Energy:

Bellefonte Nuclear Plant

PSAD-76-86: Published: Mar 1, 1976. Publicly Released: Mar 1, 1976.

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

The Tennessee Valley Authority (TVA) has a large commitment to the development of nuclear power, the best short-range assurance of an adequate supply of electricity which is both environmentally acceptable and economical. Bellefonte, TVA's fourth nuclear power plant, is located near Scottsboro, Alabama. Responsibility for licensing nuclear power plants and assurance of safe operations lies with the Nuclear Regulatory Commission (NRC).

TVA's original cost estimate for the Bellefonte Nuclear Plant was $650 million, an estimate based on prior experience and projected inflation. The revised estimate is $1.2 billion. This figure was arrived at by following basic estimating techniques. The increase was caused by inflation, delays, interest costs, and additional construction man-hours. The projected opening of commercial operation has been postponed nearly 3 years, to June 1980, for reasons including delays in gaining access to the site, the collection of environmental impact data, the extension of the construction period, TVA manpower restrictions, and revised NRC guidelines. One such holdup was related to redesigning certain components to meet earthquake resistance standards. NRC and TVA are considering standardization of nuclear plant design to minimize the effect of common delay factors. TVA customarily overlaps later design stages with early phases of construction, which agency officials deem a means of reducing costs. Future modifications may be necessary, but TVA is taking steps to anticipate and mitigate this possibility. To satisfy estimates of electric power demand in TVA's service area, the construction of seven nuclear power plants will be required, and TVA has planned its expansion to conform with this schedule.

Status Legend:

More Info
  • Review Pending-GAO has not yet assessed implementation status.
  • Open-Actions to satisfy the intent of the recommendation have not been taken or are being planned, or actions that partially satisfy the intent of the recommendation have been taken.
  • Closed-implemented-Actions that satisfy the intent of the recommendation have been taken.
  • Closed-not implemented-While the intent of the recommendation has not been satisfied, time or circumstances have rendered the recommendation invalid.
    • Review Pending
    • Open
    • Closed - implemented
    • Closed - not implemented

    Matter for Congressional Consideration

    Matter: Congress should keep apprised of updated electrical demand forecasts in order to consider requests for additional nuclear power plants.

    Status: Closed

    Comments: Please call 202/512-6100 for additional information.

    Recommendation for Executive Action

    Recommendation: TVA should reduce the emphasis on design/construction concurrency in its nuclear plants development program.

    Agency Affected:

    Status: Closed

    Comments: Please call 202/512-6100 for additional information.

    Apr 14, 2014

    Dec 17, 2013

    Nov 25, 2013

    Oct 17, 2013

    Sep 23, 2013

    Sep 11, 2013

    Jul 24, 2013

    Jul 10, 2013

    Jun 28, 2013

    Looking for more? Browse all our products here