Budget and Spending:

B-2 Facilities

NSIAD-94-45R, Nov 22, 1993

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO reviewed the design and construction of certain ground support systems at a B-2 bomber production facility, focusing on: (1) the cost of correcting problems in the systems; and (2) whether the contractor misrepresented problems with these systems to the Air Force. GAO found that the: (1) contractor has begun construction of the production facility and installation of the B-2 bomber ground support systems before completing the aircraft's design or establishing procedures to test the aircraft; (2) contractor could have avoided $1.181 million in costs for the installation and improvement of one ineffective system if it had obtained approval of final construction plans before awarding installation subcontracts; (3) costs of modifying other systems have increased due to unanticipated changes in requirements; (4) contractor has informed the Air Force that increased capabilities in the ground support systems are needed because of revised aircraft requirements; (5) Air Force has provided limited oversight of the construction project; (6) Air Force has not challenged the contractor on why systematic problems occur or who is responsible for them, since it is required to bear the costs of facility construction and modification; and (7) Air Force had not accepted delivery of the systems as of October 1993.

May 21, 2013

May 8, 2013

Apr 11, 2013

Mar 13, 2013

Feb 26, 2013

Jan 7, 2013

Dec 3, 2012

  • budget icon, source: GAO

    The Federal Government's Long-Term Fiscal Outlook

    Fall 2012 Update
    GAO-13-148SP

Nov 15, 2012

Oct 4, 2012

Sep 18, 2012

Looking for more? Browse all our products here