enhance management attention to closing out contracts, the Secretary of Defense should develop a means for department-wide oversight into components' progress in meeting their goals on closing contracts and the status of contracts eligible for closeout. (Recommendation 1)

    Agency: Department of Defense
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To enhance management attention to closing out contracts, the Secretary of Health and Human Services should develop a means for department-wide oversight into components' progress in meeting their goals on closing contracts and the status of contracts eligible for closeout. (Recommendation 2)

    Agency: Department of Health and Human Services
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To enhance management attention to closing out contracts, the Secretary of Homeland Security should develop a means, either at the agency or the component level, to track where the contracts are in the closeout process, and establish goals and performance measures for closing contracts. (Recommendation 3)

    Agency: Department of Homeland Security
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To enhance management attention to closing out contracts, the Attorney General should direct the Senior Procurement Executive to ensure the development of a means to track data on the number and type of contracts eligible for closeout and where the contracts are in the closeout process, as well as a means to assess--at the agency or component level--progress by establishing goals and performance measures for closing contracts. (Recommendation 4)

    Agency: Department of Justice
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To enhance management attention to closing out contracts, the Secretary of State should develop a means at the agency level to track data on the entirety of the number and type of contracts eligible for closeout, where the contracts are in the closeout process, and establish goals and performance measures for closing contracts. (Recommendation 5)

    Agency: Department of State
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To manage its incurred cost inventory, the Director, DCAA should assess and implement options for reducing the length of time to begin incurred cost audit work and establish related performance measures. (Recommendation 6)

    Agency: Department of Defense: Defense Contract Audit Agency
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To manage its incurred cost inventory, the Director, DCAA should comprehensively assess the use and effect of multi-year audits on both DCAA and contractors and establish related performance measures. (Recommendation 7)

    Agency: Department of Defense: Defense Contract Audit Agency
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Director: Timothy J. DiNapoli
    Phone: (202) 512-4841

    2 open recommendations
    Recommendation: To help foster strategic decision making and improvements in the acquisition of services, the Under Secretary of Defense for Acquisition, Technology, and Logistics should, as part of its effort to update the January 2016 instruction, reassess the roles, responsibilities, authorities, and organizational placement of key leadership positions, including functional domain experts, senior services managers, and component level leads.

    Agency: Department of Defense: Office of the Secretary of Defense: Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To help foster strategic decision making and improvements in the acquisition of services, the Under Secretary of Defense for Acquisition, Technology, and Logistics should, as part of its effort to update the January 2016 instruction, clarify the purpose and timing of the Services Requirements Review Board process to better align it with DOD's programming and budgeting processes.

    Agency: Department of Defense: Office of the Secretary of Defense: Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Director: William T. Woods
    Phone: (202) 512-4841

    2 open recommendations
    Recommendation: To ensure accurate reporting of personal services contracts, the Secretary of Defense should direct the Secretaries of the Air Force and the Army take steps to ensure the accurate recording of personal services contracts in the Federal Procurement Data System-Next Generation.

    Agency: Department of Defense
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To ensure accurate reporting of personal services contracts, the Administrator, United States Agency for International Development should implement periodic reviews of selected personal services contracts to ensure the effectiveness of steps taken to assist contracting officers to cite the correct statutory authority for personal services contracts.

    Agency: United States Agency for International Development
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Director: Timothy J. DiNapoli
    Phone: (202) 512-4841

    1 open recommendations
    Recommendation: The Under Secretary of Defense for Acquisition, Technology and Logistics should identify the specific types of information that would best meet the department's needs and, based on that determination, collect and analyze relevant data after contract performance is sufficiently complete to determine the extent to which contracts with incentives achieved their desired outcomes.

    Agency: Department of Defense: Office of the Secretary of Defense: Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Director: Carol C. Harris
    Phone: (202) 512-4456

    6 open recommendations
    Recommendation: To ensure that DHS effectively implements FITARA, the Secretary of Homeland Security should direct the Under Secretary for Management to direct the Chief Information Officer to update the department's IT Acquisition Review governance process to increase the number of contracts and agreements (associated with both major and non-major investments) that are reviewed by the CIO and appropriate delegates.

    Agency: Department of Homeland Security
    Status: Open

    Comments: DHS concurred with this recommendation. We will continue to monitor and evaluate the Department's progress in implementing this recommendation.
    Recommendation: To ensure that DHS effectively implements FITARA, the Secretary of Homeland Security should direct the Under Secretary for Management to direct the Chief Information Officer to establish time frames and implement a plan for (1) identifying the specific staff or positions currently within the department's IT acquisition cadre; and (2) assessing whether these staff and positions address all of the specialized skills and knowledge needed, as outlined in OMB's Office of Federal Procurement Policy's guidance for developing an IT acquisition cadre.

    Agency: Department of Homeland Security
    Status: Open

    Comments: DHS concurred with this recommendation. We will continue to monitor and evaluate the Department's progress in implementing this recommendation.
    Recommendation: To ensure that DHS effectively implements FITARA, the Secretary of Homeland Security should direct the Under Secretary for Management to direct the Chief Information Officer to establish time frames and implement a plan for (1) identifying the department's future IT skillset needs as a result of DHS's new delivery model, (2) conducting a skills gap analysis, and (3) resolving any skills gaps identified.

    Agency: Department of Homeland Security
    Status: Open

    Comments: DHS concurred with this recommendation. We will continue to monitor and evaluate the Department's progress in implementing this recommendation.
    Recommendation: To ensure that DHS effectively implements FITARA, the Secretary of Homeland Security should direct the Under Secretary for Management to update the department's acquisition policies and guidance to be consistent in identifying that the DHS CIO is to certify investments' incremental development activities.

    Agency: Department of Homeland Security
    Status: Open

    Comments: DHS concurred with this recommendation. We will continue to monitor and evaluate the Department's progress in implementing this recommendation.
    Recommendation: To ensure that DHS effectively implements FITARA, the Secretary of Homeland Security should direct the Under Secretary for Management to update DHS headquarters', Customs and Border Protection's, and U.S. Coast Guard's processes to track, for all contracts and agreements, the IT investment with which each is associated (as applicable).

    Agency: Department of Homeland Security
    Status: Open

    Comments: DHS concurred with this recommendation. We will continue to monitor and evaluate the Department's progress in implementing this recommendation.
    Recommendation: To ensure that DHS effectively implements FITARA, the Secretary of Homeland Security should direct the Under Secretary for Management to update and implement the process DHS uses for assessing the risks of major IT investments to ensure that the CIO rating reported to the Dashboard fully reflects the CIO's assessment of each major IT investment.

    Agency: Department of Homeland Security
    Status: Open

    Comments: DHS concurred with this recommendation. We will continue to monitor and evaluate the Department's progress in implementing this recommendation.
    Director: David C. Trimble
    Phone: (202) 512-3841

    6 open recommendations
    Recommendation: To allow DOE management to effectively monitor invoice reviews and have assurance that this control activity is operating as intended, the Secretary of Energy should establish a DOE-wide invoice review policy that includes requirements for sites to establish well-documented invoice review operating procedures.

    Agency: Department of Energy
    Status: Open

    Comments: DOE stated that it already has an established, detailed DOE-wide invoice review policy provided in DOE's Financial Management Handbook and in the DOE Acquisition Guide, and that they are updating the Financial Management Handbook to include additional procedures to address intra-governmental payment and collection transactions that they believe will allow the recommendation to be closed by September 30, 2017. However, DOE officials with the office of the CFO at DOE headquarters previously told us that they do not have department-wide invoice review policies and procedures, and that CFOs and contracting officials in DOE field offices are responsible to develop their own invoice review policies and procedures. In addition, we reviewed the Financial Management Handbook and the Acquisition Guide and found that these documents do not contain the detail necessary to serve as an invoice review policy. We will continue to review DOE's implementation of this recommendation to determine whether its actions meet the intent of the recommendation.
    Recommendation: To help DOE take a more strategic approach to managing improper payments and risk, including fraud risk, the Secretary of Energy should implement leading practices for managing the department's risk of fraud, including creating a structure with a dedicated entity within DOE to design and oversee fraud risk management activities.

    Agency: Department of Energy
    Status: Open

    Comments: DOE considers this recommendation to be closed without corrective action. Instead of establishing a dedicated entity within DOE to design and oversee fraud risk management activities, DOE will rely on the existing Office of Financial Policy and Internal Controls and on the DOE Office of Inspector General (OIG)to design and oversee financial fraud risk management activities. We disagree that reliance on these offices meets best practices because neither office is solely dedicated to designing or overseeing fraud risk management activities. Furthermore, according the best practices in GAO's Fraud Risk Framework, the dedicated entity should not be the OIG.
    Recommendation: To help DOE take a more strategic approach to managing improper payments and risk, including fraud risk, the Secretary of Energy should implement leading practices for managing the department's risk of fraud, including conducting fraud risk assessments that are tailored to each program and use the assessments to develop a fraud risk profile

    Agency: Department of Energy
    Status: Open

    Comments: DOE concurred with the substance of the recommendation; however they consider the recommendation to be closed without corrective action because its risk assessments meet the requirements of the Improper Payments Elimination and Recovery Improvement Act of 2012, as reported by the Office of Inspector General (OIG), and because it has implemented updates to OMB Circular A-123 that added requirements related to managing fraud risk and adherence to GAO's Fraud Risk Framework. However, we found that DOE has not conducted fraud risk assessments that are tailored to its programs and therefore do not allow the department to create a fraud risk profile. We also found that, although DOE updated its internal control assessment tools with a list of fraud risks as required by OMB Circular A-123, the list of risks were the same for all DOE sites and were not tailored to the sites' different programs.
    Recommendation: To help DOE take a more strategic approach to managing improper payments and risk, including fraud risk, the Secretary of Energy should implement leading practices for managing the department's risk of fraud, including developing and documenting an antifraud strategy that describes the programs' approaches for addressing the prioritized fraud risks identified during the fraud risk assessment.

