GAO reported on: (1) changes to the Army Corps of Engineers' review process for feasibility studies used to recommend congressional authorization for constructing proposed civil works water resource projects; and (2) the Office of Management and Budget's (OMB) role in the review process.

Recommendations

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of the Army The Secretary of the Army, through the Assistant Secretary of the Army for Civil Works, should work with the Director, OMB, to establish a realistic time frame goal for the expedited review of feasibility reports on proposed water resource development projects to be transmitted to Congress for construction authorization.
Closed – Not Implemented
The Secretary of the Army and OMB have not agreed upon a time frame for OMB review of projects, although they have taken actions cited in part I to expedite the process, which they believe is responsive to the recommendation.