In response to a congressional request, GAO reviewed certain allegations that the Tennessee Valley Authority (TVA) buried usable tools and equipment at its Hartsville nuclear project. GAO also investigated whether TVA had addressed these allegations and whether inventory control and disposal problems existed.

GAO found that TVA adequately investigated the allegations concerning current inventory and control practices at the Hartsville construction site. Further, GAO confirmed that, except for a few minor items, usable construction material and equipment were not buried at the site. However, GAO noted that, unless TVA resolves the deficiencies with inventory control and disposal practices by ensuring that its procedures are consistently implemented at all construction projects, similar allegations might arise and unnecessary small equipment losses could continue.

Sep 21, 2016

Aug 3, 2016

Aug 1, 2016

Jul 14, 2016

Jul 5, 2016

Jun 30, 2016

Jun 28, 2016

Jun 23, 2016

Jun 22, 2016

Looking for more? Browse all our products here