Superfund:

EPA Action Could Have Minimized Program Management Costs

T-RCED-93-50: Published: Jun 10, 1993. Publicly Released: Jun 10, 1993.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

GAO discussed program management costs associated with the Environmental Protection Agency's (EPA) hazardous waste cleanup contracts under Superfund. GAO noted that: (1) lack of EPA action has contributed to excessive Alternative Remedial Contracting Strategy (ARCS) program management costs; (2) program management costs have been greater than anticipated, since the expected cleanup work load never materialized; (3) EPA built in excess contract capacity and awarded a large number of contracts to avoid future capacity shortages and allow for the termination of poor contract performance; (4) the anticipated cleanup work load for ARCS contractors never materialized because EPA did not consider policy changes in its original work-load estimates; (5) EPA did not initiate action to avoid additional contract costs or correct high ARCS program management costs until the beginning of fiscal year 1992; (6) of the $465 million in ARCS costs, nearly $161 million was for indirect costs that were subject to waste and overcharging; (7) EPA has strengthened its contractor oversight; (8) EPA has increased the ARCS work load by shifting work from other contracts; (9) nearly one of every five ARCS contracts charges program management costs in excess of 20 percent of the total contract costs; and (10) EPA is currently developing new cleanup contracts that will supplement and eventually replace ARCS contracts as their capacity is exhausted.

Sep 22, 2014

Sep 19, 2014

Sep 15, 2014

Sep 12, 2014

Sep 9, 2014

Aug 11, 2014

Jul 28, 2014

Jul 16, 2014

Jul 15, 2014

Jul 9, 2014

Looking for more? Browse all our products here