    Agency: Department of Energy
    Status: Open

    Comments: DOE concurred with this recommendation but considers the recommendation closed without corrective action because DOE has implemented the updated OMB Circular A-123 and because DOE's anti-fraud strategy is imbedded in the DOE internal control program. However, DOE officials told us that they have not developed or documented a DOE-wide antifraud strategy or directed individual programs to develop program-specific strategies. Furthermore, DOE's implementation of OMB Circular A-123 included adding a list of potential risks to their internal control assessment tool that were the same for all DOE sites and were not tailored to the sites' different programs.
    Recommendation: To help DOE take a more strategic approach to managing improper payments and risk, including fraud risk, the Secretary of Energy should implement leading practices for managing the department's risk of fraud, including designing and implementing specific control activities, including fraud awareness training and data analytics, to prevent and detect fraud and other improper payments.

    Agency: Department of Energy
    Status: Open

    Comments: DOE believes that they are either implementing or have already implemented this recommendation and considers the recommendation closed without additional action. Specifically, DOE stated that the Office of Inspector General (OIG) already provides fraud awareness training and that the OIG provided expanded fraud risk training on June 12, 2017 through a CFO-hosted webinar. However, of the 10 field offices responsible for overseeing contractor costs, none required employees responsible for overseeing contractor costs to attend fraud awareness training.
    Recommendation: To help ensure that necessary data are available to employ data analytics as a tool to perform contractor cost-surveillance activities, the Secretary of Energy should require contractors to maintain sufficiently detailed transaction-level cost data that are reconcilable with amounts charged to the government, including (1) cost data that, at a minimum, represent a full data population and (2) the details necessary to determine the nature of each cost transaction, with such identifiers as transaction date, dollar amount, item or service description, and transaction codes to indicate the type of cost represented (e.g., construction materials, property lease, and office supplies).

    Agency: Department of Energy
    Status: Open

    Comments: DOE did not agree to implement this recommendation because they believe that the recommendation establishes agency-specific requirements for DOE contractors that are more prescriptive than current federal requirements. DOE states that they plan to evaluate the merits of government-wide guidance for applying data-analytics to contract costs only if an OMB working group--established as a requirement of the Fraud Reduction and Data Analytics Act of 2015 to promote interagency coordination on fraud reduction and data analytics--requires them to do so. However, the purpose of the working group is to share fraud management best practices. It is not an implementing body and agencies do not need its permission before proceeding with fraud risk reduction efforts.
    Director: Michele Mackin
    Phone: (202) 512-4841

    8 open recommendations
    Recommendation: In order to ensure universal usage and reduce duplicate work, the Secretary of Veterans Affairs should direct the Office of Acquisition and Logistics (OAL) to work with the National Acquisition Center to develop a plan for adding functionality to the Electronic Contract Management System (eCMS) that will alleviate the need for National Acquisition Center contracting officers to enter obligations for high-tech medical equipment into two different data systems.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In providing comments on this report, VA concurred with this recommendation but has not yet taken actions necessary to implement it. However, in its letter to OMB and the Congress, VA stated that it plans to pursue a new financial and contracting systems that will be interoperable.
    Recommendation: In order to ensure that VA's procurement data is complete and accurate, the Secretary of Veterans Affairs should direct the Office of Acquisitions and Logistics to develop policies and procedures to ensure that obligations made through prime vendor orders--such as medical-surgical orders--are consistently captured in eCMS.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In providing comments on this report, VA concurred with this recommendation but has not yet taken actions necessary to implement it. In its letter to OMB and the Congress, VA noted an April 2016 policy that requires monthly reporting of orders to contracting officers, but additional guidance and processes are required to implement this policy.
    Recommendation: In order to ensure that contracting officers have clear and effective policies as soon as possible, the Secretary of Veterans Affairs should direct the OAL to identify measures to expedite the revision of the Veterans Affairs Acquisition Regulation (VAAR), which has been ongoing for many years, and the issuance of the VA Acquisition Manual.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In providing comments on this report, VA concurred with this recommendation but has not yet taken any actions necessary to implement it. However, in its letter to OMB and the Congress, VA stated that it anticipated that the updated VAAR would be issued by December 2018.
    Recommendation: To help contracting officers use current policy that is in effect in the period before the updated VAAR and VA Acquisition Manual are released, the Secretary of Veterans Affairs should direct OAL to take interim steps to clarify its policy framework, including establishing and adhering to set time frames for completing the process of reviewing all Information Letters, and either rescinding them or reissuing updated policy through Procurement Policy Memoranda.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In providing comments on this report, VA concurred with this recommendation but has not yet completed the actions necessary to implement it. In its letter to OMB and the Congress, VA stated that some Information Letters are still awaiting review and rescission or reissuance.
    Recommendation: To address remaining ambiguities in roles and customer relationships, the Secretary of Veterans Affairs should direct the Office of Acquisition, Logistics, and Construction to assess whether additional policy or guidance is needed to clarify the roles of VA's national contracting organizations, beyond that provided in its March 2013 memorandum outlining the current structure.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In providing comments on this report, VA concurred with this recommendation but has not yet taken any actions necessary to implement it. However, in its letter to OMB and the Congress, VA stated that it planned to issue updated guidance on roles for its national contracting organizations.
    Recommendation: To facilitate consolidation of similar requirements and leverage buying power across medical centers within VISNs, the Secretary of Veterans Affairs should direct VHA Procurement and Logistics to conduct a review of VISN-level strategic sourcing efforts, identify best practices, and, if needed, issue guidance.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In providing comments on this report, VA concurred with this recommendation. In July 2017, Veterans Health Administration officials stated that they would take further action to collect and disseminate best practices, which they estimate will be complete by late 2017.
    Recommendation: The Secretary of Veterans Affairs should direct the Senior Procurement Executive to issue guidance to the Heads of Contracting Activity to focus internal compliance reviews on ensuring that required contract documents are properly prepared and documented.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In providing comments on this report, VA concurred with this recommendation. In its letter to OMB and the Congress, VA stated that it is beginning coordination between the Senior Procurement Executive (SPE) and its Heads of Contracting Activity (HCA) on using the findings of OMB A-123 reviews to focus its contract compliance reviews. The SPE and HCA developed a memorandum of understanding for this effort in late 2016, but VA has not yet provided information on any new guidance to focus compliance reviews.
    Recommendation: To maximize compliance with mandatory national contracts during the transition to the new medical-surgical prime vendor (MSPV) process, the Secretary of Veterans Affairs should direct the Strategic Acquisition Center (SAC) and VHA Procurement and Logistics to take steps to ensure that: (1) SAC has mechanisms in place to collect and monitor transaction data to determine the extent to which Veterans Integrated Service Networks (VISNs) and their medical centers are complying with the requirement to use national contracts. (2) They establish achievable time frames for eliminating the ability for ordering officers to directly order Federal Supply Schedule items from the MSPV catalog once SAC awards national contracts for these items and monitor progress on an ongoing basis. (3) The ordering interfaces developed by the prime vendors clearly distinguish and prioritize standardized national contracts over items on Federal Supply Schedule contracts.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In providing comments on this report, VA concurred with this recommendation. VA has taken steps to monitor compliance with mandatory national contracts. However, VA has not yet established achievable timeframes for replacing Federal Supply Schedule items made available through non-competitive agreements its new Medical-Surgical Prime Vendor program, nor has it taken steps to distinguish these items from competitive national contracts in the ordering interface.
    Director: David Trimble
    Phone: (202) 512-3841

    2 open recommendations
    Recommendation: To strengthen acquisition planning for M&O contract acquisitions, the Secretary of Energy should direct the Office of Acquisition Management, Office of Policy to require that acquisition planning documents for M&O contracts discuss alternatives beyond extending the M&O contract or conducting a competition for essentially the same scope of work.

    Agency: Department of Energy
    Status: Open

    Comments: In November 2016, DOE officials stated that the Office of Acquisition Management will amend existing or issue new policy or guidance, as appropriate, with an estimated completion date of January 2017.
    Recommendation: To strengthen acquisition planning for M&O contract acquisitions, the Secretary of Energy should direct the Office of Acquisition Management, Office of Policy to establish a process to periodically analyze DOE's experience with alternatives to the single M&O contract approach to identify and apply lessons learned during acquisition planning for M&O contracts.

    Agency: Department of Energy
    Status: Open

    Comments: In November 2016, DOE officials stated that the Office of Acquisition Management will amend existing or issue new policy or guidance, as appropriate, to require programs to periodically analyze their experiences with alternatives. Officials provided an estimated completion date of July 2017.
    Director: Williamson, Randall B
    Phone: (202) 512-7114

    2 open recommendations
    Recommendation: To develop and maintain medical sharing expertise within the network contracting offices, the Secretary of Veterans Affairs should direct the Under Secretary for Health to create a plan for increasing the retention of contracting officers that work in medical sharing teams.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In March 2017, VHA reported that it is working on creating a plan for increasing the retention of contracting officers that work in medical sharing teams. The Medical Sharing Office (MSO) has taken several steps including conducting research on possible ways to minimize or eliminate steps within its existing plan and expanding the number of topical training provided virtually network contracting offices to develop competency in VHA Health Care 1102 staff. In addition, VHA reported they are developing a training schedule to ensure newly deployed interns have received the training and resource to successfully conduct health care contracts if they are assigned to health care resources team and continuing to collaborate with the field to ensure awareness of MSO support and assistance.
    Recommendation: To ensure VHA effectively communicates with its affiliates regarding SSACs, the Secretary of Veterans Affairs should direct the Under Secretary for Health to reach out to all of its affiliates, identify any concerns, and determine the most effective method of communicating with affiliates regarding SSAC development.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In March 2017, the VHA reported that it plans to have an Academic Affiliate Contracting Forum on August 15-16, 2017 in Nashville, TN or Dallas, TX for VHA staff responsible for health care contracts and University affiliates. The purpose of the Forum is to strengthen and advance the collaborative partnership for providing service to Veterans; share perspectives; and enhance awareness about processes, procedures and tools that will help make contracting processes faster and easier for all parties.
    Director: Seto Bagdoyan
    Phone: (202) 512-6722

    2 open recommendations
    Recommendation: The Administrator of SBA should direct the Associate Administrator of Business Development to document its planned method for tracking revenue generated under subsidiaries' primary and secondary lines of business, with milestones and timelines for when and how the method will be implemented.

