GAO reviewed the efforts of the Federal Energy Regulatory Commission (FERC) to terminate the Common Support Agreement between FERC and the Department of Energy (DOE). This termination would transfer from DOE to FERC the responsibility for performing certain administrative functions in support of FERC.

GAO found that estimates of the resources needed to perform the support functions, which were made by FERC, were not based on a complete evaluation. GAO also found that FERC is not yet prepared for an orderly, economical transfer of the administrative support functions from DOE.

Recommendations for Executive Action

  1. Status: Closed - Not Implemented

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Chairman of FERC in cooperation with the Secretary of Energy should make complete evaluations of the resources which FERC needs in order to assume responsibility for the functions to be transferred, including completion of the evaluations already arranged for.

    Agency Affected: Federal Energy Regulatory Commission

  2. Status: Closed - Implemented

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Chairman of FERC in cooperation with the Secretary of Energy should prepare a transition plan for the transfer, including: (1) a schedule for acquisition of resources which would provide for installation, testing, and training; (2) a schedule for assuming responsibilities from DOE as FERC completes its preparations to receive them; and (3) provision for DOE system backup to avoid loss of vital information and problems until the FERC systems are operating satisfactorily.

    Agency Affected: Federal Energy Regulatory Commission

 

Explore the full database of GAO's Open Recommendations »

Sep 6, 2016

Aug 24, 2016

May 26, 2016

Apr 18, 2016

Mar 24, 2016

Mar 10, 2016

Feb 4, 2016

Sep 29, 2015

Mar 25, 2015

Feb 19, 2015

Looking for more? Browse all our products here