Federal Research:
Super Collider Is Over Budget and Behind Schedule
RCED-93-87, Feb 12, 1993
Contact:
Pursuant to a congressional request, GAO examined the cost and schedule for the Superconducting Super Collider (SSC).
GAO found that: (1) the SSC contractor has not fully implemented a cost and schedule system as the contract requires; (2) the prime contractor's accounting system has misallocated expenses among its accounts; (3) the contractor's accounting records were incomplete and do not include all savings and cost increases; (4) major subcontractors' reports have identified cost overruns and schedule delays; (5) the Department of Energy's (DOE) analyses of the subcontractors' reports showed that the conventional construction subcontractor was 19 percent behind schedule and 51 percent over the baseline cost; (6) funding from foreign countries has been slow to materialize; (7) DOE is considering deleting or deferring the installation of some detector components if it does not receive funding from other sources; (8) without significant funding from Japan, it is doubtful that the goal of $1.7 billion in foreign funding will be met; and (9) a 1-year slip in the project's schedule could increase total SSC cost by $400 million.
Apr 10, 2013
Science, Technology, Engineering, and Mathematics Education
Feb 15, 2013
Unmanned Aircraft Systems
Sep 12, 2012
Department of Homeland Security
Jun 20, 2012
Nanotechnology
Jan 24, 2012
Science, Technology, Engineering, and Mathematics Education
Nov 7, 2011
Next Generation Air Transportation System
Aug 25, 2011
Technology Assessment
Jul 19, 2011
Space Research
Jul 14, 2011
DHS Science and Technology
Jun 9, 2011
Department of Energy
Looking for more? Browse all our products here







