Clarence Cannon Dam and Reservoir:

Cost, Schedule, and Safety Problems

PSAD-77-131: Published: Jul 18, 1977. Publicly Released: Jul 18, 1977.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

The cost of the Clarence Cannon Dam and Reservoir project has more than tripled since 1962, primarily because of inflation and estimating and design refinements. Scheduled completion has been delayed 8 years.

In 1962, the estimated project cost was $63.3 million. The estimate has now increased to $232 million. Certain estimates still lack supporting data, and others appear too high because they contain an excessive amount for contingencies. About half of the delays in project completion was due to funding restrictions imposed by Corps of Engineers Headquarters or by the Office of Management and Budget. Other delays resulted from reassessment of construction schedules and from difficulties in negotiating with the State on road relocation designs. The main dam may not be as safe as planned because defective fill material was used in the foundation.

Matter for Congressional Consideration

  1. Status: Closed

    Comments: Please call 202/512-6100 for additional information.

    Matter: The Secretary of the Army should: have the corps review and strengthen its cost estimating procedures to develop more realistic estimates; identify for Congress those corps projects involving construction factors, such as availability of long leadtime items, which are particularly sensitive to schedule delays; and obtain an evaluation of the overall safety of the project from an expert, independent consultant.

 

Explore the full database of GAO's Open Recommendations »

Oct 23, 2017

Oct 18, 2017

Oct 16, 2017

Oct 12, 2017

Oct 2, 2017

Sep 18, 2017

Sep 6, 2017

Aug 16, 2017

Aug 3, 2017

Jun 20, 2017

Looking for more? Browse all our products here