    Agency: Small Business Administration
    Status: Open

    Comments: GAO is reviewing documentation that SBA provided regarding actions that it has taken to address this recommendation and is currently determining whether these actions fully address the recommendation.
    Recommendation: The Administrator of SBA should direct the Associate Administrator of Business Development to provide the appropriate level of access to and sharing of relevant subsidiary data across district offices, including primary and secondary North American Industry Classification System codes and revenue data, once SBA develops a database with the capabilities of collecting and tracking this revenue data as we recommended in 2012.

    Agency: Small Business Administration
    Status: Open

    Comments: GAO is reviewing documentation that SBA provided regarding actions that it has taken to address this recommendation and is currently determining whether these actions fully address the recommendation.
    Director: Cary Russell
    Phone: (202) 512-5431

    6 open recommendations
    including 1 priority recommendation
    Recommendation: To enable AFRICOM's component commands to better plan, advise, and coordinate for OCS, the AFRICOM Commander, as part of AFRICOM's ongoing efforts to update related guidance and emphasize the importance of OCS integration at the subordinate command level, should direct the service components to designate elements within their respective staffs to be responsible for coordinating OCS, and consider the establishment of an OCS Integration Cell or similar structure with these dedicated OCS personnel, as needed.

    Agency: Department of Defense: U.S. Africa Command
    Status: Open

    Comments: In July 2016, AFRICOM officials stated that there are clear advantages and benefits to establishing an OCSIC at Service-component level. USAFRICOM, as a geographic combatant command, assigns operational missions to subordinate commands for execution, including operational contract support (OCS) tasks. Joint Pub 4-10, as augmented by AFRICOM Command Instruction (ACI) 4800.01 A, specifies the tasks and functions in support of OCS that Service Components must execute. Service Components determine the most appropriate organizational structure best suited to meet its assigned mission. i.e. establishment of an OCSlC as deemed necessary. However, service components have indicated that guidance clarifying the circumstances under which they should establish OCSICs would be helpful. As such, this recommendation will remain open at this time.
    Recommendation: To enable AFRICOM's component commands to better plan, advise, and coordinate for OCS, the AFRICOM Commander, as part of AFRICOM's ongoing efforts to update related guidance and emphasize the importance of OCS integration at the subordinate command level, should clarify under what conditions a subordinate joint force command, such as Combined Joint Task Force-Horn of Africa, should establish an OCS Integration Cell.

    Agency: Department of Defense: U.S. Africa Command
    Status: Open

    Comments: AFRICOM officials told us that USAFRICOM J4 conducted a staff assistance visit (SA V) at CJTF-HOA from 16-19 August 2015. It was recommended that ClTF-HOA establish an OCS Working Group (OCSWG) that is owned b) the ClTF-HOA J4. The OCSWG is a doctrinal working group and would contain designated cross-functional staff members to enable OCS planning and policy generation as well as Oversee contractor management issues. Other OCS recommendations were made to the CJTF-HOA J4 that included adding permanent OCS billets to the J4 and executing OCSIC tasks. This recommendation will remain open at this time.
    Recommendation: To enable AFRICOM to better identify, address, and mitigate OCS readiness gaps at its component commands before inaccurate information is incorporated into formal defense readiness reporting systems, the AFRICOM Commander should clarify the scorecard process, including assessment standards, for OCS Readiness Scorecards to ensure that evaluators can accurately assess subordinate commands' OCS capabilities.

    Agency: Department of Defense: U.S. Africa Command
    Status: Open

    Comments: In July 2016, AFRICOM officials stated that while the OCS score card may be considered a best practice in the OCS execution in the AFRICOM AOR, it is not a replacement for the Defense Readiness Reporting System (DRRS) to report OCS. This recommendation will remain open at this time.
    Recommendation: To enable AFRICOM to comprehensively and consistently account for contractor personnel in Africa, the Secretary of Defense, in coordination with the Chairman of the Joint Chiefs of Staff, should direct Joint Staff to clarify what types of contractor personnel should be accounted for in its guidance on personnel status reports.

    Agency: Department of Defense
    Status: Open

    Comments: DOD has taken steps to clarify what types of contractor personnel should be accounted for in its guidance on personnel status reports, but revision of that guidance is ongoing. According to Joint Staff officials in August 2016, USAFRICOM has not yet incorporated its local policies and standards into the CJCSM 3150.13C as the manual is up for review by the Joint Staff and is projected to be completed by Spring 2017. Additionally, in February 2016, a class deviation became effective for the USAFRICOM area of responsibility (AOR). This deviation superseded Class Deviations 2014-O0005, and 2015-O0003. The deviation stated that contracting officers shall incorporate clause 252.225-7980, Contractor Personnel Performing in the United States Africa Command Area of Responsibility, in lieu of the clause at DFARS 252.225-7040, Contractor Personnel Supporting U.S. Armed Forces Deployed Outside the United States, in all solicitations and contracts, including solicitations and contracts using FAR part 12 procedures for the acquisition of commercial items that will require contractor personnel to perform in the United States Africa Command (USAFRICOM) area of responsibility. In addition, to the extent practicable, contracting officers shall modify current, active contracts with performance in the USAFRICOM AOR to include the clause 252.225-7980. The USAFRICOM Commander has identified a need to utilize the Synchronized Pre-deployment and Operational Tracker for all contracts performed in the AOR during all operational phases (including Phase 0), not limited to declared contingency operations. However, until guidance clarifying what types of contractor personnel is finalized, this recommendation will remain open.
    Recommendation: To enable AFRICOM to comprehensively and consistently account for contractor personnel in Africa, the AFRICOM Commander should develop area of responsibility-wide contractor personnel accountability guidance on or before December 2015, when the current guidance expires, that clarifies which types of contractor personnel should be accounted for using SPOT, and when SPOT accountability requirements should be incorporated into contracts.

    Agency: Department of Defense: U.S. Africa Command
    Status: Open

    Comments: In July 2016, AFRICOM officials told us Defense Federal Acquisition Regulation Supplement (DFARS) 252.225-7980 (Class Deviation 2016-00008), Contractor Personnel Performing in the United States Africa Command Area of Responsibility was published in June 2016. This clause requires the use of the Synchronized Pre-Deployment and Operational Tracker (SPOT) to account for all Contractor Authorized to Accompany the Force (CAAF), United States and third-country national contractors (TCNs), all private security contractors. and all other contractor personnel authorized to carry weapons when performing in the AFRICOM AOR on all DoD contracts, regardless of the contract amount or period of performance. Furthermore. the DoD contractor is required to submit to the cognizant contracting officer for SPOT reporting and aggregate count of all local national employees performing in the AFRICOM AOR. by country of performance, for 30 days or longer under a contract valued at or above $150.000. This recommendation will remain open at this time.
    Recommendation: To ensure that combatant commands are not contracting with entities that may be connected to or supporting prohibited organizations, the Secretary of Defense, in coordination with the Chairman of the Joint Chiefs of Staff, should develop guidance that clarifies the conditions under which combatant commands should have a foreign vendor vetting process or cell in place to determine whether potential vendors actively support any terrorist, criminal, or other sanctioned organizations, including clarifying when combatant commands should develop procedures for transmitting the names of any vendors identified through this process for inclusion in prohibited entities lists in the appropriate federal contracting databases, such as the System for Award Management.

    Agency: Department of Defense
    Status: Open
    Priority recommendation

    Comments: As of October 2016, DOD has taken steps to develop foreign vendor vetting guidance, but that guidance is in the process of being drafted. According to Joint Staff officials in August 2016, as required by NDAA for FY2015, Section 841(d)(1), the Director, Defense Procurement & Acquisition Policy, issued Class Deviation 2015-O0016, Prohibition on Providing Funds to the Enemy and Authorization of Additional Access to Records, effective September 15, 2015. Also, Joint Staff has drafted a Directive Type Memorandum (DTM)on foreign vendor vetting. When issued, the DTM will assign responsibility to each of the Combatant Commanders to establish a foreign vendor program in their respective Areas of Responsibility in accordance with NDAA for FY2015, Sections 841, 842 and 843. However, until the DTM is issued, this recommendation will remain open.
    Director: Michele Mackin
    Phone: (202) 512-4841

    3 open recommendations
    Recommendation: To improve coordination and communication between FEMA OCPO and region mission support officials region mission support officials, the FEMA Administrator should establish a plan to ensure that the agreement is reviewed on an annual basis as intended.

