Environmental Protection:

Funds Obligated for Completed Superfund Projects

RCED-98-232: Published: Jul 21, 1998. Publicly Released: Jul 31, 1998.

Additional Materials:

Contact:

Peter F. Guerrero
(202) 512-4907
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO reviewed the Environmental Protection Agency's (EPA) efforts to deobligate and recover funds for completed Superfund projects, focusing on: (1) the progress that EPA has made to recover the unspent funds on the inactive Superfund contracts and assistance agreements that GAO identified; and (2) whether any additional funds that expired during 1997 for Superfund contracts and assistance agreements are available for deobligation.

GAO noted that: (1) EPA has made a concentrated effort to recover the unspent funds that GAO identified for work orders and assistance agreements for Superfund contracts that were completed prior to 1997; (2) of the $249 million that GAO identified, EPA has recovered $210 million; (3) of the approximately $39 million remaining, EPA has detailed plans to recover about $26 million during fiscal year (FY) 1998; (4) EPA plans to recover the remaining $13 million in FY 1999; (5) EPA has an additional $125 million available for deobligation from contracts and assistance agreements that expired in 1997; (6) although EPA had identified and plans to recover $10 million, GAO identified an additional $115 million, which also expired in 1997, that can be recovered; (7) EPA did not identify the additional $115 million because its analysis, which was based on data for June 1997, covered contracts that expired prior to July 1, 1997; (8) typically, in the second half of a calendar year, significant amounts become available for deobligation; and (9) of the additional amount available for deobligation and recovery, $109 million derives mainly from contract work orders that expired during the last 6 months of 1997 and over $6 million from assistance agreements.

Recommendation for Executive Action

  1. Status: Closed - Not Implemented

    Comments: EPA disagreed with the recommendation because: (1) its process allows contractors 6 months to submit invoices for expired contracts and it does not want to risk deobligating too much money; (2) its effort is timed for sufficient evaluation and processing of each deobligation and reuse recovered funds during the fiscal year; (3) it places significant emphasis on its annual process, and requiring additional efforts would reduce the stature of its annual effort; and (4) it agency has been successful in expending recovered Superfund dollars within a reasonable timeframe.

    Recommendation: To expedite the recovery of unspent funds on inactive Superfund contract work orders, the Administrator, EPA, should modify the agency's analysis of completed contracts to include a separate analysis of contracts that have expired at the end of December in addition to June of each calendar year.

    Agency Affected: Environmental Protection Agency

 

Explore the full database of GAO's Open Recommendations »

Sep 15, 2014

Sep 12, 2014

Sep 9, 2014

Aug 11, 2014

Jul 28, 2014

Jul 16, 2014

Jul 15, 2014

Jul 9, 2014

Jun 30, 2014

Jun 16, 2014

Looking for more? Browse all our products here