Cost and Savings Estimates the Air Force Used To Decide Against Relocating the Electromagnetic Compatibility Analysis Center From Annapolis, Maryland, to Duluth, Minnesota

PLRD-83-48: Published: Mar 9, 1983. Publicly Released: Mar 9, 1983.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO reviewed the cost and savings estimates used by the Air Force to decide against relocating the Electromagnetic Compatibility Analysis Center from Government-owned and leased space in Annapolis, Maryland, to Government-owned space at the Duluth International Airport, Minnesota.

The Air Force estimated in September 1980 that relocation would, over a 10-year period, cost $11 million more than leaving the Center in Annapolis. In September 1981, the Air Force revised this estimate to $5 million over a 10-year period. GAO estimated that relocation would increase cost to the Government, over the next 15 years, between $4.3 million and $7 million, depending upon the number of personnel that would relocate. The GAO estimate of relocation costs and the Air Force's estimates differ because: (1) GAO used 1982 cost data whereas the Air Force used 1979 cost data; (2) GAO projected costs over 15 years whereas the Air Force projected costs over 10 years; (3) GAO used a 13.26-percent discount factor to compute the present value of total costs whereas the Air Force used a 10-percent factor; and (4) GAO computed higher or lower estimates for some cost items. GAO believes that the decision not to relocate was, from a cost standpoint, appropriate.

Jul 21, 2016

Jun 23, 2016

May 12, 2016

Apr 14, 2016

Mar 4, 2016

Oct 30, 2015

Sep 9, 2015

Aug 17, 2015

Jul 9, 2015

Apr 27, 2015

Looking for more? Browse all our products here