    Agency: Department of Homeland Security: Directorate of Emergency Preparedness and Response: Federal Emergency Management Agency
    Status: Open

    Comments: In commenting on this report, DHS concurred with this recommendation. According to FEMA officials, the Office of Procurement Operations has since formed a team that will address this recommendation. We will provide updated information as it becomes available.
    Recommendation: To improve coordination and communication between FEMA Office of the Chief Procurement Officer (OCPO) and region mission support officials region mission support officials, the FEMA Administrator should direct OCPO and the regional administrators to revisit the 2011 service level agreement to: add details about the extent of operational control headquarters and regional supervisors should exercise to minimize potential competing interests experienced by regional contracting officers; further detail headquarters and regional supervisors' roles and responsibilities for managing regional contracting officers to improve coordination and communication; and ensure that the agreement reflects any new requirements, including recent changes in training that may require travel funds.

    Agency: Department of Homeland Security: Directorate of Emergency Preparedness and Response: Federal Emergency Management Agency
    Status: Open

    Comments: In commenting on this report, DHS concurred with this recommendation. According to FEMA officials, the Office of Procurement Operations has since formed a team that will address this recommendation. We will provide updated information as it becomes available.
    Recommendation: To address PKEMRA, the Secretary of Homeland Security should take action to address the requirements of Section 692 to implement subcontractor limitations or request that Congress amend the law to delete Section 692.

    Agency: Department of Homeland Security
    Status: Open

    Comments: In 2016, DHS took steps to ask Congress to repeal PKEMRA Section 692, which prohibits the use of subcontracts for more than 65 percent of the cost of cost-reimbursement type contracts that exceed the simplified acquisition threshold. DHS submitted a legislative change proposal to the Office of Management and Budget (OMB), who approves such proposals before they are submitted to Congress. OMB approved the proposed change for PKEMRA Section 692 in April 2016. We will provide additional updates as information becomes available.
    Director: William Shear
    Phone: (202) 512-8678

    6 open recommendations
    including 1 priority recommendation
    Recommendation: To improve management of the Small Business Administration and to ensure that SBA assesses the effectiveness of its programs, the SBA Administrator should prioritize resources to conduct additional program evaluations.

    Agency: Small Business Administration
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To improve management of the Small Business Administration and to ensure that SBA fully meets GPRAMA requirements, the SBA Administrator should use the results of additional evaluations it conducts in its strategic planning process and ensure the agency's next strategic plan includes required information on program evaluations, including a schedule of future evaluations.

    Agency: Small Business Administration
    Status: Open
    Priority recommendation

    Comments: SBA officials stated that, as of October 2016, the agency had taken several steps to prioritize resources and establish an implementation plan for future evaluations, including hiring its first lead program evaluator to develop a long-term evaluation agenda and initiating four program evaluations. They stated that once completed, the evaluations would be incorporated into the agency's fiscal year 2018-2022 strategic plan. As of May 2017, SBA had started reviewing guidance on drafting this plan, which is due in February 2018.
    Recommendation: To improve management of the Small Business Administration and to improve SBA's human capital management, the SBA Administrator should incorporate into its next training plan key principles such as goals and measures for its training programs and input on employee development goals.

    Agency: Small Business Administration
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To improve management of the Small Business Administration and to ensure that SBA's organizational structure helps the agency meet its mission, the SBA Administrator should document the assessment of the agency's organizational structure, including any necessary changes to, for example, better ensure areas of authority, responsibility, and lines of reporting are clear and defined.

    Agency: Small Business Administration
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To improve management of the Small Business Administration and to improve SBA's program and management guidance, the SBA Administrator should set time frames for periodically reviewing and updating its SOPs as appropriate.

    Agency: Small Business Administration
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To improve management of the Small Business Administration and to help ensure that SBA's IT operations and maintenance investments are continuing to meet business and customer needs and the agency's strategic goals, the SBA Administrator should direct the appropriate officials to perform an annual operational analysis on all SBA investments in accordance with OMB guidance.

    Agency: Small Business Administration
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Director: Cristina Chaplain
    Phone: (202) 512-4841

    1 open recommendations
    Recommendation: When planning for the next phase of national security space launches, Phase 2, the Secretary of the Air Force should consider using an incremental approach to the next launch services acquisition strategy. Planning for acquisitions on a short term basis will help ensure that the Air Force does not commit itself to a strategy until the appropriate amount of data is available to make an informed decision, and will allow for flexibility in responding to a changing launch industry.

    Agency: Department of Defense: Department of the Air Force
    Status: Open

    Comments: In providing comments on this report, the agency concurred with this recommendation but has not yet completed actions necessary to implement it. The acquisition strategy for the next phase of national security launches, Phase 2, has not yet been finalized by the Air Force. The EELV program office expects it to be completed in the summer of 2018.
    Director: William T. Woods
    Phone: (202) 512-4841

    3 open recommendations
    Recommendation: To help ensure contracting officers follow ordering procedures when using FSS, and to enhance internal controls, the Secretaries of DOD and HHS and the Administrator of GSA should issue guidance emphasizing the requirement to seek discounts and outlining effective strategies for negotiating discounts when using the FSS program.

    Agency: Department of Health and Human Services
    Status: Open

    Comments: In December 2016, HHS stated that it had assessed and reviewed existing guidance and determined that existing guidance was adequate, but that HHS contracting officials needed to be refreshed on the content. While HHS stated that it had tasked the contracting heads of each HHS component with ensuring that its officials attend refresher training, the agency has not yet ensured that this has been accomplished. In June 2017, HHS officials said they were again considering issuing additional guidance, per our recommendation.
    Recommendation: To help ensure contracting officers follow ordering procedures when using FSS, and to enhance internal controls, the Secretaries of DOD and HHS and the Administrator of GSA should issue guidance reminding contracting officials of the procedures they must follow with respect to purchasing open market items through the FSS program, including the requirement to perform a separate determination that the prices of these items are fair and reasonable.

    Agency: Department of Health and Human Services
    Status: Open

    Comments: In December 2016, HHS stated that it had assessed and reviewed existing guidance and determined that existing guidance was adequate, but that HHS contracting officials needed to be refreshed on the content. While HHS stated that it had tasked the contracting heads of each HHS component with ensuring that its officials attend refresher training, the agency has not yet ensured that this has been accomplished. In June 2017, HHS officials said they were again considering issuing additional guidance, per our recommendation.
    Recommendation: To help foster competition for FSS orders consistent with the FAR, the Secretary of HHS should assess reasons that may be contributing to the high percentage of orders with one or two quotes--including the practice of narrowing the pool of potential vendors--and if necessary, depending on the results of the assessment, provide guidance to help ensure contracting officials are taking reasonable steps to obtain three or more quotes above the simplified acquisition threshold.

    Agency: Department of Health and Human Services
    Status: Open

    Comments: HHS agreed with the recommendation. In January 2017, an HHS official stated that the agency had tried to conduct an assessment but had not yet been able to obtain enough information. In June 2017, HHS officials said that they would reexamine how to conduct an assessment per our recommendation.
    Director: Frank Rusco
    Phone: (202) 512-3841

    15 open recommendations
    Recommendation: To help agencies more consistently perform their oversight responsibilities and oversee contractors' measurement and verification activities, the Secretary of Energy should direct FEMP to monitor agencies' oversight of ESPC projects that agencies have awarded using the DOE contract vehicle, including whether agencies witnessed the contractors' measurement and verification activities and reviewed and certified acceptance of the measurement and verification report.

    Agency: Department of Energy
    Status: Open

    Comments: As of December 2016, we were working with DOE officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on the effects of changing circumstances on the performance of their ESPC portfolios, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should establish a process to systematically evaluate their ESPC projects--including baseline assumptions about facilities' energy use, utility prices, and interest rates--to determine how their ESPC portfolios are performing and the extent to which they are achieving expected savings. Agencies could consider conducting such evaluations either after a certain number of years, or in response to events, such as changes in utility prices or market interest rates, or appropriations becoming available that could be used for modifications or terminations.

    Agency: Department of Defense
    Status: Open

    Comments: In comments on a draft of this report, DOD partially concurred with this recommendation. As of December 2016, we were working with DOD officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on the effects of changing circumstances on the performance of their ESPC portfolios, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should establish a process to systematically evaluate their ESPC projects--including baseline assumptions about facilities' energy use, utility prices, and interest rates--to determine how their ESPC portfolios are performing and the extent to which they are achieving expected savings. Agencies could consider conducting such evaluations either after a certain number of years, or in response to events, such as changes in utility prices or market interest rates, or appropriations becoming available that could be used for modifications or terminations.

    Agency: Department of Energy
    Status: Open

    Comments: As of December 2016, we were working with DOE officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on the effects of changing circumstances on the performance of their ESPC portfolios, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should establish a process to systematically evaluate their ESPC projects--including baseline assumptions about facilities' energy use, utility prices, and interest rates--to determine how their ESPC portfolios are performing and the extent to which they are achieving expected savings. Agencies could consider conducting such evaluations either after a certain number of years, or in response to events, such as changes in utility prices or market interest rates, or appropriations becoming available that could be used for modifications or terminations.

    Agency: Department of Justice
    Status: Open

    Comments: In comments on a draft of this report, the Department of Justice agreed with the recommendation. As of December 2016, we were working with Department of Justice officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on the effects of changing circumstances on the performance of their ESPC portfolios, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should establish a process to systematically evaluate their ESPC projects--including baseline assumptions about facilities' energy use, utility prices, and interest rates--to determine how their ESPC portfolios are performing and the extent to which they are achieving expected savings. Agencies could consider conducting such evaluations either after a certain number of years, or in response to events, such as changes in utility prices or market interest rates, or appropriations becoming available that could be used for modifications or terminations.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In comments on a draft of this report, the Department of Veterans Affairs agreed with the recommendation. As of December 2016, we were working with Department of Veterans Affairs officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on the effects of changing circumstances on the performance of their ESPC portfolios, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should establish a process to systematically evaluate their ESPC projects--including baseline assumptions about facilities' energy use, utility prices, and interest rates--to determine how their ESPC portfolios are performing and the extent to which they are achieving expected savings. Agencies could consider conducting such evaluations either after a certain number of years, or in response to events, such as changes in utility prices or market interest rates, or appropriations becoming available that could be used for modifications or terminations.

