Navy Maintenance:

Cost and Schedule Performance at San Diego and Long Beach Shipyards

NSIAD-93-85: Published: Dec 9, 1992. Publicly Released: Dec 9, 1992.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO reviewed cost and schedule information on ship repairs at San Diego, California, and Long Beach, California, area shipyards, focusing on the comparison of: (1) contract award prices and final contract prices for ship repairs; (2) government cost estimates at the start of the contract and the actual costs at work completion; (3) original completion schedules with actual completion dates for private and public shipyards; and (4) San Diego and Long Beach private shipyards' performance.

GAO found that: (1) final contract costs generally exceeded contract award prices by 30 percent on most ship repairs, but they were generally less than government estimates; (2) 50 to 57 percent of repairs exceeded the original schedule completion dates by an average of over 30 days; (3) cost and schedule overruns were similar at San Diego and Long Beach shipyards; (4) the Long Beach Naval Shipyard overall showed an insignificant difference between cost estimates and actual repair costs, although 8 of 23 ships did have cost overruns averaging $4.1 million, and 10 of 23 ships had schedule overruns averaging 22 days; (5) differences between government estimates and actual costs were small, since the government estimate was a negotiated price between the government and the shipyard, and generally included a 10- to 15-percent growth factor; and (6) the causes of cost and schedule overruns were inability to determine exact maintenance requirements, inadequate and late government-furnished information and materials, government-caused delays and disruptions, and work added after start of repairs.

Nov 8, 2017

Oct 31, 2017

Oct 26, 2017

Oct 17, 2017

Oct 12, 2017

Oct 11, 2017

Oct 10, 2017

Sep 29, 2017

Looking for more? Browse all our products here