Federal Research Projects: Concerns About DOE's Super Collider Site Selection Process
RCED-87-175FS
Published: Aug 06, 1987. Publicly Released: Aug 06, 1987.
Skip to Highlights
Highlights
In response to a congressional request, GAO reviewed the Department of Energy's (DOE) selection of a site for its proposed superconducting super collider (SSC) to determine whether: (1) precedents exist for selecting sites for multimillion dollar research projects on the basis of competitive bidding, with states providing land and other incentives; (2) federal research and development funds have become more concentrated over the past 20 years; and (3) federal agencies have made any efforts to distribute these funds among as many states as possible.
Full Report
Office of Public Affairs
Topics
Competitive procurementEvaluation criteriastate relationsFunds managementGovernment facility constructionProcurement practicesResearch and development costsResearch and development facilitiesSite selectionBid proposals