    Agency: General Services Administration
    Status: Open

    Comments: In comments on a draft of this report, GSA agreed with the recommendation. As of December 2016, we were working with GSA officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help agencies decide whether to use ESPCs to consolidate federal data centers, the Director of the Office of Management and Budget should document, for the purposes of scoring ESPCs, (1) what qualifies as energy-related savings and (2) the allowable proportion of energy and energy-related cost savings.

    Agency: Executive Office of the President: Office of Management and Budget
    Status: Open

    Comments: OMB did not comment on its plans to implement this recommendation in its review of a draft of the report and, as of December 2016, had not provided us with requested information on its actions to implement this recommendation. We will continue to follow-up on the status of this recommendation.
    Recommendation: To help agencies more consistently perform their oversight responsibilities and oversee contractors' measurement and verification activities, the Secretary of Energy should direct DOE's Federal Energy Management Program (FEMP) to evaluate existing training and determine whether additional training is needed on observing contractors' measurement and verification activities and reviewing and certifying measurement and verification reports.

    Agency: Department of Energy
    Status: Open

    Comments: As of December 2016, we were working with DOE officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on ESPC performance to oversee whether future and current contracts are achieving their expected savings, the Secretaries of Defense and Energy should specify in the scheduled revisions to their ESPC contract vehicles or in guidance to agencies that measurement and verification reports for future projects are to include estimates of cost and energy savings that were not achieved because of agency actions. Additionally, the Department of Energy (DOE) may wish to consider periodically analyzing data on other factors that may affect savings, such as utility prices, to provide information on how savings achieved by ESPCs awarded through its contract vehicle have been affected by changing utility prices since its prior study in 2007.

    Agency: Department of Defense
    Status: Open

    Comments: In comments on a draft of this report, DOD concurred with this recommendation. As of December 2016, we were working with DOD officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on ESPC performance to oversee whether future and current contracts are achieving their expected savings, the Secretaries of Defense and Energy should specify in the scheduled revisions to their ESPC contract vehicles or in guidance to agencies that measurement and verification reports for future projects are to include estimates of cost and energy savings that were not achieved because of agency actions. Additionally, the Department of Energy (DOE) may wish to consider periodically analyzing data on other factors that may affect savings, such as utility prices, to provide information on how savings achieved by ESPCs awarded through its contract vehicle have been affected by changing utility prices since its prior study in 2007.

    Agency: Department of Energy
    Status: Open

    Comments: As of December 2016, we were working with DOE officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on ESPC performance to oversee whether future and current contracts are achieving their expected savings, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should work with contractors to determine the best way to obtain estimates of cost and energy savings that are not achieved because of agency actions in order to include these estimates in future measurement and verification reports for existing contracts, in accordance with DOE guidance, and where economically feasible.

    Agency: Department of Defense
    Status: Open

    Comments: In comments on a draft of this report, DOD concurred with this recommendation. As of December 2016, we were working with DOD officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on ESPC performance to oversee whether future and current contracts are achieving their expected savings, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should work with contractors to determine the best way to obtain estimates of cost and energy savings that are not achieved because of agency actions in order to include these estimates in future measurement and verification reports for existing contracts, in accordance with DOE guidance, and where economically feasible.

    Agency: Department of Energy
    Status: Open

    Comments: As of December 2016, we were working with DOE officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on ESPC performance to oversee whether future and current contracts are achieving their expected savings, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should work with contractors to determine the best way to obtain estimates of cost and energy savings that are not achieved because of agency actions in order to include these estimates in future measurement and verification reports for existing contracts, in accordance with DOE guidance, and where economically feasible.

    Agency: Department of Justice
    Status: Open

    Comments: In comments on a draft of this report, the Department of Justice agreed with the recommendation. As of December 2016, we were working with Department of Justice officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on ESPC performance to oversee whether future and current contracts are achieving their expected savings, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should work with contractors to determine the best way to obtain estimates of cost and energy savings that are not achieved because of agency actions in order to include these estimates in future measurement and verification reports for existing contracts, in accordance with DOE guidance, and where economically feasible.

    Agency: Department of Veterans Affairs
    Status: Open

    Comments: In comments on a draft of this report, the Department of Veterans Affairs did not agree with the recommendation, but suggested changes, which we incorporated. As of December 2016, we were working with Department of Veterans Affairs officials to confirm the status of their actions to implement the recommendation.
    Recommendation: To help ensure that agencies have sufficient information on ESPC performance to oversee whether future and current contracts are achieving their expected savings, the Secretaries of Defense, Energy, and Veterans Affairs; the Attorney General; and the Administrator of the General Services Administration should work with contractors to determine the best way to obtain estimates of cost and energy savings that are not achieved because of agency actions in order to include these estimates in future measurement and verification reports for existing contracts, in accordance with DOE guidance, and where economically feasible.

    Agency: General Services Administration
    Status: Open

    Comments: In comments on a draft of this report, GSA agreed with the recommendation. As of December 2016, we were working with GSA officials to confirm the status of their actions to implement the recommendation.
    Director: David C. Trimble
    Phone: (202) 512-3841

    1 open recommendations
    Recommendation: To enhance the usefulness of NNSA's future reports to Congress describing the costs and benefits of its competition of M&O contracts under the requirements contained in Section 3121 of the National Defense Authorization Act for fiscal year 2013, as amended, the NNSA Administrator should take steps to ensure that future reports reflect DOE's information quality guidelines, federal cost accounting standards, and GAO's best practices guidance relevant to the clear and complete presentation of information on each of the required topics. In particular, future reports should clearly and completely describe costs and benefits, including the agency's expectations, as well as the associated analysis, assumptions, information sources, and key limitations and uncertainties about costs and benefits described. The description of uncertainties should include key excluded or unspecified costs and benefits, such as those that are anticipated but not fully known at the time of report writing.

    Agency: Department of Energy: National Nuclear Security Administration
    Status: Open

    Comments: NNSA recently awarded an M&O contract for Sandia NL. NNSA will have to produce a report on the costs and benefits of its competition, which will need to be delivered in early spring, 2017. Upon delivery to Congress, GAO will be able to assess whether NNSA fulfilled this recommendation.
    Director: David C. Trimble
    Phone: (202) 512-3841

    5 open recommendations
    Recommendation: To help improve its ability to assess the risk of improper payments and make more effective use of DOE and contractor resources, the Secretary of Energy should direct the department's Chief Financial Officer to revise the department's IPERA guidance and direct field office sites with responsibility for non-M&O contractor risk assessments to address risk factors as they relate to those sites and take steps to ensure sites implement it.

    Agency: Department of Energy
    Status: Open

    Comments: As of May 2017, DOE had revised its fiscal year 2015 and 2016 improper payments guidance. The revised guidance directs field office sites with responsibility for non-M&O contractor risk assessments to address risk factors as they relate to those sites. The guidance further requires each site Chief Financial Officer to certify to the accuracy of improper payments and risk rating. We will continue to monitor DOE's efforts to ensure sites implement this new guidance.
    Recommendation: To help improve its ability to assess the risk of improper payments and make more effective use of DOE and contractor resources, the Secretary of Energy should direct the department's Chief Financial Officer to revise the department's IPERA guidance and clarify how payment sites are to address risk factors and document the basis for their risk rating determinations and take steps to ensure sites implement it.

    Agency: Department of Energy
    Status: Open

    Comments: As of May 2017, DOE had revised its fiscal years 2015 and 2016 improper payments guidance requiring sites to prepare risk assessments using a new risk assessment format. The guidance states that the new format was developed to improve consistency among the sites and improve documentation supporting the risk ratings. In the new format, each risk factor includes a description of the risk factor, rating criteria and/or questions to consider during the evaluation to assist sites in determining a risk rating by payment type. The guidance also requires all sites to maintain supporting documentation for their risk assessment. We will continue to monitor DOE's efforts to ensure sites implement this new guidance.
    Recommendation: To help improve its ability to assess the risk of improper payments and make more effective use of DOE and contractor resources, the Secretary of Energy should direct the department's Chief Financial Officer to revise the department's IPERA guidance and clarify who is responsible at DOE for reviewing and approving risk assessments for consistency across sites and take steps to ensure those entities implement it.

    Agency: Department of Energy
    Status: Open

    Comments: As of May 2017, DOE had revised its fiscal years 2015 and 2016 improper payments guidance to require site Chief Financial Officers and the Director of Risk Management of the Loan Programs Office to provide a signed certification to DOE's Director of the Office of Finance and Accounting certifying to the accuracy of improper payments and the risk assessment and rating submitted. The guidance provides templates for these certifications. We will continue to monitor DOE's efforts to ensure sites implement this new guidance.
    Recommendation: To help improve its ability to assess the risk of improper payments and make more effective use of DOE and contractor resources, the Secretary of Energy should direct the department's Chief Financial Officer to revise the department's IPERA guidance and provide specific examples of other risk factors that present inherent risks likely to contribute to significant improper payments, in addition to the eight risk factors, direct payment sites to consider those when performing their improper payment risk assessments, and take steps to ensure sites implement it.

