New Denver Airport Followup

RCED-92-285R: Published: Sep 14, 1992. Publicly Released: Sep 14, 1992.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

GAO reviewed the construction schedule and cost status of the Denver International Airport. GAO found that: (1) as of July 1992, construction was on schedule, with 41 percent completed; (2) as of August 1992, the total cost was estimated to be $4 billion; (3) although costs of 27 contracts cited in its September 1991 report have increased about 5 percent due to change orders, the contracts remained about $89 million under their budgeted amount; (4) 83 percent of needed funds for the airport will come from unsecured revenue bonds, with the rest from federal grants, and passenger fees and excess revenues from Stapleton International Airport; (5) two of the four largest all-cargo carriers have decided to operate at the new airport rather than a smaller airport after officials relocated the cargo facilities at the new airport; (6) future cargo losses to the smaller airport could reduce revenues to the new airport, and increase fees to other users; and (7) expansion of the smaller airport for cargo operations would require greater federal expenditures, could potentially cause greater environmental impacts, and could delay flights at the new airport.

Sep 14, 2016

Sep 2, 2016

Aug 8, 2016

Jul 28, 2016

Jul 13, 2016

Jul 7, 2016

Jun 24, 2016

Jun 21, 2016

May 26, 2016

Looking for more? Browse all our products here