Superfund:

Cost Growth on Remedial Construction Activities

RCED-88-69: Published: Feb 24, 1988. Publicly Released: Mar 25, 1988.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO: (1) reviewed the extent of cost growth for the Environmental Protection Agency's (EPA) cleanup activities at Superfund sites with the highest expenditures; and (2) compared the growth with that experienced in the construction industry.

GAO found that: (1) construction expenditures for 30 long-term cleanup activities exceeding $1 million represented $94 million, or 87 percent, of $108 million in total Superfund long-term cleanup construction costs; (2) construction costs for 9 routine activities increased an average of 5 percent over the original contracts, while the 17 nonroutine activities increased an average of 19 percent; (3) the four activities that did not fit within the routine or nonroutine categories had an average growth of 8 percent; (4) although new Superfund legislation emphasizes cleanup activities that should permanently or significantly reduce contamination, these cleanups often cost more because of the use of new technologies; and (5) as overall Superfund cost growth rises, EPA may need to analyze the causes for growth and determine whether to take actions to control it.

Dec 6, 2016

Dec 1, 2016

Nov 28, 2016

Oct 31, 2016

Oct 24, 2016

Oct 17, 2016

Oct 14, 2016

Oct 3, 2016

Sep 28, 2016

Looking for more? Browse all our products here