Nuclear Waste:

Quarterly Report as of December 31, 1988

RCED-89-87: Published: Feb 27, 1989. Publicly Released: Feb 27, 1989.

Additional Materials:


Office of Public Affairs
(202) 512-4800

In response to a congressional request, GAO presented its quarterly report on the Department of Energy's (DOE) implementation of the Nuclear Waste Policy Act of 1982.

GAO found that: (1) DOE has completed a site characterization plan for the Yucca Mountain repository site and is in the process of obtaining public comments on the plan; (2) DOE delayed exploratory shaft construction for 5 months to reevaluate its completed design work and to ensure that its site characterization plan conformed with regulatory requirements; (3) the current DOE schedule for developing, implementing, and demonstrating the adequacy of its quality assurance program is slipping and could further delay construction work; and (4) if the Nuclear Regulatory Commission found the site characterization plan inadequate, DOE would have to request additional time to resolve the deficiencies, which would result in further construction delays.

Oct 30, 2015

Oct 13, 2015

Oct 1, 2015

Sep 23, 2015

Jul 28, 2015

Jul 27, 2015

Jul 13, 2015

Jul 10, 2015

Jul 8, 2015

Jun 29, 2015

Looking for more? Browse all our products here