    Agency: Department of Energy
    Status: Open

    Comments: As of May 2017, DOE had revised its fiscal year 2015 and 2016 improper payments guidance. In addition to the required OMB risk factors, the guidance added the following additional risk factors to be included in the risk assessments: (1) contractor payment processing oversight and (2) segregation of duties. The guidance states these factors have been added to ensure that inherently high-risk areas that can contribute to a site's susceptibility to significant improper payments are properly evaluated. We will continue to monitor DOE's efforts to ensure sites implement this new guidance.
    Recommendation: To provide better transparency regarding its total known improper payments reported under IPERA, the Secretary of Energy should direct the department's Chief Financial Officer to improve public reporting on the amount of total known improper payments by disclosing additional information regarding this amount and the extent to which improper payments could be occurring.

    Agency: Department of Energy
    Status: Open

    Comments: As of May 2017, DOE had added supplemental information to its fiscal year 2016 Agency Financial Report. We will continue to gather additional information from DOE to determine the extent to which this information addresses the amount of total known improper payments.
    Director: Chaplain, Cristina T
    Phone: (202) 512-4841

    1 open recommendations
    Recommendation: To ensure that satellites storage is fully considered at the beginning of the acquisition process for all satellite programs and sufficient detailed cost data are maintained, the Secretary of Defense should provide guidance regarding when and how to use storage in the acquisition process, and establish mechanisms so that more detailed data are maintained for use in evaluating the reasonableness of contractors' storage cost proposals and for informing DOD's oversight of satellite acquisitions.

    Agency: Department of Defense
    Status: Open

    Comments: In its response to the report, DOD concurred with the recommendation and noted that it is important to develop guidance regarding the use of satellite storage in the acquisition process. In addition, DOD agreed that it is important to establish mechanisms such that more detailed data are available to evaluate storage cost proposals and inform the oversight of satellite acquisitions. In October 2015, DOD provided GAO with draft language that it planned to include in the Space Systems chapter of the Defense Acquisition Guidebook (DAG) when the final chapter was to be published. In an August 24, 2016, response to a GAO inquiry regarding the language not appearing in the on-line version of the DAG, the office of the Under Secretary of Defense for Acquisition, Technology and Logistics (USD/AT&L) explained that the Space Systems chapter of the DAG had been deleted. USD/AT&L stated it was working to incorporate the proposed language in the next revision of the DAG, scheduled to be completed in December 2016. A September 12, 2017, search of DOD's on-line guidance did not locate any guidance related to satellite storage. DOD liaison was contacted, but no information has been provided yet as of September 2017.
    Director: William Shear
    Phone: (202) 512-8678

    2 open recommendations
    Recommendation: To improve management and oversight of the WOSB program, and to help ensure the effective oversight of third-party certifiers, the Administrator of SBA should establish and implement comprehensive procedures to monitor and assess performance of certifiers in accord with the requirements of the third-party certifier agreement and program regulations.

    Agency: Small Business Administration
    Status: Open

    Comments: In response to this recommendation, SBA has taken some actions. For example, SBA created a standard operating procedure stating that third-party certifiers are subject to a compliance review by SBA at any time, and SBA has completed a review of the four authorized third-party certifiers. We continue to monitor SBA actions to address this recommendation.
    Recommendation: To improve management and oversight of the WOSB program, and to provide reasonable assurance that only eligible businesses obtain WOSB set-aside contracts, the Administrator of SBA should enhance examination of businesses that register to participate in the WOSB program, including actions such as: (1) promptly completing the development of procedures to conduct annual eligibility examinations and implementing such procedures; (2) analyzing examination results and individual businesses found to be ineligible to better understand the cause of the high rate of ineligibility in annual reviews, and determine what actions are needed to address the causes; and (3) implementing ongoing reviews of a sample of all businesses that have represented their eligibility to participate in the program.

    Agency: Small Business Administration
    Status: Open

    Comments: In response to this recommendation, SBA has created a standard operating procedure that includes some procedures for annual eligibility examinations. We continue to monitor SBA actions to address this recommendation.
    Director: Michele Mackin
    Phone: (202) 512-4841

    3 open recommendations
    Recommendation: The Administrator of OFPP should take appropriate steps to amend the FAR to include the following requirement: at the time of the contract award, contracting officers shall conduct and document an assessment of the 8(a) firm's ability to comply with the subcontracting limitations.

    Agency: Executive Office of the President: Office of Management and Budget: Office of Federal Procurement Policy
    Status: Open

    Comments: OFPP concurred with our recommendation. We asked for updates on actions taken however as of September 2017 no updates were provided. GAO will continue to monitor OFPP's actions to address this recommendation.
    Recommendation: The Administrator of OFPP should take appropriate steps to amend the FAR to include the following requirement: contracting officers shall include monitoring and oversight provisions in all 8(a) contracts to ensure that the contractors comply with the subcontracting limitations.

    Agency: Executive Office of the President: Office of Management and Budget: Office of Federal Procurement Policy
    Status: Open

    Comments: OFPP concurred with our recommendation. We asked for updates on actions taken however as of September 2017 no updates were provided. GAO will continue to monitor OFPP's actions to address this recommendation.
    Recommendation: The Administrator of OFPP should take appropriate steps to amend the FAR to include the following requirement: prime 8(a) contractors shall periodically report to the contracting officer on the percentage of subcontracted work being performed.

    Agency: Executive Office of the President: Office of Management and Budget: Office of Federal Procurement Policy
    Status: Open

    Comments: OFPP concurred with our recommendation. We asked for updates on actions taken however as of September 2017 no updates were provided. GAO will continue to monitor OFPP's actions to address this recommendation.
    Director: David C. Trimble
    Phone: (202) 512-3841

    3 open recommendations
    Recommendation: To identify lessons learned from and provide assurance of preventing recurrence of cost increases for the MOX facility and WSB, and to develop reliable cost estimates for the Plutonium Disposition program, the Secretary of Energy should direct the DOE and NNSA Offices of Acquisition and Project Management and the NNSA office responsible for managing the Plutonium Disposition program, as appropriate, to revise and update the program's life-cycle cost estimate following the 12 key steps described in the GAO Cost Estimating and Assessment Guide for developing high-quality cost estimates, such as conducting an independent cost estimate to provide an objective and unbiased assessment of whether the estimate can be achieved.

    Agency: Department of Energy
    Status: Open

    Comments: DOE is currently evaluating dilute and dispose as a potential alternative approach to the MOX approach. As a result, DOE does not plan to update the Plutonium Disposition Program life-cycle estimate until a decision is made on which approach to pursue. We will continue to monitor this situation and update the status of this recommendation once DOE has made a decision on the approach taken by this program.
    Recommendation: To identify lessons learned from and provide assurance of preventing recurrence of cost increases for the MOX facility and WSB, and to develop reliable cost estimates for the Plutonium Disposition program, the Secretary of Energy should direct the DOE and NNSA Offices of Acquisition and Project Management and the NNSA office responsible for managing the Plutonium Disposition program, as appropriate, to ensure that the MOX contractor revises its proposal for increasing the cost of the MOX facility to meet all best practices for a high-quality, reliable cost estimate--for example, by cross-checking major cost elements to determine whether alternative estimating methods produce similar results.

    Agency: Department of Energy
    Status: Open

    Comments: DOE is currently evaluating dilute and dispose as a potential alternative approach to the MOX approach. As a result, DOE does not plan to update the proposal for increasing the cost of the MOX facility until a decision is made on which approach to pursue. We will continue to monitor this situation and update the status of this recommendation once DOE has made a decision on the approach taken by this program.
    Recommendation: To ensure that future DOE projects benefit from lessons learned that reflect the underlying causes of cost increases or schedule delays experienced by other projects, and that Congress and DOE have life-cycle cost estimates for DOE programs that include individual construction projects, the Secretary of Energy should revise DOE's project management order or otherwise implement a departmentwide requirement by requiring life-cycle cost estimates covering the full cost of programs that include both construction projects and other efforts and activities not related to construction.

    Agency: Department of Energy
    Status: Open

    Comments: DOE revised its project management order in May 2016 but did not make any changes in regards to this recommendation. We will continue to monitor DOE activities, if any, related to this recommendation.
    Director: Dinapoli, Timothy J
    Phone: (202) 512-4841

    7 open recommendations
    Recommendation: To improve civilian IC elements' or their respective departments' ability to mitigate risks associated with the use of contractors, the Director of National Intelligence, Director of the Central Intelligence Agency, Attorney General of the United States, and Secretaries of Energy and the Treasury should direct responsible agency officials to set time frames to develop guidance that fully addresses the Office of Federal Procurement Policy, Policy Letter 11-01's requirements related to closely supporting inherently governmental functions.

    Agency: Office of the Director of National Intelligence
    Status: Open

    Comments: In providing comments on this report, the agency concurred with this recommendation. ODNI has held roundtables to discuss OFPP PL 11-01 implementation with other IC agencies. ODNI also revised ICD 612 but has not developed implementing guidance for ODNI MSD.
    Recommendation: To improve civilian IC elements' or their respective departments' ability to mitigate risks associated with the use of contractors, the Director of National Intelligence, Director of the Central Intelligence Agency, Attorney General of the United States, and Secretaries of Energy and the Treasury should direct responsible agency officials to set time frames to develop guidance that fully addresses the Office of Federal Procurement Policy, Policy Letter 11-01's requirements related to closely supporting inherently governmental functions.

    Agency: Department of Energy
    Status: Open

    Comments: In its letter to OMB and the Congress, the agency concurred with this recommendation. In July 2015, the agency issued interim guidance, but the guidance does not fully address OFPP Policy Letter 11-01. The agency explained that once the Federal Acquisition Regulation is updated, the agency's acquisition regulation will be updated as necessary to reflect the new guidance. Since that time, no further action has occurred.
    Recommendation: To improve civilian IC elements' or their respective departments' ability to mitigate risks associated with the use of contractors, the Director of National Intelligence, Director of the Central Intelligence Agency, Attorney General of the United States, and Secretaries of Energy and the Treasury should direct responsible agency officials to set time frames to develop guidance that fully addresses the Office of Federal Procurement Policy, Policy Letter 11-01's requirements related to closely supporting inherently governmental functions.

