Space Shuttle:
Declining Budget and Tight Schedule Could Jeopardize Space Station Support
NSIAD-95-171, Jul 28, 1995
Contact:
(202) 512-4841
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Pursuant to a congressional request, GAO examined the extent to which the space shuttle program can support the space station's assembly requirements, focusing on the: (1) impacts of the declining shuttle budget; and (2) demanding schedule to support the space station.
GAO found that: (1) the National Aeronautics and Space Administration's (NASA) plans for increasing the shuttle's lift capability are complex and involve about 30 individual actions such as hardware redesigns, improved flight design techniques, and new operational procedures; (2) some of the hardware redesign programs have experienced early development problems, and the potential exists for additional problems; (3) the NASA schedule for meeting the space station's launch requirements appears questionable in the declining budget environment; (4) NASA must successfully complete numerous shuttle-related development programs on a tight schedule to support the first space station launch; (5) the remaining launch schedule is compressed and will be difficult to achieve without additional funding or more efficient processing methods; (6) delays in the launch schedule could substantially increase the station's cost; (7) NASA plans to forgo some of the shuttle's recertification activities and full integration testing of the propulsion system until the first launch of station components; (8) NASA plans to assess the implications of the design changes through a combination of tanking and component tests and systems analyses; and (9) NASA must ensure that the implications of integrating numerous individual design changes are fully understood and safety is not compromised.
Status Legend:
- Review Pending
- Open
- Closed - implemented
- Closed - not implemented
Recommendation for Executive Action
Recommendation: The Administrator, NASA, should establish an independent review team to assess the NASA systems integration plan for the lift-increasing enhancements, identify the associated technical and programmatic risks, and weigh the costs and benefits of NASA tight scheduling of shuttle flights to assemble the space station.
Agency Affected: National Aeronautics and Space Administration
Status: Closed - Implemented
Comments: In July 1996, the Office of Science and Technology Policy (OSTP) asked NASA to review the impact that the agency's downsizing plans and transition to a single prime contractor for shuttle operations have had or will have on shuttle safety issues. The three issues GAO raised in this report were mentioned in this OSTP request. Subsequently, NASA asked its Aerospace Safety Advisory Panel (ASAP) to perform the requested review. The ASAP's report was issued in November 1996.
Apr 17, 2013
NASA
Feb 7, 2013
Dec 3, 2012
James Webb Space Telescope
Nov 19, 2012
NASA
Jun 27, 2012
Environmental Satellites
Geostationary Weather Satellites
Polar-Orbiting Environmental Satellites
Jun 20, 2012
Commercial Space Transportation
Jun 6, 2012
Commercial Space Launch Act
Mar 28, 2012
NASA
Looking for more? Browse all our products here







