Nuclear Waste:

DOE's Program to Prepare High-Level Radioactive Waste for Final Disposal

RCED-90-46FS: Published: Nov 9, 1989. Publicly Released: Dec 14, 1989.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO provided information on the Department of Energy's (DOE) four high-level radioactive waste immobilization sites.

GAO found that: (1) the four sites stored an estimated total of 95 million gallons of waste in underground tanks; (2) DOE estimated $13 billion in processing, immobilization and storage costs; (3) complete waste immobilization could take 2 to 17 years; (4) the Savannah River immobilization facility was 2 years behind the 1983 projected schedule, but current costs corresponded with 1984 cost estimates; (5) although the West Valley immobilization project was 8 years behind its 1984 schedule, and the $1.1-billion cost estimate was almost double the 1984 estimate, a proposed 5-year plan could reduce costs by about $890 million; (6) the estimated 2008 Hanford facility completion date was questionable, because waste immobilization needs were uncertain and defense activities were expected to end ; (7) DOE had not yet determined the Idaho National Engineering Laboratory's (INEL) immobilization technology, since the facility was still in the early planning stages; and (8) because DOE will begin immobilization before a planned repository is completed, all the sites except INEL will initially store their waste on-site.

Sep 14, 2016

Sep 8, 2016

Aug 11, 2016

Aug 9, 2016

Aug 4, 2016

Jul 15, 2016

Jul 14, 2016

Jun 20, 2016

Mar 3, 2016

Looking for more? Browse all our products here