DOE Cleanup:

Status and Future Costs of Uranium Mill Tailings Program

T-RCED-96-167: Published: May 1, 1996. Publicly Released: May 1, 1996.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

GAO discussed the status and cost of the Department of Energy's (DOE) uranium mill tailings cleanup program and the factors that could affect future costs. GAO noted that: (1) surface contamination cleanup has been completed at two-thirds of the identified sites and is underway at most of the others; (2) if DOE completes its surface cleanup program in 1998, it will have cost $2.3 billion, taken 8 years longer than expected, and be $621 million over budget; (3) DOE cleanup costs increased because there were more contaminated sites than originally anticipated, some sites were more contaminated than others, and changes were needed to respond to state and local concerns; (4) the future cost of the uranium mill tailings cleanup will largely depend on the future DOE role in the program, remediation methods used, and the willingness of states to share final cleanup costs; and (5) the Nuclear Regulatory Commission needs to ensure that enough funds are collected from the responsible parties to protect U.S. taxpayers from future cleanup costs.

Mar 23, 2015

Mar 19, 2015

Mar 2, 2015

Feb 25, 2015

Dec 16, 2014

Dec 11, 2014

Nov 25, 2014

Nov 14, 2014

Looking for more? Browse all our products here