    Agency: Department of Justice
    Status: Open

    Comments: In its letter to OMB and the Congress, the agency concurred with this recommendation but has not yet taken the actions necessary to implement it.
    Recommendation: To improve civilian IC elements' or their respective departments' ability to mitigate risks associated with the use of contractors, the Director of National Intelligence, Director of the Central Intelligence Agency, Attorney General of the United States, and Secretaries of Energy and the Treasury should direct responsible agency officials to set time frames to develop guidance that fully addresses the Office of Federal Procurement Policy, Policy Letter 11-01's requirements related to closely supporting inherently governmental functions.

    Agency: Department of the Treasury
    Status: Open

    Comments: In its letter to OMB and the Congress, the agency concurred with this recommendation. Treasury issued additional supplemental guidance and is currently updating its procurement and workforce guidance to fully address OFPP Policy Letter 11-01.
    Recommendation: To improve civilian IC elements' or their respective departments' ability to mitigate risks associated with the use of contractors, the Director of National Intelligence, Director of the Central Intelligence Agency, Attorney General of the United States, and Secretaries of Energy and the Treasury should direct responsible agency officials to set time frames to develop guidance that fully addresses the Office of Federal Procurement Policy, Policy Letter 11-01's requirements related to closely supporting inherently governmental functions.

    Agency: Central Intelligence Agency
    Status: Open

    Comments: The agency did not comment on our recommendation. Please contact Timothy DiNapoli at (202) 512-4841 or dinapolit@gao.gov for additional information on the status of this recommendation.
    Recommendation: To improve congressional oversight and enhance civilian IC elements' insights into their use of core contract personnel, when reporting to congressional committees, the IC CHCO should clearly specify limitations and significant methodological changes and their associated effects.

    Agency: Office of the Director of National Intelligence: IC Chief Human Capital Officer
    Status: Open

    Comments: The IC CHCO described steps it was taking to implement the recommendation. For example, the IC CHCO stated it highlighted limitations to the data and the reasons for data adjustments from year-to-year in its FY 2014-2016 briefings to Congress. We will continue to follow up with the IC CHCO to determine whether these actions meet the intent of the recommendation.
    Recommendation: To improve the ability of the civilian IC elements to strategically plan for their contractors and mitigate associated risks, the IC CHCO should revise the Intelligence Community Directive 612's provisions governing strategic workforce planning to require the IC elements to identify their assessment of the appropriate workforce mix on a function-by-function basis.

    Agency: Office of the Director of National Intelligence: IC Chief Human Capital Officer
    Status: Open

    Comments: In August 2015, IC CHCO revised Intelligence Community Directive 612 and removed the provisions governing strategic workforce planning. We will continue to follow up with IC CHCO to determine whether steps will be taken to require IC elements to identify an appropriate workforce mix.
    Director: Rectanus, Lori
    Phone: (202) 512-2834

    4 open recommendations
    Recommendation: The Secretary of Transportation should direct the FHWA Administrator to collect data, on an ongoing basis, about which local public agencies are administering federal-aid projects.

    Agency: Department of Transportation
    Status: Open

    Comments: As of August 2017, FHWA informed us it had no plans to collect data about which local public agencies are administering federal-aid projects.
    Recommendation: The Secretary of Transportation should direct the FHWA Administrator to collect information, on an ongoing basis, from state DOTs on local public agencies' capabilities.

    Agency: Department of Transportation
    Status: Open

    Comments: As of August 2017, FHWA informed us that it did not plan collect information on the capabilities of local public agencies on an ongoing basis. In 2017 FHWA released the results of a compliance assessment review which assessed the capabilities of selected local public agencies. We are reviewing FHWA's efforts and the extent to which they address our recommendation.
    Recommendation: The Secretary of Transportation should direct the FHWA Administrator to identify and disseminate minimum and uniform qualification criteria for state DOTs to determine whether local public agencies are capable and equipped to administer federal-aid projects.

    Agency: Department of Transportation
    Status: Open

    Comments: As of August 2017, FHWA informed us it had no plans to identify and disseminate minimum and uniform qualification criteria for state DOTs to determine whether local public agencies are capable and equipped to administer federal-aid projects.
    Recommendation: The Secretary of Transportation should direct the FHWA Administrator to explore opportunities to make administration of federal-aid projects by local public agencies more efficient by examining: (a) the circumstances in which issuing guidance on administrative flexibilities targeted at local agencies would be appropriate, and (b) a potential dollar threshold under which the use of federal funds may no longer be cost-effective.

    Agency: Department of Transportation
    Status: Open

    Comments: As of August 2017, FHWA informed us that it did not plan to explore a dollar threshold under which the use of federal funds may no longer be cost-effective. However, FHWA told us it has provided guidance in this regard, and has continued disseminating guidance on administrative flexibilities beneficial to locally administered projects. We are reviewing FHWA's actions and the extent to which its these efforts address our recommendation.
    Director: Cha, Carol R
    Phone: (202) 512-4456

    2 open recommendations
    Recommendation: To improve planning and execution of the next telecommunications transition, the Administrator of General Services, in coordination with the Office of Personnel Management, should examine potential government-wide telecommunications expertise shortfalls and use the study to shape the NS2020 strategic approach.

    Agency: General Services Administration
    Status: Open

    Comments: The General Services Administration (GSA) has not addressed this recommendation. In June 2014, the agency reported that it had coordinated with OPM to incorporate key objectives in its NS2020 strategy to address and mitigate challenges with regards to government-wide expertise needed to execute the NS2020 program. However, as of May 2017, GSA had not demonstrated that it had studied potential government-wide telecommunications expertise shortfalls or used the study to shape the NS2020 strategic approach.
    Recommendation: To improve planning and execution of the next telecommunications transition, the Administrator of General Services should ensure that the lessons are applied, based on priority and available resources, to the next transition strategy.

    Agency: General Services Administration
    Status: Open

    Comments: The General Services Administration has not implemented this recommendation but has taken steps to address it. In April 2014, the agency developed a strategy for transitioning to the next telecommunications contract vehicle. The strategy described the lessons learned that contributed to the delay in the prior transition and identified approaches the agency planned to take to apply the lessons learned. For example, it identified high level plans for addressing the need for improved management of the complex acquisition process and the need for technical and contracting telecommunications expertise across the government. As of August 2016, GSA had prioritized the lessons learned and considered the resources needed to apply them. However, as of May 2017, the agency had not demonstrated that it had ensured that the lessons were applied, based on priority and available resources, to the next transition strategy. We will continue to monitor GSA's efforts to implement the recommendation.
    Director: Dinapoli, Timothy J
    Phone: (202) 512-4841

    3 open recommendations
    Recommendation: To better position DOD to determine whether its actions have improved service acquisition, the Principal Deputy Under Secretary of Defense for Acquisition, Technology, and Logistics, in consultation with the military departments' senior services managers, should identify baseline data on the status of service acquisition, in part, by using budget and spending data and leveraging its ongoing efforts to gauge the effects of its actions to improve service acquisition.

    Agency: Department of Defense: Office of the Secretary of Defense: Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics
    Status: Open

    Comments: DOD concurred with our recommendation and is in the process of developing baseline data on the current status of its service acquisitions. In July 2014, DOD issued its annual Performance of the Defense Acquisition report. For the first time, this report included information on its contracted services, such obligations for each service portfolio group, competition rates, and small business participation information. DOD expects to develop service acquisition related goals and metrics in 2017 from which it can develop additional baseline data.
    Recommendation: To better position DOD to determine whether its actions have improved service acquisition, the Principal Deputy Under Secretary of Defense for Acquisition, Technology, and Logistics, in consultation with the military departments' senior services managers, should develop specific goals associated with their actions to improve service acquisition.

    Agency: Department of Defense: Office of the Secretary of Defense: Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics
    Status: Open

    Comments: DOD concurred with our recommendation and is in the process of developing service acquisition goals and metrics as well as an action plan for improving service acquisition. As of February 2017, DOD began a review of internal guidance that will include an analysis of the roles, responsibilities, authorities, goals, metrics, and structure associated with managing service acquisitions.
    Recommendation: To better position DOD to determine whether its actions have improved service acquisition, the Principal Deputy Under Secretary of Defense for Acquisition, Technology, and Logistics, in consultation with the military departments' senior services managers, should establish metrics to assess progress in meeting these goals.

    Agency: Department of Defense: Office of the Secretary of Defense: Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics
    Status: Open

    Comments: DOD concurred with our recommendation and is in the process of developing service acquisition goals and metrics as well as an action plan for improving service acquisition. As of February 2017, DOD began a review of internal guidance that will include an analysis of the roles, responsibilities, authorities, goals, metrics, and structure associated with managing service acquisitions.
    Director: Gaffigan, Mark E
    Phone: (202) 512-3841

    1 open recommendations
    Recommendation: To help ensure that EM more effectively manages all its projects, the Secretary of Energy should direct the Senior Advisor for Environmental Management and the Director of the Office of Management, as appropriate, to provide the Office of Acquisition and Project Management with information on EM's project classification decisions to ensure that all capital asset projects have been appropriately classified and are managed in accordance with DOE Order 413.3B.

