District of Columbia:

Status of the New Convention Center Project

T-AIMD/OCE-98-239: Published: Jul 15, 1998. Publicly Released: Jul 15, 1998.

Additional Materials:

Contact:

Gloria L. Jarmon
(202) 512-4476
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO discussed the results of its review of the Washington Convention Center Authority's (WCCA) efforts to arrange for financing and constructing of a new convention center in the District of Columbia, focusing on: (1) the estimated cost of this project, including the guaranteed maximum price (GMP) for constructing the new convention center, and the risk exposure for both the contractor and the District; (2) the financing plan, including proposed changes to the revenue base, history of dedicated tax collections, projections for future revenues, and sufficiency to cover the GMP and other project costs; and (3) information on the site selection process, including WCCA's analysis of alternative sites, particularly the Northeast No. 1 site.

GAO noted that: (1) WCCA is proceeding with efforts to build a new convention center at Mount Vernon Square at a cost WCCA officials estimate to be $650 million; (2) GAO's latest review of the project identified an additional $58 million in project costs which--because WCCA expects these costs to be funded through federal grants or moved into operating costs--are not included in WCCA's total project costs; (3) these costs raise the project's cost estimate to $708 million, excluding reserve requirements and financing costs of $138 million; (4) while WCCA has maintained a $650-million budget, a number of changes have been made among the budget components, with some components increasing and some decreasing; (5) the majority of the estimated project costs are covered in a $500.6-million GMP for construction; (6) the GMP lays out 22 different cost components and sets limits on financial risks to the construction manager; (7) areas of risk are not included in the $500.6-million price; (8) the total contingency for the project is down from $75.9 million to $40 million; (9) WCCA's financing plan to cover predevelopment, construction, reserves, and operation of the convention center calls for about $846 million; (10) 73 percent of the funds needed to finance the project are expected to be derived from revenue bonds supported by dedicated taxes; (11) WCCA received $44 million in dedicated taxes in 1997, and WCCA has projected collections to increase at 1 percent a year over the next several years; (12) the financing plan assumes a lower interest rate, an increase in the annual dedicated tax revenues to support the bond financing, and an increase in the terms of the bonds from 30 to 34 years; (13) these changes would allow WCCA to borrow more money to finance the project; (14) risks associated with the financing package could affect the rating of the bonds and accordingly, the interest rate; (15) the site selection process for the convention center has a long history and numerous studies over the years have consistently identified Mount Vernon Square as a preferred site; and (16) WCCA's most recent analysis of the Northeast No. 1 site indicates that costs would be higher and would likely result in opening the convention center at a much later date than estimated for the Mount Vernon Square site.

Sep 23, 2016

Sep 21, 2016

Sep 7, 2016

Aug 30, 2016

Aug 11, 2016

Jul 22, 2016

Jul 21, 2016

Jul 6, 2016

Looking for more? Browse all our products here