    Agency: Department of Energy
    Status: Open

    Comments: When commenting on our report, DOE agreed with our recommendation. According to agency information provided in March 2017, DOE has ongoing internal discussions to develop and document a policy addressing EM capital asset project and operations activity classifications. However, DOE has not yet established and approved such a policy.
    Director: Hutton, John P
    Phone: (202) 512-4841

    2 open recommendations
    Recommendation: To better focus agencies' efforts to manage the risks related to professional and management support service contracts, the Director of OMB, through the Office of Federal Procurement Policy (OFPP), should establish a near-term deadline for agencies to develop internal procedures required by OFPP Policy Letter 11-01, including for services that closely support inherently governmental functions.

    Agency: Executive Office of the President: Office of Management and Budget
    Status: Open

    Comments: In providing comments on our report, OFPP generally agreed with this recommendation. During follow-up discussions, OFPP agreed to provide additional information to confirm the actions they have taken to address the recommendation. However, we have yet to receive this information. We will continue to follow this recommendation and provide updated information when available.
    Recommendation: To ensure that the risks of professional and management support service contracts are more fully considered and addressed, the Director of OMB, through the Office of Federal Procurement Policy, should include contracts coded in the Federal Procurement Data System - Next Generation (FPDS-NG) as Other Professional Services and Other Management Support Services in the cost savings initiative for management support services and planned service contract inventory guidance to agencies for conducting analysis of special interest functions.

    Agency: Executive Office of the President: Office of Management and Budget
    Status: Open

    Comments: In providing comments on our report, OFPP generally agreed with this recommendation. We have had discussions with OFPP and they agreed to provide additional information on the actions taken to address the recommendation. However, we have yet to receive this information. We will continue to follow this recommendation and provide updated information when available.
    Director: King, Kathleen M
    Phone: (202)512-5154

    2 open recommendations
    Recommendation: To develop more accurate data for estimating the funds needed for the CHS program and improving IHS oversight, the Secretary of Health and Human Services should direct the Director of IHS to develop a written policy documenting how IHS evaluates need for the CHS program and disseminate it to area offices and CHS programs to ensure they understand how unfunded services data are used to estimate overall program needs.

    Agency: Department of Health and Human Services
    Status: Open

    Comments: In response to this recommendation, IHS reported in October 2015 that it was completing a comprehensive update of a policy chapter related to the Contract Health Services (CHS) Program (also called the Purchased/Referred Care Program). The agency indicated that this revised chapter would incorporate a written policy on how IHS evaluates need for the CHS program. It indicated that the chapter update had been under revision since December 20, 2012, with final approval anticipated in 2015. In July 2017, IHS indicated that the policy was still under development and would be issued to all IHS sites by September 30, 2017.
    Recommendation: To develop more accurate data for estimating the funds needed for the CHS program and improving IHS oversight, the Secretary of Health and Human Services should direct the Director of IHS to provide written guidance to CHS programs on a process to use when funds are depleted and there is a continued need for services, and monitor to ensure that appropriate actions are taken.

    Agency: Department of Health and Human Services
    Status: Open

    Comments: In response to this recommendation, IHS reported in October 2015 that it developed and distributed Fund Management Standardization guidance to Area Offices to monitor compliance by federal Contract Health Services (CHS) program (also called the Purchased/Referred Care program) Service Units. Also, IHS issued standardized spending plan procedures to all Area Offices and Federally-operated programs. Also, it indicated that spending plan guidance would be included in an update of a policy chapter related to the CHS program. The agency indicated that this chapter had been under revision since December 20, 2012, with final approval anticipated in 2015. In July 2017, IHS indicated that the policy was still under development and would be issued to all IHS sites by September 30, 2017.
    Director: Shear, William B
    Phone: (202)512-4325

    3 open recommendations
    Recommendation: To more fully evaluate the effectiveness of their mentor-protege programs, the OSDBU and Mentor-Protege Program Directors of DHS, DOE, DOS, EPA, FAA, GSA, HHS, SBA, Treasury, and VA should consider collecting and maintaining protege postcompletion information.

    Agency: Department of Health and Human Services: Office of Small and Disadvantaged Business Utilization
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Recommendation: To more fully evaluate the effectiveness of their mentor-protege programs, the OSDBU and Mentor-Protege Program Directors of DHS, DOE, DOS, EPA, FAA, GSA, HHS, SBA, Treasury, and VA should consider collecting and maintaining protege postcompletion information.

    Agency: Environmental Protection Agency: Office of Small and Disadvantaged Business Utilization
    Status: Open

    Comments: Following issuance of the report, EPA established a working group to review mentor-protege policies and procedures and determine the viability and relevance of the program at EPA. The working group recommended that EPA maintain the mentor-protege program and suggested other program improvements. EPA has since suspended implementation of the working group recommendations pending finalization of SBA's revised mentor-protege program guidance. In addition, EPA noted in May 2015 that the agency did not have any mentor-protege agreements in place and thus no need to develop and implement a systemic methodology for tracking program results. EPA added that it anticipates taking steps necessary to implement program tracking in accordance with SBA's revised mentor-protege guidance once it is finalized.
    Recommendation: To more fully evaluate the effectiveness of their mentor-protege programs, the OSDBU and Mentor-Protege Program Directors of DHS, DOE, DOS, EPA, FAA, GSA, HHS, SBA, Treasury, and VA should consider collecting and maintaining protege postcompletion information.

    Agency: Department of Energy: Office of Small and Disadvantaged Business Utilization
    Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
    Director: Mackin, Michele
    Phone: (202)512-7773

    1 open recommendations
    Recommendation: The Administrator of the Office of Federal Procurement Policy should direct agencies to require their competition advocates to actively involve program offices in highlighting opportunities to increase competition.

    Agency: Executive Office of the President: Office of Management and Budget: Office of Federal Procurement Policy
    Status: Open

    Comments: In July 2017, Office of Federal Procurement Policy (OFPP) officials confirmed that they do not plan to issue guidance on increasing the role of program officials in promoting competition, but stated that they have engaged with the Chief Acquisition Officers Council regarding the issue, and reminded them of GAO?s 2010 findings. In addition, OMB officials noted that they have developed agency-level benchmarks to better measure competition that are specifically focused on reducing financial risk to the government and on the level of competition where only one offer is received.
    Director: Hutton, John P
    Phone: (202)512-3000

    1 open recommendations
    Recommendation: To ensure DOD officials are able to gain insight into the risk assessment that is required to be documented in the contract file and the basis for the government's profit or fee negotiation objective, the Secretary of Defense should redesign the weighted guidelines worksheet to explicitly show the incurred cost calculations and a narrative description of the reason for assigning a specific contract-type risk value.

    Agency: Department of Defense
    Status: Open

    Comments: In providing comments on this report, the agency concurred with this recommendation but has not completed actions necessary to implement it. Defense Procurement and Acquisition Policy's(DPAP) members have drafted two proposed changes to the Defense Federal Acquisition Regulation Supplemental (DFARS). The first proposed rule is designed to provide a more transparent means of documenting the impact of costs incurred during the undefinitized period of an undefinitized contract action (UCA) on allowable profit. Proposed changes to the worksheet include more transparency and narrative requirements to detail the rationale for contracting officers' assignments of weighted guideline values. In addition to proposed changes to the weighted guideline worksheet, the proposed DFARS rule also provides new narrative requirements for Price Negotiation Memorandums. The second proposed rule changes the undefinitized period for a UCA from UCA award to the date when the government receives a qualifying proposal from the contractor as opposed to the date when the UCA is definitized. These proposed rules are currently being reviewed and approved by senior DOD officials. DPAP expects to finalize these proposed rules sometime later this year. If one or both are approved, the final rules will be published after a 90 day comment period.
    Director: Dinapoli, Timothy J
    Phone: (202)512-3000

    2 open recommendations
    Recommendation: To better inform acquisition decisions, assist DOD personnel in performing their management oversight responsibilities, and improve DOD's surveillance of services contracts, the Secretary of Defense should require before the award of any contract or issuance of task order for services closely supporting inherently governmental functions that program and contracting officials consider and document their assessment of the unique risks of these services and the steps that have been taken to mitigate such risks.

    Agency: Department of Defense
    Status: Open

    Comments: In providing comments on this report, DOD concurred with this recommendation and had initiated actions to provide additional guidance. As of September 2017, however, DOD has not provided additional guidance to its contracting officers on considering, documenting, and mitigating the risks associated when obtaining services closely associated with inherently governmental functions.
    Recommendation: To better inform acquisition decisions, assist DOD personnel in performing their management oversight responsibilities, and improve DOD's surveillance of services contracts, the Secretary of Defense should develop guidance to identify approaches that DOD should take to enhance management oversight when contractors provide services that closely support inherently governmental functions.

    Agency: Department of Defense
    Status: Open

    Comments: In providing comments on this report, DOD concurred with this recommendation and had initiated actions to provide additional guidance. As of September 2017, however, DOD has not provided additional guidance to its contracting officers on the steps they should take to enhance oversight of contractors providing services closely associated with inherently governmental functions.
    Director: Shear, William B
    Phone: (202)512-4325

    1 open recommendations
    Recommendation: To ensure compliance with federal contracting regulations and to more transparently disclose the extent to which subcontracting opportunities are available to small businesses, the Secretaries of Homeland Security and Defense and the Administrator of General Services should consider asking their respective Inspectors General to conduct a review at an appropriate future date to ensure that this guidance and related requirements are being followed.

    Agency: Department of Homeland Security
    Status: Open

    Comments: DHS issued a chapter on its small business subcontracting program in its DHS Acquisition Manual in October 2009 and developed a subcontracting plan checklist that officials are to use when awarding a contract. In May 2010 DHS officials claimed that these documents are examples of progress they have made to address the recommendation on ensuring compliance with federal contracting regulations and other related requirements. After reviewing these documents we disagreed with the agency and do not believe that these documents constitute agency guidance on the contract administration duties to monitor contractor compliance with subcontracting plan reporting requirements.